Project Readiness Financing Project Administration Manual India: Sikkim Major District Roads Upgradation Project - Asian ...

Page created by Stanley Alvarez
 
CONTINUE READING
Project Readiness Financing Project Administration Manual India: Sikkim Major District Roads Upgradation Project - Asian ...
Project Readiness Financing
 Project Administration Manual

Project Number: 52159-003
Loan Number: {PRFXXXX}
May 2021

India:
Sikkim Major District Roads Upgradation Project
CONTENTS

I.      IMPLEMENTATION PLAN                                                     1
        A.   Overall Implementation Plan                                        1
II.     PROJECT MANAGEMENT ARRANGEMENTS                                         2
        A.   Project Implementation Organizations: Roles and Responsibilities   2
        B.   Key Persons Involved in Implementation                             3
III.    COSTS AND FINANCING                                                     5
        A.   Key Assumptions                                                    5
        B.   Allocation and Withdrawal of Loan Proceeds                         5
        C.   Detailed Cost Estimates by Expenditure Category and Financier      6
        D.   Detailed Cost Estimates by Year                                    7
        E.   Contract and Disbursement S-Curve                                  8
IV.     FINANCIAL MANAGEMENT                                                     8
        A.   Financial Management Assessment                                     8
        B.   Disbursement                                                       10
        C.   Accounting                                                         11
        D.   Auditing and Public Disclosure                                     12
V.      PROCUREMENT AND CONSULTING SERVICES                                     12
        A.   Advance Contracting and Retroactive Financing                      13
        B.   Procurement of Consulting Services                                 13
        C.   Procurement of Goods and Civil Works                               13
        D.   Procurement Plan                                                   13
        E.   Consultant's Terms of Reference                                    13
VI.     SAFEGUARDS                                                              14
VII.    PERFORMANCE MONITORING                                                  14
        A.   Monitoring                                                         14
        B.   Reporting                                                          14
VIII.   ANTICORRUPTION POLICY                                                   15
IX.     ACCOUNTABILITY MECHANISM                                                15
X.      RECORD OF CHANGES TO THE PROJECT ADMINISTRATION MANUAL                  15

APPENDIXES
1.   Indicative list of Subprojects                                             16
2.   Detailed Terms of Reference                                                17
Project Administration Manual for Project Readiness Financing Facility: Purpose and Process

The project administration manual (PAM) for the project readiness financing (PRF) facility is an abridged
version of the regular PAM of the Asian Development Bank (ADB) and describes the essential
administrative and management requirements to implement the PRF facility following the policies and
procedures of the government and ADB. The PAM should include references to all available templates
and instructions either by linking to relevant URLs or directly incorporating them in the PAM.

The executing agency–Government of Sikkim acting through Roads and Bridges (R&B) Department, and
the implementing agency–Project Management Unit (PMU), (ADB Cell) under R&B Department,
Government of Sikkim are wholly responsible for the implementation of ADB-financed PRF project, as
agreed between the borrower and ADB, and following the policies and procedures of the government
and ADB. ADB staff is responsible for supporting implementation, including compliance by R&B
Department and PMU of Government of Sikkim, of their obligations and responsibilities for PRF project
implementation following ADB’s policies and procedures.

In the event of any discrepancy or contradiction between the PAM and the loan agreement, the provisions
of the PRF loan agreement will prevail.

After ADB’s approval of the PRF proposal, changes in implementation arrangements are subject to
agreement and approval pursuant to relevant government and ADB administrative procedures (including
the Project Administration Instructions) and upon such approval, they will be subsequently incorporated
in this PAM.
ABBREVIATIONS

ADB      –   Asian Development Bank
AFS      –   audited financial statement
CAG      –   Comptroller and Auditor General
DEA      –   Department of Economic Affairs
DPR      –   detailed project report
DPRC     –   detailed project report consultant
EIA      –   environmental impact assessment
EIRR     –   economic internal rate of return
EMP      –   environmental management plan
FMA      –   financial management assessment
IEE      –   initial environmental examination
IPP      –   indigenous peoples plan
Km/km    –   Kilometer
MDB      –   multilateral development bank
MDONER   –   Ministry of Development of North Eastern Region
NEC      –   North Eastern Council
PAM      –   project administration manual
PCR      –   project completion report
PMU      –   project management unit
PPMS     –   project performance monitoring system
PRF      –   project readiness financing
PWD      –   Public Works Department
QCBS     –   quality- and cost-based selection
R&B      –   roads and bridges
SBD      –   standard bidding document
TOR      –   terms of reference
I.        IMPLEMENTATION PLAN

A.      Overall Implementation Plan

1.      Table 1 presents the overall implementation plan for the Project Readiness Financing (PRF) assistance and records key
        implementation, including project management activities (on quarterly basis), which will be updated annually and submitted to
        the Asian Development Bank (ADB) with updated contract and disbursement projections for the following year.

                                        Table 1: Implementation Plan over PRF Assistance Tenure
                                                       2021                          2022                     2023                    2024
                                             Q1     Q2        Q3    Q4   Q1     Q2      Q3    Q4     Q1    Q2     Q3     Q4    Q1      Q2     Q3
     Year/ Activities
     PRF Approval (Advance Action)
     A. Implementation
        Consultant selection
       Feasibility studies & DPRs
       Capacity building
     B. Management Activities
         ADB approval
         PRF signing
         PRF effectiveness
        Submission of QPRs
        Submission of annual report
        Submission of APFS
     ADB = Asian Development Bank, APFS = audited project financial statement, PPMS = project performance monitoring system, PRF = project readiness
     financing, Q = quarter; DPRs: Detailed Project Reports; QPRs= Quarterly Progress Reports
     Source: Asian Development Bank.
2

