Pathways to Power: 2015 - REPORT
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
REPORT SCOTLAND 2015 Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030
© WWF Scotland A report for WWF Scotland by Gina Hanrahan, Climate and Energy Policy Officer WWF Scotland January 2015 Based on technical analysis conducted for WWF Scotland by DNV GL. WWF Scotland would like to thank the following people for their helpful advice and comments in the preparation of the technical report or this summary document. Dr. Mark Winskel (UKERC/University of Edinburgh) Prof. Gareth Harrison (University of Edinburgh) Nick Mohlo (now at Aldersgate Group) Joss Blamire (Scottish Renewables) Gordon McGregor (WWF Advisory Council) Jenny Banks (WWF-UK) Alexa Morrison (RSPB Scotland) Mary Church and Richard Dixon (Friends of the Earth Scotland) Sophie Billington (Cambridge Econometrics) Mike Hemsley and Alex Kazaglis (Committee on Climate Change) WWF Scotland The Tun 4 Jackson’s Entry Holyrood Road Edinburgh EH8 8PJ 0131 659 9100 wwfscotland.org.uk @WWFScotland Cover photo: © Paul Simon Wheeler Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 2
Contents Introduction: 5 Key findings 6 Key policy recommendations 10 Developing the Scenarios 14 Assumptions 16 Results of the Scenarios 18 The Generation Mix in a Decarbonised Power Sector 18 Results of the Scenarios 20 Fulfilling Renewables Ambition 21 Maintaining System Security 22 Security of Supply with Peak Demand and Low Renewables 23 Conclusion: 25 REFERENCES 26
© WWF–Canon / Fernando Zarur Scotland is one of the best locations globally for developing a renewables- based electricity system.
Introduction: With its powerful winds and waves and its strong tradition of engineering and innovation, Scotland is one of the best locations globally for developing a low-carbon, renewables-based electricity system. Decarbonising the power sector by 2030 is the cheapest, most effective pathway to hitting legally-binding climate targets, as the UK Committee on Climate Change has repeatedly shown. Not only does it tackle direct emissions from electricity, it also acts as a building block for developing low-carbon heat and transport options. The Scottish Government has rightly adopted this approach and is committed to largely decarbonising Scotland’s electricity sector by 2030 – with a target of 50g CO2/k w h. However, current policy to meet the 2030 decarbonisation target is high risk. Despite the slow pace of carbon capture and storage (CCS) development globally,1 the Scottish Government’s Electricity Generation Policy Statement 2013 (EGPS) assumes that CCS will be operating at scale in the next decade, fitted progressively across 2.5gw of gas plant. The Government has already risked high-carbon lock-in by granting consent to a major gas plant at Cockenzie as ‘CCS-ready.’ But with no guarantee that the technology will be commercialised in time, WWF Scotland commissioned international energy consultancy DNV GL to test whether current policy is fit for purpose, and to examine whether a future based almost exclusively on proven renewable technologies is possible. The good news is that we don’t have to rely on a high-risk strategy based on unproven CCS technology. In fact, a renewables-based, efficient, flexible, electricity system is perfectly feasible by 2030. Not only that – it is less dependent on imports from the rest of Great Britain at peak demand, is cheaper, and has lower emissions than current Scottish Government scenarios in the Electricity Generation Policy Statement. And critically, it makes more of Scotland’s abundant renewable resources and flourishing green energy industry, triggering economic, social and environmental benefits. …a renewables-based electricity system is perfectly feasible by 2030. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 5
Key findings: A fossil fuel Scotland can achieve a secure, decarbonised power and nuclear sector by 2030 with only renewables and minimal CCS-fitted gas power2. An almost entirely renewables- free system based Scottish system is possible with moderate efforts to reduce demand for electricity and ongoing work to is achievable reinforce the grid. The current pipeline of renewables and credible will be more than adequate to hit the decarbonisation target and allow for substantial export of electricity to the rest of Great Britain, particularly if Scotland makes perfectly feasible progress on energy efficiency. There is also an economic opportunity for further exports. A fossil fuel A system based almost entirely on renewables would be more secure than the current Scottish Government and nuclear scenario at peak demand, as long as the overall Great free system Britain (GB) system itself is secure.3 Great Britain- wide security will be delivered by a combination of is secure interconnection, storage, demand management and flexible back-up generation. Overall, Scotland can maintain and expand on its position as a net exporter of power with an almost entirely renewable electricity system. During infrequent periods of high demand and low renewables production, electricity will need to be imported from the rest of Great Britain, but ongoing and planned grid upgrades will be more than enough to accommodate this. During periods of high renewable production and lower demand, Scotland will export to the rest of Great Britain and beyond. This is increasingly the norm as European markets move towards greater interconnection. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 6
© Wild Wonders of Europe/Inaki Relanzon/WWF Scotland can achieve a secure, decarbonised power sector by 2030 with only renewables and minimal thermal power. A fossil fuel The cost of the additional generation capacity needed and nuclear to hit the 2030 target in a renewables-based system is smaller (£663m/yr) than the cost of a system with CCS- free system fitted thermal plant (£1.85bn/yr), because the cost of new wind power is lower than the cost of CCS. 4 is cheaper The cost of a renewables-based system is broadly similar to the cost of generating the same amount of unabated gas-fired electricity. A fossil fuel While all scenarios considered achieve the decarbonisation target, it could easily be breached if the and nuclear Scottish Government’s CCS gamble does not pay off and free system unabated gas plants are operating in 2030. Unabated gas power would generate 6.6 million more tonnes of means lower carbon dioxide annually than if CCS is operating at scale,5 radically undermining Scotland’s ability to hit its climate climate risk targets. The climate risks are lower in a scenario that relies on proven renewables, already under construction or consented. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 7
