GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...

Page created by Gregory Saunders
 
CONTINUE READING
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
GTG Webinar #3: Public Release and Knowledge Sharing
Session on Minimum Load/Ramp Test Procedures
for Coal Based Thermal Power Plants (TPPs)

            Renewable Integration and Sustainable Energy (RISE) Initiative
                         Greening the Grid (GTG) Program
                 A Joint Initiative by USAID and Ministry of Power
                           April 27, 2020 (Monday)
                                                                             1
                           7 PM IST / 9:30 AM EDT
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
2

    Coal Based Flexible Power Generation with NTPC and
    GSECL

                                                         2
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
Scope & Expected Outcomes

                  Pilot Scope
                  •   Examine techno economic feasibility of faster ramp rates and
                      lower technical minimum in two (2) units each at NTPC (Jhajjar
                      & Ramagundam TPS) & GSECL (Ukai TPS)
                  •   Support implementation of recommended measures by NTPC &
                      GSECL for achieving flexible operations of the units

Expected Outcomes
•   Specific recommendations for changes to O&M procedures/standards
    and required design modifications based on Indian grid conditions
•   Optimize plant availability and efficiency (including part load
    efficiencies)
•   Evaluation of incremental cost of generation due to cyclic operation
•   Regulatory/policy advocacy & implementation strategy for identified
                                                                                       3
    interventions                                                                 3
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
Pilot supports technical interventions and operational changes at NTPC’s Ramagundam (200 MW unit), Jhajjar (500
                              MW unit) and GSECL Ukai TPS (200MW & 500 MW unit)

Stage 1:Techno                   Stage 2: Regulatory                  Stage 3: Pilot                   Stage 4: Scale up
Economic Assessment              Pathway and Fleet                    Implementation
& Roadmap                        Level Strategies                                                      • Assist in fleet-wide
                                                                      • Technical Assistance in
• Technical due diligence        • Assistance in framing                pilot / fleet level              implementation and
  and detailed feasibility         Regulatory Mechanisms                implementation to                national scale up
  assessment                       for Flexibility                      NTPC
                                                                                                       • Capacity building of
• Establishing reliable costs    • Assistance in building             • Leverage private                 operators –
  of flexibilisation – capex       fleet level strategies for           partnerships and                 Procedures and
  as well as opex                  NTPC / GSECL                         contribution in                  Operational Toolkits
                                                                        investments

           2017                           2018                                  2019                                2020
 • Pilot Conceptualization      • Technical Assessment          • Regulatory Frameworks for                 • Facilitate fleet-wide
                                  reports completed for           flexibilization to CERC & GERC              adoption and
 • On Boarding of Technical
   Assistance (TA) Firm           NTPC and GSECL units          • Pilot Test Runs & Fleet Wide Strategies     National scale up

 • Stakeholder Discussions &    • Executive Exchanges to US     • Changes to Operating Procedures           • Knowledge
   Data Collection              • Knowledge Dissemination                                                     Dissemination
                                                                • Executive Exchanges & Knowledge             Workshops
 • TA Implementation Plan         Workshops                       Dissemination Workshops                                       4
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
Glimpses from the field

                            Gujarat’s Low Load Test Runs
                            GSCEL, UKAI unit
                            March 2-4, 2020

NTPC Mauda Low Load Test
Runs
February 15-17, 2019 (Run
#1)
May 28-29, 2019 (Run #2)
                                                           5
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
6
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
Public Release and Knowledge Sharing Session
on Minimum Load/Ramp Test Procedures for Coal
Based Thermal Power Plants (TPPs)

Shri Prakash Tiwari            Michael Satin
Director Operations            Director - CLEEO
NTPC Ltd.                      USAID/India
                                                  7
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
8
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
Content

• Why do you need a test run ?
• Emerging Scenarios and Flexibility requirements
• Options vs Costs for Coal Flexing in India
• Harsh Realities of Cyclic Operation
• Criteria and Selection of units for Flexibilization
• Test run Procedures
• Key Takeaways from the field Tests
• Combustion Optimization
• Recommendations
• Best Practices
• Conclusion

                                                        9
GTG Webinar #3: Public Release and Knowledge Sharing Session on Minimum Load/Ramp Test Procedures for Coal Based Thermal Power Plants (TPPs) ...
Why do you need a test run & till what level?

  • What happened during the 9 minutes/9pm on 5th
    April? Do you see a relevance of coal units?

  • Act now. Coal Units have to prove the reasons for
    their existence for a greener role.
Questions from Participants

- What is the future of coal based thermal power plants.
- Whether coal based thermal power plants are viable.