                          II.       PROJECT MANAGEMENT ARRANGEMENTS

A.       Project Implementation Organizations: Roles and Responsibilities

                       Table 2: Roles and Responsibilities of Key Stakeholders
Implementation Organizations                                Management Roles and Responsibilities
A. Executing agency
Government of Sikkim acting              •    Appoint a Project Director dedicated for the PRF assistance and
through its Roads and                         establish a Project Management Unit at the R&B Department, which is
Bridges (R&B) Department                      adequately staffed with suitable resources (including qualified accounting
                                              personnel) and acceptable to ADB.
                                         •    Ensure good coordination with Department of Economic Affairs (DEA),
                                              Ministry of Finance, Government of India and for adequate allocation of
                                              annual budget to the project, as per recommendation of PMU.
                                         •    Be the focal point at execution level for communication with all
                                              stakeholders, including ADB, facilitation coordination for all stakeholder
                                              consultations, and be the signatory to all key documents including
                                              withdrawal applications and audit reports for submission to the
                                              Government of Sikkim and the Government of India on PRF assistance;
                                         •    Liaise with ADB to address any issues during detailed engineering
                                              design/procurement/institutional development works of consulting firm
                                              under PRF assistance.
                                         •    Conduct review and approve detailed engineering designs/any other
                                              design works and resource/effort/cost estimates, including DPRs.
B. Implementing agency
Project Management Unit                  •    Prepare through consulting firm and recommend to R&B Department for
(ADB Cell) under R&B                          approval of detailed engineering designs/any other design works, DPRs,
Department , Government of                    procurement process documentation, and institutional strengthening and
Sikkim                                        capacity building requirements and programs on training/workshops/
                                              seminars/ conferences etc., including necessary coordination with all
                                              stakeholders;
                                         •    Process bills for services contract. Conduct periodic review of the work
                                              progress under PRF assistance and submit agreed progress/project
                                              reports to the steering committee, Government of Sikkim, Government of
                                              India, and ADB.
                                         •    Disclosure of information related to the project to the public through
                                              government website(s). Facilitate in ensuring compliance with conditions
                                              of PRF loan agreement under PRF assistance, Government of India,
                                              Government of Sikkim, and ADB guidelines, procedures, and policies.
                                         •    Ensure compliance with ADB Safeguard Policy Statement, the
                                              environmental assessment, resettlement, indigenous peoples
                                              frameworks, etc. for the work under PRF assistance and the
                                              corresponding reports/plans such as EMPs, IEEs/EIAs, resettlement
                                              plans, IPPs, etc., as required, for each of the subprojects;
C. Asian Development Bank            •       Provide guidance to state agencies–R&B Department, PMU (R&B), etc.
                                             on PRF assistance-related design and implementation issues;
                                     •       Facilitate R&B Department/PMU on procurement processing for
                                             consulting firm/consultants’ selection under PRF assistance;
                                             Conduct periodic review of the PRF assistance; and Disclosure of
                                             information related to the PRF assistance, as per ADB’s Access to
                                             Information Policy.
ADB = Asian Development Bank, DEA = Department of Economic Affairs, DPR = detailed project report, EIA = environmental impact
assessment, EMP = environmental management and monitoring plan, IEE = initial environmental examination, IPP = indigenous
peoples plan, MDONER = Ministry of Development of North Eastern Region, NEC = North Eastern Council, PCR = project completion
report, PRF = project readiness financing, PMU = project management unit, R&B = roads and bridges
Source: Asian Development Bank.
3

B.    Key Persons Involved in Implementation

2.    The key persons involved in the implementation of PRF assistance are as follows:

 Executing Agency
 Government of Sikkim acting      Officer’s Name: T.P. Shangderpa,
 through its Roads and Bridges    Position: Principal Chief Engineer-cum-Secretary
 (R&B) Department                 Telephone No.: +91- 03592-203460
                                  E-mail address: roadsandbridgessikkim1@gmail.com
                                  Office Address: Roads & Bridges Department,
                                  Government of Sikkim, Nirman Bhavan, Zero Point,
                                  National Highway 10, Gangtok, Sikkim.

 Executing Agency                 Officer’s Name: Shanti Tamang,
                                  Position: Project Director
                                  Telephone No.: +91- 03592-203460
                                  E-mail address: pdadbsikkim@gmail.com
                                  Office Address: Roads & Bridges Department,
                                  Government of Sikkim, Nirman Bhavan, Zero Point,
                                  National Highway 10, Gangtok, Sikkim

 Asian Development Bank
 Indian Resident Mission          Staff Name: Takeo Konishi
                                  Position: Country Director
                                  Telephone No.: +91-11-2410-7200
                                  E-mail address: tkonishi@adb.org

 Mission Leader                   Staff Name: Prabhasha Sahu
                                  Position: Senior Project Officer
                                  Telephone No: 91-11-2410-7200
                                  E-mail address: psahu@adb.org
4

C.     Project Organization Structure

                             Figure 1: Project Organization Structure

                                            Government of Sikkim
             ADB                       (Project Steering Committee)                            DEA

                                    Roads and Bridges Department (R&B)
                                            (Executing Agency)

                                          Project Management Unit
                                             ADB Cell under R&B
                                           (Implementing Agency)

                                            Detailed Project Report
                                                  Consultant

 ADB = Asian Development Bank, DEA = Department of Economic Affairs, DPRC = detailed project report consultant.
5

                                     III.    COSTS AND FINANCING

A.        Key Assumptions

3.        The following key assumptions underpin the cost estimates and financing plan:

          (i)    Exchange rate: INR 73.1415 = $1.00 (as of 26 February 2021).
          (ii)   Contingencies (including price contingencies) calculated at 12% of base cost has
                 been considered.

B.        Allocation and Withdrawal of Loan Proceeds

4.       The PRF will finance consulting services only, including allocations workshops and
training, studies, field surveys and other reimbursable expenses. Local indirect taxes and duties
will be financed from the government resources.

                    Table 3: Allocation and Withdrawal of PRF Loan Proceeds
 Number             Category                Total Amount Allocated for   Basis for Withdrawal from the
                                                ADB Financing ($)                Loan Account
     1.     Consulting Services                     2,500,000              81.1% of total expenditure
            Total                                   2,500,000
PRF = project readiness financing.
Source: Asian Development Bank.
6

C.        Detailed Cost Estimates by Expenditure Category and Financier

                                           Table 4: Detailed Cost Estimates by Expenditure Category
                                                                   ($ million)1
                                                                        ADB OCR                              GOS                     Total Cost2
                               Item                                            % of                                % of                    Taxes and
                                                                     Amount                          Amount                       Amount
                                                                             Category                            Category                    Duties
     A.   Investment Costs
     1    Feasibility studies and Detailed engineering                     1.90        81.1%             0.44       18.9%             2.34            0.36
          designs
     2    Institutional capacity building                                  0.33        81.1%             0.08       18.9%             0.41            0.06
          Subtotal (A)                                                     2.23        81.1%             0.52       18.9%             2.75            0.42

     B.   Contingencies3                                                    0.27       81.1%             0.06       18.9%             0.33

     C.   Financing Charges4                                                   -          0%             0.05     100.0%              0.05
                 Total Project Cost (A+B+C)                                 2.50       80.0%             0.63      20.0%              3.13            0.42
                    % Total Project Cost                                      80%                             20%                                100%
ADB= Asian Development Bank, GoS= Government of Sikkim, OCR= ordinary capital resources

Notes:
1. Numbers may not sum precisely because of rounding.
2. Includes taxes and duties of $0.42 million to be financed from government resources by cash contribution.
3. Contingencies (including price contingencies) computed at 12% for consulting services.
4. Includes Interest during implementation for the ordinary capital resources (OCR) loan, computed at the 3-year United States dollar fixed swap rate plus a spread
of 0.5%. Commitment charges for the OCR loan has not been considered on the undisbursed loan amount.
Source: Asian Development Bank.
7

