Open Networks 2021 Flexibility Consultations Summary and Response 16 December 2021 - Energy ...

Page created by Derrick Parker
 
CONTINUE READING
Open Networks
2021 Flexibility Consultations
Summary and Response
16 December 2021

                                 1
Background
ENA Open Networks undertook the following consultations to seek views from stakeholders on
developments to date under the Flexibility Services workstream:

•    Flexibility consultation (Jul – Sep)
•    Standard Agreement consultation (Aug – Oct)

This slide pack summarises the responses that were received both consultations and outlines how the
Open Networks project is taking the feedback forward this year. Additionally, it also outlines how the
project will consider this feedback further in developing the final work plan for next year.
It is to be noted that as a precursor to the final work plan, the project has recently consulted on the
high-level scope for next year. The responses from the high-level scope consultation and the flexibility
consultations above will be used to inform the final work plan that will be launched in January 2022.

                                                                                                2
Headlines and Summary
• Majority of respondents were generally supportive of the topics being covered and the high-level
  objectives set out in each product.
• Majority of respondents were aware of the Flex Figures published on the ENA website and found it
  useful.
     – Suggested improvements through inclusion of additional details (such as cost savings, technology type, time
       of contracting etc)
• Majority of respondents generally welcome work on Open Governance; lack of uptake for user forum
  was mostly attributed to:
     – Low availability of resources/ limited capacity
     – Lack of clear value to operational or commercial business processes from engaging
     – High entry requirements

• Some respondents noted a need for a joined-up overview of flexibility market framework.

                                                                                                           3
Headlines and Summary
• Response to product specific questions are in the following slides.
• Three responses were concerns specific to a network company. They has been forwarded to the
  relevant engagement groups within the relevant organisation to respond through their appropriate
  channels.
• Response to the consultation on Standard agreement has been included in this slide pack as a
  separate section.
• The recommendations for future work on various products have been signposted for
  consideration in 2022 “you said, we will” section. The outcomes will be decided following a
  review of both the responses received for the Flex consultation and the 2022-High level scope
  consultation.

                                                                                                4
Overview of respondents

                          5
Responses received
• The Flexibility consultation ended on 24th Sep (additional 1 week extension of deadline offered)
• 18 responses received in total
     – Academic                                             All non-confidential individual
                                                            responses can be found here
     – Cross Industry Representative
     – Demand Side Response/Aggregator
     – Large Energy Companies
     – Supply Chain Companies
     – Trade Associations

• WS1A P4 - Standard Agreement had a separate stand-alone consultation which received
  additional responses from a Large Energy Company, a Generator and a Supply Chain.

                                                                                              6
Spread of Responses received
  Organisation Name            Organisation Type
  University of Southampton    Academics/Research company
  Citizens Advice              Consumer Protection Party
  Energy UK
                               Cross Industry Representative/Trade
  REA
                               association
  The ADE
  E-Redes                      DSO (Outside UK)
  Voltalis                     DSR/Aggregator
         $$
  Drax                         Generator
  E.ON
  Centrica                     Large Energy Company
  Octopus Energy$$
  Piclo                        Platform provider
  Heimdall Power
  M and W group
  SMS plc
                               Supply Chain
  Servelectric
  Kaluza                                                             *Requested to remain anonymous
  Supply Chain organisation*                                         $$ Responded to Standard Agreement Consultation
  Regen$$ **                   Supply Chain                          $$** Responded ONLY to Standard Agreement Consultation

                                                                                                                              7
General WS1A consultation

                            8
Responses to Q1
Do you agree with our proposals within this consultation paper and if not, please provide us with
any rationale and alternative proposals?

   • Overwhelming majority of respondents are generally supportive of the topics being
     covered by WS1A and the work being done by Open Networks.
   • One respondent recommended that energy efficiency is given equal weight within the
     ENA Flexibility workstream, or that a separate workstream is established .
   • Note: Product specific responses are addressed with the individual product responses
     in following slides.

                                                                                            9
Responses to Q2 - Eight received

Are you aware of the Flex figures being published each year on ENA Website? How does
understanding of GB’s growing Flexibility market size help you and how are you using this
information?

•   Majority of respondents are aware of the existence of Flexibility Figures.
•   Some respondents expressed concern over the granularity and suggested to add more details (
    such as cost savings, technology type, time of contracting etc).
•   Respondents supported the proposed improvements to the Flexibility webpages on the ENA
    website.

                                                                                         10
You said, we will

 You said                                          In 2021 we have/we are/we will                                     In 2022, we will
 •   Need to have a narrative to explain the       No further iterations of the Flexibility Figures are planned for   In 2022, the license condition C31E goes into effect
     progress of the use of flexibility services   2021.                                                              that mandates a requirement for the DNOs to produce
 •   Improve granularity and suggest to add more                                                                      detailed distribution flexibility procurement statements,
     details (such as cost savings, technology                                                                        which will include more detailed quantitative
     type, time of contracting etc)                                                                                   assessments.

                                                                                                                      In light of this, the current format of the Flexibility
                                                                                                                      Figures will be replaced by the requirements of C31E
                                                                                                                      and ENA will consider collating this information across
                                                                                                                      all DNOs to provide a UK-wide view. As part of this,
                                                                                                                      ENA will also consider including a short narrative to
                                                                                                                      outline progress, as suggested. Details to be confirmed
                                                                                                                      in the 2021 work plan.
 Support the proposed improvements to the ENA      ENA has launched an improved website for Open Networks
 Flexibility website                               that has dedicated pages for each WS along with a list of
                                                   associated documents (presented in a clear accessible
                                                   fashion). ENA will incorporate the proposed improvements
                                                   to provide more information about DNO flexibility tenders.
 Standardising approaches across DNOs and          Alignment of DNO and ESO process has been kicked off               In addition to continuing our work initiated in 2021, we
 between DNOs and the ESO - addressing barriers    with some of the products in 2021 [Procurement process             are considering the introduction of two new products
 to participation in flexibility markets           (P2), Primacy rules (P5), Standard agreement(P4)]                  that will further look to address barriers in flexibility
                                                                                                                      markets by improving stackability of services (2022 P6)
                                                                                                                      and also improve dispatch interoperability (2022 P3).

