Pricing Methodology Electricity Distribution Network - Pursuant to the Electricity Distribution Information Disclosure Determination 2012.

Page created by Corey Dixon
 
CONTINUE READING
Pricing Methodology
Electricity Distribution Network
Pursuant to the Electricity Distribution Information Disclosure Determination
2012.

Effective from 1st April 2022
EA Networks                                                                 Electricity Distribution Network Pricing Methodology 2022-23

Contents
1.     Introduction ......................................................................................................................... 5
     1.1.    Purpose ................................................................................................................................................. 5
     1.2.    About EA Networks ............................................................................................................................... 5
2.     Summary of current revenue and pricing............................................................................... 6
     2.1.    Target revenue for 2022-23 .................................................................................................................. 6
     2.2.    Key change to prices this year ............................................................................................................... 6
     2.3.    Average change in prices for 2022-23 ................................................................................................... 7
     2.4.    Summary of revenue and cost .............................................................................................................. 7
3.     Overview of pricing methodology ......................................................................................... 9
     3.1.    Managing consumer impacts of pricing changes ................................................................................ 11
4.     Pricing considerations and objectives .................................................................................. 12
     4.1.    Regulatory context .............................................................................................................................. 12
     4.2.    Network context ................................................................................................................................. 12
     4.3.    Overview of Network Assets & Network Characteristics .................................................................... 13
     4.4.    Customer context ................................................................................................................................ 15
     4.5.    Consumer consultation ....................................................................................................................... 15
     4.6.    Feedback ............................................................................................................................................. 16
5.     Pricing methodology ........................................................................................................... 17
     5.1.    Background ......................................................................................................................................... 17
     5.2.    What our pricing covers ...................................................................................................................... 17
     5.3.    Future pricing approach ...................................................................................................................... 18
     5.4.    Pricing philosophy ............................................................................................................................... 19
     5.5.    Pricing development activities ............................................................................................................ 20
     5.6.    Our approach to developing prices ..................................................................................................... 20
     5.7.    Price development process ................................................................................................................. 21
     5.8.    Target Revenue and costs determined ............................................................................................... 22
     5.9.    Segment connections into Customer Load Groups ............................................................................. 23
     5.10.   Allocate costs across Customer Load Groups ..................................................................................... 24
     5.11.   Pass-through and Transmission costs ................................................................................................. 24
     5.12.   Administration costs ........................................................................................................................... 25
     5.13.   Operations and Maintenance, Depreciation and Return on Investment costs .................................. 25
6.     Detail on connection segmentation approach...................................................................... 26
     6.1.    Your Customer Load Group selection ................................................................................................. 26
     6.2.    General ................................................................................................................................................ 27
     6.3.    Irrigation .............................................................................................................................................. 30
     6.4.    Industrial ............................................................................................................................................. 32

                                                                                                                                                 Page 2 of 50
EA Networks                                                                Electricity Distribution Network Pricing Methodology 2022-23

     6.5.    Large User ........................................................................................................................................... 33
     6.6.    Large Generation................................................................................................................................. 34
7.     Other information .............................................................................................................. 36
     7.1.    Low fixed charge regulation ................................................................................................................ 36
     7.2.    Non-standard contracts ...................................................................................................................... 36
     7.3.    Capital contributions ........................................................................................................................... 36
     7.4.    Discretionary discounts and dividends ............................................................................................... 37
APPENDIX A – Alignment with Electricity Authority Pricing Principles .......................................... 38
APPENDIX B – Alignment with Commerce Commission Information Disclosure ............................ 42
APPENDIX C – Pricing Schedule 2022-23...................................................................................... 49
APPENDIX D – Directors’ certification ......................................................................................... 50

                                                                                                                                              Page 3 of 50
EA Networks                                 Electricity Distribution Network Pricing Methodology 2022-23

Definitions and common acronyms

                      The hardware, equipment or plant that is part of our electricity
 Assets
                      distribution network.

                      Electricity supply for which we temporarily cease supply when required,
 Controlled Energy    typically during periods of high load. It is most commonly water heating
                      load.

 Customer             An end user who is connected to the electricity distribution network.

 Customer Load        The customer segments that have similar electricity requirements and
 Groups               that share similar pricing methodologies.

                      Grid exit Point. This is the point where EA Networks’ electricity
 GXP
                      distribution network connects to Transpower’s transmission network.

                      Installation Control Point. This is the isolation point where a customer
 ICP                  connects to the distribution network and where the retailers metering is
                      located.

 kW                   Kilowatt. The measure of electrical capacity.

                      Kilowatt-hour. The measure of electricity consumption by which retail
 kWh
                      electricity consumption is measured.

                      Kilovolt Ampere. A unit of measure for how much power is being provided
 kVA
                      through a business or home’s electrical circuits or technology.

 Retailer             The entity that charges customers for their electricity usage.

                      Regional Coincident Peak Demand. This affects the way that Transpower
 RCPD
                      allocates interconnection cost.

                      The forecasted annual revenue we expect to earn as determined under
 Target Revenue
                      the Default Price Path rules and guidelines.

                      Transmission costs are comprised of charges directly from Transpower,
 Transmission costs   Avoidable Cost of Transmission paid to Generators (now ceased), and
                      recoverable costs including regulatory levies and local authority rates.

                      Weighted Average Cost of Capital. This is the measure of the return an
 WACC                 Electricity Distribution company may achieve under the Default Price Path
                      regulations set by the Commerce Commission.

                                                                                        Page 4 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

1. Introduction
1.1. Purpose
The purpose of this document is to detail how EA Networks develops the prices it charges for
connection to, and use of, the network.

1.2. About EA Networks
EA Networks is the trading name of Electricity Ashburton Limited. We own and operate the
electricity distribution network located in Mid Canterbury. We are a consumer owned cooperative
with every connected customer entitled to own shares in the company.

