Contractor Responsibility.
   1. Prepare site for court installation
   2. Relocate sprinkler supply lines
   3. Establish base elevation
   4. Finish work and landscaping
   5. Obtain all required permits
   6. Provided all labor, materials, equipment, implements, parts and supplies necessary for the
        construction of two post tension courts per specifications and as shown on the park illustration.
   7. Provide all required labor, materials, equipment, implements, parts and supplies necessary for
        the colored/textured surfacing of pickleball courts.
   8. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
        installation of the permanent posts and nets for both courts.
   9. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
        fencing of the pickleball courts.
   10. Provide all surveying, construction observation services, and testing services.
Notes for Prospective Contractors
   1. Court construction shall meet city standards and codes, American Sport Builders Association
        (ASBA), and USA Pickleball Association.
   2. A total playing area of 64 feet x 34 feet is required for one single court. There will be a bank of
        two courts requiring an apron of 64 feet x 68 feet.
   3. Court bank apron shall be a 5” thick post-tensioned concrete slab with dropped edges around
        the perimeter of the court bank. Slabs should be constructed using acceptable engineering
        practices in accordance with the American Concrete Institute Building Code requirements for
        reinforced concrete and the post-tensioning institutes tentative specifications for post-
        tensioning materials.
   4. Court bank apron shall be finished with a two-tone acrylic color finish system, finshes shall
        ensure the following key objectives:
            a. To provide a surface properly drained, without depressions exceeding acceptable
                 tolerance.
            b. To provide a surface of uniform texture, speed of play and desired playing quality.
            c. To provide a weather-resistant and ultra-violet-resistant, durable, non-glare, protective
                 finish.
            d. To provide color, contrast and other aesthetic values.
   5. Net shall meet official USA Pickleball Association regulation to maintain 36 inches high at each
        sideline and fixed height of 34 inches in the middle of the court, net frame posts shall be city
        approved and poured in place powder-coated steel posts.
   6. Perimeter fencing shall be city approved 6 feet high chain-link around exterior, interior low
        fencing between the courts shall be 4 feet high chain-link, with two exterior entry gates and one
        interior gate.

Optional Project No. 1.
Cattle Corral Park, 150 E 200 S, Providence UT
One pickleball court & improve existing basketball half-court
Scope of Work                                                                                  Page 1 of 4
2021 Pickleball & Sport Court Project
Scope of Work 2021 Pickleball & Multi-Game Court Project
Cattle Corral Park has an existing 30’ x 30’ concrete slab with one basketball standard. This project
includes extending, improving, surfacing, and adding a 10’ and a 7’ hoop system to the existing pad.
Contractor Responsibility.
    1. Prepare site for court installation and the improvement of the existing basketball half-court.
    2. Relocate sprinkler supply lines
    3. Establish base elevation
    4. Finish work and landscaping
    5. Obtain all required permits
    6. Provided all labor, materials, equipment, implements, parts and supplies necessary for the
        construction of one design/build concrete pickleball court as shown on the park illustration; and
        improving the existing basketball half-court.
    7. Provide all required labor, materials, equipment, implements, parts and supplies necessary for
        the colored/textured surfacing of pickleball court and improving the existing basketball half-
        court.
    8. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
        installation of the permanent posts and nets for both courts.
    9. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
        fencing of the pickleball court.
    10. Provide all surveying, construction observation services, and testing services.
Notes for Prospective Contractors
    Pickleball Court
    1. Court construction shall meet city standards and codes, American Sport Builders Association
        (ASBA), and USA Pickleball Association.
    2. A total playing area of 64 feet x 34 feet is required for one single court.
    3. Court apron shall be a 5” thick concrete slab with dropped edges around the perimeter of the
        court. Slab should be constructed using acceptable engineering practices in accordance with the
        American Concrete Institute Building Code requirements for reinforced concrete.
    4. Court apron shall be finished with a two-tone acrylic color finish system, finshes shall ensure the
        following key objectives:
             a. To provide a surface properly drained, without depressions exceeding acceptable
                 tolerance.
             b. To provide a surface of uniform texture, speed of play and desired playing quality.
             c. To provide a weather-resistant and ultra-violet-resistant, durable, non-glare, protective
                 finish.
             d. To provide color, contrast and other aesthetic values.
    5. Net shall meet official USA Pickleball Association regulation to maintain 36 inches high at each
        sideline and fixed height of 34 inches in the middle of the court, net frame posts shall be city
        approved and poured in place powder-coated steel posts.
    6. Perimeter fencing shall be city approved 6 feet high chain-link around exterior, with one exterior
        entry gate.
    Basketball Half-Court
    1. Court construction shall meet city standards and codes
    2. A total playing area of 30 feet x 50 feet is required for one single court.
    3. Court apron shall be a 5” thick concrete slab with dropped edges around the perimeter of the
        court. Slab should be constructed using acceptable engineering practices in accordance with the
        American Concrete Institute Building Code requirements for reinforced concrete.