                                                                                                                                                              11
You said, we will
You said                                            In 2021 we have/we are/we will                             In 2022, we will
One respondent recommended that energy efficiency   This topic was raised with WS1A to review the
is given equal weight within the ENA Flexibility    inclusion in the programme. The discussion to review if
workstream, or that a separate workstream is        and how we can incorporate energy efficiency in to the
established                                         programme is ongoing . The outcome of this
                                                    discussion along with the rationale of the decision will
                                                    be included in response to the comments received on
                                                    our high level scope document.
Need to bring more transparency in how DNOs         The Common Evaluation Methodology (CEM) was                In 2022, all DNOs will be reporting against licence
facilitate local markets for flexibility            adopted by all DNOs in April 2021 to use a common          condition C31E that will provide further transparency.
                                                    and transparent approach for assessing flexibility
                                                    against traditional options.                               Additionally, we have proposed to introduce a product
                                                                                                               “Overarching common framework for flexibility services”
                                                    In 2021, we launched an “Flexibility Connections:          to integrate the various aspects of flexibility into a
                                                    Explainer and Q&A” which is intended to help improve       coherent framework. It is envisioned that this product
                                                    transparency around ANM enabled Flexible                   will set out a clear strategic view of further development
                                                    connections. This paper also helped flesh some of the      required to mature processes across key aspects of
                                                    nuances of the interplay between Flexible connections      flexibility (e.g. real time procurement, interoperability
                                                    and Flexible services.                                     across platforms etc.) and will help to provide more
                                                                                                               transparency on progress and direction of travel.

                                                                                                                                                       12
Responses to Q3

Open Networks members are committed to implementing outputs and driving the benefits of
recommendations. Which product or area would swift implementation of the outputs be most
desirable?
•   Would like to see clarity over areas which are deemed out of scope for the CEM.
•   We also need clarity on how Whole Systems CBA fills the gaps that are out of the CEM’s scope.
•   Preference would be to see faster implementation (and more non-network stakeholder
    engagement) around the CEM of flexibility options compared to traditional reinforcement.
•   We would be happy to facilitate further discussion on this with our members.
•   ENA needs to ensure that processes for connecting flexible residential Low Carbon Technologies –
    including EV-chargers and heat pumps – are working efficiently in preparation for mass uptake, so
    that consumers remain positive about engaging in the energy market.

                                                                                            13
You said, we will
 You said                                                 In 2021 we have/we are/we will                             In 2022, we will
 •   Preference would be to see faster                    The CEM product team will undertake a multi pronged        The inputs received form the workshops will be
     implementation (and more non-network                 stakeholder engagement over Nov-Dec 2021. We will          reflected in updating the tool (if applicable).
     stakeholder engagement) around the CEM of            reach out to key interested /affected parties, including   The work undertaken with regards to option and
     flexibility options compared to traditional          those who have expressed interest through this             carbon value will be put to public consultation in Q1
     reinforcement                                        consultation and earlier via the focus group               2022 .
 •   We would be happy to facilitate further discussion   application to set up workshops to present the key
     on this with our members.                            development undertaken to the CEM tool in 2021 and
                                                          seek their critical inputs.
 ENA needs to ensure that processes for connecting        Work on specific technologies such as EV and other         We will continue working closely with the relevant
 flexible residential Low Carbon Technologies –           LCTs are addressed by parallel working groups with in      working groups maintain a two way communication
 including EV-chargers and heat pumps – are               ENA and there are a number of initiatives being            exchanging learning from those groups are well as
 working efficiently in preparation for mass uptake,      undertaken to facilitate rollout at pace. This includes    feeding key learnings form Open Networks. The
 so that consumers remain positive about engaging in      digitalisation of the EV and Heat Pump connections         dependencies of such working groups will be mapped
 the energy market                                        process                                                    out in the 2022 work plan for transparency and clarity

                                                                                                                                                             14
Common Evaluation Methodology
WS1A P1

                                15
Key headlines and summary
• Majority of respondents generally welcome Open Governance.
• Lack of uptake for user forum due to:
     – low availability
     – lack of clear value to operational or commercial business processes from engaging in specific User
       Forums

     – high entry requirements

• Few respondents expressed the need for clarity on how the Whole Systems CBA fills the
  gaps that DNOs say are out of the CEM’s scope.
• CEM should include attributing a cost or benefit to impacts on third parties.

                                                                                                            16
Responses to Q4
What factors do you believe have led to the lack of response to the call to join the
User Forum for the CEM this year?

•   Both the pandemic and the large number of industry consultations since June have reduced the ability
    for stakeholders to be able to participate in further industry consultations or consider future-focused
    market developments.
•   The published commitment and ‘qualifications’ required from members of the forum was deemed by
    some members to be excessive.
•   The only way to increase engagement and interest in the User Forum is to clearly explain and
    communicate the risks and opportunities to flexibility providers, as opposed to promoting the tool as a
    DNO focused product.
•   Addressing this issue by creating a less stringent approach would increase participation.

                                                                                                    17
Responses to Q5

We are keen to understand whether our model of Open Governance for the User Forum was a
factor in the lack of response, do you believe that a User Forum approach would be useful to
consider for progressing key products next year or are there alternative approaches that we
should consider?

•   There was no consensus on the best approach for stakeholders to contribute to the development of key
    products.
•   Majority of the stakeholders believe organisations cannot currently be certain of committing to the time
    required to focus groups, and running more open focus groups or ‘show & listen’ sessions/webinars,
    supplemented by formal consultation would be more efficient.
•   Some of the stakeholders believe an Open Networks rep to present to their members would be the best
    approach.

                                                                                                     18
You said, we will
You said                                                  In 2021 we have/we are/we will                         In 2022, we will
Both the pandemic and a large number of industry          This was useful information, since the response was    WS5 (communication and Engagement) team will
consultations since June have reduced the ability for     lower then last year. We reached out to stakeholders   review inputs from several stakeholders to develop the
stakeholders to be able to participate in further         who had not responded this year. They echoed similar   most effective/efficient approach to organise
industry consultations or consider future-focused         concerns for not responding to the consultation.       consultations to maximise stakeholder responses.
market developments.
Majority of the stakeholders organisations cannot                                                                In 2022, we will be setting up a challenge group and a
currently be certain of committing to the time required                                                          dissemination forum that will enable stakeholders to
to focus groups, and running more open focus groups                                                              participate and provide input in ways that suit them.
or ‘show & listen; sessions/webinars, supplemented                                                               • The Challenge Group gives interested stakeholders
by formal consultation would be more efficient.                                                                     a bigger voice in the programme and the
                                                                                                                    opportunity to shape the direction of the programme
                                                                                                                 • A wider dissemination forum will be open to public
                                                                                                                    and will meet once every 3 months.

