Washington State University Modernization Initiative Quality Assurance Assessment – November 16, 2020 – December 15, 2020 Prepared by: ISG December 15, 2020 Copyright © 2020 Information Services Group, Inc. All Rights Reserved
December 15, 2020 Stacy Pearson Project Executive Sponsor and Vice President, Finance and Administration Washington State University Finance and Administration PO Box 641046 Pullman, WA 99164-1045 Sue Langen Deputy Director for Strategy & Management Office of the Chief Information Officer 1500 Jefferson St SE Olympia, WA 98504 Nicole Simpkinson Assistant Director Office of the Chief Information Officer 1500 Jefferson St SE Olympia, WA 98504 Dear Ms. Pearson, Ms. Langen, and Ms. Simpkinson: ISG has completed its Quality Assurance Assessment (the Assessment) of the Washington State University (WSU) Modernization Initiative (the Project) for the period November 16, 2020 through December 15, 2020. This month the Modernization Initiative Steering Committee will convene on Wednesday, December 16, a week and a day earlier than usual, due to the Christmas holiday. This report therefore reflects progress over a four-week period which was last reported out at the Project Management Office (PMO) meeting of Tuesday, December 8 and reflects progress reported in the Project Workplan through Thursday, December 10. The timing of this assessment provides timely reporting to the Steering Committee. The Assessment was completed in accordance with the requirements of WSU and the State of Washington Office of the Chief Information Officer (OCIO). WSU’s Imminent Go Live During the assessment period, the Project team gained authorization from the Steering Committee to go live with Workday beginning with Human Capital Management (HCM) functionality including payroll on December 16, the same day the Steering Committee meets, and move into the Support or Stabilization Phase of the Project. The Steering Committee authorized the Executive Sponsor to approve the move to go live during the November 19 meeting and received an additional status update from Project leadership during an interim Steering Committee meeting held on Friday, December 4. During the November 19 meeting, Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page i
each of the Project team leads and Deloitte expressed the belief that the Project was ready to go live. ISG stated that, in our assessment, a go live as planned during the December 16 / early January time frame represents WSU’s least risky go live option. ISG congratulates WSU, Project leadership, and the Project team on achieving this significant milestone. Go Live Readiness The Project team has focused on the build out of the Gold Tenant, the tenant that will seed the initial Production Tenant that Workday will accept to support WSU operations. This multi-week process has reportedly been proceeding well with only a few exceptions that the Project team considers manageable. Record loads have been successfully loaded at 99.6% to 99.9% levels for HCM, Financials, security, and payroll, with the latter two having the higher success rates. Project Business Analysts have been highly responsive in their support of this critical activity. ISG observes that his process has been very well managed. After automated conversions have been loaded into the Gold Tenant, a set of additional manual updates are planned to bring the tenant up-to-date and to reflect transactions due for recognition as Workday goes live. Progress continues on integrations. The Project team continues to meet with the Controller’s Office to update the Workday – Agency Financial Reporting System (AFRS) crosswalk and with the State Office of Financial Management (OFM) to test the integration. Outstanding transaction crosswalks are primarily related to less frequently occurring transactions. The Project team has initiated contingency planning to address transactions that are not fully mapped when the first integration run is required in January. Progress related to completion of the gift calculator continues to track well. End-to-end processing has been successfully tested. The most recently reported defects related to the set-up of three gift income distributions. Inception-to-date conversions, the one significant item that Project management considered a potential threat to go live, has moved forward to a point where it is no longer considered a threat. Transactions have reportedly been validated at the fund and account level. The Project team is meeting with the Controller’s Office to resolve those items that remain outstanding. The myWSU Student Receivables integration to Workday continues to receive attention. Per the Project team report out on December 8, some 300 items types continue to require attention. These are all financial integrations, although payroll transactions are included in the scope of the AFRS integration. Financial cutover is scheduled for January 2021. Report development was suspended until migrations have been completed. Approximately 87 reports classified as “medium” and “low” priority remain outstanding. All of these reports would not be needed at go live. Project leadership has broadly communicated to the Steering Committee and the WSU community at large that some reports will not be ready at go live. Projections indicate that completion is currently anticipated by April 2021. The Project team has initiated daily meetings to prepare for the Hypercare period immediately following go live. The Workday Service Desk has been activated and the support team oriented. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page ii
Plans are in place to provide the Team with a guidebook documenting responsibilities and the resolution process. The Project team has developed reporting to monitor intake, prioritize and assign/escalate requests, and track response time. Status reporting will be provided to the Project team and Project leadership to monitor response timing and aging of individual service requests. The Project team plans to respond to service requests by referencing Project materials (e.g., knowledge base, training videos, reference guides) available through the Modernization Initiative web site to highlight the availability of the materials on the web site, orient the service requestor as to the content of the materials, and encourage them to resolve the request using their own resources. Mainframe processing time concerns noted in last month’s report were addressed through an increase in CPU capacity. The Project team indicates that the additional capacity has resolved the concern. Project Management and WSU have met with Workday and completed the required Workday Delivery Assurance (DA) Functional Review checkpoints. End User Training and Unit Readiness In this assessment, ISG closes the end user training and unit readiness issue. In addition to actions noted in previous