The Dovre Line: Kleverud-Sørli-Åkersvika Stine Ilebrekke Undrum Project Director Bane NOR Tender Conference June 5. 2019
Important HSE principles for Bane NOR • Safety always has first priority • Our safety culture shall ensure that we work systematically with safety to avoid human injury and environmental or material damages. − we adhere to the highest safety standards. − we understand and consider risk. − we have zero tolerance for breach of safety regulations • The Working Environment Act applies to EVERYONE working in Norway, both Norwegian and foreign nationals. − http://www.arbeidstilsynet.no/working-conditions-in- norway.html Everybody safely home 4
Infrastructure Construction Division Infrastrucure Construction Einar Kilde Project 2020 Plan & Portfolio Brede Nermoen Elsebeth A Bakke Finance & Communication projectcontrol Cecilie Melland Birger Steffensen Contract & Market Safety & Quality Henning Scheel Vigdis Bjørlo Technique & Concept HR Trude Anke Gry Jødestøl Folloline Ringerikeline/ E16 East (Østfoldline & West/Mid Vestfoldline New Oslo-tunnel Per David Morten Dovreline) Borenstein Klokkersveen Hans-Egil Larsen Lars A Tangerås Anne Siri Haugen Stine I Undrum 5
East – Østfold Line & Dovre Line Project director Stine Ilebrekke Undrum Dep. Projectcontrol Project director Tor-A Holst Larsen Per B Vilnes Communication HR TBN Arild Sæthre Contract & Safety & Quality strategy Bente Gamst Karin Kaasen Hornnæs Venjar – Langset Kleverud – Sørli – Planprojects Sandbukta – Moss Planprojects Rønnaug-Ingeborg Åkersvika Dovreline – Såstad Østfoldline Resset Geir H Kvillum Lars Eide Jarle Rasmussen Elisabeth Nordli 6
1:23 (2:14) InterCity-projects Oslo-Lillehammer on Dovre Line 0:55 (1:23) Oslo-Hamar • Venjar-Langset 2023 • Kleverud-Sørli 2026 0:37 (1:23) • Sørli-Åkersvika 2026 Oslo-Hamar • Brumunddal-Moelv 2030 • Hamar-Brumunddal 2032 • Moelv-Lillehammer 2034 1:00 (1:28) Oslo-Tønsberg 1:30 (2:45) 0:45 (1:08) 1:08 (1:45) Oslo-Porsgrunn Oslo-Fredrikstad Oslo-Halden 8
Project status • Kleverud-Sørli • Sørli-Åkersvika − Preparatory work ongoing − Zoning plan expected to be approved late 2019 − Preparation of invitation to tenders − Start pre-qualifications of contracts late 2020 − Start pre-qualification of two first main − Contract award remaining contract 2021/2022 contracts autumn 2019 − Contract award first Main Contract late 2020 Tangen Railway Station Hestnes Tunnel Sørli Timber Stange Åkersvika (3 km) Terminal Railway Station Wetland Area Tangenvika Bridge (1 km) 9
Lillehammer Project summary Moelv Brumunddal • Facts and numbers Hamar Converter Jessnes Hamar − 30 km new double track railway from Kleverud to Åkersvika Sørli-Åkersvika Stange − The Hestnes Tunnel 3,1 km Sørli Tangen − Tangenvika Railway Bridge 1,07 km Kleverud-Sørli − Construction of a new railway station at Tangen Kleverud − Rebuild of existing railway station at Stange − Åkersvika Wetland Langset − 21 other large constructions Eidsvoll − Tracks and catenary. Railway technique Venjar − Designed for a max speed of 250 km/h Oslo Airport • Planned government funding − Kleverud-Sørli 2020 including Hamar Converter station − Sørli-Åkersvika 2021 Lillestrøm Oslo S 10
Kleverud – Sørli - Åkersvika Geir Kvillum Head of Project Bane NOR Tender Conference June 5. 2019
1:23 (2:14) InterCity-projects Oslo-Lillehammer on Dovre Line 0:55 (1:23) Oslo-Hamar • Venjar-Langset 2023 • Kleverud-Sørli 2026 0:37 (1:23) • Sørli-Åkersvika 2026 Oslo-Hamar • Brumunddal-Moelv 2030 • Hamar-Brumunddal 2032 • Moelv-Lillehammer 2034 1:00 (1:28) Oslo-Tønsberg 1:30 (2:45) 0:45 (1:08) 1:08 (1:45) Oslo-Porsgrunn Oslo-Fredrikstad Oslo-Halden 12
Contract structure 15
Procurement plan 16
KS-1 The Hestnes tunnel 17
Contract KS-1 The Hestnes tunnel Preparatory works at KS-1 KS-2 KSÅ-3 SÅ-4 Hamar Kleverud Tangen Sørli Stange Åkersvika Hamar Espa From Kleverud to Espa 1200 m open landscape 3100 m rock tunnel no. of large constructions: 3 18
Contract KS-1 The Hestnes tunnel • Civil work - EPC contract • Contract basis: Norwegian total contract 2015 (NTK 15) • Procurement procedure: Negotiated procedure (konkurranse med forhandling) • Number of pre-qualified tenderers should preferably be between 3-5 • Planned schedule − Start prequalification Q4 (December) 2019 − Contract award Q4 (December) 2020 19
KS-1 Civil works • Handling of excavated rock: • 4 technical buildings − 130 000 m3 fillings in lake Mjøsa • 2 access tunnels, total length 850m − Surplus of rock being transported to Sørli • Bridge over stream Labbelva 20
