STEAM TURBINE MAJOR OVERHAUL 2022 - TECHNICAL SPECIFICATION - ETHICS
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
AFFALDSSELSKABET VENDSYSSEL VEST I/S STEAM TURBINE MAJOR OVERHAUL 2022 TECHNICAL SPECIFICATION PROJECT NO. DOCUMENT NO. A119311-05 031 VERSION DATE OF ISSUE DESCRIPTION PREPARED CHECKED APPROVED 1.0 October 2021 MHJS ALEA/EAHA MHJS
TECHNICAL SPECIFICATION 3 CONTENTS 1 Introduction 5 2 The project 5 2.1 Unit and operating data 5 2.2 Maintenance history 6 2.3 Timeframe and scheduling 8 3 Basic Scope of Works 8 3.1 Planning of the overhaul 9 3.2 Disassembly of turbine 9 3.3 Bearings for turbine 9 3.4 Turbine outer casing and blade carriers/diaphragms 10 3.5 Balance piston and steam glands 10 3.6 Turbine rotor 11 3.7 Main oil pump and auxiliary pumps 11 3.8 Valves 12 3.9 Assembly of turbine 12 3.10 Commissioning 13 4 Optional Scope of Works 14 4.1 New sealing strips for the rotor 15 4.2 New sealing strips for stationary parts (diaphragms) 15 4.3 New blades and replacement 16 4.4 High-speed balancing of turbine rotor 17 4.5 Weld repair of blade carrier/diaphragm 17 4.6 Turbine bearings 18 4.7 Split line stud bolts for turbine outer casing 18 4.8 Control valve – seats 19 https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
4 TECHNICAL SPECIFICATION 4.9 Shaft sealing rings 19 4.10 Steel inserts for diaphragm 20 4.11 Sealing segments for diaphragms 21 4.12 Sealing segments for balance piston 22 4.13 Recommended spare parts or services 22 5 Variations 23 6 General supplies 23 6.1 Manpower 23 6.2 Spare parts 25 6.3 Tools 26 6.4 Consumables 26 6.5 On-site and off-site transport 26 6.6 Cleaning and blasting 27 6.7 NDT 27 6.8 Documentation 27 7 Supply by AVV 30 https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 5 1 Introduction Affaldsselskabet Vendsyssel Vest I/S (hereinafter "AVV") is planning for a major overhaul of the 4,6 MW Siemens steam turbine, type ATP93 V25A-HH at the WtE plant in Hjørring, Denmark. The turbine was commissioned in 1998. The last time to turbine had a major overhaul was in 2012. To ensure continuous reliable, safe and efficient operation of the unit for the next 8-10 years a major overhaul of the steam turbine is needed. 2 The project The project includes the following main tasks: › Basic Scope of Works as stated in Section 3. The Basic Scope of Works consists of: › Major overhaul of the turbine › Commissioning of the unit including vibration measurements and verification tests › Optional Scope of Works as stated in Section 4. The Optional Scope of Works consists of: › Options that can be ordered before the outage › Options that can be ordered during the outage based on fact-findings and evaluations › Variations as stated in Section 4.10. Variations can consist of: › Extra works based on findings or unforeseen tasks, which can be based on a fixed price or the Contractors hourly rates › Refurbishment of used components, supply of new spare parts or machining of components › General supplies as stated in Section 6: › Manpower › Delivery of spare parts › Delivery of tools › Delivery of consumables › On-site and off-site transport › Cleaning and blasting of components › Perform NDT › Documentation. 2.1 Unit and operating data Turbine Manufacturer : Siemens (ABB) https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
6 TECHNICAL SPECIFICATION Type : ATP93 V25A-HH Power : 4,59 MW (max. 5,435 MW) Speed : 10860 rpm Steam pressure : 48 bara Steam temperature : 400˚C Condenser pressure : 0,7/0,25 bara (design) 0,65/0,35 bara (during operation) Fig. 2.1.1 Longitudinal section of steam turbine. It is expected that the unit will reach approximately 192.000 operating hours at the outage 2022 and 197.800 EOH. 2.2 Maintenance history In 2021 Year Activity Remark 1998 First start 2003 Videoscope A few smaller impact marks were noted on the control stage and Inspection (first) on the inlet edges of the guide vanes in diaphragm #2. There (1CS35521) were also some deformed inlet edges on rotating blades in stage #2. In the turbine exhaust there were only slight corrosion and moderate deposits on the last stage blades. 2012 Major overhaul Only minor findings and minor repairs (replacement of sealing strips). Minor erosion/corrosion on blades and diaphragms, that did not required repair. Recommendations for next major overhaul: 1. Machine the fit for the piston rings in the nozzle chamber 2. New sealing ring in the inlet end https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 7 3. New sealing ring in outlet end. 4. It is recommended to prepare for the installation of a stainless- steel insert for stage # 10 and # 11 blade roof sealing area 5. Weld repair of the split joint of diaphragm # 9 with following machining to nominal size 6. Weld repair the turbine casing by the attachment area for diaphragm #9. The recommendations are included as options in this Technical Specification. Safety Inspection Recommendation to install a new trip block according to service after MO bulletin SB13/2009. Ever since 2001 this problem has existed. There is still a pressure of 7 bar (g) left when the trip block is tripped with 2 out of 3 solenoid valves. It is essential that there is no hydraulic pressure left when the trip block is supposed to be tripped. Found a steam leak from a pipe next to ESV valve, recommend correction of the leak. 2014 Modification Modification of bearing bracket oil seal to prevent oil leakage. 2015 LI, Limited Limited overhaul. Inspection Additional work including control of steam strainer and alignment check. Turbine bearings without remarks. On the inlet end the oil sealing of the bearing bracket was modified due to oil leakage. Both gear box and generator were repositioned during alignment check. Videoscope Inlet parts of the turbine were generally in good condition with Inspection deposit free surfaces. General moderate corrosion was found on stationary parts in the 136 235 h middle section of the turbine. The exhaust area was in good condition with only thin deposits on the blades and minor erosion-corrosion on last diaphragms outer ring. Recommendation for next major overhaul: Install a new inspection port between stage 10 and 11 to increase the possibilities to inspect the turbine and exhaust area towards condenser 2. 