- At what minimum load a 660MW super critical thermal unit can be run
  without oil support.
- How long it can be run at that minimum load?
- What should be the maximum limit for ramping up & down to meet
  the
  grid requirement
- How frequently the load change will occur during the day (tentative
  forecast).
- Weather this load change will be based on merit order or some other
  methodology will be applied.
- At Minimum load unit heat rate & APC will be effected, weather this
  will be considered in calculating target Heat rate for those units which
  are operating under PAT cycle.
- What will be the impact on boiler life cycle?

                                                                             11
Is this an economic despatch as claimed under SCED ?

   Scheduling Effect on running of ISGS Stations –One example(April 20th)
                                                                                     Safety Issues
                                                                                     O&M cost –         under
                                                                                     recovery

         Ramp@2%                                        Ramp@2%                      Need for investments in
         30% down                                       43% down                     retrofits
                                                                                     Would the dispatcher
              15% down                                                               schedule this way if
                                                                                     there were provisions
                                                                                     for additional O&M
                                                                                     cost recovery?

                                                                                     There is a clear
                                                                                     misalignment in the
                                                                                     understanding amongst
                                                                                     Generator, Despatcher
                                                                                     and Regulator

If we consider a significant load following of ramp size>15%,then we have at least 7 significant load
                                                                                                            12c
followings
Each of this event costing >2lakhs for the generator, which the generator has no way to recover from
the present regulatory mechanism.
           Is it still better than shutting down and starting the unit repeatedly?
Emerging Scenario & Need for Flexibility
  With SCED mechanism in
place-already, the low merit
order Stations have started
 facing the heat of frequent                 With 175 GW RE ……      Falling PLF for coal stations
     changes in schedule

  Units are typically facing
around 15 or more significant
  load-followingg in a day.
  Units which are unable to
 reduce their minimum load
   are asked to start-stop

There is no compensation for
   recovery of O&M costs
 incurred due to increased
     cycling on the units

It is important for the station
     to know what value of
    flexibilization it can best
              deliver

Coal units will have to compete with other resources for delivery of balancing power
                                                                                             13c
Harsh Realities of Cyclic Operation

•   Flexible operation is a difficult mode of operation
    and even the most conservative approach will              •   Flexing with lack of awareness,
    increase plant O&M costs along with per MW                    can be disastrous
    variable costs
                                                              •   Well known that cycling causes
•   However those plants that can operate flexibly to             damage and when equipment
    meet market conditions while minimizing the                   degrades, performance
    financial impact of operating in this environment,
                                                                  degrades.
    will continue to be dispatched, at least for the near
    future.
                                                              •   Damage not immediate but
•   Investments in retrofits can enhance the flexibility to       accumulated and not easy to
    a large extent                                                quantify

•   Revisiting the operational procedures, Training of        •   By the time symptoms of
    O&M manpower can enhance flexibilization                      damage is visible it may have
                                                                  become very costly to Correct
•   Proactive participation of stakeholders in enhancing
    latent system flexibility can be driven by Policy and
    regulatory interventions
                                                                                                    14
Harsh Realities of Cyclic Operation

•    The limitations of a particular mode of operation are often not known. Sometimes they are due to faulty
     operational practices .
•    Subsequent flexibility in the units can be unlocked by procedural changes and upgrade of C&I systems.
•    Proper operational strategies and procedures can minimise the damages and costs.
•    There is no “one-fit-for all’ solution for flexibilization. Units need to identify what is best and cost effective
     intervention required on individual level through test runs
                                                                                                                          15
Options vs Costs for Coal Flexing in India
                                                                       Does It Matter How Unit Flexibility is achieved?
                                                                       Trade-off between Investment and Return
                        No                                                         required to be done
                   Intervention
                   (Business as
                      Usual)

                                      Operational
                                      Alterations
                                                            Operational
                                                             Alterations
Operational Cost

                                                                 and
                   Cost of Flexible                          Control &                Operational Alterations
                    Operations                            Instrumentation          + C&I+ Digitalisation/Fleet wide
                                                                                            Monitoring                        Operational
                                                                                                                              Alteration +
                     Cold Start                                                                                                   C&I +
                                                                                                                              Digitalisatio
                    Warm Start                                                                                                n/Fleet wide
                                                                                                                              monitoring+
                     Hot Start
                                                                                                                              Technologic
                    High Turn                                                                                                       al
                    Down/MTL                                                                                                  Intervention
                     Fast Ramp
                   Load Following

                                                                                                                Increasing Investment
                                      Operational
                                                              Control &                  Fleet
                                       Changes /                                                                              Technological
                                                           Instrumentatio       Monitoring/Maintenance       Digitalisation
                                       Training                                                                               Interventions
                                                               n (C&I)                 Practices
                                          Coal
                                        Blending                                                                              ▪ Modify
                                                                                                                              ▪ Upgrade
                                                    Technical Interventions for Flexible Operations
                                                                                                                                              16
Identification of Units for different modes of operation