Box 1. Scotland’s 2020 and 2030 targets – what’s the difference? Scotland’s 2020 target is to meet Scotland’s 2030 target is to achieve 100% of its electricity demand from power sector carbon intensity of 50g renewables. It is well on track to hitting CO2/k w h or lower. The latest available this, at 46% in 2013. It’s estimated that figures (2011) show that Scotland’s grid 14-16gw of renewables capacity will be intensity is approximately 271gCO2/ needed to hit the target and there is k w h,6 considerably less than the rest more than enough in the pipeline to do of the UK due to Scotland’s thriving so (see Box 5). However, the renewables renewables sector. The target could capacity needed may be lower if the be theoretically be achieved using a current trend of declining electricity variety of low carbon technologies, demand continues. The 2020 target is including renewables, nuclear, and not a carbon intensity target and places fossil fuel plants fitted with carbon no restrictions on the amount of fossil capture and storage, although the fuel generation on the system. In fact, Scottish Government rightly sees no the Scottish Government has clearly role for nuclear in its vision of the stated that it envisages thermal power future electricity sector. continuing ‘to play an important role’ in Scotland’s energy future. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 8
© WWF/CANON Box 2: What role for Carbon Capture and Storage? While Scotland’s abundant renewable resources mean it can enjoy a clean, renewable electricity supply, carbon capture and storage (CCS) has the potential to play a role in cutting emissions globally from existing (fossil fuel) power plants while we transition to a 100% renewable energy future, as well as in decarbonising heavy industry, which currently has few alternatives for reducing emissions other than CCS and biomass. Scotland has the opportunity to demonstrate CCS technology at Peterhead and WWF’s support for CCS is limited to the demonstration programme. For this reason we have included a minimum of 340mw of CCS at Peterhead in all scenarios studied. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 9
Key policy recommendations: Scotland does not need any fossil fuel power stations operating by 2030 so the Scottish Government should not consent new plants as CCS- ready The Scottish Government does not need to grant life extensions for nuclear plants into the 2030s The UK Government needs to stop incentivising coal The UK Government needs to make Electricity Market Reform work better for offshore wind Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 10
© National Geographic Stock/Sarah Leen/WWF The UK Government must show strong ambition for renewables growth and clarity about the future market for renewables post-2020 as soon as possible in order to drive investment The UK and Scottish Governments must work with industry to ensure that the wave and tidal sectors are adequately supported The UK and Scottish Governments must continue working with industry towards a solution to the problem of affordable and timely grid connection for the Western Isles, Orkney and Shetland Greater effort is needed from the UK and Scottish Governments on electricity demand reduction as it requires less new generation capacity to achieve power sector decarbonisation The UK and Scottish Governments need to work with industry to incentivise investment in pumped storage Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 11
Key policy recommendations: 1 Scotland does not need any fossil fuel power stations operating by 2030 so the Scottish nuclear stations to help maintain security of supply once safety standards are met.8 DNV GL’s analysis shows that Government should not consent there is no need for nuclear to still be new plants as CCS-ready operating in 2030 to maintain security A system based almost entirely on of supply. Thermal renewables is feasible and desirable Power and therefore life-extending coal plants or building new gas plants is unnecessary. However, should new gas 3 The UK Government needs to stop incentivising coal Efforts to decarbonise power supply plants be built in Scotland they must are being undermined by policies that have operational CCS from the outset. are incentivising life extensions to Consenting plants as ‘CCS-ready’ risks coal, including the failure to apply an breaching the decarbonisation target Emissions Performance Standard to and locking Scotland into a high-carbon existing coal plants; the freezing of the future. Operating a gas plant like the carbon floor price; and the fact that one consented at Cockenzie at more than revenues from the capacity market may 50% capacity factor would, for instance, well exceed the cost of compliance with exceed the target in most credible the Industrial Emissions Directive.9 The scenarios.7 UK Government should provide a clear regulatory signal through a progressively 2 The Scottish Government does not need to grant life extensions for nuclear plants into tightening Emissions Performance Standard for existing coal from 2023 to give lower carbon generation clear the 2030s incentives to invest and the Scottish The Scottish Government has stated Government should champion this that, while it does not support new approach, including in the five year nuclear in Scotland, it is open to life review of the UK Energy Act. extensions for Scotland’s existing £££ 4 5 The UK Government needs The UK Government must to make Electricity Market show strong ambition for Reform work better for offshore renewables