PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Design Team Agenda • General Business • Cost Estimate • Permitting • FFE • Photographic Documentation of Hunnewell pre-demo • Curb Ramp Scope • Budget & Value Management • Review List of VM items • Site Plan Impacts • Floor Plan Impacts • Project Budget Update and Next Steps
Design Development Cost Estimate Overview SD DD Budget Delta $45,329,275 $45,038,495 $45,061,000 $22,505 (under budget) • 76,478 GSF • $588.91 per GSF • In-depth reconciliation process; AM Fogarty reconciled estimate: $45,076,114
DD Cost Estimate Summary Breakdown Item Rate Amount New Building Construction $28,731,644 Building Demolition $379,700 Haz Mat Removals at Existing Building $353,000 Sitework $6,172,075 Design & Estimating Contingency 5.00% $1,781,821 Escalation To Mid-point of Construction 4.75% $1,777,366 Total Direct Cost Of Work $39,195,606 General Conditions $2,526,980 General Requirements $1,129,084 Fast Track/Premium Time Contingency 0.60% $235,000 Bond & Insurance 1.20% $540,461 CM Fee 2.00% $806,494 GMP Contingency 1.50% $604,870 Total Construction Cost Estimate $45,038,495
General Business - Permitting • Received Planning Board PSI Approval/Conditions on 1/4/2021 o Approximately $457k off-site improvements identified scope added to project costs o Off-Site Utility Upgrades o Cameron Street Improvements (Paving, Markings & Striping) o Sidewalk and Accessibility Improvements (within 600 feet of Property Lines) o Traffic signalizations o Post Occupancy Traffic Review • Request to add “barrier” between library parking lot and school o Looking to absorb cost through removal of paths and grading changes at north side of site • NOI Submission 1/14 as planned • ZBA Submission (Site Plan Review) 2/1 as planned o Anticipating minor impacts to budget • Design Review Board (DRB) – Next Meeting TBD o PBC recommendation/authorization to meet after 1/21/21 meeting
Additional Costs for Off Site Permitting Mitigations Mill and Overlay pavement on Cameron Street $ 56,806 Replacement of the stormwater pipes and $ 94,279 structures at the Fuller Brook Path Off site traffic light and striping modifications $ 22,767 Off site curb cut modifications $283,454 Total $457,306
General Business – FF&E • Budget capped at $1,800 per student • Current budget assumes no reuse of any furniture; reuse of some area rugs • Design team has worked to balance built-in shelving and casework with furniture to meet storage and educational needs • $1800 per student budget, assumes 22 students per classrooms in grades 1-5 (not “max” number of 24), and 18 students per classroom in K (not “max” number of 20) • School department has requested design to max student numbers and include standing desks. This would require $2,023 per student budget • Neither budget includes the following add alternates: • 2 Bean Bag Chairs; 1 Teachers’ Aid desk per classroom • Recommended $50,000 equipment allowance • Individual student (triangle) desks, in lieu of group tables
General Business - Other • Documentation of Existing Building • No State funding = No Mass Historic Commission (MHC) requirements • Some minor salvage items planned (to be discussed later in presentation) • Pre-demo photographic documentation - not requested by Wellesley Historic Commission to-date, however, recommended. • Curb Ramp Work • Started with a "Google Street View" walk of all intersections within 600 feet of the project. • Removed Washington Street curb ramps and curb ramps within 600 feet of the Tolles Parsons. The 600-foot zone from Library project not taken / excluded. • Field survey the remaining curb ramps by BETA (draft memo circulated). • Need to confirm detailed scope of work; BETA will submit ASR based on this
General Business - Other • Documentation of Existing Building • No State funding = No Mass Historic Commission (MHC) requirements • Some salvage items planned (to be discussed later in presentation) • Pre-demo photographic documentation - not requested by Wellesley Historic Commission to-date, however, recommended. • Curb Ramp Work • Started with a "Google Street View" walk of all intersections within 600 feet of the project. • Removed Washington Street curb ramps and curb ramps within 600 feet of the Tolles Parsons. The 600 foot zone from Library project not taken / excluded. • Field survey the remaining curb ramps by BETA (draft memo circulated).