D.       Detailed Cost Estimates by Year

                                                      Table 5: Detailed Cost Estimates by Year
                                                                      ($ million)1
                         Item                                           Total        2021                           2022                 2023                2024
 A.      Investment Costs2
         Feasibility studies and Detailed
     1                                                                        2.34               0.66                1.01                0.42                0.25
         engineering designs
     2   Institutional capacity building                                      0.41                  -                0.08                0.25                0.08
                       Total Base Cost                                        2.75               0.66                1.10                0.66                0.33
 B.      Contingencies3                                                       0.33               0.08                0.13                0.08                0.04
 C.      Financing Charges4                                                   0.05               0.00                0.01                0.02                0.02
            Total Project Cost (A+B+C)                                        3.13               0.74                1.24                0.76                0.39
Notes:
1. Numbers may not sum precisely because of rounding.
2. Includes taxes and duties of $0.42 million to be financed from government resources by cash contribution.
3. Contingencies (including price contingencies) computed at 12% for consulting services.
4. Includes Interest during implementation for the ordinary capital resources (OCR) loan, computed at the 3-year United States dollar fixed swap rate plus a spread
of 0.5%. Commitment charges for the OCR loan has not been considered on the undisbursed loan amount.
Source: Asian Development Bank.
8
E.          Contract and Disbursement S-Curve

                              Table 6: Contract Awards and Disbursement
     Year           Contract Awards (in $ million)                     Disbursements (in $ million)
                Q1      Q2     Q3      Q4       Total           Q1        Q2        Q3     Q4       Total
     2021      2.50      -      -       -        2.50            -       0.20      0.20   0.20      0.60
     2022        -       -      -       -          -           0.25      0.25      0.25   0.25      1.00
     2023        -       -      -       -          -           0.15      0.15      0.15   0.15      0.60
     2024        -       -      -       -          -           0.30         -        -      -       0.30
                   Total Contract Awards         2.50                 Total Disbursements           2.50
Q= quarter.
Source: Asian Development Bank.

                                              Figure 2: S-Curve

         Q= quarter.

                                    IV.      FINANCIAL MANAGEMENT

A.          Financial Management Assessment

5.    The Financial Management Assessment (FMA) was conducted in June 2020 – July 2020,
in accordance with ADB’s Guidelines for Financial Analysis and Evaluation, Financial
Management Assessment, and related technical guidance notes1.

6.     The Executing / Implementing Agency has prior experience of executing ongoing ADB-
funded project, however there is scope for improvement in the areas of disbursements, financial-
recording keeping, reporting, and auditing requirements. Deficiencies in the areas of audit as
observed for the ongoing ADB funded project requires attention. Apart from subordinate level
accountants, a financial management specialist with adequate experience shall be engaged to

1   ADB. 2019. Financial Analysis and Evaluation. Manila; and ADB. 2015. Financial Management Assessment. Manila
9

address the accounting issues identified. Adequate training to familiarize the executing and
implementing agency on ADB’s financial management matters will be imparted by ADB. Suitable
accounting policies on audited project financial statements (APFS) will be drafted by PMU and
approved by ADB. Considering the risk factors identified, subject to mitigation arrangements
during implementation period, overall FM risk is assessed as moderate.

7.      R&B Department has agreed to implement an action plan as key measures to address the
deficiencies. The financial management action plan is provided in the following Table:

 Key Risks                 Risk Mitigating Activity                 Timeline        Responsible
                                                                                    Entity
 Staff in finance and      Adequate      staff   training   and     No later than   R&B
 accounting section are    handholding      through     capacity    2 years from    Department
 not trained for ADB       building on financial management         the             and ADB
 Projects.                 will be done (output 2 of PRF).          effectiveness
                                                                    of the PRF
                                                                    project.
 Timely preparation of     An experienced FM specialist shall       Continuous      R&B
 project       financial   be engaged mainly for estimation of                      Department
 statements including      budgets, provide support to
 inappropriate             accounts staff on preparation of                         ADB
 accounting     policies   disbursement     claims,      overall
 and issue of project      financial    management          and
 audit report.             preparation of project financial
                           statements. Consultation with ADB
                           FM staff on accounting policy shall
                           be made prior to finalization of first
                           submission of PFS.

                           Engagement of private auditor as
                           an alternative measure in case
                           delays from government auditors
                           are anticipated.
 Delay in payment to       Services of a single Consultant will     Continuous      R&B
 the Consultant            be used for the PRF and funds can                        Department
                           be transferred online from State                         and ADB
                           finance to the ADB project fund for
                           payments.
                           Necessary hand holding will be
                           done by the FM specialist.
 Budget is not recorded    Budget is recorded in the PFMS           No later than   R&B
 and           therefore   (central level system for budget),       2 years from    Department.
 comparison         with   and such data should be used for         the
 actuals is not done.      comparison.       Engagement     of      effectiveness   ADB       to
                           experienced FM specialist to hand-       of the PRF      monitor
                           hold will be necessary.                  project.
 Lack of documented        FM specialist engaged for the            No later than   R&B
 policies        and       project      to      develop    an       2 years from    Department
 procedures to the         implementable standard operating         the
 extent relevant for       procedure (SOP) on accounting            effectiveness
 ADB projects.             functions     relevant   for  ADB
10
                                 compliances and for overall                     of the PRF
                                 safeguard against fraud, abuse and              project.
                                 waste.
    Manual records are           Feasibility of basic automation for             No later than       R&B
    maintained leading to        maintaining books of accounts                   2 years from        Department
    risk    of     errors        should be explored.                             the
    omissions etc.                                                               effectiveness
                                                                                 of the PRF
                                                                                 project.

B.       Disbursement

8.      R&B Department, Government of Sikkim will disburse the project readiness loan proceeds
following the Asian Development Bank (ADB) Loan Disbursement Handbook (2017, as amended
from time to time), and detailed arrangements agreed between the government and ADB. Online
training for project staff on disbursement policies and procedures is available.2 Project staff are
encouraged to avail online training facility and also to attend annual workshops by ADB on
disbursement procedures conducted every year to get familiarized with the disbursement
procedures.

9.     Reimbursement method using full documentation procedures (by submitting complete
supporting-documents) shall be the primary method of disbursement. Additionally, it may also use
Statement of expenditure (SOE) procedure using a threshold limit of US$ 100,000 by submitting
SOEs without any supporting documents. All relevant supporting documents claimed under SOE
procedures should be maintained and made readily available for review by ADB’s disbursement
review missions, upon ADB’s request for submission of supporting documents on a sampling
basis, and for independent audit3. Advance procedures and direct payment procedures for
disbursements shall not be used in PRF

10.      A PMU to monitor and manage the PRF assistance will be established at R&B
Department, Government of Sikkim and led by a project director who will be the authorized
signatory for withdrawal applications. The PMU will include an experience financial management
specialist who will be responsible for (i) collecting supporting documents; (ii) preparing the
withdrawal applications for signature by the Project Director; and (iii) uploading the draft
withdrawal applications on ADB’s Client Portal for Disbursements (CPD)4 system to CAAA for
finalization and approval.