growth and clarity wind about the future market for Clear volume signals and foresight renewables post-2020 as soon The Investment about available funding are needed to create the conditions for long-term, as possible in order to drive investment Climate for sustainable investment in offshore A future UK framework needs a 2030 Renewables wind, boost the domestic supply chain power sector decarbonisation target of and accelerate cost reductions. The 50g CO2/k w h, clarity about the post- enduring regime under Electricity 2020 Levy Control Framework, and a Market Reform is currently constraining prompt and firm decision on the Fifth growth to around 8-900mw equivalent Carbon Budget in 2016, all based on the to around one project under the first advice of the UK Committee on Climate allocation round across the whole of Change. The current lack of ambition the UK, which could severely restrict and certainty risks stymying investment growth in Scotland. in an industry with long-lead in times and a need for deployment at scale to drive learning and cost-reductions. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 12
6 The UK and Scottish Governments must work with industry to ensure that the wave 7 The UK and Scottish Governments must continue working with industry towards and tidal sectors are adequately a solution to the problem of supported affordable and timely grid The sectors are at risk of being ignored connection for the Western Isles, in the short-term. Given their long-term Orkney and Shetland economic potential, both Governments Once connected, the islands would need to support the wave and tidal produce several hundreds of mw of industries to ensure that connection onshore wind generation at costs issues, transmission charging, and significantly cheaper than offshore Electricity Market Reform do not impede wind. This would also provide major progress in what could potentially economic and social benefits to remote be a major long-term contributor to and rural areas, and, critically, could power sector decarbonisation, with the enable the demonstration and long-term potential to deliver up to 20% of UK commercialisation of wave and tidal electricity by 2050.10 arrays at reasonable connection cost. 8 Greater effort is needed from the UK and Scottish Governments on electricity and through constructive engagement with the EU on efficiency standards for electrical appliances. At a Scottish demand reduction as it requires level, a clear electricity demand less new generation capacity reduction strategy is required, using Reducing to achieve power sector Scottish powers and policy levers to decarbonisation the full to ensure continued decoupling Demand and Moderate demand reduction (of 1% year) of economic growth and electricity will allow Scotland to decarbonise the demand, and to ensure that negawatts Enhancing grid well within the current renewables – electricity savings – receive greater Flexibility pipeline. Making efforts on demand policy attention. reduction would help to insulate Scotland from uncertainties about future electricity and renewable energy policy at UK and EU levels and enhance 9 The UK and Scottish Governments need to work with industry to incentivise security. By reducing demand and in investment in pumped storage turn pressure on supply infrastructure, Despite its important role in storing it could help protect households against energy generated from variable rising energy bills while achieving renewables and in providing balancing decarbonisation more cost-effectively. services to ensure security of supply, While there has been progress in pumped storage is not recognised under reducing electricity demand in recent the current UK Electricity Market years in Scotland, it is important that Reform regime. Notwithstanding its the downward trend continues and clear benefits, and the fact that consent economic recovery does not lead to for a major project is already in place in surging demand. Scotland with another included in the National Planning Framework, there At a UK level, electricity demand is no mechanism to enable investment reduction could be incentivised through decisions to be taken. A solution must improvements to the UK capacity be found that unlocks the potential market which would prioritise demand of pumped storage to contribute to a reduction, through the introduction flexible decarbonised grid. of an energy efficiency feed in tariff, Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 13
Developing the Scenarios: We commissioned a technical report by respected international energy and engineering consultancy DNV GL (incorporating Garrad Hassan) – the world’s largest renewables advisory – which was reviewed independently. DNV GL investigated a range of scenarios for power sector decarbonisation in Scotland which are technically and economically possible. Here we focus in depth on the two which represent current Scottish Government policy and WWF’s preferred scenario. The first is termed the ‘High Climate Risk ’ scenario. This generation scenario is based on current Government policy as set out in the Electricity Generation Policy Statement (which is in turn based on modelling conducted by SKM). CCS is commercialised and fitted across 2.5gw of thermal power. Elsewhere energy and climate issues, especially energy efficiency, have relatively low political priority. Regulatory, market and public acceptance barriers remain for pumped storage. The second is termed the ‘Low Climate Risk ’ scenario. CCS is not commercialised beyond a single demonstration plant at Peterhead and no other gas, coal or nuclear plant exists on the system. Elsewhere there is high political priority for energy and climate issues, a strong policy drive and public acceptance, with moderate, but sustained, efforts to reduce energy demand, high uptake of electric vehicles (EVs), and low barriers to building new pumped storage. The axes on which the scenarios vary are: • Demand: How much • Flexibility: How much • Carbon Capture and progress will be made on progress will be made Storage: Will CCS be energy efficiency and the on pumped storage and developed beyond a electrification of heat demand response? single demonstration and transport?11 plant at Peterhead? Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 14
