SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018

Page created by Cindy Lyons
 
CONTINUE READING
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
SCS January 2018
Using a commissioning simulator
to secure plant schedule
                                  SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Agenda                                 © Copyright
                                          TNPJVC

   TAISHAN EPR simulators
   Engineering Simulator overview
   V&V using Engineering Simulator
   Commissioning Tests on Simulator
   TSN U1 Cold Functional Tests
   TSN U1 pre Hot Functional BAS Tests

                                         SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Taishan EPRTM Simulators
   • CORYS provides simulators to both TNPJVC and FRAMATOME
                                        TNPJVC                                               FRAMATOME
                            Operators training and licensing                           Commissioning risk mitigation

   Taiffu Simulator                        Full Scope Simulator                    Engineering Simulator
   •   Copy of FA3 simulator for initial   •   RFT signed on Sept   27th   2014    •    February 2015 1st version installed
       operator training                   •   Used full time for training         •    Four complete I&C update
   •   First version July 2010, updated    •   Successful completion of RO              afterward for CFT and HFT
       twice afterwards                        examination December 2014, SRO           configuration
                                               examination May 2015                •    Simulated operational I&C
   •   Simulated I&C (spec level)
                                           •   Update forecasted after plant       •    Emulated Safety I&C
                                               commissioning
                                           •   Emulated operational I&C
                                                •   Simulated I&C in early stage
                                           •   Emulated Safety I&C

  • FSS project early stage use of simulated I&C before switching to
    emulated I&C was fit to face upcoming commissioning challenges of
    TSN EPR
  • Design is still in progress, simulated I&C is more flexible than emulated
    I&C
                                                                                                              SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Engineering Simulator Scope
   Normal Operation: Full range from primary circuit opened to 100% power
   — Start-up, Shutdown, Load follow, House load, Reactor Trip…

   Incidental and accidental transients
   — Steam Generator Tube Rupture
   — Loss Of Coolant Accident
   — Main Steam Line Break                     TSN Engineering Simulator
   — …                              Simulation     • NSSS
   Malfunctions & local actions     scope          • BNI
                                                   • CI
   — failures of systems,                          • Turbine
   — equipment,                                    • Electrical systems
                                                   • HVAC limited to reactor building
   — breaks in pipes,
                                    I&C            • Simulated operational I&C
   — loss of power,                                • Emulated safety I&C
   — loss of I&C …                                 • Simulated HMI

   Out of scope
   — Operation from safety back-up panels
   — Severe accident
                                                                            SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Engineering Simulator Model
                                                                                          HMI
       Models       Thermal hydraulic:                                           OM690: ALICES simulation
    Inherited from DRAC and SPL (ALICES)                                                    Manual orders
Full Scope Simulator                                                                        Annunciation
                                                                                            signalization

                    Containment                                                          I&C
                                                                                TXS: emulator
                                                                                T2000: ALICES simulation
                                                                                Turbine control: ALICES
   Rod controls       Heat losses,                              Sensors                     Orders and
                    Breaks mass flow                          measurements                  check backs
                       and energy
                                                                                      Electrical
                                                                                     distribution
                                           RCS
                                                                                            Power supply

                                                                              Auxiliary systems
                                       Thermal exchanges,
                                       [B10], Water density    Mass flow     Conventional Island
                                                                Pressure
                  Neutronic model                               Enthalpy
                      COX3D                                    exchanges

                                                                                            SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Electrical and I&C simulation models                             SECTION 1
                                                                                                                  TS1
                                                                                                                        1110JA-

                                                                                                                                                LGA
                                                                                                                                                      1120JA-
                                                                                                                                                                TA

                                                                                                                                                                           99999 V

                                                                                                  LGB
                                                                                                            LGK                                                                                              LGP
                                                                                                                                                                     LIA

   Electrical systems distribution fully simulated
                                                                                                                                                                                                 LKA         LKF
                                                                                                       CI
                                                                   DIVISION 1                          NI                                   G
                                                                                                                                                 LHP
                                                                                                                                                                       99999 V
                                                                                        LGF                                                       LHA
                                                                                                                                            G
                                                                                                                                                 LJP

   —   Main generator                                                                            LIF
                                                                                                                              LJV
                                                                                                                                  LJK

                                                                                                                                  LJF
                                                                                                                                                            2H                   LJV
                                                                                                                                                                                    LJZ
                                                                                                                                                                                           LJA

                                                                                                                                                                                                       12H

       Emergency/Safety diesel generators
                                                                                                                                                                 LAA

   —                                                                                    LKK                        LLA                                                                                             LLU

                                                                                              LKQ                                   LLQ                                LOB
                                                                             LKU                 LKP               LLF                LLP                                 LOA                                      LAK

   —   Batteries
                                                                                                                                                                 LVA