11.     Before submitting the first withdrawal application, the borrower should submit to ADB
sufficient evidence of the authority of the person who will sign the withdrawal applications on
behalf of the government, together with the authenticated specimen signatures of each authorized
person. The minimum value per withdrawal application is stipulated in ADB’s Loan Disbursement
Handbook. Individual payments below such amount should be paid (i) by the R&B Department of
Government of Sikkim and subsequently claimed from ADB through reimbursement, unless
otherwise accepted by ADB. PMU and borrower shall ensure that sufficient category and contract
balances are available before requesting disbursements. Use of ADB’s CPD system for
submission of withdrawal applications to ADB will be considered mandatory.

2 Disbursement eLearning. http://wpqr4.adb.org/disbursement_elearning
3 Independent auditors are required issue opinion under annexure 7 template of terms of reference (TOR) agreed
   between ADB, Department of Economic Affairs (DEA) and Comptroller and Auditor General of India.
4 ADB’s Client Portal for Disbursements system facilitates online submission of withdrawal applications to ADB,

   resulting in faster disbursement. The forms to be completed by the borrower are available at ADB. Guide to the Client
   Portal for Disbursements.
11

12.    No further disbursements will be made from the PRF account upon refinancing under an
ensuing or ongoing loan. The PRF loan amount is paid out under the PRF cost category of the
ensuing or ongoing loan that will refinance the PRF loan. Provided the following costs are eligible
expenditures, the ensuing or ongoing loan will finance (i) costs incurred under PRF that have not
yet been paid from the PRF account by the refinancing date; (ii) costs for activities initiated under
PRF and continuing beyond the refinancing date; and (iii) costs incurred during PRF
implementation but ineligible under PRF.

C.         Accounting and Auditing

13.     R&B department, Government of Sikkim will maintain separate PRF project accounts and
records by funding source for all expenditures incurred on the PRF project. A project financial
statement (PFS) will be prepared at the PMU following cash basis of accounting as per accepted
accounting principles and standards followed by the Government of India and the state
government. ADB expects audited project financial statements prepared in accordance with
International Public Sector Accounting Standard (IPSAS) or accounting standards prescribed by
nationally constituted professional accounting organization (PAO).5

14.     Given the FM capacity at IA, PFS can be prepared using template of cash based project
financial statements provided in the standardized terms of reference (TOR) of audit of ADB-
assisted projects, agreed with the Comptroller and Auditor General of India, the Department of
Economic Affairs and ADB. The audit report including scope of audit shall be as per TOR
document by following Annexure 13 of TOR guidance template. Accordingly, the expected
disclosures in the project financial statements will include at least the following:

(i) Statement of cash receipts (by financing source) and payments (by expenditure category) for
the current reporting period, past reporting period, and cumulative to date;

(ii) Statement of expenditure by category and financier for the year/period end;

(iii) statement of disbursement, disclosing all funds claimed from ADB by disbursement method,
total expenditure claimed for the current reporting period, past reporting period, and cumulative
to date. The notes of the financial statements should include a detailed list of all withdrawal
applications submitted to ADB, and the amounts paid by ADB as follows: (a) withdrawal
application number, (b) the amount claimed and currency, (c) date submitted, and (d)
disbursement method and the amount disbursed by ADB; The statement should be supported by
relevant withdrawal accounts used for claiming disbursements from ADB.

(iv) Notes on the PFS financial statements and significant accounting policies followed at the
project including other relevant explanatory notes and explanations as appropriate.

(v) Statement of disbursements claimed using Statement of Expenditure (SOE) procedures during
reporting period by giving reference to withdrawal application numbers;

(vi) A statement of appropriation vs. actual expenditures. Any significant variances must be duly
explained;

(vii) Expenditure by output/components for the current reporting period, past reporting period, and
cumulative to date;

5   Institute of Chartered Accountants of India (ICAI) is the relevant PAO for India
12

15.      Auditor for the PFS shall be any independent auditor which can be either from audit-office
of Accountant General (A&E), Sikkim or any private independent chartered accountant having
certificate of practice and registered with ICAI. By default the auditor from state office from (A&E)
is the auditor. Scope of audit shall be strictly in accordance with TOR document. Audit report
issued shall be as per audit-report template provided in annexure-13 of the TOR as a guidance.
To facilitate timely-audit, PMU shall ensure draft PFS be ready within 3 months of close of fiscal
year during project-implementation. In case delays to commence audits by the government
auditor is anticipated, PMU may engage a reputable private independent chartered accountant to
perform the project audit within 1 month after close of 3 months of fiscal year. The auditor’s opinion
in report shall be in English with project financial statements (APFS) shall be submitted to ADB
within 6 months of close of fiscal year.

16.     GOS shall enable ADB upon ADB’s request, to discuss the financial-statements for the
project, where they relate to the project with their auditors appointed by the state or PMU, and
shall authorize and require any representative of such auditors to participate in any such
discussions requested by ADB. This is provided that such discussions shall be conducted on in
presence of an authorized officer of the state having sufficient understanding on audit and
accounting related matters, unless the state shall otherwise agree.

17.     ADB has made the R&B Department, GOS aware on ADB’s approach to delayed
submission of APFS and the requirements for satisfactory and acceptable quality of the audited
project financial statements.6 ADB reserves the right to require an addition in the auditor, if the
audits required are not conducted in a manner satisfactory to ADB or if the audits are substantially
delayed. ADB reserves the right to verify the financial accounts to confirm that its policies and
procedures were followed when the share of ADB’s financing was used.

D.         Public Disclosure

18.     ADB’s Access to Information Policy 2018 will guide the public disclosure of the audited
project financial statements. ADB shall disclose the annual project audit report and related PFS
(without management letter) within 14 days of the date of ADB’s confirmation of their acceptability
by posting them on ADB website.

