Roads - Road Development Tracker

Page created by Joan Moore
 
CONTINUE READING
Roads

        1
IPP Monthly - Roads

                      2
Roads

Initiatives in Light of Covid-19
MoRTH relaxes rules to allow wider participation of domestic companies in road projects

 • The Ministry of Road Transport and Highways (MoRTH) has revised the eligibility criteria for road projects built on the engineering,
   procurement and construction (EPC) mode to ensure wider participation from domestic companies.

 • It has revised the average annual turnover of the bidder to 15% of the estimated project cost for the past five years. Earlier, the average
   annual turnover was required to be 20% of the estimated project cost.

 • Among other changes, the MoRTH has also relaxed the threshold technical capacity for normal highway projects, which will be 0.75 times the
   estimated project cost in case of projects up to Rs 1 billion, while it will be equal to the estimated project cost in case of projects more than Rs
   1 billion. For specialised projects, the threshold technical capacity has been revised to equal the estimated project cost or Rs 10 billion
   whichever is lower, for projects more than Rs 10 billion.

 • Further, no additional qualification will be required for bridges up to 60 metres long and tunnels up to 200 metres long, being built on the EPC
   mode, besides the bidder having constructed one similar work of 20 per cent of the estimated project cost. The ministry has also brought
   down the size of eligible projects for ascertaining technical experience from 10% to 5% of the project cost.

MoRTH eases norms for HAM projects

 • MoRTH has eased norms for hybrid annuity model (HAM) projects. The government will now make the upfront construction payment
   to a highway project concessionaire under HAM in 10 tranches as against 5, subject to the overall ceiling of 40% of the project cost.

 • Increasing the frequency of the installments will help concessionaires better manage their working capital requirements. Besides, the
   release of upfront payments during the construction period will be linked to the physical progress of the project.

 • Besides, the annuity payment will be made on the reducing balance of completion cost at an interest rate equal to average of one-year
   marginal cost of fund-based lending rate (MCLR) of top five scheduled commercial banks plus 1.25%.

                                                                                                                                                          3
Roads

Initiatives in Light of Covid-19
NHAI set to make FY 2021 the best year of highway construction

 • Reportedly, NHAI plans to award contracts worth Rs 2 trillion during the current fiscal year.
 • As per NHAI, there is no dearth of money and the government has encouraged the authority to build roads with full vigour and make it the
   best year of highway construction. Besides, NHAI will also be rating the best roads to enhance quality and speed of execution. NHAI has also
   urged the authorities to advocate innovative land pooling methods to save land acquisition costs across the country by upto Rs 2 trillion.

                                                          Other Policy Developments

MoRTH issues notification for promotion of toll payment through FASTag

 • MoRTH has issued a notification making FASTag mandatory to be available by January 1, 2021 in old vehicles as well, i.e., M and N category of
   motor vehicles (four wheelers) sold before December 1, 2017, through amendments in Central Motor Vehicles Rules (CMVR), 1989.
 • It has also been mandated that a valid FASTag is mandatory while getting a new 3rd Party Insurance through an amendment in FORM 51
   (certificate of Insurance), wherein the details of FASTag ID shall be captured. This shall be applicable with effect from April 1, 2021.

Andhra Pradesh government considers levying toll tax on state roads

 • Reportedly, Andhra Pradesh government is considering a plan to levy toll tax on state highways with high traffic density, in a bid to enhance
   the state government’s revenue.
 • The toll fee collected from the state highways will go to Andhra Pradesh Road Development Corporation (APRDC) to be used for maintenance
   of highways. A decision to this effect is expected to be taken soon by the State Cabinet.
 • In the first phase, toll will be collected at about 35 state highways, including the KadapaPulivendula, Eluru-Jangareddygudem and
   Bhimavaram-Gudivada highways. If the pilot succeeds, toll fee collection would be done in the remaining 24 routes as well.

                                                                                                                                                   4
Roads

Initiatives in Light of Covid-19
                                                             Key Announcements

National highway project awards double despite COVID-19 pandemic

 • As per media reports, the pace of award of national highway projects has almost doubled during April-October 2020, compared to the past
   year, despite the ongoing COVID-19 pandemic. Highway project awards for April-October 2020 have reached 5,679 km, compared to 2,982
   km in the same period of last year.
 • Besides, construction of highways has also improved from 210 km in April 2020 to 4,628 km by October 2020. This translates into average
   construction of nearly 22 km/day during April-October 2020.

NHAI toll collections cross pre-COVID levels in November 2020

 • Toll collection on national highways across the country surpassed pre-COVID levels in November 2020, signalling sharp signs of recovery in
   road traffic.

 • The toll collections in the first week of November have reached 114 per cent of pre-COVID levels in the month under review. On March 25,
   2020, the central government had announced temporary suspension of toll collection in the wake of COVID-19 pandemic.

 • NHAI as well as highway developers resumed collection at toll plazas in line with the Ministry of Home Affairs directives on April 20, 2020.
   Traffic across national highways had dipped to as low as 25-30 per cent of pre-COVID levels during the first phase of the nationwide lockdown
   in March 2020.

FASTag users cross 20 million count
 • NHAI has announced that the number of FASTag users in the country has crossed the 20 million mark, registering a growth of 400 per cent in
   a year.
 • This has increased the total toll collection to Rs 920 million per day, a substantial increase from Rs 700 million per day, a year back. FASTag
   contributes to nearly 75 per cent of the total toll collection as of now.

                                                                                                                                                     5
Roads

Initiatives in Light of Covid-19
                                                             Key Announcements

NHAI to introduce prepaid touch-and-go cards to cut long queues

 • With the aim to minimise cash transaction at toll plazas, NHAI will soon roll out a Delhi Metro type prepaid touch-and-go card for commuters.
   Each card would cost around Rs 50 and can be used only on ‘hybrid’ lanes where payments are made by cash or through electronic means.
 • NHAI’s toll management wing, Indian Highways Management Company Limited (IHMCL), has invited bids for rollout of this system. According
   to the tender document, the successful bidder will set up at least two dedicated point-ofsales (PoS) manpower in three shifts for card
   issuance, recharge, top-up facility and cash management at each national highway toll plaza for the initial three months.
 • The pre-paid card system will be integrated with the toll management systems (TMS) to enable the toll operator to select vehicle class so that
   the applicable toll fee can be deducted immediately from the prepaid card on tapping the PoS device.

                                                                                                                                                    6
Roads

Key Recent Developments
                                                Impact of COVID-19 on Competitive Intensity

 •   According to ICRA Ratings, expects the central government spend on infrastructure to be maintained given the positive multiplier affect it will
     have on overall economy amid the COVID-19 pandemic. The state governments in particular are staring at a huge revenue deficit in current
     financial year; and therefore, the headroom available to them for incurring capital expenditure has reduced substantially.
 •   The private sector capex and the interest in public private partnership (PPP) based infrastructure projects is also expected to be limited in
     near term, due to increased risk averseness and limited capital availability.
 •   As a result, NHAI/MoRTH EPC projects are expected to witness heightened competition.
 •   As per a study conducted by ICRA covering 160 EPC projects awarded by NHAI during F2017-20 spread across 22 states spanning 6,260 km,
     the average number of bidders per project for the EPC segment ranged between 4 to 10. These 160 projects were awarded to as high as 69
     EPC players.
 •   Of total 160 projects, 69% were awarded at a discount to NHAI’s base price (median discount of 11.2 per cent), 3% were awarded at par to
     base price and remaining 28% were awarded at a premium (median premium of 7.7%).
 •   The top 10 players bagged around 62 projects totaling 2,713 km which is 43% of total awards in length.