reports, Project leadership has dedicated significant effort to eliciting support from WSU institutional leadership to encourage participation in end user training and unit readiness for go live. This has included correspondence from the Project Executive Director to institutional leadership via the WSU Executive Summary and Project leadership discussions and/or presentations with: • The President’s Cabinet; • Deans; and • Administrative Financial Officers (AFOs). The Project team also leveraged established communication channels such as the monthly Modernization Newsletter and the bi-weekly communication in the WSU Insider to encourage members of the WSU community to take advantage of Project training opportunities in preparation for go live. Additionally, the Project team made videos of live training sessions available to the WSU community for those seeking initial training and for those interested in a refresher. These videos serve to mitigate the risk that users who missed or failed to sign up for earlier in-person training sessions would be unable to receive training prior to go live. The Project team also delivered the first Reporting Workshop to approximately 150 participants. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page iii
Sustainment In previous reports, ISG has suggested labs to allow unit members to convene (most likely virtually) so they could develop, confirm, and practice local procedures. These labs would be supported by Project team members, most likely Business Analysts. During the assessment period, Project leadership approved the extension of a training tenant for six months. This tenant will be available to units to practice local procedures using Workday. Training labs remain in the queue of potential Project activities and will be available if Project resources are sufficient. High Service Desk Volume For the reasons noted above, ISG encourages the Project team to anticipate substantially higher volume of Service Desk contacts than otherwise and provide for a commensurate level of Project team and central office availability to address incoming queries. Project Status The PMO Status Report for the week ending December 4 was reviewed during the December 8 PMO meeting. It classifies Training and the Project overall in “yellow” status. During the meeting, Project leadership agreed to move the overall Project status rating to “green,” indicating a readiness to go live ISG agrees with the PMO that the Project is ready for go live but we continue to assign it a “yellow” status due to the status of unit readiness, an area not specifically assigned a status rating by the PMO. Project Activity Project activities during the current assessment period have focused on: • Loading the Gold tenant in preparation for the transfer of data to the Production tenant that Workday will support; • Resolving outstanding action items; • Moving remaining financial integrations toward completion; • Completing training materials and materially completing training delivery; • Preparing the Service Desk environment and Service Desk-assigned staff for post-go live support including clarification of roles and responsibilities and training; • Finalizing and executing the detailed cutover plan; • Reviewing and updating the Workday Deployment Readiness spreadsheet and completing Workday DA reviews; • Issuing the Project monthly newsletter, and preparing other communications to WSU leadership and the WSU community; • Engaging with WSU institutional, academic, and administrative leadership to set expectations regarding cut-over and the stabilization period that follows; Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page iv
• Updating the Project website; and • Updating and elaborating the Project Workplan. Assessment Structure This document is structured as follows: 1. Executive Summary We summarize significant data points, progress toward the achievement of important project activities or milestones, and our observations, findings, and recommendations in this section. We also present a high-level dashboard overview. 2. Project Progress and Detailed Assessment by Project Management Area As required by the OCIO and consistent with best practice, we present our initial observations, findings, and recommendations organized by the ten practice areas of project management as promulgated by the Project Management Institute. These ten areas encompass the critical activities of a successful project. 3. Summary of Findings We summarize findings from our assessment with corresponding recommendations. This section will include new findings, as well as open and completed findings. Thank you for this opportunity to serve WSU and the State of Washington. I attest that ISG has prepared this report independently. Please contact me with any questions or comments. Sincerely, David Hemingson, Partner ISG Public Sector Email: isg_usa.highered@isg-one.com Phone: (512) 231-9212 Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page v
Table of Contents EXECUTIVE SUMMARY ......................................................................................................................................... 1 Overview................................................................................................................................................ 1 Dashboard ............................................................................................................................................. 2 ASSESSMENT OF PROJECT PROGRESS ............................................................................................................ 4 Schedule ................................................................................................................................................ 5 Budget ................................................................................................................................................... 6 QUALITY ASSURANCE ASSESSMENT................................................................................................................ 7 PMBOK Practice Area 1: Integration Management .............................................................................. 8 PMBOK Practice Area 2: Scope Management ...................................................................................... 9 PMBOK Practice Area 3: Schedule Management ............................................................................... 10 PMBOK Practice Area 4: Cost Management....................................................................................... 11 PMBOK Practice Area 5: Quality Management .................................................................................. 12 PMBOK Practice Area 6: Resource Management ............................................................................... 