GUIDE TO SET UP AN URBAN FARM ON HDB MULTI-STOREY CARPARK ROOFDECK
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
GUIDE TO SET UP AN URBAN FARM ON HDB MULTI-STOREY CARPARK ROOFDECK Highlights SFA aims for Singapore to produce 30% of its nutritional needs by 2030. Rooftop farms are one of the solutions and SFA has worked with HDB to secure under-utilised HDB multi-storey car park (“MSCP”) rooftop parking decks (the “Premise”) to be converted to increase the supply of space to meet farming needs. SFA will be progressively appointing farm operators for the various sites. If you are thinking of setting up an Urban Farm at a HDB MSCP rooftop parking deck, this guide will let you have a better understanding of the procedures to follow, including information on the various submissions, fees and timelines involved. This guide also introduces the government agencies overseeing the necessary permits, should you wish to contact them to make specific enquiries. The following agencies have contributed to this guide: Singapore Food Agency, Housing Development Board, Building & Construction Authority, National Environment Agency, Public Utilities Board, Urban Redevelopment Authority and Singapore Civil Defence Force. Steps to set up an urban farm on MSCP Premise 1. Prospective MSCP rooftop farm operators will need to be appointed by way of tender. SFA has launched an open Tender on 23 Feb 2021 a. Tender Documents are available on https://www.sfa.gov.sg/urban-farming and www.gebiz.gov.sg b. Interested parties shall Submit Tender on Gebiz by 23 Mar 2021, 4 pm. Please refer to https://www.gebiz.gov.sg/ptn/gtpregistration/signup.xhtml for registration as GeBIZ Trading Partners. (Note: If your company is not registered with ACRA or if you are an individual, your registration will take approximately 3 to 5 working days for verification and approval). c. Submission Information: i. Each tender submission shall be for a single MSCP Premise or a cluster of MSCP Premises. If you wish to bid for more than one premise or cluster, please make multiple tender submissions (i.e. 1 submission for 1 premise OR 1 submission for 1 cluster of premises). ii. Documents to be submitted: 1. Form of Tender 2. Tender Proposal Form and relevant supporting documents 3. Tenderer’s Information 4. Proof of payment for Tender Deposit a. A tender deposit of Five Hundred Singapore Dollars (S$500/-) shall be included for each tender submission. Tenderers are to pay the tender deposit via internet bank transfer to the Singapore Food Agency to the following DBS Bank account number: 001- 072102-0. d. Please adhere to the current COVID-19 Safe Distancing Measures for any visits made to the MSCP premises. 2. Tender will Close on 23 Mar 2021, 4 pm a. If your proposal is shortlisted, you might be contacted for clarifications. 1
3. Tender Award a. Tender results will be published on SFA website once the tender has been awarded. b. Tender Award letters will be sent to Successful Tenderers via email. 4. Successful Tenderers will be required to execute the Tenancy Agreement and pay the Annual Rent, Annual Management fee and Security Deposit within 2 weeks from SFA’s notification. The amounts payable as indicated in the Tenancy Agreement are exclusive of Goods and Service Tax. Site will be handed over to the Successful Tenderer after Tenancy Agreement has been executed and all Payments are made. 5. Stamp Duty is payable to Inland Revenue Authority of Singapore within 14 days when Tenancy Agreement is signed. For computation of stamp duty, please visit https://mytax.iras.gov.sg/ESVWeb/default.aspx?target=MSDCalculatorIntro. 6. The following are required submissions to the relevant authorities based on farming systems proposed. Successful Tenderers are required to engage a Professional Engineer or Registered Architect as Qualified Person (“QP”) to make proper plan submissions and obtain all the necessary written approvals from the relevant authorities before the commencement of construction or related works. Farming system 1: Farming System 2: Open systems, with minor non-structural System with structures (ie. room, sheds, elements and installation of equipment (ie. covered areas, greenhouse, containers, racking system which is open to sky) polytunnel) SFA Type: Plan Submission Type: Plan Submission Processing Time: Approximately Fourteen Processing Time: Approximately Fourteen (14) (14) Days Days Cost: NA Cost: NA Documents required: Documents required: a) Layout Plan a) Layout Plan b) Section/ Elevation Plan b) Section/ Elevation Plan c) Table showing breakdown of c) Table showing breakdown of Production and Ancillary and Uses. Production and Ancillary and Uses. d) Farming systems and process details d) Farming systems and process details HDB Type: Plan Submission Type: Plan Submission Processing Time: Approximately Fourteen Processing Time: Approximately Fourteen (14) (14) Days Days Cost: NA Cost: NA Documents required: Documents required: a) Layout Plan a) Layout Plan b) Section/ Elevation Plan b) Section/ Elevation Plan 2
