MAGNA GLOBAL                                                                                                  Table of Contents
SUPPLY CHAIN REQUIREMENTS                                                                                     SECTION                                          CONTENT                                                PAGE

As part of an increasingly competitive and            This Global Supply Chain Requirements Manual            1. Introduction                                  1.1 – The Magna-Supplier Relationship                     4
demanding industry, Magna has a diversified,          defines Magna’s requirements on behalf of all           		                                               1.2 – Communication – Notification of Change              5
global supply chain that supports our global          global manufacturing locations. There may be            		                                               1.3 – Continuity of Supply                                6
operations and, ultimately, our OEM Customers.        additional, customer/Division specific requirements     		                                               1.4 – Corporate Social Responsibility/Sustainability      6
Magna has implemented many changes over the           that are also required at a Division level, which may
past few years, and we continue to evolve, in our     be more detailed or stringent than requirements         2. Leadership & the Organization                2.1 – Supplier Qualifications                             9
efforts to maintain our position as a world-class     defined in the Global Supply Chain Requirements,            		                                           2.2 – Certifications                                      9
design, engineering and manufacturing company.        and Suppliers are expected to comply with both          		                                               2.3 – Supplier Assessments                               11
                                                      sets of requirements. Every attempt has been
We recognize that our supply chain is an integral     made to ensure that requirements in this Manual         3. Operation- Design                            3.1 – Defining the Scope                                 12
part of what we do, and we have committed to          and requirements defined by a Division level                & Development Planning                       3.2 – Planning and Definition of Requirements            13
continue our efforts at standardizing many of         document, are not in conflict. If such conflict         		                                               3.3 – Product Design and Development                     13
our supply chain management processes and             does in fact occur, you are expected to contact         		                                               3.4 – Tooling, Gauges & Test Fixtures                    14
systems. As part of that effort, this Global Supply   your local Division representative who will work to     		                                               3.5 – Process Design and Development                     14
Chain Requirements Manual forms the basis of          ensure resolution of that conflict.                     		                                               3.6 – Product and Process Validation                     15
our business relationship with our Suppliers. In                                                              		                                               3.7 – Feedback and Assessment                            16
addition to defining manufacturing, logistics and     Our Suppliers are important to Magna, and we
quality requirements, this Manual also details        will continue to strive to ensure a relationship of     4. Operation - Control Of Production            4.1 – Control of Fixtures & Test Equipment               17
necessary environmental, compliance and other         mutual respect and benefit, and we thank you for                                                         4.2 – Monitoring of Product & Process                    18
sustainability requirements that have become          your support.                                           		                                               4.3 – Non-conformance & Corrective Action                18
critical to the industry.                                                                                     		                                               4.4 – Product or Process Change & Deviations             21
                                                                                                              		                                               4.5 – Warranty                                           21

                                                                                                              5. Operation – Control of Materials/Logistics   5.1 – General Requirements                               23
                                                                                                                  		                                           5.2 – Packaging                                          23
                                                                                                              		                                               5.3 – Labelling                                          24
                                                                                                              		                                               5.4 – Materials Planning & Forecasting                   25
                                                                                                              		                                               5.5 – Transportation, Schedules & Routing                25
Tom Skudutis                                                                                                  		                                               5.6 – Border Security                                    26
COO Magna International
                                                                                                              		                                               5.7 – FTA/Customs Compliance                             27
                                                                                                              		                                               5.8 – Documentation                                      27
                                                                                                              		                                               5.9 – MMOG                                               28

                                                                                                              6. Control of External Products & Services      6.1 – Supplier Performance Reporting                     29
                                                                                                                  		                                           6.2 – Operational Rating Criteria                        29
                                                                                                              		                                               6.3 – Continuous Improvement                             29

                                                                                                              7. Glossary of terms		                                                                                    30

                                                                                                              8. References		                                                                                           32
1. INTRODUCTION                                                                                                        Division standards applicable to the Magna
                                                                                                                           operating Group(s) with which you conduct
                                                                                                                                                                                     2. All proposed material and/or process changes,
                                                                                                                                                                                        including any change in process or product
                                                                                                                           business. The quality and delivery requirements              safety or critical characteristics.
                                                                                                                           defined herein are to be considered an addendum           3. All proposed changes, including:
                                                                                                                           to the Purchase Order and Terms & Conditions                 • Manufacturing location change
                                                                                                                           issued to all Suppliers and do not replace or                • Tooling capacity change
                                                                                                                           alter the terms and conditions covered by these              • Re-commissioning of tooling that has been
                                                                                                                           purchasing documents, the Statement of Work               		 inactive for one year

                                                                   1.1 THE MAGNA – 			                                     (SOW) or warranty agreements. Suppliers are also
                                                                                                                           expected to comply with any terms and conditions
                                                                                                                                                                                        • Tooling refurbishment/replacement
                                                                                                                                                                                        • Proposed use of new manufacturing
                                                                       SUPPLIER                                            imposed on Magna, by the customer to whom the             		equipment

