SAFE Notice 2020 - Extranet

Page created by Gabriel Lawrence
 
CONTINUE READING
SAFE Notice 2020 - Extranet
SAFE NOTICE

SAFE Notice 2020
Number: 2-4604 AMENDMENT 2
Goobang Junction
Basic Block Working and Commissioning
To be read in conjunction with Safe Notice 2-4371 Extension 3 and Train Alteration
Advice 1048-2019 and TAA 1100 - 2020
General
Commencing 0600 hours Friday 11th September 2020 until 1800 hours Sunday 20th
September 2020 or until works are completed, as part of the Inland Rail upgrading
and commissioning works, to facilitate rail traffic movements Basic Block Working
will be introduced within Goobang Junction Yard Limits as detailed in this SAFE
Notice and in accordance with Network Rule ANSY 512.
The commissioning works will involve the testing of level crossings, signals, points
and track circuits.
For the duration of the commissioning works Goobang Junction will be locally
controlled by a Competent Rail Safety Worker (Officer In Charge / Signaller) to
facilitate and manage rail traffic movements and Work on Track Authorities and
methods.
Goobang Junction Yard limits on the Narromine Main Line will be extended from
GJ 144 at 449.164km to GJ 154 at 451.927km.
An Infrastructure Booking Advice must be compiled as per the ARTC Network Rule
ANWT 312 and Procedure ANPR 704 book out all affected infrastructure for the
duration of the works.
Safeworking Arrangements
To undertake rail traffic movements all signals within the Goobang Junction Yard
Limits will be booked out of use, and Basic Block Working will be introduced with
the use of STOP Signs/Red Lights and Handsignallers in attendance. Whilst Basic
Block Working is in operation, Rail Traffic Crews are to disregard all signal aspects
within the block working limits.
All work on track authorities will be issued by the Officer in Charge (OIC) Goobang
Junction after being authorised by the NCCS TOCO Network Controller.

                             OPE-FM-001 Version Number: 1.1                 Page 1 of 12
SAFE NOTICE

The OIC Goobang Junction will be responsible for CAN warning rail traffic of the
following conditions;
   •   Blaxland Road Level Crossing 447.136km is booked out with Handsignallers
       in attendance; and
   •   Of a temporary speed restriction of maximum 25km/h for all Rail Traffic
       through Goobang Junction basic block working limits.
It will not be permissible to apply for any work on track methods using eTAP for
Goobang Junction for the duration of the commissioning.
STOP signs/Red lights will be placed on the following signals:

       Signal No.                   Track                      KM
        GJ 144          Narromine Line                        449.164
        GJ 145          Main Line                             449.468
        GJ 147          Loop Line                             449.468
        GJ 150          Main line                             451.792
        GJ 134          Main Line                             447.527
        GJ 136          Branch Line                           447.527
        GJ 138          Siding No 1                           447.585
        GJ 131          Parkes South Line                     447.352
        GJ 133          Main Line                             447.352
        GJ 122          Parkes South West Fork                627.210
        GJ 120          CRN Branch Line                       627.500
        GJ 123          Main Line                             627.280
        GJ 127          Main Line                             446.950
Blaxland Road Level Crossing 447.136km
Blaxland Road level crossing will be booked out use for the duration of the
commissioning works and Handsignallers will be in attendance.
Warning approaching rail traffic
Up direction rail traffic

                             OPE-FM-001 Version Number: 1.1                   Page 2 of 12
SAFE NOTICE

Up direction through rail traffic movements must be CAN warned by the Network
Controller at NCCS prior to departure from Gunningbland, SCT and Parkes North
West Link.
The CAN warning must contain the following information:
   • Basic Block Working is in operation within the Goobang Junction Yard Limits
     and commences at Signal number GJ150,
   • A STOP Sign/Red light is located at GJ150 signal and must only be passed
     on the authority of the OIC at Goobang Junction.