High Climate Risk Low Climate Risk Scenario, Scenario, (Weak Policy Drive, (Strong Policy Drive, High CCS) Low CCS) Electricity Demand Increased underlying demand, and some Moderate efforts on energy efficiency electrification of heat and transport outweigh increased electric heating and outweigh energy efficiency improvements. electrification of transport. Transport demand is stabilised System Flexibility Some increase in pumped-storage capacity, Substantial additional pumped-storage and limited demand response some demand response Fossil fuel generation 2500mw 340mw (Peterhead) fitted with CCS Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 15
Assumptions High Climate Risk Scenario Low Climate Risk Scenario Higher Demand: Lower Demand: 18% It assumes electricity demand increases by 18% to 43.1 TWh It assumes lower electricity demand of 30.5 TWh in 2030. assumed electricity in 2030, in line with previous This equates to a 17% reduction 17% demand increase forecasting for the Scottish on current levels and a 1% annual Government by SKM.12 Efforts assumed electricity reduction (broadly in line with on energy efficiency are offset by demand decrease National Grid’s Slow Progression increased electrification of heat Scenario).13 Energy efficiency and transport. improves rapidly, by 2030 half of all new car sales will be electric Lower Flexibility: (750,000 electric vehicles overall), and transport demand stabilises. It assumes that deployment of While there is a relatively high non-hydro energy storage and uptake of air and ground source demand response measures heat pumps, electricity demand are hampered by technical and from heat is reduced overall due 1340MW regulatory barriers and don’t contribute to meaningful ‘load to uptake of energy efficiency and low-carbon options. pumped storage capacity shifting’ before 2030. 600mw of new hydro pumped storage proceeds (there is already Higher flexibility: planning consent for this scale It assumes that there is significant at Coire Glas), resulting in a growth in storage and demand total pumped storage capacity response, with hydro pumped of 1340mw and 46gw h. At peak storage remaning the dominant periods, demand response (e.g. deferred electric vehicle charging) 2540MW technology in Scotland. Three new 600mw pumped storage schemes pumped storage is conservatively assessed at capacity are built by 2030, resulting in 100mw. total capacity of 2540mw and 106gw h. At peak periods, demand Higher CCS: response (e.g. deferred EV charging or heat pump use) is It assumes that there is 2.5 gw of conservatively assessed at 500mw. existing or new gas plant fitted with CCS by 2030, building on the Scottish Government’s Electricity Lower CCS: Generation Policy Statement. It assumes that CCS fails to reach commercialisation beyond a single demonstration gas plant at Peterhead of 340mw by 2030. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 16
© National Geographic Stock/Jason Edwards/WWF Box 3: Scottish Government Assumptions for Thermal Power The Scottish Government’s assumptions for electricity generation are as follows: co2 Coal: Gas: CCS: Nuclear: Longannet 2gw of new gas 500mw of Torness and (2.4gw) will plant will be CCS-fitted gas Hunterston will close in 2020 operating by plant will be be closed by 2020 operating by 2030 2020, with 1.6gw in operation by 2027 Overall: 2.5 gw of thermal plant will be operating by 2030, progressively fitted with CCS. While the closure dates for coal and nuclear plant are not certain, currently there are no indications that they will be running in 2030. However, their closure depends on a range of regulatory and commercial considerations, including the signals provided by the capacity market, the carbon price, fuel costs and other factors. Recently, Scottish Power decided not to progress Longannet in the UK capacity market auction, increasing the likelihood of its closure by 2020. Box 4: Hydro Power Both scenarios assume 2.5gw of hydro (of which 1.5gw is already in place). There is approximately 1.2 gw of run of the river hydro technically and financially available in Scotland, the bulk of which is assumed to be developed by 2030, although some uncertainties around support for hydro are currently impeding developers. Should this level of hydro fail to be developed, the shortfall could easily be met by other renewables such as onshore wind or solar photovoltaics. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 17
Results of the Scenarios The Generation Mix in a Decarbonised Power Sector Generation Mix, High Climate Risk Scenario PRODUCTION HIGH RISK CAPACITY FACTOR HIGH RISK CCS HYDRO CCS ONSHORE WIND HYDRO MARINE (OFFSHORE, WIND, WAVE AND TIDAL) SOLAR PV ONSHORE WIND BIOMASS MARINE (OFFSHORE, WIND, WAVE AND TIDAL) SOLAR PV Capacity BIOMASS Factor Production GENERATING CAPACITY HIGH RISK CCS HYDRO DNV GL developed ONSHORE WIND MARINE (OFFSHORE, WIND, WAVE AND TIDAL) a generation mix SOLAR PV for each scenario, BIOMASS shown here, building on the assumptions Generating Capacity Fraction of gross consumption outlined on page from renewables 25.6 TWh, 59% 16. It’s important to stress that the scenarios have been conservatively designed to consider only the minimum level of renewables required to decarbonise Capacity and should not be Source Factor Generating Capacity Production seen as a cap on CCS 0.8 2500 MW (defined by scenario) 17.5TWh overall renewables Hydro 0.34 1500 MW existing 7.4 TWh total ambition. In 1000 MW extra assumed practice, there is likely to be more Onshore wind 0.29 4500 MW existing capacity (2013). 11.4 TWh from existing capacity. 1000 MW extra assumed. 2.5 TWh from assumed additional capacity renewables built Marine (offshore wind, 0.45 190 MW existing offshore wind 0.7 TWh from existing capacity. than assumed wave and tidal) capacity. below (see Box Solar PV 0.08 116 MW existing. 0.1 TWh from existing capacity. 5 on Scotland’s Biomass 0.8 140 MW existing 3.5 TWh total Renewable Power 360 MW extra assumed Pipeline). Total 43.1 TWh Fraction of gross consumption from renewables 25.6 TWh, 59% Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 18