                                                                       RELATIONSHIP                                        final products are ultimately being shipped.                 • Tooling transfer (re-source)
                                                                                                                                                                                     4. Any potential manufacturing/quality issues,
                                                                                                                           This includes compliance with any specific forms             including any change in Quality Management
                                                                   Magna is committed to maintaining its position as
                                                                                                                           or documents specified by any Customer of                    Systems certification status (expiry, suspension,
                                                                   a global leader within the automotive sector and
                                                                                                                           Magna. Suppliers to Magna are also expected to               withdrawal or revocation).
                                                                   we recognize the integral role that each supplier
                                                                                                                           manage their sub-tier Suppliers of products and           5. Any potential supply and/or capacity issues.
                                                                   to Magna has in maintaining our position of
                                                                                                                           services to ensure compliance to the requirements         6. Changes to sub-Suppliers of raw material,
                                                                   excellence in innovation, technology, cost, quality
                                                                                                                           defined within this manual, Magna Purchasing                 components or services.
                                                                   and delivery.
    The expectations, requirements and standards                                                                           Terms & Conditions, Magna’s Supplier Code of              7. Information Technology (IT) or supporting system
    defined within this manual are applicable to all                                                                       Conduct and Ethics, the latest automotive industry           changes that might impact production or
                                                                   Magna is committed to a zero PPM strategy and
    Suppliers providing materials, products and                                                                            standards and any additional Customer or Division            shipment of product to Magna.
                                                                   expects all Suppliers to support this strategy and
    services to any Magna manufacturing facility.                                                                          specific requirements.                                    8. Organizational changes with the potential for
                                                                   manage their own operations, similarly. Our intent is
    This includes Suppliers of direct materials and,                                                                                                                                    impact on manufacture or supply of product to
                                                                   to establish strategic, long-term relationships with
    as appropriate, indirect materials, packaging                                                                                                                                       Magna.
                                                                   our Suppliers, and it is incumbent on each supplier
    materials and services (including containment,                                                                                                                                   9. Changes to ownership structure.
                                                                   to maintain a position of cost leadership while
    sorting and calibration services) with potential
    impact on any product characteristics affecting
                                                                   demonstrating a commitment to sustained quality,        1.2 	COMMUNICATION –                                     Suppliers will support all tests, validations, approvals
                                                                   highest levels of service and a strong focus on
    Magna’s Customer requirements. These
                                                                   continuous improvement.
                                                                                                                                 NOTIFICATION OF 			                                 and submissions required as a result of product or
    requirements also apply, in whole, to any supplier                                                                                                                               process changes, as directed by Magna. Suppliers
    that is directed to Magna, by any OE Customer.
                                                                                                                                 CHANGES                                             cannot charge for samples or testing resulting
    The requirements as detailed in this manual                    We will endeavour to make every effort to manage                                                                  from supplier related or requested changes, unless
    define basic requirements and are supplemental                 our supplier relationships with the highest degree      It is critical that the relationship between Magna        approved by Magna.
    to requirements as defined within the latest ISO               of integrity and professionalism, and we will ensure    and our Suppliers be premised on open, effective
    9001 and IATF 16949 Standards, and any specific                that our decisions are based upon optimization of       and proactive communication. The occurrence of            Suppliers must be proactive in their communication
    requirements as communicated by your procuring                 value to Magna and its stakeholders. We will not        non-conforming product, unauthorized changes or           with their Magna customers (Reference Section 4.4)
    division. The latest version of this manual will               allow any undue influence or inappropriate activity     any related supply chain issues, present a risk to        and all changes must be communicated to Magna,
    be posted on the Magna website supplier portal                 to compromise those decisions.                          both Magna and to Magna’s customer(s), when not           prior to proceeding with those changes. Failure to
    (https://www.magna.com/company/suppliers) or                                                                           communicated and managed effectively. These risks         notify Magna of potential issues or changes will result
    the ERFX portal (https://ERFX.magna.com), and                  This Supplier Manual outlines the fundamental           also manifest themselves at the sub-tier Suppliers        in internal elevation, as appropriate, and may result
    the Magna Quality Platform – QPF (https://qpf.                 requirements for all Suppliers to Magna                 and sub-contractors that comprise the overall supply      in notification of the issue to Magna’s customers. If
    magna.com/). Suppliers must review any one of                  International’s global operations. The Quality          chain. In order to manage these risks most effectively,   necessary, a supplier’s ISO and/or IATF Registrar will
    these sites on a regular basis to ensure they have             Systems requirements have been aligned across           all Suppliers must communicate as early as possible,      be contacted and asked to conduct any necessary
    the most recent version available. Suppliers must              all our global manufacturing sites, to the greatest     the following:                                            investigations or assessments. In the absence of
    have access to ERFX (https://ERFX.magna.com)                   extent possible. In addition to the requirements        1. Any pending or potential issue which the 		            proactive communication of potential changes,
    and to QPF (https://qpf.magna.com/).                           defined in this document, there may be additional             supplier has identified.                            any costs incurred by Magna as a result of late

4   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                                5
notification or insufficient lead time, from the supplier,
                                                                   and requirements covering corporate social                having the objective of achieving certification       Magna expects our Suppliers and their sub-tier
    will be the responsibility of the supplier and will be
                                                                   responsibility/sustainability,                            status. In support of managing impact on the          Suppliers, as appropriate, to register and comply
    charged to the supplier, as appropriate. Continued                                                                       environment, Suppliers should be monitoring           with all applicable reporting requirements that are
    non-compliance may lead to loss of business.
                                                                   LEGAL COMPLIANCE & ETHICAL BEHAVIOUR                      and optimizing greenhouse gas emissions, water        applicable to their products and processes.
                                                                                                                             consumption and emissions of volatile organic
                                                                   We expect that our Suppliers will always act              compounds (VOCs), particulate matter and ozone        RESPONSIBLE SOURCING OF RAW MATERIALS
                                                                   with integrity by obeying the letter and spirit of        depleting substances.
                                                                   laws, regulations, standards and Magna policies                                                                 The automotive parts we produce involve the use
    1.3 CONTINUITY OF                                              that apply to them, regardless of where they do           In support of sustainability initiatives we           of several minerals and other raw materials. We are
        SUPPLY                                                     business, including:                                      encourage our Suppliers to effectively manage,        committed to ensuring that the materials used in
                                                                   •   Antitrust and Competition Laws                        monitor and optimize energy consumption               our parts have been sourced responsibly – that is,
                                                                   •   Anti-bribery laws                                     through an effective energy management                they do not originate from conflict-affected areas.
    Suppliers are required to have well defined business           •   Gifts & Entertainment limits or prohibitions          program. We encourage Suppliers to consider           Responsible sourcing of raw materials is key to
    contingency plans in place to ensure continuity of             •   Sanctions and Export Control Laws                     using ISO 50001 as a guideline to an effective        ensuring that Magna and its Suppliers are able to
    supply in the event of disruption to their operations          •   Responsible sourcing, including prohibitions 		       energy management standard, however                   meet its commitments to respect human rights,
    and/or supply of materials, as a result of man-                    on sourcing materials from areas of conflict          certification is not mandatory at this time, unless   as reflected in our Code of Conduct and Supplier
    made events, natural disasters, utility or labour              •   Respect for Human Rights                              as directed by the jurisdiction within which          Code of Conduct, respectively.
    disruptions, equipment or logistics failures or                •   Diversity and Inclusion                               operations exist.
    interruptions, or disruptions/attacks on information           •   Health & Safety requirements                                                                                A growing number of regulations, emerging
    technology systems. These contingency plans shall              •   Environmental Sustainability                          Magna, and its supply base, must meet all             industry best practices, and OEM customers
    be reviewed on a regular basis. Suppliers shall                •   Preventions of Conflicts of Interest                  requirements of End-of-Life Vehicle (ELV),            require Magna to disclose the origin of various
    immediately notify all Magna Divisions to which they           •   Protection of Magna Information and 		                International Material Data System (IMDS),            raw materials used in its products. Given the
    ship product, the moment they become aware of                      Intellectual Property or, if applicable, that of 		   Registration, Evaluation, Authorization and           breadth and complexity of Magna’s supply chain,
    any potential supply disruption.                                   Magna’s OEM customers                                 Restriction of Chemicals (REACH) and China            we necessarily rely on our Suppliers for accurate
                                                                                                                             Automotive Material Data System (CAMDS)               information about products supplied to Magna. I
    Each Supplier to Magna shall identify an individual            Suppliers must abide by the full requirements of          directives. As required, Suppliers shall comply
    from the Supplier’s manufacturing location, with               the Magna Supplier Code of Conduct and Ethics             with applicable standards on the classification,      In order to accurately and completely meet
    sufficient authority to assume responsibility for              and should, in turn, also require that their Suppliers    packaging and labeling of hazardous substances        disclosure requirements related to raw materials
    dealing with any product quality and/or delivery               abide by the same requirements (https://www.              and mixtures, including national implementations      in our products, Magna expects and requires its
    related issues that may impact Magna or Magna’s                magna.com/company/Suppliers) .                            of the UN Globally Harmonized System (GHS),           Suppliers to conduct appropriate due diligence to
    Customers. The identified contact needs to be                                                                            such as Regulation (EC) No 1272/2008 on               enable the Supplier to provide information about
    available at any time such issues arise.                       ENVIRONMENTAL RESPONSIBILITY                              the classification, labeling and packaging of         product origin. Where necessary, this will require
                                                                                                                             substances and mixtures (CLP Regulation) and          Suppliers to obtain such information from its own
    Contact information shall be made available to the             Magna’s objective is to be an industry leader in          the Workplace Hazardous Material Information          Suppliers as well.
    Magna Division being supplied, or uploaded in the              health, safety and environmental practices. We            System (WHMIS). For all parts supplied to Magna,
    appropriate database(s), as directed by Magna.                 are committed to environmental responsibility and         including new or modified parts and spare parts,      CONFLICT MINERALS
                                                                   have many different programs designed to protect          compliance to current legal requirements must be
                                                                   our environment and manage critical resources             ensured (e. g. REACH, GADSL).                         Under legislation which came into effect in
                                                                   so as to sustain and replenish these resources                                                                  2012, manufacturers, including Magna, who
    1.4 CORPORATE SOCIAL 		                                        for future generations. We expect our Suppliers           Correct and complete Material Data Sheets             file certain reports with the U.S. Securities and
                                                                   to show the same dedication and commitment to             (MDS), that comply with Conflict Minerals             Exchange Commission (SEC) must disclose
        RESPONSIBILITY/ 			                                        the environment and recommend certification to            Guidelines, must be submitted in the IMDS             whether products they manufacture, or contract
        SUSTAINABILITY                                             ISO 14001 environmental standards. ISO 14001              (International Material Data System) and/             to manufacture, contain conflict minerals that
                                                                   certification is currently monitored, and Suppliers       or CAMDS (China Automotive Material Data              come from sources that support or fund inhumane
    Magna is committed to being a responsible                      not currently holding environmental certification         System), to prove compliance. For parts not           treatment in the region of the Democratic Republic
    corporate citizen. We expect our Suppliers to                  are encouraged to develop a plan of execution             subject to PPAP, MDS must be submitted in             of the Congo or an adjoining country.
    adhere to the elements of Magna’s policies                                                                               IMDS, upon request.

