London Underground and the PPP - The first year 2003/04 - Transport for London

Page created by Erica Rivera
 
CONTINUE READING
Transport for London

                       London Underground
                       and the PPP
                       The first year
                       2003/04

                       As at financial year end 2003/04
                       Issue date: June 2004

MAYOR OF LONDON
London Underground and the PPP
The first year
2003/04
Contents
1.   Foreword                         2

2.   Background and overview           8

3.   PPP contractual performance       9

4.   PPP financial performance        20

5.   Asset performance                22

6.   Asset management                 37

7.   Safety performance               39

8.   Relations with the PPP Arbiter   42

9.   Underground operations           43

10. Conclusion                        54
2   Transport
     Transportfor
               forLondon
                   London

     1. Foreword
     In April 2003, London Underground             Infracos based upon actual system
     completed the transfer of the                 performance, and the efficacy of this
     responsibility for the care, maintenance      quite experimental system is unproven
     and renewal of its assets - its rolling       in the world of urban rail transport.
     stock, stations, track and signals - to the   Second, many of the promised
     private sector through a Public Private       improvements of PPP - including the line
     Partnership. This past financial year,        upgrades intended to increase capacity -
     concluding on March 31, 2004, marks           are not intended to be delivered until
     the first full year of London                 after the end of the first 7.5 years of the
     Underground and Infraco performance           contract, and PPP scope, pricing and
     under this ‘PPP’. This report is a review     funding could all be subject to significant
     of that performance.                          renegotiation at that point. Finally, the
                                                   Government imposed significant
     The one observation with which                affordability constraints when previous
     everyone would agree is that London           management negotiated the details of
     Underground suffers from a range of           the PPP, with the result that the bidders
     deep-seated problems resulting from           pushed out promised improvements
     decades of under-investment. This             from the first 7.5 year period to the
     under-investment produced persistent          second and from the second to the
     asset failures that, in turn, led to an       third. There is no committed funding for
     acceptance of inadequate performance.         the periods beyond the first 7.5 years.
     Management grew to accept doing more          Even if the PPP is fully implemented as
     with less while perfecting the art of         intended, existing assets will not be fully
     apology and passengers’ expectations          restored to a state of good repair until
     were driven down.                             the year 2025.

     PPP. After much debate and dispute, the       For current users of the Tube that is an
     Government adopted the PPP as its             unacceptable eternity. And for future
     antidote to this spiral of inadequate         passengers, the capacity increase
     investment. Over the first 7.5 years of       promised by the PPP must be
     this 30-year arrangement, billions of         substantially accelerated if the London
     pounds will be paid to three private          Plan forecasts of 800,000 more
     sector companies, Tube Lines Ltd.,            Londoners and 630,000 additional jobs
     Metronet BCV Ltd. and Metronet SSL            by 2016 are to be realised.
     Ltd. (the ‘Infracos’). This investment was
     intended to be in exchange for the            Current management of London
     restoration and upgrade of the                Underground took charge in July 2003
     Underground’s assets.                         when control of the Underground
                                                   transferred to the Mayor of London and
     It remains to be seen whether the scope       became part of Transport for London.
     of improvements promised by the PPP           We have had less than a year to observe
     will prove real or ephemeral. This is a       the performance of the Infracos under
     function of several interrelated factors.     private ownership and their relationship
                                                   to the operations of the remaining
     First, the scope of work of the PPP is        publicly-controlled portions of the
     primarily driven by financial incentives      system.
     intended to reward or penalise the
London Underground 2003/04       3

Over the past year, £1.1 billion was paid      Future reports will benefit from our joint
to these companies. During that same           efforts with Tube Lines and Metronet to
year, the Underground’s assets                 establish an asset register and a capital
continued to provide dramatic                  programme reporting system. These new
demonstrations of their inadequacy:            data systems will measure the
● Central Line fleet withdrawn for 8           effectiveness of maintenance regimes
   weeks following the 25 January 2003         and the performance against schedule
   Chancery Lane derailment with               and budget of planned capital
   continuing effects on services              programmes. Improved information will
● Inability to cope with excessive heat        provide a common understanding of
   in August exacerbated discomfort of         performance and will assist the parties
   passengers                                  to the PPP in focussing on and tackling
● Power outage on August 28 revealed
                                               problems.
   shortcomings of communications
   network and signalling and control          Improved maintenance practices and
                                               resulting reliability improvements should
   systems
                                               be observable in the short term. Tube
● Hammersmith and Camden Town
                                               Lines and Metronet have predicted
   derailments
                                               reductions in failures within different
● Continuing track, signalling and rolling
                                               asset categories of between 15 and 49
   stock failures at a rate not                per cent over the first 7.5 years. We
   demonstrably different from pre-PPP         intend to do everything in our power to
   performance years.                          hold them to these predictions. Under
                                               the renewals programme, the PPP must
It is clear that the failure of historically
                                               deliver major asset upgrades in the form
neglected, long-lived assets is
                                               of new trains, signalling systems and
continuing. It is impossible to determine
                                               rebuilt track structure, which will permit
at this early point, however, in what way
                                               a step change in performance. Many of
this continuing failure may be tied to the
                                               these major upgrades are years away, but
structure of the PPP. One cannot as yet
                                               their delivery – as well as the overall
clearly distinguish between the
                                               success of the PPP – is dependent on
performance lag in programmes that are
                                               the Infracos’ proper execution of current
just being implemented, teething
                                               design and planning activities. These too
problems, structural problems and
                                               will be monitored vigorously.
genuine performance issues. We have
attempted, therefore, to ground this
                                               In some respects, the parties to the PPP
report on a presentation of data that will
                                               contract are working co-operatively and
form a baseline to judge future
                                               are demonstrating a willingness to
performance. We set forth performance
                                               consider joint solutions to management
under the contractual and financial
                                               problems. Certain joint initiatives have
measures, as well as Infraco
                                               shown early promise, such as the anti-
performance with regard to planning,
                                               graffiti programme. The Underground
reporting and asset failures for the key
                                               agreed with the Infracos to attack the
asset classes. We have added
                                               paint on trains as a symbolic first step in
commentary within each asset class to
                                               demonstrating a greater concern for the
provide a context for the data.
                                               Underground’s assets and the travelling
                                               environment for passengers. All fleets
4   Transport for London