Our network delivers electricity to households and businesses across an area of about 3,500km2,
between the Rangitata River in the south, the Rakaia River in the north and the foothills of the
Southern Alps in the west. Three distribution lines run into up-river gorges through the foothills.

                                                       From a network engineering perspective there
                                                       are two general network designs; rural and
                                                       urban.

                                                       The rural distribution network configuration is
                                                       predominantly long radial overhead feeders
                                                       with some interconnection to adjacent feeders
                                                       and substations.

                                                       The urban 11kV distribution network is based
                                                       upon a similar principle to the rural
                                                       arrangement, except the network is largely
                                                       underground cable, the interconnections are
                                                       more frequent, and the overall feeder lengths
                                                       are significantly shorter.

                                                       There are four hydro generating stations
                                                       embedded in the network. Lavington is
                                                       0.5MW, Cleardale is 1MW station, Montalto is
                                                       1.6MW station and Highbank is 28MW station.

                                                                                            Page 5 of 50
EA Networks                                          Electricity Distribution Network Pricing Methodology 2022-23

2. Summary of current revenue and pricing
We have reviewed our pricing against the Commerce Commission’s (Commission) Default Price Path
(DPP) requirements. The pricing approach is in-line with previous years with the main exception being
changes to our ‘General’ load group brought about by changes to low fixed charge regulations.

Gross prices will reduce on average for 2022-23 compared to 2021-22 because forecast chargeable
quantities provide an uplift in revenue. When balanced against our regulated allowable revenue,
average overall prices reduce.

2.1. Target revenue for 2022-23
Target revenue for 2022-23 is $41.7 million, representing a $0.6 million, or 1.4% increase from $41.2
million in 2021-22. The target revenue for 2022-23 is set to recover:

      •    $33.6 million for delivering Distribution services, representing a $0.5 million or 1.5% increase
           from 2021-22.
      •    $8.2 million for pass-through and Transmission costs, representing a $0.07 million or 0.8%
           increase from 2021-22.

2.2. Key change to prices this year
During 2021 the Government announced changes to the low fixed charge regulation1 (LFC). We have
implemented changes to our equivalent LFC load group (General Supply 20 – GS20) and intend to
mirror the glide path to phase out LFC prices set by the regulations.

Introducing the revised fixed price of $0.30 per day for 2022/23 (increasing from $0.15 per day) has
required changes to all other tariffs within the General supply category to maintain the same
revenue requirement from each. We have also reduced the variable rate to ensure that, in
aggregate, the changes are revenue neutral for all categories.

We expect to continue to align GS20 with the glide path set by the revised regulations, increasing
the fixed price to match those detailed in the regulations (i.e., increasing the fixed rate by 15 cents
each year through to 1st April 2026 (from 1st April 2027 the regulation will be removed).

This is discussed further in Section 6.2 General Customer Load Group information and Section 7.1
Low fixed charge regulation.

There have been no other significant changes to our prices or our Pricing Methodology.

1   Electricity (Low Fixed Charge Tariff Option for Domestic Consumers) Regulations 2004

                                                                                                 Page 6 of 50
EA Networks                                              Electricity Distribution Network Pricing Methodology 2022-23

More detail on the change to target revenue for 2022-23 compared to 2021-22 is shown here:

 Target revenue, $000                        2022-23              2021-22          $ change           % change

 Distribution services                         $33,560              $33,052           $508                  1.5%

 Pass-through and
                                                $8,179                 8,114           $65                  0.8%
 transmission costs

 Target Revenue                                $41,739              $41,166           $573                  1.4%

2.3. Average change in prices for 2022-23
Prices for each Customer Load Group, in aggregate, will on average reduce for 2022-23 by 0.1%
(compared to 2021-22) largely due to an increase in forecast chargeable energy quantities that will
help recover revenue. The average aggregate change for each Customer Load Group is shown here:

 Customer Load Group                                                                         Average change %
   General                                                                                           0.1%
   Irrigation                                                                                       -0.3%
   Industrial                                                                                        0.5%
   Large Users                                                                                       0.0%
   Generation                                                                                       -0.1%
 Average change – all groups                                                                        -0.1%

Note: For this Table the Large User Customer Load Group includes Streetlighting.

2.4. Summary of revenue and cost
The following tables provide an overview of our revenue recovery by customer type, as well as a
breakdown of major cost types and more detail on recoverable pass-through costs.

                                                                                                     Page 7 of 50
EA Networks                                    Electricity Distribution Network Pricing Methodology 2022-23

Target Revenues by Customer Load Group
This table shows how total Target Revenue for 2022/23 is recovered by Customer Load Group.

 Customer Load Group                              Connections              Target revenue ($000)
   General                                           18,814                        $19,841
   Irrigation                                         1,615                        $18,382
   Industrial                                            42                         $1,754
   Large Users                                           12                         $1,355
   Generation                                             4                           $407
 Total                                               20,487                        $41,739

Target Revenues by Cost Category
This table shows the main costs comprising the Target revenue for 2022-23.
 Cost category                                                               Target revenue ($000)
 Distribution services
   Operations & maintenance                                                          $13,058
   Administration                                                                     $5,574
   Depreciation                                                                      $10,882
   Cost of capital                                                                    $4,046
          Subtotal                                                                   $33,560
 Pass-through costs
   Rates & levies                                                                        $294
 Transmission
   Transmission – connection                                                          $2,004
   Transmission – interconnection                                                     $5,881
   Transmission – subtotal                                                            $7,885
          Subtotal                                                                    $8,179
 Target revenue                                                                      $41,739

Pass-through costs are actual costs. No cost of capital or margin is recovered from these costs.