6   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                         7
Currently, SEC requirements list Tin, Tantalum,
    Tungsten and Gold (collectively, 3TG) as Conflict
                                                                   Counterfeit product is defined as items that are, or
                                                                   contain, unlawful or unauthorized reproductions,         2. LEADERSHIP &
    Minerals. Other minerals may be added in the
    future.
                                                                   substitutions or alterations that have been
                                                                   knowingly mismarked, misidentified or otherwise
                                                                   misrepresented to be an original manufacturer’s
                                                                                                                                THE ORGANIZATION
    Other jurisdictions, including the EU, are in                  part. Suppliers must have strict procurement
    the process of implementing or considering                     policies in place to ensure traceability for all items
    similar Conflict Minerals regulations. To ensure               incorporated into their product.                                                                                the supplier assessment and supplier sourcing
    compliance with the SEC requirements, and any                                                                                                                                  processes. Key performance metrics and
    requirements implemented by other jurisdictions                                                                                                                                Supplier ratings are also communicated via these
    in the future, Magna must request information                                                                                                                                  databases.
    regarding the use of conflict minerals, from any                                                                        2.1 SUPPLIER
    appropriate Suppliers. Any Suppliers contacted
    by Magna, are required to support Magna by
                                                                                                                                QUALIFICATIONS Suppliers to Magna must also meet key
                                                                                                                                               operational, financial and quality criteria, which
    accurately providing all requested data and reports                                                                                                                            combined determine a supplier’s status. These
    in a timely manner.                                                                                                     All direct material Suppliers must have a valid        metrics are reviewed on a regular basis and assist
                                                                                                                            DUNS number as issued by Dun & Bradstreet              in development of Magna’s overall purchasing
    Additional information on conflict minerals                                                                             and, as applicable by region, a valid VAT or HST       strategies, while at the same time driving Magna’s
    reporting can be found by clicking on either of                                                                         number. DUNS numbers are validated by Magna,           Supplier development processes.
    these two links: http://www.aiag.org                                                                                    and misrepresentation could disqualify you from
    http://www.conflict-minerals.com. Magna’s Policy                                                                        Magna business. Suppliers of indirect materials
    Statement on Conflict Minerals can be found at:                                                                         and services may also require a DUNS number, as
    https://www.magna.com/company/Suppliers                                                                                 directed by your procuring Division.
                                                                                                                                                                                   2.2 CERTIFICATIONS
    REPORTING OF OTHER RAW MATERIALS                                                                                        Any Suppliers shipping to any Magna group must
                                                                                                                            be registered in both ERFX (https://ERFX.magna.        A Supplier’s top management shall demonstrate
    In addition to Conflict Minerals disclosure                                                                             com) and QPF (https://qpf.magna.com/). Suppliers       leadership and commitment to their quality
    requirements above, heightened industry and                                                                             registering in these databases must complete all       management system, and they are ultimately
    customer focus on responsible sourcing has                                                                              information fields profiling applicable business       accountable for the overall effectiveness of that
    increased demand for transparency into the                                                                              systems, commodity capabilities and identifying        system. Top management is responsible to ensure
    origins of other raw materials used in automotive                                                                       key contact personnel. When registering in             that risk-based thinking is evident and effective in
    products. Currently, disclosure is being sought for                                                                     ERFX, Suppliers will be required to register one       all aspects of a Supplier’s management system. To
    a number of other raw materials including: Cobalt,                                                                      Quality contact, one Commercial contact and            ensure this, management’s responsibilities should
    Mica and Rubber. Disclosure regarding additional                                                                        one Financial contact, at minimum. If a Supplier       include:
    raw materials may be requested or required in the                                                                       has multiple manufacturing sites with applicable       • Conducting contingency planning reviews
    future. It is our expectations that such information                                                                    unique DUNS identification, each manufacturing         • Identify and support process owners
    will increasingly become a prerequisite for                                                                             DUNS site is required to register in the appropriate   • Support and participate in the escalation
    quotation by OEM customers, and Magna expects                                                                           database. Suppliers are required to maintain               process related to all safety relevant products
    its Suppliers will conduct similar due diligence with                                                                   information in the database to ensure it remains           and processes
    respect to additional raw materials as it requires                                                                      current. At a minimum, data must be reviewed           • Ensure achievement of customer quality targets
    for 3TG.                                                                                                                and, if necessary, updated at least annually.              and performance requirements
                                                                                                                                                                                   • Implement corporate responsibility initiatives
    COUNTERFEIT PRODUCT                                                                                                     Maintaining current information is critical as these       dealing with anti-bribery, code of conduct
                                                                                                                            global databases are accessible to all Magna               and ethics and sustainability initiatives
    Suppliers must ensure that there is no risk of                                                                          buyers and quality personnel, worldwide. The               (including Human Rights, Health & Safety and
    counterfeit product being shipped to Magna.                                                                             ERFX and QPF platforms are also used during                Environmental sustainability)