     on the Underground are now being             reduced the scope of the work
     cleaned and new graffiti is removed          performed. Many track renewal projects
     within 24 hours. Metronet particularly       done so far have achieved 50-60% of
     has demonstrated effective management        what should have been delivered.
     in cleaning the fleet most defaced by        Because of the modest amount of
     graffiti, the sub-surface fleet. Metronet    renewal work that was scheduled over
     has also introduced new management           this first year, this shortfall can be
     teams to improve the performance of          recovered, but this early pattern cannot
     rolling stock, demonstrating early           be allowed to continue: the Infracos
     success on the Central and Circle Lines.     must undertake the promised work,
     Tube Lines successfully brought forward      while protecting service.
     the opening of the eastern end of Canary
     Wharf station.                               The effectiveness of maintenance
                                                  programmes will be revealed over time,
     However, the first year also gives           however the past year has left much to
     significant cause for concern. The area of   be desired. Again, proper planning is
     greatest concern is in planning and          critical. Smart planning, efficient delivery
     programme/project management, which          and professional supervision in the field
     drives the effectiveness of the              are attributes in short supply across the
     maintenance programmes as well as            Infracos. Addressing these weaknesses
     major capital programmes. High-level         will require a greater addition of outside
     asset management strategies have been        talent from Infraco shareholders or
     haltingly produced and suffer from           extensive training and recruitment
     inadequate engineering input, while          programmes.
     detailed work plans have sometimes
     been either non-existent, incomplete or      Over the coming year, the first major
     inconsistent rather than competent and       station rebuilds will be underway with
     professional. The planning capability        work on 19 stations and more track
     demonstrated this past year will not be      renewal work will be undertaken. The
     adequate to manage the volume of work        rebuilding of the District Line between
     once the renewals programme                  Earl’s Court and Whitechapel should
     accelerates.                                 reduce asset failures and produce a
                                                  smoother ride, but at the cost of loss of
     A very troublesome example of                that service over numerous weekends.
     inadequate planning is the damaging          Planning for the first major line upgrades,
     engineering overruns that frequently         the Jubilee, Victoria and Northern line
     interrupted peak service in the last         programmes, must develop to the point
     months of the year under review.             of accurately developing schedules and
     Metronet and Tube Lines priced their         accountabilities.
     bids for work under the PPP based upon
     plans to perform heavy maintenance at        Good management can overcome some
     night and on weekends. This is an            of the shortcomings we have observed
     inefficient and expensive way of doing       in Infraco planning activities, but all the
     the work, but was designed to protect        parties to the PPP remain captive to the
     weekday service. Infraco overruns            limitations of the PPP contracts
     occurred from weekends and nights into       themselves. It is likely that there will
     service hours because of poor planning.      need to be changes to the PPP contracts
     In response, the Infracos have often         reflecting actual experience during the
London Underground 2003/04        5

first year or two of their execution. We      together to London Underground’s
will also be evaluating whether the           advantage, with the consequence that
financial incentives engrained in the         the public sector is exposed to
contracts in fact motivate appropriate        significant cost risk.
behaviour and outcomes, and whether
the work the Infracos elect to perform is     Prestige is the ticketing PFI that now
the highest priority work in light of the     supplies ticketing systems for TfL
condition of Underground assets and the       generally, including the new smart card
needs of Underground customers.               technology. In the past year, the Oyster
                                              card has been introduced and the
I was not a party to the process that led     underlying technology has performed
to PPP. I came to London to restore the       remarkably well. The card’s full
Underground’s lost reputation as the          functionality has not yet been
world’s premier rapid transit network. In     introduced however, and the coming year
this brief time, I have been struck by the    should see the delivery of further smart
opportunity presented by the new              card applications.
investment and the dedication of many
of the people who work on the                 The Power PFI contract with Seeboard
Underground. But I have also been             Powerlink was entered into in
disappointed by the overly convoluted         connection with the decommissioning of
processes that the contracts require, the     the Underground’s Lots Road power
limitations on London Underground’s           plant. The Power PFI’s resilience was
rights and the inadequacies of real world     called into question during last year’s
technical planning and analysis that went     power outage. We have worked with
into the PPP. These conditions need to        Seeboard Powerlink to strengthen
be changed.                                   management and communications with
                                              the Underground, EdF and the National
PFI. Metronet and Tube Lines essentially      Grid to remedy shortcomings. An
control the performance of the                additional concern, however, is the need
Underground’s assets, which is the            to provide power to support line and
major determinant of service quality.         rolling stock upgrades under the PPP.
Nonetheless, they are not the whole           Over the past year, we have put together
story. Prior to the PPP, London               the planning apparatus to bring forward
Underground entered into a series of          any such power upgrade, and we have
Private Finance Initiatives for delivery of   co-located teams with Seeboard
discrete systems. Tube Lines has              Powerlink and the Infracos to define the
inherited one, the Alstom provision of        future power requirements in an attempt
Northern Line trains. Another, stations       to ensure that we do not contract for
for the British Transport Police, has been    (and hence incur unnecessary costs for)
largely delivered. Three others, Prestige     more power than is required. This work
(ticketing), Connect (communications)         is on the critical path for PPP upgrades
and Power, present enormous challenges        and will require substantial infrastructure
in themselves and in combination with         improvements by the end of the decade.
the PPP. These PFIs and the PPP were
not planned or designed to work
6   Transport for London

     Connect is the PFI under which the            Following the discussion of PPP
     Underground’s current radio system is         performance, this report summarises
     maintained and its new radio system is        and reviews London Underground’s
     to be delivered. The delivery of the new      operating performance for those aspects
     radio system is already two years late        of the system that remain under its
     and over budget. In the Connect PFI, we       control.
     have inherited a poorly managed
     contractual arrangement that has so far       We face many of the same challenges as
     failed to deliver the system that is          the Infracos. We must upgrade our
     critical to our efforts to improve            project management practices if we are
     operations, safety and information. The       to effectively integrate the number of
     system is now scheduled for delivery in       competing capital schemes that are
     2006. That deadline will be met and           before us. We must complete the
     substantial cost overruns avoided only if     development of systems that will permit
     the Connect team, working in co-              effective coordination of all renewal
     ordination with the Infracos, completes       work, including non-PPP investments.
     the basic engineering and construction
     work over the next 18 months. In order        The PPP scope calls for the renewal of
     for this to happen, Connect must share        existing stations but does not deliver
     limited engineering hours and draw on         major necessary changes that will relieve
     the Infracos’ engineering trains,             congestion. For example, Victoria Station
     protection personnel and other assets,        must be expanded or it will limit the
     creating an enormous co-ordination            exploitation of the new trains and signals
     challenge, rife with potential conflict and   on the Victoria Line. Moreover, the
     resulting delays.                             Underground is an inhospitable
                                                   environment for many Londoners. The
     Underground Operations. Following the         PPP provides some relief for users with
     adoption of the PPP, Transport for            special needs, particularly those with
     London assumed control of London              hearing or sight limitations. But the PPP
     Underground on July 15, 2003.                 provides very little in the way of
     In assuming control, we have articulated      improved step-free access to the
     three immediate challenges:                   Underground. There currently are 40
     ● Management of the PPP and PFI               step-free stations and the PPP station
        relationships and responsibilities         programme will make 16 more stations
     ● Improved operations                         step-free. The Mayor and Commissioner
     ● Investment in stations to expand            of Transport wish to make at least half
        access, building on the PPP                the network step-free within 15 years.
        investment programme where                 That imperative and the need for
        possible.                                  congestion relief come together to
                                                   define additional investment, as yet
     Over the past year, we have defined           unfunded, that must be undertaken
     improved operations as the delivery of a      coincident with the PPP stations
     safer, cleaner and more reliable service.     programme.
     In the face of the extreme conditions
     faced over the past months, substantial       In the end, the PPP contracts were a
     progress has already been made.               product of substantial compromise,
London Underground 2003/04    7

trading time and scope for reduced           The complexity of turning the
investment. Projects were removed from       Underground around within the context
the programme or moved far into an           of these novel contractual and
unfunded future to reduce the cost of        management structures makes for an
the PPP. This compromise creates grave       endless list of performance metrics and
potential risk because the sizeable          commentary. At the end of the day,
investment in the early years does not       however, the system’s performance as
produce the kinds of visible outcomes        experienced by passengers will provide
that would inspire confidence in the         the only judgement that counts.
project and rally financial commitment
going forward. Billions of pounds will be
spent, but little change will be apparent,
save possibly the effects of improved
maintenance – but even this is uncertain,
given the continuing degradation of the
assets. Therefore, support for the long-     Tim O’Toole
term programme of renewal is at risk of      Managing Director
short memories and demagoguery.              London Underground Limited
Government must follow through on its        June 2004
commitment to 30 years of investment,
and the parties to the PPP will have to
look for ways to accelerate visible
improvements.
8   Transport for London