                                                               Grants/Allocations

 • The Uttar Pradesh Expressway Industrial Development Authority (UPEIDA) Board has approved a proposal of Rs 221.45 billion for civil works
   for the construction of the Ganga expressway project.
 • In order to generate finances, the Board has proposed that avenues of the public-private-partnership (PPP) model should be explored. The
   Board has suggested that investors should be identified as per the records of NHAI and then expression of interest (EOI) should be signed.

 • The Himachal Pradesh government has approved funds worth Rs 1.96 billion for the Pathankot-Mandi road project.
 • The project involves four-laning of 219 km long road stretch connecting Pathankot, Suini, Parour, Chauntada, Chauntra, Padhar and Mandi in
   Himachal Pradesh.

 • The Finance Committee of the Government of Uttar Pradesh has approved implementation of the Ghaziabad-Haridwar two-lane canal road
   project.
 • The project involves construction of 111 km two-lane canal road connecting Ghaziabad and Haridwar and is proposed on the right-side bank
   of the upper Ganga canal originating from Haridwar in Uttar Pradesh at an estimated cost of Rs 6.28 billion.

                                                                                                                                                       7
Roads

Key Recent Developments
                                                                  Loans/Bonds

 • The Asian Development Bank (ADB) and the central government have signed a $177 million loan to upgrade 450 km of state highways and
   major district roads in Maharashtra.
 • The project will improve connectivity between rural areas and urban centres in the state. Another feature of the project is to update the road
   maintenance system by encouraging five-year performance-based maintenance obligations to contractors to sustain asset quality and service
   levels.
 • The project will upgrade two major district roads and 11 state highways, with combined length of 450 km, to two-lane standard across seven
   districts of Maharashtra, and improve connectivity to national highways, interstate roads, seaports, airports, rail hubs, district headquarters,
   industrial areas, enterprise clusters and agricultural areas.

 • The World Bank has signed a $120 million project to improve and modernise the transport sector in Meghalaya. The $120 million loan from
   the International Bank for Reconstruction and Development (IBRD) has a maturity of 14 years, including a grace period of six years.
 • The Meghalaya Integrated Transport Project (MITP) will improve about 300 km of strategic road segments and stand-alone bridges by using
   innovative, climate-resilient, and nature-based solutions.
 • The segments will serve major agriculture areas, important tourist destinations, small-scale industries, major towns and underserved
   populations by linking them to markets, health and education centres, besides national and international corridors.

 • A consortium of public sector banks has sanctioned a fresh loan of Rs 2.50 billion for the Gorakhpur Link expressway project. The Bank of
   Maharashtra has also joined the consortium and Punjab National bank and UCO Bank have already provided credit of Rs 7.5 billion and Rs 2.5
   billion, respectively, for the project.
 • So far, three public sector banks have provided Rs 12.5 billion for the project. Meanwhile, the Uttar Pradesh cabinet has already granted
   approval for setting up the consortium of banks for funding the expressway project.

                                                                                                                                                      8
Roads

Key Recent Developments
                                                                    TOT/InvITs

 • NHAI has received upfront consideration of Rs 50.11 billion from Cube Highways and Infrastructure, under the third bundle of the tolloperate-
   transfer (TOT) model. The Singapore-based firm had delayed the payment to NHAI amid the uncertainties posed by COVID-19 outbreak.
 • The TOT Bundle III, with a cumulative length of 566 km, consists of nine toll plazas in the state of Uttar Pradesh, Jharkhand, Bihar and Tamil
   Nadu.
 • Cube Highways had deferred paying up for the bundle as traffic density had started dwindling since March this year, when India went under a
   nationwide lockdown to curb the spread of COVID-19. However, the company has not been penalised for delay in payment as the
   government continues to implement relaxations announced in light of the pandemic.

 • Reportedly, NHAI is set to come up with its Rs 50 billion Infrastructure Investment Trust (InvIT) by early-2021.
 • NHAI’s InvIT, the first InvIT to be sponsored by any government entity in the country, will initially consist of the highway road assets under the
   TOT Bundle II.
 • Auction for the second TOT bundle, with 586 km of national highways in Rajasthan, Gujarat, West Bengal, and Bihar at a base price of Rs
   53.62 billion, got cancelled last year after the bids offered were much below NHAI expectation.

 • Reportedly, IL&FS Limited has finalised the InvIT structure for its road assets in order to resolve its debt of about Rs 150 billion.
 • IL&FS has set up Roadstar Infra Private Limited (RIIPL), as a new subsidiary of IL&FS Transportation Networks India Limited (ITNL) to act as a
   sponsor to the proposed InvIT. Besides, North Karnataka Expressway Limited (NKEL) has been appointed as the investment manager to the
   proposed InvIT.
 • As per the reports, ITNL has infused fresh capital of Rs 750 million in the sponsor entity post receipt of requisite approvals, in order to meet
   the SEBI’s InvIT norm of Rs 1 billion net worth. In addition, NKEL will be transferred by ITNL to Roadstar Infra Private Limited.
 • IL&FS has received in-principle approval from SEBI for registering the InvIT and is likely to approach SEBI shortly for seeking final registration
   of the trust.

 • IRB Infrastructure Trust, the private InvlT, has successfully closed the second tranche of fund raising by way of Rights Issue of Units amounting
   to Rs 5.10 billion.
 • IRB Infrastructure Developers Limited, being the sponsor and 51 per cent stakeholder, contributed Rs 2.6 billion and GIC affiliates, holding the
   balance 49 per cent stake, have contributed Rs 2.5 billion.
 • This is part of the total commitment of Rs 44 billion by GIC affiliates towards 49 per cent stake in the private InvIT housing nine BOT assets,
   out of which IRB Infrastructure Trust had already received Rs 37.53 billion from GIC affiliates in February 2020.

                                                                                                                                                        9
Roads

Key Recent Developments
                                                              Financial Closures

 • Ashoka Kandi Ramsanpalle Road Private Limited, a wholly owned subsidiary of Ashoka Buildcon Limited, has achieved financial closure letter
   dated October 23, 2020 from NHAI.
 • The company received financial closure on October 5, 2020, for the project entailing four-laning of 39.98 km section of NH-161 from Kandi
   (Design km 0) (km 498.25 of NH-65) to Ramsanpalle (Design km 39.98/existing km 44.76) in Telangana.
 • The HAM project is being implemented under Bharatmala Pariyojna at a bid project cost of Rs 10 billion.

                                                         Asset Sales/Stake Dilution

 • Reportedly, the Life Insurance Corporation of India (LIC) has raised its stake in IRB Infrastructure Developers Limited to 5.27 per cent in
   quarter ended September 2020.
 • LIC has been increasing its holding in the company for a long time. In the September quarter, LIC's stake in the company rose to 5.27 per cent,
   from 3.81 per cent in the quarter ended June 2020.

 • Sadbhav Infrastructure Project Limited has received approval from Ahmedabad Urban Development Authority (AUDA) for 100 per cent stake
   sale in Ahmedabad Ring Road Infrastructure Limited (ARRIL), a wholly owned subsidiary of the company, to Indinfravit Trust and refinancing
   of existing debts of ARRIL subject to fulfillment of certain conditions.
 • The company had signed definitive agreements with lndinfravit on July 1, 2019 to sell 100 per cent stake in nine operational projects for an
   enterprise value of Rs 66.1 billion (including equity value of Rs 25.5 billion).

 • Reportedly, Welspun Enterprises Limited is in talks with a Canadian pension fund for investment in the company’s road project assets.
 • The company has nine road projects, with a project cost of over Rs 120 billion. Of the nine road projects, seven are on the hybrid annuity
   model (HAM).