2018 Service visit Overhaul of ESV due to reported spindle leakage and inventory of customer spare parts. Videoscope Inspection Recommendation next major overhaul: Plan for replacement of eroded sealing strip in stage #11 162 247 h during major overhaul, likely needed in stage #10 as well. Upgrade of Control Upgrade of control system by ABB. system 2019 Safety Inspection Siemens Energy recommends implementing routines to perform the (E1B100579124) single channel overspeed tests and ESV part stroke test after verification by ABB. Also recommend updating logic for bypass valve to allow part stroke test. 2020 Alignment check The gearbox was opened under supervision from Flender- Graffenstaden. All bearings, pinion, and cogwheel where dismantled and replaced by new units. An alignment check of the gearbox was carried out. Safety Inspection Siemens Energy recommends implementing routines to perform the single channel overspeed tests and ESV part stroke test after verification by ABB. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
8 TECHNICAL SPECIFICATION In 2021 a desktop LTA was performed by Siemens. The analysis do not identify any issues with the mechanical integrity of the turbine, other than the recommendations from the previous major and minor overhauls listed above. 2.3 Timeframe and scheduling Please refer to Appendix 5, Milestones AVV must be informed immediately in writing, if the Contractor at any time during the planning or execution phase finds any actual or expected deviations from the time schedule. If, during the project period, AVV requests to introduce minor and non-material changes to the time schedule, the Contractor shall actively cooperate to organize and plan the required changes to the time schedule to avoid unnecessary delays. The outage is planned to start in week 36 2022 (September 5, 2022); however, it needs to be finally confirmed by AVV. AVV reserves the right to postponement or change of the overhaul start time. The outage period is 4 weeks, and the unit is expected to be on grid and in commercial operation by September 30, 2022. Deliveries to the power plant must be clarified with AVV and must always be done on weekdays and within normal office hours. 3 Basic Scope of Works The Scope of Works includes the following activities: › Planning, arranging, and performing the major overhaul of turbine, main and auxiliary oil pumps, turning gear, turbine valves (ESV and control valves) › Inspection and NDT of turbine parts › Install steel insert rings in row 10 and 11 diaphragms › Delivery of spare parts, options and repairs after fact finding and by prior agreement with AVV All parts must to the extent it makes reason be transported to the Contractor's workshop for the cleaning, blasting NDT, fact-finding and overhaul works. However, a first visual inspection of all parts, and an NDT inspection of the CV casing and seats must be carried out in-situ. General supplies specified in Section 6 are all included in the Scope of Works when relevant. Should the Contractor find it necessary to cut one or more pipelines, it rests with the Contractor to re-establish these pipelines and produce documentation for implementation, control, and approval of the work. Cutting of any pipeline requires the approval of AVV. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 9 The Scope of Works include, but not be limited to, the following equipment and services (the Contractor's offer describes in more details the scope): 3.1 Planning of the overhaul › 1 or 2 project meetings on site before the overhaul by the Project Manager to prepare the overhaul in detail › A site visit before the overhaul by the Project Manager and the Site Manager to prepare the overhaul (inspect available spare parts, lifting equipment, site facilities, discuss time schedule and other practicalities) › A de-commissioning engineer should preferably be available on site for making necessary records such as pre-outage tests, check of rotor run out, oil pressure records, bearing temperature etc. when the plant it shut down and the turbine runs down. Alternatively, the needed, relevant and available data could be extracted from the control system. 3.2 Disassembly of turbine › Disconnect and removal of all relevant cabling and instrumentation › Remove all auxiliaries, valves, pipes, hoses, covers etc. to gain necessary access and cut small drainpipes if required › Remove turning gear, overhaul of turning gear › Opening of the bearing and coupling covers › Opening of coupling towards the gearbox and perform alignment measurements for the shaft line (including gear/generator) › Remove stop valve (ESV) › Loosen outer split line bolts and remove turbine top casing › Loosen inner split line bolts and remove all upper parts (blade carriers, diaphragms, balance piston) › Remove top gland bushes › Measure all radial and axial clearances (rotor and stator blades, sealing segments, sealing strips, labyrinths etc.) › Lift out turbine rotor and remove all lower parts like blade carriers, diaphragms, balance piston steam glands etc. from the lower casing › remove all sealing elements and oil deflectors. 3.3 Bearings for turbine › General cleaning externally and internally › Visual inspection of bearings, including pedestals, - replacement of keys and shims as required › Perform PT of white metal (Babbitt), and UT to check bonding according to DIN/ISO 4386 or similar standard. Replacement of Babbitt parts depends on inspection results; reference is made to section 4 Option › Check of the bearing clearances (before and after) › Check bearing electrical insulation › Check bearing shaft seals and clearances (before and after). https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