The scenarios have been conservatively designed to consider only the minimum level of renewables required to decarbonise, and should not be seen as a cap on overall renewables ambition. Generation Mix, Low Climate Risk Scenario PRODUCTION LOW RISK CAPACITY FACTOR HIGH RISK CCS CCS HYDRO ONSHORE WIND HYDRO MARINE (OFFSHORE, WIND, WAVE AND TIDAL) ONSHORE WIND SOLAR PV BIOMASS MARINE (OFFSHORE, WIND, WAVE AND TIDAL) SOLAR PV Capacity BIOMASS Factor Production GENERATING CAPACITY LOW RISK Box 5: Scotland’s CCS Renewable Power HYDRO Pipeline ONSHORE WIND MARINE (OFFSHORE, WIND, WAVE AND TIDAL) SOLAR PV The latest figures14 BIOMASS show that Scotland has 7.1 gw of installed Generating Capacity Fraction of gross consumption renewable electricity from renewables 28.5 TWh, generation capacity, 92% with an additional 6.2 gw either under construction or consented, the majority of which is expected from onshore wind. Including projects in planning, this Source Capacity Generating Capacity Production Factor figure totals 20.4 CCS 0.8 340 MW defined by scenario 2.4 TWh gw – nearly three Hydro 0.34 1500 MW existing 7.4 TWh total times the level of 1000 MW extra assumed renewables currently deployed. While a Onshore wind 0.29 4500 MW existing capacity (2013). 11.4 TWh from existing capacity. 2100 MW extra assumed to be 5.4 TWh from assumed additional capacity certain amount of constructed. attrition is inevitable, Marine (offshore wind, 0.45 190 MW existing offshore wind 0.7 TWh from existing capacity. there is more than wave and tidal) capacity. enough renewable Solar PV 0.08 116 MW existing. 0.1 TWh from existing capacity. capacity in the Biomass 0.8 140 MW existing 3.5 TWh total pipeline to hit future 360 MW extra assumed targets. Total 30.9 TWh Fraction of gross consumption from renewables 28.5 TWh, 92% Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 19
Results of the Scenarios Both scenarios show that the current renewables pipeline will easily allow Scotland to meet the decarbonisation target. The High Climate Risk Scenario requires an additional 1 gw of onshore wind (which is already under construction), while the Low Climate Risk Scenario relies on an additional 2.1 gw of onshore wind (which is already consented). The mix within the scenarios should not be seen as the only way to hit the target. Other renewable technologies, such as well-sited offshore wind or solar PV, could easily form a larger part of the mix. For instance, solar PV units have dropped in price by two-thirds between 2009 and 201315, leading to growing uptake on domestic and commercial buildings in the UK. Solar PV output was up 67% in Q2 2014 against the same period in 2013, reaching over 4gw of installed capacity across the UK, though less than 200mw are currently installed in Scotland.16 However, the scenarios crucially don’t depend on future solar growth – only on wind capacity already consented.17 Box 6: Reducing Electricity Demand How successful Scotland is in reducing electricity demand will determine how easily it hits its decarbonisation target. After all, the cheapest, cleanest and most secure energy is the energy that is never used and reducing demand is cheaper and less technically challenging than building new generation capacity. In fact, the scenarios show that a perfectly feasible demand reduction of 1% annually will allow Scotland to hit the 2030 target well within the current renewables pipeline, even allowing for the electrification of heat and transport. Electricity demand 1% has reduced in Scotland in recent years (about 3% per year between 2008 and 2012, though this is affected by a weak economy). The Scottish Government assumes increasing demand long-term as a result of increased electrification of heat and transport,18 supported by analysis for the Scottish Government by SKM, which forecast demand rising by 18% to demand 2030. This assumption is based on rising demand from heat and transport electrification. DNV GL analysis shows that, despite growing electrification of reduction heat, heat demand falls due to insulation and a switch from resistive heating to per year heat pumps. This nearly offsets the growth in demand from Electric Vehicles.19 will allow Analysis by National Grid for the Future Energy Scenarios20 report supports more conservative assumptions about demand growth to 2030 than the Scottish Scotland to Government. In the Slow Progression Scenario, demand falls by 6% between 2013 and 2035 (driven by energy efficiency, improved lighting and lower hit the target industrial output), while in the Gone Green Scenario, it rises by 6% by 2035 well within (driven by heat and transport electrification and greater industrial output, after falling initially). Ofgem recently highlighted, however, that “structural changes the current might be taking place” in the relationship between the economy and electricity demand, as a drop in demand in 2013/14 happened “against a backdrop of the renewables strongest economic growth in GB since the economic crisis”.21 pipeline E3G analysis points to clear evidence that with the right incentives electricity demand reductions of 2% per year are achievable Great Britain-wide.22 There is approximately 32TWh/year of electricity demand reduction technical potential available GB-wide according to analysis for DECC.23 Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 20