                          V.       PROCUREMENT AND CONSULTING SERVICES

19.    R&B department (the executing agency) has been executing road improvement works in
Sikkim as a part of ADB-funded North Eastern State Roads Investment Program.7 R&B

6   ADB’s approach and procedures regarding delayed submission of audited project financial statements:
      (i) When ADB does not receive the audited project financial statements by the due date, ADB will write to the
            executing agency to inform it that (a) the audit documents are overdue; and (b) if they are not received within
            the next 6 months, requests for new contract awards and disbursement such as new replenishment of advance
            accounts, processing of new reimbursement, and issuance of new commitment letters will not be processed.
      (ii) When ADB does not receive the audited project financial statements within 6 months after the due date, ADB
            will withhold processing of requests for new contract awards and disbursement such as new replenishment of
            advance accounts, processing of new reimbursement, and issuance of new commitment letters. ADB will
            inform the executing agency (a) of ADB’s actions and (b) that the loan may be suspended if the audit
            documents are not received within the next 6 months.
      (iii) When ADB does not receive the audited project financial statements within 12 months after the due date, ADB
            may suspend the loan.
7   ADB. 2011. Report and Recommendation of the President to the Board of Directors on Proposed Multitranche
    Financing Facility to India for North Eastern State Roads Investment Program. Manila (Loan 2770-IND, $74.8 million,
    approved on 22 August 2011).
13

department undertook the recruitment of consultants and contractor in accordance with ADB
Guidelines. Upon approval of advance contracting under the proposed PRF by ADB, R&B
department has successfully completed recruitment of consulting firm following ADB’s
Procurement Regulations, which demonstrate adequate capacity of the executing agency to
recruit consulting services. The consultants recruited under PRF will further support R&B
department and enhance their procurement capacity.

A.     Advance Contracting and Retroactive Financing

20.     Advance contracting. All advance contracting will follow ADB Procurement Policy:
Goods, Works, Non- consulting and Consulting Services (2017, as amended from time to time)
and Procurement Regulations for ADB Borrowers: Goods, Works, Non- consulting and Consulting
Services (2017, as amended from time to time). The issuance of consulting services recruitment
notice under advance contracting will be subject to ADB approval. ADB has advised the borrower,
R&B department and PMU of Government of Sikkim that approval of advance contracting does
not commit ADB to finance the PRF assistance.

21.     Retroactive financing. Withdrawals from the loan account may be made to finance
eligible expenditures incurred under the PRF before the effective date, but not earlier than 12
months before the date of the loan agreement for this PRF, in connection with items to be
retroactively financed, subject to a maximum amount equivalent to 20% of the loan amount

B.     Procurement of Consulting Services

22.      Government of Sikkim has selected a consulting firm as detailed project report consultants
(DPRC) following the ADB Procurement Policy and its associated project administration
instructions and/or staff instructions. The DPRC consulting firm has been procured on quality-
and cost-based selection (QCBS) method with quality-cost ratio of 80:20, to ensure high quality
of technical outputs under PRF assistance. DPRC will assist R&B department, Government of
Sikkim in feasibility studies and preparation of detailed project report for roads and bridges in
Sikkim. The duration of assignment for the DPRC consulting firm would be 36 months with 202
person-months inputs of key experts. DPRC is expected to be mobilized from December 2020
(will be further confirmed during contract negotiation process).

C.     Procurement of Goods and Civil Works

23.  Procurement of goods and civil works for pilot-testing is not envisaged under the proposed
PRF.

D.     Procurement Plan

24.   One consulting firm is envisaged under the PRF and has been selected upon approval of
advance contracting by ADB.

E.     Consultant's Terms of Reference

25.     The detailed TOR for expected outputs of the consulting services package (DPRC
consulting firm) recruited by the PRF executing agency– R&B department, Government of Sikkim
has been agreed with ADB (Appendix 2). The consulting services would cover: (i) initial screening
of the tentative list of candidate roads and bridges; (ii) feasibility studies of the shortlisted roads
for final selection; (iii) detailed design for selected road and bridge subprojects, including the
environmental and social safeguard assessments and preparation of environmental and social
safeguard planning documents, preparation of realistic cost estimate benchmarking with contracts
14
of similar nature and conditions, economic analysis, due diligence and capacity building on
financial management, assistance and capacity building on procurement including streamlining
the decision making processes, preparation of bid documents and supporting the bidding process
until contract award; and (iv) providing assistance in sector analysis and developing the road
maintenance, road safety, and institutional strengthening, capacity development component and
preparation of gender analysis and gender equality and social inclusion plan for incorporation of
gender elements in the design of the ensuing project.

                                     VI.     SAFEGUARDS

26.     Sikkim has a mountainous terrain and forest zones, and it is likely that some sections of
the selected roads may pass through forest areas. However, the project will avoid subprojects in,
or close to, national parks, wildlife sanctuaries, or any other environmentally sensitive areas. The
environmental impacts under the selected subprojects may not be major and are expected to be
minimized to an acceptable level through mitigation measures. The environment safeguard
category is taken as B.

27.     The social safeguard categorization is taken as B, as the population of Sikkim is small and
road sections passing through hilly terrain are less likely to pass through populated areas
requiring significant resettlement and land acquisition. If the subproject would have any impact on
the indigenous peoples, those are expected to be limited. Improvement of the roads is expected
to have positive impacts on social and economic life for the population in the subproject influence
zone including the indigenous peoples. The indigenous peoples category is taken to be B.

28.    Prohibited investment activities. Pursuant to ADB’s Safeguard Policy Statement
(2009), ADB funds may not be applied to the activities described on the ADB Prohibited
Investment Activities List set forth in Appendix 5 of the Safeguard Policy Statement.

                            VII.    PERFORMANCE MONITORING

A.     Monitoring

29.      Project readiness financing project performance monitoring. Roads and Bridges
(R&B) Department, Government of Sikkim (the EA) will monitor PRF assistance performance
semiannually and provide consolidated reports to ADB. These reports will include (i) each
activity’s progress measured against the implementation schedule; (ii) key implementation issues
and solutions; (iii) an updated implementation plan. To ensure PRF assistance continue to be
both viable and sustainable, the EA should adequately review project financial statements of PRF
assistance and the associated auditor's report. In the event that an ensuring loan is not approved,
the EA will submit a project completion report to represent the performance of completed PRF, to
ADB within 6 months of physical completion of PRF project.

30.     Compliance monitoring. The EA will monitor compliance of loan covenants, including
that relating to policy, legal, financial, economic, environmental, and others and ensure
compliance with loan covenants and assurances. All non-compliance issues, if any, will be
updated in quarterly progress reports together with remedial actions. ADB review missions will
also monitor the status of compliance with loan covenants and raise the noncompliance issues
with the EAs and agree on remedial action.

B.     Reporting

31.    The EA will provide ADB with:
15

          (i)      quarterly progress reports on the PRF assistance in a format consistent with ADB's
                   project performance reporting system;
          (ii)     reports prepared by the consultants under the PRF assistance;
          (iii)    consolidated annual reports, including (a) progress achieved by output measured
                   against the performance targets, (b) key implementation issues and solutions, and
                   (c) an updated implementation plan for the next 12 months; and
          (iv)     project accounts of PRF assistance, audited financial statements (AFSs), and the
                   associated auditor’s report.