                                                                                                                 Taking this feedback onboard, where input is required,
                                                                                                                 we will run targeted focus groups with stakeholders to
                                                                                                                 facilitate this as much as possible.

                                                                                                                                                        19
You said, we will
You said                                              In 2021 we have/we are/we will                             In 2022, we will
Few respondents expressed the need for clarity on                                                                This has been noted and will be considered as a
how the Whole Systems CBA fills the gaps that DNOs                                                               product element for 2022. The product will seek to
say are out of the CEM’s scope.                                                                                  clarify the CEM interaction with various other tools and
                                                                                                                 methodologies (including the WS4 Whole System CBA
                                                                                                                 framework) and how these fit into the overall Network
                                                                                                                 Options Assessment processes; with a view to identify
                                                                                                                 alignment opportunities in the short term, medium and
                                                                                                                 longer term.
CEM should include attributing a cost or benefit to   The CEM and Tool is designed to evaluate only the          In 2022, as a part of the product deliverables we
impacts on third parties.                             DNO’s costs and benefits across a range of                 propose to publish a paper clarifying the use of both
                                                      intervention options; whereas the Whole System CBA         CEM and WS CBA detailing their similarities and
                                                      is designed to evaluate the total costs and benefits for   differences.
                                                      a range of parties across a range of interventions.

                                                                                                                                                         20
Procurement Processes
WS1A P2

                        21
Key headlines and summary
• General agreement of P2 findings that concurrent or alignment of timelines would not be
  of particular benefit to FSPs.
• Welcome the innovation trials and move toward real-time procurement.
• Pre-qualification and standardisation should be consistent across ESO and DNO activities.
• Agreeing more visibility of activities would be beneficial.

                                                                                            22
Responses to Q6
Do you agree with the P2 team’s findings regarding the alignment of DNO and ESO timescales?
Please provide your rationale and any supporting evidence that we can use to inform our
approach, particularly in short – medium timescales (now – start of ED2)?

•   Priority to move to real-time procurement.
•   Prefer to have more standardised pre-qualification across DNOs.
•   Alignment should be focused more on key requirements, testing, data requests and
    technical specifications.
•   Again, more focus on aligning and standardising applications valid for all markets.

                                                                                          23
Responses to Q7

How could we further evolve alignment of procurement processes in future?

•   More visibility and transparency of development of services, e.g. Cross-over points between Whole
    System solutions interaction with WS1A.
•   More visibility of requirements and standardisation of pre-qualification questionnaires.
•   “We do not believe full alignment between DNO and ESO processes is possible given procurement
    functions are in separate corporate entities.”

                                                                                               24
Responses to Q8

Do you agree that the proposed improvements to visibility of requirements will be of direct
benefit to your sector of the industry, if so, please share your rationale and how you would utilise
this information? Do you have thoughts on how we can improve visibility further?

•   “..supports the proposal to introduce a single webpage on the ENAs website collating all flexibility
    procurement.”
•   All other respondents are in agreement that improved visibility of upcoming procurement activities
    will be of direct benefit to the flexible service providers.

                                                                                                25
You said, we will

You said                                                In 2021 we have/we are/we will                           In 2022, we will
Useful to move towards real-time procurement for        Continue to work closely with the T.E.F consortium to    We propose to evaluate and review output from the
DNOs.                                                   understand progress with real-time procurement trials.   real-time trials and understand whether convergence
                                                                                                                 of timelines would be of value.
Standardisation and alignment of procurement                                                                     Noted. Standardised pre-qualification has been
applications for all markets would provide greater                                                               identified and proposed in scope for WS1A P2 for
benefit.                                                                                                         2022.
Improve visibility of upcoming procurement activities   Work with ENA and stakeholders to improve                Will continue to work closely with stakeholders to
will be of direct benefit to FSPs.                      information on webpages and signposting                  understand what further improvements can be made.
                                                        requirements.

                                                                                                                                                       26
Principles to Review Legacy ANM Contracts
WS1A P3

                                            27
Key headlines and summary
• All supportive of the Flexible Connection (ANM) exit route (using the G99 Form) and the
  need for communication.
  • However: several reported that whilst the G99 form is standardised the DNO processes
    and approach to using it are not and this is an issue.
• Need to ensure more coordination / links to Ofgem’s A&FLC SCR.
• Generally agreement with findings of the P3 Report and next steps although mixed
  support for the two-phase connection contract.
• Several (different) suggestions to time limit constraints on Flexible Connections (ANM).
• One response is anticipating set of principles to review FC(ANM) Legacy Contracts;
  however this has been refocused to align more with A&FLC SCR minded to decision.

                                                                                             28
Responses to Q9

Do you agree that there is an exit route, using the current G99 approach, for existing FC(ANM)
customers who want access to firm(er) connections? If not, what do you see as the barriers?

 • Generally agree: but exit routes / process need to be aligned with the A&FLC SCR.
 • G99 forms not applied consistently across DNOs/ processes that apply it differ by DNO making it confusing and
   complex.
 • Generally agree with approach because they have generic concerns with in perpetuity contracts and the asymmetry
   of information (DNO v customer).
 • Want to the communications re: the Exit Option / process to provide transparency on cost implications for the
   customer; and be clear on the potential to reduce costs if wait until the A&FLC SCR proposals are implemented.
 • Remove open ended connection contracts; replace with time restricted contracts, based on reinforcement timescales
   / availability of Flex. Services. If DNOs fail to meet timescales then customer rewarded for the flexibility provided.
   However, customers should be still be able to choose a long term non-firm connection contract.
 • Dislike term “Flexible Connection” as its only flexible for the DNO. Should be a Curtailed Connection.