For 2022-23, the Transmission – interconnection cost includes a $1.0 million early repayment of a
Transpower New Investment Contract. The early repayments are designed to reduce material year-
to-year volatility in transmission – interconnection costs caused by the current transmission pricing
methodology (TPM). The year-to-year volatility was adversely affecting customers, particularly in the
Irrigation Customer Load Group. The volatility in transmission costs is expected to cease with
introduction of the proposed new TPM.

                                                                                           Page 8 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

3. Overview of pricing methodology
EA Networks is an electricity distribution business (EDB). Our costs are largely fixed as we build and
maintain long-life network assets. These assets are designed to enable the delivery of electricity to
connected customers (current and future) in the Mid Canterbury region. We are a non-exempt EDB
meaning we are regulated in terms of prices and quality of supply.

We recover our regulated revenue through prices charged (via electricity retailers) to customers that
are connected to the electricity network. Where possible, we aim to provide a fixed price signal
reflecting the cost to deliver capacity to customers, albeit that a proportion of our revenue is
recovered from variable price structures, largely due to current regulations.

The prima facie strategy to develop prices is to reflect and recover as accurately as feasible the cost
of providing network services to connected customers. In general terms, the greater the capacity
(the level of demand) required by a customer, the greater the cost to provide network service to the
customer. This is because the fixed cost of infrastructure required to meet greater demands at a
connection is higher. Put another way, our costs are driven by peak demands (how fast energy is
being used) rather than volume (how much energy is used).

The development of our methodology and the prices that result is based on economic pricing
principles given practical, physical, regulatory and commercial constraints. An overview of the price
development process and pricing methodology is provided here:

     1. Target Revenue and            2. Segment                        3. Allocate costs
     forecast costs                   connections into                  across load groups to
     determined.                      customer load groups              reflect cost drivers

        Validate against                                 Develop cost reflective price
                                       Forecast
       Forecast Allowable                                structures (e.g. $/kW/day) for each
                                      quantities
                                                         load group to efficiently recover costs.
            Revenue

 Overview of Pricing Methodology

Costs are allocated based on segmentation of connected users. The purpose of these segmented
types is to group individual customers into load groups that share similar electricity demand profiles,
capacity requirements and cost drivers – this enables the allocation of network assets by group to
reflect utilisation by that group.

                                                                                            Page 9 of 50
EA Networks                                          Electricity Distribution Network Pricing Methodology 2022-23

There are five broad connection types (some have sub-categories to further delineate capacity
requirements and better reflect cost to serve, such as the General group):

      1. General – households, commercial businesses connected to the low voltage network,
         including single and 3-phase supply.
      2. Irrigation – connections with irrigation pumps (>20kW).
      3. Industrial – industrial/commercial connections.
      4. Large Users – connections with dedicated assets and specific connection requirements2.
      5. Generation – distributed generators (>10kW).

We allocate our costs across these Customer Load Groups based on the assets required to meet
their level of demand needs.

Price components
Prices are applied across a combination of fixed, capacity, and variable price components, depending
on the Customer Load Group. The proportion of total revenue recovered, in aggregate, from each
customer group using fixed, capacity and variable price components is shown here:

                                                       Customer Load Groups
                         General        Irrigation       Industrial      Large Users      Generation      Total
    Fixed                   8%             0%                0%               2%              1%           11%
    Capacity                0%             44%               4%               2%              0%           39%
    Variable               39%             0%                0%               0%              0%           50%
    Total                  48%             44%               4%               3%              1%          100%

    The price components used for pricing for each Customer Load Group are shown here:

    Fixed               $/con/day                                           $/day            $/day

    Capacity                            $/kW/day         $/kVA/day       $/fixture/day

    Variable              $/kWh                                           $/kVA/day

Where possible, we recover costs through fixed charges or capacity charges. However, we must
comply with the Electricity (Low Fixed Charge Tariff Option for Domestic Consumers) Regulations
2004 (‘Low Fixed Charge Regulations’). This regulation requires a low ‘fixed charge’ component to
the pricing design (for 2022/23 this price is $0.30 per day for networks) and therefore the balance of
the revenue requirement must be met through a high variable component for these customers. This
fixed charge, totalling just under $110 per annum for the average residential customer, in no way
reflects or recovers the fixed costs that are associated with delivering electricity network services to
customers who are eligible for this price category. Instead, the regulations drive us to recover, or try
to recover, the true cost to serve these customers via variable energy demand and associated prices.

However, the government recently updated the legislation, establishing a 5-year period before it will
be repealed. During this period a new maximum fixed rate has been defined, allowing EDBs to
charge a higher fixed rate, increasing incrementally over the 5-year period. EA Networks plans to

2Streetlighting costs are allocated to a Streetlighting Customer Load Group. This load group is included in the
Large User Customer Load Group.

                                                                                                 Page 10 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

mirror the prices defined in the legislation. For simplicity we allow all General (GS20) customers
access to the Low Fixed Charge product type and have used it to shape the overall design of the
wider ‘General’ product group.

3.1. Managing consumer impacts of pricing changes
We assess the impact on consumers of each change to price structure and price level. We take
account of the potential that the price change will result in bill shock for a Customer Load Group, or
consumers within a Customer Load Group.

We believe that price stability is important and critical to the efficient running of the local economy,
and our customer research confirms this. Our pricing is designed to minimise volatility between
years across the Customer Load Groups. This is to mitigate bill shock and assist them with efficient
budgeting and planning of electricity expenses.

Price stability is maintained through consistency and our approach to price development. Only when
critical to customers’ needs, regulatory change or for the financial stability of the business, will we
make wholesale changes to our Pricing Methodology. Our upcoming pricing reform work may lead
to changes to the structure of our prices and allocation of our costs to load groups/customer
segments.

Our Customer Load Groups have also been developed to promote price stability and specifically
mitigate price volatility.