                                         VIII.    ANTICORRUPTION POLICY

32.     The Government of India, the State Government of Sikkim and other implementing
agencies are advised of ADB’s Anticorruption Policy (1998, as amended to date). Consistent with
its commitment to good governance, accountability, and transparency, implementation of the
project shall adhere to ADB’s Anticorruption Policy. ADB reserves the right to investigate, directly
or through its agents, any violations of the Anticorruption Policy relating to the PRF project
following ADB’s Integrity Principles and Guidelines. All contracts financed by ADB will include
provisions specifying ADB’s right to audit and examine the records and accounts of the executing
agency and all PRF project contractors, suppliers, consultants, and other service providers. This
includes the examination of project outputs, assets, and all other information that may be
considered relevant for audit or inspection by ADB regardless of project completion, termination,
or cancellation. Firms or individuals on ADB’s anticorruption debarment list are ineligible to
participate in activities that are financed, supported, or administered by ADB; and may not be
awarded any contracts under the PRF project.8 Investigation of Government officials, if any, will
be requested by ADB to be undertaken by the Borrower.

33.     To support these efforts, relevant provisions of ADB’s Anticorruption Policy are included
in the project readiness loan agreement and any bidding documents under the PRF assistance.

                                   IX.           ACCOUNTABILITY MECHANISM

34.     People who are, or may in the future be, adversely affected by the PRF assistance may
submit complaints to ADB’s Accountability Mechanism. The Accountability Mechanism provides
an independent forum and process whereby people adversely affected by ADB-assisted PRF
assistance can voice and seek a resolution for their problems, as well as report alleged violations
of ADB’s operational policies and procedures. Before submitting a complaint to the Accountability
Mechanism, affected people should make an effort in good faith to solve their problems by working
with the concerned ADB operations department. Only after doing that, and if they are still
dissatisfied, should they approach the Accountability Mechanism.9

         X.       RECORD OF CHANGES TO THE PROJECT ADMINISTRATION MANUAL

35.     All revisions and/or updates during implementation of project readiness loan should be
retained in this section to provide a chronological history of changes to implemented
arrangements recorded in the PAM, including a revision to contract awards and disbursement S-
curves.

8   ADB. Anticorruption and Integrity.
9   ADB. Accountability Mechanism.
16

                                                                                                   Appendix 1

                                        Indicative List of Subprojects

      S. No.                          Name of the Road                                     Length (km)
         1         Damthang - Ravangla                                                        12.35
         2         Rangpo - Duga - Pendam                                                     14.64
         3         Ravangla - Yangang                                                         13.97
         4         Duga - Pacheykhani                                                         11.04
         5         Rongli Road (Kingstone) - Rongli                                            9.17
         6         Machong - Rangpo Khola - Rolep                                               14
         7         Sombarey - Hilley                                                          25.13
         8         Legship (Gangtok more) - Tashiding Gumpa Phatak                            14.21
         9         Melli - Phong via Ratepani                                                  22.9
        10         Ravangla - Ralang                                                            13
        11         YangYang - Kimbubotey                                                      16.62
        12         Namboo - Chingtapu (Nepal Border)                                            20
        13         Sopakha - Chewabhanjyang (Nepal Border)                                      18
        14         Sang – Sirwani                                                              9.93
        15         Darap – Namboo                                                              7.24
        16         Namlung - Zorong - Tashiding Road                                            15
        17         Chongrang Kongri Labdang                                                     19
        18         Sang Khola Zingla                                                             8
        19         Sang Dipu Dara                                                               15
        20         Khamgdong Lingey Tinket (KLT)                                                22
     Bridges
      S. No.       BRIDGES                                                                    SPAN
         1         Steel bridge over Limu Khola along Darap Namboo road                        35 m
         2         Bridge over Kali Khola- Ranka- Sichey road Km 7th                           35 m
         3         Seti Khola Ranka- Sichey road Km 6th                                        20 m
         4         Sim Khola Ranka- Sichey road km 3rd                                         15 m
         5         Ghattey Khola Namchi- Rong- Sumbuk road Km 4th                              20 m
         6         Singh Khola Phongla- Bermiok road Km 9th Ch 23rd                            20 m
         7         Siring Khola Phongla- Bermiok road Km 12th Ch 30th                          20 m
         8         Budhang Khola Ralang- Phamtham road Km 14th                                 20 m
         9         Bhaley Khola Sirsiray- Kalung Dara                                          40 m
        10         Kali Khola Passi- Ketang                                                   : 65 m
        11         Sangpu Khola                                                                40 m
        12         Ringtam Khola Ringhim Nampatam road                                         20 m

Note: The list will be reviewed in consultation with the executing agency and may undergo some changes.
17

                                                                                         Appendix 2

                       DETAILED TERMS OF REFERENCE (TOR)
                          FOR CONSULTING SERVICES FOR
     FEASIBILITY STUDIES AND PREPARATION OF DETAILED PROJECT REPORT FOR
                           ROADS AND BRIDGES IN SIKKIM

A.     General

1.      The proposal for up-gradation of major and other district roads and construction of bridges
in Sikkim is being considered through Asian Development Bank (ADB) funding. The scope of the
project includes up-gradation of major district roads, other district roads and replacement of weak
bridges thus creating a sound network of roads in the State with adequate linkage to the national
highway and state highway network and connectivity to important towns, commercially important
rural areas, pilgrimage and other tourist destinations in the State. The selection of roads and
bridges to be taken up under the project and further project preparation including feasibility studies
and preparation of detailed project report is yet to be taken up. Apart from the investment
component, the proposed project will assist in strengthening institutional arrangements for road
maintenance and strengthening institutional capacity of Road and Bridges (R&B) Department,
Government of Sikkim.

2.      R&B Department, Government of Sikkim will be the employer and executing agency for
the consultancy services. R&B Department has prepared a tentative list of candidate roads and
bridges for initial screening and undertaking further studies for the final selection and the
preparation of detailed project report for the selected roads and bridges. R&B Department now
invites proposal for Consulting Services for undertaking Feasibility study and Preparation of
Detailed Project Report for roads and bridges in Sikkim. The cost of the Consulting Services is
proposed to be funded through ADB loan and is subject to approval of the loan by ADB. The
selected roads and bridges for which the detailed project report and detailed design have been
undertaken may be funded under one or more loans by ADB or through other funding
mechanisms.

Objectives and Scope

Objective

3.      The main objective of the consultancy services is to (i) establish technical, social,
environmental and economic viability of the road and bridge projects and prepare detailed project
reports for upgradation of major and other district roads and construction of bridges for the viable
and selected projects after undertaking initial screening of the tentative list of candidate roads and
bridges; and (ii) develop an institutional development and capacity building component for R&B
department and strengthening institutional arrangements for road maintenance under the
proposed project; and (iii) capacity building of R&B Department.