     2. Background and overview1
     On 31 December 2002, Tube Lines, the          approach was not deemed adequate; for
     private consortium comprising Bechtel,        these areas, the scope of work is more
     Jarvis and Amey, assumed the                  precisely defined. Infracos are then paid
     responsibility for the maintenance and        a fee every four weeks that is adjusted
     renewal of the assets of the Jubilee,         upwards or downwards on the basis of
     Northern and Piccadilly lines. On 4 April     actual performance.
     2003, Metronet, the private consortium
     comprising Balfour Beatty, W. S. Atkins,      In assessing first-year performance, this
     Thames Water, Bombardier                      report reviews:
     Transportation and Seeboard assumed           ● PPP contractual performance: How
     responsibility for two entities: Metronet        the Infracos are performing against
     Rail BCV, which has responsibility for           the performance output benchmarks
     maintenance and renewal of the assets            and with respect to progress on the
     of the Bakerloo, Central, Victoria and           major projects required in the
     Waterloo & City lines, and Metronet Rail         contract, such as line upgrades and
     SSL (Sub-Surface Lines), which has               station improvements.
     responsibility for maintenance and            ● PPP financial performance: How
     renewal of the assets of the District,           contractual performance is reflected
     Circle, Metropolitan, Hammersmith &              in the payments. We also look at the
     City and East London lines.
                                                      extent to which the increased
                                                      resources anticipated by the PPP have
     The idea underlying the PPP was that
                                                      materialised so far.
     private sector companies were better
                                                   ● Asset performance: How the assets
     positioned than the public sector to
     deliver improved performance for                 have performed since transfer.
                                                   ● Asset management: Infracos’ plans
     London Underground through access to
     specialist technical resources, greater          for whole-life asset management.
                                                   ● Safety performance: How the PPP
     financial certainty and more efficient use
     of financial resources, project                  has performed in delivering the
     management skills, and knowledge of              requirement of ‘no degradation in
     good industry practice (particularly in the      safety.’
     area of whole-life asset stewardship).        ● Relations with the PPP Arbiter. How

                                                      London Underground has worked
     The Infracos are expected to optimise            with the PPP Arbiter.
     cost and performance by looking at the        ● Underground operations. How
     whole asset life-cycle. The PPP contract         London Underground’s operations
     is based significantly on output-based           have performed over the last year and
     performance specification, with the              plans for the future.
     expectation that Infracos decide what
     maintenance to do and which                      All measures are as of 31 March 2004,
     investment projects to carry out to              the financial year-end for 2003/04,
     deliver the required performance. In             unless otherwise indicated. This
     some areas, such as station                      represents the one-year anniversary of
     improvements, an output-based                    the Metronet contracts and 15 months
                                                      of the Tube Lines contract.
     1. Nothing in the report shall create any legal relations between London Underground and
     any other party nor shall it be deemed to interpret, amend, waive or otherwise affect any
     provision of any contract or agreement identified herein. The report is issued without
     prejudice to the exercise by Transport for London or London Underground of their rights
     under any contract or agreement identified herein.
London Underground 2003/04      9

3. PPP contractual performance
The PPP contracts define three primary        surrogate for quantifying the total
output performance measures:                  amount of delay caused by that incident
● availability, a measure of day-to-day       to customers across the network.
  service reliability;
● capability, a measure of the potential      Infraco LCH performance is measured
  capacity of the assets ultimately to        against a benchmark set at 105% of
  reduce journey time;                        London Underground’s historic level of
● ambience, a measure of the quality of
                                              lost customer hours, with performance
  the travelling environment.                 worse than benchmark incurring
                                              abatements. Performance worse than a
In addition, the contracts measure            further ‘unacceptable’ level incurs
performance according to a regime of          additional abatements.
service points, which are allocated for
facilities faults and faults that are not     Performance
rectified within a set time.                  BCV
                                              Performance against the availability
Each of the first three measures              benchmark has been mixed over the
compare Infraco performance to a              year. In the last quarter of the year
benchmark based on previous London            performance on all BCV lines was better
Underground performance. Performance          than benchmark, although a slight
better than benchmark receives a              deteriorating trend could be observed
financial bonus,2 while performance           over the quarter.
worse than benchmark receives a
financial abatement.                          Central line performance was worse than
                                              benchmark for the majority of the year,
In addition, the Infracos are required to     which was consistent with performance
deliver a series of defined major projects    immediately preceding transfer. Apart
such as line upgrades and station             from an escalator problem at Bond
modernisations. Performance on major          Street in period 4, the most significant
projects is measured by progress against      cause has been ongoing problems with
contractual milestones for a defined          the line’s rolling stock. The Chancery
scope of work.                                Lane incident (which occurred before
                                              transfer) also caused an increase in both
3.1 Availability                              staff and customer sensitivity to unusual
                                              train noise, which led to an increase in
Definition and measurement                    reporting of unusual noise and therefore
Availability takes into account each          an increase in trains withdrawn from
disruption to the service that lasts two      service in response to these reports. The
minutes or more. The actual length of         step change improvement in
each incident is then multiplied by a set     performance towards the end of the year
factors (which varies by the location and     shows the positive effect of the
time of day of the incident) to determine     Metronet remedial programme.
the impact on customers. This produces
Lost Customer Hours (LCH), which are a

2. Except for service points, where only abatements are applied for failure to meet
threshold.
10 Transport for London

                             Bakerloo line - Lost Customer Hours
                   120
                                                                                                                              Abeyance
                   100

                   80
                                                                                                                              Agreed
                   60
                                                                                                                              Unacceptable
     LCH (000's)

                   40

                   20
                                                                                                                              Benchmark
                    0
                              1       2       3       4       5       6       7       8       9       10 11        12    13
                             Period

                              Central line - Lost Customer Hours
                   1000
                    900                                                                                                        Abeyance
                    800
                    700
                    600                                                                                                        Agreed
                    500
                    400
                                                                                                                               Unacceptable
     LCH (000's)

                    300
                    200
                    100                                                                                                        Benchmark
                      0
                                  1       2       3       4       5       6       7       8       9        10 11    12 13
                              Period