10 TECHNICAL SPECIFICATION 3.4 Turbine outer casing, nozzle block and blade carriers/diaphragms The turbine has four blade carriers: › Blade carrier 1: 3 rows › Blade carrier 2: 4 rows › Blade carrier 3: 2 rows › Blade carrier 4: 1 row › General cleaning of outer casing including careful preparation for NDT by hand cleaning at the grooves for the blade carriers, balance pistons and steam glands › Cleaning and NDT of nozzleblock › 100% blast cleaning of all blade carriers › Visual inspection of all parts for cracks, rubbing, scaling, erosion, corrosion etc. › Perform NDT (according to detailed NDT plan provided by Contractor) as a minimum 100% at blades and areas with smaller radius/transitions, high loads, and other critical places › Check of turbine casing and blade carriers for roundness, dimensions etc. › Check sealing segments for wear/rubbing › Replace springs for sealing segments › Check the joint faces of the outer casings and blade carriers for erosion and steam leakage and verify it by blue print. The blue dye print must be performed as soon as possible during the disassembly process. The Contractor must perform necessary scraping/polishing by hand of the split line flanges to have clean surfaces. If repair or machining of a split line flange is performed must it be verified by a blue dye check test (cost for repair/machining and extra blue dye check is not part of the base scope, but must be carried out as extra work by prior agreement) › Inspection of flange bolts including cleaning by blasting, NDT, and length measurement. The loosening of the bolts must be made according to bolt design, and provision of all equipment needed for loosening of the bolts is included in the Scope of Works › Perform test to verify that the blades are correctly fixed and secured › Check of supports for lower parts (axial and lateral keys) for sliding ability, clearances etc. 3.5 Balance piston and steam glands › General cleaning › 100% blast cleaning of all parts › Visual inspection of all parts for cracks, rubbing, scaling, erosion, corrosion etc. › Perform NDT (according to detailed NDT plan provided by Contractor) › Check for roundness, dimensions etc. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 11 › Check the joint faces for erosion and steam leakage and verify it by blue dye check. The Contractor must perform necessary scraping/polishing by hand of the split line flanges to have clean surfaces. If repair or machining of a split line flange is performed must it be verified by a blue dye check test (cost for repair/machining and extra blue dye check is not part of the base scope but must be carried out as extra work by prior agreement) › Check spring loaded sealing segments for wear/damages – delivery and installation of new springs is included scope 3.6 Turbine rotor › Check the condition of the rotor sealing strips (balance piston and gland seals) › Cleaning of complete rotor (by blasting). Unless seal strips are deemed too worn or damaged at the initial visual inspection, they must be covered to avoid being damaged during blasting › Visual examination of all surfaces (including shaft journals, rotor blades, shrouds and locking pieces) › Perform NDT at the coupling holes, shaft journals, rotor blades, areas with smaller radius and transitions and other critical places. Special attention on the control stage shroud and damping wire › Check and document the size, distribution, and condition of balancing weights › Measure rotor straightness › Check and document rotor blade off-set › Perform test to verify that the blades are correctly fixed and secured › Transport of rotor on-site and off-site including delivery of transport box (must be approved for road transport). 3.7 Main oil pump and auxiliary pumps › Dismantle main oil pump (MAV20AP110) and the auxiliary pump (MAV20AP120) and the emergency oil pump (MAV25AP110) and opening for visual inspection › Cleaning externally, internally and all parts › Visual inspection of internals, bearings etc. › Replacement all gaskets and soft sealings (delivery of parts are included in the scope) › Assembly and alignment of main oil pump and checking of lube oil pressure and flow (during commissioning) › Assembly and reinstallation of auxiliary pumps, and check/verify pressure and flow (the DC pump is at present running at a pressure that is 0.1 bar too low, and the correct operating pressure must be recovered by overhauling the pump – delivery of necessary spares are included in the Scope of Works) › Test of function Pumps are all from Allweiler: https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
12 TECHNICAL SPECIFICATION Main oil pump (driven by gear) MAV20AP110: SNG44D L46 Q-W67FA2.0 No: G24263 Auxiliary pump (electrical driven) MAV20AP120: VKF-ABB210R46 132S – T860 – 31B No: G24264 DC pump MAV25AP110: VKF-ABB80 R46 – 100L – T860 – 3.1B No: G24265 3.8 Valves Major overhaul of Emergency Shutdown Valve (ESV MAA10AA310) and Control Valves (CV MAA10AA210), including blue dye check of seats and flanges. › Dismantle and open actuators and clean all parts › Visual inspection of the casings for cracks and erosion › Clean and check steam strainer › Blast cleaning of all internal components and bolts › Perform NDT inspection inside surfaces according to the NDT plan provided by the Contractor, › Visual inspection of internal components (valve seats, valve heads, spindles, bushings, sealings etc.) for cracks, wear, deformity, and erosion › Perform NDT of all internal components (valve seats, valve heads, spindles, bushings, sealings, strainer etc.) › Verify flanges and valve seats/heads by blue print. Light machining by hand is part of the scope › Assembly of actuators, adjustment and functional test, including gland steam system. In the present situation the changing in gland steam supply from external to internal supply does not work properly, and the external supply is permanently engaged › Check clearances and tolerances › All consumables (gaskets, seals (packing and stuffing rings), soft parts etc. and replacement hereof are all included in the Scope 3.9 Assembly of turbine › Install all lower parts, bearings, rotor, gear and coupling shaft. All needed shims, keys and guiding elements for adjustment is part of the scope › Measure all radial and axial clearances (rotor and stator blades, glands, balance piston, sealing strips etc.) › Assembly of turning gear › Assembly of gland seals' top part › Place all upper parts and tighten split line bolts › Place top