                                                                                                                                                     10
Roads

Key Recent Developments

                                                                   Others

 • NHAI has accepted arbitration award amounting to Rs 439.51 million in favour of Dhule Palesner Tollway Limited (DPTL), a subsidiary of
   Sadbhav Infrastructure Project Limited, without any pendente-lite interest and interest on delayed payment. Sadbhav Infrastructure Project
   Limited had earlier announced the winning of an arbitration award against NHAI through DPTL.
 • DPTL had received appointed date on December 21, 2009 to augment the 89 km existing road from km 168.5 to km 265 on the Madhya
   Pradesh/Maharashtra Border - Dhule section of NH-3 in Maharashtra by four-laning on DBFOT basis.
 • The original concession period is 18 years from the appointed date. DPTL achieved first commercial operations date on January 23, 2012.

 • IRB InvIT Fund has announced that IRB Surat Dahisar Tollway Limited has concluded its conciliation process with NHAI and accordingly, the
   concession period for its project has been extended by 460 days.
 • As a result, the concession period for the project will expire on May 25, 2022, as against the original transfer date of February 19, 2021.

                                                                                                                                                 11
Roads

Key Upcoming Projects
                                                                 Key Upcoming Projects
                          Cost          Length                          Current
 Project name                                          State                                                Detailed status
                       (Rs billion)      (km)                            Status
                                                                                     The first phase between Nagpur-Shirdi will be commissioned
Mumbai-Nagpur                                                                        by May 1, 2021. The second phase of 103 km between Shirdi
                                                                      Under
Communication               553.35      701.00   Maharashtra                         and Igatpuri will be opened for traffic in December 2021 while
                                                                      Construction
expressway                                                                           the remaining 78 km between Igatpuri and Wadpe near
                                                                                     Mumbai will be commissioned on May 1, 2022.
                                                                                     As of September 2020, 26 packages have been awarded under
                                                 Delhi, Rajasthan,
                                                                                     the project. Besides, construction work has already
Delhi-Vadodara                                   Haryana, Madhya      Under
                            424.80      845.00                                       commenced on 13 packages. Recently, Dilip Buildcon Limited,
expressway                                       Pradesh and          Construction
                                                                                     in JV with Altis Holding Corporation, has been declared the
                                                 Gujarat
                                                                                     lowest (L-1) bidder for Package 15 of the project.
                                                                                     As of September 2020, seven packages have been awarded
Vadodara-                                                                            under the project. Besides, construction work has already
                                                 Gujarat and          Under
Mumbai                      400.33      447.00                                       commenced on five packages. Most recently, IRB
                                                 Maharashtra          Construction
expressway                                                                           Infrastructure Developers Limited has received letter of award
                                                                                     (LoA) for construction of 27.5 km Gandeva-Ena section.
                                                                                     The Cabinet has approved a district-wise alignment of the
                                                                                     expressway. The government has also decided to monetise the
Ganga                                                                                Agra-Lucknow expressway for funding the Ganga expressway
                            299.24      628.00   Uttar Pradesh        Approved
expressway                                                                           project and has decided to set up a high-power committee to
                                                                                     take procedural and operational decisions to monetise the
                                                                                     Agra-Lucknow expressway.

Delhi - Amritsar                                 Delhi, Punjab and
                                                                      Under          Recently, NHAI invited bids for various packages under the
- Katra                     309.36      600.00   Jammu &
                                                                      Bidding        project.
expressway                                       Kashmir

Source: India Infrastructure Research

                                                                                                                                                      12
Roads

Key Upcoming Projects
                                                                 Key Upcoming Projects
                       Cost             Capacity                   Current
Project name                                          State                                                 Detailed status
                    (Rs billion)          (km)                      Status
                                                                                In September 2020, the Andhra Pradesh government gave
                                                                                administrative sanction for Rs 1 billion to acquire land for the project.
Amaravati-                                                                      The alignment of the proposed access-controlled expressway has been
                                          384 km    Andhra
Anantapur                276.25                                  Approved       approved by the Land Acquisition Committee and the total cost of the
                                        (approx.)   Pradesh
expressway                                                                      land acquisition has been estimated to be Rs 22.31 billion. The state
                                                                                government will provide the land owned by it free of cost and bear
                                                                                50% of the cost to be incurred for acquiring additional land.

Purvanchal                                          Uttar        Under          UPEIDA is aiming to throw open the Purvanchal expressway to the
                         224.95           340.82
expressway                                          Pradesh      Construction   public from January 26, 2021, ahead of the deadline of April 2021.

                                                                                As of September 2020, about 16% construction work has been
Bundelkhand                                         Uttar        Under          completed on the project. In August 2020, UPEIDA signed a loan
                         148.49           296.07
expressway                                          Pradesh      Construction   agreement of Rs 59 billion with a consortium of six banks for timely
                                                                                project execution.
Chennai-                                            Karnataka,
                                                                 Under
Bengaluru                207.99           272.00    Tamil                       Recently, bids have been invited for various under the project.
                                                                 Bidding
expressway                                          Nadu
Surat-
                                                    Gujarat,
Ahmednagar-                                                                     The project is still in the announced stage. Construction work on the
                         205.53           300.00    Maharasht    Announced
Solapur                                                                         Surat-Ahmednagar highway is expected to commence by April 2021.
                                                    ra
highway

Mumbai
                                                    Maharasht    Under          The construction work on the 21.8 km Mumbai Trans Harbour Link
Trans                    178.43            21.80
                                                    ra           Construction   (MTHL) project is expected to be completed by September 2022.
Harbour Link

Source: India Infrastructure Research

                                                                                                                                                            13
Roads

Key Upcoming Projects
                                                                   Key Upcoming Projects
                       Cost             Capacity                      Current
Project name                                           State                                                 Detailed status
                    (Rs billion)          (km)                         Status

Amritsar-                                          Punjab,
                                                                                   It is one of the greenfield expressways being constructed under the
Bhatinda-                                          Haryana,         Under
                         176.77           762.00                                   Bharatmala Pariyojana. Currently, the project is under construction
Jamnagar                                           Rajasthan,       Construction
                                                                                   and is expected to be completed by FY23.
highway                                            Gujarat

Raipur-                                            Chhattisgarh,
                                                                                   It is one of the greenfield expressways being constructed under the
Vishakhapatn                                       Odisha,
                         163.43           464.00                    Approved       Bharatmala Pariyojana. As of June 2020, land acquisition is ongoing
am                                                 Andhra
                                                                                   on the project. The project is expected to be completed by FY24.
expressway                                         Pradesh
Solapur-                                           Maharashtra,
                                                                                   Currently, the project is in the announced stage and is expected to
Kurnool                  104.30           279.00   Andhra           Announced
                                                                                   be completed by FY2025.
highway                                            Pradesh
                                                                                   Currently, the project is in the announced stage and bids are likely
Bengaluru
                                                                                   to be invited soon. On June 29, 2020, the Expert Appraisal
Satellite
                         144.04           281.00   Karnataka        Announced      Committee (EAC) of the Ministry of Environment, Forest and Climate
Town Ring
                                                                                   Change (MoEFCC) recommended grant of environment clearance
Road
                                                                                   (EC) for Phase III of the project.

Mumbai                                                                             The construction work on Phase I of the Mumbai Coastal Road
                                                                    Under
Coastal Road             140.00            29.20   Maharashtra                     project is expected to be completed by July 2023.
                                                                    Construction
Project                                                                            About 23% construction work has been completed on the project.