8   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                          9
as detailed within this manual. Assessments or
     Magna’s goal is for all Suppliers of materials and             safety representative for each applicable              notification to Magna, for any potential impact to
                                                                                                                                                                                 reviews may be conducted from time to time in
     services, producing or affecting direct production             manufacturing location.                                Magna data or business.
                                                                                                                                                                                 order to ensure the on-going stability and viability
     material, to become certified to IATF 16949.
                                                                                                                                                                                 of Magna’s supply base. All Suppliers, including
     At minimum, all Suppliers of direct production                 Suppliers shall establish and maintain a               With the ever-increasing dependence on electronic
                                                                                                                                                                                 Customer-designated or Customer-directed, are
     material to Magna, must demonstrate conformity                 documented process to ensure identification            systems and communications, and in recognition
                                                                                                                                                                                 expected to provide, upon reasonable notice,
     to the latest IATF 16949 Standard, and to other                of training needs and documentation showing            of the ever-increasing threats to information
                                                                                                                                                                                 access to their facility as well as those of sub-tier
     standards that might be directed by the procuring              achieved competence levels for all personnel           protection and security, all Suppliers are
                                                                                                                                                                                 Suppliers, as necessary. Following notification of a
     Division(s) including, but not limited to VDA,                 performing activities affecting conformity to          encouraged to become certified to ISO/IEC 27000.
                                                                                                                                                                                 requested assessment, Suppliers are expected to
     ISO 17025, ISO 45001, ISO/IEC 27001, TISAX/                    product and process requirements. This shall
                                                                                                                                                                                 acknowledge and respond to such request, within
     TPISR, ISO 26262 and ISO 15504-5 Automotive                    include documented verification of competence          Magna is working to be a leader in the area of
                                                                                                                                                                                 30 days. All appropriate measures will be taken to
     SPICE, latest revision of IPC-A-610, latest                    for personnel conducting internal audits, including    cyber/information security, and it is important
                                                                                                                                                                                 protect confidentiality of operational and financial
     revision of DIN EN 61430 and ANSI/ESD S20.20.                  Quality Management System audits and applicable        that all identified confidential information such
                                                                                                                                                                                 information.
     Suppliers who are not certified to IATF 16949                  CQI assessments.                                       as, but not limited to, specifications, design and
     must, as a minimum, be certified to the latest ISO                                                                    engineering data and other critical information, is
                                                                                                                                                                                 Assessment results are intended for verification
     9001 standard and comply with the “Minimum                      In addition to direct material Suppliers the          managed and maintained in a secure environment.
                                                                                                                                                                                 of applicable ISO, IATF, VDA and applicable
     Automotive Quality Management System                           scope of these requirements applies to Suppliers
                                                                                                                                                                                 Customer Specific Requirements and in no way
     Requirements for Sub-Tier Suppliers” (Magna                    of subassembly, sequencing, sorting and re-            TISAX (Trusted Information Security Assessment
                                                                                                                                                                                 reduce or negate responsibility to meet specific
     MAQMSR – available at https://qpf.magna.com/).                 work (either on-site or at a remote location) and      Exchange) (www.tisax.org) and TPISR (Third Party
                                                                                                                                                                                 regulatory, health and safety or other legal
                                                                    services. Suppliers are expected to maintain the       Information Security Requirements) (https://www.
                                                                                                                                                                                 requirements applicable to the Supplier.
     Magna also encourages our Suppliers to work                    same level of quality and manufacturing controls,      aiag.org/supply-chain-management/cybersecurity)
     towards certification to ISO 45001 and ISO 14001.              for the production of service parts and assemblies     define industry standards for information security
     Suppliers who are only certified to ISO 9001 may               (i.e. for the full life of the program). This shall    and establish assessment requirements to ensure
     be subject to an annual management system                      include any service requirements transferred to any    globally harmonized levels of information security.
     audit, by a qualified Magna or 3rd party auditor. At           alternate site, location or organization. Suppliers
     a minimum, Suppliers who are not IATF certified,               of service parts, components or assemblies must        As determined by the nature and need for
     will be required to complete an annual MAQMSR                  comply with the AIAG Service Parts Production          protection of information and data, Suppliers shall
     self-audit, available in the Audit Module in Magna’s           Approval Process (Service PPAP).                       be able to demonstrate adequate safeguards
     QPF system (https://qpf.magna.com ). Should                                                                           and appropriate levels of information security. If
     any existing certification expire, be revoked, or be           Suppliers shall post, and update all applicable        directed by Magna’s OE Customer, certification to
     placed in suspension or probation, the Supplier                certifications based on notifications received from    TISAX or TPISR may be required. Specific cyber
     must immediately contact every Magna Division to               the ERFX system.                                       security requirements will be directed by your
     which the Supplier ships product, notifying them of                                                                   procuring Division.
     the change in certification status. Any suspension             Failure to upload required or renewed certifications
     in certification status must be reported to all                will result in a penalty to your supplier scorecard
     applicable Magna Divisions within 5 working days.              and could impact future business.
                                                                                                                           2.3 SUPPLIER
     Suppliers shall also maintain all required CQI                 CYBER AND INFORMATION SECURITY
     Assessments, as defined by their processes (Ref.
                                                                                                                               ASSESSMENTS
     http://www.aiag.org) and all applicable FMVSS                  Suppliers must have systems and procedures
                                                                                                                           Magna reserves the right to review and assess
     Standards, including but not limited to FMVSS 302              in place to protect computers, servers, mobile
                                                                                                                           a Supplier’s financial, operational, information
     (Flammability reporting) requirements, in support of           devices, electronic systems, networks and data
                                                                                                                           and IT security, quality, environmental and
     applicable OE Customer-specific requirements                   from any form of malicious attack.
                                                                                                                           Health & Safety systems, for the purposes of
     (Ref. http://www.iatfglobaloversight.org/). CQI
                                                                                                                           validating compliance to standards established
     Assessments need to be renewed on an annual                    Suppliers must have procedures in place, detailing
                                                                                                                           by applicable ISO, IATF, VDA 6.3 Standards, OE
     basis, as determined by the latest date of                     response to any attempted or actual cyber-
                                                                                                                           Customer Specific Requirements or requirements
     completion. Suppliers shall nominate a product                 attack. These procedures must include immediate

10   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                        11
3. OPERATION – DESIGN &                                                                                                Suppliers are expected to use all appropriate
                                                                                                                            tools in the product and process planning phase
                                                                                                                                                                                  • Historical quality data on previous designs or
                                                                                                                                                                                    revisions of the current part, or on similar parts

     DEVELOPMENT PLANNING
                                                                                                                            including, but not limited to:
                                                                                                                                                                                    and manufacturing processes, shall be
                                                                                                                            • Geometric dimensioning & tolerancing (GD&T)
                                                                                                                                                                                    reviewed. Problem reports and corrective
                                                                                                                            • Design for manufacturing & assembly (DFMA)
                                                                                                                                                                                    actions, rework and scrap shall be reviewed to
                                                                                                                            • Design of experiments (DOE)
                                                                                                                                                                                    ensure inclusion of adequate controls to
                                                                                                                            • Simulation & Modelling
                                                                                                                                                                                    prevent recurrence of previous non-
                                                                                                                            • Failure Modes & Effects (FMEA)
                                                                    Responsibilities shall be mutually agreed upon                                                                  conformities.
                                                                                                                            • Finite Element Analysis (FEA)
                                                                    prior to the start of any certification activity.
                                                                    Suppliers will ensure that resources are available                                                            • Any campaign prevention data, or
                                                                                                                            The Supplier’s scope of planning will also ensure
                                                                    and able to communicate effectively, to ensure                                                                  government recall or technical service
                                                                                                                            that all capital and tooling budgets necessary to
     3.1 DEFINING                                                   successful completion of all requirements to meet
                                                                    defined program timing. It is also the responsibility
                                                                                                                            support the program, are approved and in place in
                                                                                                                                                                                    bulletin data shall be reviewed, if available.

