PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA

Page created by Angela Guerrero
 
CONTINUE READING
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
Hunnewell Elementary School
Design

  PBC Meeting
  Design Development Review
  Update
  January 14, 2021
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
Design Team Agenda

•   General Business
    •   Cost Estimate
    •   Permitting
    •   FFE
    •   Photographic Documentation of Hunnewell pre-demo
    •   Curb Ramp Scope
•   Budget & Value Management
    •   Review List of VM items
•   Site Plan Impacts
•   Floor Plan Impacts
•   Project Budget Update and Next Steps
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
Design Development Cost Estimate Overview

        SD                  DD                Budget               Delta

 $45,329,275          $45,038,495         $45,061,000            $22,505
                                                              (under budget)

• 76,478 GSF
• $588.91 per GSF
• In-depth reconciliation process; AM Fogarty reconciled estimate: $45,076,114
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
DD Cost Estimate Summary Breakdown
                       Item               Rate    Amount
New Building Construction                          $28,731,644
Building Demolition                                  $379,700
Haz Mat Removals at Existing Building                $353,000
Sitework                                            $6,172,075
Design & Estimating Contingency           5.00%     $1,781,821
Escalation To Mid-point of Construction   4.75%     $1,777,366
Total Direct Cost Of Work                          $39,195,606
General Conditions                                  $2,526,980
General Requirements                                $1,129,084
Fast Track/Premium Time Contingency       0.60%      $235,000
Bond & Insurance                          1.20%      $540,461
CM Fee                                    2.00%      $806,494
GMP Contingency                           1.50%      $604,870
Total Construction Cost Estimate                   $45,038,495
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
General Business - Permitting
•   Received Planning Board PSI Approval/Conditions on 1/4/2021
     o   Approximately $457k off-site improvements identified scope added to project costs
     o   Off-Site Utility Upgrades
     o   Cameron Street Improvements (Paving, Markings & Striping)
     o   Sidewalk and Accessibility Improvements (within 600 feet of Property Lines)
     o   Traffic signalizations
     o   Post Occupancy Traffic Review
•   Request to add “barrier” between library parking lot and school
     o   Looking to absorb cost through removal of paths and grading changes at north side of site
•   NOI Submission 1/14 as planned
•   ZBA Submission (Site Plan Review) 2/1 as planned
     o   Anticipating minor impacts to budget
•   Design Review Board (DRB) – Next Meeting TBD
     o   PBC recommendation/authorization to meet after 1/21/21 meeting
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
Additional Costs for Off Site Permitting Mitigations

Mill and Overlay pavement on Cameron Street         $ 56,806
Replacement of the stormwater pipes and             $ 94,279
    structures at the Fuller Brook Path
Off site traffic light and striping modifications   $ 22,767
Off site curb cut modifications                     $283,454
                                            Total   $457,306
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
General Business – FF&E
  •   Budget capped at $1,800 per student
  •   Current budget assumes no reuse of any furniture; reuse of some area rugs
  •   Design team has worked to balance built-in shelving and casework with furniture to meet storage
      and educational needs
  •   $1800 per student budget, assumes 22 students per classrooms in grades 1-5 (not “max” number
      of 24), and 18 students per classroom in K (not “max” number of 20)
  •   School department has requested design to max student numbers and include standing desks.
      This would require $2,023 per student budget
  •   Neither budget includes the following add alternates:
       •   2 Bean Bag Chairs; 1 Teachers’ Aid desk per classroom
       •   Recommended $50,000 equipment allowance
       •   Individual student (triangle) desks, in lieu of group tables
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
General Business - Other
•   Documentation of Existing Building
     •   No State funding = No Mass Historic Commission (MHC) requirements
     •   Some minor salvage items planned (to be discussed later in presentation)
     •   Pre-demo photographic documentation - not requested by Wellesley Historic Commission to-date,
         however, recommended.

•   Curb Ramp Work
     •   Started with a "Google Street View" walk of all intersections within 600 feet of the project.
     •   Removed Washington Street curb ramps and curb ramps within 600 feet of the Tolles Parsons. The
         600-foot zone from Library project not taken / excluded.
     •   Field survey the remaining curb ramps by BETA (draft memo circulated).
     •   Need to confirm detailed scope of work; BETA will submit ASR based on this
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
General Business - Other
•   Documentation of Existing Building
     •   No State funding = No Mass Historic Commission (MHC) requirements
     •   Some salvage items planned (to be discussed later in presentation)
     •   Pre-demo photographic documentation - not requested by Wellesley Historic Commission to-date,
         however, recommended.

