Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR

Page created by Johnny Duncan
 
CONTINUE READING
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
The Dovre Line:
Kleverud-Sørli-Åkersvika
Stine Ilebrekke Undrum
Project Director

Bane NOR Tender Conference June 5. 2019
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Important HSE principles for Bane NOR
• Safety always has first priority
• Our safety culture shall ensure that we
  work systematically with safety to avoid
  human injury and environmental or
  material damages.
    − we adhere to the highest safety standards.
    − we understand and consider risk.
    − we have zero tolerance for breach of safety
      regulations

• The Working Environment Act applies to
  EVERYONE working in Norway, both
  Norwegian and foreign nationals.
    − http://www.arbeidstilsynet.no/working-conditions-in-
      norway.html
                                                             Everybody safely home
4
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Infrastructure Construction Division
                                                         Infrastrucure
                                                         Construction
                                                          Einar Kilde

                                             Project 2020          Plan & Portfolio
                                            Brede Nermoen         Elsebeth A Bakke
                           Finance &
                                                                                         Communication
                         projectcontrol
                                                                                         Cecilie Melland
                       Birger Steffensen
                                           Contract & Market       Safety & Quality
                                            Henning Scheel          Vigdis Bjørlo
                         Technique &
                           Concept                                                             HR
                         Trude Anke                                                       Gry Jødestøl

                              Folloline    Ringerikeline/ E16                                              East (Østfoldline &
                                                                     West/Mid           Vestfoldline
    New Oslo-tunnel          Per David          Morten                                                         Dovreline)
                             Borenstein      Klokkersveen         Hans-Egil Larsen    Lars A Tangerås
    Anne Siri Haugen                                                                                        Stine I Undrum

5
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
East – Østfold Line & Dovre Line
                                                   Project director
                                                   Stine Ilebrekke
                                                       Undrum

                                            Dep.
                                                               Projectcontrol
                                       Project director
                                                             Tor-A Holst Larsen
                                        Per B Vilnes
                   Communication                                                          HR
                      TBN                                                            Arild Sæthre
                                         Contract &            Safety & Quality
                                          strategy              Bente Gamst
                                        Karin Kaasen              Hornnæs

     Venjar – Langset   Kleverud – Sørli –          Planprojects          Sandbukta – Moss       Planprojects
    Rønnaug-Ingeborg        Åkersvika                Dovreline                 – Såstad            Østfoldline
         Resset           Geir H Kvillum             Lars Eide            Jarle Rasmussen       Elisabeth Nordli

6
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Construction
Projects
Dovre Line

  7
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
1:23 (2:14)
    InterCity-projects                          Oslo-Lillehammer

    on Dovre Line
                                                             0:55 (1:23)
                                                             Oslo-Hamar

    • Venjar-Langset 2023
    • Kleverud-Sørli 2026
                               0:37 (1:23)
    • Sørli-Åkersvika 2026     Oslo-Hamar

    • Brumunddal-Moelv 2030
    • Hamar-Brumunddal 2032
    • Moelv-Lillehammer 2034
                               1:00 (1:28)
                               Oslo-Tønsberg

                               1:30 (2:45)                                0:45 (1:08)        1:08 (1:45)
                               Oslo-Porsgrunn                             Oslo-Fredrikstad   Oslo-Halden

8
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Project status
        • Kleverud-Sørli                                     • Sørli-Åkersvika
            − Preparatory work ongoing                          − Zoning plan expected to be approved late 2019
            − Preparation of invitation to tenders              − Start pre-qualifications of contracts late 2020
            − Start pre-qualification of two first main         − Contract award remaining contract 2021/2022
              contracts autumn 2019
            − Contract award first Main Contract late 2020

                                   Tangen
                                Railway Station
Hestnes Tunnel                                            Sørli Timber       Stange                      Åkersvika
  (3 km)                                                   Terminal        Railway Station               Wetland Area
                 Tangenvika Bridge
                   (1 km)

        9
Kleverud-Sørli-Åkersvika - The Dovre Line: Stine Ilebrekke Undrum Project Director - Bane NOR
Lillehammer

 Project summary
                                                                          Moelv
                                                                                         Brumunddal
 • Facts and numbers                                     Hamar Converter                   Jessnes
                                                                                             Hamar
     − 30 km new double track railway from Kleverud
       to Åkersvika                                      Sørli-Åkersvika                         Stange

     − The Hestnes Tunnel 3,1 km
                                                                                                      Sørli

