GUIDE TO SET UP AN URBAN FARM ON HDB MULTI-STOREY CARPARK ROOFDECK - Sfa

 
CONTINUE READING
GUIDE TO SET UP AN URBAN FARM ON HDB MULTI-STOREY CARPARK ROOFDECK
Highlights
SFA aims for Singapore to produce 30% of its nutritional needs by 2030. Rooftop farms are one of the
solutions and SFA has worked with HDB to secure under-utilised HDB multi-storey car park (“MSCP”)
rooftop parking decks (the “Premise”) to be converted to increase the supply of space to meet farming
needs. SFA will be progressively appointing farm operators for the various sites.

If you are thinking of setting up an Urban Farm at a HDB MSCP rooftop parking deck, this guide will let
you have a better understanding of the procedures to follow, including information on the various
submissions, fees and timelines involved. This guide also introduces the government agencies
overseeing the necessary permits, should you wish to contact them to make specific enquiries.

The following agencies have contributed to this guide: Singapore Food Agency, Housing Development
Board, Building & Construction Authority, National Environment Agency, Public Utilities Board, Urban
Redevelopment Authority and Singapore Civil Defence Force.

Steps to set up an urban farm on MSCP Premise
1. Prospective MSCP rooftop farm operators will need to be appointed by way of tender. SFA has
   launched an open Tender on 12 May 2020
       a. Tender Documents are available on https://www.sfa.gov.sg/urban-farming and
          www.gebiz.gov.sg
       b. Interested parties shall Submit Tender on Gebiz by 9 June 2020, 4 pm. Please refer to
          https://www.gebiz.gov.sg/ptn/gtpregistration/signup.xhtml for registration as GeBIZ
          Trading Partners. (Note: If your company is not registered with ACRA or if you are an
          individual, your registration will take approximately 3 to 5 working days for verification
          and approval).
       c. Submission Information:
                i. Each tender submission shall be for a single MSCP Premise or a cluster of MSCP
                   Premises. If you wish to bid for more than one premise or cluster, please make
                   multiple tender submissions (i.e. 1 submission for 1 premise OR 1 submission for
                   1 cluster of premises).
               ii. Documents to be submitted:
                       1. Form of Tender
                       2. Tender Proposal Form and relevant supporting documents
                       3. Tenderer’s Information
                       4. Proof of payment for Tender Deposit
                                a. A tender deposit of Five Hundred Singapore Dollars (S$500/-)
                                    shall be included for each tender submission. Tenderers are to pay
                                    the tender deposit via internet bank transfer to the Singapore
                                    Food Agency to the following DBS Bank account number: 001-
                                    072102-0.
       d. Please adhere to the current COVID-19 Safe Distancing Measures for any visits made to
          the MSCP premises.

2. Tender will Close on 9 June 2020, 4 pm
      a. If your proposal is shortlisted, you may be contacted for clarifications.
3. Tender Award
      a. Tender results will be published on SFA website on Tender Award Day.
      b. Tender Award letters will be sent to Successful Tenderers via email.

4. Tenancy Agreement will be sent to Successful Tenderer 1 week after the Tender Award. Successful
   Tenderers will be required to execute the Tenancy Agreement and pay the Annual Rent, Annual
   Management fee and Security Deposit within 2 weeks from issuance of Tenancy Agreement. The
   amounts payable as indicated in the Tenancy Agreement are exclusive of Goods and Service Tax.
   Site will be handed over to the Successful Tenderer after Tenancy Agreement has been executed
   and all Payments are made.

5. Stamp Duty is payable to Inland Revenue Authority of Singapore within 14 days when Tenancy
   Agreement      is    signed.   For   computation      of   stamp     duty,    please  visit
   https://mytax.iras.gov.sg/ESVWeb/default.aspx?target=MSDCalculatorIntro.

6. The following are required submissions to the relevant authorities based on farming systems
   proposed. Successful Tenderers are required to engage a Professional Engineer or Registered
   Architect as Qualified Person (“QP”) to make proper plan submissions and obtain all the necessary
   written approvals from the relevant authorities before the commencement of construction or
   related works.

