DISCLAIMER These Presentation Materials are for information purposes only and must not be used or relied upon for the purpose of making any investment decision or engaging in any investment activity and should not be construed as, an offer for sale or subscription of, or solicitation of any offer to buy or subscribe for, any securities of Rainbow Rare Earths Limited (the “Company”). Whilst the information contained herein has been prepared in good faith, neither the Company, its subsidiaries (together, the “Group”) nor any of the Group’s directors, officers, employees, agents or advisers makes any representation or warranty in respect of the fairness, accuracy or completeness of the information or opinions contained in this presentation and no responsibility or liability will be accepted in connection with the same. The information contained herein is provided as at the date of this presentation and is subject to updating, completion, revision, verification and further amendment without notice. These Presentation Materials contain forward-looking statements in relation to the Group. By its very nature, such forward-looking information Disclaimer requires the Company to make assumptions that may not materialise or that may not be accurate. Such forward-looking statements involve known and unknown risks, uncertainties and other important factors beyond the control of the Company that could cause the actual performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Nothing in this presentation should be construed as a profit forecast. Past share performance cannot be relied on as a guide to future performance. 2 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
INTERIM RESULTS: LONDON’S ONLY LISTED RARE EARTHS PRODUCER WITH COUNTRY AND PROJECT DIVERSIFICATION • Strong safety performance: 22 months LTI-free production at Gakara • Effective measures to address Covid-19; operations running largely as normal • Global macroeconomic trends drive strong and diversified demand for NdPr H1 2021 interim Results PHALABORWA – EXCITING NEAR-TERM GROWTH OPPORTUNITY • Earn-in agreement signed with Bosveld Phosphates in November 2020 • Initial assay results: 0.5% TREO, 29-30% NdPr with Dy (1%) and Tb (0.3%) credits • ANSTO Minerals (Australia) performing testing to confirm metallurgical variability • Metallurgical test work at ANSTO used to optimise process flow sheet PEA/scoping study • Expected to be brought into production quicker, with lower capital intensity than traditional hard-rock rare earths mining project GAKARA – ROBUST LONG-TERM ECONOMICS • Ongoing trial mining continues to demonstrate potential: 300t concentrate produced in H1 2021 (H1 2020: 114t) Image: Sasol’s RE carbonate pilot plant at Phalaborwa • Viability of 10,000tpa down-stream processing plant confirmed 3 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
MARKET OVERVIEW RARE EARTHS: THE CRITICAL BUILDING BLOCKS Market Overview IN THE GREEN REVOLUTION 4 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
NdPr CONSTITUTE 90%+ OF RARE EARTHS VALUE NEODYMIUM AND PRASEODYMIUM (NdPr) ARE CRITICAL ELEMENTS IN PERMANENT MAGNETS USED FOR MOTORS AND TURBINES Permanent magnet production accounted for 91% of the total value of TREO consumption in 2019 Market Overview Source: Adamus Intelligence 5 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
GLOBAL TRENDS ACCELERATE NdPr DEMAND… KEY GLOBAL MEGATRENDS ARE DRIVING STRONG AND DIVERSIFIED DEMAND FOR NdPr ANTICIPATED GLOBAL REO MAGNET DEMAND GROWTH 160,000 • AUTOMATION: Accelerating technological progress 141Kt by 2030 140,000 • LOW CARBON TRANSITION: environmental protection and climate change Market Overview 120,000 • SUSTAINABLE RESOURCE SECURITY: Increasing scarcity of and global 100,000 competition for resources 80,000 • SUPPLY CHAIN SECURITY: Against backdrop of heightened national 61Kt protectionism 60,000 NdPr DEMAND ACCELERATED BY EVOLVING GLOBAL EMISSIONS 40,000 LEGISLATION 20,000 • Wind power will be a key contributor to meeting Paris Climate Goals - • UK to ban new petrol and diesel car sales by 2030 and increase offshore 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 wind capacity to a level sufficient to power every home by this date Electric Vehicles / mobility Wind Power • Germany targets offshore wind power expansion targets of 20GW by Industrial Consumer 2030 and 40GW by 2040 Other • France aims to produce 1m EVs annually by 2025 Source: Adamus Intelligence 6 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