•   Curb Ramp Work
     •   Started with a "Google Street View" walk of all intersections within 600 feet of the project.
     •   Removed Washington Street curb ramps and curb ramps within 600 feet of the Tolles Parsons. The
         600 foot zone from Library project not taken / excluded.
     •   Field survey the remaining curb ramps by BETA (draft memo circulated).
PBC Meeting Design Development Review Update January 14, 2021 - Hunnewell Elementary School Design - Wellesley, MA
General Business - Other
Value Management

Start of VE targeted +/- $450,000 savings to support off-site permitting
requirements’ costs.
Approximate total of acceptable VE identified:

• Site VE                $375,000 (Option 1 items)                          Sustainability
                                                             Ed Plan
                                                                                Goals
• Building VE            $425,000
  Total                  $800,000
                                                                       Quality
Site VM Items: Option 1 Summary
Total: $375,000
•   C-01 Cameron Street Wall                                     •   C-16A Simplify screen walls at Gym outdoor
     o   $125,000                                                    play space
     o   Total removal not recommended for safety – strategies        o   $45,000
         for reducing cost include partial wall, fence and            o   Make more fence-like (faces residential neighborhood)
         plantings.
                                                                      o   Avoid two-sided veneer walls
     o   Avoid double sided masonry walls
                                                                 •   C-17A Simplify screen walls at Refuse area
•   C-02 Replace unit pavers at outdoor learning
                                                                      o   $75,000
    space
                                                                      o   Make more fence-like
     o   $15,000
                                                                      o   Durability from dumpsters and play surface side
•   C-04 Remove concrete terraced seating at
         south side
     o   $65,000
     o   Requires some grading mitigation in redesign
•   C-13A Use Bituminous setting bed at Unit
    Pavers
     o   $50,000
Site VM Items: Option 1
Total: $375,000
•   C-01 Cameron Street Wall                                  •   C-16A Simplify screen walls at Gym outdoor
     o   $125,000                                                       play space
     o   Total removal not recommended for safety –                o   $45,000
         strategies for reducing cost include partial wall,        o   Make more fence-like
         fence and plantings.
                                                                   o   Avoid two-sided veneer walls
     o   Avoid double sided masonry walls
                                                              •   C-17A Simplify screen walls at Refuse area
•   C-02 Replace unit pavers at outdoor
                                                                   o   $75,000
         learning space
                                                                   o   Make more fence-like
     o   $15,000
                                                                   o   Durability from dumpsters and play surface side
•   C-04 Remove precast terraced seating at
         south side
     o   $65,000
     o   Requires some grading mitigation in redesign
•   C-13A Use Bituminous setting bed at Unit
          Pavers
     o   $50,000
Site Plan:

                                        Fuller Brook

                  C-01
                  Cameron Street Wall

             Cameron Street
Site VM Items: Option 1
Total: $375,000
•   C-01 Cameron Street Wall                                  •   C-16A Simplify screen walls at Gym outdoor
     o   $125,000                                                       play space
     o   Total removal not recommended for safety –                o   $45,000
         strategies for reducing cost include partial wall,        o   Make more fence-like
         fence and plantings.
                                                                   o   Avoid two-sided veneer walls
     o   Avoid double sided masonry walls
                                                              •   C-17A Simplify screen walls at Refuse area
•   C-02 Replace unit pavers at outdoor
                                                                   o   $75,000
         learning space
                                                                   o   Make more fence-like
     o   $15,000
                                                                   o   Durability from dumpsters and play surface side
•   C-04 Remove precast terraced seating at
         south side
     o   $65,000
     o   Requires some grading mitigation in redesign
•   C-13A Use Bituminous setting bed at Unit
          Pavers
     o   $50,000
Site Plan:

                                             Fuller Brook

                  C-02
                  Outdoor Classroom
                  Unit Pavers

                   C-00
                   Per PSI:
                   Add physical barrier
                   between library parking
                   lot and school