Value Management Start of VE targeted +/- $450,000 savings to support off-site permitting requirements’ costs. Approximate total of acceptable VE identified: • Site VE $375,000 (Option 1 items) Sustainability Ed Plan Goals • Building VE $425,000 Total $800,000 Quality
Site VM Items: Option 1 Summary Total: $375,000 • C-01 Cameron Street Wall • C-16A Simplify screen walls at Gym outdoor o $125,000 play space o Total removal not recommended for safety – strategies o $45,000 for reducing cost include partial wall, fence and o Make more fence-like (faces residential neighborhood) plantings. o Avoid two-sided veneer walls o Avoid double sided masonry walls • C-17A Simplify screen walls at Refuse area • C-02 Replace unit pavers at outdoor learning o $75,000 space o Make more fence-like o $15,000 o Durability from dumpsters and play surface side • C-04 Remove concrete terraced seating at south side o $65,000 o Requires some grading mitigation in redesign • C-13A Use Bituminous setting bed at Unit Pavers o $50,000
Site VM Items: Option 1 Total: $375,000 • C-01 Cameron Street Wall • C-16A Simplify screen walls at Gym outdoor o $125,000 play space o Total removal not recommended for safety – o $45,000 strategies for reducing cost include partial wall, o Make more fence-like fence and plantings. o Avoid two-sided veneer walls o Avoid double sided masonry walls • C-17A Simplify screen walls at Refuse area • C-02 Replace unit pavers at outdoor o $75,000 learning space o Make more fence-like o $15,000 o Durability from dumpsters and play surface side • C-04 Remove precast terraced seating at south side o $65,000 o Requires some grading mitigation in redesign • C-13A Use Bituminous setting bed at Unit Pavers o $50,000
Site Plan: Fuller Brook C-01 Cameron Street Wall Cameron Street
Site VM Items: Option 1 Total: $375,000 • C-01 Cameron Street Wall • C-16A Simplify screen walls at Gym outdoor o $125,000 play space o Total removal not recommended for safety – o $45,000 strategies for reducing cost include partial wall, o Make more fence-like fence and plantings. o Avoid two-sided veneer walls o Avoid double sided masonry walls • C-17A Simplify screen walls at Refuse area • C-02 Replace unit pavers at outdoor o $75,000 learning space o Make more fence-like o $15,000 o Durability from dumpsters and play surface side • C-04 Remove precast terraced seating at south side o $65,000 o Requires some grading mitigation in redesign • C-13A Use Bituminous setting bed at Unit Pavers o $50,000
Site Plan: Fuller Brook C-02 Outdoor Classroom Unit Pavers C-00 Per PSI: Add physical barrier between library parking lot and school Cameron Street
Site VM Items: Option 1 Total: $375,000 • C-01 Cameron Street Wall • C-16A Simplify screen walls at Gym outdoor o $125,000 play space o Total removal not recommended for safety – o $45,000 strategies for reducing cost include partial wall, o Make more fence-like fence and plantings. o Avoid two-sided veneer walls o Avoid double sided masonry walls • C-17A Simplify screen walls at Refuse area • C-02 Replace unit pavers at outdoor o $75,000 learning space o Make more fence-like o $15,000 o Durability from dumpsters and play surface side • C-04 Remove concrete terraced seating at south side o $65,000 o Requires some grading mitigation in redesign • C-13A Use Bituminous setting bed at Unit Pavers o $50,000
Site Plan: Fuller Brook C-04 Concrete Terraced Seating Cameron Street
Site VM Items: Option 1 Total: $375,000 • C-01 Cameron Street Wall • C-16A Simplify screen walls at Gym outdoor o $125,000 play space o Total removal not recommended for safety – o $45,000 strategies for reducing cost include partial wall, o Make more fence-like fence and plantings. o Avoid two-sided veneer walls o Avoid double sided masonry walls • C-17A Simplify screen walls at Refuse area • C-02 Replace unit pavers at outdoor o $75,000 learning space o Make more fence-like o $15,000 o Durability from dumpsters and play surface side • C-04 Remove precast terraced seating at south side o $65,000 o Requires some grading mitigation in redesign • C-13A Use Bituminous setting bed at Unit Pavers o $50,000
Site Plan: Fuller Brook C-13A Use Bituminous Setting Bed Cameron Street
Site VM Items: Option 1 Total: $375,000 • C-01 Cameron Street Wall • C-16A Simplify screen walls at Gym outdoor o $125,000 play space o Total removal not recommended for safety – strategies o $45,000 for reducing cost include partial wall, fence and o Make more fence-like (faces residential neighborhood) plantings. o Avoid two-sided veneer walls o Avoid double sided masonry walls • C-17A Simplify screen walls at Refuse area • C-02 Replace unit pavers at outdoor learning o $75,000 space o Make more fence-like o $15,000 o Durability from dumpsters and play surface side • C-04 Remove precast terraced seating at south side o $65,000 o Requires some grading mitigation in redesign • C-13A Use Bituminous setting bed at Unit Pavers o $50,000