         THE SCOPE                                                  of Suppliers to ensure any sub-tier Suppliers for
                                                                                                                            time to meet timing requirements.
                                                                                                                                                                                  Suppliers shall work closely with Magna to
                                                                    which they are responsible, also have sufficient                                                              ensure all processes are controlled adequately
     Magna requires Suppliers to complete all advance               resources assigned.                                                                                           so as to prevent the manufacture and transfer of
     product planning and submission in full accordance                                                                                                                           defects. Process controls must be sufficient so
     with the AIAG Advance Product Quality Planning                 Suppliers will develop timing and progress charts,      3.2 PLANNING &                                        as to control failure modes identified through the
     and Control Plan manual. Unless otherwise                      in a format as defined by the procuring Magna                                                                 Process Failure Modes Effects Analysis (PFMEA).
     directed and approved by your procuring Magna                  Division(s) and will maintain and review timelines on       DEFINITION OF 			                                 All related sub-tier documentation shall be
     Division(s), all PPAP submissions shall be as per
     Level 3 requirements, at minimum. As determined
                                                                    a regular basis.                                            REQUIREMENTS                                      available for review, by Magna, upon request.
                                                                                                                                                                                  Special attention shall be given to all Customer
     by Magna’s customer and upon request by Magna,                 The Supplier shall have a documented sourcing                                                                 attach or interface points on the final product and
     Suppliers must additionally meet submission                    process, for all sub-tier Suppliers affecting           As part of their risk analysis, suppliers will work   to critical processes such as heat treating, plating ,
     requirements as per the current version of VDA2.               customer requirements. The sourcing process shall       with the appropriate Magna plant(s) to ensure         coating, soldering, welding and appearance items.
                                                                    include a risk analysis that takes into consideration   definition of key program deliverables, including
     Suppliers shall ensure a multi-disciplinary                    any available past performance data, overall risk       at minimum:
     approach is used throughout the product life                   analysis (commodity, geography, financial stability,
     cycle, and most especially through the design                  technology, supply interruption, manufacturing          • Definition of all customer expectations and
     and development planning process. Suppliers                    capability, etc.) of sub-tier Suppliers. The risk         government or legislative requirements
                                                                                                                                                                                  3.3 PRODUCT DESIGN
     shall conduct all necessary and prescribed
     activities to ensure clarity of all customer and
                                                                    analysis shall also include an evaluation of the
                                                                    sub-tier Supplier’s Quality Management System.
                                                                                                                              (e.g. FMVSS) related to product development             & DEVELOPMENT
                                                                                                                              and approval, as well as serial launch and
     Group-specific expectations as defined within                  Suppliers shall have similar requirements, as             production. Customer requirements 			               Suppliers with design responsibility must receive
     Purchase Orders, Statement of Work etc. This                   defined in this document, in place for all sub-tier       shall include all requirements of the               Magna approval of all product design, test
     includes activities and reporting related to                   Suppliers. Upon request from Magna, Suppliers             applicable Magna plant(s) as well as all final 		   and validation specifications, including CAD
     design, testing, verification and/or validation and            shall provide any relevant information impacting          Customer and compliance expectations and 		         specifications and transfer requirements. Suppliers
     product conformance. Suppliers shall conduct                   upon product compliance or performance,                   requirements.                                       with design responsibility shall ensure all personnel
     and document detailed feasibility reviews to                   including full transparency through the applicable
                                                                                                                                                                                  with design responsibility are competent in all
     ensure all technical, manufacturing, performance,              sub-tier supply chain.
                                                                                                                            • Review of past warranty or field return issues      applicable tools and techniques, as identified by
     specification, certification (homologation) and
                                                                                                                              for any similar product design and/or 		            the supplier. All deviations must be approved by
     timing requirements can be supported. Suppliers                As defined specifically by the Magna group or
                                                                                                                              application. Wherever possible, every 		            Magna, in writing, in advance of implementation.
     shall submit such feasibility reviews to Magna,                Division involved, Suppliers must have the ability to
                                                                                                                              attempt to benchmark competitor products 		         Supplier requests for deviations and engineering
     upon request. In cases where product certification             securely communicate CAD data, as required. The
                                                                                                                              shall be made. The warranty analysis shall 		       approvals shall be documented and controlled
     (homologation) is required, the Supplier is                    Supplier shall have adequate safeguards in place
                                                                                                                              include all sub-tier suppliers, where 			           as per the requirements and documents of the
     responsible for ensuring completion of all                     to prevent any improper use or communication of
                                                                                                                              appropriate.                                        procuring plant(s).
     homologation specifications and requirements.                  this data.