                                                                                                                                                                                     LVP
                                                                                                                                                                     LVB
                                                                       S YN L I S T E
                                                                                                                                                                        LVF                                    LOF

   Non-safety class I&C: Simulated Siemens SPPA-T2000
   —   PROS
       Flexible for analysis/debugging, signals/parameters forcing, I&C logic modifications
       Highly detailed, down to the allocation to cabinets and fallback values
       Easy initial conditions maintenance
   —   CONS cabinets are all synchronized, and I&C time transfers not in the
       model

   Safety-class I&C: Emulated FRAMATOME TXS
   —   Functionality for on-line diagram and running code display,
       parameters modification and implementation of hardware malfunctions

                                                                                                                                                        SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Electrical and I&C simulation models
   Black Boxes
   — Simulated with CORYS engineering toolbox ALICES (turbine and
      generator control, Emergency Diesel Generator, Chillers…)

   HMI: Simulated OM690
   — Same look and feel as the real system

                                                             SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Engineering Simulator and V&V process
                                                 Import I&C database and HMI
                                                 after platform tests…

                                                  OR

                                          … before platform tests

                                                             XML import

   V-cycle                  TEC4 I&C Diagrams         Simulation Diagrams
   — ES can been loaded with I&C databases using export/import tools
      within 2 months.
      So far 4 versions have been loaded for CFT and HFT
   — Latest design changes requested for site tests can be implemented
     quickly on ES to support design, V&V or commissioning
      ~45 design modifications tested on ES to prepare HFT
                                                                          SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Engineering Simulator and V&V process
  V&V activities for an I&C plant configuration are done at different level
                                                                           •   Site Commissioning
      •   Functional verification by Design
                               (Per System)                            •   Engineering Simulator
                                                                           (I&C and process model)
                 •   Implementation verification by              •   Test Bay platform (I&C in cabinets or
                                I&C (Per System)                     emulator) (Per System)

  Advantage of Engineering simulator versus other test means
  —       Fully integrated I&C (safety and operational I&C, priority management, main black boxes) with plant HMI
          (operating displays, procedures and alarms) and process model (closed loop)
  —       Engineering simulator is the best test means that can provide FRAMATOME engineers with a
          comprehensive feedback over the design and procedures quality
  —       Simulated operational I&C is flexible and easy to use to correct/adapt until configuration is frozen. Very
          useful to support design and standard V&V.
  Limitations
  —       Not a qualified tool – complementary of mandatory standard V&V and help to design
  —       I&C performance (time responses) not representative of the real system
  —       Are process models and simulated BBOX representative enough ?
  —       Advanced tool requiring specific skills to work efficiently

                                                                                                     SCS January 2018
SCS January 2018 Using a commissioning simulator to secure plant schedule - SCS January 2018
! Engineering Simulator test objectives
   The initial objective was commissioning risk mitigation by testing:
   —   Normal operation procedures
   —   Commissioning procedures, ~85 procedures chosen among:
       Main plant Control loops
       NSSS Fluid systems tests
       Power supply loss (Main/Auxiliary grid transfer, Emergency Diesel Generator)
       I&C division loss
    → Complex systems, harsh transients, deviation from normal operating range…
   Engineering Simulator use was extended to:
   —   Test of I&C transverse functions hardly testable on site
   —   Particular Operating Rules (operation with loss of an I&C function)
   —   Emergency Operating Procedures test
   —   Human factor tests
   —   Pretest and validation of I&C design changes before standard V&V
   —   Control loops preliminary tuning
   —   FRAMATOME Commissioning team training
   —   Site tests preparation (hydro test, BAS test…)
                                                                                  SCS January 2018
! REX - Benefits for Commissioning

   Validate complex/risky commissioning test procedures
   —   Test sequences, feasibility (I&C interlocks or spurious actions) and
       ergonomics
   —   Check component protection features and assess risk of equipment
       damage
   —   Identify the required I&C temporary modifications to be performed during
       tests

   Verify and validate I&C behavior together with the process
   —   Complex scenario involving many I&C systems interfaces
   —   Control loops behavior, Optimization strategy identification, and pre-tuning
   —   Study fallback operations (reverse path, loss of control loops, …)

   Secure schedule
   —   Early findings of design/procedure flaws saves time on site

                                                                             SCS January 2018
! REX - Benefits for Commissioning
  Training
  —   Very efficient to train staff for good surveillance and avoiding human errors
  —   Commissioning team CFT training and S1 Training
           Mandatory Commissioning and Operation training for Startup Shift Engineers

  Team building and Communication between disciplines
  —   Design and commissioning engineers work out issues together
  —   All disciplines are involved at some point (Process and Safety team, I&C,
      Commissioning…)

  On site support for design/commissioning teams
  —   Design evolutions and Commissioning tests adaptation can be work out quickly
  —   Efficient tool for troubleshooting

                                                                              SCS January 2018
! TSN U1 Cold Functional Tests
  In November 2015, specific simulator activities were done by FRAMATOME
  to finalize CFT preparation using a CFT I&C version.