Scope of Work                                                                                  Page 2 of 4
2021 Pickleball & Sport Court Project
Scope of Work 2021 Pickleball & Multi-Game Court Project
4. Two basketball hoop systems; one with a hoop height of 10 feet, and one with a hoop height of
         7 feet. Adjustable hoop systems may be considered.
Optional Project No. 2.
Hillcrest Park, 425 E 800 S, Providence UT
One multi-game court (pickleball & half-court basketball)
Contractor Responsibility.
     1. Prepare site for court installation
     2. Relocate sprinkler supply lines
     3. Establish base elevation
     4. Finish work and landscaping
     5. Obtain all required permits
     6. Provided all labor, materials, equipment, implements, parts and supplies necessary for the
         construction of design/build concrete sport court as shown on the park illustration.
     7. Provide all required labor, materials, equipment, implements, parts and supplies necessary for
         the colored/textured surfacing of sports courts.
     8. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
         installation of the permanent posts and basketball hoop system and nets for pickleball and
         basketball.
     9. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
         fencing of the multi-game courts.
     10. Provide all surveying, construction observation services, and testing services.
Notes for Prospective Contractors
     1. Court construction shall meet city standards and codes, American Sport Builders Association
         (ASBA), and USA Pickleball Association.
     2. A total playing area of 64 feet x 34 feet is required for one single court. NOTE: Sidewalk exists
         around the perimeter of the area for this court; the city and the contractor will determine the
         actual size and placement.
     3. Court apron shall be a 5” thick concrete slab with dropped edges around the perimeter of the
         court. Slabs should be constructed using acceptable engineering practices in accordance with
         the American Concrete Institute Building Code requirements for reinforced concrete.
     4. Court apron shall be finished with a two-tone acrylic color finish system, finshes shall ensure the
         following key objectives:
              a. To provide a surface properly drained, without depressions exceeding acceptable
                  tolerance.
              b. To provide a surface of uniform texture, speed of play and desired playing quality.
              c. To provide a weather-resistant and ultra-violet-resistant, durable, non-glare, protective
                  finish.
              d. To provide color, contrast and other aesthetic values.
     5. Net shall meet official USA Pickleball Association regulation to maintain 36 inches high at each
         sideline and fixed height of 34 inches in the middle of the court, net frame posts shall be city
         approved and poured in place powder-coated steel posts.
     6. Two basketball hoop systems; one with a hoop height of 10 feet, and one with a hoop height of
         7 feet. Adjustable hoop systems may be considered.
     7. Perimeter fencing shall be city approved 6 feet high chain-link around exterior, with one exterior
         entry gates.
Optional Project No. 3.
Meadowridge Park, 249 S 325 W, Providence UT
One multi-game court (pickleball & half-court basketball)
Scope of Work                                                                                   Page 3 of 4
2021 Pickleball & Sport Court Project
Scope of Work 2021 Pickleball & Multi-Game Court Project
Contractor Responsibility.
    1. Prepare site for court installation, which includes removing existing concrete slab.
    2. Relocate sprinkler supply lines
    3. Establish base elevation
    4. Finish work and landscaping
    5. Obtain all required permits
    6. Provided all labor, materials, equipment, implements, parts and supplies necessary for the
        construction of a design/build concrete sport court as shown on the park illustration.
    7. Provide all required labor, materials, equipment, implements, parts and supplies necessary for
        the colored/textured surfacing of sports courts.
    8. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
        installation of the permanent posts and basketball hoop system and nets for pickleball and
        basketball.
    9. Provide all labor, materials, equipment, implements, parts and supplies necessary for the
        fencing of the multi-game courts.
    10. Provide all surveying, construction observation services, and testing services.
Notes for Prospective Contractors
    1. Court construction shall meet city standards and codes, American Sport Builders Association
        (ASBA), and USA Pickleball Association.
    2. A total playing area of 64 feet x 34 feet is required for one single court. NOTE: This court will be
        located in an existing park; the city and the contractor will determine the actual size and
        placement.
    3. Court apron shall be a 5” thick concrete slab with dropped edges around the perimeter of the
        court. Slabs should be constructed using acceptable engineering practices in accordance with
        the American Concrete Institute Building Code requirements for reinforced concrete.
    4. Court apron shall be finished with a two-tone acrylic color finish system, finshes shall ensure the
        following key objectives:
             a. To provide a surface properly drained, without depressions exceeding acceptable
                 tolerance.
             b. To provide a surface of uniform texture, speed of play and desired playing quality.
             c. To provide a weather-resistant and ultra-violet-resistant, durable, non-glare, protective
                 finish.
             d. To provide color, contrast and other aesthetic values.
    5. Net shall meet official USA Pickleball Association regulation to maintain 36 inches high at each
        sideline and fixed height of 34 inches in the middle of the court, net frame posts shall be city
        approved and poured in place powder-coated steel posts.
    6. Two basketball hoop systems; one with a hoop height of 10 feet, and one with a hoop height of
        7 feet. Adjustable hoop systems may be considered.
    7. Perimeter fencing shall be city approved 6 feet high chain-link around exterior, with one exterior
        entry gates.
See the following Map & Court Designs (The court designs are illustrative. The City will consider
alternate design proposals from the contractor):
    1. Braegger Park
    2. Cattle Corral Park
    3. Hillcrest Park
    4. Meadowridge Park