    Category             Metrics
                   ECRRs.2.5/KWH)
Load               GCV >2800,VM > 15%

                  Units>25 Years
Flex with
                  Unit size-200 and above
Efficiency        HR> 2500
Retrofit

Flexible Daily     ECR>> State M.O.
                   (unlikely to get schedule in 2022)
Start              HR>2500,               GCV>3400

Retire/replace    >25Years
                  HR>2600
                  Unit sizes
Test Run Procedures

                      18
Gujarat’s Low Load Test Runs
                                GSCEL, UKAI unit
                                March 4th, 2020

NTPC Mauda Low Load Test Runs
NTPC, Mauda Unit
February 15 – 17, 2020

                                                               19
Test Run Procedures
Objectives                                       Testing Approach
• Evaluate the Unit’s response to:               • Gradual load reduction until a
                                                   challenge/ obstacle occurs. (All loops in
     – Ramp up/ Ramp down characteristics
       between new/ old minimum load and
                                                   auto)
       base load evaluation.                     • Define an approach to overcome any
     – Response to minimum stable load             such obstacle/s.
       (Target: 40% minimum load without any
       changes in plant configuration)                – Manual intervention

• Identifying of the process limitations/             – Changing operation regime (e.g.
  restrictions (thermal, mechanical,
                                                       changing combination of mills,
  aerodynamically, operation) during the
  new/ old minimum load                                changing main steam pressure)
• Check of control system and evaluation              – Implementation of supplementary logic
  of aging of equipment                                 in the DCS
• Identification of Operational procedures
                                                      – Changes in set points of control loops
• Identification of retrofits for this plant -
  Required and Possible                               – Revising the sliding pressure curves/PA
                                                        flow curves..

                                                                                                  20
Expected Issues during the Tests

                                   • Poor combustion/poor flame
                                   • Drum level control/TDBFPs
                                   • Hot reheat steam temperature
                                   • Main steam temperature
                                   • Flame scanners
                                   • Primary Air Fan Stalling
                                   • Coal Pipes choking and improper
                                     balancing between different coal
                                     pipes
                                   • Flue gas exit temperature
                                     approaching acid dew point
                                   • Turbine vibrations

                                                                    21
Description: 500 MW Unit

• Boiler: Drum type subcritical design,
  Two pass boiler, Tilting tangential
  fired, Controlled circulation with
  rifled tubing, Balanced draft furnace
  with fusion welded water walls,
  Radiant reheat type
• Turbine: 3 cylinders turbine
  consisting of HP, IP and LP module,
  Single flow HP Turbine with 17
  reaction stages, Double flow IP
  Turbine with 12 reaction stages per
  flow, Double flow LP Turbine, with 6
  reaction      stages    per     flow, • Coal Quality during the test:
  Conventional governing system, 2-        – GCV in the range of 2700-3930
  pass double flow condenser                  Kcal/Kg
                                           – VM-19-22%
                                           – Ash-40-47%
                                                                             22
Field Tests done

                      Low Load
  From 500MW to 198MW & BACK with hold points                           Ramp Rate
  ▪ 500-360 MW- 5mills
  ▪ 360MW-300MW- 4mills                                   ▪    Ramp up/down of 1%, & 3% were
  ▪ 300MW-275MW-4mills                                         checked at different load range
  ▪ 275-198MW-3 mills(C,D,E)                              ▪ CMC on except during ramp up @3%
                                                               from     360-500MW       when    CMC
                                                               response was very fast (CMC made off)
                                                          ▪ There was a difference in CMC
                Turndown of Mills                              response and actual ramp achieved at
 Loading of mills were reduced till 50% load                   lower loads (for 3% ramp)
 If any mill was required to be loaded below 50%,it was   ▪ Unacceptable deviation in parameter
 withdrawn and other mills loaded                              (SHTemp, RH, excessive SH spray)
                                                          ▪ Due to thermal shock, falling of big
                                                               sized clinker which dislocated the SC
                                                               chain
 Review of sliding pressure curve and PA flow             ▪ Sliding pressure needed to be
 curve                                                         modified
                                                          Conclusion: Upgrade of C&I system
                                                          needed changes in operational procedures
                                                          (eg- Soot blowing, Burner tilt operation,
 Unit assessment with HP heaters bypass                   air flow, mills turndown)
                                                                                                       23
Issues faced during the test runs