                                                                                                                29
Responses to Q10
Do you agree with the findings of the Product 3 report and if so, which area(s) are of most interest
going forward?
     • Majority of stakeholders support the deliverables identified esp. those made more pertinent by Ofgem’s A&FLC minded-
       to-decision. ONP to be fully coordinated / aligned with the Ofgem’s intended approach.
     • Generally supportive but customers have had issues with the G99 process and want to see it streamlined.
     • Most support two-stage connection offer as non-firm connections could be used as a temporary measure to facilitate
       quicker connection to the network whilst the DNO increases network capacity (via flexibility procurement or reinforcement.)
       although these should be time limited and consistent.
         – One stakeholder believes a two-stage connection offer does not enable discovery of true value of the flexibility; plus
           maintains asymmetric bilateral negotiations.
 •    DNOs should avoid market-splitting Integration of different approaches to managing constraints: DNO flex tender products
      and ANM contracts are managing constraints.
     • Suggest introducing a “declining budget” of curtailable hours through the ANM schemes, building on the budgeted hours
       that will be introduced for non-firm connections through the Access reforms. Curtailment “over budget” to be procured from
       flexibility tenders so over time more curtailment would be addressed by flexibility tenders.
 •    One stakeholder has reservations about flexible connections, even on a time limited basis as that will impact the formation
      and value of flexibility markets.

                                                                                                                   30
You said, we will
You said                                                         In 2021 we have/we are/we will                          In 2022, we will
Coordinate / align activity with A&FLC SCR                       Conversations with Ofgem and ENA Regs Team              Coordinated approach will be implemented to
                                                                 underway                                                avoid duplication of effort and make sure activity
                                                                                                                         sits with the team best placed to deliver solution.
Proactive signposting of exit (G99 form) options is supported    Plans to complete this by Dec 2021
but…
DNO processes using G99 are not standardised and create          We recognise the processes around the G99 form          Identify and implement changes to connection
issues. Cost transparency required, incl potential benefits of   are not consistent. We also appreciate that the         agreements before 4/2023 to meet the needs of
delaying connection exit (SCR).                                  Ofgem A&FLC SCR may require changes to                  the Access & FLC SCR decision. In parallel,
                                                                 connection agreements from 4/2023. Both                 incorporate standardisation to address the
                                                                 requirements are being discussed within the ONP         consistency issues identified.
                                                                 and ENA to identify where the activity best sits.
Most stakeholders supports 2-phase connection with one           Two-phase connections generally supported but           Coordinated approach will be implemented to
exception.                                                       with one stakeholder expressing reservations.           avoid duplication of effort and make sure activity
                                                                 Ofgem’s SCR activity also identifies this as a          sits with the team best placed to deliver solution.
                                                                 potential solution and activity be taken forward with
                                                                 the appropriate team
One stakeholder – expecting legacy FC(ANM) contract              Decision taken, with ON SG and Focus Group              Coordinated approach will be implemented to
review to go ahead                                               support, to align more with A&FLC SCR minded to         avoid duplication of effort and make sure activity
                                                                 decision. Resources to focus on standardising           sits with the team best placed to deliver solution.
                                                                 future connection agreements to meet the A&FLC
                                                                 SCR needs and include transition arrangements for
                                                                 FC(ANM) legacy contracts.

                                                                                                                                                             31
Primacy Rules for Service Conflicts
WS1A P5

                                      32
Key headlines and summary
• No further projects to review as part of the product.
• Some questions about the scope and breadth of the product. These should be clarified in
  the upcoming report due at the end of November.

                                                                                            33
Responses to Q11

 Are there any particular projects/reports we should be considering as part of our initial review of
 work carried out on Primacy to date? This could include international examples.

• Most respondents did not answer this question specifically.
• Where they did, they generally confirmed that there were no other relevant projects.
• One respondent provided feedback on the wider product.

                                                                                         34
You said, we will
 You said                                                                 In 2021 we have/we are/we will                                                   In 2022, we will
We are concerned about the lack of clear scope and definition of         The product is currently developing a list of the relevant Primacy use            Continue to review the
this product. We would like to see a more explicit description and       cases . We are also defining a set of criteria that will be used to reduce the    use cases to prioritise the
scale of the problem this product is trying to address. This could       number of use cases and provide an initial view of those that are of              next set of rules.
include a list of identified conflicts between DNO and ESO               highest priority (using a scoring approach based on the agreed set of
products, a list of products and services these primacy rules would      criteria). This will then help to shape the upcoming deliverables of the
apply to, as well as current regulatory and market pre-requisites for    product, with a focus on tackling the higher priority Use Cases and
the implementation of these primacy rules.                               Scenarios first. The list of prioritised use cases will be published in 2021
• Primacy rules may artificially dictate the dynamics of the market      Furthermore, we are currently developing Primacy Principles to help guide         Apply the agreed
   and dispatch patterns of flexible assets, instead of responding to    the rules that will be created later in the product. One of these emerging        principle to the Primacy
   genuine system needs and signals.                                     principles is the need to facilitate market competition. These are currently      rules being developed
• we believe there is a risk that these primacy rules may create a       being refined by the product team and the Primacy Focus Group. These
   distortion to what would, otherwise, be a fully market and            Principles will be published in 2021
   system-led dispatch and utilisation.
With regards to high-level principles, key consideration should be       The product team recognises that there is a need to ensure that                   This topic has been
given to real-time information availability and optionality and choice   appropriate information is available to flexibility providers in order to offer   identified to be developed
for participants. Flexibility providers should be able to assess the     their services.                                                                   under WS1B - P7 as
value of their services and optimise their participation in the most                                                                                       proposed in the 2022
economically efficient way.                                                                                                                                high level scope
                                                                                                                                                           document.
Additionally, a clear and consistent market framework needs to be The Primacy Rules will be developed in an open and transparent way, with Start to develop the
developed, with clearly defined roles, responsibilities and control stakeholder feedback at the heart of this process. As part of the product governance framework
structures.                                                         we will also develop a forward looking governance framework with
                                                                    appropriate mechanisms to ensure they evolve to meet changing
                                                                    scenarios, as required.