…POWERED BY THE GREEN REVOLUTION PROJECTED ANNUAL GLOBAL EV SALES NO EXISTING ACCEPTABLE SUBSTITUTES FOR NdPr IN PERMANENT MAGNETS FOR EVS AND WIND TURBINES WHILST BATTERY CHEMISTRY IS STILL EVOLVING, THE MOTOR TECHNOLOGY REQUIRED ACROSS ALL EVS DRIVES NDPR DEMAND REGARDLESS OF BATTERY CHEMISTRY Market Overview • Growth in EV production forecast to lead to increase in demand for NdPr of 25-90% by 2030 • Each new EV requires between 1-3kg of NdPr • Average annual NdPr demand from EVs forecast to increase by ~4,200 – 9,600tpa from 2020-20251 RANGES FOR CUMULATIVE NdPr DEMAND FOR GLOBAL • Value of global magnet REO consumption to increase from US$2.98bn to WIND TURBINE PRODUCTION THROUGH 2050 US$15.65bn by 20302 PERMANENT MAGNET ELECTRICITY GENERATORS FOR WIND TURBINES • Wind turbines consume ~600-830kg of REO per Megawatt3 • Estimated wind-capacity growth of 5.7% year-on-year to 20504 • Growing to +1.9TW of total wind capacity by 20505 Sources: 1. SP Angel 2. Adamus Intelligence 3. Curtin University 4. Bloomberg NEF New 7 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021 Energy Outlook 2020 5. NDRC-ERI “Aggressive Scenario. Graph 1: Bloomberg New Energy Finance, Katusa research, US Global Investors Graph 2: World Bank
SIGNIFICANT PROJECTED NdPr SUPPLY CONSTRAINTS SECURING AN ETHICAL AND SUSTAINABLE SUPPLY CHAIN FOR STRATEGIC MATERIALS NdPr OXIDE – FORECAST SUPPLY – DEMAND BALANCE • China currently dominates global RE production (~80%) 160,000 • The EU’s Action Plan on Critical Raw Materials aims to strengthen 140,000 domestic sourcing of raw materials in the EU and diversifying supply Market Overview from both primary and secondary sources 120,000 • US has announced contracts with REE producers to strengthen its 100,000 domestic supply chain 80,000 SUPPLY DEFICIT LIKELY DUE TO CHALLENGES TO BRINGING NEW RARE EARTH MINES INTO PRODUCTION INCLUDE: 60,000 • Many projects are low grade 40,000 • Estimated high levels of capital for complex processing, ranging from 20,000 US$200-500m for major listed rare earths projects - • Current rare earth prices unlikely to support significant development 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 (20,000) RAINBOW’S GAKARA AND PHALABORWA PROJECTS DEMONSTRATE COMPARATIVELY LOW CAPITAL INTENSITY VERSUS OTHER MAJOR (40,000) RARE EARTHS PROJECTS Production Demand Balance Source: Adamus Intelligence 8 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
RAINBOW PROJECTS: SUPPORTED EVEN AT CURRENT NdPr PRICES NDPR PRICES ARE FORECAST TO INCREASE SIGNIFICANTLY BY 2030… ...but the economic viability of Rainbow’s Gakara and Phalaborwa projects is supported even at current prices NdPr PRICE FORECASTS 120 Market Overview 110 100 90 80 70 60 50 40 30 2015a 2016a 2017a 2018a 2019a 2020f 2021f 2022f 2023f 2024f 2025f 2026f 2027f 2028f 2029f 2030f Nd Oxide - US$/kg Pr Oxide - US$/kg Source: Adamus Intelligence 9 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PROJECT OVERVIEW Project Overview: Phalaborwa Project PHALABORWA PROJECT 10 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