outer casing and tighten split line bolts › Proper surface contact shall be verified by blue-check where relevant, e.g., on bearing saddles, covers, housings, casings, blade carriers, valve seats and flanges etc. › Alignment check of the turbine/gear/generator (complete shaft line) includes all necessary coupling measurements/checks (like run out, https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 13 parallelism, concentricity, gab etc.). If re-alignment is necessary, it must be carried out as extra work by prior agreement › Assembly of bearings, couplings and covers › Assembly of all auxiliaries, valves, pipes, hoses etc. 3.10 Commissioning The Contractor is responsible for the re-commissioning of the turbine, oil pumps and gland steam system after the overhaul but AVV will support with the operational staff. The Contractor shall prepare a commissioning program and time schedule that shall be presented to AVV for approval. The following is as a minimum included: › Cold commissioning › Test of instrumentation › Post outage tests and checks › Valve curves and systems › Start up and test of oil system › Inspection and test of safety systems (safety check) › Run out test from of unit from turning operation. Please note that it may not be possible to perform Hot commissioning immediately after the Cold commissioning. It depends on the possibility of operation for district heat production. › Hot commissioning › Test of steam gland system › Tightness test of turbine valves › Full speed no load › Run out test of unit from full speed › Operating data recording › General commissioning tests › Electronic overspeed test › Synchronization › Tests in different load points – decision of and performed by AVV › Vibration verification measurement (reference measurement prior to outage and verification during commissioning) 3.10.1 Vibration measurements It must be guaranteed that the shaft and pedestal vibration level of the turbine set is acceptable during run up, run-down and normal operation. Measurements from the I&C system will be used prior to and after the overhaul. The measurements prior to the overhaul are considered as base lines. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
14 TECHNICAL SPECIFICATION The vibration level must be measured during the hot commissioning. The Contractor will get access to vibration data prior the overhaul from the I&C system and these measurements are considered as base line. The Contractor is responsible for performing the vibration measurements after the overhaul, analyse the data and if measures are needed to bring the vibration level at an acceptable level a balancing of the rotor may be required. 3.10.2 Tests and Performance Guarantees Tests to verify the performance of the unit will be carried out before and after the overhaul. These tests will determine whether the operational data (power, efficiency, vibration etc.) after the overhaul of steam turbine are comparable to the operational data before the overhaul or better. AVV may carry out a performance test and prove the turbine efficiency by using the operating instruments prior to and after the overhaul at comparable load and operating conditions. AVV has the right to claim a compensation or a remedy (including re-opening of the steam turbine if deemed relevant for a root-cause analysis) if the operational data are not comparable or better after the overhaul. The Contractor will get access to all test results. 3.10.3 Hand-over When the turbine is hot commissioned, and verification tests have been executed and the performance is to AVV’s satisfaction, the Contractor is entitled to request Hand-Over. At the request of the Contractor, AVV convenes a Hand-over meeting where the Contractor and AVV in cooperation will inspect the Works. When this inspection has been performed to AVV’s full satisfaction and a punch list has been produced with milestones for their remedy, the Works will be handed over to AVV. This Hand-Over is conducted in writing and must be signed by project managers from both parties. Putting into service or using the supply fully or in part does not as such constitute approval of Hand-Over. 4 Optional Scope of Works The Tender must include optional prices and delivery time according to the Price List for the below mentioned optional deliveries. General supplies specified in Section 6 are all included in the Optional Scope of Works when relevant. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 15 4.1 New sealing strips for the rotor There are sealing strips installed in the balance piston and the gland seals. There are no sealing strips between the blade rows of the rotor. The following must be included, as a minimum: › Installation of the rotor in the lathe › Removal of old sealing strips › Cleaning of sealing strip grooves › Making of new sealing strips › Installation of new sealing strips (caulking) › Machining of sealing strips to correct dimensions (height) › Supply report included clearances, tolerances, and findings. The cost of new sealing strips must be based on the following: › A cost for placing/preparing the rotor in lathe machine and replacing all strips on the rotor › Prices deduction per sealing strip not to be replaced for: › Balance piston (total number is not known) › Front gland (total of 36 sealing strips) › Rear gland (total of 20 sealing strips) Front end gland detail Rear end gland detail Balance piston detail (rotor) 4.2 New sealing strips for stationary parts (diaphragms) The following must be included, as a minimum: › Installation of blade carriers/diaphragms in machine https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