          Farming system 1:                              Farming System 2:
          Open systems, with minor non-structural        System with structures (ie. room, sheds,
          elements and installation of equipment (ie.    covered areas, greenhouse, containers,
          racking system which is open to sky)           polytunnel)

 SFA      Type: Plan Submission                          Type: Plan Submission

          Processing Time: Approximately Fourteen Processing Time: Approximately Fourteen (14)
          (14) Days                               Days

          Cost: NA                                       Cost: NA

          Documents required:                       Documents required:
             a) Layout Plan                            a) Layout Plan
             b) Section/ Elevation Plan                b) Section/ Elevation Plan
             c) Table showing breakdown of             c) Table    showing      breakdown     of
                Production and Ancillary and Uses.        Production and Ancillary and Uses.
             d) Farming systems and process details    d) Farming systems and process details

 HDB      Type: Plan Submission                          Type: Plan Submission

          Processing Time: Approximately Fourteen Processing Time: Approximately Fourteen (14)
          (14) Days                               Days

          Cost: NA                                       Cost: NA

          Documents required:                            Documents required:
a) Layout Plan                                  a) Layout Plan
          b) Section/ Elevation Plan                      b) Section/ Elevation Plan
          c) Table showing breakdown of                   c) Table showing breakdown of
             Production and Ancillary and Uses.              Production and Ancillary and Uses.
          d) Farming systems and process details          d) Farming systems and process details
          e) Artist Impression (if any)                   e) Artist Impression (if any)
          f) Floor plan showing the proposed              f) Floor plan showing the proposed
             layout and usage of the premises                layout and usage of the premises
          g) Clearances from all relevant                 g) Clearances from all relevant technical
             technical agencies including SCDF,              agencies including SCDF, NEA, BCA,
             NEA, BCA, PUB (can be submitted                 PUB (can be submitted later when
             later when obtained)                            obtained)

URA   Type: Change of Use Submission to URA’s Type: Addition and Alteration Submission to
      Development Control Group               URA’s Development Control Group

      Submission platform: CoreNet (for QP Submission platform: CoreNet
      submission) or GoBusiness Licensing Portal
      (for non-QP submission)

      Type of works involved                          Type of works involved
      Pure change of use of space, erection of        Erection of rooms / sheds / covered areas (e.g.
      minor non-structural elements (including        vegetable polytunnels, greenhouses, container
      internal partitioning), and installation of     farms), structural elements (e.g. columns,
      equipment (e.g. generators, netting, open-to-   structural walls, and/or involves an increase in
      sky racking systems)                            Gross Floor Area (GFA)

      Processing Time: Approximately Ten (10) Processing Time: Approximately Twenty (20)
      working days                            working days

      Cost: $500 (subject to prevailing GST)          Cost: $3500 + $600 per affected storey (subject
                                                      to prevailing GST)

      Documents Required:                          Documents Required:
         a. Written endorsement from lessor           a. Written endorsement from lessor
         b. Authorisation letter from owner /         b. Authorisation letter from owner /
            lessee of the land to authorise QP to        lessee of the land to authorise QP to
            make the application                         make the application
         c. Location plan indicating where the        c. CAD/BIM drawings for propose
            works are located within the                 development
            development                                  Clearances from all relevant technical
         d. Floor plan showing the proposed              agencies including SCDF, NEA, BCA,
            layout and usage of the premises             PUB
         e. Clearances from all relevant technical    d. Payment of processing fees
            agencies including SCDF, NEA, BCA,
            PUB
         f. Payment of processing fees
SCDF   Type: Change of Use/Addition and Alteration (A&A) Submission to SCDF Fire Safety
       Department

       Processing Time: Five (5) working days upon receipt of fee payment. Five (5) working days for
       TFP/FSC application

       Cost: S$90 per storey for change of Use/A&A work, $160/100 m2 for any roof over
       Documents required:
           a) Layout Plan
           b) Section/ Elevation Plan
           c) Site plan