Source: India Infrastructure Research

                                                                                                                                                          14
Roads

Key Upcoming Projects
                                                                  Key Upcoming Projects
                         Cost           Capacity                      Current
 Project name                                          State                                                 Detailed status
                      (Rs billion)        (km)                         Status

                                                                                   • Bids have been invited for the Delhi and Uttar Pradesh portions
Delhi-
                                                   Delhi, Uttar                      of the Delhi-Saharanpur highway in two packages. Currently, the
Saharanpur-                                                         Under
                          123.09          169.00   Pradesh,                          same are under evaluation.
Dehradun                                                            bidding
                                                   Uttarakhand                     • Besides, bids have also been invited for various packages under
expressway
                                                                                     the Ganeshpur-Dehradun stretch.

Ambala-
                                                   Haryana,         Under          Currently, the project is under construction and is expected to be
Kotputli                  113.75          227.00
                                                   Rajasthan        Construction   completed by FY23.
expressway

Versova-                                                                           The project has been impacted by shortage of manpower amid the
                                                                    Under
Bandra Sea                113.33           17.17   Maharashtra                     COVID-19 pandemic. Meanwhile, the construction work on the
                                                                    Construction
Link                                                                               project is expected to be completed by August 2025.

                                                                                   On March 5, 2020, the Government of Karnataka allocated funds
                                                                                   worth Rs 145 billion under the state budget 2020-21 for
Bengaluru
                                                                                   implementation of the project.
Peripheral Ring
                          200.00           68.50   Karnataka        Announced      The project will be jointly funded by a loan from the Japan
Road (PRR)
                                                                                   International Cooperation Agency (JICA) and the state government.
(Phase I)
                                                                                   Currently, the project is facing issues on account of opposition to
                                                                                   environmental damage. DPR for the project is yet to be finalised.

Source: India Infrastructure Research

                                                                                                                                                         15
Roads

Key Upcoming Tenders
                                                       Key Upcoming Tenders
Implementing                                                                                        Cost (Rs   Bid Issue       Bid due
                                              Scope of the project
   agency                                                                                           billion)     Date           date
               Appointment of EPC contractor for construction of four-lane greenfield Delhi-Katra
               expressway from junction with Amritsar-Tanda road (NH-503A) near Sri Hargobindpur               November      January 28,
NHAI                                                                                                   11.35
               to Junction with Pathankot-Gurdaspur road (NH-54) near Gurdaspur (km 362.42-km                  27, 2020      2021
               397.7) under Bharatmala Pariyojana in Punjab.
               Appointment of EPC contractor for construction of four-lane greenfield Delhi-Katra
               expressway from junction with Jalandhar-Kapurthala road (NH-703A) near Khojewal                 November      January 28,
NHAI                                                                                                   14.37
               village-junction with Amritsar-Tanda road (NH-503A) near Sri Hargobindpur (km                   27, 2020      2021
               319.4-362.42) under Bharatmala Pariyojana in Punjab.
               Appointment of contractor for development of six-lane Chittoor-Thatchur highway
                                                                                                               November      January 12,
NHAI           from km 0 to km 43.8 on HAM mode under Bharatmala Pariyojna in Andhra Pradesh           11.52
                                                                                                               25, 2020      2021
               and Tamil Nadu (Package-I).
               Appointment of EPC contractor for construction of four-lane greenfield Delhi-
               Amritsar-Katra expressway from Junction with Jalandhar-Moga road (NH-703) near
               Kang Sahibu village to Junction with Jalandhar-Kapurthala road (NH-703A) near
                                                                                                               November      January 21,
NHAI           Khojewal village (km 303.9 to km 319.4 of main expressway) and Junction with            12.31
                                                                                                               18, 2020      2021
               Jalandhar-Moga road (NH-703) near Kang Sahibu village to Junction with Kapurthala-
               Sultanpur Lodhi road (NH-703A) near Isharwal village (km 0 to km 24 of Amritsar
               connectivity) in Punjab under Bharatmala Pariyojana.
               Appointment of EPC contractor for construction of four-lane greenfield Delhi-
               Amritsar-Katra expressway from Junction with Ludhiana-Moga road (NH-5) near                     November      January 21,
NHAI                                                                                                   14.04
               Mullanpur Dakha to Junction with Jalandhar-Moga road (NH-703) near Kang Sahibu                  17, 2020      2021
               village (km 260.86 to km 303.9) under Bharatmala Pariyojana in Punjab.
               Appointment of EPC contractor for construction of four-lane greenfield Delhi-
               Amritsar-Katra expressway from Junction with Ludhiana-Malerkotla road (SH-11) near              November      January 21,
NHAI                                                                                                   11.29
               Bhogiwal village to Junction with Ludhiana-Moga road (NH-5) near Mullanpur Dakha                17, 2020      2021
               (km 225.77 to km 260.86) in Punjab under Bharatmala Pariyojana.

                                                                                                                                           16
Roads

Key Upcoming Tenders
                                                         Key Upcoming Tenders
Implementing                                                                                            Cost (Rs    Bid Issue       Bid due
                                                Scope of the project
   agency                                                                                               billion)      Date           date
               Appointment of contractor for construction of four-lane expressway from km 26.4 to
                                                                                                                   November       December
NHAI           km 53.5 of Malur to Bangarpet section of Bangalore-Chennai expressway on hybrid            10.36
                                                                                                                   6, 2020        21, 2020
               annuity model under Bharatmala Pariyojna in Karnataka (Phase-I Package-II).
               Appointment of contractor for six-laning of Ramanattukara Junction - start of
               Valanchery bypass section of NH-66 from design chainage 258.82 (existing km 27.84 of                October        December
NHAI                                                                                                      19.45
               Kozhikode bypass) to design chainage 298.5 (existing km 304.25) in Kerala on hybrid                 15, 2020       17, 2020
               annuity model under Bharatmala Pariyojana.
               Appointment of contractor for six-laning of Valanchery bypass - Kappirikkad section of
                                                                                                                   October        December
NHAI           NH- 66 (old NH-17) from design chainage km 298.5 (existing km 304.25) to design            17.06
                                                                                                                   14, 2020       17, 2020
               chainage 335.85 (existing km 349.26) in Kerala on hybrid annuity model.
               Appointment of contractor for construction of four-lane Delhi-Amritsar-Katra
               greenfield expressway from Junction with Ambala-Kaithal-Hissar road (NH-152) to                     September      January 7,
NHAI                                                                                                      11.00
               Junction with Patiala-Samana Patran road (SH-10) (km 120.25 to km 157.92) on hybrid                 29, 2020       2021
               annuity model in Haryana.
               Appointment of contractor for construction of four-lane Delhi-Amritsar-Katra
               greenfield expressway from Jussur Kheri on KMP Expressway to Junction with Rohtak-                  September      December
NHAI                                                                                                      10.53
               Panipat road (NH-709) near Rukhi Paani village (km 0 to km 34) on hybrid annuity                    29, 2020       21, 2020
               model in Haryana. The project is being implemented under Bharatmala Pariyojana.
               Appointment of EPC contractor for construction of eight-lane access-controlled
               expressway starting from MP-Gujarat Border near Chhayan village and ending after                    June           January 6,
NHAI                                                                                                      14.18
               bridge over hadaf river near Hathiyavan village (chainage 696.92 to 729.76) section of              23,2020        2021
               Delhi-Vadodara greenfield alignment (NH-148N).
               Appointment of EPC contractor for construction of six-lane NH-344M (Package II) from                December       December
NHAI                                                                                                      11.21
               Karala-Kanjhawala road (km 15) to Nangloi Najafgarh road (km 28.45) in Delhi.                       26, 2019       15, 2020
               Appointment of EPC contractor for construction of six-lane NH-344M (Package I) from                 December       December
NHAI                                                                                                      15.52
               NH-1 (km 0.7) to Karala-Kanjhawala Road (km 15) in Delhi.                                           26, 2019       15, 2020