Scope of Work                                                                                   Page 4 of 4
2021 Pickleball & Sport Court Project
Scope of Work 2021 Pickleball & Multi-Game Court Project
E 300 S
                                                       300 S                                                                  Possible Court Design
300 E

                                                            1

                                               2

                                                   3

                                                                                           EDGEWOOD DR
                                               5

                                           Braegger Park
                            LN
                        Sm i t h LSnMITH

                                           4
                                                                                                          E
                                                                                                           dg
                                                                                                                ew
                                                                                                                     oo

                                                                                                                PL
                                                                                                                      d
                                                                                                                          D

                                                                                                            D
                                                                                                                          r

                                                                                                         OO
                                                                                             G    EW
                                                                                          ED
                                                                                     Pl
                                                                                 d
                                                                            oo

1   Existing Tennis Court                              4   Existing Volleyball Court
                                                                      ew
                                                                     E dg

2   Existing Pavilion                                  5   Proposed Pickleball Courts

3   Existing Playground
Scope of Work 2021 Pickleball & Multi-Game Court Project
Possible Court Designs

                                                                      3
S 100 E

                                      4
                                      Cattle Corral
                                          Park

                                  2

                                      3
                        1

                                                                      4

          1   Existing Pump House     3   Proposed Pickleball Court

          2   Existing Pavilion       4   Resurface and Improve
                                          Existing Basketball Court
Scope of Work 2021 Pickleball & Multi-Game Court Project
Possible Court Design
    400 E

                                    2

                     1
                                                    3

                                                        E 80 0 S

                     E 800 S            800 S
        S 400 E

                                                                               4                     5
                                         450 E

                                                                 E00
                                                              S 5
                                          S 450 E

                                                        500
                                                        E

1    Existing Detention Basin

2    Existing Path                                                     4   7' Basketball Standard

3    Proposed Multi-purpose Court                                      5   10' Basketball Standard
Scope of Work 2021 Pickleball & Multi-Game Court Project
Possible Court Design

                                6
                                                  1

                                Meadowridge
                                   Park
                                3            2

                                             4
                                                                                    7                     8

                                    5

1   Existing Playground             4   Existing Pump House

2   Existing Pavilion               5   Existing Path
                                                                            7   7' Basketball Standard
3   Existing Volleyball Court       6   Replace Existing Basketball Court
                                        with Multi-purpose Court            8   10' Basketball Standard
Scope of Work 2021 Pickleball & Multi-Game Court Project