NEA    Type: Plan Submission         (Development Type: Plan Submission (Development Control/
       Control/ Building Plan)                    Building Plan)

       Processing Time: Seven (7) working days for Processing Time: Seven (7) working days for
       each written direction issued for non- each written direction issued for non-
       compliance                                  compliance

       Cost: NA                                      Cost: NA

       Documents required:                            Documents required:
          a) Cover letter clarifying scope of work,      a) Cover letter clarifying scope of work,
             farming process flow, work activities          farming process flow, work activities as
             as well as chemicals use/storage               well as chemicals use/storage
          b) One set of building plans including         b) One set of building plans including site
             site plan, floor plans layout, sectional       plan, floor plans layout, sectional,
             and elevation plans complying with             elevation and roof plans complying
             NEA requirements as specified in the           with NEA requirements specified in the
             Code of Practice on Environmental              Code of Practice on Environmental
             Health (COPEH) and Code of Practice            Health (COPEH) and Code of Practice
             for Pollution Control (SS593:2013).            for Pollution Control (SS593:2013).
          c) Any waiver application/approval by          c) Any waiver application/approval by
             NEA                                            NEA
          d) Letter of Undertaking (LOU) by              d) Letter of Undertaking (LOU) by
             developer/Owner/Operator of the                developer/Owner/Operator of the
             farms to NEA (if required)                     farms to NEA (if required)

BCA    QP to enquire whether submission is required Type: Building plan and structural plan
       (or      not)      by      emailing       to
       bca_enquiry@bca.gov.sg. If submission is Processing Time: 7 to 14 working days for each
       required, please refer to next column (on submission
       Farming system 2)
                                                    Cost:
       Processing Time: 3 working days              a) $400 per storey for works without increase
                                                    in statistical gross floor area (SGFA)
       Cost: NA                                     b) $400 per storey + $300 per 100m2 for 1st
                                                    2500m2 of SGFA. For subsequent SGFA, it is
       Documents required:                          $240 per 100m2
a) Layout Plan
         b) Section/ Elevation Plan                   Documents required:
      Farming systems and process details
                                                      Building Plan submission:
                                                          a) URA planning approval
                                                          b) Site and architectural layout Plans
                                                          c) Architectural section/ Elevation Plans
                                                          d) Farming systems and process details
                                                          e) Technical agencies’ such as SCDF, NEA,
                                                              PUB etc clearance letters

                                                      Structural Plan submission:
                                                          a) Structural plans
                                                          b) Application for permit to commence
                                                              structural work

PUB   Type: Development Control (DC)                  Type: Development Control (DC)

      Processing Time: Fourteen (14) working days     Processing Time: Fourteen (14) working days

      Cost: NA                                        Cost: NA

      Documents required:                          Documents required:
         a. Cover letter indicating the scope of      a. Cover letter indicating the scope of
            works for the project/submission             works for the project/submission
         b. Certified plans by QP (Site Plans,        b. Certified plans by QP (Site Plans, Floor
            Floor Plans, Sections/Elevations)            Plans, Sections/Elevations)
         c. e-Submission Forms endorsed by QP         c. e-Submission Forms endorsed by QP or
            or PE                                        PE
         d. Relevant     technical    calculations    d. Relevant      technical     calculations
            endorsed by the appropriate QP/PE            endorsed by the appropriate QP/PE
         e. Endorsement                         by    e. Endorsement by owner/developer/QP
            owner/developer/QP

      Note: Development plans which are eligible      Note: Development plans which are eligible for
      for Simplified Submission Scheme do not         Simplified Submission Scheme do not need to
      need to obtain DP/TOP/CSC Clearance after       obtain DP/TOP/CSC Clearance after carrying
      carrying out a DC lodgement. Please refer to    out a DC lodgement. Please refer to PUB’s QP
      PUB’s QP Portal for more info on this Scheme.   Portal for more info on this Scheme.