                                                                                                                                                                     35
Non-DSO Services
WS1A P6

                   36
Key headlines and summary

• Half the respondents didn’t answer this question.
• Most of the respondents only spoke about the trading/sharing of capacity and ignored
  curtailment of risk.
• Most of the respondents were more interested in the DNO/ESOs views on this question.
• General interest in seeing the results of any trials in the future.
• General agreement that this needs to be matured and will become more important as a
  topic as time goes on (i.e. facilitating peer to peer trading).

                                                                                         37
Responses to Q12-Nine received
 Is the trading and/or sharing of capacity or curtailment risk of interest? What do you see as the
 major barriers currently?

• Many stakeholders are interested in the DNOs views on barriers. Asking why two/data customers
  can't come to an agreement as it is? See main barriers as information provision, conflict
  management, DNO system study delays.
• "Theoretically of interest and could become more important over the next few years." Say DNOs will
  have a better view and are interested in the DNO's view.
• Welcome trials and stakeholder engagement to progress this topic. Recommend the "product is
  progressed with urgency."
• Certain barriers need to be addressed; like lack of market signals, lack of real time system charges,
  and rewards for flexibility with a central control mechanism (i.e. with the DNO/ESO procuring it).

                                                                                                 38
Responses to Q12 -Nine received
Is the trading and/or sharing of capacity or curtailment risk of interest? What do you see as the
major barriers currently?
• Some stakeholders were there is industry interest in seeing the trading and sharing of
  capacity delivered.
     – Interested in curtailment risk being valued closer to real-time. Worried that this may be limited to
       speculative trading.
     – Potential benefits need to be clearly demonstrated in order to get stakeholders engaged and committing
       to this workstream

• One stakeholder was unconvinced of value of capacity trading and sharing. Worries about
  participants being "significantly asymmetric". Major concerns about there being a lot more
  sellers than buyers (with short term sales on offer and no buyers wanting to invest).

                                                                                                                39
You said, we will

You said                                              In 2021 we have/we are/we will                        In 2022, we will
•   We would be interested in understanding the       Held market facilitation workshops with a range of    The wider Open Networks (ON) programme will
    DNOs views on non-DSP services                    stakeholders, including DNOs, to understand general   progress P6’s “considerations for future work” from
•   We would be interested in seeing the results of   responses to Q12 (report available).                  these workshops and the responses from this
    any trials related to WS1A P6 .                                                                         consultation.
                                                                                                            WS1A aims to submit a better informed PID for “Non-
                                                                                                            DSO Services” in the 2023 programme to build on
                                                                                                            2022’s learning.

                                                                                                                                                 40
Baseline Methodologies
WS1A P7

                         41
Key headlines and summary

 •   Most stakeholders agreed with our approach to the delivery of alignment baseline
     methodologies.
 •   Broad support for our proposal to continue the development of baseline
     methodologies through the Open Networks from 2022 onwards.
 •   The need for technology specific baselines flagged.
 •   More detail on the timeline for DNO adoption of aligned methodologies requested.

                                                                                        42
Responses to Q13

Does the roadmap outlined for the delivery and development of aligned distribution constraint
baseline methodologies (as detailed in the Product 7 interim report) meet the needs of the
market?
•   Four of the responses confirmed their support with our approach.
•   Two of the responses flagged the need for technology specific baselines, particularly
    technologies that may be limited in responding due to intermittency and/or consumer
    behaviour.
•   Two responses called for more detail to be added to the P7 delivery timeline so that is
    was clear when DNOs would adopt aligned methodologies.
•   One respondent requested the analysis results to be made available so wider
    assessment can be made on the methodologies market suitability.

                                                                                              43
You said, we will

You said                                           In 2021 we have/we are/we will                    In 2022, we will
While the timeline for continued consultation is    Add clarity to the timeline to signpost when
noted, it was not clear that there was a target     DNOs expect to adopt the 20/21 common            Continue to update this timeline to reflect any
 date for completion of the work. It would be      methodologies and any future adoption of the      developments as a result of the ongoing
    useful to set a target date for aligned            evolved methodologies as they are             consultation for baseline methodologies.
                methodologies.                                       developed.

We would like to see a concise product map of    We recognise that differing technology types
  existing products and a comprehensive         may benefit from a tailored baseline approach,
 summary of technology-specific validation      currently Technology Specific methodologies
   mechanisms for each of the products.            do not yet exist, we expect this to be an
                                                                                                     The workstream will continue monitoring the
                                                outcome of the ongoing evolution of baseline
Baselines are needed for emerging technologies methodologies will be directly influenced by          use of the tool and use the learning to develop
   such as residential flexibility. Home energy                                                      recommendation for further development of
                                                   DNO experience operating more diverse
  technologies - electric vehicles, heat pumps,                                                      baseline methodologies for 2023
                                                 technologies for flexibility both through their
 and other emerging tech which can show high     existing and trial flexibility market activities,
   variability across different households and   and from the feedback of flexibility providers
    further compounded by the natural daily             operating within those markets
               variability in the home

                                                                                                                                        44
You said, we will

We would encourage the ENA to make
available the results of their analysis based on   Analysis of all baselines will be published   We encourage any parties wishing to provide
historical datasets. The ENA could then get        and available when the product concludes      feedback on this analysis the Open Networks
further feedback on whether the results            this year.                                    team.
address market needs.
 It is not clear whether and how this product is
                                                                                                 The Primacy Rule Product (P5) is assessing
 co-ordinated with the Primacy rules
                                                                                                 any impact on other WS1A products as part
 development. We would welcome a clear
                                                                                                 of its work over 2021 and 2022.
 overview of any interactions between the two
                                                                                                 We will continue to monitor the product and
 products and further engagement with the
                                                                                                 action any impact recommendations from P5
 industry throughout the year.
                                                                                                 when they become apparent

                                                                                                                              45
Apportioning Curtailment Risk
WS1A P8

                                46
Key headlines and summary
• Broad agreement on caps and collars approach to apportioning curtailment risk with some
  caveats:
  – Greater transparency of curtailment apportionment mechanism.
  – Flexible connections (ANM) as a temporary measure.
  – Coordination with flexibility service procurement.
• One respondent very clear of objections to flexible connections and ANM in general, with a
  view that generation connections should be firm by default with constraints managed by
  DNO reinforcement / procurement of flexibility from connectees (who would be mandated
  to offer such services).
  – However, agreement that caps and collars does re-apportion risk although are of the
    view that DNO is still not taking on any risk.