             Cameron Street
Site VM Items: Option 1
Total: $375,000
•   C-01 Cameron Street Wall                                  •   C-16A Simplify screen walls at Gym outdoor
     o   $125,000                                                       play space
     o   Total removal not recommended for safety –                o   $45,000
         strategies for reducing cost include partial wall,        o   Make more fence-like
         fence and plantings.
                                                                   o   Avoid two-sided veneer walls
     o   Avoid double sided masonry walls
                                                              •   C-17A Simplify screen walls at Refuse area
•   C-02 Replace unit pavers at outdoor
                                                                   o   $75,000
         learning space
                                                                   o   Make more fence-like
     o   $15,000
                                                                   o   Durability from dumpsters and play surface side
•   C-04 Remove concrete terraced seating at
         south side
     o   $65,000
     o   Requires some grading mitigation in redesign
•   C-13A Use Bituminous setting bed at Unit
          Pavers
     o   $50,000
Site Plan:

                              Fuller Brook

                              C-04
                              Concrete Terraced
                              Seating

             Cameron Street
Site VM Items: Option 1
Total: $375,000
•   C-01 Cameron Street Wall                                  •   C-16A Simplify screen walls at Gym outdoor
     o   $125,000                                                       play space
     o   Total removal not recommended for safety –                o   $45,000
         strategies for reducing cost include partial wall,        o   Make more fence-like
         fence and plantings.
                                                                   o   Avoid two-sided veneer walls
     o   Avoid double sided masonry walls
                                                              •   C-17A Simplify screen walls at Refuse area
•   C-02 Replace unit pavers at outdoor
                                                                   o   $75,000
         learning space
                                                                   o   Make more fence-like
     o   $15,000
                                                                   o   Durability from dumpsters and play surface side
•   C-04 Remove precast terraced seating at
         south side
     o   $65,000
     o   Requires some grading mitigation in redesign
•   C-13A Use Bituminous setting bed at Unit
          Pavers
     o   $50,000
Site Plan:

                                               Fuller Brook

                              C-13A
                              Use Bituminous
                              Setting Bed

             Cameron Street
Site VM Items: Option 1
Total: $375,000
•   C-01 Cameron Street Wall                                     •   C-16A Simplify screen walls at Gym outdoor
     o   $125,000                                                    play space
     o   Total removal not recommended for safety – strategies        o   $45,000
         for reducing cost include partial wall, fence and            o   Make more fence-like (faces residential neighborhood)
         plantings.
                                                                      o   Avoid two-sided veneer walls
     o   Avoid double sided masonry walls
                                                                 •   C-17A Simplify screen walls at Refuse area
•   C-02 Replace unit pavers at outdoor learning
                                                                      o   $75,000
    space
                                                                      o   Make more fence-like
     o   $15,000
                                                                      o   Durability from dumpsters and play surface side
•   C-04 Remove precast terraced seating at
         south side
     o   $65,000
     o   Requires some grading mitigation in redesign
•   C-13A Use Bituminous setting bed at Unit
    Pavers
     o   $50,000
Site Plan:

                                                      Fuller Brook
                              C-16a & 17a
                              Simplify Screen Walls

             Cameron Street
Outdoor Environments

Fencing and Screening
Site VM Items: Option 2 Summary
Total: $390,000
•   C-19A Replace Pavers at bus drive area with 5” color concrete
     o   $300,000
     o   Not Recommended

•   C-10 Memorial Garden
     o   $90,000
     o   Town or School to take on design and installation
Site Plan:

                                                              Fuller Brook

                                      C-19A
                                      Replace Pavers
                                      with Colored Concrete

                    C-10
                    Memorial Garden

             Cameron Street
Outdoor Environments

Memorial Garden
Architectural VM Items Summary
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50,000
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10,000
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40,000                                     lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225,000
         from sealed Conc to Rubber
     o   $20,000
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
Architectural VM Items
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50k
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10k
     o   $5k                                     o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40k                                        lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225k
         from sealed Conc to Rubber
     o   $20k
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30k
Roof Plan

            S-01
            Mechanical Screen
Architectural VM Items
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45k                                    o   $50k
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10k
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40k                                        lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225k
         from sealed Conc to Rubber
     o   $20k
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
Second Floor Plan                                              Fifth Grade