c) Table showing breakdown of c) Table showing breakdown of Production and Ancillary and Uses. Production and Ancillary and Uses. d) Farming systems and process details d) Farming systems and process details e) Artist Impression (if any) e) Artist Impression (if any) f) Floor plan showing the proposed f) Floor plan showing the proposed layout and usage of the premises layout and usage of the premises g) Clearances from all relevant g) Clearances from all relevant technical technical agencies including SCDF, agencies including SCDF, NEA, BCA, NEA, BCA, PUB (can be submitted PUB (can be submitted later when later when obtained) obtained) URA Type: Change of Use Submission to URA’s Type: Addition and Alteration Submission to Development Control Group URA’s Development Control Group Submission platform: CoreNet (for QP Submission platform: CoreNet submission) or GoBusiness Licensing Portal (for non-QP submission) Type of works involved Type of works involved Pure change of use of space, erection of Erection of rooms / sheds / covered areas (e.g. minor non-structural elements (including vegetable polytunnels, greenhouses, container internal partitioning), and installation of farms), structural elements (e.g. columns, equipment (e.g. generators, netting, open-to- structural walls, and/or involves an increase in sky racking systems) Gross Floor Area (GFA) Processing Time: Approximately Ten (10) Processing Time: Approximately Twenty (20) working days working days Cost: $500 (subject to prevailing GST) Cost: $3500 + $600 per affected storey (subject to prevailing GST) Documents Required: Documents Required: a. Written endorsement from lessor a. Written endorsement from lessor b. Authorisation letter from owner / b. Authorisation letter from owner / lessee of the land to authorise QP to lessee of the land to authorise QP to make the application make the application c. Location plan indicating where the c. CAD/BIM drawings for propose works are located within the development development Clearances from all relevant technical d. Floor plan showing the proposed agencies including SCDF, NEA, BCA, layout and usage of the premises PUB e. Clearances from all relevant technical d. Payment of processing fees agencies including SCDF, NEA, BCA, PUB f. Payment of processing fees SCDF Type: Change of Use/Addition and Alteration (A&A) Submission to SCDF Fire Safety Department 3
Processing Time: Five (5) working days upon receipt of fee payment. Five (5) working days for TFP/FSC application Cost: S$90 per storey for change of Use/A&A work, $160/100 m2 for any roof over Documents required: a) Layout Plan b) Section/ Elevation Plan c) Site plan NEA Type: Plan Submission (Development Type: Plan Submission (Development Control/ Control/ Building Plan) Building Plan) Processing Time: Seven (7) working days for Processing Time: Seven (7) working days for each written direction issued for non- each written direction issued for non- compliance compliance Cost: NA Cost: NA Documents required: Documents required: a) Cover letter clarifying scope of work, a) Cover letter clarifying scope of work, farming process flow, work activities farming process flow, work activities as as well as chemicals use/storage well as chemicals use/storage b) One set of building plans including b) One set of building plans including site site plan, floor plans layout, sectional plan, floor plans layout, sectional, and elevation plans complying with elevation and roof plans complying NEA requirements as specified in the with NEA requirements specified in the Code of Practice on Environmental Code of Practice on Environmental Health (COPEH) and Code of Practice Health (COPEH) and Code of Practice for Pollution Control (SS593:2013). for Pollution Control (SS593:2013). c) Any waiver application/approval by c) Any waiver application/approval by NEA NEA d) Letter of Undertaking (LOU) by d) Letter of Undertaking (LOU) by developer/Owner/Operator of the developer/Owner/Operator