                              Victoria line - Lost Customer Hours
                    250

                    200                                                                                                        Abeyance

                    150
                                                                                                                                Agreed
                    100
     LCH (000's)

                                                                                                                               Unacceptable
                     50

                         0                                                                                                     Benchmark
                               1       2      3       4       5       6       7       8       9       10    11 12       13

                              Period
London Underground 2003/04       11

                   Waterloo & City line - Lost Customer Hours
              25
                                                                                     Abeyance
              20

              15                                                                     Agreed

              10
                                                                                     Unacceptable
LCH (000's)

              5
                                                                                     Benchmark
              0
                    1   2    3   4   5    6   7    8   9   10 11 12       13

                   Period

Poor performance on the Victoria line                  On the Bakerloo line, average
(with results worse than benchmark in                  performance has improved since
half the year’s periods) resulted                      transfer; performance has been better
principally from a combination of signal               than benchmark for most of the year.
failures and train failures. BCV’s interim
programme of improvements to the                       SSL
signalling assets have led to improved                 Metronet SSL is performing better than
performance in recent periods and                      benchmark on all lines as at year-end. To
should deliver further performance                     address the reliability of the Circle line,
improvements. Ultimately, the Victoria                 which has always been weak, Metronet
line upgrade due in 2013 will provide a                have put more technicians in place over
completely new signalling system.                      the last year; this appears to be
                                                       improving response time to incidents
Poor performance in the first half of the              and thereby improving contractual
year on the Waterloo & City line was                   performance.
primarily due to ongoing rolling stock
and track defects. It uses the same                    Scores for the East London line were
rolling stock as the Central line and                  worse than benchmark due to problems
therefore has suffered from similar                    associated with the installation of a new
problems. However, as with the Central                 computerised signalling control system
line, performance has been improving,                  midway through the year. These
with the most recent quarter’s                         problems have now been substantially
performance better than benchmark.                     resolved, as measured by a return to a
                                                       normal fault rate.3

3. Due to the limited size of the East London line, a single defect has a disproportionate
effect (just as on the Waterloo and City). This means performance for these lines will
tend to be more volatile than other lines.
12 Transport for London

                            Metropolitan, Circle and Hammersmith & City lines - Lost
                            Customer Hours
                   600

                   500
                                                                                              Abeyance
                   400

                   300                                                                        Agreed
     LCH (000's)

                   200                                                                        Unacceptable
                   100                                                                        (494K LCH)
                                                                                              Benchmark
                       0
                                1       2   3   4   5   6   7   8   9   10 11     12    13

                            Period

                            District line - Lost Customer Hours
                   600
                                                                                              Abeyance
                   500

                   400
                                                                                              Agreed
                   300
                                                                                              Unacceptable
                   200
     LCH (000's)

                   100
                                                                                              Benchmark
                    0
                             1      2       3   4   5   6   7   8   9   10 11     12    13
                            Period

                           East London line - Lost Customer Hours

                   5                                                                          Abeyance

                   4
                                                                                              Agreed
                   3

                   2                                                                          Unacceptable
     LCH (000's)

                   1
                                                                                              Benchmark
                   0
                            1       2       3   4   5   6   7   8   9   10   11    12    13
                           Period
London Underground 2003/04   13

JNP                                                             Northern line availability has been
Availability on the Jubilee line has been                       variable, with scores worse than
variable, with scores worse than                                benchmark for half the post-transfer
benchmark in 11 of the 16 periods post-                         periods. Performance was substantially
transfer. Although recent performance                           worse than benchmark in Periods 4 and 7
has improved, the allocation of a large                         due to a number of significant signal
number of lost customer hours relating                          failures at various locations. The
to the signal problems at Green Park has                        allocation of responsibility and financial
still not been agreed; this is likely to be                     abatement for the Camden Town
referred to dispute resolution4. The                            derailment in Period 8 has not yet been
Green Park problems have now been                               agreed and is likely to be referred to
solved and additional improvements to                           dispute resolution.
the Jubilee line signalling system are
underway; further improvements will be
delivered with the line upgrade.

                       Jubilee line - Lost Customer Hours
              250
                                                                                              Abeyance
              200

              150                                                                             Agreed

              100                                                                             Unacceptable
LCH (000's)

              50
                                                                                              Benchmark
               0
                        1    2      3   4   5   6   7   8        9   10    11    12    13
                       Period

                       Northern line - Lost Customer Hours
              900
              800                                                                             Abeyance
              700
              600
                                                                                              Agreed
              500
              400
              300                                                                             Unacceptable
LCH (000's)

              200
              100                                                                             Benchmark
                   0
                         1      2   3   4   5   6   7       8    9    10   11     12   13
                       Period

4. Following three internal stages of discussion, disputes are then referred to
adjudication. The adjudication decisions can be appealed and are then heard by a court.
14 Transport for London

                         Piccadilly line - Lost Customer Hours
                   450
                   400                                                                             Abeyance
                   350
                   300
                                                                                                   Agreed
                   250
                   200
                   150                                                                            Unacceptable
     LCH (000's)

                   100
                    50                                                                            Benchmark
                     0
                           1      2   3   4   5   6    7   8         9     10 11    12   13
                         Period

     Piccadilly line availability scores have                    ●       Station ambience includes elements
     been worse than benchmark for roughly                               such as condition of platform roofs
     half of the 16 post-transfer periods;                               and canopies; condition of seating,
     however, availability is on an improving                            waiting rooms, toilets, signs, etc;
     trend and has been better than                                      cleanliness and levels of litter and
     benchmark in the last 8 periods.                                    graffiti.
     Problems were due to rolling stock and a
     number of major signal failures. Tube                       Ambience is measured through a
     Lines are implementing a major wheelset                     quarterly ‘Mystery Shopping Survey’
     modification programme to rectify the                       (MSS) conducted by an independent
     axle box problems, which should                             organisation. The score is compared
     improve reliability and reduce the need                     against a benchmark derived from
     for further work until the fleet is                         previous London Underground
     refurbished in 2014. The issue of the                       performance.
     amount of abatements to be charged for
     the effects of the axle box problems is                     Performance
     likely to go to dispute resolution.                         BCV
                                                                 Metronet BCV’s average post-transfer
     3.2 Ambience                                                ambience score is slightly better than
                                                                 benchmark. Both train and station scores
     Definition and measurement                                  are better than benchmark. The
     Ambience is a measure of the quality of                     substantial improvement in the BCV
     the travelling environment, including                       score post-transfer is primarily the result
     both train and station ambience.                            of work done by BCV, both before and
     ● Train ambience includes elements
                                                                 after transfer, on the Central line. While
        such as the condition of seats;                          the Central line was closed after the
        cleanliness of surfaces and train                        January 2003 Chancery Lane incident,
        exteriors; levels of litter and graffiti;                BCV used the time to deep-clean
                                                                 stations which appears to have
        public address (PA) audibility; ride
                                                                 somewhat improved BCV’s ambience
        quality and in-car noise; lighting,
                                                                 scores.
        heating and ventilation.
London Underground 2003/04   15

                                     Ambience - BCV
                   71
                   70
                   69
     MSS Score

                   68
                   67
                   66
                   65
                   64
                        Q1-2003/4    Q2-2003/4        Q3-2003/4      Q4-2003/4
                                           Quarter

                                     MSS             Benchmark

SSL                                                   down the SSL average to be worse than
Metronet SSL’s average ambience score                 benchmark. The successful anti-graffiti
is slightly below the benchmark. Stations             initiative is expected to move SSL’s
ambience is better than benchmark but                 scores in subsequent periods above
graffiti on the rolling stock has pulled              benchmark.