KS-1 Hestnes tunnel • Drill & blast • 3,1 km single tube tunnel, cross- section area 125m2 • Excavation volume, 420 000 sm3 − Hard rock, mainly granitic gneiss and amphibolite • Water & frost-protection; membrane and concrete lining 21
KS-2 Tangenvika railway bridge 22
Contract KS-2 Tangenvika railway bridge Preparatory works at KS-1 KS-2 KSÅ-3 SÅ-4 Hamar Kleverud Tangen Sørli Stange Åkersvika Hamar Espa From Espa to Furnesbakken 1800 m open landscape 1070 m bridge no. of large constructions: 2 23
Contract KS-2 Tangenvika railway bridge • Civil work - EPC contract • Contract basis: Norwegian total contract 2015 (NTK 15) • Procurement procedure: Competitive dialogue (Konkurransepreget dialog) − With the aim to: ‒ Focus and align project needs and goals in an early phase ‒ Make use of competence and technology in the market / Exploit innovative ideas and solutions ‒ Empower efficient project execution through common understanding of technical solutions and allocation of risk • Number of pre-qualified tenderers should preferably be between 3-5 • Planned schedule − Start prequalification Q4 (October) 2019 − Contract award Q4 (December) 2020 24
KS-2 Tangenvika railway bridge • Tangenvika railway bridge • Restructuring of local road • Civil work in open landscape • Rock cut approx. 250 000 sm3 • Fillings for abutment and embankments • Temporary quay facilities at northern side of Tangenvika bay • Wildlife crossing 25
KS-2 Tangenvika Railway bridge • Concrete bridge • Water depth of up to 50 m with 40 m layer of soils/subsoils above bedrock • Challenging foundation due to location and depths • Focus on increased degree of freedom in span-widths and piling method 26
KSÅ-3 Open landscape, incl. 2 stations 27
Contract KSÅ-3 Open landscape, incl. 2 stations Preparatory works at KS-1 KS-2 KSÅ-3 SÅ-4 Hamar Kleverud Tangen Sørli Stange Åkersvika Hamar Espa From Furnesbakken to Stange including Stange station 13 250 m open landscape 2 stations no. of large constructions: 7 28
Contract KSÅ-3 Open landscape, incl. 2 stations • Civil work - EPC contract • Contract basis: Norwegian total contract 2015 (NTK 15) • Procurement procedure: Negotiated procedure (Konkurranse med forhandling) • Number of pre-qualified tenderers should preferably be between 3-5 • Planned schedule − Start prequalification Q4 2020 − Contract award Q4 2021 29
KSÅ-3 • 13,3 km substructure including civil works at two stations, Tangen and Stange • Excavation and handling of approx. 1 500 000 sm3 rock and soils − Large capacity landfills close to site • “Greenfield” areas to Sørli • Close to existing railway from Sørli timber- terminal • Wildlife crossings 30
KSÅ-3 Tangen station • New 4-track Tangen station, 2 tracks to platform. • Parking areas 31
KSÅ-3 Stange station • New 3- track station situated at the same place as existing Stange station • Stange station shall be at full operation during construction. • Parking, bus and taxi areas 32
SÅ-4 Open landscape 33
Contract SÅ-4 Open landscape Preparatory works at KS-1 KS-2 KSÅ-3 SÅ-4 Hamar Kleverud Tangen Sørli Stange Åkersvika Hamar Espa From Stange to Åkersvika 9000 m open landscape no. of large constructions: 9 34
Contract SÅ-4 Open landscape • Civil work - EPC contract • Contract basis: Norwegian total contract 2015 (NTK 15) • Procurement procedure: Negotiated procedure (konkurranse med forhandling) • Number of pre-qualified tenderers should preferably be between 3-5 • Planned schedule − Start prequalification Q4 2020 − Contract award Q4 2021 35
SÅ-4 • 9 km civil works in open landscape • Excavation and handling of: − approx. 680 000 sm3 rock and soils − 72 000 sm3 of alum shale • Large landfill at Nesten/Skjerden • Approved landfill for disposal of alum shale close to site • 2 large culvert/ concrete tunnels • Restructuring of roads 36
SÅ-4 • Two large culverts/concrete tunnels • Deep cuttings in agricultural landscape 37
SÅ-4 Åkersvika and construction work • Permanent filling above existing track in Åkersvika – Ramsar area • New operational phase with temporary fillings • Restrictions in construction work during the breeding period for birds (April-May) • Permission from county governor granted before construction starts 38
Kleverud – Sørli - Åkersvika Niklas Marcussen Engineering manager Bane NOR Tender Conference June 5. 2019
KSÅ-6 & KSÅ-7 – Railway technique 40
Contract KSÅ-6 and KSÅ-7 Railway technique Preparatory works at KS-1 KS-2 KSÅ-3 SÅ-4 Hamar Kleverud Tangen Sørli Stange Åkersvika Hamar Espa KSÅ-6 Tracks and OCL KSÅ-7 Power supply and Telecom From Kleverud to Åkersvika 30 000 m railway no. of technical buildings: 19 41