12   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                          13
Suppliers with design responsibility must complete             if necessary. Suppliers are responsible for the        10, or as defined by any unique requirements of      process. Production Validation (PV) samples must
     all appropriate Design Failure Modes Effects                   maintenance of all tooling, testing and inspection     a Magna customer, the risk must be addressed         come from the approved manufacturing process
     Analysis (DFMEA), in compliance with latest AIAG               equipment. Customer owned tooling, gauges              through design action/controls or process            and flow, unless specifically authorized in writing
     standards and have them available for review                   and test fixtures must be identified as prescribed     prevention and detection actions, regardless of      by the procuring Magna Division. Final production
     and Suppliers with design responsibility must                  by the customer, including identification with         the Risk Priority Number (RPN). Suppliers are        approval will require completion of all AIAG/VDA
     receive Magna approval of all product design,                  appropriate asset tags, or similar identification.     expected to have a strong focus on prevention,       prescribed activities including component part
     test and validation specifications, including CAD              Final payment of tooling will be contingent upon       as opposed to detection, and potential failure       dimensions, material certifications (as defined by
     specifications and transfer requirements. Suppliers            verification of proper identification and completion   modes identified through the Advance Quality         procuring Division) and all approved supporting
     with design responsibility shall ensure all personnel          of PPAP as defined by AIAG PPAP or VDA2 Level          Planning process must have appropriate error-        documents, and any additional requirements
     with design responsibility are competent in all                3 requirements. PPAP approval will not be signed       proofing designed into the manufacturing process     that may be defined by your procuring Magna
     applicable tools and techniques, as identified by              off without completion and signing of Magna            to ensure capture and containment of product         Division. Deviations required to be part of a PPAP/
     the Supplier. All deviations must be approved by               approved bailment documentation (including             non-conformances.                                    EMPB submission package, must be approved in
     Magna, in writing, in advance of implementation.               bailment receipts incorporating pictures of tooling,                                                        writing by the procuring Magna Division, prior to
     Supplier requests for deviations and engineering               gauges and test fixtures, and associated tagging       Suppliers must ensure that enough floor space is     PPAP submission. Unless otherwise specified by
     approvals shall be documented and controlled                   or identification) reflecting the rights of Magna      available to support all necessary manufacturing     Magna, all level 3 requirements as detailed in the
     as per the requirements and documents of the                   and its customer in goods, including tooling,          and testing equipment. Once production approval      AIAG PPAP Manual, or as agreed upon per VDA2,
     procuring Division(s).                                         which are placed in supplier’s care and custody.       is received from Magna, any change to the            must be met. If applicable, Suppliers must meet
                                                                    At any time following notification to the supplier,    manufacturing process must be communicated           submission requirements according to VDA2
     Suppliers with design responsibility must complete             Magna reserves the right to complete an on-            to Magna, prior to the change taking place. These    specification agreed upon. Unless otherwise
     all appropriate Design Failure Modes Effects                   site inspection of tooling owned by any Magna          changes must subsequently be approved by             approved in writing, by Magna, production
     Analysis (DFMEA), in compliance with latest AIAG               customer directly, or by Magna Payment terms           Magna prior to implementation.                       approval will be contingent upon successful
     standards and have them available for review and               may differ within various Magna groups, and                                                                 completion of run-at-rate production trials at the
     approval by Magna. The supplier and Magna will                 suppliers need to make certain that they reference     The Supplier will also develop necessary             quoted rates, including low or high threshold
     establish performance approval expectations for                any applicable tooling purchase order(s) for actual    packaging and labeling, as per the latest            rates as defined by Magna, and using the
     each phase including Engineering Validation (EV),              payment schedule.                                      Automotive Industry Action Group (AIAG) or VDA       procuring Division’s process and form. Successful
     Design Validation (DV) and Production Validation                                                                      guidelines, or as defined by Customer or any         run-at-rate must meet statistical capability
     (PV) as defined by the procuring Division(s).                                                                         applicable legal requirements. In the event that     requirements as defined through technical, AIAG/
                                                                                                                           specialty handling or packaging is required, the     VDA standards, or as approved by Magna. For
     Data and results from EV, DV and PV testing shall              3.5 PROCESS DESIGN &                                   appropriate Magna Division will communicate          PPAP of new or modified parts, the Supplier
     be used in the design and construction of test and                                                                    requirements to the Supplier.                        must submit correct and complete Material Data
     inspection equipment that will later control the               		DEVELOPMENT                                                                                               Sheets (MDS) in IMDS. The PPAP Warrant/Initial
     manufacturing process.                                                                                                                                                     Sample Inspection Report must include the
                                                                    As part of the advance planning process,                                                                    version number and the ID number of the MDS
                                                                    Suppliers must design and develop a                    3.6 PRODUCT & PROCESS                                approved by Magna. Failure to comply may result
                                                                    manufacturing process that will meet quoted                                                                 in a delay of PPAP approval and subsequent
                                                                                                                               VALIDATION
     3.4 	 TOOLING, GAUGES &                                       production volumes and all quality requirements                                                             payment of tooling funds. For IMDS assistance,
                                                                    as approved by Magna. The Supplier shall use a                                                              contact the IMDS Helpdesk at imds@magna.com
            TEST FIXTURES                                           multi-disciplinary approach for risk identification    Prior to final production approval, the Supplier     or the contact numbers listed within the IMDS
                                                                    and mitigation in developing and improving             shall validate all control documentation (FMEA,      site at www.mdsystem.com. For assistance with
     Tooling design and build is generally the                      plant, facility and equipment plans. Quality           PCP, and PFD) to ensure the manufacturing            the CAMDS system, contact the corresponding
     responsibility of the supplier, however many                   planning documentation such as Failure Modes           process is properly detailed and all measurement     CAMDS support within the CAMDS site, at www.
     Magna groups have developed detailed Tooling                   Effects Analysis (FMEA), Process Flow Diagram          and control systems are identified and               camds.org. Final approval will be determined
     Standards to ensure suppliers manufacture tools                (PFD) and Process Control Plan (PCP) must be           implemented. The Supplier shall establish            by the procuring Division. Suppliers are also
     that will provide high quality parts throughout the            developed, reviewed and approved by Magna              appropriate production reliability/quality goals     expected to develop and implement detailed
     life of the tooling. These Tooling Standards will              prior to production approval and launch. When          along with disciplined corrective action processes   launch readiness reviews.
     be communicated to you via the procuring plant,                a FMEA has a severity or failure mode of 9 or          to drive improvement through the manufacturing