12 PMBOK Practice Area 7: Communication Management .................................................................... 14 PMBOK Practice Area 8: Risk Management ....................................................................................... 15 PMBOK Practice Area 9: Procurement Management ........................................................................ 15 PMBOK Practice Area 10: Stakeholder Management ........................................................................ 16 ASSESSMENT OF THE ACCURACY OF THE PROJECT’S TRACKING OF PROGRESS ......................... 19 RISK ASSESSMENT .............................................................................................................................................. 20 SUMMARY OF OBSERVATIONS ....................................................................................................................... 22 SUMMARY OF OPEN FINDINGS ....................................................................................................................... 24 ISG QUALITY ASSURANCE METHODOLOGY ............................................................................................... 25 Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page vi
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Executive Summary ISG Public Sector (ISG) presents this Quality Assurance (QA) Assessment Report for the Washington State University (WSU or the University) Modernization Initiative for the period November 16, 2020 through December 15, 2020 (the assessment period). Overview This is the twenty-eighth monthly QA Assessment Report presented by ISG in its role as QA consultant for the WSU Modernization Initiative (the Project). With respect to earlier QA Assessment Reports, we conclude that Project leadership continues to consider the recommendations presented in the reports and is acting to address them. Human Capital Management (including payroll) go live is scheduled for tomorrow (December 16). Financials and Procurement processes will be activated on or about January 1, 2021. Review of the recently updated Project Workplan indicates that the following key activities deserve close monitoring: post-automated conversion manual updates and Service Desk operation. Risks related to unit readiness cause us to conclude that Project status remains “yellow.” ISG reports no issue that we classify as a finding.1 We make several observations, noting several risks that will be monitored as the Project progresses.2 We will continue to monitor these risks. 1 An issue is “a situation that is certain and that could affect Project success in a positive or negative manner.” 2 A risk is “an uncertain situation, the likelihood of the situation, and the impacts (which can be positive or negative) that the occurrence of the situation would have on Project success.” Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 1
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Dashboard This dashboard presents an overview of our assessment of the Project and the ten Project Management Book of Knowledge (PMBOK) practice areas as of December 15, 2020. Project Status -- Focused Attention Required Change since Last Findings & Project Management Area Area Status Assessment Observations 1. Integration Management Risk Reduced 2. Scope Management -- 3. Schedule Management Risks Continued 4. Cost Management -- 5. Quality Management -- 6. Resource Management Risks Reduced 7. Communication Management -- 8. Risk Management -- 9. Procurement Management -- 10. Stakeholder Management Issue Closed; Risks Continued Findings & Traditionally High-Risk Areas* Area Status Observations 1. Change Management 2. Integrations/System Remediations 3. Reporting** * Areas that have proven to be high-risk during the implementations of enterprise systems at research universities like WSU. ** Generation of dashboards, analytics, queries, and reports needed for decision-making at all levels of the University and for compliance with regulatory and other third-party reporting. This includes reporting that is impacted by the replacement by Workday of current HCM and Financial data sources. ISG Monitored Areas* Rationale 1. PMO Troika Variance from best practice 2. Inter-agency Agreements Criticality to project success 3. Lack of Critical Path Variance from best practice * Areas monitored by ISG but not rising to a level that requires Project leadership’s attention at this time. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 2
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Legend Assessment Status Change Risks/issues being addressed Neutral; risks/issues partially being addressed or newly listed Risks/issues increasing Area Status Major finding likely to adversely impact project progress or outcome Finding/issue requiring attention or observation/risk being addressed and monitored No finding or observation requiring action at this time Findings & Observations Finding(s)/issue(s) noted Finding(s)/issue(s) and observation(s)/risk(s) noted Observation(s)/risk(s) noted No finding or observation at this time Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 3
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Assessment of Project Progress The Project continues to operate in a work-from-home environment. This will continue for the foreseeable future. ISG believes that the Project is ready for go live but we continue to assign it a “yellow” status due to the status of unit readiness. Although not critical enough to halt go live, we believe the state of unit readiness will result in a higher impact on the Service Desk. The Project team continues to: • Develop deliverables corresponding to tasks in the Project Workplan; • Execute Deploy Phase tasks; and • Elaborate the Project Workplan. Project Staffing Deloitte is providing interim support for the Core Finance and Budget Lead who resigned several months ago. The absence of a lead in this key role represents a risk to the Project. The WSU Change Management Lead is on maternity leave. This is a key position in an area that is traditionally high risk and the vacancy in this position also represents a risk to the Project. Deloitte Staffing Commitment Deloitte’s original contract was fixed cost. Current services as part of the timeline extension provided by Deloitte under the recently modified SOW are now paid on a time and material basis. Project leadership confirms that WSU measures Deloitte’s progress based on timely delivery of quality deliverables. A comparison of the effort committed by Deloitte in its Statement of Work (SOW) against actual hours applied was for monitoring purposes only and was provided in response to a request from Project leadership. An unanticipated shortage of actual hours applied, if it were to occur, may be cause for concern. Deloitte’s commitment cumulatively throughout the Project substantially exceeds the anticipated hours presented in the SOW. Project Deliverables Status The Deliverable Log was updated during the assessment period. The Deliverables Log indicates that all Test, Deploy, and Support Phase Deliverable Expectation Documents (DEDs) have been submitted to WSU and all have been accepted. As the Deploy Phase draws to a close, the following deliverables remain outstanding: • Knowledge transfer acknowledgement; • Training Completion and Sustainment Plan; Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 4