of the farms to NEA (if required) farms to NEA (if required) BCA QP to enquire whether submission is required Type: Building plan and structural plan (or not) by emailing to bca_enquiry@bca.gov.sg. If submission is Processing Time: 7 to 14 working days for each required, please refer to next column (on submission Farming system 2) Cost: Processing Time: 3 working days a) $400 per storey for works without increase in statistical gross floor area (SGFA) Cost: NA b) $400 per storey + $300 per 100m2 for 1st 2500m2 of SGFA. For subsequent SGFA, it is Documents required: $240 per 100m2 a) Layout Plan b) Section/ Elevation Plan Documents required: Farming systems and process details 4
Building Plan submission: a) URA planning approval b) Site and architectural layout Plans c) Architectural section/ Elevation Plans d) Farming systems and process details e) Technical agencies’ such as SCDF, NEA, PUB etc clearance letters Structural Plan submission: a) Structural plans b) Application for permit to commence structural work PUB Type: Development Control (DC) Type: Development Control (DC) Processing Time: Fourteen (14) working days Processing Time: Fourteen (14) working days Cost: NA Cost: NA Documents required: Documents required: a. Cover letter indicating the scope of a. Cover letter indicating the scope of works for the project/submission works for the project/submission b. Certified plans by QP (Site Plans, b. Certified plans by QP (Site Plans, Floor Floor Plans, Sections/Elevations) Plans, Sections/Elevations) c. e-Submission Forms endorsed by QP c. e-Submission Forms endorsed by QP or or PE PE d. Relevant technical calculations d. Relevant technical calculations endorsed by the appropriate QP/PE endorsed by the appropriate QP/PE e. Endorsement by e. Endorsement by owner/developer/QP owner/developer/QP Note: Development plans which are eligible Note: Development plans which are eligible for for Simplified Submission Scheme do not Simplified Submission Scheme do not need to need to obtain DP/TOP/CSC Clearance after obtain DP/TOP/CSC Clearance after carrying carrying out a DC lodgement. Please refer to out a DC lodgement. Please refer to PUB’s QP PUB’s QP Portal for more info on this Scheme. Portal for more info on this Scheme. Type: Detailed Plan (DP) Type: Detailed Plan (DP) Processing Time: Fourteen (14) working days Processing Time: Fourteen (14) working days Cost: NA Cost: NA Documents required: Documents required: Refer to the submission guides at Refer to the submission guides at https://www.pub.gov.sg/compliance for https://www.pub.gov.sg/compliance for Detailed Plan submission on: Detailed Plan submission on: a. Drainage (Minor Projects) a. Drainage (Minor Projects) b. Sanitary & Sewerage b. Sanitary & Sewerage 5
Type: Water Supply - Notification of Water Type: Water Supply - Notification of Water Service Installation (WSI) Service Installation (WSI) Processing Time: Twenty-one (21) working Processing Time: Twenty-one (21) working days days Cost: NA Cost: NA Documents required: Documents required: a. Layout / Floor plan a. Layout / Floor plan b. Schematic Drawing of Water b. Schematic Drawing of Water Reticulation System Reticulation System For the installation of a PUB water submeter, c. For the installation of a PUB water QP shall include a letter from the building submeter, QP shall include a letter owner/management corporation indicating from the building no objection for the installation of PUB owner/management corporation submeter. indicating no objection for the installation of PUB submeter. (Note: Toilet facilities are not allowed on the HDB MSCP) Other submission required: For any trade effluent to be discharged to public sewer: - Trade effluent discharged into a public sewer must comply with the Sewerage and Drainage Act and the discharged standards stipulated in Sewerage and Drainage (Trade Effluent) Regulations. Further information about this requirement can be found at: http://www.pub.gov.sg/compliance/industry/codeofpractice. - Before operation, written approval from PUB is required for discharge of trade effluent into the public sewerage system. QP can apply for approval via the LicenseOne Portal at: https://www.gobusiness.gov.sg/licenses. For rainwater harvesting: - If there are plans to develop a system to collect rainwater for non-potable use, please make a separate application to PUB. Further information can be found online, at: https://www.pub.gov.sg/savewater/atwork/alternatesources - The collected rainwater is only allowed for non-potable use within the Successful Tenderer’s own premises. Any transaction or sale of the collected rainwater by the Successful Tenderer to other parties for use at other premises is not allowed. 