14   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                     15
All product characteristics, as identified by
     Magna or its OE Customer, affecting design,
                                                                    3.7 FEEDBACK &
                                                                        ASSESSMENT
                                                                                                                           4. OPERATION – CONTROL OF
     manufacture, assembly, fit or function (including
     future/subsequent processing), will be identified
     and communicated by the procuring Magna                        As part of the production part approval process
                                                                                                                               PRODUCTION
     Division. As part of the ultimate product and                  for all new and transfer product, Suppliers shall
     process validation, Suppliers shall be required to             develop an early product launch, or Safe Launch
     establish, validate and maintain short and long                containment plan. The process shall include                                                                    the supplier’s facility and be traceable to the actual
     term capability, as defined by Magna. Customer                 regular reviews of data collected as part of the                                                               identification information and to the appropriate
     designated special characteristics, as identified              containment checks, with appropriate controls                                                                  standard (e.g. NIST). Calibration Services of
     by Magna or its OE Customer, affecting safety or
     compliance with regulations, must be validated
                                                                    and corrective action implemented to address
                                                                    all instances of non-conformance. Containment
                                                                                                                           4.1 CONTROL OF FIXTURES                                 equipment must meet the requirements of the
                                                                                                                                                                                   latest released edition of ISO and/or IATF 16949
     to have acceptable short and long term capability              plans, results and corrective action must be               & TEST EQUIPMENT                                    standards.
     and must be controlled through acceptable                      approved by Magna and available for review upon
     statistical process control methods. As determined             request.                                               MONITORING                                              INSPECTION, MEASURING, AND TEST
     by Magna’s OE Customer(s) and as directed by                                                                                                                                  EQUIPMENT RECORDS
     your procuring Division, all FMEA items with a                 Early product containment must remain in place         The Supplier must have a documented system in
     severity score of 8, or higher, must be controlled             until the production process is validated to be        place to control, calibrate, and maintain the proper    Records must include any revision information,
     through appropriate error/mistake proofing.                    stable and approval is obtained from Magna.            function and an accepted level of repeatability and     traceable to the part revision level. External/
                                                                    Unless otherwise specifically directed by your         reproducibility of all inspection fixtures, measuring   commercial/independent laboratory facilities
     As dictated by IATF 16949 Customer Specific                    procuring Division, your early product containment     / testing instruments and equipment. All customer-      used for inspection, test or calibration services
     Requirements, and unless otherwise directed by                 plan must remain in effect for the first 2000 parts,   owned fixtures and test/inspection equipment            by the supplier shall have a defined laboratory
     Magna, Suppliers must complete annual revalidation             or for the first 90 days of production (whichever is   must be clearly identified in the manner prescribed     scope that includes the capability to perform the
     to the technical specifications and submission level           more stringent).                                       by Magna or by Magna’s customer.                        required inspection, test or calibration and must
     as determined by their procuring Division(s).                                                                                                                                 have evidence that the laboratory is acceptable to
                                                                    Suppliers shall not proceed with shipments of          UPDATING INSTRUCTIONS                                   Magna or must be accredited to ISO/IEC 17025
     In the absence of specific direction from Magna,               production material without full PPAP approval,                                                                or national equivalent, by an accreditation
     Suppliers must complete an annual revalidation                 unless an approved waiver, deviation or interim        Operating instructions must be readily available        body of the ILAC MRA (International Laboratory
     and submit the ISIR/PSW to the procuring Magna                 approval has been granted in writing by Magna.         at every inspection station with a standard,            Accreditation Forum Mutual Recognition
     Division. Any reduction in validation requirements             Suppliers can only ship the volume of parts, or        describing the proper methodology for use in            Arrangement).
     must support applicable OEM requirements and                   for the duration of time specified by the interim      inspection. These instructions must include a
     can only be at the direction of Magna.                         approval.                                              reference to the standard, and revision level, and      MEASUREMENT SYSTEM ANALYSIS
                                                                                                                           be approved by appropriate personnel. Whenever
     Reference samples must be provided at no                                                                              there is any change to the inspection procedure         Gage and fixture Measurement System
     cost, for any product requiring surface finish or                                                                     that affects the use of the standard, or when any       Analysis (MSA) must be performed as detailed
     appearance requirements. These samples shall                                                                          identification information is revised, the operating    in the latest released edition of the AIAG
     be taken from a production run made under serial                                                                      instructions must be updated to reflect the current     Measurement System Analysis Manual, and
     production conditions. Suppliers shall provide the                                                                    status.                                                 must meet the standards of the procuring Magna
     number of samples required by Magna and all                                                                                                                                   Division(s).
     samples must be regarded as controlled samples,                                                                       VALIDATION
     along with approval signatures and expiry dates,                                                                                                                              RECORD RETENTION
     if applicable. Samples will represent the minimal                                                                     All measurement and test equipment must be
     acceptance standards.                                                                                                 calibrated annually, at a minimum, or at such           Suppliers are expected to maintain applicable
                                                                                                                           greater frequency as established by the Supplier’s      retention periods as specified in IATF 16949 latest
                                                                                                                           Measurement Systems Analysis (MSA) process.             edition standard, unless subject to longer retention
                                                                                                                           The calibration record/certificate must be on file at   periods in compliance with all applicable legal,

16   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                           17
governmental or Customer specific requirements,                obsolete material or material certification or other      • Division sort of Supplier product at the Magna       production, at a maximum. In the event of certain
     pursuant to requirements communicated in writing               failure modes. Nonconformance notices will also             facility, until certified stock arrives              commodity-based material, methods such as
     by the procuring Magna Division(s). Records must               be issued for materials/logistics noncompliance           • Production line shutdown                             “dye lots” or steel coils will be acceptable. For
     be stored in a location and/or environment that                issues, such as over or under shipments, missed           • Finished product sort and/or scrap of material       approval of a traceability method exceeding 8
     protects against inadvertent destruction.                      shipments, late deliveries, packaging issues and or       • Any material transfer of nonconforming supplier      hours, or one shift of production, the Division’s
                                                                    required documentation (e.g. ASN) noncompliance             product                                              quality group must be contacted. The Supplier must
                                                                    issues. The nonconformance process is typically           • Quality Department time for problem 		               ensure implementation and management of an
                                                                    managed through the following procedure:                    investigation                                        effective FIFO method of stock rotation in both the
     4.2 MONITORING OF                                                                                                        • Testing if required                                  production and shipping process. The FIFO date
                                                                    • Supplier will be notified of the concern, through       • Any sort/rework charges incurred by Magna, 		        used in determining stock rotation, must be the
         PRODUCT & PROCESS                                              the QPF system. All relevant containment 		             either directly or via 3rd Party sort/rework         manufacturing date of the material affected.
                                                                        actions must be initiated immediately and             • Related transportation expenses
     Manufacturing process control must include                         remain in place until corrective action has 		        • Any costs incurred by Magna for disruption of        Failure to comply with traceability requirements may
     a continuous monitoring of product/process                         been reviewed and approved by Magna. 		                 our customers, including costs associated with       lead to rejection of material and issuance of non-
     characteristics and of all key parameters                          Unless otherwise specified, initial response to         sorting, rework, yard holds and applicable field     conforming material reports. Traceability Records
     influencing the manufacturing process. Appropriate                 the nonconformance must be completed 		                 actions                                              shall be maintained and accessible for the life of the
     statistical process control methods, or error-                     within 24 hours of notification.                      • Costs associated with the disposition/return of      product, including Service, plus one year.
     proofing, must be applied on all characteristics               • Upon notification, the Supplier shall initiate 		         unapproved or unauthorized material sent by
     identified through the APQP process and as                         the Corrective Action Report (CAR) and any 		           the Supplier                                         Traceability record retention deviations are only
     directed by your procuring Magna Division(s).                      other supporting documentation as directed 		         • Costs related to unauthorized deviations             permitted if approved in advance in writing from
     Process parameters and product characteristics                     by the procuring Division(s). The initial CAR, 		     • Costs incurred by Magna associated with 		           your procuring Division(s).
     subject to legislative safety, environmental and/                  detailing root cause and corrective action must         customer recalls or product failures, caused by
     or emissions regulations must be documented in                     be submitted to the Magna procuring Division            Supplier non-conformance                             CONTROLLED SHIPPING
     control plans in compliance with Magna specific                    within 5 days, unless otherwise specified by
     requirements and IATF 16949 requirements.                          Magna. Validation and closure will be 		              These costs are charged to Suppliers specifically      When directed by Magna, Suppliers may need to
                                                                        determined by the procuring division                  to offset costs incurred by Magna and will vary        certify product after a lot rejection has occurred.
     Suppliers must validate compliance to product and              • Suppliers shall assess the risk of any reported         according to the Division and specific issue           Two types of controlled shipping actions are usually
     process requirements on a regular basis. This can                  non-conformance for potential impact at any           involved.                                              employed when this situation occurs:
     be accomplished through layered process audits                     other Magna location, globally, that they ship                                                               • Supplier conducted sort and certification of
     (Ref. CQI-8 LPA Guidelines), systems self-audits                   to. If such risk exists, they will immediately 		     TRACEABILITY                                              subsequent part shipments, and
     or similar methods of verification. Records of such                contact all affected Magna locations                                                                         • Third party sorting and certification
     audits shall be immediately available for review               • Quality and delivery non-conformance will be            The Supplier shall follow the traceability method
     when requested by Magna.                                           reflected in monthly supplier scorecards              as determined by the procuring Magna Division          All controlled shipping actions are the responsibility
                                                                    • Suppliers are responsible to review their 		            (e.g. date and shift of manufacture along with         of the Supplier to coordinate and manage. Any
                                                                        monthly scorecards, on-line, in ERFX                  sequential processing number). In some cases,          third-party sorting, re-work, inspection and
                                                                    		                                                        the component may be critical enough so as to          containment activity must be conducted by a
     4.3 NON-CONFORMANCE                                            Under-performing Suppliers may be escalated to            warrant part identification; these instances will be   Supplier that is designated or approved by Magna.
                                                                    the Magna Top Focus Supplier process. Suppliers           communicated through the appropriate quality           Any third-party arrangements, not specifically
         & CORRECTIVE ACTION                                        will be expected to support any development               and engineering groups unless superseded by the        directed by Magna, must be reviewed and approved
                                                                    activity that is part of this process. Costs related to   procuring Division(s).                                 by the procuring Magna Division(s). Continued part
     Nonconformance notices will be issued upon                     the Top Focus process may be the responsibility of        Traceability requirements on prototype production      supply to Magna must meet released quantities and
     discovery of defective product identified as a                 the Supplier, as appropriate.                             parts may be defined by Magna and must be              without supply interruption.
     result of, but not limited to line rejections, mis-                                                                      supported by the Supplier.
     labelling, incorrect packaging, testing failures,              Suppliers will be responsible for all validated costs                                                            The Supplier and the Magna Division will agree
     failed inspection results, customer concerns,                  for non-conformance issues, based on (but not             A lot should contain a specific quantity of parts      on the method to be used to identify all certified
     warranty and/or customer returns, receipt of                   limited to) the following criteria:                       and should not exceed eight hours or one day of        material.