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 • Site Readiness and Deployment deliverable; and • Cutover confirmation (due following cutover). Most deliverables reviewed by ISG have been of quality. In those instances when ISG has not found the deliverables to be of quality, ISG has presented WSU with recommendations to bring the deliverables to a leading practice standard. Project deliverables are being classified consistent with guidelines in the Project Charter and are being posted on a Deliverables Log accessible through the internal Project web site maintained by Deloitte. Project Workplan Project leadership routinely updates the Project Workplan. Project leadership should continue to review and elaborate tasks in the Project Workplan. Based on our assessment of the Project Workplan this period, we conclude that it accurately reflects the status of the Project at this time. Schedule During the assessment period, the Project team: • Loaded the Gold tenant in preparation for the transfer of data to the Production tenant that Workday will support; • Resolved outstanding action items; • Moved remaining financial integrations toward completion; • Completed training materials and materially completed training delivery; • Prepared the Service Desk environment and Service Desk-assigned staff for post-go live support including clarification of roles and responsibilities and training; • Finalized and is executing the detailed cutover plan; • Reviewed and updated the Workday Deployment Readiness spreadsheet and completed the required Workday DA reviews; • Issued the Project monthly newsletter, and prepared other communications to WSU leadership and the WSU community; • Engaged with WSU institutional, academic, and administrative leadership to set expectations regarding cut-over and the stabilization period that follows; and • Updated the Project website. The PMO: • Updated the Project Workplan for current activity; • Encouraged documentation of project decisions in the Risks, Actions, Issues and Decisions (RAID) log; and Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 5
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 • Actively addressed risks including those identified in earlier QA reports. We find that the Project Workplan is being updated on a timely basis. We will continue to monitor the Project Workplan as the Project moves forward. The Project Workplan presents a high-level timeline for the Project with estimated completion dates. The HCM is planned for 8 a.m. PST tomorrow. Workday Financial Management processes will be activated on January 1, 2021. The final phase (i.e. the Support Phase) is estimated for completion in mid-March 2021. Budget The Project is operating with sufficient budget. Project Management has provided ISG with a monthly project spend plan for the current fiscal year and an updated report of actual expenses through November 2020. The report indicates that budget tracking is current, that WSU had allocated a contingency that we consider reasonable and prudent for the Project timeline, and that the Project was running an overall positive variance, before consideration of the contingency. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 6
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Quality Assurance Assessment ISG presents below its Quality Assurance Assessment for the time period November 16, 2020 through December 15, 2020 (the assessment period). We report our assessment of Project performance for each of the ten Project Management Book of Knowledge (PMBOK) practice areas: 1. Integration Management 6. Resource Management 2. Scope Management 7. Communication Management 3. Schedule Management 8. Risk Management 4. Cost Management 9. Procurement Management 5. Quality Management 10. Stakeholder Management Each section below begins with a definition of the respective practice area. Please refer to the final section of this report, ISG Quality Assurance Methodology, for a description of the ISG Quality Assurance methodology that serves as the basis for this Assessment. On the following pages, ISG discusses the status of each of the ten Practice Management Book of Knowledge (PMBOK) practice areas. As appropriate, we identify observations, findings, risks, and issues and, for each observation or finding, we describe the impact, present our recommendation and report status. Risks and issues are defined consistent with PMBOK standards. A risk is “an uncertain situation, the likelihood of the situation, and the impacts (which can be positive or negative) that the occurrence of the situation would have on Project success.” An issue is “a situation that is certain and that could affect Project success in a positive or negative manner.” The OCIO requires WSU responses to issues raised in QA reports. We commend WSU for its timely attention to both risks and issues, and for its transparency in presenting written responses. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 7
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 PMBOK Practice Area 1: Integration Management Integration management includes the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities within the project management process groups. Discussion Coordination with Resources Outside the Project Timely completion of operational tasks is dependent upon successful integration with resources not within the direct control of Project leadership. Examples include: • University partners that report to Project leadership but are not Project team members (e.g., Controller’s Office, Human Resources); • University partners that do not report to Project leadership (e.g., Information Technology Services, Sponsored Projects); • WSU’s commercial partners (e.g., financial institutions); and • WSU’s State agency partners. Risk Actions resulting from the COVID 19 pandemic have impacted these partners just as they have the Project team but, in some cases, to a much more significant degree, which further increases this risk. Recommendation We recommend that Project Management continue to monitor these relationships, as they have been, and be prepared to engage the Executive Sponsor, the Steering Committee, and University leadership, as necessary, in encouraging timely completion of tasks necessary and in some cases critical for Project success. Status Project Management is aware of this risk. The Project Executive Sponsor has indicated her willingness to act as necessary. Project leadership has communicated the status of these various open items to the Board of Regents, the President’s Cabinet, the Steering Committee, and various other WSU leadership groups, and highlighted the need for close coordination to complete them in a timely manner. ISG will continue to monitor this risk. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 8