                                                                                                                                               17
Roads

Key Upcoming Tenders
                                                        Key Upcoming Tenders
Implementing                                                                                         Cost (Rs   Bid Issue       Bid due
                                               Scope of the project
   agency                                                                                            billion)     Date           date
               Appointment of contractor for four-laning of Puducherry-Poondiyankuppam section of
               NH-45A from km 29 to km 67 (Design Chainage) on hybrid annuity model in Tamil                    December      December
NHAI                                                                                                    10.45
               Nadu and Puducherry. The project is being implemented under Bharatmala                           26, 2019      16, 2020
               Pariyojana.
               Appointment of contractor for four-laning of Poondiankuppam to Sattanathapuram
               section of NH-45A from km 67 to km 123.8 (Design Chainage) on hybrid annuity model               December      December
NHAI                                                                                                    17.77
               in Tamil Nadu and Puducherry. The project is being implemented under Bharatmala                  26, 2019      16, 2020
               Pariyojana.
               Appointment of EPC contractor for construction of about 2.64 km uni-directional
               tunnel and its approach road from km 6.41 to km 12.85 including one viaduct, three               May 28,       January 11,
NHIDCL                                                                                                  12.41
               viaducts cum bridge on Sudhmahadev-Daranga section of NH-244 in Jammu and                        2020          2021
               Kashmir (Package II).
               Appointment of contractor for construction of about 5.45 km uni-directional tunnel
               and its approach road from km 0 to km 6.41 including one viaduct cum bridge and one              May 28,       January 11,
NHIDCL                                                                                                  18.96
               major junction at start of the project on Sudhmahadev-Daranga section of NH-244 in               2020          2021
               Jammu and Kashmir (Package I).

                                                                                                                                            18
Roads

Awarded/Completed Projects
                                                          Awarded/Completed Projects

                                                 Length       Cost (Rs
           Project                      Status                             Contractors                            Details
                                                  (km)        billion)

10 Highway projects in                                                                       MoRTH has inaugurated 10 highway projects in
                                    Completed    532.69      80.07       NA
Andhra Pradesh                                                                               the state.

Thiruvananthapuram                                                       KNR
                                                                                             MoRTH has recently inaugurated the road
Bypass from Kazhakuttom             Completed    26.50       11.21       Constructions
                                                                                             project in Kerala.
to Mukkola on NH-66                                                      Limited
                                                                                             Ashoka Ranastalam Anadapuram Road
Ranastalam-                                                                                  Limitedhas received provisional completion
                                                                         Ashoka Buildcon
Anandapuram highway                 Completed    47.00       NA                              certificate (PCC) for completion of 45.55 km of
                                                                         Limited
project                                                                                      the 47 km Ranastalam-Anandapuram highway
                                                                                             project.
                                                                         Uttar Pradesh
Guru Govind Singh Marg                                                                       The central government has recently
                                    Completed    1.65        1.24        State Bridge
flyover                                                                                      inaugurated the project in Uttar Pradesh.
                                                                         Corporation
                                                                         Dilip Buildcon
Package-15 of the Delhi-                                                 Limited and Altis   The JV has been declared as the lowest bidder
                                    Awarded      8.30        10.00
Vadodara expressway                                                      Holding             for the project.
                                                                         Corporation JV
Gagalheri-Saharanpur-                                                                        Welspun Enterprises Limited has received
                                                                         Welspun
Yamunanagar                                                                                  provisional commercial operation date (PCOD)
                                    Completed    NA          13.54       Enterprises
(UP/Haryana Border)                                                                          with effect from October 31, 2020, for the
                                                                         Limited
section of NH-73                                                                             project.

Source: India Infrastructure Research

                                                                                                                                               19
Roads

Awarded/Completed Projects
                                                           Awarded/Completed Projects
                                                  Length       Cost (Rs
           Project                      Status                              Contractors                           Details
                                                   (km)        billion)
Bhandara-Khat-Ghotitok                                                    H.G. Infra         H.G. Infra Engineering Limited has received
Junction section of NH-             Completed    38.57        NA          Engineering        provisional completion certificate PCC for the
547E                                                                      Limited            project.
                                                                          H.G. Infra         H.G. Infra Engineering Limited has received
Nagpur-Katol-Warud
                                    Completed    40.47        NA          Engineering        provisional completion certificate PCC for the
national highway
                                                                          Limited            project.
U-turn Flyover near                              455-                                        The project has been recently inaugurated in
                                    Completed                 0.52        NA
Shankar Chowk on NH-48                           metre                                       Gurugram, Haryana.
                                                                          JV of Dilip        The JV has received appointed date from NHAI
New Link NH-133B and
                                    Awarded      21.69        19.00       Buildcon Limited   with effect from November 1, 2020 for the
Manihari bypass
                                                                          and HCC Limited    project.
Repallewada to                                                                               Repallewada Highways Private Limited has
                                                                          Dilip Buildcon
Telangana/Maharashtra               Awarded      52.64        11.41                          executed concession agreement with NHAI for
                                                                          Limited
border section of NH-363                                                                     the project.
Dodaballapur Bypass-                                                                         Dodaballapur Hoskote Highways Private Limited
                                                                          Dilip Buildcon
Hoskote section of NH-              Awarded      38.00        12.78                          has executed the concession agreement with
                                                                          Limited
648                                                                                          NHAI for the project.
                                                                                             Ashoka Kandi Ramsanpalle Road Private Limited
Kandi-Ramsanpalle                                                         Ashoka Buildcon
                                    Awarded      39.98        10.00                          has received October 5, 2020, as the appointed
section of NH-161                                                         Limited
                                                                                             date for the project.
                                                                          J. Kumar           J.Kumar Infraprojects Limited has received the
Sewri-Worli elevated road
                                    Awarded      4.50         10.52       Infraprojects      letter of acceptance (LoA) from MMRDA for the
project
                                                                          Limited            project.
Source: India Infrastructure Research

                                                                                                                                              20
Roads

Awarded/Completed Projects
                                                            Awarded/Completed Projects
                                                    Length      Cost (Rs
             Project                     Status                                 Contractors                         Details
                                                     (km)       billion)
                                                                                                 H.G. Infra Engineering Limited has received
Package 8 of Delhi-Vadodara                                                H.G. Infra
                                        Awarded     33.05      9.03                              the appointed date as November 6, 2020
expressway project                                                         Engineering Limited
                                                                                                 from NHAI for implementation of the project.
Amravati-Nandgaon-Morshi-
Warud-Pandhurna national                                                   H.G. Infra            H.G. Infra Engineering Limited has received
                                        Completed   43.00      2.43
highway from existing km                                                   Engineering Limited   PCC for the project.
95.67 to km 52.44
Amravati-Nandgaon-Morshi-
Warud-Pandhurna national                                                   H.G. Infra            H.G. Infra Engineering Limited has received
                                        Completed   52.39      2.95
highway from existing km                                                   Engineering Limited   PCC for the project.
52.44 to km 0
Shastri Park, Seelampur                                                                          The Shastri Park, Seelampur flyover projects
                                        Completed   NA         NA          NA
flyover projects                                                                                 have been inaugurated in Delhi.
                                                                           Sunway
Meensurutti to
                                                                           Construction Group    NHAI has issued LoA to the consortium for
Chidambaram section of                  Awarded     31.50      NA
                                                                           Berhad and RNS        the project.
NH-227
                                                                           Infrastructure
                                                                                                 Narenpur Purnia Highways Private Limited
Narenpur-Purnea highway                                                    Dilip Buildcon
                                        Awarded     49.00      19.05                             has executed concession agreement with
project                                                                    Limited
                                                                                                 NHAI on October 24, 2020.
                                                                           IRB Infrastructure    AE Tollway has been issued a completion
Agra-Etawah highway                     Completed   NA         NA
                                                                           Developers Limited    certificate (CE) by the Competent Authority.