      Type: Detailed Plan (DP)                        Type: Detailed Plan (DP)

      Processing Time: Fourteen (14) working days     Processing Time: Fourteen (14) working days

      Cost: NA                                        Cost: NA

      Documents required:                   Documents required:
      Refer to the submission guides at Refer to the submission guides at
      https://www.pub.gov.sg/compliance for https://www.pub.gov.sg/compliance for
      Detailed Plan submission on:          Detailed Plan submission on:
          a. Drainage (Minor Projects)          a. Drainage (Minor Projects)
b. Sanitary & Sewerage                           b. Sanitary & Sewerage

          Type: Water Supply - Notification of Water Type: Water Supply - Notification of Water
          Service Installation (WSI)                 Service Installation (WSI)

          Processing Time: Twelve (12) working days         Processing Time: Twelve (12) working days

          Cost: NA                                          Cost: NA

          Documents required:                           Documents required:
               a. Layout / Floor plan                       a. Layout / Floor plan
               b. Schematic Drawing of Water                b. Schematic      Drawing of      Water
                   Reticulation System                         Reticulation System
          For the installation of a PUB water submeter,     c. For the installation of a PUB water
          QP shall include a letter from the building          submeter, QP shall include a letter
          owner/management corporation indicating              from             the          building
          no objection for the installation of PUB             owner/management          corporation
          submeter.                                            indicating no objection for the
                                                               installation of PUB submeter.

(Note: Toilet facilities are not allowed on the HDB MSCP)

Other submission required:

    For any trade effluent to be discharged to public sewer:

    -   Trade effluent discharged into a public sewer must comply with the Sewerage and Drainage
        Act and the discharged standards stipulated in Sewerage and Drainage (Trade Effluent)
        Regulations. Further information about this requirement can be found at:
        http://www.pub.gov.sg/compliance/industry/codeofpractice.

    -   Before operation, written approval from PUB is required for discharge of trade effluent into
        the public sewerage system. QP can apply for approval via the LicenseOne Portal at:
        https://www.gobusiness.gov.sg/licenses.

    For rainwater harvesting:

    -   If there are plans to develop a system to collect rainwater for non-potable use, please make
        a separate application to PUB. Further information can be found online, at:
        https://www.pub.gov.sg/savewater/atwork/alternatesources

    -   The collected rainwater is only allowed for non-potable use within the Successful Tenderer’s
        own premises. Any transaction or sale of the collected rainwater by the Successful Tenderer
        to other parties for use at other premises is not allowed.

7. After all relevant agencies’ approval are obtained, construction and related works can commence.
   Please adhere to these guidelines for any proposed works at the MSCP Premise.

            a) The proposed works and all daily operations, equipment and fittings shall not affect
               the safety aspects of the building, including structural safety, fire safety, operational
               safety, etc. Where measures need to be taken arising from the works and operations,
               this is to be done at the Successful Tenderer’s own cost
b) The proposed works shall not affect the vehicular access/ driveways/ parking lots and
               operational requirements to serve the existing HDB precincts. The consultant/
               contractor is also required to ensure motorists and pedestrians safety.

            c) Ensure that the proposed works will not cause ground settlement and all protective
               measures are to be implemented to ensure the vehicular road access/driveway is not
               adversely affected by the proposed works. No dumping or stockpiling of building
               materials, equipment etc. are allowed in HDB car parks and access.

            d) At all times, the function of the driveways should not be compromised e.g. for refuse
               collection, fire-fighting etc. Motorists need to be able to gain access to HDB car parks
               at all times.

            e) Necessary measures must be put in place to ensure public safety at all times and
               warning signage must be erected adequately. HDB Branch must be kept informed of
               the work schedule and details once available especially when it is approaching HDB’s
               car parks / access roads.

            f)    For car parks that have been implemented with the Electronic Parking System (EPS),
                  should any of the EPS equipment be affected by the proposed works, the consultant/
                  contractor is to bear all costs relating to the relocation/ replacement of the equipment
                  (e.g. relocation/diversion of EPS, loss of parking revenue, replacement of EPS parts,
                  etc.). The consultant/contractor is also required to make arrangement with HDB’s
                  appointed EPS service provider on the relocation/ replacement works. Should the EPS
                  contract be terminated prior to the contract end date due to the proposed works,
                  HDB will seek compensation for the losses and expenses due to the early termination
                  of the contract period.