      For example: our Irrigation Price is a fixed daily charge based on connected kilowatts (kW)
      (capacity size). This charge is incurred irrespective of usage. We price in this way to ensure
      consistency each year in the price charged to irrigators and to signal to them the fixed costs
      incurred in building the network to meet their demand. If a variable charge was applied, it
      would be challenging to forecast demand and establish appropriate pricing to accurately
      recover our fixed costs. Variable charging would, for this load group, result in volatile prices
      between years.

In addition to load group and price design, our board of directors approve any changes made to
prices and this Pricing Methodology. Prior to any approval, a review is undertaken to firstly ensure
compliance with the Default Price Path (DPP) determination. The board then take a holistic approach
to determining the final changes (if any) to be made. Factors such as the fairness of a change as it
affects our different Customer Load Groups, the ultimate impact on these groups and the financial
position of the company are, amongst other factors, considered. Only when the board of directors is
satisfied that all stakeholders have been considered and fairly treated will a change be approved.

Practically, this means discretion will be applied to a material increase in the level of any price
component of the price structure for any Customer Load Group. Options we have to manage price
shocks include averaging the associated costs across other Customer Load Groups or foregoing a
portion of the Forecast Allowable Revenue.

As with prior years, EA Networks has worked to mitigate price shocks expected from significant
increases in forecast transmission costs (under a proposed new TPM). We have done this by early
repayment of Transpower New Investment Contracts. Early repayment mitigates price volatility by
smoothing total revenue across financial years and reducing potential volatility. At the time of
writing there was no confirmed date for implementation of the proposed new TPM. All repayments
have been based on EA Networks’ best estimate of this.

                                                                                           Page 11 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

4. Pricing considerations and objectives
4.1. Regulatory context
Our pricing is regulated by the Commerce Commission (‘Commission’) under Part 4 of the Commerce
Act and the Electricity Authority under the Electricity Industry Act 2010 and Electricity Industry
Participation Code 2010. These regulations ensure that distribution services are delivered at prices
that are fair and reasonable and at an acceptable quality.

EA Networks’ Pricing Methodology and prices are guided by and comply with regulations and
guidelines governing the electricity industry, including:

    •   Distribution Pricing Principles published by the Electricity Authority (EA).
            o We are expected to set efficient prices consistent with the Authority Pricing
                 Principles published in June 2019. APPENDIX A – Alignment with Electricity Authority
                 Pricing Principles describes how we do this.
            o The EA also released a pricing practice note in 2021.
    •   Electricity Distribution Information Disclosure Determination 2012 (IDD).
            o We are required to disclose information about our pricing approach and prices.
                 APPENDIX B – Alignment with Commerce Commission Information Disclosure
                 describes how we do this.
    •   Electricity (Low Fixed Charge Tariff Option for Domestic Consumers) Regulations 2004.
            o We are required to offer a low fixed charge price option (of not more than 30
                 cents/day) for a consumer’s primary residence.
    •   Electricity Distribution Services Default Price-Quality Path Determination 2020.
            o We are required to set prices to recover no more than the Forecast Allowable
                 Revenue under the DPP determination.
    •   Electricity Industry Participation Code 2010, Part 6 (Connection of Distributed Generation).
            o Sets out requirements for setting prices for distributed generators connecting to and
                 using our network.

4.2. Network context
We have one supply point from the transmission grid. A 33kV and 66kV sub-transmission network
supplies 24 zone substations varying in size from 5 MVA to 40 MVA. The distribution network is a
mixture of 22kV, 11kV and low voltage (LV) with both overhead and underground variants of each.
Overall, the distribution system is about 24% underground cable by circuit length.

The main urban area in the district is Ashburton township, with about 20,000 residents. Smaller
towns of Methven (1,900 people) and Rakaia (1,600 people) are also significant in terms of
residential electricity consumer count. The district has a total population of about 35,000 people.

The area we serve is largely rural land used for cropping and dairy farming and has a high level of
irrigation. Other significant loads are vegetable and meat processing facilities, and a ski-field.

Dramatic load growth has occurred in the Mid-Canterbury region. The summer maximum demand
has more than trebled since 1996 and more than doubled since 2003. The network has peaked at
181 MW twice in the past five years. Irrigation load has doubled since 2005 and now is approaching
an installed capacity of 147 MW. This growth has in-turn driven significant capital development on

                                                                                           Page 12 of 50
EA Networks                                             Electricity Distribution Network Pricing Methodology 2022-23

EA Networks’ network. However, irrigation load growth has now slowed and we do not expect to see
any further growth.

We anticipate uptake of large scale distributed generation and electrification of industrial processes
(heat) and transport to impact our network, though the timing of this remains uncertain.

There is already a large amount of distributed generation on our network, with an installed capacity
of approximately 33 MW, though most capacity is associated with four distributed generators. The
largest Distributed Generation (DG) connection is Highbank, a hydro generator owned by
Trustpower, with 29 MW capacity.

4.3. Overview of Network Assets & Network Characteristics
EA Networks 2021-2031 Asset Management Plan (AMP) comprehensively describes the network
assets and network characteristics. The following overview is from that AMP3:

       Network Inputs and Outputs:

          Maximum Load Demand                    181       MW (Dec 2020)

          Maximum Delivered Energy               607       GWh (2019-20)

          Annual Load Factor                       42      % (2019-20)

          Subtransmission Lines                  422        km

          MV Distribution Lines                2,204        km

          LV Distribution Lines                  473        km

          Distribution Substations             6,581        km

          * Data as at January 2021

       Substations                Peak Load   Load characteristics

          Ashburton                19 MW      Supplies 60% of urban Ashburton and some outlying areas. The
                                              load has a winter peak consisting almost entirely of residential
                                              dwellings.

          Carew                    16 MW      Mostly summer peaking and irrigation based. The high general
                                              demand is a consequence of the large number and size of dairy
                                              sheds. Load exceeds firm capacity.

          Coldstream               16 MW      Load exceeds firm capacity. The high general demand is a
                                              consequence of the large number and size of dairy sheds. The
                                              dominant load is irrigation pumps which are summer peaking.