18   Magna Global Supply Chain Requirements – Revision 01-01-2021                                                                                                                                                                             19
SUPPLIER TOP FOCUS AND ESCALATION                                                                                                                                                                        • Performance Monitoring                               of parts or duration of shipment. Requests must
     PROCESS                                                                                                                                                                                                  • Development activity with under-performing 		        be made in advance and with ample time for
                                                                                                                                                                                                                Suppliers                                            implementation, if approved. Suppliers will be
                                                                                                                                                                                                                                                                     required to build and maintain sufficient inventories
                                                                                                                                                                                                              Escalation E-1 includes escalation to the Group/       of parts, as determined by Magna, to support any
                                                                                                                                                                                                              Business Unit level and includes:                      changes and required approvals.
                                                                                ROLES
                                                                                (R)   Responsible
                                                                                (S)   Support                                                                                                                 • Magna Top Focus Process
                                                                                (I)   Inform
                                                                                                                     - Plant Quality/Materials (R)            - Monthly Risk Mgmt Report                      • Performance review & risk assessment across          Suppliers are expected to effectively manage
       Magna Supply Chain Management Process
                                               Top Focus/Escalation Process

                                                                                                                     - Group SQA/D Leads (S)
                                                                                                                     - Regional SQA/D Leads (S)
                                                                                                                                                              - Top Focus Process
                                                                                                                                                              - New Business Hold                   E-2         all Magna Groups                                     deviation expiry dates and must apply for any
                                                                              - 6 Month rating remains
OEM Customers have stipulated that warranty
     costs will be shared with their supply base. As                5.	OPERATION – CONTROL OF
     such, Suppliers will be expected to participate in
     warranty activities including:
     • Warranty returns reviews/analysis
                                                                        MATERIALS & LOGISTICS
     • Improvement actions
     • Warranty cost responsibility
                                                                    In support of lean and efficient business              3. Other (As directed by Magna)
     When a Supplier’s component is implicated in a                 processes, Suppliers must be able to support              Based on the information provided, Magna will
     warranty, campaign or recall issue, with financial             electronic data interchange via Standard or Web           determine the Incoterms that will be used.
     consequences to Magna based on Magna’s                         EDI. Acceptable message standards include VDA,
     Customers’ warranty or recall policies, the Supplier           ANSI and EDIFACT.                                      Brokerage fees on all imported products are
     must be prepared to accept these costs. The costs                                                                     typically the responsibility of Magna, unless
     for which a Supplier shall be responsible shall be                                                                    otherwise indicated, by the procuring Division.
     determined in accordance with Magna Purchase
     Order Terms & Conditions, and as defined by                    5.1 GENERAL
     any Division specific Statement of Work (SOW)
                                                                        REQUIREMENTS
                                                                        REGARDING LOGISTICS 5.2 PACKAGING
     or Statement of Requirements (SOR) or warranty
     agreement.
                                                                        PROCESSES           Suppliers are required to adhere to Packaging
                                                                                                                           Guidelines as defined by the Magna Global
                                                                    Suppliers shall design and manage their logistics      Packaging and Shipping Manual, as well as all
                                                                    processes to ensure quality and on time delivery of    necessary AIAG/VDA Standards and Global
                                                                    directed quantities to the location and at the times   REACH requirements. The Magna guidelines can
                                                                    specified by Magna.                                    be accessed via the Magna website (www.magna.
                                                                                                                           com), ERFX Portal (https://ERFX.magna.com), QPF
                                                                    In partnership with our Suppliers, Magna will work     Portal (https://qpf.magna.com/) or from the Magna
                                                                    to develop logistics planning that ensures:            packaging representative. Special packaging
                                                                                                                           and labeling requirements, in support of specific
                                                                    • Minimal complexity in logistics business 		          Product Launch activity, may be requested by a
                                                                      processes                                            Magna facility. In the event that special packaging
                                                                    • Maximum flexibility to support response to late      is required, design and approval will be managed
                                                                      changes in volume or timing of deliveries            as part of our overall APQP Program Delivery
                                                                    • Minimal inventories in the supply chain              Process.
                                                                    • Packaging designs support all handling and
                                                                      loading requirements                                 In preparation for product launch, production
                                                                    • Just in time delivery that complies with 		          packaging approval, as well as back up packaging
                                                                      established delivery times                           approval must be obtained from the Magna
                                                                    • Focus on continuous improvement                      procuring Division(s) prior to a line Run @ Rate.
                                                                    • Timely communication of all potential supply
                                                                      interruptions                                        In order to ensure planned packaging optimizes
                                                                                                                           the cube utilization of the transport vehicle, the
                                                                    Suppliers must be prepared to provide delivery         Division assembly practices and lean operations,
                                                                    costs based on:                                        Suppliers are responsible to validate packaging
                                                                    1. FCA (Free Carrier)                                  design to these requirements if not directed
                                                                    2. DDP (Delivered Duty Paid)                           differently by Magna. Approval must be submitted