Scope of Services

4.     The Consultant reporting to the R&B Department will work under the overall guidance,
technical control, and direction of the designated Project Director. The Consultants will undertake:
       (a)     initial screening of the tentative list of candidate roads and bridges (about 400km
               including bridges on the candidate roads, if any and about 12 other bridges
               (cumulative span of 300meters); [As shown in Annexure-I]
18
       (b)     feasibility studies of the shortlisted roads (about 220-250km bridges on the
               candidate roads, if any, and about 8 to 10 other bridges (cumulative span of 220-
               250 metres) for final selection;
       (c)     detailed design for selected road (about 150Km including bridges on the candidate
               roads, if any) and about 8 other bridges (cumulative span of 250m);
       (d)     the above work includes the environmental and social safeguard assessments and
               preparation of environmental and social safeguard planning documents,
               preparation of realistic cost estimate benchmarking with contracts of similar nature
               and conditions, economic analysis, due diligence and capacity building on financial
               management, assistance and capacity building on procurement including
               streamlining the decision making processes and the use of e-procurement or
               phased adoption of e-procurement system, preparation of bid documents and
               supporting the bidding process until contract award; and
       (e)     providing assistance in sector analysis and developing the road maintenance, road
               safety, and institutional strengthening and capacity development component of the
               project. The subproject will be carefully selected and designed keeping into
               consideration the existing local hazard maps or actual surveys. Disaster risk and
               climate change will be taken into consideration in the design of resilient/all-weather
               roads. The detailed scope of services is given in the sections that follow. However,
               the entire scope of services would, inter-alia, include the items mentioned in the
               Letter of Invitation and the TOR. The standards of output required from the
               appointed consultants are of international level both in terms of quality and
               adherence to the agreed time schedule.

Engineering Studies and Detailed Design

5.     The engineering studies and detailed design is divided into three parts:

       (i)     initial screening of the tentative list of candidate roads and bridges;
       (ii)    feasibility studies of the shortlisted roads for final selection; and
       (iii)   detailed design for selected road and bridge subprojects.

6.      The viability of the project shall be established taking into account the requirements with
regard to rehabilitation, upgrading and improvement based on highway design, pavement design,
bridge design, protection works and other improvement and safety measures, as necessary,
quantities of various items of works and cost estimates vis-à-vis the economic analysis within the
given time frame. The Detailed Project Report would inter-alia include detailed highway design,
design of pavement and overlay, drainage studies and design, design of protection works, design
of slope stabilization works, design of bridges and cross drainage structures, road safety audits,
quantities of various items, detailed working drawings, detailed cost estimates, economic and
financial viability analyses, environmental and social feasibility, social and environmental action
plans as appropriate and documents required for bidding for the project as per ADB Guidelines
and standard bidding documents. Disaster risk and climate change will be taken into consideration
in the design of resilient/all-weather roads and bridges. The Consultants shall ensure detailed
project preparation incorporating aspects of value engineering, quality audit and safety audit
requirement in design and implementation.

7.      Sikkim is prone to a multitude of natural hazards such as earthquakes and earthquake
induced landslides; and climate- and weather-related hazards, such as precipitation induced
landslides, floods cloudbursts, flash floods. These are likely to increase with increasing frequency
of heavy precipitation due to climate change. The frequency and magnitude of drought events are
also likely to increase. The sensitivity of project components would largely depend on location,
19

system design and specifications, materials, safety plans and procedures, maintenance regime,
and investments.

8.     The Consultants will particularly take the following into account to design disaster and
climate change resilient all-weather roads and bridges:

       i.      Sites should be carefully selected with reference to existing local hazard maps or
               actual surveys.
       ii.     Disaster risk and climate change will be taken into consideration in the design of
               resilient/all-weather roads and bridges.
       iii.    The subproject will be designed and executed as seismic resistant structure in
               accordance with relevant national standards, as applicable.
       iv.     The design and construction standards will be raised to appropriate level. The
               revised high flood levels of the rivers or the natural streams or drainage channels
               shall be considered, while designing facilities, as applicable. Geotechnical studies
               shall be undertaken and slope stabilization measures considered for slide zones,
               wherever applicable.
       v.      Detailed engineering design for roads and bridges will address slope instability
               problems and shortages of good construction material.
       vi.     Climate mitigation and climate adaptation cost will be estimated.
       vii.    Chronic landslide zones will be identified and mapped and specialized
               technological solutions for slope stabilization and protection will be provided.

Part-I Initial screening of the tentative list of candidate roads and bridges

9.       The Consultant will undertake a review and screening of the tentative list of candidate
road and bridge subprojects prepared by R&B Department attached as Annexure 1. The review
and screening will be carried out through (i) review of all available reports and published
information about the tentative list of candidate road and bridge subprojects and the project
influence area including the Land Transport Management and Master Plan for Sikkim (Final
Report - May 2012) prepared under ADB Technical Assistance (TA 7538-IND);
(ii) reconnaissance survey in the field; and (iii) discussions with the officials of R&B Department.
The Consultant may devise a simplified selection criterion to facilitate the preparation of a short
list of candidate road and bridge subprojects in consultation with R&B Department. Subprojects
in or close to, national parks, wildlife sanctuaries, or any other environmentally sensitive areas
should be avoided. Subprojects passing through populated areas requiring significant
resettlement and land acquisition should also be avoided. Based on the review and initial
screening, the Consultant will finalize a shortlist of candidate road and bridge subprojects in
consultation with the R&B Department for taking up the feasibility study for the final selection of
the roads.

Part-II: Feasibility Study for Shortlisted candidate roads and bridge subprojects

10.    The Consultant will undertake a feasibility study for the shortlisted candidate road and
bridge subprojects for the final selection of the roads.

       The Scope of Services shall cover but be not limited to the following major tasks:

       i.      review of all available reports and published information about the project road and
               the project influence area;

       ii.     detailed reconnaissance and preliminary topographic surveys;
       iii.    road inventory and condition surveys;
20
       iv.      inventory of bridges, culverts and structures;
       v.       preliminary material and geotechnical investigation;
       vi.      identification of possible improvements in the existing alignment,
       vii.     preliminary traffic studies including traffic surveys and demand forecasting;
       viii.    preliminary environmental and social impact analyses;
       ix.      preliminary proposals and design for upgradation of roads and bridges;
       x.       strip plan indicating the scheme for carriageway widening, location of all existing
                utility services (both over- and underground) and the scheme for their relocation,
                trees to be felled and planted and land acquisition/resettlement requirements;
       xi.      project costing;
       xii.     economic analyses;
       xiii.    Reports, documents and drawings.

11.     The detailed Scope of Services and the methodology for achieving the objective are
described in the pages that follow. The Consultants are to follow the relevant portions of this TOR
for the Part-II Feasibility Study corresponding to the Scope of Services.