          Dorie                    11 MW      Summer peaks with irrigation load. The high general demand is a
                                              consequence of the large number and size of dairy sheds.

          Eiffelton                9 MW       Mostly irrigation.

          Fairton                  8 MW       Supplies rural residential, industrial, and irrigation load. The ex-
                                              Silver Fern Farm meat-works are now owned by a vegetable
                                              processing company, and indications have been given that the site

3   The latest Asset Management Plan (2022-2032) was an update only and did not refresh these values.

                                                                                                   Page 13 of 50
EA Networks                                                            Electricity Distribution Network Pricing Methodology 2022-23

       Substations                         Peak Load           Load characteristics
                                                               will be developed for vegetable processing. Previously, the
                                                               industrial load was non-seasonal, but total load peaked in summer
                                                               with irrigation load. Another vegetable processing plant forms the
                                                               base load.

             Hackthorne                      15 MW             The load is summer peaking and irrigation based. The high general
                                                               demand is a consequence of the large number and size of dairy
                                                               sheds. Maximum load currently exceeds firm capacity.

             Lagmhor                         11 MW             Mainly irrigation. Firm capacity exceeds maximum load.

             Lauriston                       15 MW             Summer peaking due to irrigation demand. The high general
                                                               demand is a consequence of the large number and size of dairy
                                                               sheds.

             Methven 66/11                    5 MW             Summer peaking due to irrigation demand. The high general
                                                               demand is a consequence of the large number and size of dairy
             &                                    +
                                                               sheds and related irrigation.
             66/33                            5 MW

             Mt Hutt                          2 MW             Peaks in winter associated with ski-field activities. Maximum load
                                                               exceeds firm capacity. Zero irrigation. Cleardale hydro generation
                                                               is connected at 11kV. Switched firm capacity is sufficient for
                                                               essential services of the major consumer.

             Montalto                        2.5 MW            A temporary substation located near the Montalto hydro power
                                                               station.

             Mt Somers                        3 MW             Maximum load matches firm capacity. The load is balanced
                                                               between extensive rural farms, Mt Somers township, and a couple
                                                               of lime quarries. The load is slightly summer peaking due to the
                                                               irrigation but remains close to the summer peak during winter due
                                                               to the residential demand.

             Northtown                       17 MW             Provides additional capacity and security to Ashburton township
                                                               and immediate surrounds. Load is winter peaking in line with
                                                               residential demand

             Overdale                        14 MW             The load is summer peaking and irrigation based, although Rakaia
                                                               township with its residential/commercial demand causes higher
                                                               base loads than some other irrigation-serving substations.

             Pendarves                       16 MW             Irrigation load causes this site to summer peak at 10 times its
                                                               winter peak. Firm capacity is available to all load.

             Seafield                         8 MW             Dedicated to ANZCO’s meat-works. Non-seasonal peak load

             Wakanui                         13 MW             A summer peak load; mostly irrigation.
Source: EA Networks Asset Management Plan 2021-31, pp208-209

Additional information is available in our published Asset Management Plan, available at:
https://www.eanetworks.co.nz/disclosures/

                                                                                                                  Page 14 of 50
EA Networks                                    Electricity Distribution Network Pricing Methodology 2022-23

4.4. Customer context
The network has been designed to service customers (both load and generation) with their energy
distribution needs. There are five main categories of customer (load groups):
    1.   General
    2.   Irrigation
    3.   Industrial
    4.   Large Users
    5.   Generation
The General and Irrigation Customer Load Groups provide 92% of total revenue, with the General
group providing 48% of total revenue and the Irrigation group providing 44% of total revenue. There
are 18,814 low voltage residential and small business connections in the General group, and 1,615
connections in the Irrigation group.
Irrigation load can be high. While most distribution networks in New Zealand experience peak loads
during winter, EA Networks’ maximum network demand occurs during the irrigation season
(typically September to April), and can be three times higher (on average) than base load during
winter. This is almost entirely driven by farmers’ response to prevailing weather conditions and thus
difficult to forecast. Irrigation demand during the season has a significant bearing on Transpower’s
interconnection cost that is charged to EA Networks and passed-on to our connected customers.

4.5. Consumer consultation
During October-November 2021, EA Networks undertook consumer consultation. This was based on
a random selection of end user customers conducted by an independent survey firm.
EA Networks uses the results of consumer consultation in developing pricing approaches and this
pricing methodology. In summary, the results indicated that customers continue to be supportive of
the current level of prices, with a majority of those surveyed not willing to pay higher prices to
reduce potential for outages, or to reduce time without power. No detailed questions were asked
about the structure of our prices.

How we obtain customer insights to help shape prices
We take a proactive approach in gathering the views of consumers using the electricity distribution
network. Every 24 months an independent survey is carried out to address pricing and consumer
expectations regarding outages and quality of supply (and how these relate to price). The survey
samples residential (urban and rural) and small business customers. The output of any survey or
relevant public information is used when determining prices and other business matters such as
capital investment. Our next broad customer survey is planned to be completed in the final quarter
of 2023.

In addition to our biennial survey that directly targets consumers, the company structure lends itself
to direct feedback from customers. EA Networks is a co-operative company, our end user customers
are also (generally) our shareholders. A Shareholders’ Committee has been established and has
operated since the co-operative was set-up. This committee represents all consumer shareholders
and is focussed on ensuring that consumer views are prioritised. The committee takes an active role
in providing feedback to our board and management regarding customer expectations on price
changes and related matters.

                                                                                          Page 15 of 50
EA Networks                                      Electricity Distribution Network Pricing Methodology 2022-23

Our single largest shareholder is the local District Council. This entity is also one of our largest
connected customers and is represented on the Shareholders Committee. We seek and receive
regular direct feedback in relation to pricing from the District Council.