Down direction rail traffic
Down direction through rail traffic movements must be CAN warned by the Network
Controller at NCCS prior to departure from Forbes.
The CAN warning must contain the following information:
    • Basic Block Working is in operation within the Goobang Junction Yard Limits
         and commences at Signal number GJ123
    • A STOP Sign/Red light is located at GJ123 signal and must only be passed
         on the authority of the OIC at Goobang Junction.
Down direction rail traffic exiting John Holland Rail (Parkes)
All rail traffic movements entering the Goobang Junction from Parkes must be CAN
warned by Network Controller at John Holland Rail (CRN) prior to departure from
Parkes.

The CAN warning must contain the following information:
   • Basic Block Working is in operation within the Goobang Junction Yard Limits
     and commences at Signal number GJ127 on the Main line and GJ 120 on
     East Fork
   • A STOP Sign/Red light is located at GJ127 on the Main Line and GJ120
     signal on the East Fork and must only be passed on the authority of the OIC
     at Goobang Junction.
Safeworking Arrangements for through Rail Traffic Movements
The OIC at Goobang Junction must ensure
   •   the route is correctly set and the points have been clipped and SL locked for
       the intended movement prior to authorising rail traffic to pass the STOP
       signs/red lights.
   •   All points and groundframes must only be operated on the authority of the
       OIC at Goobang Junction.
   •   The OIC must ensure that the block is clear prior to authorising a rail traffic
       movement to enter the block.
   •   Rail Traffic Crews are CAN warned that all rail traffic movements within the

                              OPE-FM-001 Version Number: 1.1                 Page 3 of 12
SAFE NOTICE

      Goobang Junction Yard Limits are restricted to a maximum track speed of
      25km/h.
All safety critical safeworking communications MUST be repeated back and
understood before being acted upon.
Equipment to be Commissioned and Booked into Use
Level Crossings
  LX         Road       Line              KM           Traffic   Access   Control
  Number     Name       segment                        Type               Type
  LX 1076    Parkes     Parkes -          449.592 Road           Public   Stop
             Stock      Narromine                                         Signs
             Crossing
  LX 1077    Brolgan    Parkes -          449.774 Road           Public   Half
             Road       Narromine                                         Boom
             East                                                         Flashing
                                                                          Lights
Brolgan Road East Level Crossing
Type “F” flashing lights, half booms and audible warning devices are provided at
Brolgan Road East level crossing at 449.774km.
Down directional standard trackside signage is located at 449.114km.
Up directional standard trackside signage is located at 450.767km.
Emergency operation of the level crossing equipment
Emergency switches are provided to isolate the warning equipment in the event of
a failure. The “Emergency Switch Boxes” are located on the Level crossing
Equipment Hut and are opened by the emergency keys obtained from the ARTC
Provisioning Centre at Parkes. The Level Crossing warning equipment must be
operated in accordance with ARTC Network Rule ANGE 218 “Type F Level
Crossing Management”, ARTC Procedures ANPR 715 “Protecting Type F level
crossing and ANPR 717 Using Emergency Roadside Warning Equipment.
Manual operation of level crossing warning equipment
Manual operation switches are provided on the outside of the Level Crossing
Equipment Hut. The manual operation switch is unlocked by SL key and provided
for use by Competent Rail Safety Worker in accordance with ARTC Network Rule

                             OPE-FM-001 Version Number: 1.1                Page 4 of 12
SAFE NOTICE

ANGE 218 “Type F Level Crossing Management”, ARTC Procedures ANPR 715
“Protecting Type F level crossing.
Testing of level crossing warning equipment
The level crossing will be remotely monitored from the Network Control Centre
South by 4Site (Cerberus) Alarm Monitoring System.
Failure of the Cerberus monitoring equipment
In the event of a failure of the Cerberus monitoring equipment a daily test must be
implemented by the Signal Electrician Parkes in accordance with ARTC Rule 218
“Type F Level Crossing Management”.
Test switch boxes are located on the outside of the Level Crossing Equipment Hut
and are opened by the test key obtained from the ARTC Provisioning Centre
Parkes.