                                                                                                        Tangen
     − Tangenvika Railway Bridge 1,07 km                 Kleverud-Sørli
     − Construction of a new railway station at Tangen                                                  Kleverud

     − Rebuild of existing railway station at Stange
     − Åkersvika Wetland                                                                                Langset

     − 21 other large constructions                                                                     Eidsvoll

     − Tracks and catenary. Railway technique                                                         Venjar

     − Designed for a max speed of 250 km/h
                                                                                               Oslo Airport

 • Planned government funding
     − Kleverud-Sørli 2020 including Hamar Converter
       station
     − Sørli-Åkersvika 2021
                                                                                               Lillestrøm
                                                                          Oslo S

10
Kleverud – Sørli - Åkersvika

Geir Kvillum
Head of Project

Bane NOR Tender Conference June 5. 2019
1:23 (2:14)
 InterCity-projects                          Oslo-Lillehammer

 on Dovre Line
                                                          0:55 (1:23)
                                                          Oslo-Hamar

 • Venjar-Langset 2023
 • Kleverud-Sørli 2026
                            0:37 (1:23)
 • Sørli-Åkersvika 2026     Oslo-Hamar

 • Brumunddal-Moelv 2030
 • Hamar-Brumunddal 2032
 • Moelv-Lillehammer 2034
                            1:00 (1:28)
                            Oslo-Tønsberg

                            1:30 (2:45)                                0:45 (1:08)        1:08 (1:45)
                            Oslo-Porsgrunn                             Oslo-Fredrikstad   Oslo-Halden

12
Contract structure

15
Procurement plan

16
KS-1 The Hestnes tunnel

17
Contract KS-1 The Hestnes tunnel
                                                                                            Preparatory
                                                                                            works at
        KS-1      KS-2                  KSÅ-3                          SÅ-4                 Hamar

     Kleverud

                         Tangen            Sørli          Stange                Åkersvika   Hamar
                Espa

From Kleverud to Espa

1200 m open landscape     3100 m rock tunnel    no. of large constructions: 3

18
Contract KS-1 The Hestnes tunnel

• Civil work - EPC contract
• Contract basis: Norwegian total contract 2015 (NTK 15)
• Procurement procedure: Negotiated procedure (konkurranse med forhandling)
• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule
     − Start prequalification   Q4 (December) 2019
     − Contract award           Q4 (December) 2020

19
KS-1 Civil works

• Handling of excavated rock:                       • 4 technical buildings
     − 130 000 m3 fillings in lake Mjøsa
                                                    • 2 access tunnels, total length 850m
     − Surplus of rock being transported to Sørli

• Bridge over stream Labbelva

20
KS-1 Hestnes tunnel
• Drill & blast
• 3,1 km single tube tunnel, cross-
  section area 125m2
• Excavation volume, 420 000 sm3
     − Hard rock, mainly granitic gneiss and
       amphibolite

• Water & frost-protection; membrane
  and concrete lining

21
KS-2 Tangenvika railway bridge

22
Contract KS-2 Tangenvika railway bridge
                                                                                          Preparatory
                                                                                          works at
        KS-1      KS-2                     KSÅ-3                       SÅ-4               Hamar

     Kleverud

                         Tangen               Sørli       Stange              Åkersvika   Hamar
                Espa

From Espa to Furnesbakken

1800 m open landscape      1070 m bridge     no. of large constructions: 2

23
Contract KS-2 Tangenvika railway bridge

• Civil work - EPC contract
• Contract basis: Norwegian total contract 2015 (NTK 15)
• Procurement procedure: Competitive dialogue (Konkurransepreget dialog)
     − With the aim to:
       ‒ Focus and align project needs and goals in an early phase
       ‒ Make use of competence and technology in the market / Exploit innovative ideas and solutions
       ‒ Empower efficient project execution through common understanding of technical solutions and allocation of risk

• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule
     − Start prequalification               Q4 (October) 2019
     − Contract award                       Q4 (December) 2020

24
KS-2 Tangenvika railway bridge
• Tangenvika railway bridge
• Restructuring of local road
• Civil work in open landscape
• Rock cut approx. 250 000 sm3
• Fillings for abutment and embankments
• Temporary quay facilities at northern
  side of Tangenvika bay
• Wildlife crossing

25
KS-2 Tangenvika Railway bridge
• Concrete bridge
• Water depth of up to 50 m with 40 m layer of soils/subsoils above bedrock
• Challenging foundation due to location and depths
• Focus on increased degree of freedom in span-widths and piling method