Fulfilling Renewables Ambition Scotland has the potential to be a renewable powerhouse within the UK and Europe, with over 25% of Europe’s offshore wind and tidal power and 10% of its wave power.24 It has a strong track record on renewable electricity and is making steady progress towards its target of meeting 100% of demand from renewables by 2020. Renewables are already the largest source of power generation in Scotland, outstripping nuclear, coal and gas.25 125% The Low Climate Risk Scenario allows Scotland to have an almost wholly renewable generation system (with only 340mw of gas plant fitted with CCS) and to meet almost all of its needs from renewables – 92%. This contrasts with the High Climate Risk Scenario, where only 59% of Scotland’s needs are met from renewables. Given that needs met Scotland has a 100% target by 2020, and a magnificent resource base, it would send a confusing signal to dilute Scotland’s renewables ambition to less than two-thirds of Scotland could maintain and even build on its role as an what it currently is. exporting nation. Indeed, the Low Climate Risk Scenario would easily allow Scotland to meet 100%, 125% or potentially even more of Scotland’s needs from renewables.26 This would not only allow Scotland to maintain its status as a net power exporter, it would actually allow Scotland to become a net exporter of green power. Reaching 125% could be done with only a portion of the level of onshore and offshore wind already consented (for instance around half the currently consented offshore wind capacity in Scotland) and ongoing grid upgrades will easily accommodate this level of export.27 By contrast, meeting 125% of Scottish demand from renewables in the High Climate Risk scenario, though possible, would be more technically and economically challenging, requiring a large amount of new renewables capacity and related transmission infrastructure to be built, beyond what’s currently under discussion. The graph below sets out how much additional capacity would be required to hit the 2030 decarbonisation target and what capacity over and above this will be needed to hit more ambitious renewables goals. By 2030, further Onshore Meet 100% of Meet 100% of Meet 125% of Total Installed Wind Capacity (or Demand Demand from Demand from Capacity28 equivalent) required Renewables Renewables at 125% of to hit decarbonisation demand from target and… renewables High Climate Risk 1GW +7GW +4GW 16.5GW Scenario (4.5GW existing) Low Climate Risk 2.1GW +0.9GW +3.1GW 10.6GW Scenario (4.5GW existing) The 125% figure should not be seen as a cap on renewables growth, however. There is a huge amount of further renewable energy capacity available in Scotland, especially in the offshore sectors, which could be exported as an economic opportunity and to assist in meeting wider UK or EU climate and renewables goals. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 21
Maintaining System Security Maintaining system security during periods of high electricity demand and low renewable production is critical, even though this will be a relatively infrequent System occurrence as high demand for electricity in winter often coincides with high wind output. Where there is any shortfall between demand and supply, this can safely security can be and securely be met by imports from the rest of Great Britain or Europe through achieved interconnection, more efforts to manage Scottish demand, or back-up gas plants based in Scotland, depending on the economic case for each. without any For all scenarios, DNV GL stress tested system security in a worst case scenario - conventional with peak demand for electricity (e.g. winter evenings), low renewables generation and assuming that the largest power plant on the system wasn’t working. The coal, gas results show a much smaller gap between demand and supply in the Low Climate or nuclear Risk scenario than the High Climate Risk Scenario as demand is lower and there is substantially more pumped storage. in Scotland The Low Climate Risk Scenario is less vulnerable from a security of supply provided that perspective, requiring Scotland to import less electricity to meet peak demand. the GB system itself is secure Box 7: Securing the GB system Studies have shown that a secure GB system is perfectly feasible with high levels of renewables. The Committee on Climate Change, National Grid and others have published long-term decarbonisation scenarios that maintain system security.29 While the GB capacity margin is expected to tighten over the next two years before rising again, Ofgem’s 2014 capacity assessment stresses that the new balancing tools available to National Grid and the forthcoming capacity market will lessen the risks of supply disruptions.30 A suite of new interconnection projects will also boost security of supply for GB as a whole. Most decarbonisation scenarios show significant amounts of new build gas-fired generation providing peaking and balancing services to complement renewables, operating ultimately at low capacity factors though working initially at high loads to recoup capital costs.31 While it is feasible that some of this generation could 50% capacity be based in Scotland, given the transmission regime, it is likely to be cheaper to locate it closer to major demand centres further south. DNV GL’s analysis shows analysis shows that while, in principle, a major gas plant that while, in principle, a major gas plant could be located in Scotland, it would could be located in Scotland, have to operate at a relatively low capacity factor (
Security of Supply with Peak Demand and Low Renewables Less: Demand Potential Plus: Loss of response shortfall at largest unit in available at Scenario peak demand Scotland peak demand Net shortfall High Climate Risk 2200 mw 1250 mw 100 mw 3350 mw (CCS unit) Low Climate Risk 900 mw 600 mw 500 mw 1000 mw (pumped- storage unit) It is important to stress that ongoing grid upgrades, including a subsea bootstrap on the west coast, will be enough to cover any shortfall between supply and demand well before 2020 in both scenarios. So system security can be achieved without any conventional coal, gas or nuclear capacity in Scotland, provided that the GB system itself is secure. Ultimately, as Scotland is part of the GB electricity system, which is operated and regulated as one system, security of supply is most effectively and a green cheaply delivered at GB level.32 electricity DNV GL also considered a range of technical issues relating to system stability grid must and balancing (such as black start, inertia and frequency control).33 While there are a number of challenges that will need to be addressed in the transition to a move away renewables-dominated system, DNV GL is confident that these can be managed in