16 TECHNICAL SPECIFICATION › Removal of old sealing strips › Cleaning of sealing strip grooves › Making of new sealing strips › Installation of new sealing strips by stemming › Machining sealing strips to correct dimensions › Supply report included clearances, tolerances and findings. Each diaphragm holds two (2) sealing strips. The cost of new sealing strips must be based on the following: › Start-up fee for placing/preparing one blade carrier in a vertical lathe machine › Prices per sealing strip to be replaced for: › blade carrier 1 (rows 2, 3 and 4, total of 6) › blade carrier 2 (rows 5, 6, 7 and 8, total of 8) › blade carrier 3 (rows 9 and 10, total of 4) › Blade carrier 4 (row 11, total of 2) Detail of sealing at blade tips "as found", major overhaul 2012 4.3 New blades and replacement Making and installation of new blades must be offered: › Row 1 (Curtis wheel) › Row 11 of rotating blades The cost shall include removing old blades, delivery, and installation of new blades (incl. shims, keys, locks etc.), preparation of blade groove and machining shrouds to correct diameter. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 17 If a row of rotating blades needs to be replaced option 4.4 High-speed balancing of turbine rotor will be required by prior agreement. 4.4 High-speed balancing of turbine rotor A high-speed balancing can be required in case replacement or repair works have been performed on the rotating blades or the rotor itself. The minimum rotor work that will trigger the Contractors requirement for a high-speed balancing is stated in the Tender (which could be due to blast cleaning, due to replacement of sealing strips, or replacement of blades/blade rows) The following must be included, as a minimum: › Transport to balancing bunker › Needed and approved transport frame/box › Road transport permit (if applicable) › Transport insurance › Install rotor in bunker › A balancing according to ISO 21940 class G 2,5 › Perform test to verify that the blades are still correctly fixed and secured › Remove rotor from bunker › Transport to site › Balancing report (in English. All run-ups/downs must be reported and form part of the documentation) The service shall include needed bearing(s) for the high-speed balancing. The Contractor shall inform AVV if a slot for the high-speed balancing of the rotor must be booked up front to make sure that a bunker is available during the outage. Booking fee is included in the option price. Any extra cost for AVV to be witnessing the high-speed balancing must be priced and listed separately (as Recommendation). 4.5 Weld repair of blade carrier/diaphragm Based on recommendation from the major overhaul conducted in 2012 a repair of the splitline of the blade carrier 3 around blade row/diaphragm 9 may be needed during this overhaul. The extent of the damage when the observation was first made in 2012 is shown below. Some development over the years must be expected. Included in the option all required to perform correction of plane surfaces and diameters to restore the proper tightness of the sealing surfaces. The price is according to the tender list and the following must be included, as a minimum: › Planning and engineering (WPQR's and WPS' as relevant) https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
18 TECHNICAL SPECIFICATION › Equipment for heating, welding, the mobile machining as relevant › All needed alignment, adjustment, and machining › All needed manpower › All needed working environment measures to avoid noise, dust, etc. Consequences for critical, adjacent surfaces must be observed, and e.g. diameters for blade carrier vertical flange/rib must be dressed accordingly. 4.6 Turbine bearings Inspection, white metal condition and bonding check is included in general Scope of Work, outcome of this work determines if bearings are unfit for further, long-term operation and are to be replaced. New turbine journal bearings must be offered for front and rear. Also, a complete set of 16 segments (8 pcs. cw, 8 pcs. ccw) thrust bearing pads must be offered. Full sets of new bearings for front, rear and thrust bearings are already on stock. The option will only come into force if replenishment of the stock should become necessary. 4.7 Split line stud bolts for turbine outer casing Prices for the delivery of split line stud bolts, including sleeves and nuts for the following dimensions and amounts: • M56, L = 440 mm, incl. nut and sleeve (5 pcs) • M48, L = 300 mm, incl. nut and sleeve (5 pcs) • M42, L = 250 mm, incl. nut and sleeve (5 pcs) https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 19 Materials used are (according to OEM documentation) 21CrMoV5 7 V (Werkstoff nr. 1.7709), X22CrMoV11-1 (Werkstoff nr. 1.4923) or X19CrMoVNbN11-1 (Werkstoff nr. 1.4913). 4.8 Control valve – seats and spindle In case the seats and/or the spindle need to be replaced (based on the fact finding) an option price for design, manufacture and delivery and installation of new seats (cages) and spindle are required. It is recognized that manufacture and replacement cannot be carried out within the outage period of 4 weeks. Contractor's proposal to minimize the impact on the time schedule in case a fact finding should reveal critical damages to seats and spindle, must be included in the tender description. It must be noted, that there are no known issues with the seats nor spindle. Control valve cross section. New seats must be designed with an allowance for final machining. 4.9 Shaft sealing rings Based on recommendation from 2012 major overhaul: Option price for the delivery of: › Set of front-end shaft seal ring › Set of rear-end shaft seal ring At the 2012 overhaul the front sealing ring was found to have suffered moderate mechanical wear. The front sealing ring is designed with labyrinth grooves. The rear sealing ring had suffered both mechanical damages, as well as damages due to erosion and corrosion. The rear sealing ring is without grooves https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