26
KSÅ-3 Open landscape, incl. 2 stations

27
Contract KSÅ-3 Open landscape, incl. 2 stations
                                                                                             Preparatory
                                                                                             works at
        KS-1      KS-2                      KSÅ-3                         SÅ-4               Hamar

     Kleverud

                          Tangen               Sørli         Stange              Åkersvika   Hamar
                Espa

From Furnesbakken to Stange including Stange station

13 250 m open landscape      2 stations   no. of large constructions: 7

28
Contract KSÅ-3 Open landscape, incl. 2 stations

• Civil work - EPC contract
• Contract basis: Norwegian total contract 2015 (NTK 15)
• Procurement procedure: Negotiated procedure (Konkurranse med forhandling)
• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule
     − Start prequalification   Q4 2020
     − Contract award           Q4 2021

29
KSÅ-3
• 13,3 km substructure including civil
  works at two stations, Tangen and
  Stange
• Excavation and handling of approx. 1
  500 000 sm3 rock and soils
     − Large capacity landfills close to site

• “Greenfield” areas to Sørli
• Close to existing railway from Sørli
  timber- terminal
• Wildlife crossings

30
KSÅ-3 Tangen station
• New 4-track
  Tangen station,
  2 tracks to
  platform.
• Parking areas

31
KSÅ-3 Stange station
• New 3- track station situated at the same place as existing Stange station
• Stange station shall be at full operation during construction.
• Parking, bus and taxi areas

32
SÅ-4 Open landscape

33
Contract SÅ-4 Open landscape
                                                                                         Preparatory
                                                                                         works at
        KS-1      KS-2                     KSÅ-3                      SÅ-4               Hamar

     Kleverud

                         Tangen               Sørli          Stange          Åkersvika   Hamar
                Espa

From Stange to Åkersvika

9000 m open landscape        no. of large constructions: 9

34
Contract SÅ-4 Open landscape

• Civil work - EPC contract
• Contract basis: Norwegian total contract 2015 (NTK 15)
• Procurement procedure: Negotiated procedure (konkurranse med forhandling)
• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule
     − Start prequalification   Q4 2020
     − Contract award           Q4 2021

35
SÅ-4
• 9 km civil works in open landscape
• Excavation and handling of:
     − approx. 680 000 sm3 rock and soils
     − 72 000 sm3 of alum shale

• Large landfill at Nesten/Skjerden
• Approved landfill for disposal of alum
  shale close to site
• 2 large culvert/ concrete tunnels
• Restructuring of roads

36
SÅ-4
• Two large culverts/concrete tunnels
• Deep cuttings in agricultural landscape

37
SÅ-4 Åkersvika and construction work

• Permanent filling above
  existing track in Åkersvika –
  Ramsar area
• New operational phase with
  temporary fillings
• Restrictions in construction
  work during the breeding
  period for birds (April-May)
• Permission from county
  governor granted
  before construction starts

38
Kleverud – Sørli - Åkersvika

Niklas Marcussen
Engineering manager

Bane NOR Tender Conference June 5. 2019
KSÅ-6 & KSÅ-7 – Railway technique

40
Contract KSÅ-6 and KSÅ-7 Railway technique
                                                                                          Preparatory
                                                                                          works at
        KS-1       KS-2                     KSÅ-3                      SÅ-4               Hamar

     Kleverud

                          Tangen                Sørli      Stange             Åkersvika   Hamar
                Espa

                 KSÅ-6 Tracks and OCL        KSÅ-7 Power supply and Telecom
From Kleverud to Åkersvika

30 000 m railway       no. of technical buildings: 19

41
Contract KSÅ-6/ KSÅ-7 Railway technique

• Railway technique - Construction contract
• Engineering – Integrated team with Bane NOR employees and consulting engineers
• Contract basis construction contract: NS 8405
• Procurement procedure: Negotiated procedure
• Number of pre-qualified tenderers should preferably be between 3-5

• Planned schedule Construction contract
     − Start prequalification   Q3 or Q4 2021
     − Contract award           Q3 or Q4 2022

42
KSÅ-6 Railway technique electrical power/telecom
• Power systems and installations:
     − 19 technical buildings
     − Two stations
     − All subsystems and components

• Installation of emergency systems in the Hestnes tunnel
• High voltage cables, 22kV
• Public information systems and video surveillance