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 University Operations Funding Reductions resulting from COVID-19 Impacts WSU has reduced funding for University operations, in part due to the impact of the COVID-19 pandemic. Although Project funding is intact, WSU Project participants have been impacted. The impacts take various forms but perhaps the most pervasive impact is on campus, college, and central administrators. These administrators are among those most impacted by the Project (e.g., transition to new Workday-driven processes). They are also most likely to be involved in assessing, planning for, and implementing changes resulting from COVID-19-related wellness and safety protocols and reductions in University funding. These are competing commitments. Status The Project has successfully moved to go live and will move into the Support Phase shortly. Accordingly, we close this risk. Critical Path Throughout the Project, ISG has observed that the identification and maintenance of a critical path through the Project Workplan will provide Project leadership with insight that informs scope and resource decisions. It will also allow Project leadership to monitor key, critical path tasks and recognize the implication to completion slippage. Importantly, the critical path will provide the Project Steering Committee and Project leadership with confidence that the activities necessary to support Project go live can be completed by planned go live dates. Review of the critical path document delivered by Deloitte indicates that it identifies important tasks. However, it does not incorporate resource availability and does not provide Project leadership and the PMO with information regarding slack time (if any) available to the Project, which is the primary purpose of critical path analysis. Awareness of the slack time available is important for the reasons noted above. Status The Project has successfully moved to go live and will move into the Support Phase shortly. Accordingly, we close this risk. Observations regarding the Project Workplan are presented earlier in the “Project Workplan” section of “Assessment of Project Progress.” Observations regarding end user community engagement are presented in the Stakeholder Management section below. PMBOK Practice Area 2: Scope Management Scope management includes the processes required to ensure that the Project includes all the work required, and only the work required, to complete the Project successfully. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 9
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Discussion University Stores had planned to implement a new inventory system separate from Workday. The Project team, having demonstrated Workday capabilities to University Stores representatives and learned of the organization’s decision to move forward with a separate system, scoped the Project and configured the Workday software based on this operating assumption. Since that decision was made, a number of factors have impacted University Stores operations. University Stores has not implemented a new inventory system and has very recently determined that its best option at this time is to re-platform its mainframe-based system. ISG acknowledges that implementation of inventory functionality in Workday was not in Project scope. Although not a Project risk, this does represent a risk to WSU. Status ISG has identified no reportable Project risks or issues in this area at this time. PMBOK Practice Area 3: Schedule Management Schedule management includes the processes required to manage the timely completion of the Project. Discussion Resource Bottlenecks The business analysts on the Project team have the most detailed understanding of the configuration of the new system. Demands on HCM and Finance team business analysts’ time and attention are from many sources and, in many cases, Project team resources have been overcommitted. Prioritizing and coordinating these activities require the careful planning and the integration of numerous tasks. Any project delay causes the business analyst activities to stack on top of each other against a deadline and easily overcommit the time available. Risk Without prioritization and careful planning, business analyst effort can be applied ineffectively, resulting in bottlenecks and delays in the completion of Project tasks. Recommendation As noted earlier, we recommend that the PMO estimate the effort associated with tasks in the Project Workplan for all Project team members (including Deloitte resources), load resource availability, identify gaps in resource availability, and establish a critical path through the duration of the project. We recommend that the PMO monitor team member utilization to anticipate bottlenecks and take other actions necessary to avoid recurrence of the same problems with resource utilization. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 10
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Status Project leadership has developed and monitors “resource plans” for WSU project team members over a rolling multi-week period. The Finance Team Lead and the HCM Team Lead routinely estimate the effort required of Project resources and adjust assignments to level effort, in recognition of resource constraints. ISG will continue to monitor. Report and Integration Development Report development efforts have proven to be challenging for the Project team, as they are traditionally for similar projects. A few integrations remain outstanding. Risk Design, build, and unit test of reports and completion of a few integrations are among the set of tasks past due and/or represent a risk area. Recommendation Continue to monitor the pace of development. Assign priority to development of reports required for go live. As appropriate, apply additional Project resources in support of resolution of outstanding operational decisions. Status Development of reports classified as “critical” and “high” has been completed. Eighty-seven medium and low reports remained outstanding at the conclusion of the assessment period. Project leadership reports that these have been prioritized within these overall classifications and will be addressed in priority sequence. The Steering Committee and the University community have been informed that some reports will not be available at go live. PMBOK Practice Area 4: Cost Management Cost management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the Project can be completed within the approved budget. Discussion Observations regarding the Modernization Initiative budget and spend plan are presented earlier in the “Budget” section of “Assessment of Project Progress.” Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 11