SIGNIFICANT NDPR PRODUCTION TO POWER THE GREEN REVOLUTION PHALABORWA – EXCITING, NEAR-TERM GROWTH OPPORTUNITY C.35MT OF GYPSUM IN TWO STACKS FROM 50+ YEARS PHOSPHATE Project Overview: Phalaborwa Project HARD ROCK MINING IN SOUTH AFRICA • Project is largely permitted and positioned in an established mining town, with: • associated skilled labour availability • supporting industry (i.e. local production of key reagent, sulphuric acid) • Initial grab sample assays: c.210,000t rare earth oxides at 0.5% TREO; 29%-30% NdPr, with significant Dy (1%) and Tb (0.3%) credits – supported by Rainbow’s first batch of assay results • Considerably higher grade than a typical ionic clay style rare earth deposit • Assay results by SGS Laboratories indicate low levels of radioactive elements in gypsum stacks • Re-processing has significant environmental benefits: redepositing clean, benign gypsum suitable for usage in building and cement industries 11 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PHALABORWA EXCITING OPPORTUNITY FROM TWO GYPSUM STACKS • Historical processing, including initial flotation Site boundary Project Overview: Phalaborwa Project and concentration by Foskor followed by processing in Sasol’s PhosAcid plant, has deposited REEs in chemical form in two gypsum stacks • Contained in a ‘cracked’ chemical, rare earths expected to deliver higher-value carbonate, with Existing plant area significantly lower operating costs than a typical rare earth project • No need for 1st stage of usual complex processing requirements, which involves producing a concentrate and then ‘cracking’ it before delivering a higher value rare earth Gypsum stack A carbonate • No requirement for waste stripping, hard-rock mining or milling/grinding Gypsum stack B Phalaborwa Project layout 12 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PHALABORWA EXCELLENT LOCAL INFRASTRUCTURE SASOL’S PILOT PLANT REMAINS ON SITE WITH [INSERT PICS FROM DAVE] Project Overview: Phalaborwa Project ASSOCIATED INFRASTRUCTURE OF PHOSPHORIC ACID PLANT, INCLUDING: • High voltage switchyard (providing access to Eskom grid power) • Equipped machine shops • Workshops • Laboratory buildings • Administration offices Stores High voltage switchyard • Acid storage and ammonia tanks • Boilers and rail sidings Laboratory building Sasol pilot plant 13 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
INITIAL ASSAY RESULTS CONFIRM THE HIGH-GRADE NATURE OF THE MINERALISATION INITIAL RESULTS DEMONSTRATE EXPECTED HOMOGENOUS NATURE OF MINERALISATION IN THE GYPSUM STACKS AND ARE SUPPORTIVE OF Project Overview: Phalaborwa Project PREVIOUS INDICATIONS FROM THE SASOL SAMPLE AND TEST WORK PROGRAMME Hole ID Length Dy Nd Pr Tb TREO NdPr Th U 0.5% TREO m ppm ppm ppm ppm ppm % ppm ppm PAH01 12.0 33 946 217 14 4,653 29 43 3 PAH02 9.0 32 1,011 229 12 4,829 30 46 2 29-30% NdPr PAH03 10.5 34 1,055 240 11 5,076 30 47 1 PAH04 12.0 34 1,118 254 10 5,293 30 50 1 PAH05 10.5 33 1,026 235 10 4,894 30 47 2 Significant PAH08 18.0 42 1,187 270 15 5,703 30 40 2 Dy/Tb PAH09 18.0 43 1,155 263 15 5,548 30 42 2 credits PAH10 19.5 36 978 224 11 4,635 30 37 2 PAH11 15.0 37 1,152 263 9 5,462 30 41 2 PAH14 21.0 38 1,052 251 12 5,078 30 44 2 Low levels of PAH15 21.0 35 962 238 10 4,660 30 40 2 reactivity PAH16 21.0 33 928 232 9 4,502 30 41 2 PAH17 18.0 38 1,040 253 9 5,069 30 44 1 PAH23 16.5 41 1,036 238 1 5,093 29 44 2 Value: PAH29 13.5 44 968 223 1 4,826 29 46 2 US$167.55/t PAH34 9.0 38 877 200 1 4,292 29 48 2 of gypsum1 PAH35 13.5 43 964 219 1 4,808 29 50 2 PAH39 9.0 39 844 193 1 4,242 28 44 3 Total 267.0 Average 37 1,024 239 9 4,957 30 43 2 1. based on the assay results announced to date, with reference to rare earth prices published by Argus Media on 5 February 2021 14 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PHALABORWA EARN-IN AGREEMENT • Earn-in agreement signed with Bosveld Phosphates Project Overview: Phalaborwa Project • US$750k consideration for earn-in payable in three tranches in cash and shares over a period of 12 months • US$250k paid in cash in December 2020 on completion of initial confirmatory due diligence process, • Second US$250k tranche payable after 6 months in Rainbow shares at the then prevailing share price • Final tranche payable after 12 months in cash or shares (at the then prevailing share price) at election of Bosveld • Rainbow to fund pre-feasibility study to earn an initial 70% in the unincorporated JV – mechanism to allow Rainbow’s JV ownership to vary from 60% to 85% depending on IRR of PFS at spot rare earth prices versus initial 25% benchmark Image: Sasol’s RE carbonate pilot plant 15 