43
KSÅ-7 Railway technique Tracks/OCL
Track works​
• Ballasted tracks
• Installation of company provided items:​
     − 65 000 m of tracks​
     − 100 000 Sleepers​
     − 36 turnouts​
• 300 000 m3 ballast

Overhead contact line
• Standard Bane NOR S25 overhead contact
  line system
• Autotransformers

44
KSÅ-5 - Engineering contract
• Engineering consultancy contract
     − Engineering of railway systems
     − Project support civil works
     − Manpower support to integrated team, Railway technique
     − Interface coordination

45
Ground conditions - site investigations

          • Geotechnical site investigations with
            more than 500 holes drilled
            along the planned track
          • Kleverud-Sørli
            - Good ground conditions for construction
              purposes. Visible rock or thin
              layers of topsoil

          • Sørli-Åkersvika
            - Hard moraine of varying
              depth above a soft
              type of rock. Stable
              soils for civil works

          • Focus on analysis
            – soil and rock

46
Ground conditions – Tangenvika
• Comprehensive geotechnical
  site investigation program with 90
  drilling points performed 2015/2016
• Stable barge ensure correct data
• Use of "down-the hole” technology
  to verify bedrock in addition to
  geophysical investigation
• Soil consist mud and hard moraine

47
Special conditions – Lake Mjøsa
• There is a large
  difference between
  the regulated water
  levels in summer and
  winter in Lake Mjøsa.
• Highest regulated
  water level HRV =
  122.94 m
• Lowest regulated
  water level LRV =
  119.33 m
• Discharge permit
  granted
48
Åkersvika wetland
• Åkersvika is Norways first Ramsar site (1974)-one of the
  largest (4300 ha) and best-developed freshwater deltas in
  Norway.
• Application for exemption from RAMSAR-regulations-
  Hedmark county – in good progress
• Building new railway will have a footprint of 29 daa, of
  which 19 daa is permanent.

49
What do we think about risk
•    Main principles for allocation of risk in the contract will be:
     - The risk shall be carried by the party most familiar with the risk and best able to control it
     - Risk allocation in the contract shall be fair (balanced) and well-defined
     - Compensation format will be compiled to reflect the above

•    Risk mitigation is also applied by:
     -   Reduced uncertainty through thorough geological and geophysical surveys
     -   Test pile driving in Mjøsa by contractor, to be considered
     -   Use of competitive dialogue for Tangenvika railway bridge
     -   Environmental regulations; Several permits for environmental emissions in good progress

•    The compensation format will aim for neutral liquidity

50
Kleverud-Sørli-Åkersvika. Contract Summary

               Prequal. Q4.2019                             Prequal. Q4.2019

                EPC contract                                 EPC contract       Hamar
                                                                               Hamar
                   KS-1                                         KS-2               Stange
                                                                                  Stange
                  Tunnel                                       Bridge
                                                                                         Tangen
                                                                                        Tangen

      Civil
                Prequal. 2020                                Prequal. 2020          Eidsvoll

                EPC contract                                 EPC contract
                     KSÅ-3                                      SÅ-4
               Open landscape                               Open landscape
                Incl. 2 stations

                                       Prequal. 2021

                                   Construction contract
     Railway                       KSÅ-6 Tracks and OCL
     systems
                                   Construction contract
                                   KSÅ-7 Electro and Tele

51
Kleverud-Sørli-
Åkersvika
Dovre Line – a part of InterCity
• Reduced travel time
• Increased capacity
• 2 new stations
• Project estimated to 12 billion NOK
• Opening scheduled for 2026
Kleverud-Sørli-Åkersvika
• For project information, please see
  Bane NOR’s home page:
     − www.banenor.no

• Project home page:
     − www.banenor.no/Prosjekter/prosjekter/klev
       erud-sorli/
     − www.banenor.no/Prosjekter/prosjekter/dovr
       ebanen/sorli-akersvika/

• Supplier contact:
     − Gro-Ane.Haarklou.Westbye@banenor.no

53
People to ask!
Head of project   Project manager           Contract manager     Engineering manager   Manager Tunnel
Geir Kvillum      Gunnar Sletten            Gro-Ane H. Westbye   Niklas Marcussen      Kjetil Bøyeie

Enginering        Manager land acqusition    Quality advisor     Manager Bridge        Environ. advisor
Thomas Nævestad   Bjørn J. Sørum             Anniken Tranberg    Steinar Hognestad     Trine M. Holm