EA Networks also ensures that there is a local focus to the make-up of our Board of Directors. This
ensures that local views are always considered when making business decisions, including pricing.

From these combined sources we are comfortable that we are considering the views of both
individual customers and the wider market from a macro perspective, especially where that relates
to pricing.

4.6. Feedback
We welcome feedback on our Pricing Methodology and any questions that customers may have
regarding this or their specific circumstances. Any enquiries should be addressed to;
        General Manager Customer & Commercial
        Phone (03) 307 9800, or email; enquiries@eanetworks.co.nz

                                                                                            Page 16 of 50
EA Networks                                              Electricity Distribution Network Pricing Methodology 2022-23

5. Pricing methodology
5.1. Background
The purpose of this section is to outline in detail our methodology for setting prices and to disclose
the current pricing derived from that methodology.

5.2. What our pricing covers

               Generation               Transmission               Distribution                   Retail

    Electricity industry market segments. Our prices include costs relating to Transmission and Distribution only.
    Together these costs are referred to as delivery costs.

There are four key market segments to the electricity industry; generation, transmission, distribution
and retail. EA Networks is responsible for Distribution within the Mid-Canterbury region.

It is Transpower’s role to deliver electricity up and down the length of New Zealand (Transmission),
taking energy supply from the Generation companies. Transpower hand-over within each region to
the relevant distribution company via a number of grid exit points (GXPs).

End user customers have their electricity relationship with Retailers. It is generally the retail sector
that charge end user customers for the total cost of electricity supply and usage. This charge
includes all costs from the different market segments. As such, despite end users receiving only one
electricity invoice each month, the four participants’ costs and margins are included in that charge.
We invoice retailers that have customers connected to our distribution network.

Our pricing (that is charged to Electricity Retailers) covers both Transmission and Distribution costs –
together called delivery costs. Transmission charges are a direct pass-through of those charges levied
on us by Transpower (the national grid operator). Distribution charges reflect the costs associated
with maintaining and operating our local electricity distribution network. We disclose each
separately in the Pricing Schedule.

This document details the methodology we use to derive pricing for Distribution and how we
allocate Transmission costs that are ultimately included in our final delivery prices invoiced to
retailers each month.

Equitable treatment of retailers
Our charges are applied to retailers that use our network to provide electricity to end users.
Retailers that wish to sell electricity to customers within our network area must sign a Default
Distributor Agreement (DDA). The DDA forms the commercial terms and understanding between the
Retailer and ourselves and covers a myriad of operational and performance objectives and
responsibilities. It also details how we charge and how we will invoice retailers.

Our DDA is based on the principle of providing equitable treatment of retailers.. That is, each retailer
is treated equally regardless of size or any other differentiating factor. We do not have differential
prices, service targets or operational procedures for each individual retailer. Whilst this maintains

                                                                                                           Page 17 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

simplicity in how we deal with retailers, it also ensures a level playing field and should enable greater
competition within the retail sector.

5.3. Future pricing approach
The purpose of this section is to provide customers and interested parties with an indication of the
direction that EA Networks sees pricing (in terms of methodology and pricing approach) heading.

Our prices are determined by taking account of the network, consumer and regulatory
characteristics relevant to our network. As such, we recognise the importance of evolving pricing as
circumstances and characteristics change.

We have a pricing development workplan that sets out a roadmap for evolving our pricing approach
and structures that reflect the underlying cost to supply the distribution service desired by our
customers.

The near-term focus of the workplan is to identify the activities we will undertake to develop a
pricing structure which, to the extent practicable, has fixed and variable price components that align
to the fixed and variable costs of supply for each customer (load) group.

High level implication of future pricing approach
We believe it is important to provide an early signal of any changes to our methodology, given the
long-term nature of our investments and those of our customers that may be affected by electricity
network pricing approaches.

The impacts of the future pricing approach will differ for each Customer Load Group and each
customer. Identifying customer impacts of pricing changes is an action included in the pricing
development workplan.

Broadly, the likely impact of transitioning to a pricing structure which has fixed and variable price
components which align to the fixed and variable costs of supply for each customer group will be to
increase the proportion of revenue recovered through fixed and fixed-like charges, and reduce the
proportion of revenue recovered through variable charges.

More than two decades of significant network investment mean the network has significant
capacity, with only isolated areas of network congestion which might result in marginal (avoidable)
costs which would be reflected in variable or congestion based charges. As such, we expect most
costs recovered through prices will be fixed or capacity based. This is the approach for the large
user, industrial and irrigation customer groups.

However, the General customer group can expect a gradual rebalancing of the levels of the variable
charge and fixed charge, with the level of the variable charge falling and the level of the fixed charge
increasing. This commenced this year as we align to changes in low fixed charge regulation.

An implication for these customers is an overall decline in the individual benefit of reducing or
avoiding consumption by investing solar panels and batteries. There may continue to be localised
benefits from reducing or avoiding consumption depending on the specific network conditions. We
began the transition this year with changes to our General load group portfolio.

                                                                                           Page 18 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

5.4. Pricing philosophy
Our philosophy to pricing is based on two views; the internal (business) view focusses on what we
must do and what we require financially to operate our business sustainably over the long term. The
second view is external and that of customers and how we price in the most accurate (cost
reflective) and equitable way that we can. The external view considers the wider market including
the regulatory framework that we work within and must comply with.

Internal perspective
We are a commercial organisation and therefore accurate pricing is fundamental to the financial
sustainability of our business. Prices applied to use the services that we provide must recover our
costs of doing business as well as ensure that we can maintain the assets required to deliver our
services. Inherently our pricing is based on forecast quantity information and therefore it is
important that we have the most accurate information and assumptions to ensure that our prices
result in actual revenue that in-turn recovers our cost of doing business.