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PROJECT OVERVIEW GAKARA PROJECT Project Overview: Gakara Project 16 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PRODUCING HIGH-GRADE RARE EARTH CONCENTRATE FROM THE ONLY AFRICAN RARE EARTHS MINE IN PRODUCTION PRODUCING HIGH-GRADE RARE EARTH CONCENTRATE FROM THE ONLY AFRICAN RARE EARTHS MINE IN PRODUCTION Project Overview: Gakara Project • Located just south of Bujumbura, Burundi (East Africa) • Large mining permit – 39km2 with over 1,500 occurrences of Rare Earth (RE) discovered in outcrop on surface demonstrating large scale mineralised system • Trial mining and processing since 2017 has demonstrated amenability for simple, low-cost gravity separation from ore sourced from across the licence area • Produces a high value RE concentrate of 52-58% • TREO with low levels of radioactivity currently exported to China for further processing • Weighted towards magnet REs: NdPr represent >88% of value (19.5% of mass) 17 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
GAKARA DEPOSIT A MIX OF BRECCIA AND HIGH-GRADE VEINS Project Overview: Gakara Project Source: PhD thesis, University of Rennes, December 2019 18 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
JORC EXPLORATION TARGET FROM ACROSS THE LICENCE Gasagwe – Trial mined by Rainbow between 2017–2019 Murambi South – Currently being trial mined by Rainbow. producing 1,200t high grade concentrate. Production data and vein mapping data delivered updated Production data and vein mapping data delivered updated target tonnage: 27kt-39kt @ 7-12% TREO Project Overview: Gakara Project target tonnage: 27kt-39kt @ 7-12%TREO Gasenyi – Historic Belgian mine which produced c.500t of high-grade concentrate. Mapped veins, trenching of large veins and historical Kiyenzi – Breccia style mineralization records delivered updated target tonnage: Drilling data re-evaluated alongside trenching, vein 47kt-67kt @7-12% TREO mapping and channel sampling delivered updated target tonnage: 252kt-342kt @ 1-1.5% TREO Rusutama – Historic Belgian mine which produced c. 500t of high-grade concentrate. Mapped veins and historical records delivered updated target tonnage: 23kt-33kt @7-12% TREO Gashirwe West & East – Breccia and vein style mineralization in high priority TECT target corridor. Trenching & mapping of large veins and channel sampling Bigugo – Historic Belgian mine with three large veins mined data delivered updated target tonnage: briefly before Belgian operations ceased entirely. 45kt-64kt @ 7-12%TREO Mapped veins and historical records delivered updated target tonnage: 8kt-11kt @7-12% TREO Gomvyi Central – Breccia and vein style mineralization in Gakara – Largest historic Belgian mine which produced high priority TECT target corridor. c.3,500t of high-grade concentrate between 1947 – 1978. Trenching & mapping of large veins and channel sampling Mapped veins and historical delivered updated target data delivered updated target tonnage: tonnage: 61kt-87kt @7-12% TREO 15kt-22kt @ 7-12%TREO 19 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
GAKARA EXPLORATION TARGET JORC (2012) EXPLORATION TARGET ANNOUNCED OCTOBER 2020 DEFINED CLEAR STRATEGY FOR MODULAR DEVELOPMENT Targeting 10,000-20,000tpa RE concentrate production Lower estimate Upper estimate Project Overview: Gakara Project Tonnes TREO % Tonnes TREO % Vein Hosted Mineralisation Murambi South 36,000 7.0% 52,000 12.0% Gasagwe 27,000 7.0% 39,000 12.0% Rusutama 23,000 7.0% 33,000 12.0% Gakara 61,000 7.0% 87,000 12.0% Gomvyi Central 15,000 7.0% 22,000 12.0% Gashirwe West and East 45,000 7.0% 64,000 12.0% Bigugo 8,000 7.0% 11,000 12.0% Gasenyi 47,000 7.0% 67,000 12.0% Total Vein Hosted Exploration Target 262,000 7.0% 375,0000 12.0% Breccia Hosted Mineralisation Kiyenzi grade tonnage model 98,000 1.0% 132,000 1.5% Kiyenzi depth extension 60,000 1.0% 82,000 1.5% Kiyenzi lateral extension 94,000 1.0% 128,000 1.5% Total Breccia Hosted Exploration Target 252,000 1.0% 342,000 1.5% Note: The potential quantity and grade of the Exploration Target is conceptual in nature, there being insufficient exploration to estimate a Mineral Resource and that it is uncertain if further exploration will result in the estimation of a Mineral Resource. Numbers are rounded to appropriate levels commensurate with the level of accuracy of an Exploration Target. The Exploration Target was estimated as a range as required by the JORC Code (2012) and is based on data of varying quantity and quality, although is based largely on actual exploration, mining and processing results 20 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