20 TECHNICAL SPECIFICATION Rear sealing ring "as found", 2012 Major Design detail of sealing ring (no overhaul grooves in stationary part) Front sealing ring with grooves. 4.10 Steel inserts for diaphragm Based on recommendation from 2012 major overhaul: Erosion of the diaphragms around blade rows 10 and 11 may require installation of steel inserts to re-establish the integrity of the diaphragms and extend the lifetime of the diaphragm. The option includes: › Planning, engineering, and manufacture of steel inserts including new sealings › Transport of parts from site to workshop and return › Machining of diaphragm and preparing for steel inserts › Any required NDT of parts https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 21 Erosion in diaphragms #11 and #10, "as found", major overhaul 2012. Some development in the amount of erosion must be expected over an additional 10 years of operation The time schedule prepared by the Contractor for the tender must include the preparation, design, (pre-)fabrication and installation of the steel inserts for rows #10 and #11. The operation must be planned and prepared so removal of the blades are avoided. 4.11 Sealing segments for diaphragms During the major overhaul in 2012 the average wear of the diaphragms' spring loaded sealing segments were found to be 0,04 mm, but on the bottom halves, the average wear was 0,15 mm (the power loss due to excessive leakages was estimated to be 50-80 kW). Option prices for replacement segments including springs are required (full set for each diaphragm): › Row #2-#8 › Row #9-#11 Details of diaphragms' seals design https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
22 TECHNICAL SPECIFICATION 4.12 Sealing segments for balance piston Option prices for spring loaded sealing segments for the balance piston are required. The system is designed with four (4) rows. The details of the differences between the rows are not available. Individual prices for the 4 rows are required (new springs are included in the basic Scope of Works): › Row/set 1 incl. springs › Row/set 2 incl. springs › Row/set 3 incl. springs › Row/set 4 incl. springs 4.13 Recommended spare parts or services Spare parts or services not mentioned in this Technical Specification should be recommended in case the Contractor finds them necessary to successfully complete the major overhaul of turbine and gear. Recommendations must include breakdown prices for all recommended parts and services. All recommended spare parts must hold a unique ID as well as delivery time. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 23 5 Variations General supplies specified in Section 6 are all included in the variations when relevant. Refurbishment and repair of dismantled components and parts, and supply of new components not included in the Basic Scope of Works or defined as options may be required and will be considered as extra work. Ordering of extra work can be based either on a fixed price offer from Contractor or on the Contractor's hourly rates depending on the nature of the work. Price sheet with the Contractor's hourly and daily rates for the relevant personnel shall be included in the tender and the rates must include travel time, travel cost, daily allowances, transport, PPE (Personal Protective Equipment) etc. For extra work carried out based on hourly rates the Contractor’s weekly timesheets must be approved by AVV before the work can be invoiced. Any extra work or additional supply is to be agreed with AVV in writing (a Variation). If a variation has not been signed by AVV, then AVV has the right to reject any cost related to the additional supply or extra work claimed by the Contractor. 6 General supplies 6.1 Manpower The work is to be organised, manned, and supervised by the Contractor. 6.1.1 Project management The Contractor must appoint a Project Manager with the required experience and competence to oversee the project planning and execution who communicate efficiently in English or Danish. The Contractor must participate in coordination meetings with AVV and other Suppliers, as required. One (1) weekly meeting during the outage must be expected. 6.1.2 Site personnel The Contractor must estimate the need for staffing in his offer, and must as a minimum provide the following personnel for the overhaul, considering the expectation that all parts (to the extend reasonable) are transported to the Contractor's workshop: https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
24 TECHNICAL SPECIFICATION › 1 Site Manager/supervisor who communicates efficiently in English or Danish › All needed mechanical fitters. The Contractor shall provide enough manpower during the overhaul, to ensure that it is finished according to the time schedule › Certified crane drivers › All needed assistance for cleaning › Fact-finder › NDT specialist(s) according to the NDT plan › Balancing/vibration specialist available during start-up › A Commissioning Engineer must be available at site during shut-down and start-up until the plant is operating normally. The Project Manager does not need to be on site during the complete overhaul. Access via e-mail or phone is accepted. The Site Manager can leave site in case all main parts have been shipped to a workshop. The Basic Scope of Works includes all travel and accommodations cost. Additional cost for extra days on‐site to be informed and will be settled according to hourly rates. Replacement of key personnel can only be done by prior agreement with AVV. 6.1.3 HSE It is required that the Contractor provides an HSE Coordinator during the overhaul, who can communicate in Danish or English and has knowledge on the Danish working environment rules and legislation. The Contractor’s Site Manager, Supervisor and Shift Leaders must participate in safety evaluation and planning of the work to be performed. Furthermore, employees working on-site must be introduced to AVV's HSE requirements (ref. Appendix 8 AVV HSE Conditions. The Site Manager must attend health and safety meetings on-site when needed (minimum one per week). Duration approximated one (1) hour. Operator certificates to be acknowledged and approved by AVV and the Danish authorities. It is required that the Contractor participates at a safety meeting in due time before the overhaul starts. 