We must ensure the company generates an adequate return to ensure that we can continue as a
viable business (going concern). This requires revenue but also a strong focus on costs and
management of our investment in network assets. Our investments are typically long term and
therefore planning is very important so that we ensure decisions made today will not burden the
company in the future.

Accuracy and Sustainability are therefore two over-arching principles that we focus on from an
internal pricing methodology perspective.

External perspective
As well as considering internal requirements, we pay particular attention to external factors when
considering our pricing methodology. There are four principles that underpin our approach to
developing products and prices; Simplicity, Stability, Equity and Transparency.

By focussing on simplicity, we aim to have a pricing methodology that is easy to understand and
follow whilst being cost reflective. It is critical to us that end user customers can understand the
prices that they are charged in relation to the nature of their supply, and further, to appreciate why
we charge for our services the way we do. This allows customers to make informed decisions about
their supply to ensure it is sized appropriately.

We believe that price stability is important and critical to the efficient running of the local economy.
Businesses and residents need confidence in the prices they pay for core services such as electricity.
Our pricing is designed to minimise volatility across the Customer Load Groups. This is to mitigate bill
shock and assist them with efficient budgeting and planning of electricity expenses. We cannot
always control this given the quantum of some input costs, notably transmission costs. However, to
the extent possible we aim to develop prices that are stable year-on-year.

Equity is the fairness of our pricing, both between customer types as well as inter-generational
customer groups. Whilst inherently difficult to apply charges that exactly correlate to the costs of
supplying an individual customer, we endeavour to allocate the cost of running the business and the
distribution network in such a way that those who use more, or drive more of the cost, in-turn pay
for that (beneficiary pays). This is the purpose of establishing Customer Load Groups and identifying
the assets and costs associated with running our network and allocating those accurately and fairly
to each group of users.

                                                                                           Page 19 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

We are entirely open and transparent with our methodology for pricing. We make this information
publicly available and explain it in detail. Further, we engage with the community to share this
information and seek feedback by way of customer surveys and regular interaction and
communication with electricity users.

Through application of these four over-arching principles we aim to create a pricing methodology
that serves the needs of our business whilst meeting customer expectation.

5.5. Pricing development activities
The pricing development workplan sets out near and longer-term activities.

The workplan reflects the uncertainty about what may come, identifying near-term activities focused
on preparing for pricing changes once more is known about the nature and timing of regulatory
changes. There are material regulatory changes on the horizon, particularly regarding the adoption
of a new Transmission Pricing Methodology (TPM). However, the nature and timing of that change is
not currently known.

Near term pricing development activities are:

•   overarching pricing development activities relating to obtaining information and capability
    required to identify pricing structures which meet the pricing objective and philosophy

•   low fixed charge-related activities relating to responding to the allowable price changes
    embedded within the low fixed charge regulations

•   Transmission Pricing Methodology (TPM) activities relating to responding to prospective changes
    to the TPM

More detail is available in the Pricing Development Workplan on our website.

5.6. Our approach to developing prices
The development of our methodology and the prices that result is based on economic pricing
principles given practical, physical, regulatory and commercial constraints.

In general, shared assets and shared costs are allocated proportionally across Customer Load Groups
using network capacity (kVA) associated to that load group. Specific assets and specific costs that can
be attributed to a load group are allocated to that group only.

      For example: if we build a new feeder (electricity line) that only allows irrigation
      connections to connect to the network, the costs associated with that line will be allocated
      only to the Irrigation load group. Other load groups pricing will be unaffected by this
      capital development.

      If on the other hand, we invest in equipment that improves the general quality of electricity
      supply (i.e. it benefits all connected users) then the costs associated with that will be
      shared amongst all load groups proportionally.

There are practical limits to the information available to allocate assets and costs. Electricity
networks generally have significant legacy assets upon which modern upgrades have been applied.
In addition, technology improvements can and will be incorporated where appropriate, but these
can take many years to have an effect across the aggregate network.

                                                                                           Page 20 of 50
EA Networks                                           Electricity Distribution Network Pricing Methodology 2022-23

Consequently, when allocating assets and developing prices a degree of averaging is inevitable.
Despite this, and by applying the four principles of our approach to pricing, we aim to establish
prices that do reflect the costs associated with supplying electricity to different end users (Customer
Load Groups).

5.7. Price development process
The price development process is outlined in the following diagram.

       1. Target Revenue and                 2. Segment                          3. Allocate costs
       Costs determined.                     connections into                    across load groups to
                                             Customer Load                       reflect cost drivers
                                             Groups

            Validate against                                      Develop cost reflective price
                                              Forecast
           Forecast Allowable                                     structures (e.g. $/kW/day) for each
                                             quantities
                                                                  load group to efficiently recover costs.
                Revenue

   Overview of Pricing Methodology

The following diagram illustrates how the process links together to form our pricing methodology
and pricing.

                                               Customer Segmentation / Price Structures

                                                     General                         $ price        ∑ QTY
        Target Revenue

                         Cost Allocation
                          Methodology

                                                    Irrigation                       $ price        ∑ QTY

                                                    Industrial                       $ price        ∑ QTY

                                                   Large Users                       $ price        ∑ QTY

                                                   Generation                        $ price        ∑ QTY

                                                                                     ∑ = Target Revenue

   Where QTY (quantity) may be volume, capacity, demand, number or any combination. See Pricing details for
   specific information.

   Overview of Cost Allocation Methodology

                                                                                                    Page 21 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

5.8. Target Revenue and costs determined
Each year we review the costs associated with operating the electricity distribution network for the
financial year (from 1st April to 31st March). These costs are separated into five key areas.

    •   Distribution services costs:
                o Operations and maintenance
                o Administration
                o Depreciation
                o Cost of capital (return on investment)
    •   Pass-through and Transmission costs:
                o Rates & levies
                o Transmission.
The sum of these five costs is our Target Revenue.