Site Plan: Fuller Brook C-16a & 17a Simplify Screen Walls Cameron Street
Outdoor Environments Fencing and Screening
Site VM Items: Option 2 Summary Total: $390,000 • C-19A Replace Pavers at bus drive area with 5” color concrete o $300,000 o Not Recommended • C-10 Memorial Garden o $90,000 o Town or School to take on design and installation
Site Plan: Fuller Brook C-19A Replace Pavers with Colored Concrete C-10 Memorial Garden Cameron Street
Outdoor Environments Memorial Garden
Architectural VM Items Summary Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45,000 o $50,000 • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10,000 o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40,000 lieu of displacement ventilation • A-9c Change Innovation Space floor o $225,000 from sealed Conc to Rubber o $20,000 • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
Architectural VM Items Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45,000 o $50k • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10k o $5k o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40k lieu of displacement ventilation • A-9c Change Innovation Space floor o $225k from sealed Conc to Rubber o $20k • A-12c Reduced Media Center Specialty Ceiling Qty. o $30k
Roof Plan S-01 Mechanical Screen
Architectural VM Items Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45k o $50k • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10k o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40k lieu of displacement ventilation • A-9c Change Innovation Space floor o $225k from sealed Conc to Rubber o $20k • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
Second Floor Plan Fifth Grade Fourth Grade Third Grade Learning Commons Media Center A-02 A-12c Reduce Media Center windows into Cafetorium & Specialty Ceiling Art, Music & Innovation Outdoor Learning Classroom
Architectural VM Items Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45,000 o $50,000 • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10,000 o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40,000 lieu of displacement ventilation • A-9c Change Innovation Space floor o $225,000 from sealed Conc to Rubber o $20,000 • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
First Floor Plan Second Grade Main Entrance First Grade Gym Entrance Service Entrance Kindergarten Service & Loading A-6b Change Terrazzo Flooring to Rubber Nurse Main Entrance Administration
Architectural VM Items Summary Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45,000 o $50,000 • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10,000 o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40,000 lieu of displacement ventilation • A-9c Change Innovation Space floor o $225,000 from sealed Conc to Rubber o $20,000 • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
Second Floor Plan Fifth Grade Fourth Grade Third Grade Learning Commons Media Center A-9c Change Innovation Space Floor to Rubber Art, Music & Innovation Outdoor Learning Classroom
Architectural VM Items Summary Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Centers (3) screen at back (east) side Clerestory windows o $45,000 o $50,000 • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10,000 o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40,000 lieu of displacement ventilation • A-9c Change Innovation Space floor o $225,000 from sealed Conc to Rubber o $20,000 • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
Second Floor Plan Fifth Grade A-16 Remove 3 Roof Fourth Grade Clerestory Monitors Third Grade Learning Commons Media Center Art, Music & Innovation Outdoor Learning Classroom
Roof Plan A-16 Learning Commons Clerestories
Architectural VM Items Summary Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45,000 o $50,000 • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10,000 o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40,000 lieu of displacement ventilation • A-9c Change Innovation Space floor o $225,000 from sealed Conc to Rubber o $20,000 • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
Salvage Cast Stone Scrolls Plaques Weathervane
Second Floor Plan Fifth Grade Fourth Grade Third Grade Learning Commons Media Center A-22 Reduce quantity of Salvage items: Decorative Stone Weathervane Art, Music & Innovation Outdoor Learning Classroom
Architectural VM Items Summary Total: $425,000 • S-01 Reduce Visual rooftop mechanical • A-16 Remove Learning Center screen at back (east) side Clerestory windows o $45,000 o $50,000 • A-02 Reduce Media Center glass into • A-22 Reduce Salvage Items Cafetorium o $10,000 o $5,000 o Save 6 cast stone elements • A-6b Change Entrance Lobby from o Save Weathervane Terrazzo to Rubber Flooring • M-01 Provide Overhead VRF system in o $40,000 lieu of displacement ventilation • A-9c Change Innovation Space floor o $225,000 from sealed Conc to Rubber o $20,000 • A-12c Reduced Media Center Specialty Ceiling Qty. o $30,000