Permanent Speed Signs
    Track Speed KPH                       KM                        Direction
            X25                        449.026                         Up
            75                         449.026                        Down
            115                        449.850                        Down
            100                        450.767                         Up
Signals
 Signal           Location/KM               Aspect
 Number
 GJ 143           Main Line 448.690         Will now display the following aspects.
                                            Red - STOP
                                            Yellow - Caution
                                            Green - Proceed

 GJ 151           Main Line 449.554         Red - STOP
                                            Yellow - Caution

                             OPE-FM-001 Version Number: 1.1                   Page 5 of 12
SAFE NOTICE

 Signal          Location/KM                 Aspect
 Number
                                             Green - Proceed
 GJ 153          Main Line 451.210           Red - STOP
                                             Yellow - Caution
                                             White – Pulsating/Proceed
                                             Shunt aspect
 GJ 156          Main line 441.437           Red - Stop
                 via Narromine
                                             Yellow - Caution
                 449.762 via Broken          Green - Clear proceed
                 Hill
                                             Shunt aspect
 GJ 154          Main Line                   Red - Stop
                 451.927km                   Yellow - Caution
                                             Green - Clear proceed
                                             Shunt aspect
NOTE: GJ 153 signal shunt aspect will be commissioned then booked out of use
on an Infrastructure Booking Advice (IBA) form.
GJ 156 will be commissioned then booked out use on an Infrastructure Booking
Advice (IBA) form
New Points/Point Machines
 Location            Points                    Point Machine         Remarks
                                               Type
 451.350             240 A                     M23A                  Main line
                                                                     connection to
                                                                     Pacific National
                                                                     Private Siding
NOTE:
240A points will be commissioned and then booked out of use on an Infrastructure
Booking Advice (IBA) form.

                              OPE-FM-001 Version Number: 1.1                   Page 6 of 12
SAFE NOTICE

240B catch points will not be installed
Prior to returning the Main line to rail traffic use, a suitable Competent Person
MUST ensure that 240A points at 451.358 km are double clipped, XL locked and
spiked in the NORMAL position.
The points will be provided with electrical detection. Loss of detection will place
protecting signals at STOP.
New Notice Signs
        Equipment                              Km                     Remarks
 End Yard Limit Sign                      451.927km             End Yard Limit sign
                                                                attached to GJ 154
 Yard Limit Sign                          451.927km             Yard Limit sign
                                                                attached to GJ 154
 Goobang Junction Up                      451.927km             Goobang Junction
 location                                                       Up location sign
 End Train Order Working                  451.927km             End Train Order
                                                                Working sign
 Notice Sign Begin Train                  451.927km             Begin Train Order
 Order Working                                                  Working sign
 Notice Sign Goobang                      451.927 km            Goobang North
 North Location Sign                                            Location sign
 Do not proceed past this                 451.210km             Do not proceed past
 point to Goobang North                                         this point to
 unless in Possession of a                                      Goobang North
 Train Order                                                    unless in
                                                                Possession of a
                                                                Train Order sign

Network Information Book
Network Information Book (NIB) Goobang Junction (exc) to Gulgong (inc) via
Dubbo and Merrygoen – Merrygoen to Werris Creek / gap (exc) OGW-30-24 will be
updated and available on the ARTC website
Network Information Book (NIB) Broken Hill to Stockinbingal (Exc) and Bogan Gate
to Bogan Gate North OGW-30-01 will be updated and available on the ARTC

                              OPE-FM-001 Version Number: 1.1                  Page 7 of 12
SAFE NOTICE

website.
The work must be carried out as per the appropriate ARTC Network Rules and
Procedures.
SAFE Notice recipients must ensure this SAFE Notice is circulated to and
understood by all personnel affected by, or needing to know, its content.
SAFE Notices must be issued to all affected Competent Workers.
Competent Workers who receive a SAFE Notice must follow the requirements in
the SAFE Notice.

Date 8 September 2020
Approved by Service Delivery Manager South
ARTC
FOR THE INFORMATION OF ALL COMPETENT WORKERS AND USERS OF THE ARTC
NETWORK

                            OPE-FM-001 Version Number: 1.1                  Page 8 of 12
SAFE NOTICE

OPE-FM-001 Version Number: 1.1        Page 9 of 12
SAFE NOTICE

OPE-FM-001 Version Number: 1.1        Page 10 of 12
SAFE NOTICE

OPE-FM-001 Version Number: 1.1        Page 11 of 12
SAFE NOTICE

OPE-FM-001 Version Number: 1.1        Page 12 of 12