7. After all relevant agencies’ approval are obtained, construction and related works can commence. Please adhere to these guidelines for any proposed works at the MSCP Premise. a) The proposed works and all daily operations, equipment and fittings shall not affect the safety aspects of the building, including structural safety, fire safety, operational safety, etc. Where measures need to be taken arising from the works and operations, this is to be done at the Successful Tenderer’s own cost 6
b) The proposed works shall not affect the vehicular access/ driveways/ parking lots and operational requirements to serve the existing HDB precincts. The consultant/ contractor is also required to ensure motorists and pedestrians safety. c) Ensure that the proposed works will not cause ground settlement and all protective measures are to be implemented to ensure the vehicular road access/driveway is not adversely affected by the proposed works. No dumping or stockpiling of building materials, equipment etc. are allowed in HDB car parks and access. d) At all times, the function of the driveways should not be compromised e.g. for refuse collection, fire-fighting etc. Motorists need to be able to gain access to HDB car parks at all times. e) Necessary measures must be put in place to ensure public safety at all times and warning signage must be erected adequately. HDB Branch must be kept informed of the work schedule and details once available especially when it is approaching HDB’s car parks / access roads. f) For car parks that have been implemented with the Electronic Parking System (EPS), should any of the EPS equipment be affected by the proposed works, the consultant/ contractor is to bear all costs relating to the relocation/ replacement of the equipment (e.g. relocation/diversion of EPS, loss of parking revenue, replacement of EPS parts, etc.). The consultant/contractor is also required to make arrangement with HDB’s appointed EPS service provider on the relocation/ replacement works. Should the EPS contract be terminated prior to the contract end date due to the proposed works, HDB will seek compensation for the losses and expenses due to the early termination of the contract period. 8. Please Obtain Temporary Occupation Permit or Certificate of Statutory Completion (“TOP/CSC”) approval before commencement of operations on the urban farm, and submit proof of TOP and CSC to SFA and HDB. Table A: Submissions required for TOP/CSC: Agencies Documents Required BCA TOP/CSC Clearance Processing Time: Fourteen (14) working days Cost: NA (included in plan submission fees) Documents Required: a. QP Declaration Form b. Certificate of Supervision of Building Works c. Certificate of Supervision of Lightning Protection System and related Test Reports and As- built drawings) d. Builder's Certificate of Completion of Building Works e. Rectification/ Closure Report on items from Written Advice issued after TOP inspection. f. List of the various types of safety barriers installed on–site and their structural approvals (Annex A). g. Listing of the installation of engineered facade (Cladding, curtain wall, screen wall green wall) (Annex A) h. QP declaration letter for compliance to the following clauses: 7
i. Clause H.3.5 [Glass Barrier] ii. Clause N2.1 [Use of glass at height] iii. Clause P.2.1 [Daylight Reflectance]. To provide the value of the daylight reflectance for the material (supplier’s specification) used for this development. i. QP declaration letter that the as-built height of the building in the development does not exceed stipulated AMSL j. DSTA clearance (where applicable) k. CAAS clearance (where applicable) SCDF Temporary Fire Permit URA TOP/CSC Clearance (Required for Addition and Alteration Submissions only, declaration to URA is not needed for Change of Use applications) Processing Time: Approximately Five (5) working days Cost: NA Documents required: a. Declaration to be submitted by QP via CoreNet declaring that the development has been built in accordance with the WP Approved Plans PUB TOP/CSC Clearance Processing Time: Fourteen (14) working days Cost: NA Documents required: a. Certified as-built plans by QP (Site Plans, Floor Plans, Sections/Elevations) b. As-built survey plans c. e-Submission Forms endorsed by QP or PE d. Relevant