Source: India Infrastructure Research

                                                                                                                                                21
Roads

Awarded/Completed Projects
                                                            Awarded/Completed Projects

                                                    Length      Cost (Rs
             Project                     Status                                 Contractors                          Details
                                                     (km)       billion)
Dhangaon-Boregaon section                                                  KCC Buildcon          The project has been awarded to KCC
                                        Awarded     58.00      NA
of NH-347BG                                                                Private Limited       Buildcon.
                                                                                                 After nearly 1.5 years after inauguration, the
                                                                                                 transport corridor of the 47 km Ring Road
Ring Road transport corridor
                                        Completed   NA         NA          NA                    connecting Ajmer Road, Tonk Road and Agra
in Rajasthan
                                                                                                 Road, has been made operational after
                                                                                                 making temporary arrangements.
Ahmedabad-Dholera
                                                                           Sadbhav               Sadbhav Engineering Limited has received
Greenfield Alignment                    Awarded     22.00      6.90
                                                                           Engineering Limited   letter of award (LoA) from NHAI for two
(Package I)
                                                                                                 packages of Ahmedabad-Dholera Greenfield
Ahmedabad-Dholera                                                                                Alignment (GA) project, being implemented
                                                                           Sadbhav
Greenfield Alignment                    Awarded     26.52      8.82                              under Bharatmala Pariyojana.
                                                                           Engineering Limited
(Package II)

Source: India Infrastructure Research

                                                                                                                                                  22
Roads

Initiatives in Light of Covid-19
MoRTH relaxes rules to allow wider participation of domestic companies in road projects

 • The Ministry of Road Transport and Highways (MoRTH) has revised the eligibility criteria for road projects built on the engineering,
   procurement and construction (EPC) mode to ensure wider participation from domestic companies.

 • It has revised the average annual turnover of the bidder to 15% of the estimated project cost for the past five years. Earlier, the average
   annual turnover was required to be 20% of the estimated project cost.

 • Among other changes, the MoRTH has also relaxed the threshold technical capacity for normal highway projects, which will be 0.75 times the
   estimated project cost in case of projects up to Rs 1 billion, while it will be equal to the estimated project cost in case of projects more than Rs
   1 billion. For specialised projects, the threshold technical capacity has been revised to equal the estimated project cost or Rs 10 billion
   whichever is lower, for projects more than Rs 10 billion.

 • Further, no additional qualification will be required for bridges up to 60 metres long and tunnels up to 200 metres long, being built on the EPC
   mode, besides the bidder having constructed one similar work of 20 per cent of the estimated project cost. The ministry has also brought
   down the size of eligible projects for ascertaining technical experience from 10% to 5% of the project cost.

MoRTH eases norms for HAM projects

 • MoRTH has eased norms for hybrid annuity model (HAM) projects. The government will now make the upfront construction payment
   to a highway project concessionaire under HAM in 10 tranches as against 5, subject to the overall ceiling of 40% of the project cost.

 • Increasing the frequency of the installments will help concessionaires better manage their working capital requirements. Besides, the
   release of upfront payments during the construction period will be linked to the physical progress of the project.

 • Besides, the annuity payment will be made on the reducing balance of completion cost at an interest rate equal to average of one-year
   marginal cost of fund-based lending rate (MCLR) of top five scheduled commercial banks plus 1.25%.

                                                                                                                                                          23
Roads

Initiatives in Light of Covid-19
NHAI set to make FY 2021 the best year of highway construction

 • Reportedly, NHAI plans to award contracts worth Rs 2 trillion during the current fiscal year.
 • As per NHAI, there is no dearth of money and the government has encouraged the authority to build roads with full vigour and make it the
   best year of highway construction. Besides, NHAI will also be rating the best roads to enhance quality and speed of execution. NHAI has also
   urged the authorities to advocate innovative land pooling methods to save land acquisition costs across the country by upto Rs 2 trillion.

                                                          Other Policy Developments

MoRTH issues notification for promotion of toll payment through FASTag

 • MoRTH has issued a notification making FASTag mandatory to be available by January 1, 2021 in old vehicles as well, i.e., M and N category of
   motor vehicles (four wheelers) sold before December 1, 2017, through amendments in Central Motor Vehicles Rules (CMVR), 1989.
 • It has also been mandated that a valid FASTag is mandatory while getting a new 3rd Party Insurance through an amendment in FORM 51
   (certificate of Insurance), wherein the details of FASTag ID shall be captured. This shall be applicable with effect from April 1, 2021.

Andhra Pradesh government considers levying toll tax on state roads

 • Reportedly, Andhra Pradesh government is considering a plan to levy toll tax on state highways with high traffic density, in a bid to enhance
   the state government’s revenue.
 • The toll fee collected from the state highways will go to Andhra Pradesh Road Development Corporation (APRDC) to be used for maintenance
   of highways. A decision to this effect is expected to be taken soon by the State Cabinet.
 • In the first phase, toll will be collected at about 35 state highways, including the KadapaPulivendula, Eluru-Jangareddygudem and
   Bhimavaram-Gudivada highways. If the pilot succeeds, toll fee collection would be done in the remaining 24 routes as well.

                                                                                                                                                   24
Roads

Initiatives in Light of Covid-19
                                                             Key Announcements

National highway project awards double despite COVID-19 pandemic

 • As per media reports, the pace of award of national highway projects has almost doubled during April-October 2020, compared to the past
   year, despite the ongoing COVID-19 pandemic. Highway project awards for April-October 2020 have reached 5,679 km, compared to 2,982
   km in the same period of last year.
 • Besides, construction of highways has also improved from 210 km in April 2020 to 4,628 km by October 2020. This translates into average
   construction of nearly 22 km/day during April-October 2020.

NHAI toll collections cross pre-COVID levels in November 2020

 • Toll collection on national highways across the country surpassed pre-COVID levels in November 2020, signalling sharp signs of recovery in
   road traffic.

 • The toll collections in the first week of November have reached 114 per cent of pre-COVID levels in the month under review. On March 25,
   2020, the central government had announced temporary suspension of toll collection in the wake of COVID-19 pandemic.

 • NHAI as well as highway developers resumed collection at toll plazas in line with the Ministry of Home Affairs directives on April 20, 2020.
   Traffic across national highways had dipped to as low as 25-30 per cent of pre-COVID levels during the first phase of the nationwide lockdown
   in March 2020.

FASTag users cross 20 million count
 • NHAI has announced that the number of FASTag users in the country has crossed the 20 million mark, registering a growth of 400 per cent in
   a year.
 • This has increased the total toll collection to Rs 920 million per day, a substantial increase from Rs 700 million per day, a year back. FASTag
   contributes to nearly 75 per cent of the total toll collection as of now.