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Status ISG has identified no reportable risks or issues in this area at this time. PMBOK Practice Area 5: Quality Management Quality management includes the processes and activities of the performing organization that determine quality policies, objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken. Discussion WSU has incorporated a quality assurance process into its deliverable development process. This process is documented in the Project Management Plan and has been accepted and put into practice by the Project team. We have observed the Project team continuing the cadence for Project deliverable definition and acceptance for deliverables outlined in the Deloitte SOW and included in the Project Workplan. In our assessment, the quality of DEDs, which we review following WSU’s review, and adherence to the definitions has been mixed. With a few exceptions that we have noted in our assessment reports, we have found the final products to be acceptable. Status ISG has identified no reportable risks or issues in this area at this time. PMBOK Practice Area 6: Resource Management Resource management includes the processes that organize, manage, and lead the Project team. Discussion ISG continues to find that WSU has staffed the team with a very professional Project team. We commend Project leadership for the high standards it has established and maintained. Project Team Position Vacancies Deloitte is providing interim support for the Core Financials position vacancy. The Change Management Lead position is temporarily vacant as the lead for this area is out on maternity leave. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 12
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Risk Vacancies filled with Deloitte staff exposes WSU to considerable loss of knowledge when the Deloitte consultants leave. Recommendation Continue to pursue the current approach. Status ISG will continue to monitor this risk. Departmental Resource Availability The Project team has analyzed the impact of Workday on departmental operations and continues to be cognizant of campus, college, and other unit interests. Risk As Project Management recognizes, the Project is dependent upon resources outside the Project team to accomplish tasks in a timely manner and necessary to maintain the Project schedule. Recommendation ISG recommends that the Project team: • Continue providing the WSU community with effective communication of Project plans, activities, and decisions. • Continue to develop project plans and communicate anticipated area resource requirements and the timing of critical project activities. Develop and communicate support available to campus, college, and departmental units. • Establish an internal process to identify and resolve key user constraints or other bottlenecks in the impacted WSU community (i.e., outside the Project team). As appropriate, engage institutional and departmental leadership and remind them of their commitments to Project objectives and the benefits that achieving those objectives will provide their departments. Monitor key user participation and, as appropriate, identify alternative participants to spread the opportunity to contribute to the Project more evenly across the user community. Status WSU has activated the Change Network and has provided the change agents with monthly checklists of activities to prepare for the implementation. WSU continues to update the WSU community as plans are developed. WSU is aware of the risk and is acting to mitigate it. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 13
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Project leadership has taken actions to address this risk as outline earlier in this report. ISG will continue to monitor. COVID-19 Impact The COVID-19 pandemic has the potential to impact Project team members and other significant resources necessary for Project success. Risk A COVID-19 infection could incapacitate a member or members of the Project team or other significant resources necessary for Project success. Recommendation Continue to monitor the health and safety of Project team members. Develop a contingency plan in case a Project resource is incapacitated. Status During the assessment period, a member of the Project team contracted the COVID-19 virus. The ISG team hopes for his timely and full recovery. Project Management is aware of this risk. ISG will continue to monitor it. Slow Processing by Mainframe Computer During Dress Rehearsals for cutover, the Project team experienced processing times that were notably longer than during previous rehearsal cycles. Team members report that this results from a reduction in CPU throughput capacity recently implemented to reduce operating costs. Status WSU acquired additional CPU capacity which eliminated the extended processing times. This risk is therefore closed. PMBOK Practice Area 7: Communication Management Communications management includes the processes that are required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposition of project information. Discussion The Project team is maintaining project documentation in a reasonably effective and timely manner. The Project Deliverables Log details planned due dates for Deliverable Expectation Documents (DEDs) and the deliverables themselves, and review responsibilities for completed Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 14
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 and current Project phases. As documentation reviews are completed, acceptance is noted in a timely manner. In addition, the Project team is maintaining the Modernization Initiative web site, http://modernization.wsu.edu. In our assessment, the web site represents an excellent orientation to the Project and provides an interested community member with an effective means of understanding the Project, its future course, and setting expectations regarding the impact of new business processes and the Workday software based on Project decisions. The web site communicates events well into the future so that the WSU community can plan to participate effectively in Project events. Status ISG has identified no reportable risks or issues in this area at this time. PMBOK Practice Area 8: Risk Management Risk management includes the processes of conducting risk management planning, identification, analysis, response planning, and controlling risk on a project. Discussion Project leadership is conducting risk meetings approximately monthly. Participation is meaningful and effective. In our assessment, the participants give serious consideration to Project risks and identification of mitigating actions to address them. In addition, key risk topics are reviewed with the Steering Committee. Status ISG has identified no reportable risks or issues in this area at this time. PMBOK Practice Area 9: Procurement Management Procurement management includes the processes necessary to purchase or acquire products, services, or results needed from outside the Project team. Discussion ISG believes the activities in this practice area are on track. Status ISG has identified no reportable risks or issues in this area at this time. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 15