Part-III Detailed design for selected road and bridge subprojects

12.    The following sections describe the scope of services to be undertaken for the detailed
design of the subprojects. The detailed design will be undertaken for (i) 150 km of roads including
bridges, if any and, (ii) 08 (eight) bridges (on other roads) of cumulative span of about 220-250m.

13.    Scope of Services shall cover but not be limited to the following major tasks:

       (i)      Review of all available reports and published information about the candidate
                subprojects and the project influence area;
       (ii)     Environmental, poverty and social impacts, including those related to cultural
                properties, indigenous people natural habitats, involuntary resettlement etc.;
       (iii)    Public consultation, including consultation with Communities located along the
                road, NGOs working in the area, other stake-holders and relevant Government
                departments at different stages of assignment;
       (iv)     Detailed reconnaissance;
       (v)      Identification of possible improvements in the existing alignment;
       (vi)     Traffic studies including traffic surveys and axle load survey and demand
                forecasting;
       (vii)    Inventory and condition surveys for road, bridges, cross-drainage structures and
                drainage provisions;
       (viii)   Detailed topographic surveys using Total Stations and GPS;
       (ix)     Pavement investigations ;
       (x)      Sub-grade characteristics and strength: investigation of required sub-grade and
                sub-soil characteristics and strength for road and embankment design and sub soil
                investigation;
       (xi)     Identification of sources of construction materials;
       (xii)    Road safety audit to identity areas of major concern, including black spots, and
                measures to be taken for improving detailed engineering design with respect to
                road safety;
       (xiii)   Preliminary proposal for rehabilitation / widening including shoulder composition
                and cross-section details;
       (xiv)    Detailed design for rehabilitation / widening of road;
       (xv)     Detailed design for rehabilitation/widening/reconstruction of bridges, cross
                drainage;
21

       (xvi)   Identification of the type and the design of intersections;
       (xvii)  Design of complete drainage system and disposal point for storm water;
       (xviii) Value analysis / value engineering and project costing;
       (xix)   Economic analyses;
       (xx)    Strip plan indicating the scheme for carriageway widening, location of all existing
               utility services (both over- and underground) and the scheme for their relocation,
               trees to be felled and planted;
       (xxi) Preparation of project report, cost estimate, rate analysis, detailed bill of quantities;
       (xxii) Bid documents for execution of civil works;
       (xxiii) Preparation of resettlement plans for the project affected people as per ADB
               guidelines and Govt. of India R & R Policy and assessment of the land acquisition
               requirements;
       (xxiv) Preparation of initial environmental examination and environmental management
               plan.

14.    While carrying out the field studies, investigations and design, the development plans
being implemented or proposed for future implementation by the local bodies, shall be taken into
account. Such aspect shall be clearly brought out in the reports and drawings.

15.    The details of the tasks to be undertaken are described in following paragraphs.

       Standards and Codes of Practices

16.     All activities related to field studies, design and documentation shall be done as per the
latest guidelines/ circulars of Ministry of Road Transport and Highways (MORTH) and relevant
publications of the Indian Roads Congress (IRC) and Bureau of Indian Standards (BIS). For
aspects not covered by IRC and BIS, international standard practices, such as, British and
American Standards may be adopted. The Consultants upon award of the Contract may reflect
the same in the inception report.

       Quality Assurance Plan (QAP)

17.     The Consultants shall have detailed Quality Assurance Plan (QAP) for all field studies
including topographic surveys, traffic surveys, engineering surveys and investigations, design,
analyses and documentation activities. The draft detailed QAP Document must be discussed and
finalized with the officers concerned immediately upon the award of the Contract and submitted
as part of the inception report.

       Traffic Survey

18.     The Consultants shall undertake necessary surveys for classified traffic volume count,
origin-destination and commodity movement, characteristics axle loading, characteristics
intersection volume count, speed-delay characteristics, pedestrian/animal crossing. The
Consultants shall, immediately upon award of the work, submit to PMU, proposals regarding the
total number as well as the locations of the traffic survey stations as part of at each stage. Suitable
maps and charts should accompany the proposals clearly indicating the rationale for selecting the
location of survey stations. The methodology of collection and analysis of data, number and
location of traffic survey stations shall be finalized in consultation with PMU/PIU.

       Traffic Demand Estimates

19.     The Consultants shall make traffic demand estimates and establish possible traffic growth
rates in respect of all categories of vehicles, taking into account the past trends, annual population
22
and real per capita growth rate, elasticity of transport demand in relation to income and estimated
annual production increase. The methodology for traffic demand estimates shall be finalized by
the Consultants in consultation with PMU/PIU. Overall traffic forecast thus made shall form the
basis for the design of each pavement type and other facilities/ancillary works.

Engineering Surveys and Investigations

       Reconnaissance and Alignment

20.     The Consultants shall make an in-depth study of the available land width (ROW),
topographic maps, and other available relevant information collected by them concerning the
existing alignment. The Consultants in coordination with the PMU will arrange the required maps
and the information needed by them from the potential sources. The detailed ground
reconnaissance may be taken up immediately after the study of maps and other data. The primary
tasks to be accomplished during the reconnaissance surveys include:

       (i)      Topographical features of the area;
       (ii)     Typical physical features along the existing alignment within and outside ROW i.e.
                land use pattern;
       (iii)    Scheme for the widening of the existing road;
       (iv)     Realignment requirements;
       (v)      Preliminary identification of improvement requirements including treatments and
                measures needed for the cross-roads;
       (vi)     Traffic pattern and preliminary identification of traffic homogenous links;
       (vii)    Sections through congested areas;
       (viii)   Inventory of major aspects including land width, terrain, pavement type,
                carriageway type, bridges and structures (type, size and location), intersections
                (type, cross-road category, location) urban areas (location, extent), geologically
                sensitive areas, environmental features;
       (ix)     Critical areas requiring detailed investigations; and,
       (x)      Requirements for carrying out supplementary investigations;
       (xi)     Soil (textural classifications) and drainage conditions;
       (xii)    Type and extent of existing utility services along the alignment (within ROW).

21.    The data derived from the reconnaissance surveys will be utilized for planning and
programming the detailed surveys and investigations. All field studies including the traffic surveys
should be taken up on the basis of information derived from the reconnaissance surveys.

       Topographic Surveys

22.    The basic objective of the preliminary topographic survey would be to capture the essential
ground features along the alignment in order to consider improvements and for working out
improvements, rehabilitation and upgrading costs. The detailed topographic surveys should be
taken up after the completion of reconnaissance surveys. The field surveys shall be carried out
using high precision instruments i.e. total station, auto level etc.

       Details of Utility Services and Other Physical Features

23.    The Consultants shall collect details of all important physical features along the alignment.
These features affect the project proposals and should normally include buildings and structures,
monuments, burial grounds, cremation grounds, places of worship railway lines, stream / river /
canal, water mains, severs, gas/ oil pipes, crossings, trees, plantations, utility services such as
You can also read