                                       Ambience - SSL
                   71

                   70
       MSS Score

                   69

                   68

                   67

                   66
                         Q1-2003/4    Q2-2003/4        Q3-2003/4       Q4-2003/4
                                            Quarter
                                     MSS               Benchmark
16 Transport for London

     JNP                                           cleaning. Ambience scores are still
     Tube Lines’ ambience performance has          marginally worse than benchmark at
     improved since transfer due to a series       present but are forecast to exceed
     of new initiatives including train washing,   benchmark next quarter.
     improved station cleaning and seat

                                         Ambience - JNP
                  72
                  71
      MSS Score

                  70
                  69
                  68
                  67
                  66
                       Q1-2003/4       Q2-2003/4       Q3-2003/4         Q4-2003/4
                                             Quarter

     3.3 Service points                            Performance
                                                   All three Infracos are performing better
     Definition and measurement                    than benchmark on fault rectification.
     Service points are allocated for failures     Performance on facilities faults has been
     by the Infraco to meet certain                mixed, as detailed briefly below.
     contractual obligations according to a
     regime set out in the contract. Some of       BCV
     the significant types of failures that can    On facilities faults, Metronet BCV scores
     contribute to service points are:             poorly due to ongoing faults with CCTV
     ● Facilities faults (a failure of a           and PA systems. BCV launched a series
        customer facing asset, such as a PA        of targeted initiatives to improve its
        system)                                    performance on facilities faults in the
     ● Fault rectification (the failure of a
                                                   last quarter of 2003, which may explain
        non-customer facing asset and faults       the improvement in Period Nine
        not rectified within standard              performance (although this was still
        clearance times)                           slightly worse than benchmark).
     ● Engineering overrun service points (a
                                                   However, towards year-end performance
                                                   deteriorated again, due in part to faults
        failure to return Underground assets
                                                   on CCTV and PA systems. BCV have
        by commencement of traffic. Service
                                                   implemented a remedial programme and
        points are applied to the first two
                                                   expect to see results in upcoming
        hours of an overrun to supplement
                                                   periods.
        the availability abatements).
London Underground 2003/04      17

                                   Service Points - BCV - Facilities faults
                   9,000
                   8,000
  Service Points

                   7,000
                   6,000
                   5,000
                   4,000
                   3,000
                   2,000
                   1,000
                       0
                           1   2     3    4      5    6       7  8      9    10   11    12   13
                                                          Period
                                              Service Points         Threshold

SSL                                                            half of the year. This is due primarily to
After weak performance in the first half                       improved performance of Dot Matrix
of the year, Metronet SSL’s performance                        Indicators (DMIs), together with some
on facilities faults improved and was                          improvement in CCTV and PA systems.
better than benchmark in the second

                                   Service Points - SSL - Facilities faults
                   8,000
                   7,000
 Service Points

                   6,000
                   5,000
                   4,000
                   3,000
                   2,000
                   1,000
                       0
                           1   2    3    4       5    6       7  8      9    10   11   12    13
                                                          Period
                                              Service Points         Threshold
18 Transport for London

     JNP                                                main issues have been CCTV, DMIs and
     After good performance in the first                PA system faults. Tube Lines has
     quarter, Tube Lines facilities faults              developed a new source of supply to
     performance has been worse than                    resolve the DMI spares shortage.
     benchmark for most of the year. The

                              Service Points - JNP - Facilties faults
          18,000
          16,000
          14,000
          12,000
          10,000
           8,000
           6,000
           4,000
           2,000
               0
                    1     2      3    4     5    6       7  8     9   10    11   12   13
                                                     Period
                                          Service Points        Threshold

     3.4 Major projects                                 Performance
                                                        BCV
     Definition and measurement                         No specific information has been
     The PPP contracts require the Infracos to          received from Metronet BCV on the
     deliver certain defined projects by                Victoria Phase 1 upgrade (which will use
     specified dates. These include:                    existing trains and signalling to improve
     ● line upgrades to increase the                    journey time by March 2006). Similarly,
        capability of the line (involving the           the Central line upgrade, which promises
        replacement of trains and signalling)           modest improvements, has not been
     ● train enhancements (including arm
                                                        explained or documented.
        rests, CCTV, emergency help points,
        and visual information displays on the          Metronet BCV’s Victoria line Phase 2
        train)                                          upgrade has been one of the key areas
     ● train refurbishment (including
                                                        of focus this year, as it is both a
                                                        substantial amount of work and is due
        replacing flooring and scratched glass,
                                                        to be completed in the medium-term
        reducing noise, improving ventilation,
                                                        (August 2013). The upgrade will include a
        etc.)
                                                        new signalling system and a new fleet of
     ● improvements to stations (wide range
                                                        47 trains. We understand from BCV that
        of work including accessibility,                design work on the Phase 2 Victoria line
        increasing platform seating, displays           train layouts has started. BCV has also
        of expected arrival times, structural           told us that conceptual design for the
        repairs, repair and/or renewal of most          new signalling system is underway,
        aspects of the station including                including a survey of stations and
        floors, lighting, signs, etc).                  tunnels to verify where and how the
                                                        signalling system will be put in place.
London Underground 2003/04      19

Computer simulations are being run to         ●   The seventh car upgrade for the
test the post-upgrade patterns of train           Jubilee line is proceeding on
service. The upgrade will also require            schedule. Tube Lines have placed the
comprehensive renewal of the Victoria             rolling stock order and manufacturing
line track; currently BCV are working on          has started. The first car will be
heavy track maintenance on the Victoria           delivered for testing in early 2005.
Line.
                                              London Underground and Tube Lines are
SSL                                           currently engaged in discussions as to
Metronet SSL has reported a six-month         the scope of station projects. So far, the
programme delay for the District line         work plans submitted for the enhanced
rolling stock refurbishment as a result of    refurbishments have been rejected by
supply issues. However, the target date       London Underground as inadequate.
for first train back in service is still
achievable. As regards the line upgrade       Tube Lines is also in the process of
work, preliminary feasibility work has        completing several additional special
begun and the overall programme is on         projects.
target.                                       ● Leicester Square, Knightsbridge