                                                                                                                                                     25
Roads

Initiatives in Light of Covid-19
                                                             Key Announcements

NHAI to introduce prepaid touch-and-go cards to cut long queues

 • With the aim to minimise cash transaction at toll plazas, NHAI will soon roll out a Delhi Metro type prepaid touch-and-go card for commuters.
   Each card would cost around Rs 50 and can be used only on ‘hybrid’ lanes where payments are made by cash or through electronic means.
 • NHAI’s toll management wing, Indian Highways Management Company Limited (IHMCL), has invited bids for rollout of this system. According
   to the tender document, the successful bidder will set up at least two dedicated point-ofsales (PoS) manpower in three shifts for card
   issuance, recharge, top-up facility and cash management at each national highway toll plaza for the initial three months.
 • The pre-paid card system will be integrated with the toll management systems (TMS) to enable the toll operator to select vehicle class so that
   the applicable toll fee can be deducted immediately from the prepaid card on tapping the PoS device.

                                                                                                                                                    26
Roads

Key Recent Developments
                                                Impact of COVID-19 on Competitive Intensity

 •   According to ICRA Ratings, expects the central government spend on infrastructure to be maintained given the positive multiplier affect it will
     have on overall economy amid the COVID-19 pandemic. The state governments in particular are staring at a huge revenue deficit in current
     financial year; and therefore, the headroom available to them for incurring capital expenditure has reduced substantially.
 •   The private sector capex and the interest in public private partnership (PPP) based infrastructure projects is also expected to be limited in
     near term, due to increased risk averseness and limited capital availability.
 •   As a result, NHAI/MoRTH EPC projects are expected to witness heightened competition.
 •   As per a study conducted by ICRA covering 160 EPC projects awarded by NHAI during F2017-20 spread across 22 states spanning 6,260 km,
     the average number of bidders per project for the EPC segment ranged between 4 to 10. These 160 projects were awarded to as high as 69
     EPC players.
 •   Of total 160 projects, 69% were awarded at a discount to NHAI’s base price (median discount of 11.2 per cent), 3% were awarded at par to
     base price and remaining 28% were awarded at a premium (median premium of 7.7%).
 •   The top 10 players bagged around 62 projects totaling 2,713 km which is 43% of total awards in length.

                                                               Grants/Allocations

 • The Uttar Pradesh Expressway Industrial Development Authority (UPEIDA) Board has approved a proposal of Rs 221.45 billion for civil works
   for the construction of the Ganga expressway project.
 • In order to generate finances, the Board has proposed that avenues of the public-private-partnership (PPP) model should be explored. The
   Board has suggested that investors should be identified as per the records of NHAI and then expression of interest (EOI) should be signed.

 • The Himachal Pradesh government has approved funds worth Rs 1.96 billion for the Pathankot-Mandi road project.
 • The project involves four-laning of 219 km long road stretch connecting Pathankot, Suini, Parour, Chauntada, Chauntra, Padhar and Mandi in
   Himachal Pradesh.

 • The Finance Committee of the Government of Uttar Pradesh has approved implementation of the Ghaziabad-Haridwar two-lane canal road
   project.
 • The project involves construction of 111 km two-lane canal road connecting Ghaziabad and Haridwar and is proposed on the right-side bank
   of the upper Ganga canal originating from Haridwar in Uttar Pradesh at an estimated cost of Rs 6.28 billion.

                                                                                                                                                       27
Roads

Key Recent Developments
                                                                  Loans/Bonds

 • The Asian Development Bank (ADB) and the central government have signed a $177 million loan to upgrade 450 km of state highways and
   major district roads in Maharashtra.
 • The project will improve connectivity between rural areas and urban centres in the state. Another feature of the project is to update the road
   maintenance system by encouraging five-year performance-based maintenance obligations to contractors to sustain asset quality and service
   levels.
 • The project will upgrade two major district roads and 11 state highways, with combined length of 450 km, to two-lane standard across seven
   districts of Maharashtra, and improve connectivity to national highways, interstate roads, seaports, airports, rail hubs, district headquarters,
   industrial areas, enterprise clusters and agricultural areas.

 • The World Bank has signed a $120 million project to improve and modernise the transport sector in Meghalaya. The $120 million loan from
   the International Bank for Reconstruction and Development (IBRD) has a maturity of 14 years, including a grace period of six years.
 • The Meghalaya Integrated Transport Project (MITP) will improve about 300 km of strategic road segments and stand-alone bridges by using
   innovative, climate-resilient, and nature-based solutions.
 • The segments will serve major agriculture areas, important tourist destinations, small-scale industries, major towns and underserved
   populations by linking them to markets, health and education centres, besides national and international corridors.

 • A consortium of public sector banks has sanctioned a fresh loan of Rs 2.50 billion for the Gorakhpur Link expressway project. The Bank of
   Maharashtra has also joined the consortium and Punjab National bank and UCO Bank have already provided credit of Rs 7.5 billion and Rs 2.5
   billion, respectively, for the project.
 • So far, three public sector banks have provided Rs 12.5 billion for the project. Meanwhile, the Uttar Pradesh cabinet has already granted
   approval for setting up the consortium of banks for funding the expressway project.

                                                                                                                                                      28
Roads

Key Recent Developments
                                                                    TOT/InvITs

 • NHAI has received upfront consideration of Rs 50.11 billion from Cube Highways and Infrastructure, under the third bundle of the tolloperate-
   transfer (TOT) model. The Singapore-based firm had delayed the payment to NHAI amid the uncertainties posed by COVID-19 outbreak.
 • The TOT Bundle III, with a cumulative length of 566 km, consists of nine toll plazas in the state of Uttar Pradesh, Jharkhand, Bihar and Tamil
   Nadu.
 • Cube Highways had deferred paying up for the bundle as traffic density had started dwindling since March this year, when India went under a
   nationwide lockdown to curb the spread of COVID-19. However, the company has not been penalised for delay in payment as the
   government continues to implement relaxations announced in light of the pandemic.

 • Reportedly, NHAI is set to come up with its Rs 50 billion Infrastructure Investment Trust (InvIT) by early-2021.
 • NHAI’s InvIT, the first InvIT to be sponsored by any government entity in the country, will initially consist of the highway road assets under the
   TOT Bundle II.
 • Auction for the second TOT bundle, with 586 km of national highways in Rajasthan, Gujarat, West Bengal, and Bihar at a base price of Rs
   53.62 billion, got cancelled last year after the bids offered were much below NHAI expectation.

 • Reportedly, IL&FS Limited has finalised the InvIT structure for its road assets in order to resolve its debt of about Rs 150 billion.
 • IL&FS has set up Roadstar Infra Private Limited (RIIPL), as a new subsidiary of IL&FS Transportation Networks India Limited (ITNL) to act as a
   sponsor to the proposed InvIT. Besides, North Karnataka Expressway Limited (NKEL) has been appointed as the investment manager to the
   proposed InvIT.
 • As per the reports, ITNL has infused fresh capital of Rs 750 million in the sponsor entity post receipt of requisite approvals, in order to meet
   the SEBI’s InvIT norm of Rs 1 billion net worth. In addition, NKEL will be transferred by ITNL to Roadstar Infra Private Limited.
 • IL&FS has received in-principle approval from SEBI for registering the InvIT and is likely to approach SEBI shortly for seeking final registration
   of the trust.

 • IRB Infrastructure Trust, the private InvlT, has successfully closed the second tranche of fund raising by way of Rights Issue of Units amounting
   to Rs 5.10 billion.
 • IRB Infrastructure Developers Limited, being the sponsor and 51 per cent stakeholder, contributed Rs 2.6 billion and GIC affiliates, holding the
   balance 49 per cent stake, have contributed Rs 2.5 billion.
 • This is part of the total commitment of Rs 44 billion by GIC affiliates towards 49 per cent stake in the private InvIT housing nine BOT assets,
   out of which IRB Infrastructure Trust had already received Rs 37.53 billion from GIC affiliates in February 2020.