Mechanical System Considerations & Recommendation M-01 Provide Overhead VRF system in lieu of displacement ventilation $225k savings • The current Displacement Air system is a good, tried and true system, however, given the Net Zero and all-Electric Systems and lower hot water temperature considerations there are compelling reasons to utilize an overhead VRF system. This is prompted primarily by educational space considerations – particularly within the classrooms and to realize beneficial cost savings and a simplified system: • SMMA reviewed multiple systems during SD and DD to balance the various design goals • Flexibility of the general classrooms • Air quality • Energy efficiency • Ease of operations and maintenance • Life cycle cost • The single biggest factor that has evolved since early DD is the low hot water temperatures when a radiant heating system is employed – a requirement of the displacement ventilation model. This is a factor of an all-electric hot water heating system and has added extensive amounts of fin tube radiation at the classrooms - • Impacts the teacher’s ability to easily move furniture to create multiple configurations as demanded by a modern classroom. As well as adding storage over time (always a drawback historically in classrooms with unit vents or radiant heat at the floor level (at the high school this was overcome with radiant ceiling panels – which are also not effective at lower hot water temperatures). • Overhead system increases available floor area over Displacement air system
Mechanical System Considerations & Recommendation • An overhead system will not compromise on energy efficiency (no change in the EUI target) • VRF model shows slightly better energy savings • LCCA • Equipment is similar – and eliminates a lot of fin tube - • Acoustics • Improvements for the displacement system are not deemed cost effective given the sacrifice of room flexibility. Both systems meet required Noise Criteria (NC) level • Ventilation Effectiveness • Marginal benefits with Displacement system offer improved Ventilation effectiveness Both systems meet 100% fresh air requirements • Overhead system eliminates colder air source/draft at floor • Preparing for the Hardy project and keeping systems consistent and costs • Will benefit this project and is more replicable for future conversions of other elementary schools in town
Mechanical Systems Classroom Wing Perimeter Heat & Displacement Air
Mechanical Systems Classroom Wing Perimeter Heat & Displacement Air
Mechanical Systems Classroom Wing Overhead System
Architectural VM Items: Ongoing analysis Total: $TBD • A-00 Reduce Cost of façade materials • In progress • E-01 Reduce size of generator (not recommended – but anticipating finetuning for final design) • $50k • Maintain building temperature • Future battery storage anticipated
January 1/21/2021 Meeting Agenda Interior Design • Interior Design Options: PCT Wainscot • Classroom & learning Commons Updates • Main Entrance Lobby updates Exterior Design • Façade Material Options • Main Entrance updates Site Design • TBD Updates
Design Development Cost Estimate Overview Description DD Control Budget Delta to Budget Construction Estimate $45,038,495 $45,061,000 ($22,505) (under budget) Add Off site Mitigation $457,306 Value Engineering ($800,000) ($365,199) Net Cost Estimate $44,695,801 $45,061,000 (under budget) • Previous SD Cost Estimate $45,329,275 • 76,478 GSF • $588.91 per GSF base estimate • In-depth reconciliation process; AM Fogarty reconciled estimate: $45,076,114
Budget Changes since Feasibility Study • Received actual proposals from Commissioning Agents. • Construction Schedule changed (due to CM schedule, COVID delay and longer pre-construction ramp phase) • FF&E budget has been updated to include TLC program. • PSI Permitting mitigation requirements (include post occupancy traffic study, offsite improvements) • Potentially perform more extensive existing conditions survey of abutters property
Hunnewell Elementary School Construction Phase Budget Tracking Feasibility Tracking Potential Revised Construction Potential DD Construction Description Phase Budget Increases Phase Budget Target November Timeline July 2019 January 2021 2021 Tracking Cost Delta DD phase $1,074,156 Proposed VE for Acceptance & ($822,505) estimate savings Subtotal Delta Tracking costs overage $251,651 Total Project Budget $52,853,000 $53,104,651
Breakdown of Budget Increases Since Feasibility Phase Consultants Commissioning $ 120,250 Hazardous Materials $ 20,000 Traffic Studies (PSI required) $ 15,000 OPM Construction Phase $ 91,000 Admin – Pre-condition survey $ 77,600 Off-site Mitigations (PSI required) $ 457,306 (pre-VE) FF&E (TLC program) $ 73,000 Owner’s Contingency $ 220,000 (offset or transfer) Total $1,074,156 $251,651 (with $822,505 VE)
Hunnewell Elementary School Feasibility Study Thank you
You can also read