                                                 stations. These are the remaining
SSL has also provided a delivery                 major station improvement projects
programme for station works, despite             that were inherited by Tube Lines
initial delays due to requests from SSL          from before transfer. These projects
to change (often to reduce) the scope of         are proceeding according to plan.
work. Changes in scope require London         ● Piccadilly Line Extension (PiccEx) to
Underground approval as to whether the           Heathrow T5. The British Airports
new proposed output is acceptable,               Authority is providing the PiccEx to
both in terms of the contract’s intent           London Underground; Tube Lines will
and in terms of safety. London                   provide the signalling system for this
Underground and SSL had to discuss
                                                 project through a specified right
these and come to a mutually agreeable
                                                 currently being negotiated with Tube
solution. There were delays in SSL
                                                 Lines. We are having some difficulties
producing the necessary safety
                                                 in reaching agreement on terms and
documentation but work is now
progressing.                                     conditions and one element of the
                                                 cost is now in formal dispute. These
JNP                                              issues need to be resolved urgently if
Progress on the early phases of the line         the project is to be delivered on time.
upgrade works appears to be proceeding        ● Wembley Park station. The Mayor has

on schedule.                                     now accelerated this project so that
● Tube Lines have submitted their work           the completion date will be in line
   plans to London Underground for the           with the reopening of the stadium. An
   signalling and control systems for the        extensive investment of time by both
   Jubilee and Northern line upgrades            London Underground and Tube Lines
   (which are the first stage of the work).      over the year means that the project
   They have informed us that the                is expected to be delivered on time.
   signalling contract has been placed
   for these upgrades.
20 Transport for London

     4. PPP financial performance
     The PPP, through the Infracos,               Major projects and renewal. The
     introduces approximately £5bn of long-       Infracos inform us that they are on target
     term private finance, which London           to spend their budgets for the year on
     Underground repays through the               maintenance and renewal. Based on the
     infrastructure service charge (ISC). The     limited information available, London
     ISC is adjusted on the basis of contract     Underground has some concerns
     performance as outlined in the previous      regarding progress on major projects and
     section, with levels of performance tied     track renewal work. The Infraco accounts
     to adjustments to the ISC in the form of     for the penultimate period of 2003/04
     bonuses and abatements.                      indicate actual capital expenditure at 80-
                                                  85 per cent of budgeted capital
     Cash payments of ISC, bonuses and            expenditure for all three Infracos for the
     abatements for 2003/04 are summarised        year. The concern in this area is not so
     in the table below. BCV and JNP have         much the absolute levels of spend, it is
     both ended the year with net                 the amount of work being produced per
     abatements, while SSL has a net bonus.       pound spent. For example, completing
     It is worth noting that all three Infracos   50 per cent of a given length of track
     did worse on availability than they had      renewal work in the time allotted due to
     projected in their bids but better than      poor planning and inefficient working
     they had expected on ambience. JNP           still incurs the budgeted cost for the full
     and BCV outperformed their bid               scope of work.
     expectations on net performance
     payments by 35 per cent and 65 per           Risks and contingencies. The complexity
     cent respectively, while SSL                 of the PPP contracts and of their
     underperformed their expectations by         interfaces with other contracts
     delivering less than half the expected net   (particularly the large PFIs, as discussed
     bonus.                                       in the Foreword) means that there is
     Apart from the high-level financial          substantial risk around delivery. Many of
     outcomes in terms of ISC and                 these risks will not be reflected in the
     performance adjustments, which are           budget for 2004/05, as they will only
     relatively modest in the context of          materialise once these works are
     overall ISC payments, it has been            performed. As these risks are currently
     difficult so far to draw conclusions         evolving, we would expect that as the
     about performance from the financial         volume of work accelerates, the level
     data. Cost information that should           of contingency would need to increase
     ultimately be available through the          as well.
     master projects database was not
     yet available at year-end due to the
     drawn-out dispute over this issue over
     the course of the year.
London Underground 2003/04   21

FY 2003-         ISC         Bonus         Abatements Value of            Net          Net           Net
2004             Paid        Paid          Paid       Lost                Bonus        Bid           Variance
                                                      Customer            /Abatement   Forecast***   Bonus
                                                      Hours in            Out-turn     Bonus         /Abatement
                                                      Abeyance *          Range        /Abatement    Out-turn
                                                                                                     Range
                 £m          £m            £m              £m             £m           £m            £m

    Metronet     333          +1.6          -3.0**          -4.9           -1.4 to     -4.0           +2.6 to -
    BCV                                                                    -6.3                       2.3

    Metronet     385          +5.4          -2.5            -1.1           +2.9 to     +4.9           -2.0 to -3.1
    SSL                                                                    +1.8

    Tube Lines   356          +0.5          -8.1            -8.4           -7.6 to -   -10.4          +2.8 to -
                                                                           16.0                       5.6

    Total        1,074        +7.5          -15.9           -14.4          -6.1 to -   -9.5           +3.4 to -
                                                                           20.5                       11.0

*   Period 9 and prior Lost Customer Hours in abeyance when Period 11’s ISC Adjustment Statement
    was issued
** Includes +£2.3m of agreed ‘roll back’ adjustment of abatements incorrectly charged
*** Cash forecast for performance per Bidder’s final financial models

      Costs for additional works and services.       the charging arrangements, for example
      There have been some delays in securing        on-costs and profits for additional works
      additional services and works through          that London Underground considers
      the Infracos. London Underground is            excessive. In the event these issues are
      examining its own processes as well as         not resolved, London Underground will
      reviewing the performance of the               seek to have these services provided
      Infracos. There are some disputes over         through other means.
22 Transport for London

     5. Asset performance
     Definition and measurement                      however, is that the number of failures
     For the purposes of this report, six key        arising from these underlying problems
     asset groups are discussed: rolling stock,      appears to have increased in the last
     track, signals, points, lifts and escalators.   year.
     Asset performance since transfer is
     compared with London Underground                The reasons for points failures are
     historic average performance.5                  typically complex as points performance
                                                     is heavily dependent on the quality of
     Within the 12-15 month period since             the track and track maintenance. The
     transfer, it would be difficult to observe      service impact is very high when signals
     the type of improvements in asset               and points fail, as these failures tend to
     stewardship that would be expected in a         take a substantial time to fix.
     few years’ time. With that caveat,
     however, changes in asset performance           Performance
     can be detected year on year. Below we          Across the network, there has not been
     provide data and commentary on                  any significant improvement in the
     performance for the major asset classes         performance of the signalling system,
     (i.e., those where failures have a              and in key areas such as points there has
     significant impact on the service).6            been a decline in performance.7 There
                                                     are a number of likely contributing
     5.1 Signalling system                           factors:
                                                     ● The level and quality of supervision

     Background                                         over the technicians doing the work
     Many of the root causes of signal                  has declined over the last few years;
     failures predate transfer in that they are         this does not appear to have been
     related to pre-existing component                  reversed under Infraco management
     weaknesses. What has been of concern,

     5. Asset performance is measured in a number of different ways. There are certain
     measures that can be looked at consistently across different asset types, i.e. total
     number of failures, average downtime per failure and mean service hours or distance
     between failures. In addition, each asset class has a wide range of specific measures
     that can help in further understanding the condition and underlying root causes for the
     performance of that asset. A mix of measures is used for the six asset types in the
     section below.
     6. In looking at the asset performance data:
     ● Number of failures data cannot necessarily be directly compared between Infracos,

         as Infracos with more lifts (say) would tend to have more failures. The benchmark
         data provided is meant to partially overcome this.
     ● There can often be some correlation between the number of failures and the

         duration of failures; this is because the greater the number of failures, the less the
         likelihood the Infraco will have the resources (additional trains, skilled technicians,
         etc) to fix the incremental failure.
     ● Base data comes from systems shared with the Infracos and used for incident

         attribution. Differences from aggregated Infraco data will only arise if certain
         underlying causes are included/excluded.
     7. For purposes of this report, the term ‘signalling systems’ will be used to refer to
     signals and points.
London Underground 2003/04       23