as-built technical calculations endorsed by the appropriate QP/PE e. Any documents as required for TOP/CSC submissions as listed in Code of Practice on Surface Water Drainage, Code of Practice on Sewerage and Sanitary Works, or e- Submission Forms. Refer to the submission guides at https://www.pub.gov.sg/compliance/qualifiedpersonsportal/quicksubmissionguides Type: Water Supply - Water Service Installation (WSI) Works Processing Time: Fourteen (14) working days Cost: NA Documents required: For water supply to be turned on, a Certificate of Satisfactory Completion of WSI Works certifying that the works are completed in accordance with the PUB’s requirements including the Public Utilities (Water Supply) Regulations, Singapore Standard 636 – Code of Practice for Water Services, other Authorities’ requirements and other statutory requirements. 8
NEA TOP/CSC Clearance Processing Time: Seven (7) working days for each written direction Cost: NA Documents required: a) Cover letter clarifying scope of work, farming process flow, work activities as well as chemicals use/storage b) One set of building plans including site plan, floor plans layout, sectional and elevation plans complying with NEA requirements as specified in the Code of Practice on Environmental Health (COPEH) and Code of Practice for Pollution Control (SS593:2013). c) Noise assessment report to ensure compliance to Boundary Noise Limits for Air Conditioning and Mechanical Ventilation Systems in Non-Industrial Buildings d) Any waiver approval by NEA e) Letter of Undertaking (LOU) by developer/Owner/Operator of the farms Table B: Submissions required for CSC: Agencies Documents Required SCDF Fire Safety Certificate NEA TOP/CSC Clearance PUB TOP/CSC Clearance (Note: For direct CSC application, all the documents stated in Table A and B above are to be submitted) Helpful Tips 1. For works requiring a QP, consider engaging someone who is familiar with and understands farm operations/ needs 2. Appoint a competent licenced builder to ensure that building works are built in accordance to approved plans and are code compliant. This will minimise issues during post-construction inspections. Submissions to NEA 3. To facilitate NEA submission, you are advised to provide the following information: a. Tabulation of refuse output and clarify how each generated waste stream will be stored, transported and disposed; b. Farming process activities, proposed working hours, type of chemicals/fertilisers used; c. Clarify mitigation measures to ensure that the proposed use will not cause odour, noise or pollution issues to the premises and its vicinity; and d. Ensure no roof gutters are installed and avoid features that may result in water stagnation and become potential breeding habitat for mosquitoes. 9
e. To declare upfront any requirements that are not able to comply with the Code of Practice on Environmental Health (COPEH) and the Code of Practice for Pollution Control SS593:2013. 4. If you have a specific question related to your submitted farm plans, please contact the NEA processing officer assigned to your project. Otherwise, please submit a Building Plan Consultation Request at https://www.eportal.nea.gov.sg/app/#/applications/create/building-plan- consultation-request or drop an email to DCLD_Consultation@nea.gov.sg for all other enquiries. Submissions to URA 5. Waiver application process for URA’s Addition and Alteration submissions via CoreNet: a. QP submits a waiver on the CORENET platform, indicating the specific URA condition / guideline to be waived b. The QP will have to provide the reasons for the deviation, consider the potential impact on the amenity of surrounding developments and streetscape, and propose appropriate mitigating measures. c. The request will be considered on a case-by-case basis and a reply will typically be provided within fifteen (15) working days. Submissions to PUB 6. Check if your development plans are eligible for PUB’s Simplified Submission Scheme. This will reduce the processing time. 7. Check your BIM model using PUB’s e-Plan Checker for compliance with PUB's requirements before making your submission to CORENET. This reduces your clearance time provided the modelling submitted has been reviewed and cleared of all non-compliances. For more info on PUB's BIM e-Checker, please refer to the following link at https://buildingplanchecker.pub.gov.sg. 8. If you have questions about your submission, you can book a consultation or find out the status of submission