8. Please Obtain Temporary Occupation Permit or Certificate of Statutory Completion (“TOP/CSC”)
   approval before commencement of operations on the urban farm, and submit proof of TOP and
   CSC to SFA and HDB.

Table A: Submissions required for TOP/CSC:

 Agencies        Documents Required
 BCA             TOP/CSC Clearance
                 Processing Time: Fourteen (14) working days
                 Cost: NA (included in plan submission fees)

                 Documents Required:
                 a. QP Declaration Form
                 b. Certificate of Supervision of Building Works
                 c. Certificate of Supervision of Lightning Protection System and related Test Reports and As-
                     built drawings)
                 d. Builder's Certificate of Completion of Building Works
                 e. Rectification/ Closure Report on items from Written Advice issued after TOP inspection.
                 f. List of the various types of safety barriers installed on–site and their structural approvals
                     (Annex A).
                 g. Listing of the installation of engineered facade (Cladding, curtain wall, screen wall green
                     wall) (Annex A)
h. QP declaration letter for compliance to the following clauses:
               i. Clause H.3.5 [Glass Barrier]
              ii. Clause N2.1 [Use of glass at height]
             iii. Clause P.2.1 [Daylight Reflectance]. To provide the value of the daylight reflectance
                  for the material (supplier’s specification) used for this development.
        i. QP declaration letter that the as-built height of the building in the development does not
           exceed stipulated AMSL
        j. DSTA clearance (where applicable)
        k. CAAS clearance (where applicable)
SCDF   Temporary Fire Permit

URA    TOP/CSC Clearance
       (Required for Addition and Alteration Submissions only, declaration to URA is not needed for
       Change of Use applications)

       Processing Time: Approximately Five (5) working days

       Cost: NA

       Documents required:
          a. Declaration to be submitted by QP via CoreNet declaring that the development has
             been built in accordance with the WP Approved Plans

PUB    TOP/CSC Clearance

       Processing Time: Fourteen (14) working days

       Cost: NA

       Documents required:
          a. Certified as-built plans by QP (Site Plans, Floor Plans, Sections/Elevations)
          b. As-built survey plans
          c. e-Submission Forms endorsed by QP or PE
          d. Relevant as-built technical calculations endorsed by the appropriate QP/PE
          e. Any documents as required for TOP/CSC submissions as listed in Code of Practice on
             Surface Water Drainage, Code of Practice on Sewerage and Sanitary Works, or e-
             Submission Forms. Refer to the submission guides at
             https://www.pub.gov.sg/compliance/qualifiedpersonsportal/quicksubmissionguides

       Type: Water Supply - Water Service Installation (WSI) Works

       Processing Time: Three (3) days

       Cost: NA

       Documents required:
       For water supply to be turned on, a Certificate of Satisfactory Completion of WSI Works
       certifying that the works are completed in accordance with the PUB’s requirements including
       the Public Utilities (Water Supply) Regulations, Singapore Standard 636 – Code of Practice for
       Water Services, other Authorities’ requirements and other statutory requirements.
NEA           TOP/CSC Clearance

               Processing Time: Seven (7) working days for each written direction

               Cost: NA

               Documents required:
                  a) Cover letter clarifying scope of work, farming process flow, work activities as well as
                     chemicals use/storage
                  b) One set of building plans including site plan, floor plans layout, sectional and elevation
                     plans complying with NEA requirements as specified in the Code of Practice on
                     Environmental Health (COPEH) and Code of Practice for Pollution Control
                     (SS593:2013).
                  c) Noise assessment report to ensure compliance to Boundary Noise Limits for Air
                     Conditioning and Mechanical Ventilation Systems in Non-Industrial Buildings
                  d) Any waiver approval by NEA
                  e) Letter of Undertaking (LOU) by developer/Owner/Operator of the farms