                                Fourth Grade

                  Third Grade

                                               Learning Commons
                                                  Media Center
                                                                     A-02
                                                                     A-12c
                                                                     Reduce Media
                                                                     Center windows
                                                                     into Cafetorium &
                                                                     Specialty Ceiling

                                     Art, Music & Innovation
             Outdoor Learning
                Classroom
Architectural VM Items
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50,000
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10,000
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40,000                                     lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225,000
         from sealed Conc to Rubber
     o   $20,000
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
First Floor Plan                                                       Second Grade

 Main Entrance
                                                First Grade

 Gym Entrance

 Service Entrance
                    Kindergarten

                                                                                      Service &
                                                                                       Loading

                                                              A-6b
                                                              Change Terrazzo
                                                              Flooring
                                                              to Rubber

                                   Nurse               Main Entrance

                                           Administration
Architectural VM Items Summary
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50,000
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10,000
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40,000                                     lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225,000
         from sealed Conc to Rubber
     o   $20,000
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
Second Floor Plan                                              Fifth Grade

                                Fourth Grade

                  Third Grade

                                               Learning Commons
                                                  Media Center

                                                A-9c
                                                Change
                                                Innovation Space
                                                Floor to Rubber

                                     Art, Music & Innovation
             Outdoor Learning
                Classroom
Architectural VM Items Summary
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Centers (3)
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50,000
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10,000
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40,000                                     lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225,000
         from sealed Conc to Rubber
     o   $20,000
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
Second Floor Plan                                              Fifth Grade

                                                                             A-16
                                                                             Remove 3 Roof
                                Fourth Grade                                 Clerestory Monitors

                  Third Grade

                                               Learning Commons
                                                  Media Center

                                     Art, Music & Innovation
             Outdoor Learning
                Classroom
Roof Plan
            A-16
            Learning Commons
            Clerestories
Architectural VM Items Summary
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50,000
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10,000
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40,000                                     lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225,000
         from sealed Conc to Rubber
     o   $20,000
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
Salvage

              Cast Stone Scrolls   Plaques

Weathervane
Second Floor Plan                                                    Fifth Grade

                                      Fourth Grade

                        Third Grade

                                                     Learning Commons
                                                        Media Center

          A-22
          Reduce quantity of
          Salvage items:
          Decorative Stone
          Weathervane                      Art, Music & Innovation
                  Outdoor Learning
                     Classroom
Architectural VM Items Summary
Total: $425,000
•   S-01 Reduce Visual rooftop mechanical   •   A-16 Remove Learning Center
         screen at back (east) side                  Clerestory windows
     o   $45,000                                 o   $50,000
•   A-02 Reduce Media Center glass into     •   A-22 Reduce Salvage Items
         Cafetorium                              o   $10,000
     o   $5,000                                  o   Save 6 cast stone elements
•   A-6b Change Entrance Lobby from              o   Save Weathervane
         Terrazzo to Rubber Flooring        •   M-01 Provide Overhead VRF system in
     o   $40,000                                     lieu of displacement ventilation
•   A-9c Change Innovation Space floor           o   $225,000
         from sealed Conc to Rubber
     o   $20,000
•   A-12c Reduced Media Center Specialty
          Ceiling Qty.
     o   $30,000
Mechanical System Considerations & Recommendation
M-01 Provide Overhead VRF system in lieu of displacement ventilation $225k savings
    •   The current Displacement Air system is a good, tried and true system, however, given the Net Zero and all-Electric Systems and lower
        hot water temperature considerations there are compelling reasons to utilize an overhead VRF system. This is prompted primarily by
        educational space considerations – particularly within the classrooms and to realize beneficial cost savings and a simplified system:

• SMMA reviewed multiple systems during SD and DD to balance the various design goals
    •   Flexibility of the general classrooms
    •   Air quality
    •   Energy efficiency
    •   Ease of operations and maintenance
    •   Life cycle cost
• The single biggest factor that has evolved since early DD is the low hot water temperatures when a
  radiant heating system is employed – a requirement of the displacement ventilation model. This is a
  factor of an all-electric hot water heating system and has added extensive amounts of fin tube
  radiation at the classrooms -
    •   Impacts the teacher’s ability to easily move furniture to create multiple configurations as demanded by a modern classroom. As well as
        adding storage over time (always a drawback historically in classrooms with unit vents or radiant heat at the floor level (at the high school
        this was overcome with radiant ceiling panels – which are also not effective at lower hot water temperatures).
• Overhead system increases available floor area over Displacement air system
Mechanical System Considerations & Recommendation

• An overhead system will not compromise on energy efficiency (no change in the EUI target)
    •   VRF model shows slightly better energy savings
• LCCA
    •   Equipment is similar – and eliminates a lot of fin tube -
• Acoustics
    •   Improvements for the displacement system are not deemed cost effective given the sacrifice of room flexibility.
        Both systems meet required Noise Criteria (NC) level
• Ventilation Effectiveness
    •   Marginal benefits with Displacement system offer improved Ventilation effectiveness
        Both systems meet 100% fresh air requirements
    •   Overhead system eliminates colder air source/draft at floor
• Preparing for the Hardy project and keeping systems consistent and costs
    •   Will benefit this project and is more replicable for future conversions of other elementary schools in town
Mechanical Systems
Classroom Wing Perimeter Heat & Displacement Air
Mechanical Systems
Classroom Wing Perimeter Heat & Displacement Air
Mechanical Systems
Classroom Wing Overhead System
Architectural VM Items: Ongoing analysis
Total: $TBD
• A-00 Reduce Cost of façade materials
    •   In progress
• E-01 Reduce size of generator (not recommended – but anticipating finetuning for final design)
    •   $50k
    •   Maintain building temperature
    •   Future battery storage anticipated
January 1/21/2021 Meeting Agenda
Interior Design
  •   Interior Design Options: PCT Wainscot
  •   Classroom & learning Commons Updates
  •   Main Entrance Lobby updates

Exterior Design
  •   Façade Material Options
  •   Main Entrance updates

Site Design
  •   TBD Updates
Design Development Cost Estimate Overview

           Description                    DD              Control Budget            Delta to Budget

    Construction Estimate           $45,038,495            $45,061,000             ($22,505)
                                                                                (under budget)
    Add Off site Mitigation           $457,306

      Value Engineering              ($800,000)

                                                                                   ($365,199)
      Net Cost Estimate             $44,695,801            $45,061,000
                                                                                (under budget)

•    Previous SD Cost Estimate $45,329,275
•    76,478 GSF
•    $588.91 per GSF base estimate
•    In-depth reconciliation process; AM Fogarty reconciled estimate: $45,076,114
Budget Changes since Feasibility Study

• Received actual proposals from Commissioning Agents.
• Construction Schedule changed (due to CM schedule, COVID
  delay and longer pre-construction ramp phase)
• FF&E budget has been updated to include TLC program.
• PSI Permitting mitigation requirements
      (include post occupancy traffic study, offsite improvements)
• Potentially perform more extensive existing conditions survey of
  abutters property
Hunnewell Elementary School
   Construction Phase Budget Tracking
                                         Feasibility     Tracking     Potential Revised
                                        Construction    Potential     DD Construction
Description                             Phase Budget    Increases      Phase Budget
                                                                      Target November
Timeline                                  July 2019    January 2021
                                                                            2021

Tracking Cost Delta DD phase                           $1,074,156

Proposed VE for Acceptance &
                                                        ($822,505)
estimate savings

Subtotal Delta Tracking costs overage                   $251,651

Total Project Budget                     $52,853,000                     $53,104,651
Breakdown of Budget Increases
     Since Feasibility Phase
Consultants
       Commissioning                    $ 120,250
       Hazardous Materials              $ 20,000
       Traffic Studies (PSI required)   $ 15,000
       OPM Construction Phase           $ 91,000
Admin – Pre-condition survey            $ 77,600
Off-site Mitigations (PSI required)     $ 457,306 (pre-VE)
FF&E (TLC program)                      $ 73,000
Owner’s Contingency                     $ 220,000 (offset or transfer)
                             Total      $1,074,156

                                        $251,651 (with $822,505 VE)
Hunnewell Elementary School
Feasibility Study

  Thank you
You can also read