Contract KSÅ-6/ KSÅ-7 Railway technique • Railway technique - Construction contract • Engineering – Integrated team with Bane NOR employees and consulting engineers • Contract basis construction contract: NS 8405 • Procurement procedure: Negotiated procedure • Number of pre-qualified tenderers should preferably be between 3-5 • Planned schedule Construction contract − Start prequalification Q3 or Q4 2021 − Contract award Q3 or Q4 2022 42
KSÅ-6 Railway technique electrical power/telecom • Power systems and installations: − 19 technical buildings − Two stations − All subsystems and components • Installation of emergency systems in the Hestnes tunnel • High voltage cables, 22kV • Public information systems and video surveillance 43
KSÅ-7 Railway technique Tracks/OCL Track works • Ballasted tracks • Installation of company provided items: − 65 000 m of tracks − 100 000 Sleepers − 36 turnouts • 300 000 m3 ballast Overhead contact line • Standard Bane NOR S25 overhead contact line system • Autotransformers 44
KSÅ-5 - Engineering contract • Engineering consultancy contract − Engineering of railway systems − Project support civil works − Manpower support to integrated team, Railway technique − Interface coordination 45
Ground conditions - site investigations • Geotechnical site investigations with more than 500 holes drilled along the planned track • Kleverud-Sørli - Good ground conditions for construction purposes. Visible rock or thin layers of topsoil • Sørli-Åkersvika - Hard moraine of varying depth above a soft type of rock. Stable soils for civil works • Focus on analysis – soil and rock 46
Ground conditions – Tangenvika • Comprehensive geotechnical site investigation program with 90 drilling points performed 2015/2016 • Stable barge ensure correct data • Use of "down-the hole” technology to verify bedrock in addition to geophysical investigation • Soil consist mud and hard moraine 47
Special conditions – Lake Mjøsa • There is a large difference between the regulated water levels in summer and winter in Lake Mjøsa. • Highest regulated water level HRV = 122.94 m • Lowest regulated water level LRV = 119.33 m • Discharge permit granted 48
Åkersvika wetland • Åkersvika is Norways first Ramsar site (1974)-one of the largest (4300 ha) and best-developed freshwater deltas in Norway. • Application for exemption from RAMSAR-regulations- Hedmark county – in good progress • Building new railway will have a footprint of 29 daa, of which 19 daa is permanent. 49
What do we think about risk • Main principles for allocation of risk in the contract will be: - The risk shall be carried by the party most familiar with the risk and best able to control it - Risk allocation in the contract shall be fair (balanced) and well-defined - Compensation format will be compiled to reflect the above • Risk mitigation is also applied by: - Reduced uncertainty through thorough geological and geophysical surveys - Test pile driving in Mjøsa by contractor, to be considered - Use of competitive dialogue for Tangenvika railway bridge - Environmental regulations; Several permits for environmental emissions in good progress • The compensation format will aim for neutral liquidity 50
Kleverud-Sørli-Åkersvika. Contract Summary Prequal. Q4.2019 Prequal. Q4.2019 EPC contract EPC contract Hamar Hamar KS-1 KS-2 Stange Stange Tunnel Bridge Tangen Tangen Civil Prequal. 2020 Prequal. 2020 Eidsvoll EPC contract EPC contract KSÅ-3 SÅ-4 Open landscape Open landscape Incl. 2 stations Prequal. 2021 Construction contract Railway KSÅ-6 Tracks and OCL systems Construction contract KSÅ-7 Electro and Tele 51
Kleverud-Sørli- Åkersvika Dovre Line – a part of InterCity • Reduced travel time • Increased capacity • 2 new stations • Project estimated to 12 billion NOK • Opening scheduled for 2026
Kleverud-Sørli-Åkersvika • For project information, please see Bane NOR’s home page: − www.banenor.no • Project home page: − www.banenor.no/Prosjekter/prosjekter/klev erud-sorli/ − www.banenor.no/Prosjekter/prosjekter/dovr ebanen/sorli-akersvika/ • Supplier contact: − Gro-Ane.Haarklou.Westbye@banenor.no 53
People to ask! Head of project Project manager Contract manager Engineering manager Manager Tunnel Geir Kvillum Gunnar Sletten Gro-Ane H. Westbye Niklas Marcussen Kjetil Bøyeie Enginering Manager land acqusition Quality advisor Manager Bridge Environ. advisor Thomas Nævestad Bjørn J. Sørum Anniken Tranberg Steinar Hognestad Trine M. Holm 54