Scotland, and technologies such as pumped storage will have an important role to from a system play in this respect. National Grid is currently working on a range of regulatory and optimised technical options to mitigate any potential effects on the operation of the grid, which will ensure that system stability remains robust in the transition to a decarbonised around electricity system across Great Britain.34 conventional Ultimately, the future electricity grid must move away from a system optimised ‘baseload’ around conventional ‘baseload’ power plants, which run all the time, towards a system where renewables become the new ‘baseload’, supplemented by flexible power plants back-up generation, demand side response, storage (including heat storage) and interconnection. Many of the technologies that will underpin this system already exist. However, the current incentive structures in place do not adequately reward the electricity system services of the future.35 Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 23
© Aquamarine power ltd The Low Climate Risk Scenario is a credible, pragmatic way of meeting Scotland’s decarbonisation target. Pursuing this pathway would allow Scotland to maintain and build on its reputation as a renewable powerhouse. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 24
Conclusion: The two scenarios outlined present alternative blueprints for decarbonising Scotland’s power sector in 2030 – one where gas power fitted with CCS still has a big role to play, and one where Scotland moves beyond conventional generation and maintains strong renewables ambition. First and foremost, the High Climate Risk Scenario is – as the name suggests – higher risk from a climate perspective because it relies on CCS rather than proven renewable technologies. Pursuing a future energy policy reliant on a technology that has not been commercialised is a high stakes game that could derail delivery of Scotland’s Climate Act and distract from progress on renewables. Furthermore, while the High Climate Risk Scenario achieves the decarbonisation target, it provides a weaker foundation for Scotland’s renewables ambition (meeting less than two-thirds of demand from renewables in the decarbonisation scenario) and presents technical and economic challenges to delivering stretch renewables targets. It is also more expensive than the alternative, due to the relative cost of CCS compared to wind, and has higher import dependency on the rest of Great Britain at peak demand. With its reliance on fossil fuels, it continues to expose Scotland to gas price volatility, which has been the main driver of fuel poverty and rising energy bills, and continues the dependence on gas imports from overseas, including politically unstable regions, which undermines energy security. The Low Climate Risk Scenario is a credible, pragmatic way of meeting Scotland’s decarbonisation target. It means Scotland would have an efficient, flexible system based almost entirely on renewables which would meet almost all of Scottish demand and even allow for substantial exports of renewable power, all within the current renewable pipeline. Scotland could maintain and even expand on its position as an electricity exporting nation, maximising the economic opportunities presented by further renewables growth. The Low Climate Risk Scenario is cheaper to achieve than the Scottish Government’s favoured alternative and has a lower import dependency at peak demand. Pursuing this pathway would allow Scotland to maintain and build on its reputation as a renewable powerhouse. If there is enough political will to commit to a renewable powered future, it’s clear that Scotland does not need to take a high stakes gamble on CCS. Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 25
REFERENCES 1 I EA (2014) Tracking Clean Energy Progress: www.iea.org/publications/freepublications/ publication/Tracking_clean_energy_progress_2014.pdf 2 We’ve included 500mw of biomass and a minimum of 340mw of gas plant fitted with CCS in our scenarios. See Box 2 to explain the role of CCS and WWF’s position on the technology. See Section 4 of the Technical Report where credible generation mixes are developed. 3 or full details of the security of supply implications of the report’s scenarios, see Section 4.4. of F the Technical Report. 4 hile the two scenarios compared in this summary vary in terms of energy demand and system W flexibility, even with the same assumptions about demand and flexibility, the scenarios with CCS have higher costs. See Section 5.7 of the technical report for a discussion of the cost implications. This considers the levelised cost of additional generation capacity. This per mw h price includes the costs of building, operating, and decommissioning, including the carbon costs, but not wider costs such as network costs or air pollution costs. In terms of transmission costs, no extra transmission capacity will be required between Scotland and the rest of Great Britain in the scenarios beyond what’s already planned but grid reinforcement and new capacity will be needed at a GB level, with an estimated capital investment of £2bn between 2020 and 2030, according to the UK Committee on Climate Change. The costs represent only a fraction of the cost of generation. 5 See Technical Report Table 5.1 6 he Scottish Greenhouse Gas Annual Emissions Target Report 2012: T www.scotland.gov.uk/Publications/2014/10/5292 7 See Technical Report Table 5.1 8 ee for instance, First Minister Alex Salmond’s letter to EDF energy: S www.scribd.com/doc/237414552/Letter-Alex-Salmond-to-Vincent-de-Rivaz-180614 9 ee Gross, R., Speirs, J., Hawkes, A., Skillings, S., and Heptonstall, P. (2014): Could retaining old S coal lead to a policy own goal? Imperial College London: http://assets.wwf.org.uk/downloads/ wwf_coal_report_imperial_college_final.pdf for a discussion of how the UK policy regime on coal is undermining climate policy. 