●   There have been some difficulties          better than the first half. Signal
    over the last year in agreeing access      performance has improved somewhat as
    to the track for signalling technicians.   against pre-transfer performance.
    This appears to be due to a                Downtime for both signals and points
    combination of factors, including new      has been slowly worsening.
    staff and adjustments to the new
                                               BCV has implemented a number of
    system including concerns about
                                               initiatives to address ongoing problems:
    accountability and liability for
                                               ● Automatic Train Protection (ATP)
    decision-making (now that different
                                                   system problems on the Central line.
    companies employ the technicians
                                                   BCV is moving towards a
    and operational staff).
                                                   maintenance regime determined by
●   The quality of signalling system
                                                   volume of traffic rather than set time
    engineers is quite variable across the
                                                   periods.
    Infracos and indeed across different
                                               ● Circuit controller problems on the
    lines, with different levels of
                                                   Central line. BCV is in discussions
    experience. The historic practice of
                                                   with the manufacturer to come up
    ‘loaning’ engineers from one line to
                                                   with a solution to this problem.
    another has not been continued by
                                               ● Component obsolescence in the
    Infracos at the same rate as pre-
                                                   Central line control system. New
    transfer.
                                                   sourcing arrangements for
There are some encouraging signs of                functionally equivalent parts are being
joint working across all three Infracos.           pursued with BCV’s suppliers to
For example:                                       address this.
● Redressing the technical skills              ● Signalling relay problems on the

   shortfall through joint recruitment             Victoria line. BCV are working with
   programmes and training, including a            the manufacturer on a long-term fix
   new training school at Stratford.               for these problems.
● Developing renewal programmes for
                                               SSL
   degraded components of the system
                                               Overall, SSL’s signalling system
   (e.g., broken track wires, defective
                                               performance has been mixed. SSL
   blockjoints, tuning units). In some
                                               started off the year with an
   cases, one Infraco is trialling solutions
                                               improvement in the number of signalling
   on behalf of the others, which is           failures but since then has shown a
   positive (e.g. SSL testing a new            worsening trend. We would expect
   material for redressing contact             signalling downtime to improve in future
   failures).                                  as SSL have recently increased their
                                               number of signalling technicians. Points
BCV
                                               failures were improving in the first half
On the BCV lines, average points
                                               but have been worsening in the second
performance for the year is not
                                               half, although points downtime has been
significantly changed as against pre-
                                               decreasing in the second half of the year.
transfer performance, although
performance in the second half was
24 Transport for London

Signals
Metronet - BCV

                                Metronet - BCV - Signals                                                                                             Metronet - BCV - Signals
                                Number of in service failures resulting in Service Disruptions > 2 minutes                                           Average Duration of in service failures resulting in Service Disruptions > 2 minutes
                          120                                                                                                               80

                                                                                                                                            70
                          100
                                                                                                                                            60
                           80
                                                                                                                                            50

                           60                                                                                                               40
    Number of Failures

                                                                                                                                            30
                           40
                                                                                                                                            20

                                                                                                                            Minutes
                           20
                                                                                                                                            10

                           0                                                                                                                    0
                                 1 2     3 4 5 6        7 8 9 10 11 12 13 1 2         3 4 5 6       7 8 9 10 11 12 13                                1     2 3 4       5 6    7 8    9 10 11 12 13 1 2        3 4 5     6 7      8 9 10 11 12 13

                                Period 02/03 to 03/04                                                                                               Period 02/03 to 03/04
                                       Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)                                                         Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)

Tube Lines - JNP
                                Tube Lines - JNP - Signals                                                                                               Tube Lines - JNP - Signals
                                Number of in service failures resulting in Service Disruptions > 2 minutes                                               Average Duration of in service failures resulting in Service Disruptions > 2 minutes
                          120                                                                                                                       80

                                                                                                                                                    70
                          100
                                                                                                                                                    60
                          80
                                                                                                                                                    50

                          60                                                                                                                        40
     Number of Failures

                                                                                                                                                    30
                          40
                                                                                                                                                    20
                                                                                                                                      Minutes

                          20
                                                                                                                                                    10

                           0                                                                                                                        0
                                 1 2     3 4 5 6        7 8 9 10 11 12 13 1 2          3 4 5 6          7 8 9 10 11 12 13                                 1    2 3 4      5 6    7 8    9 10 11 12 13 1 2        3 4 5     6 7     8 9 10 11 12 13

                                Period 02/03 to 03/04                                                                                                    Period 02/03 to 03/04
                                       Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)                                                           Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)

Metronet - Subsurface
                                Metronet - Subsurface - Signals                                                                                          Metronet - Subsurface - Signals
                                Number of in service failures resulting in Service Disruptions > 2 minutes                                               Average Duration of in service failures resulting in Service Disruptions > 2 minutes

                          120                                                                                                                       80

                                                                                                                                                    70
                          100
                                                                                                                                                    60
                          80                                                                                                                        50

                          60                                                                                                                        40
 Number of Failures

                                                                                                                                                    30
                          40
                                                                                                                                                    20
                                                                                                                                      Minutes

                          20                                                                                                                        10

                           0                                                                                                                        0
                                 1 2     3 4 5 6        7 8 9 10 11 12 13 1 2         3 4 5 6       7 8 9 10 11 12 13                                     1    2 3 4     5 6     7 8   9 10 11 12 13 1 2        3 4 5      6 7    8 9 10 11 12 13

                                Period 02/03 to 03/04                                                                                                    Period 02/03 to 03/04

                                       Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)                                                           Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)
London Underground 2003/04                                                  25

Points
Metronet - BCV

                               Metronet - BCV - Points                                                                                                Metronet - BCV - Points
                               Number of in service failures resulting in Service Disruptions > 2 minutes                                             Average Duration of in service failures resulting in Service Disruptions > 2 minutes
                          45                                                                                                            160
                          40                                                                                                            140
                          35
                                                                                                                                        120
                          30
                                                                                                                                        100
                          25
                                                                                                                                             80
                          20
     Number of Failures

                                                                                                                                             60
                          15
                          10                                                                                                                 40

                                                                                                                             Minutes
                          5                                                                                                                  20

                          0                                                                                                                  0
                                   1   2 3 4     5 6 7      8 9 10 11 12 13 1 2 3          4 5 6        7 8 9 10 11 12 13                              1    2 3 4       5 6 7      8 9 10 11 12 13 1 2 3          4 5 6       7 8 9 10 11 12 13

                                  Period 02/03 to 03/04                                                                                           Period 02/03 to 03/04
                                       Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)                                                        Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)