                                                                                                                                                        29
Roads

Key Recent Developments
                                                              Financial Closures

 • Ashoka Kandi Ramsanpalle Road Private Limited, a wholly owned subsidiary of Ashoka Buildcon Limited, has achieved financial closure letter
   dated October 23, 2020 from NHAI.
 • The company received financial closure on October 5, 2020, for the project entailing four-laning of 39.98 km section of NH-161 from Kandi
   (Design km 0) (km 498.25 of NH-65) to Ramsanpalle (Design km 39.98/existing km 44.76) in Telangana.
 • The HAM project is being implemented under Bharatmala Pariyojna at a bid project cost of Rs 10 billion.

                                                         Asset Sales/Stake Dilution

 • Reportedly, the Life Insurance Corporation of India (LIC) has raised its stake in IRB Infrastructure Developers Limited to 5.27 per cent in
   quarter ended September 2020.
 • LIC has been increasing its holding in the company for a long time. In the September quarter, LIC's stake in the company rose to 5.27 per cent,
   from 3.81 per cent in the quarter ended June 2020.

 • Sadbhav Infrastructure Project Limited has received approval from Ahmedabad Urban Development Authority (AUDA) for 100 per cent stake
   sale in Ahmedabad Ring Road Infrastructure Limited (ARRIL), a wholly owned subsidiary of the company, to Indinfravit Trust and refinancing
   of existing debts of ARRIL subject to fulfillment of certain conditions.
 • The company had signed definitive agreements with lndinfravit on July 1, 2019 to sell 100 per cent stake in nine operational projects for an
   enterprise value of Rs 66.1 billion (including equity value of Rs 25.5 billion).

 • Reportedly, Welspun Enterprises Limited is in talks with a Canadian pension fund for investment in the company’s road project assets.
 • The company has nine road projects, with a project cost of over Rs 120 billion. Of the nine road projects, seven are on the hybrid annuity
   model (HAM).

                                                                                                                                                     30
Roads

Key Recent Developments

                                                                   Others

 • NHAI has accepted arbitration award amounting to Rs 439.51 million in favour of Dhule Palesner Tollway Limited (DPTL), a subsidiary of
   Sadbhav Infrastructure Project Limited, without any pendente-lite interest and interest on delayed payment. Sadbhav Infrastructure Project
   Limited had earlier announced the winning of an arbitration award against NHAI through DPTL.
 • DPTL had received appointed date on December 21, 2009 to augment the 89 km existing road from km 168.5 to km 265 on the Madhya
   Pradesh/Maharashtra Border - Dhule section of NH-3 in Maharashtra by four-laning on DBFOT basis.
 • The original concession period is 18 years from the appointed date. DPTL achieved first commercial operations date on January 23, 2012.

 • IRB InvIT Fund has announced that IRB Surat Dahisar Tollway Limited has concluded its conciliation process with NHAI and accordingly, the
   concession period for its project has been extended by 460 days.
 • As a result, the concession period for the project will expire on May 25, 2022, as against the original transfer date of February 19, 2021.

                                                                                                                                                 31
Roads

Key Upcoming Projects
                                                                 Key Upcoming Projects
                          Cost          Length                          Current
 Project name                                          State                                                Detailed status
                       (Rs billion)      (km)                            Status
                                                                                     The first phase between Nagpur-Shirdi will be commissioned
Mumbai-Nagpur                                                                        by May 1, 2021. The second phase of 103 km between Shirdi
                                                                      Under
Communication               553.35      701.00   Maharashtra                         and Igatpuri will be opened for traffic in December 2021 while
                                                                      Construction
expressway                                                                           the remaining 78 km between Igatpuri and Wadpe near
                                                                                     Mumbai will be commissioned on May 1, 2022.
                                                                                     As of September 2020, 26 packages have been awarded under
                                                 Delhi, Rajasthan,
                                                                                     the project. Besides, construction work has already
Delhi-Vadodara                                   Haryana, Madhya      Under
                            424.80      845.00                                       commenced on 13 packages. Recently, Dilip Buildcon Limited,
expressway                                       Pradesh and          Construction
                                                                                     in JV with Altis Holding Corporation, has been declared the
                                                 Gujarat
                                                                                     lowest (L-1) bidder for Package 15 of the project.
                                                                                     As of September 2020, seven packages have been awarded
Vadodara-                                                                            under the project. Besides, construction work has already
                                                 Gujarat and          Under
Mumbai                      400.33      447.00                                       commenced on five packages. Most recently, IRB
                                                 Maharashtra          Construction
expressway                                                                           Infrastructure Developers Limited has received letter of award
                                                                                     (LoA) for construction of 27.5 km Gandeva-Ena section.
                                                                                     The Cabinet has approved a district-wise alignment of the
                                                                                     expressway. The government has also decided to monetise the
Ganga                                                                                Agra-Lucknow expressway for funding the Ganga expressway
                            299.24      628.00   Uttar Pradesh        Approved
expressway                                                                           project and has decided to set up a high-power committee to
                                                                                     take procedural and operational decisions to monetise the
                                                                                     Agra-Lucknow expressway.

Delhi - Amritsar                                 Delhi, Punjab and
                                                                      Under          Recently, NHAI invited bids for various packages under the
- Katra                     309.36      600.00   Jammu &
                                                                      Bidding        project.
expressway                                       Kashmir

Source: India Infrastructure Research

                                                                                                                                                      32
Roads

Key Upcoming Projects
                                                                 Key Upcoming Projects
                       Cost             Capacity                   Current
Project name                                          State                                                 Detailed status
                    (Rs billion)          (km)                      Status
                                                                                In September 2020, the Andhra Pradesh government gave
                                                                                administrative sanction for Rs 1 billion to acquire land for the project.
Amaravati-                                                                      The alignment of the proposed access-controlled expressway has been
                                          384 km    Andhra
Anantapur                276.25                                  Approved       approved by the Land Acquisition Committee and the total cost of the
                                        (approx.)   Pradesh
expressway                                                                      land acquisition has been estimated to be Rs 22.31 billion. The state
                                                                                government will provide the land owned by it free of cost and bear
                                                                                50% of the cost to be incurred for acquiring additional land.

Purvanchal                                          Uttar        Under          UPEIDA is aiming to throw open the Purvanchal expressway to the
                         224.95           340.82
expressway                                          Pradesh      Construction   public from January 26, 2021, ahead of the deadline of April 2021.

                                                                                As of September 2020, about 16% construction work has been
Bundelkhand                                         Uttar        Under          completed on the project. In August 2020, UPEIDA signed a loan
                         148.49           296.07
expressway                                          Pradesh      Construction   agreement of Rs 59 billion with a consortium of six banks for timely
                                                                                project execution.
Chennai-                                            Karnataka,
                                                                 Under
Bengaluru                207.99           272.00    Tamil                       Recently, bids have been invited for various under the project.
                                                                 Bidding
expressway                                          Nadu
Surat-
                                                    Gujarat,
Ahmednagar-                                                                     The project is still in the announced stage. Construction work on the
                         205.53           300.00    Maharasht    Announced
Solapur                                                                         Surat-Ahmednagar highway is expected to commence by April 2021.
                                                    ra
highway

Mumbai
                                                    Maharasht    Under          The construction work on the 21.8 km Mumbai Trans Harbour Link
Trans                    178.43            21.80
                                                    ra           Construction   (MTHL) project is expected to be completed by September 2022.
Harbour Link

Source: India Infrastructure Research

                                                                                                                                                            33
You can also read