                                                                                               47
Responses to Q14

  We are exploring the use of curtailment caps and collars to apportion curtailment risk better; do
  you agree with our high-level impact assessment on the various parties?

• Most stakeholders agree with high level impact assessment.
    • The following were also noted:
      – Desire to see how ANM mechanisms coordinate with wider flex markets as well as how DNOs
        make flex procurement decisions coupled with ANM actions. Question whether ESO has
        assessed impact on (flex?) market participation and revenue stacking.
      – Notes that more transparency over merit order and curtailment methodologies is needed.
• One stakeholder fundamentally opposed to flexible connections but agree that risks do need to be
  reapportioned. Feeling that DNOs use ANM to tackle constraints due to load growth.

                                                                                             48
Responses to Q15

  Do you support the use of caps and collars as described in the report?

• Most stakeholder were supportive of the approach.
    • Some points were noted:
          – ANM should be considered temporary measure and subject to maximum time limit
            pending DNO flex procurement or reinforcement.
          – Feeling that DNO not taking on any risk. Suggestion that all generators have firm
            connections but with requirement to provide flex services similar to BM participation
            requirements.

                                                                                                49
Responses to Q16

Do you have any views on the alternatives presented? E.g. Peer-to-peer flexibility trading; an
incentive scheme similar to that currently used for Customer interruption/ Customer minutes
lost (CI/CML)?

 •   Most stakeholders support the proposals and these alternatives should be explored in
     parallel (one stakeholder noted dynamic ratings to increasing capacity).
 •   P2P flex trading diluted form of DNO flex services. Preference for willow connection
     boundary. Incentive scheme sounds attractive, acknowledgement of difficulties setting
     targets.

                                                                                             50
You said, we will

You said                  In 2021 we have/we are/we will                                                        In 2022, we will
Fundamentally opposed     Connecting generation customers are currently liable for the costs (or a proportion
to flexible connections   of the costs) associated with any network reinforcement required to accommodate
                          their connection. Where these up-front network reinforcement charges are cost-
                          prohibitive to a customer, Flexible (ANM) Connections offer a more cost-effective
                          and, typically, more rapid means of connecting. The FC(ANM) connection allows
                          customers to significantly reduce up front charges by accepting a degree of
                          reduction in network access rights – the connection will be curtailed when
                          networks are unable to accept the customers full load. Strong uptake of such
                          connections indicates that customers are broadly happy with these connection
                          offers.
                          Move from implementation product to recommendation product to be handed over
                          to SCR implementation team
                          • All feedback will be captured and noted as part of handover document
                          • Broad agreement with proposals means no material changes to
                             recommendations, support for alternative approaches (incentive schemes etc)
                             will be highlighted
                          • Concerns over transparency largely captured already

                                                                                                                                   51
Curtailment Information
WS1A P9

                          52
Key headlines and summary

• Full support for using a Focus Group - on the proviso material and recordings are
  shared with wider stakeholders, and supplemented with industry consultation.
• The priority curtailment information needs identified by the Focus Group were largely
  supported.
• There is also support for focusing on the low regret quick wins, given the changes
  being considered by Ofgem’s Access SCR.
• Two respondents suggested the choice of whether market participants decide to
  process curtailment data themselves, or use a third-party, should be left to the market.

                                                                                             53
Responses to Q17

We have used a Flexible Connection (ANM) Stakeholder Focus Group to help us identify the
specific curtailment information needs and priorities for current and potential users of Flexible
Connections; do you agree with this approach?
•   Unanimous support for the Focus Group.
•   Several caveated support by adding:
    •   Publish the supporting materials and recording.
    •   Supplement with wider industry consultation.

                                                                                        54
Responses to Q18

Do the curtailment information requirements we have identified as a priority, with input from the
Stakeholder Focus Group, meet your needs? If not, what additional requirements are there?

 •   Most stakeholders agree the ONP should focus on the low regrets options and ‘quick
     wins’ that are inline with the proposals from Ofgem’s Access SCR.
 •   One stakeholder agreed with the focus group requirements but surprised that 70% of
     respondents only need the curtailment details at offer stage. Believes majority would
     need this earlier and at least at discussion stage with network planners.
 •   One stakeholder noted they do not have any additional data requirements.

                                                                                             55
Responses to Q19

In addition to improving curtailment data provision, Product 9 has also considered the
role of third-party curtailment information providers where more sensitivities can be
provided specific to customer assets. Would you consider using a third party for more
curtailment tailored information and if so, should we explore this option further or leave
it to the market?
• “Not clear how the use of third party curtailment information providers (TPCIP) helps either DNOs or
  generators; DNOs will still have to provide the bulk of the data to the third party”- believe the best route is to
  leave it to the market to decide whether there is additional value for generators using TPCIP.
• Requested to see more regarding timescales for delivering the modelling required by the DNOs. Have the
  DNOs forecast the future resource requirement to carry out this work?
• Whole market needs to be provided with the same underlying data in a form that can be easily processed.
  The choice of whether market participants decide to process the data themselves, or use a third-party,
  should be left to the market.
• Role of the DNOs and ONP should be to provide the same data in a common format to enable customers
  and third parties to extract the value of that information. ONP should abide by the open data principles
  established by the Energy Data Taskforce, allowing the market to decide how it uses that information.

                                                                                                           56
You said, we will
You said                                               In 2021 we have/we are/we will                                                 In 2022, we will
Full support for Focus Group provided material         The sessions are not recorded as a general practice and as such is not         Continue to use the focus group as
and recordings shared with wider stakeholders          shared on a public forum. However, Materials of the Focus Group                required to support the development
and supplemented with wider industry consultation      workshops including the slides , meeting notes and outcomes are                of solutions. All relevant materials
                                                       available. These will be signposted better.                                    will be shared with wider
                                                                                                                                      stakeholders.
Generally support the priority information needs       Use the information to prioritise the Curtailment Information implementation   Implement the Curtailment
identified                                             plans                                                                          Information plans
Support for focusing on low regrets options / ‘quick   Continue with this approach                                                    Continue with this approach
wins’ inline with the A&FLC SCR proposals
The choice of whether market participants decide       Given general appetite was to leave this option to the market it will not
to process curtailment data themselves, or use a       feature in the P9 activity.
third-party, should be left to the market.
DNOs should provide the same data in a common          Consistency is information provision has been identified as a key principle    Consistency of data provision will
format to enable customers and third parties to        in the activity and deliverables of the P9 Curtailment Information Product     continue to be a key focus for the
extract value.                                                                                                                        implementation plans.