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 PMBOK Practice Area 10: Stakeholder Management Stakeholder management includes the processes required to identify all people or organizations impacted by the project, analyzing stakeholder expectations and impact on the project, and developing appropriate management strategies for effectively engaging stakeholders in project decisions and execution. Discussion The focus on OCM-specific activities has increased as the Project moves into its final phases. The Project team has deployed the Change Network. Members of this group have participated in activities such as monthly Change Network meetings and facilitating completion of checklist assignments. Project leadership, recognizing resource constraints, has moved local procedure workshops into the Sustainment period that follows go live. The objective of these workshops is to increase understanding of Workday business processes and increase user confidence in the ability to conduct local operations after Workday goes live. Training The lack of participation in Workday training continues to be a point of concern. The Project team has taken numerous actions to communicate the importance of training and unit readiness to the University community. The Team has also made available significant training resources that the University community can access. We consider this a Project risk. Risk A well-trained user community is critical to a successful implementation. Without sufficient knowledge of Workday concepts and processes and confidence in their ability to conduct operations using the Workday software, WSU users will find themselves experiencing significant difficulties in providing the level of service they anticipate of themselves and the University community expects of them. Recommendation ISG presented a set of recommended actions in our October report including offering training labs that assist unit leadership and their reports in effectively transitioning and conducting unit operations in the Workday environment. Plan for delivery during Sustainment and clearly communicate these plans to the user community. Status Since the Project is going live and has made significant efforts to encourage training participation and unit readiness, we close this item. It remains as a risk that is addressed in the following observation. We close this risk. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 16
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Unit Ability to Adapt to Business Process Changes Most HCM and Finance business processes will be impacted significantly by the introduction of Workday. Risk In some cases, academic and operating unit personnel do not understand how to adopt and accept the change brought about by the Workday implementation. Recommendation Continue to refine a unit readiness approach that identifies change impacts to the unit business processes and how the Project team will work with the unit’s change agents to ensure the changes are understood, accepted, and adopted ideally prior to go live to ensure a smooth transition to production operations. In addition to training, end users need the opportunity to practice. It is most beneficial for users to practice with other members of their unit to reinforce not only how to use the system, but how the business processes will work within their operation. Providing the Change Agents and Super Users the tools (e.g., practice tenant) and support to organize these practice sessions, allows them to work through concerns that they may not encounter until after go live. It can also provide an opportunity to pilot the support organization. WSU Project leadership has determined that resource constraints are such that training labs will not be available until Sustainment. Although not ideal timing, facilitating training labs in which unit personnel can meet virtually to discuss how their unit will conduct business and provide services with Workday support during the early weeks of the next calendar year will coincide with a relative “lull” in other administrative activity, particularly given the University’s decision to delay Spring semester start-up for a week. Even with the delay in training labs, WSU Project leadership should consider a transition workshop, held with a broad set of units, to address key processes that will be critical shortly after go live. These workshops might be provided to groups of similarly organized units (e.g., central units, academic units with central school support). Key processes might include time reporting/absence management and payroll, faculty contract renewal, student hiring, and purchasing (Pcards processing, in particular). The Project team has used Zoom effectively to accomplish many Project tasks. We suggest that Zoom can be used to create an effective environment to conduct these labs. Status The Project team prepared a user engagement strategy and plan and departmental impact assessment. These efforts includes tasks to validate business process changes and impacts. The team had planned to publish business processes and anticipated that Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 17
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 providing access to these will provide the user community with insight that will be helpful in addressing their interests. WSU Project leadership, recognizing resource constraints, has moved local procedure workshops into Sustainment. This represents a risk to the Project that leadership should closely monitor. ISG will continue to monitor it as well. Faculty Readiness Overall readiness in the academic units includes engaging the faculty at the appropriate level for their system use and on a timeline that takes into consideration their academic duties. Risk Faculty will not be prepared for performing business processes/tasks in the new system due to lack of engagement or required training that conflicts with key academic timelines. Recommendation Work with change agents in academic units to fully understand faculty use of the system. Where possible depending upon level of use (core system, self-service), provide training options with flexibility (i.e. micro-learning). Status Training curriculum is developed with multiple delivery channels. The Change Network is in place with representation from the academic units. The Project team has provided targeted communications to Deans regarding training sessions that are most applicable to faculty. ISG will continue to monitor this risk. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 18