PROGRESSING MINING AT GAKARA TO MECHANICAL METHODS TRIAL MINING HAS PROGRESSED FROM SMALL-SCALE MANUAL …TO BULK MECHANICAL WASTE MINING AND SELECTIVE MECHANICAL FOCUSSED OPERATION… MINING METHOD Project Overview: Gakara Project • A second new mining fleet is now in operation on site PRE-2020 CURRENT OPERATIONS 21 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
ROAD MAP DELIVERING OUR LONG-TERM PLAN AT GAKARA EXPLORATION TARGET ANNOUNCED OCTOBER 2020 DEFINED CLEAR STRATEGY FOR MODULAR DEVELOPMENT Targeting 10,000-20,000tpa RE concentrate production Project Overview: Gakara Project STAGE 1 STAGE 2 STAGE 3 STAGE 4 STAGE 5 Current status 2021-22 2022 2023 2024+ • Trial mining proof of • Upgrade Gakara JORC • Grow JORC resource • Build commercial scale • Establish downstream concept at Gakara Project exploration target to base: large mineralised process facility for an beneficiation to produce a in Burundi inferred resources1 system expected to initial 5ktpa concentrate cerium depleted mixed RE support up to 10ktpa - production expanding to carbonate • Producing +/- 54% TREO • Define technical 20ktpa concentrate 10-20ktpa concentrate via simple requirements for initial • Further downstream open pit mining and commercial scale • Complete full technical • Capital cost not expected processing to separated gravity separation from production study on modular to exceed US$20 million Nd and Pr oxides to supply high-grade stockwork commercial production for up to 10ktpa permanent magnet vein system • Expand trial mining to facility concentrate plant manufacturers confirm detailed • Planned break-even trial knowledge of resources mining delivering 100+ and mineralogy tpm concentrate from Q2 2021 1. Exploration drilling to upgrade existing JORC Exploration Target to inferred resources dependent on future financing 22 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
GAKARA SIMPLE DEVELOPMENT OPPORTUNITY EXPLORATION TARGET ANNOUNCED OCTOBER 2020 DEFINED CLEAR STRATEGY FOR LOW CAPITAL INTENSITY MODULAR DEVELOPMENT Targeting 10,000-20,000tpa RE concentrate production Project Overview: Gakara Project 23 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
SUMMARY RAINBOW: A STRATEGIC SOURCE OF RARE EARTH Summary MINERALS FOR A GROWING MARKET 24 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
RAINBOW A STRATEGIC SOURCE OF RARE EARTH MINERALS FOR A GROWING MARKET Rainbow Rare Earths is uniquely positioned to benefit from the expected growth in the demand for Rare Earths to power the Green Revolution • Rainbow has both project and country risk diversification from two potentially world-class, scalable projects in Burundi and South Africa • Huge growth in demand expected for NdPr to power the green Summary revolution • Growing supply/demand imbalance • Mounting pressure from Governments and investors to secure independent rare earth mineral supply • Both Rainbow’s projects enjoy simple mining and processing with low levels of radioactivity for expected low capital intensity development opportunity 25 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