6.1.4 Commissioning, balancing, and testing The Contractors’ Site Manager, Commissioning Engineer and at least two (2) fitters are to be present on site during the commissioning and the Contractor is https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 25 responsible for the turbine operation until the end of commissioning and possible balancing. The Contractor is to specify and execute required inspections and tests on the turbines prior to and during the commissioning. A Balancing Specialist is to be standby during the first starts during the commissioning to verify the vibration measurements. The costs for a Commissioning Engineer at AVV's site for two (2) days (plus travel time) and accommodation costs, are included in the Basic Scope of Works. It also includes an extra travel for the Commissioning Engineer between cold and hot commissioning (it must be the same Commissioning Engineer for cold and hot commissioning). AVV may accept that the cold commissioning is performed by the site manager, depending on his experience. Cost for additional days on site will be according to hourly rates for the personnel concerned. 6.2 Spare parts The Contractor has the full responsibility for the supply of spare parts and replacement works, and the acquisition of all necessary spare parts as well as handling of parts supplied from other suppliers if needed during the overhaul. New flange bolts must have rolled thread unless otherwise agreed and material should be stated and be compliant. AVV has some spare parts available in stock to be used in connection with the turbine overhaul if needed and if possible. Spare parts in stock are listed in Appendix 7 Additional Technical Information. All spare parts in stock are OEM parts and unused. The Contractor has no liability for parts delivered by AVV, only for the correct installation of such parts. Optional spare parts can be ordered before the outage or during the outage based on fact-findings and evaluations and possible recommendations. The following must be included in the price and delivery time, as a minimum: › Reverse engineering (if required) › Fabricate and deliver new spare parts to site › Remove the old parts › Install the new spare parts › Machine to correct dimensions if needed › Test of function. Upon delivery, spare parts shall be packed and preserved for long-term storage. The packaging of individual parts shall be marked with the following information: https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
26 TECHNICAL SPECIFICATION › AVV I/S, Mandøvej 8, DK-9800 Hjørring › Purchase order number and date › Position number as per order or requisition › Description › Drawing number, position number, spare part number › KKS number (if applicable) › Contractor › Name of AVV contact person. 6.3 Tools A tool container including hand tools is part of the Scope of Works. In addition, special tools, lifting equipment, supports, rotor stands (also for transport if needed) must be included. Tools for untightening and tightening of flange and coupling bolts are to be provided by the Contractor, whether it is by induction, heating rods or hydraulic wrenches. The large split line bolts are tightened with heating rods. Prior to use during the overhaul all tools must be tested and approved in accordance with relevant regulation. The approval certificates must be available to AVV upon request. 6.4 Consumables Ordinary consumables like gaskets, O-rings, rags, lubricants, chemicals, cleaning materials, small bolts/pins/ nuts etc. are included in the Scope of Works. Typical specifications for gaskets, O-rings etc. expected to be used during the overhaul must be mentioned in the Contractor's offer. All personal safety equipment (PSE) shall be included in the scope. 6.5 On-site and off-site transport The Scope of Works also includes all on-site and off-site transportation and handling of parts. › All needed on-site and off-site transport (to workshops) are included in the scope, for any option and for extra work › The Contractor is solely responsible for the organization of the transport. All cost related to the transportation shall be included in the offered prices. This includes, but is not limited to transportation cost, packing, needed transport frame/box, road transport permit, insurance for transportation of equipment etc. › The transport company must be qualified to transport high value items https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 27 › All transports from and to site must be dedicated transports without reload/transfer › All transports/shipping is DPU 6.6 Cleaning and blasting All cleaning by hand and blasting is part of the Scope of Works. Component cleaning is to be performed by hand, blasting or whichever method required. The extent of blast cleaning and method of the cleaning is described in the NDT plan provided by the Contractor. If the Contractor need to carry out the blasting on site, the provision of a blasting tent with proper ventilation, all needed working environment measures (to avoid noise, dust, etc.) and removal of used blasting material is part of the Scope of Works. The Contractor is responsible for all cleaning after blasting. Blasting equipment, blasting media and skilled personnel are provided by the Contractor. Disposal of used blasting media must be agreed with AVV. 6.7 NDT The Scope of Works includes visual inspection of dismantled parts, measuring of tolerances and clearances and performing NDT of relevant parts (PT, MPI and UT). The proposed extent and method of NDT must be clearly described in the NDT plan provided with the tender. All NDT activities included in the NDT plan prepared by the Contractor prior to the overhaul and agreed upon is part of the Works. Based on (visual) fact-finding AVV can ask the Contractor to perform additional NDT. Such requirements will be handled as a Variation. 6.8 Documentation The Contractor must thoroughly record all inspections, measurements, repairs, and materials for each component inspected, refurbished, manufactured, and replaced. All documents must be traceable for each component. AVV has protocols from previous inspections (OEM templates). Templates for dimension check protocols and fact-finding report are provided by the Contractor for AVVs approval prior to the outage start. The templates must be in accordance with the historic record sheets to facilitate the comparison with the records of the 2022 overhaul. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