  The engineering simulator was used for different purposes :
  — Validation/redlining of Normal operation procedures used for CFT
     performance,
  — Validation of TP ENS 21 hydro test procedure on the simulator,
  — Identification of all the I&C temporary modifications necessary to avoid
     spurious actions or blocking actions from I&C during CFT Performance,
  — Validation/Tuning of some control loops used during CFT,
  — Training/qualification of Shift Supervisor Engineer on the simulator before CFT
     (one week).

                                                                          SCS January 2018
! TSN U1 Cold Functional Tests
   Meanwhile TNPJVC rehearsed CFT as well on the FSS
   — FSS I&C was unfortunately not in CFT configuration
   — Validation of emergency plan for over pressure transients during CFT
   — Elaboration of RBS start up and pressure control plan
   — Working on the risk of safety injection from diversification signals
   — Working on I&C interlocks

                                                                        SCS January 2018
! TSN U1 Cold Functional Tests
   TSN Unit 1 Cold Functional Test (CFT) successfully completed on Jan.
   27th, 2016
   — TNPJVC and FRAMATOME preparation proved to be complementary
   — No major problem of procedure identified during CFT
   — The temporary I&C modifications identified during preparation and on
      simulator were exhaustive for hydro test (no concern during CFT
      Performance)
   — Good behavior of the control loops optimized on simulator during CFT
      performance.

                                                                     SCS January 2018
! TSN U1 preHFT BAS Tests
   TSN Unit 1 preHFT NI Electrical Power Supply Change-over Tests (TP
   BAS)
   —   ANT/AST switchover
   —   Switch-over to EDG (LOOP situation)
   —   SBO Diesel Generator Black Start
   —   Complex I&C logics with fully integrated plant
   —   Many I&C forcing and scripting to conduct some tests
   —   Potential risk for some equipment
   3 BAS tests run on Engineering Simulator by FRAMATOME BAS test
   coordinator
   — Run 1 and 2
       Detect main I&C design issues for simulated systems
       Debug simulator electrical model + BBOX issues (EDG/SBO/chillers/…)
       Improve TP tests strategies and instructions
       ›   In particular I&C forcing and scripts to be used during the tests (TCA)

   —   Run 3 performed just before site tests
       Rehearse critical tests taking into account latest site constraint (RPV closed)
       Finalize and validate critical design change
       Validate TP and TCA and gain confidence for upcoming site tests

                                                                                         SCS January 2018
! TSN U1 preHFT BAS Tests
   Tests completed successfully on TSN U1 on March 3, 2017
   — No major issues found on the ES simulation scope, mostly synchronization
      issues due to I&C performance that could not be seen with simulated I&C,
      and BBOX issues
   — Logic issues found on systems out of ES simulation scope (mostly HVAC)
      and/or tests not rehearsed on ES

              Despite known limitations (HVAC/BBOX), ES preparation was
              highly valuable

                                                                       SCS January 2018
! Conclusion
  Close partnership between CORYS and FRAMATOME engineering teams
  allowed regular update of the simulator to stick to the design and meet plant
  schedule
  Engineering simulator allows us to
  — Discover and solve issues (I&C, procedures) before site tests
  — Gather different teams and improve communication and cooperation
  — Train our staff efficiently
  A powerful tool to support design integration and commissioning
  — First full integration of I&C coupled with process before site tests
  — Detail design I&C simulation is very relevant for Commissioning
     Even though it is not as representative as an emulator (time responses in particular)
     A bug found in the simulator I&C logic or parameters is a bug on site as well…
     …and the flexibility of the simulation allows to quickly sort it out
     The exact I&C forcing to be done during Commissioning can be tested
  — Simulator most advanced users are now members of the Start Up Team
  ES is a well known and recognized tool now on the TSN project
  CFT and HFT preparation proved very useful… and we look forward to
  confirm it with successful FLG tests.
                                                                                             SCS January 2018
! LATEST DEVELOPMENTS

  TAISHAN Unit 1 is expecting to have CFL authorisation in coming
  days

  French Flamanville 3 EPR plant just finish beginning of January
  CFT successfully
  — Using also dedicated commissioning simulator loaded with latest
     I&C database
  — Taken into account TAISHAN REX

                                                               SCS January 2018
Thank you for your attention !

        Questions ?

                  Romain BALP – FRAMATOME
                  Patrice ROTH - CORYS
                  Bian Xiu Shi 卞秀⽯石 - TNPJVC

                                       SCS January 2018
You can also read