Tube Lines - JNP

                                  Tube Lines - JNP - Points                                                                                           Tube Lines - JNP - Points
                                  Number of in service failures resulting in Service Disruptions > 2 minutes                                          Average Duration of in service failures resulting in Service Disruptions > 2 minutes
                          45                                                                                                            160
                          40                                                                                                            140
                          35
                                                                                                                                        120
                          30
                                                                                                                                        100
                          25
                                                                                                                                             80
                          20
 Number of Failures

                                                                                                                                             60
                          15

                          10                                                                                                                 40
                                                                                                                             Minutes

                           5                                                                                                                 20

                           0                                                                                                                 0
                                   1   2 3 4     5 6      7 8   9 10 11 12 13 1 2      3 4     5   6 7     8 9 10 11 12 13                             1 2       3 4 5 6       7 8 9 10 11 12 13 1 2 3 4              5 6 7       8 9 10 11 12 13

                                  Period 02/03 to 03/04                                                                                           Period 02/03 to 03/04
                                       Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)                                                       Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)

Metronet - Subsurface

                                  Metronet - Subsurface - Points                                                                                        Metronet - Subsurface - Points
                                  Number of in service failures resulting in Service Disruptions > 2 minutes                                            Average Duration of in service failures resulting in Service Disruptions > 2 minutes
                          45                                                                                                                  160
                          40
                                                                                                                                              140
                          35
                                                                                                                                              120
                          30
                                                                                                                                              100
                          25
                                                                                                                                                 80
                          20
     Number of Failures

                                                                                                                                                 60
                          15

                          10                                                                                                                     40
                                                                                                                                   Minutes

                              5                                                                                                                  20

                              0                                                                                                                   0
                                   1   2 3 4     5 6      7 8   9 10 11 12 13 1 2       3 4 5      6 7    8 9 10 11 12 13                                  1 2     3 4 5 6       7 8 9 10 11 12 13 1 2 3 4             5 6 7       8 9 10 11 12 13
                                  Period 02/03 to 03/04                                                                                                Period 02/03 to 03/04
                                        Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)                                                           Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)
26 Transport for London

     Of particular concern is signal reliability     indicated above, the Infracos have not
     on the northern section of the Circle           continued this practice to the same
     line. A significant problem is water            extent post-transfer.
     ingress and poor drainage. SSL and
     London Underground are in discussions         The first step towards addressing these
     with Thames Water to resolve these            problems effectively is much more
     problems, which have worsened in the          aggressive analysis of asset performance
     last year. Other problems include points      data by the Infracos to understand
     failures, broken track wires, and             underlying trends behind failures and
     blockjoint failures, giving rise to a         then to develop the appropriate
     concern about the quality of the              response.
     maintenance regime for blockjoints.
     Signal lamp failures have risen               On the Piccadilly line, reliability
     dramatically due to manufacturing             problems with the control system
     defects in the recent batch of lamps;         have continued due to component
     this is expected be redressed once a          obsolescence. JNP is buying up
     new batch is put in place (and ultimately     second-hand components to
     through plans to move to a newer signal       supplement the stock of spare parts,
     lamp technology). On the District line,       which is intended to reduce the level
     control cables at the eastern end of the      of disruption.
     line have experienced problems over the
     year due to degradation from age and
                                                   5.2 Rolling stock
     damage from track fires.                      Background
     JNP                                           The Underground network includes
     The number of points failures on JNP          fleets with a wide range of ages and
     has roughly doubled since transfer,           different designs. Analysing the
     which has been matched by a doubling          performance of rolling stock can be
     in downtime as well. The number of            complicated since the trains’
     signal failures has remained relatively       performance is substantially driven by
     stable over the year, while signal            the interface with the track - in other
     downtime has nearly doubled. In our           words, the same rolling stock can
     view, this overall decline in performance     perform differently on different lines due
     is due in part to:                            to variations in track conditions.
     ● There appears to be insufficient

         management attention given to             Performance
         signalling system problems. This was
         exemplified by problems with a faulty     BCV
         track circuit at Green Park which had a   BCV is the only Infraco showing some
         major impact on service, with trains      improvement on mean distance between
         having to terminate at Green Park         failures over the year. Looking at
         numerous times including during the       number/duration of failures, BCV’s mean
         morning peak. These problems have         distance between failures performance
                                                   has been on a worsening trend for most
         now been addressed but follow a long
                                                   of the year, but this was due to the
         period of failure
                                                   increase over the course of the year in
     ● Historically JNP lines were weaker on
                                                   mileage operated as the Central line was
         signalling and relied on technicians
                                                   gradually reintroduced following the
         from other parts of the network. As       Chancery Lane derailment.
London Underground 2003/04                                   27

Rolling stock
Metronet - BCV

                             Metronet - BCV - Rolling Stock                                                                           Metronet - BCV - Rolling Stock
                             Number of in service failures resulting in Service Disruptions > 2 minutes                               Average Duration of in service failures resulting in Service Disruptions > 2 minutes
                                                                                                                                120
                      500
                      450
                                                                                                                                100
                      400
                      350                                                                                                       80
                      300
                      250                                                                                                       60
Number of failures

                      200
                                                                                                                                40
                      150
                      100
                                                                                                                                20

                                                                                                                      Minutes
                       50
                        0                                                                                                        0
                              1 2 3 4       5 6 7 8 9 10 11 12 13 1 2             3 4    5 6 7 8      9 10 11 12 13                    1 2 3     4 5 6 7 8         9 10 11 12 13 1 2 3 4 5            6 7 8 9 10 11 12 13
                             Period 02/03 to 03/04                                                                                    Period 02/03 to 03/04
                                  Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)
                                                                                                                                            Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)

                             Metronet - BCV - Rolling Stock
                             Mean Distance Between Failure

                     10000
                     9000
                     8000
                     7000
                     6000
                     5000
                     4000
                     3000
Kilometres

                     2000
                     1000
                       0
                              1 2 3 4 5 6 7 8 9 10 11 12 13 1 2 3 4 5 6 7 8 9 10 11 12 13

                             Period 02/03 to 03/04
                                   Actual Post Transfer - 6 per. Mov. Avg. (Actual Post Transfer)

                     As measured by the mean distance between                                                         The mean distance between failures
                     failures, the Central line shows consistent                                                      measurement improved for the Bakerloo and
                     improvement over the course of the year as the                                                   Victoria lines over the year. The two main issues
                     rolling stock problems highlighted by the                                                        with the Victoria line fleet over the year were
                     Chancery Lane derailment are being addressed. A                                                  problems with doors not closing properly at
                     programme of heavy maintenance was initiated                                                     stations and faults relating to Automatic Train
                     during the year, and a new management team has                                                   Operation (ATO). A revised maintenance regime
                     been put in place for the Central line fleet,                                                    has been put in place to address the door
                     including resource from Bombardier. This                                                         problems. The ATO faults are due to equipment
                     programme appears to be starting to show                                                         that has become unreliable. Faults cause the
                     results in terms of improvements in asset                                                        trains to stop between stations, at which point
                     performance, particularly since the programme                                                    the driver must switch to manual operation.
                     was accelerated at the end of the year.                                                          The replacement of the trainborne ATO
                                                                                                                      equipment by the end of 2004 is expected to
                                                                                                                      improve performance.
You can also read