10 See DECC (2013): https://www.gov.uk/wave-and-tidal-energy-part-of-the-uks-energy-mix 11 T hroughout this report, electricity demand is defined as Gross Consumption. This is defined as total electricity generated within Scotland, less net exports. It therefore includes energy consumed in transmission and distribution losses before it reaches consumers, and by generators (‘own use’). Total Consumption is an alternative definition, which is defined as total electricity generated, less net exports, losses and ‘own use’. These definitions are taken from Scottish Government, “Energy in Scotland 2014”, February 2014. [Online]. Available: www.scotland.gov.uk/ Resource/0044/00444530.pdf Gross Consumption is more appropriate in this study, as it includes an estimate of transmission and distribution losses. 12 S KM (2012) Scottish generation scenarios and power flows: www.scotland.gov.uk/ resource/0039/00393483.pdf 13 S ee National Grid’s Future Energy Scenarios (2013): http://www2.nationalgrid.com/mediacentral/ uk-press-releases/2013/national-grid-s-uk-future-energy-scenarios-2013/ 14 D ECC, Renewable Energy Planning Database, July 2014: https://restats.decc.gov.uk/cms/ planning-database/. 15 IRENA (2014) REthinking Energy: www.irena.org/rethinking/Rethinking_FullReport_web.pdf 16 S ee DECC’s quarterly energy statistics: https://www.gov.uk/government/statistics/energy-trends- section-6-renewables 17 F or a vision for future solar growth in Scotland, see Solar Energy – a viable contributor to renewables in Scotland: http://siser.eps.hw.ac.uk/docs/a__solar_vision_for_scotland.pdf 18 S cottish Government (2013) Low Carbon Scotland – Meeting our Emissions Reduction Targets 2013-2017 – the Second Report on Policies and Proposals: www.scotland.gov.uk/Topics/ Environment/climatechange/scotlands-action/lowcarbon/meetingthetargets p104 Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 26
19 See Technical Report, p9 20 National Grid Future Energy Scenarios 2014: http://www2.nationalgrid.com/uk/industry- information/future-of-energy/future-energy-scenarios/ 21 O fgem, Electricity Capacity Assessment Report 2014: https://www.ofgem.gov.uk/ofgem- publications/88523/electricitycapacityassessment2014-fullreportfinalforpublication.pdf . Skillings, E3G (2014): The demand side of the electricity market. Why we’re still failing and 22 S how to succeed: www.e3g.org/library/electricity-demand-side-measures-why-were-still-failing- and-how-to-succeed 23 D ECC (2013). Impact Asessment of Electricity Demand Rudction - Amendment to Market Caluses: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/246126/Impact_ Assessment_for_Electricity_Demand_Reduction_Policy_Options_FINAL.pdf 24 See www.scotland.gov.uk/topics/marine/marineenergy 25 S ee Scottish Renewables (2014). Historic milestone as new figures show renewables now Scotland’s largest source of power: www.scottishrenewables.com/news/historic-milestone-new-figures- show-renewables-now/ 26 T he possibility of delivering 125% of demand from renewables was raised in the Scottish Government’s Electricity Generation Policy Statement, based on the generation scenario developed: www.scotland.gov.uk/Resource/0042/00427293.pdf. 27 See Technical Report 28 F rom onshore wind – other technology balances are possible and would yield different installed capacity figures. 29 S ee for instance Committee on Climate Change (2013): Next Steps on Electricity Market Reform: www.theccc.org.uk/publication/next-steps-on-electricity-market-reform-23-may-2013/ Committee on Climate Change (2011): www.theccc.org.uk/publication/the-renewable-energy- review/ National Grid, Future Energy Scenarios (2014): http://www2.nationalgrid.com/uk/industry- information/future-of-energy/future-energy-scenarios/ Poyry (2011): Analysing Technical Constraints on Renewables Generation: http://archive. theccc.org.uk/aws/Renewables%20Review/232_Report_Analysing%20the%20technical%20 constraints%20on%20renewable%20generation_v8_0.pdf WWF-UK (2011): Positive Energy – how renewable electricity can transform the UK by 2030: http://assets.wwf.org.uk/downloads/positive_energy_final_designed.pdf?_ga=1.262687496.5420 84774.1394123155 30 O fgem (2014): Electricity Capacity Assessment Report 2014: https://www.ofgem.gov.uk/ofgem- publications/88684/electricitycapacityassessment2014-supplementaryappendices.pdf 31 See UKERC (2013) The UK Energy System in 2050: Comparing Low Carbon Resilient Scenarios. lanned grid reinforcement is anticipated to deliver 6.5gw of interconnection between Scotland 32 P and the rest of Great Britain by 2016, rising to 8.5gw by 2020 and up to 13gw by 2025. 33 See the Technical Report Section 4.4. for a full analysis of these issues. 34 N ational Grid (2014) System Operability Framework: http://www2.nationalgrid.com/UK/ Industry-information/Future-of-Energy/System-Operability-Framework/ 35 F or a compelling vision of how Germany is envisaging the future electricity system under the Energiewende, see Agora Energiwende (2014)12 insights into Germany’s Energiewende: www.agora-energiewende.org/fileadmin/downloads/publikationen/Impulse/12_Thesen/ Agora_12_Insights_on_Germanys_Energiewende_web.pdf Pathways to Power: Scotland’s route to clean, renewable, secure electricity by 2030 | 27
Renewable energy in numbers 100% • Pathways to Power RECYCLED 50g co2/kwh Scotland’s 2030 power sector decarbonisation 32% target. Renewables generated 32% more power than any other form of electricity generation in Scotland the first half of 2014. 11.9m tonnes co2 Emissions displaced by Scotland’s renewables in 2013. That’s more 11,695 than Whythe we entire transport sector! are here Renewables jobs in RL To stop the degradation of the planet’s natural environment and Scotland in 2013 to build a future in which humans live in harmony and nature. WWFscotland.ORG.UK Why we are here To stop the degradation of the planet’s natural environment and gular to build a future in which humans live in harmony with nature. wwfscotland.org.uk WWF-UK, registered charity number 1081247 and registered in Scotland number SC039593. A company limited by guarantee number 4016725 © 1986 panda symbol and ® “WWF” Registered Trademark of WWF-World Wide Fund For Nature (formerly World Wildlife Fund), WWF-UK Panda House, WeysidePark, Godalming, Surrey GU7 1XR, t: +44 (0)1483 426333, e: wildworld@wwf.org.uk, wwf.org.uk
You can also read