ONP should abide by the open data principles           The ONP is guided by ENA’s Data and Digitalisation Steering Group              The work of the DDSG will continue
established by the EDTF allowing the market to         (DDSG). This group was created to ensure the benefits of accessible data       to guide ONP and networks
decide how it uses that information                    and digitalisation are realised inline with the EDTF principles. The DDSG      throughout 2022.
                                                       has developed two products: the National Energy System Map (NESM)
                                                       and the Energy Data Request Service available via ENA’s website. A Data
                                                       Triage Playbook guides networks on responding to data requests and
                                                       aligning to a ‘Presumed Open Data’ principle.

                                                                                                                                                             57
Residential Flexibility

                          58
Key headlines and summary
• One stakeholder sited problems faced by many customers purchasing a heat pump or EV
  on fixed rate, non-time of use tariffs that use load during peak periods. Also, customer
  variability and other asset-specific issues can make it hard for these technologies to meet
  their full potential in existing flexibility services.
• One stakeholder identified a potential for ENA to address the problem of rising residential
  demand at its core and mobilise residential flexibility with a new service procured ahead of
  time.
• Two stakeholders shared the concerns of other aggregators, that the proposals from the
  ESO to limit aggregation to Grid Supply Points (GSP) for its new response and reserve
  products will seriously disincentivise residential propositions.
• One stakeholder expressed concern over the current conception of flexibility (and flexible
  services) may preclude flexibility as a property of a wider system that includes dwelling
  fabric (for thermal storage) as well as the bounded electricity network and its connected
  appliances.

                                                                                                 59
Responses to Q20

Do you have any ideas on how we might better engage and encourage participation of
residential flexibility in flexibility service provision and identify any barriers that might currently
exist along with potential solutions?

•   Two stakeholders shared the concerns of other aggregators, that the proposals from the
    ESO to limit aggregation to Grid Supply Points (GSP) for its new response and reserve
    products will seriously disincentivise residential propositions.
•   One stakeholder noted the potential to for Open Networks to address the problem of
    rising residential demand at its core and mobilise residential flexibility with a new
    service procured ahead of time.

                                                                                             60
You said, we will
You said                                                  In 2021 we have/we are/we will                       In 2022, we will
Concerns of aggregators, that the proposals from the      This feedback has been passed on to the relevant
ESO to limit aggregation to Grid Supply Points            department within National Grid ESO and will be
(GSP)for its new response and reserve products            addressed through their appropriate channels
will seriously disincentivise residential propositions.

We believe there is potential to for ENA to address                                                            Noted. In 2022 we propose to review the flexibility
the problem of rising residential demand ( due to                                                              product definitions to reflect on the experience and
EV/HP) at its core and mobilise residential flexibility                                                        learnings from their deployment. Full details of the
with a new service procured ahead of time.-This                                                                recommendations received will be noted passed on to
service would be based on ‘avoided load’ rather than                                                           the product team for consideration
specific demand reduction

One stakeholder expressed concern over the current        The work undertaken in the Open Network has been     We will continue working closely with the relevant ENA
conception of flexibility (and flexible services) may     technology agnostic. Ensuring that the development   working groups ( that work closely with specific
preclude flexibility as a property of a wider system      of flexibility market does not preclude any          technologies) maintain a two way communication
that includes dwelling fabric (for thermal storage)       technology/stakeholder form participating in the     exchanging learning from those groups are well as
                                                          market has been and will continue to remain our      feeding key learnings form Open Networks.
                                                          priority.                                            In addition , in 2022 we have proposed the review of
                                                                                                               standard flexible products definitions. The learning
                                                                                                               form the past years will help us identify potential
                                                                                                               barriers to market proliferation.

                                                                                                                                                      61
WS1A P4 Workstream Consultation-
Standard Agreement

                                   62
Responses to Consultation
    There was no specific questions asked regarding the published consultation, instead
    Stakeholders where invited to review the contract and supporting detail in full and provide
    feedback and their insights on the documents, it’s useability and accessibility overall.
         We received 3 responses to the consultation, 1 supporting the Consultation, 1 gave no view and 1
         challenged if the Standard agreement was fit for aggregators.

•    Key themes from the responses were
     –   How will the ESO be using the Standard Agreement across it balancing services
     – Thoughts on how the Standard agreement works with flexibility services provided by EVCP
     –   Challenges of services being delivered by EVCP
     –   Level of insurance and indemnities for smaller organizations
•    Other areas raised not directly related to Standard Agreement
     –   Service delivery provided by EVCP
     –   Metering requirements for community providers and power to participate publication

                                                                                                            63
You said, we will

 You said                                                In 2021 we have/we are/we will                                                In 2022, we will
 The standard contract needs adjusting to ensure it      Building on updates made in Version 1.2, which include, the removal of        In 2022 we have proposed to further
 works for aggregators, including the aggregation of     singular terminology and the use of pluralised statements to reflect          align the structure of schedules and
 demand response from smaller assets.                    applicability to aggregators and aggregated assets                            documentation which can be used for
                                                                                                                                       all existing and future products.
                                                         Version 2 incorporates more extensive changes which provide the
                                                         flexibility for providers to contract either as asset owners or
                                                         aggregators. This includes aspects such as the provision of requisite
                                                         documents for assets under development.