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Assessment of the Accuracy of the Project’s Tracking of Progress Our comments in the “Project Workplan” and “Schedule” sections of the “Assessment of Project Progress” present our assessment of the accuracy of the Project’s Tracking of Progress. We have presented recommendations in earlier QA reports to increase the accuracy of the Project’s tracking of progress. Our recommendations include identification of interim project milestones highlighted on the high-level Project Timeline. We believe adoption of these recommendations are necessary for the Project Workplan to accurately report project status. We also note that Status Reports presented at the PMO meeting and to the Steering Committee are deliverable-based and do not reflect all Project tasks reported in the Project Workplan. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 19
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Risk Assessment ISG summarizes project risks and issues below which are potential or actual barriers to meeting project objectives and milestones, the probability of occurring and impact if they occur, and recommended and observed mitigations. Shaded entries indicate the observation or issue has been closed. Practice Area/Risk/Issue Probability Impact Recommended and Observed Mitigations Alert leadership of potential need to engage resources outside the Project to 1: Risk: Coordination with gain timely task completion. Encourage Resources Outside the and support timely Controller’s Office Project Medium High participation in Project decision-making. Anticipate operational changes (e.g., 1: Risk: Funding Reductions revising budgets) impacting priority and from COVID-19 Impacts High High pace of Project task execution. Identify and maintain the critical path in the Project Workplan. Incorporate resource planning in the Project Workplan and critical path analysis. Utilize with resource planning to assess tasks to move to 1: Risk: Lack of Critical Path High High Sustainment. In conjunction with re-planning, incorporate resource estimates, availability, 3: Risk: Resource and dependencies in revised Project Bottlenecks High High Workplan. Monitoring integration completion. 3: Risk: Reports and Communicate to user community that a set Integrations Medium Low of reports will not be available at go live. Continue the current course, applying Deloitte support on an interim basis and 6: Risk: Project Team recruiting a replacement. Provide support Position Vacancies High Medium from Finance Team leadership. Continue to communicate departmental 6: Risk: Departmental resource requirements including timing. Resource Management High Medium Continue to monitor. 6: Risk: COVID 19 Threat to Continue to monitor Project team health the Project Team Low Medium and safety during COVID 19 pandemic. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 20
QA Assessment for the WSU Modernization Initiative Washington State University December 15, 2020 Practice Area/Risk/Issue Probability Impact Recommended and Observed Mitigations Investigate the cause of the slow processing and identify adjustments to 6: Risk: Slow Processing by address or accommodate it during Mainframe Computer Medium High conversion. See recommendations in Summary of Open 10: Issue: Training High High Findings below. Develop detailed unit readiness approach that identifies change impacts and how the Project team will work with the unit’s change agents to ensure a smooth 10: Risk: Unit Ability to transition. Develop a unit readiness Adapt to Business Process scorecard and report out unit readiness at Changes High High PMO and Steering Committee meetings. Leverage change agents to assess faculty readiness. Provide training recommendations tailored to faculty 10: Risk: Faculty Readiness Medium Medium interests. Provide executive leadership with talking points and recommended delivery timing of 10: Risk: Executive communications addressing Project Leadership Demonstrated interests (e.g., continuous improvement Support Medium Medium during Sustainment). 10: Risk: Change Management High High Continue to monitor. Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 21
Summary of Observations The table below summarizes risks based on observations from ISG’s QA report as of December 15, 2020. Shaded entries indicate the observation has been closed. Status as of Practice Area/Observation December 15, 2020 1: Coordination with Resources Outside Project. Alert leadership of potential On-going: need to engage resources outside the Project to gain timely task completion. Monitoring 1: Funding Reductions from COVID-19 Impacts: Reiterate Project contributions to streamlining operations. Anticipate operational changes (e.g., revising Closed budgets) impacting priority and pace of Project task execution. 1: Critical Path. Identify and maintain the critical path in the WSU Project Workplan. Incorporate resource planning in WSU Project Workplan and critical path analysis. Refine the draft provided by Deloitte to achieve the purpose of Closed critical path analysis (i.e., an understanding of the slack time available to the Project), maintain, and monitor on an on-going basis. 3: Resource Bottlenecks. Incorporate resource estimates, availability, and Closed dependencies in revised Project Workplan. Identify and monitor critical path. 3: Reports and Integrations. Monitor pace of development to confirm pace On-going: and assess impact of delays on downstream tasks. Monitoring 6: Project Team Position Vacancies. Continue current course. Leverage Deloitte interim support. Continue recruiting effort. Provide support from Closed Financials leadership. 6: Departmental Resource Availability. Campus and college representative are anxious to learn how the Project impacts their areas. Develop plans and Closed communicate departmental resource requirements and timing. 6: COVID 19. Continue to monitor health and safety of the Project team. On-going: Develop contingency plan in case a Project team member is incapacitated. General Monitoring 6: Risk: Slow Processing by Mainframe Computer. Investigate the cause of the slow processing and identify adjustments to address or accommodate it during Closed conversion. 10: Unit Ability to Adapt to Business Processes Changes. Develop a detailed On-going: unit readiness approach that identifies change impacts to unit business Monitoring Copyright © 2020 Information Services Group, Inc. All Rights Reserved Page 22