Santa Susana Substation Simi Valley City Council Presentation
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Bird Type 24’ to 28’ 11’ to 15’ Rock Pigeon: Rock Pigeon: Rock Pigeons directly outside substation on Size ‐ beak to tail: 11 to 15 inches Wingspan: 24 to 28 inch distribution pole and wires Weight: 8.4 – 13.4 ounces. 4
Bird Damage Illustration 12’ from bottom of clip to the top of the blade hinge 12’ from bottom of clip to the top of the blade hinge 5
Animal Incidents & Average Customer Base Note: Data as of 8/26/2017 • Momentary outage of 30 seconds per incident. 7
Problem Overview • A majority of the outages which have occurred at Santa Susana Substation have been bird caused. A reason for the bird caused outage could be attributed to walnut trees (bird feed) located next to the substation. The birds pick up the nuts and perch on the energized rack which can cause phase-to-phase or phase-to- ground faults (outage). • Santa Susana Substation was initially identified for permanent critter mitigated in 2018. • Due to the recent uptrend in bird caused outages, SCE has implemented short-term solution and expedited the permanent mitigation plan to 2017. 8
Temporary Critter Mitigation • The critter mitigation is a process where electrical components are insulated with plastic covers to prevent animals (birds or squirrels) from contacting energized parts and causing outages. • SCE has installed temporary critter mitigation in the 16 kV rack where most animal contacts occurred. • Two bird propellers were installed above problem areas. • Completed 8/31/2017 9
Temporary Disconnect Covers 11
Bird Propellers • Currently two bird propellers installed. • Total of eight will be installed in future. 12
Permanent Critter Mitigation • The critter mitigation components to be installed are insulated covers, Whirly-Birds (rotating insulated propellers), sonic bird deterrent (makes a sound of a hawk) and critter fencing. • SCE is committed to a 12/15/2017 completion date. • Engineering is expediting material • Covers expected to arrive the end October • Fence expected to arrive by mid-November 13
Permanent Critter Mitigation • Example of what bird guard covers and critter guard fencing will look like when installation is complete at Santa Susana Substation. Bird Guard Covers • Bird Guard Covers Critter Guard Fencing Critter Guard Fencing 14
Back-up slides
Planned Work on Overhead Network (2017-2019*) • 26 Branch Line Fuses • Increase protection of small branches and help localize faults • 21 Pole Switches • Allow sectionalizing of circuits and re-routing of power • 10 Fault Indicators • Help expedite troubleshooting • 2 Remote Automatic Reclosers • Increase protection of circuitry and help localize faults • ~10,500 feet of new overhead conductor • Replacing aging conductor *More work to be planned for 2019 16
Planned Work on Underground Network (2017-2019*) • 4 Underground Switches • Allow sectionalizing of circuits and re-routing of power • 2 Fault Indicators • Help expedite troubleshooting • 7 Remote Controlled Switches • Help expedite troubleshooting • ~5000 feet of new underground cable • Replacing aging conductor *More work to be planned for 2019 17
Automated Load Restoration • Introducing complex self-restoring algorithm that will analyze current conditions and will attempt to automatically re-route the load to adjacent circuits in the event of fault • Will speed up troubleshooting and restoration of power • 5 out of 11 circuits planned for initial implementation • More circuits are being planned for a later date 18
You can also read