In terms of access, obligation on the Company to         This clause has been further relaxed within Version 2.
comply with reasonable requirements for site access.     The clause regarding site access will remain. The rewording of the
(e.g. health and safety requirements and having to       clause means that the company will contact the provider to arrange
cooperate on scheduling – it’s not acceptable to many    access rather than the company contacting the asset owner directly.
customers to give DSOs an unrestricted right of entry,
even with notice).
Harmonisation of the liabilities and Indemnities         The liabilities and indemnities provision has been updated to align with
provisions across DNOs and the ESO.                      the ESO’s dual cap approach. Thus, under the Standard Agreement,
                                                         there is a general cap on liability for asset damage, with specific limits
                                                         for the DNOs and the ESO.
                                                         Specific indemnities as relevant to individual services, will be set out in
                                                         that service’s schedules. This allows for lower limits to be set for when
                                                         applicable across services which will remove any unnecessary barriers
                                                         to entry, in particular for smaller providers.

                                                                                                                                                            64
Key Amendments to the Standard Agreement
 Further Amendments to the Standard Agreement
 Records and Audit                      Version 2 makes a distinction between financial, contractual and performance data and the ensuing
                                        data retention obligations.
 Confidentiality                        This clause has been amended to retain the simplicity in version 1.2, whilst also allowing the
                                        sharing/publication of relevant data to enable greater industry transparency.

 Dispute Resolution                        Version 2 adopts a layered approach to dispute resolution, with disputing parties having access to a
                                           range of dispute resolution mechanisms, including negotiation, mediation, arbitration and expert
                                           determination. This approach ensures that parties are afforded the opportunity to explore amicable
                                           settlement through negotiation before recourse is had to other forms of dispute resolution including
                                           mediation, arbitration, expert determination and litigation.

 Inclusion of Community                    Updates have been made within Version 2 to recognise participation by entities other than ‘body
 Bodies/Charitable Groups and Smaller      corporates,’ thereby accommodating small scale flexibility service providers, community bodies and
 Scale DER                                 charitable groups. Overall, this ensures increased participation in the provision of flexibility services
                                           and drives competition in the market.
 Termination for Convenience               Version 2 retains each party’s right to termination for convenience. The Product Team considered
                                           that it would be particularly useful for smaller providers to have this right, so as to not be locked into
                                           the contract.
 Termination Due to Change in              All references to ‘Change of Ownership’ being a material breach of the contract have been
 Ownership                                 excluded from Version 2. The clause has also been updated/relaxed to ensure that the Company
                                           can only terminate for change of ownership, if the new Provider/ controlling entity fails to meet
                                           reasonable due diligence checks.

                                                                                                                                                        65
Provider Feedback and WS1A P4 responses

Provider Feedback                                                             P4 Response
DERs are defined in these contracts as: ‘the electricity generators,          The definition is agnostic as possible and there is no primary source of
electricity storage or electrical load, and other Site and Provider           flexibility service. All assets must meet technical requirements at
equipment, machinery, apparatus, materials and other items used for           procurement stage (procurement rules). in regard to which definition
the provision of the Flexibility Services as described in Schedule 3’ –       Electric Vehicle Charging Points fall under, they would fall under the
with a bit of creative thinking EVCPs could be considered to fall into this   electricity load definition.
definition, but it is by no means perfect and certainly does not envisage
EVCPs or similar assets being the primary source of flexibility. We would
suggest including EVPs, or some generic wording around alternative
DERs, to accommodate for this.

ENA needs to ensure that processes for connecting flexible residential        It is expected that any contracted service can be fully delivered. For
Low Carbon Technologies –including EV-chargers and heat pumps –               aggregated assets we would expect that the Provider manages the
are working efficiently in preparation for mass uptake, so that               aggregated portfolio to enable the provision of the contracted.
consumers remain positive about engaging in the energy market

                                                                                                                                                         66
Provider Feedback and WS1A P4 responses

Provider Feedback                                                            P4 Response
We are asked to Permit / grant / secure a right of access to the Sites       It would be highly unlikely that visit will ever take place by the
and the DERs and to inspect the DERs and add monitoring equipment            contracting organisation however the right to inspect or have access to
to the DER if the Company so choose. Given these are people’s EVCPs          contracting organisation owned equipment should remain As clause
(which may be leased from the original owner), this is very difficult to     4.1.7 states the contracting organisation will contact in advance and in
give practically.                                                            the case of domestic properties will contact the provider and not the
                                                                             asset owner.

Disclose any change in circumstance which could affect the delivery of       It is the providers responsibility to mange the portfolio within the
the services and notify DNO each time we change the DER providing            geographical/ specified zone, this would include the addition/removal of
the service – Again, this is subject to our drivers complying with our end   assets form the portfolios. As an aggregated asset provider it is
agreements, which is not totally within our control.                         expected that the portfolio delivering any service would be managed so
                                                                             that it was capable of delivering any service that it was contracted for.

                                                                                                                                                         67
Provider Feedback and WS1A P4 responses

 Provider Feedback                                                      P4 Response
 The indemnities included in some model agreements (against loss        The Standard Agreement designed to align the General Terms and
 or damage to any property, breach of the agreement for example)        Conditions across the DNO's and ESO so that there is a consistent
 are too broad and would not be accepted as part of a standard          approach going forward. These terms were developed with the core
 commercial negotiation. I have seen these included in some             objectives of simplification, alignment and to be fair for all parties.
 contracts and not others, so I wonder whether this is being included
 by some DNOs over and above the standard terms.
 The consultation notes that the ESO has structured its contributions   The ESO will start using the Standard agreement initially with the launch
 around the Dynamic Containment (DC) and Optional Downward              of the new response and reserve products. Once that the new services
 Flexibility Management (ODFM) services and is committed to             have been established other existing services will look at wherever
 adopting the Standard Agreement for its future product launches, but   possible move to using the Standard terms. This will require and industry
 it is not clear whether and how this agreement will apply to other     consultation as required by EBGL and Clean energy package legislation.
 ESO products. As noted in our response to the recent Flexibility
 Consultation, a lack of engagement with the ENA Open Networks
 project can lead to a limited understanding of how changes
 proposed by the project will apply at the grid level until those
 changes are put forward for implementation. We would therefore
 suggest that the ESO communicates its plans on adopting the
 proposed Service Agreement separately via relevant communication
 channels. We would expect that communication to include a list of
 current and future ESO balancing services that this Agreement will
 apply to, subject to approval of the changes by Ofgem. We would
 also welcome clarity on timelines for adopting the agreement by the
 ESO.

                                                                                                                                                    68
You can also read