through our QP Portal E-services at https://www.pub.gov.sg/compliance/qualifiedpersonsportal/eservices. For further assistance, please call PUB Building Plan Division (BPD) hotline at 67313512 during office hours between 9am to 5pm, or email to pub_bpu@pub.gov.sg. Submissions to BCA 9. Structural design standards to be used are indicated in the BCA’s Approved Document, which can be consulted here: https://www.bca.gov.sg/Publications/BuildingControlAct/others/Approveddocument.pdf 10. The safety of occupants is paramount. For safety reasons, requests for partial TOP (i.e. splitting of the development plot to allow for TOP to be received earlier for part of the site) will not be accepted if there are on-going structural works and/or crane hoisting works within the land site. 10
11. The Code on Envelope Thermal Transfer Value (ETTV) calls for sufficient thickness of glass to prevent energy loss if a greenhouse is air-conditioned. Alternatively, a developer can provide energy saving mitigation measures such as solar panels to make up for energy loss from the use of thinner glass. 12. Please refer to SS 555: 2019 for design and technical compliance to Lightning Protection System. Maintenance Matters The following maintenance matters are also highlighted for attention:- a) The Successful Tenderer will be responsible for taking over the property in as-is condition, and maintenance of the space within the tenanted boundary. Generally, the tenanted boundary is pegged to the bottom of the vehicular ramp serving the parking deck, but it will exclude shared building systems. b) The Successful Tenderer shall apply for and bear all costs for installation of water and electrical sub-meters. The tenant must also open its own utilities account and cover all related charges incurred for supply of water, sanitation, refuse removal, electricity usage etc. The utilities account will need to commence together with the tenancy commencement date, even if there is any concessionary rent-free period granted. c) The Successful Tenderer will be held responsible for the maintenance of the site, e.g. cleaning, pest control, proper refuse removal from site to the bin centre, and fulfil all other maintenance responsibilities as stated in the Tenancy Agreement. 11
Contact Information For Questions relating to tender or site: Agencies SFA Landsales@sfa.gov.sg HDB For purchase of plans Mode Process Payment Email SOP@mailbox.hdb.gov.sg with Cost of drawings is $30 first copy, subsequent drawings @ $6.00 per 1) Address/ location of the MSCP, copy. (inclusive of GST) 2) Plans required: Architectural MSCP roof deck layout plan, 3) Contact details (email/contact no). For different projects, the cost will be $30 first copy, subsequent drgs @$6.00 per copy (inclusive of GST) HDB will contact you within 3 working days on the request. For Questions relating to Agencies’ submission requirements: Agencies Email Address URA URA_DCD@ura.gov.sg NEA DCLD_Consultation@nea.gov.sg BCA bca_enquiry@bca.gov.sg PUB pub_bpu@pub.gov.sg SCDF scdf_qp_consultant@scdf.gov.sg
Urban Farm Development Approvals – HDB Multi-Storey Carpark START START FARM START APPROVALS START STRUCTURAL ARCHITECTURAL TOP/CSC TENDER LAUNCH TENDER AWARDED CONCURRENTLY WORKS APPLICATION OPERATIONS WORKS 4 weeks Est. 4 weeks Est. 6- 8 weeks Est. 3 to 6 weeks Est. 2 to 4 weeks STRUCTURAL ARCHITECTURAL SPACE ACQUISITION STAGE PLANNING STAGE COMPLETION WORKS WORKS SFA & Tenderer SFA Farm HDB Submit Tender License Tender Evaluation SFA & HDB URA BCA BCA BCA Plan Clearance Change of Use/ Permit to Structural BP Approval A&A works Plan Commence Works SCDF TFP/FSC SCDF Change of Use/ BCA TOP/CSC A&A works NEA NEA Environmental Health This diagram highlights the main steps in setting up a farm on NEA Environmental Health PUB HDB Multi-storey Carpark Premises. Use it to help you plan PUB Drainage & Sewerage your business and cash flow. URA PUB Drainage & Sewerage Please note that this is a general overview, for scenario where SCDF Fire Safety Requirements CAAS structural works are required. Your experience of the process CAAS (where applicable) may vary, depending on your specific circumstances. For DSTA example, the completeness of an application made, the time BUILDING PLAN (BP) DSTA (where applicable) intervals between an agency’s correspondence and the subsequent application by your appointed Qualified Person TOP/CSC (QP) are contributing factors to the actual timeline of your DEVELOPMENT CONTROL Clearances farm’s development. (DC)