Table B: Submissions required for CSC:

 Agencies      Documents Required
 SCDF          Fire Safety Certificate
 NEA           TOP/CSC Clearance
 PUB           TOP/CSC Clearance

(Note: For direct CSC application, all the documents stated in Table A and B above are to be
submitted)

Helpful Tips
    1. For works requiring a QP, consider engaging someone who is familiar with and understands
       farm operations/ needs

    2. Appoint a competent licenced builder to ensure that building works are built in accordance to
       approved plans and are code compliant. This will minimise issues during post-construction
       inspections.

Submissions to NEA

    3. To facilitate NEA submission, you are advised to provide the following information:
           a. Tabulation of refuse output and clarify how each generated waste stream will be
                stored, transported and disposed;
           b. Farming process activities, proposed working hours, type of chemicals/fertilisers
                used;
           c. Clarify mitigation measures to ensure that the proposed use will not cause odour,
                noise or pollution issues to the premises and its vicinity; and
           d. Ensure no roof gutters are installed and avoid features that may result in water
                stagnation and become potential breeding habitat for mosquitoes.
e. To declare upfront any requirements that are not able to comply with the Code of
                Practice on Environmental Health (COPEH) and the Code of Practice for Pollution
                Control SS593:2013.

    4. If you have a specific question related to your submitted farm plans, please contact the
       NEA processing officer assigned to your project. Otherwise, please submit a Building Plan
       Consultation                                  Request                                  at
       https://www.eportal.nea.gov.sg/app/#/applications/create/building-plan-consultation-
       request or drop an email to DCLD_Consultation@nea.gov.sg for all other enquiries.

Submissions to URA

    5. Waiver application process for URA’s Addition and Alteration submissions via CoreNet:
          a. QP submits a waiver on the CORENET platform, indicating the specific URA condition
              / guideline to be waived
          b. The QP will have to provide the reasons for the deviation, consider the potential
              impact on the amenity of surrounding developments and streetscape, and propose
              appropriate mitigating measures.
          c. The request will be considered on a case-by-case basis and a reply will typically be
              provided within fifteen (15) working days.

Submissions to PUB

    6. Check if your development plans are eligible for PUB’s Simplified Submission Scheme. This will
       reduce the processing time.

    7. Check your BIM model using PUB’s e-Plan Checker for compliance with PUB's requirements
       before making your submission to CORENET. This reduces your clearance time provided the
       modelling submitted has been reviewed and cleared of all non-compliances. For more info on
       PUB's BIM e-Checker, please refer to the following link at https://pubbimchecker.com.sg

    8. If you have questions about your submission, you can book a consultation or find out the
       status      of     submission      through       our     QP      Portal    E-services      at
       https://www.pub.gov.sg/compliance/qualifiedpersonsportal/eservices.          For      further
       assistance, please call PUB Building Plan Unit (BPU) hotline at 67313512 during office hours
       between 9am to 5pm, or email to pub_bpu@pub.gov.sg.

Submissions to BCA

9. Structural design standards to be used are indicated in the BCA’s Approved Document, which can be
   consulted here:
       https://www.bca.gov.sg/Publications/BuildingControlAct/others/Approveddocument.pdf

10. The safety of occupants is paramount. For safety reasons, requests for partial TOP (i.e. splitting of the
    development plot to allow for TOP to be received earlier for part of the site) will not be accepted if
    there are on-going structural works and/or crane hoisting works within the land site.

11. The Code on Envelope Thermal Transfer Value (ETTV) calls for sufficient thickness of glass to prevent
    energy loss if a greenhouse is air-conditioned. Alternatively, a developer can provide energy saving
    mitigation measures such as solar panels to make up for energy loss from the use of thinner glass.
12. Please refer to SS 555: 2019 for design and technical compliance to Lightning Protection System.