OUR BOARD ADONIS POUROULIS GEORGE BENNETT NON-EXECUTIVE CHAIRMAN CEO • Mining engineer: an entrepreneur whose expertise lies in the discovery, exploration • 25 years in finance and management, including as partner in stockbroking/advisory and development of natural resources across Africa including diamonds, firms in SA precious/base metals, coal and oil and gas. • Former CEO of Shanta Gold Ltd, successfully listed on LSE in 2005 • Founder of Rainbow and Petra Diamonds (LSE:PDL); Founder and Director of Chariot • CEO and Founder of MDM Engineering, listed on LSE in 2008; responsible for building Oil & Gas (AIM:CHAR) and Founder of Pella Resources Limited 22 process plants and completing over 80 feasibility studies – sold after 8 years to Foster Wheeler for US$120 million • Seed-funded and raised initial capital for OreCorp Ltd, now ASX listed Summary SHAWN MCCORMICK ROBERT SINCLAIR NON-EXECUTIVE DIRECTOR NON-EXECUTIVE DIRECTOR • International affairs specialist • Chartered Accountant with over 38 years’ experience in finance & accountancy • Over 25 years of political and extractive industries sector experience having served • Founder and former MD of Artemis Trustees Limited in The White House as Director for African Affairs on the National Security Council • Fellow of the Institute of Chartered Accountants in England and Wales (Washington) • Previously Political Affairs Director of BP (London) and VP of TNK-BP (Moscow) ALEXANDER LOWRIE ATUL BALI NON-EXECUTIVE DIRECTOR NON-EXECUTIVE DIRECTOR • Investment banker with 13 years’ experience and previous director roles at Deutsche • Corporate CEO with extensive experience in tech, government contracting and Bank and RBS regulated industries • Co-founder of Telemark Capital LLP • Currently Non-Executive Director of Gaming Realms Plc and Chairman of Meridian • Significant market experience: IPOs and primary and secondary equity offerings Gaming • Previously held divisional CEO or President positions with IGT (NYSE), Aristocrat (ASX), and Real Networks (NASDAQ), as well as a venture capital firm 26 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
OUR EXECUTIVE MANAGEMENT GEORGE BENNETT PROF. GILBERT MIDENDE CEO CHARGE D’AFFAIRS - BURUNDI • 25 years in finance and management, including as partner in stockbroking/advisory • Former Minister of Energy and Mines of Burundi, twice firms in SA • Former Minister of Higher Education and Scientific Research of Burundi • Former CEO of Shanta Gold Ltd, successfully listed on LSE in 2005 • Former Rector of the National Burundi University • CEO and Founder of MDM Engineering, listed on LSE in 2008; responsible for building • Former Director General of Geology and Mines of Burundi 22 process plants and completing over 80 feasibility studies – sold after 8 years to • Six years as a World Bank consultant on mining issues in the sub-region and Burundi Foster Wheeler for US$120 million • Seed-funded and raised initial capital for OreCorp Ltd, now ASX listed Summary PETER GARDNER CHRISTOPHER ATWOOD CHIEF FINANCIAL OFFICER PROJECT MANAGER - BURUNDI • Qualified Chartered Accountant • 25 years’ experience in mining and extractive industries. • 15 years’ experience in mining industry leading finance teams across Africa and • Track record of driving expansion and minimising costs developing nations • Associated with startup ventures in remote locations. • Former CFO of Amara Mining plc (up to acquisition by Perseus Mining Ltd), Chaarat • Led Operations up to 35MTPA successfully Gold, Piran Resources and Alexander Mining DAVE DODD TECHNICAL DIRECTOR • 45 years of extractive metallurgy experience • Dave Dodd – Metallurgical Project Consultant • BSc (Hons) Chemical Engineering (1974) • Fellow of Southern Africa Institute of Mining & Metallurgy 27 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
KEY SHAREHOLDER INFORMATION BOARD SHAREHOLDINGS Shareholder Holding Ticker Market Market cap Share price Shares in Brokers issue Adonis Pouroulis* 16.1% RBW.L LSE £76m 16p 474m SP ANGEL George Bennett* 7.3% SHARE PRICE Summary Shawn McCormick* 2.0% Alexander Lowrie 1.3% Robert Sinclair 1.1% Atul Bali 0.8% Total 28.9% * Held through a discretionary trust 28 Rainbow Rare Earths Limited H1 2021 Interim Results Presentation – March 2021
RAINBOW RARE EARTHS THANK YOU Contact us: GEORGE BENNETT PETE GARDNER CEO CFO SA Mobile: +27 82 652 UK Mobile: +44 771 779 4251 Office Number: + 27 11 996 3500 Skype: petegardner73 Skype: George.bennett72 Email: peteg@rainbowrareearths.com Email: georgeb@Rainbowrareearths.com