28 TECHNICAL SPECIFICATION 6.8.1 Status reports The Contractor must supply documentation for the status of the overhaul during the execution. The status reports must contain information regarding all field- service activities for parts sent to the Contractor's workshop or elsewhere, and for parts staying on site. As a minimum, the following is to be included: › Daily updates from the Site Manager on ongoing activities on the site (short daily reports) › Weekly status reports for all field-service activities on-site and off-site (Contractor's workshop and Sub-Contractor's workshop). 6.8.2 Fact-finding report Fact finding check list (to be discussed and delivered as soon as possible after inspection has been completed) including statements with agreed actions and repair and a fulfilling description of all works performed and recommendations given The fact-finding report is an ongoing document that should be updated on regularly basis as inspections are performed. Minimum requirements for the fact-finding report: › It must be delivered as an open file with the possibilities to text search in in order easy to find relevant information › It must have bookmarks and Index for easy overview and navigation › It must be divided into main groups (like rotor, outer casing, inner casing, bearings, steam glands, etc.) › There must be a column describing the component › There must be a column with the findings and comment › There must be a column with the Contractor recommendation, including cost and time schedule if possible (or a statement of why it is not possible) › There must be a column with the AVV decision (performed or not) › A statement if a measurement is out of tolerance › A statement for not accepted NDT › Pictures to see the fact finding. Results from inspections are discussed daily, and major findings must be presented to AVV immediately upon discovery. A preliminary fact-finding report must be delivered as soon as possible after the inspection and according to the agreed time schedule as would be discussed as part of a final fact-finding meeting. It is of highest priority for AVV to have an overview and follow the progress in the overhaul, at all time. https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
TECHNICAL SPECIFICATION 29 6.8.3 Inspection report The inspection report includes all visual inspection and NDT findings. As a minimum, the following is to be included: › Measurement of bolt lengths, as well as calculation for tightening and permanent stretch › Measurements of all rotor-stator clearances before disassembly and after assembly › Clearances at the bearings during disassembly and at assembly › Measurements of rotor straightness › Measurements of roundness/dimensions of casings, blades carriers, balance pistons, steam glands etc › Size and distribution of balance weights › Result from inspection of rotor and stator blades, including NDT › Check for steam leakages and contact surfaces at casings, bearing saddles, covers, housings and end frames etc. › Result from blue print of casing and other contact surfaces › NDT reports of all relevant components (NDT plan, part of offer) › Measurements of alignment at the couplings during disassembly and assembly. 6.8.4 Final documentation The final documentation is delivered in Danish or English in an electronic copy on a portable HD drive. All documents of the final documentation should be one open PDF file with all reports included. It should include bookmarks/index for an easy overview and navigation and divided into main groups (like: Fact finding report, protocols, commissioning, new spare parts). The Contractor must submit a draft of the table of contents where AVV can get an overview of the structure of the document before start of commissioning. Drawings (if required) shall be delivered in .DWG or .DXF and .pdf. All documents (reports, datasheets, protocols etc.) shall be delivered in latest versions of Microsoft Office (Word, Excel, Project) or as open .pdf. The identification system for Power Stations (KKS) must be used where applicable (delivery of spare parts, fact findings, protocols). The documentation must be submitted on a continuous basis and the final version must include the following as a minimum: Minimum requirements for the final documentation: › It must be delivered as an open file with the possibilities to text search for relevant information › It must have bookmarks and index for easy overview and navigation › It must be divided into main groups for the Field-service activities, like: › NDT reports https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
30 TECHNICAL SPECIFICATION › Fact-finding reports including statements with agreed actions and repairs › All inspection reports › Commissioning report › Balancing report, if applicable › All relevant pictures as electronic version (.jpg-format). As a minimum, the naming of the photos used to for illustrations in the fact-finding report must include a reference to the fact-finding report Manufacturing drawings and material certificates for all new components manufactured by the Contractor or his sub-contractor. 7 Supply by AVV AVV will be responsible for the following: › Removal and re-assembly of noise hood. The noise hood may only be partly removed upon agreement with the Contractor. › Removal and renewal of the turbine insulation (cushions) is handled by AVV (or third party) › Scaffolding (if relevant) › Ensuring the double isolating shutting off live steam (witnessing and approval by the Contractor) › Execution of a performance test / recording parameters of the turbine set before and after the overhaul of the turbine (if decided) › Changing of filters in lubrication oil and hydraulic systems › Power outlet 1 x 230 VAC, 16 A and 3 x 400 VAC 16/32A CEE › Pressurized air approx. 7 bar › Site facilities (high-speed internet connection (DSL and WLAN), sanitary facilities, locker room, water (potable and service water). › Access to AVV’s workshop for the Contractor when agreed › Crane at site can be used (by Contractor's certified personnel only) https://cowi.sharepoint.com/sites/A119311-project/Shared Documents/03 Project documents/05. Turbine major overhaul 2022/1. Udbudsmateriale/Endeligt udkast til udbudsmateriale (15. okt. 2021)/Dokumenter til upload/A119311-05-031, Technical Specification.docx
You can also read