This table shows the main costs making up the Target revenue for 2022-23.
 Cost category                                                                Target revenue ($000)
 Distribution services
   Operations & maintenance                                                           $13,058
   Administration                                                                      $5,574
   Depreciation                                                                       $10,882
   Cost of capital                                                                     $4,046
          Subtotal                                                                    $33,560
 Pass-through costs
   Rates & levies                                                                         $294
 Transmission
   Transmission – connection                                                           $2,004
   Transmission – interconnection                                                      $5,881
   Transmission – subtotal                                                             $7,885
          Subtotal                                                                     $8,179
 Target revenue                                                                       $41,739

We use historic financial information and known changes (e.g. staff numbers changing affecting
salaries and wages) to derive operations and maintenance, administration and depreciation cost
trends to forecast these costs for the next financial year.

Cost of capital is unique in that it is not separately identifiable (additional steps are required to
determine the value of cost of capital). To calculate Cost of Capital; first, we determine our Forecast
Allowable Revenue as calculated under the Default Price Path regulatory regime (or lower target as
specified by our Board). This is effectively the total return on assets we are allowed to earn as
defined by the Commerce Commission (the Regulator). Secondly, we subtract the costs already
identified (operations and maintenance, administration depreciation, and Transmission) with the
difference being our Cost of Capital.

                                                                                           Page 22 of 50
EA Networks                                               Electricity Distribution Network Pricing Methodology 2022-23

Forecast Revenue from Prices (FRAP, derived by multiplying our prices by forecast quantities) is
compared with Forecast Allowable Revenue (FAR) to ensure that we set prices (and therefore derive
revenue) that is consistent with the Default Price Path Determination. FRAP must not exceed FAR.
Additional information can be found in the Price Setting Compliance Statement4.

For the financial year ending 31st March 2023 our Target Revenue is $41.739 million.

5.9. Segment connections into Customer Load Groups
Segmenting connections into Customer Load Groups allows us to establish prices that better reflect
the nature of assets and costs incurred in delivering electricity to specific groups of customers.

           For example: the assets and costs associated with delivering low voltage connections to the
           average family home are significantly different to those required to deliver electricity to an
           industrial manufacturing business. Segmentation is essential so that one group is not
           subsidising another group or being disproportionately charged for infrastructure that they are
           not benefitting from.

The criteria for segmenting connections is to group connections that share similar electricity usage
patterns (load profiles), have similar demand requirements (e.g. criticality of supply and diversity
needs) and that drive similar incremental cost to our business. This this enables the allocation of
network assets by group to reflect utilisation by that group.

Once connections are segmented logically, Customer Load Groups are created. We aim to have as
few groups as possible as we believe that this simplifies the pricing methodology and the derivation
of prices. It also improves segmentation accuracy by reducing the potential for a customer to be
consistent with more than one group.

From this segmentation process we have created five Customer Load Groups;

       •    General (low volt)
       •    Industrial (medium volt)
       •    Irrigation (medium volt)
       •    Large Users
       •    Generation

Where the segments are broad we have established sub-groups within each (where appropriate)
that allows better granularity when it comes to allocating prices to end users. However, the pricing
methodology applied to these sub-groups is identical within the broader group, except that different
fixed daily prices apply based on connected capacity (kVA).

            For example: within General (low volt) we have five sub-groups that differ based on size
            of connected load – GS05 (up to 7kVA), GS20 (up to 29kVA), GS50 (up to 45kVA), G100
            (up to 111kVA) and G150 (above 111kVA).

4   A copy is available at https://www.eanetworks.co.nz/disclosures/

                                                                                                     Page 23 of 50
EA Networks                                     Electricity Distribution Network Pricing Methodology 2022-23

       The methodology for allocating costs and determining prices is identical for the five sub-
       groups, except that a higher fixed daily price applies for larger connections.

In essence – a customer who has higher network needs, uses more of the available network capacity
and/or requires more network assets to deliver their energy requirements will pay more through our
network prices. Put another way, a customer can reduce their network prices by reducing the
capacity or amount of demand they place on the electricity network.

Each Customer Load Group is described in more detail later.

5.10. Allocate costs across Customer Load Groups
The Cost Allocation Methodology simply refers to the way that we allocate our Target Revenue (by
category) across the Customer Load Groups. The intention of the methodology is to establish a
relationship between the Customer Load Groups and the costs associated with supplying electricity
to them – in other words, how to recover Target Revenue in the most cost reflective way that we
can. From this we can derive pricing by load group.

      For example: we may construct a sub-station to supply a single Major User. The costs
      associated with this are allocated to that user and their pricing reflects recovery of those costs.
      Other Customer Load Group pricing is unaffected by those costs.

      However, if a sub-station services all Customer Load Groups, the costs associated with it a
      shared proportionally by all groups.

Summary of allocation method
       Cost                                          Allocation method
                                                     Anytime maximum demand of Customer
       Pass-through and Transmission
                                                     Load Group
       Distribution services costs:
                                                     Anytime maximum demand of Customer
       Operations and maintenance
                                                     Load Group
       Administration                                Number of connections (ICPs)
                                                     Anytime maximum demand of Customer
       Depreciation
                                                     Load Group
                                                     Anytime maximum demand of Customer
       Cost of capital (return on investment)
                                                     Load Group

5.11. Pass-through and Transmission costs
Transmission costs are passed on to us by Transpower. There are two costs incurred; ‘Connection’
and ‘Interconnection’ costs.

Connection costs recover the costs associated with Transpower’s local grid exit point (GXP).

As interconnection assets are also used to supply other lines companies, interconnection costs are
shared based on the demand measured for each distribution network during the 100 half-hour peak
demand periods on the Upper South Island region (known as the Regional Coincident Peak Demand
– RCPD). These peaks are recorded each year by Transpower. We allocate these costs to each
customer group based on that group’s contribution to total network capacity used.

                                                                                           Page 24 of 50
You can also read