Maintenance Matters

The following maintenance matters are also highlighted for attention:-

    a) The Successful Tenderer will be responsible for taking over the property in as-is condition, and
       maintenance of the space within the tenanted boundary. Generally, the tenanted boundary
       is pegged to the bottom of the vehicular ramp serving the parking deck, but it will exclude
       shared building systems.

    b) The Successful Tenderer shall apply for and bear all costs for installation of water and electrical
       sub-meters. The tenant must also open its own utilities account and cover all related charges
       incurred for supply of water, sanitation, refuse removal, electricity usage etc. The utilities
       account will need to commence together with the tenancy commencement date, even if there
       is any concessionary rent-free period granted.

    c) The Successful Tenderer will be held responsible for the maintenance of the site, e.g. cleaning,
       pest control, proper refuse removal from site to the bin centre, and fulfil all other
       maintenance responsibilities as stated in the Tenancy Agreement.
Contact Information

For Questions relating to tender or site:
 Agencies
 SFA                Landsales@sfa.gov.sg

 HDB               hdbcarparks@mailbox.hdb.gov.sg

For Questions relating to Agencies’ submission requirements:
 Agencies           Email Address

 URA               URA_DCD@ura.gov.sg

 NEA               DCLD_Consultation@nea.gov.sg

 BCA               bca_enquiry@bca.gov.sg

 PUB               pub_bpu@pub.gov.sg

 SCDF              scdf_qp_consultant@scdf.gov.sg
Urban Farm Development Approvals – HDB Multi-Storey Carpark

                                                                                                                                                                        START
                                                                                                                                           START                                           FARM
                                                                          START APPROVALS                       START STRUCTURAL       ARCHITECTURAL                   TOP/CSC
TENDER LAUNCH          TENDER AWARDED                                      CONCURRENTLY                              WORKS                                           APPLICATION         OPERATIONS
                                                                                                                                          WORKS
         4 weeks        Est. 4 weeks                 Est. 6- 8 weeks                        Est. 3 to 6 weeks                                                        Est. 2 to 4 weeks

                                                                                                                            STRUCTURAL               ARCHITECTURAL
        SPACE ACQUISITION STAGE                                           PLANNING STAGE                                                                              COMPLETION
                                                                                                                              WORKS                     WORKS

                         SFA &
         Tenderer                                                                                                                                                    SFA Farm
                         HDB
         Submit
                         Tender                                                                                                                                      License
         Tender
                         Evaluation

                                         SFA & HDB            URA                                     BCA
                                                                                    BCA                                  BCA
                                         Plan Clearance       Change of Use/                          Permit to
                                                                                    Structural                           BP Approval
                                                              A&A works             Plan              Commence Works
                                                                                                                                                                     SCDF TFP/FSC
                                                                                    SCDF
                                                                                    Change of Use/                                                                   BCA TOP/CSC
                                                                                    A&A works
                                                                                                                                                                      NEA
                                                                                                                           NEA Environmental Health
        This diagram highlights the main steps in setting up a farm on              NEA Environmental Health                                                           PUB
        HDB Multi-storey Carpark Premises. Use it to help you plan                                                         PUB Drainage & Sewerage
        your business and cash flow.                                                                                                                                   URA
                                                                                    PUB Drainage & Sewerage
        Please note that this is a general overview, for scenario where                                                    SCDF Fire Safety Requirements              CAAS
        structural works are required. Your experience of the process               CAAS (where applicable)
        may vary, depending on your specific circumstances. For
                                                                                                                                                                       DSTA
        example, the completeness of an application made, the time                                                                 BUILDING PLAN (BP)
                                                                                    DSTA (where applicable)
        intervals between an agency’s correspondence and the
        subsequent application by your appointed Qualified Person                                                                                                        TOP/CSC
        (QP) are contributing factors to the actual timeline of your                 DEVELOPMENT CONTROL                                                                Clearances
        farm’s development.                                                                  (DC)
You can also read