• In all the test runs conducted, it was                • Steam coil APH was not available/not used
  observed that control loops were not tuned              regularly
  for low loads
• Burner tilts were on manual- key variable             • Sliding pressure was in service
  having significant influence on steam                 • The partial steaming of ECO occurred at low
  temperature parameter control
                                                          load. Which can be allowed only for a short
• More number of mills than required were                 time.
  kept in service to take care of the exigencies
  of mill tripping.                                     • Increase in SH temperature during load
                                                          ramping
• Primary air flow maintained higher than
  anticipated values as mills were operated at          • High SH spray
  full mill air flow irrespective of the mill
  loading                                               • Jerky operation of feed water flow on
                                                          opening of the recirculation valves at low
• Secondary air flow is very much less than               load.
  the desired level resulting in no or low
  windbox dP at part loads                              • The analysis of Dirty air flow results reveals
• WB pressure was improved by closing the                 that there is a good degree of imbalance in
  secondary air dampers of the mills that were            coal flow across the pipes at low load.
   not in service and optimising the primary air flow

                                                                                                           24
Key Takeaways from the field Tests

                                     25
COMBUSTION OPTIMISATION
                                                        Improving Mill Turndown

Combustion
must be
completed
here

      Residence
      Time
      Optimisati
      on

                                                                             Auto Coal Sampler
                                  Fuel Firing System Optimization Package
                                  for low load oprn:
                                  • Air/Fuel ratio
   Flame scanners modifications   • Coal pipes dynamic balancing
   Burner modification            • Auto mill start
                                  • Coal analyser
                                                                                                 26
Combustion Optimization to attain Minimum load reduction potential
                                                       • Compliance to the NFPA (National Fire Protection Association) guidelines.
• Balancing of Coal flow across the coal pipes         • The standards of NFPA 8502 which requires that the airflow is maintained
                                                         at or above the purge rate (not less than 25% of the full load mass airflow)
• Fuel/Air ratio, Combustion air
                                                         during all operations must never be violated.
                                                       • Never add air to a dark smoky furnace. It is advisable to trip the unit &
• Furnace exit gas temperature
                                                         remove all ignition sources, then purge thoroughly before restarting.
                                                       • Improve Mill turndown- Minimum load on a mill – 50%
• Bottom Ash & Fly Ash Unburnt

• Flue gas temperature and excess air stratification

• Flue gas oxygen /Excess air level
                                                       • Temperature in the range of 70-930C with low VM coal (15-30%)
• Coal mill inlet/outlet temperature
                                                         and a range of 60-800C. Maintaining a slightly higher mill outlet
                                                         temperature at low loads will help faster stabilization of the
                                                         flame.
• Primary Air header pressure
                                                       • The primary air flow in mills to be as per air/fuel ratio
• Pulverized coal flow velocity /Temperature of coal
  pipes
                                                       • Optimization of secondary air flow. Tertiary vanes of elevations that are
• Windbox pressure                                       not in service to be reduced, ensuring just adequate flow for burners
                                                         cooling. Measurement of secondary air flow at individual burners to be
• Burner Tilt                                            provided. This will help in further optimization of the process.
• Flame scanners

• Coal fineness

• Selection of burner

                                                                                                                               27
Key Takeaways from the field Tests
                                      • Measurement of excess air for
• Sliding pressure induces a            combustion /Flue gas O2
  sluggish load response for drum       measurement may be validated
  boilers. But the advantages are       with CO measurement as CO is
                                        unaffected by air in leakages.
  far more. Modification of sliding
  pressure curve (increased           • Traditionally, C&I specs aimed at
                                        automatic operation in the range
  slightly) in small steps is to be     of 60% to 100% MCR. The
  done to ensure that there is no       automatic control at lower loads
  steaming in economizer and no         becomes poor and sluggish mainly
  DNB.                                  due to changing unit response
                                        characteristics.
• BFP recirculation valves must be    • Another limitation with low load
  able to operate at intermediate       operation in the improper sizing
  positions (inching type).             of many control valves for low
                                        load or low flows operation,
                                        causing poor control response and
                                        sometimes hunting of valves.

                                                                            28
Key Recommendations                               • Modified Procedures for low load, start-
• C&I System is crucial:                                up and lay-ups
• Fine tuning of Existing CMC Logic                   • Replacement of R/C valves for BFPs
• MS ,RH , Flue Gas Temperature Control
                                                      • Modification of sliding pressure curve
• Unit Control and Automatic Mill Operation (Mill
  Scheduler)                                          • Modification of PA fan curve
• Boiler lifetime monitoring
                                                      • Including operator’s view of the process
     – Some available solutions for lifetime
         monitoring                                     (displayed on LVS or other screen) to
     • COSTCOM(Intertek)                                include the actions that may be needed
     • EPRI (BLESS)                                     during the particular operating regime.
     • PowerGEN Creep Fatigue Monitoring                Eg Start-up/ Shutdown/Minimum Load
     • ODAS(Australia)                                • Installation of Steam coil air pre-heater
     • ERA Plus System                                • Replacement of actuators: to improve
     • PADO(STEAG)                                      fast load ramping and to meet the
     • SIEMENS                                          requirements of low load operation
     • Flexsuite (GE)
• Automatic Plant Start-up
                                                      • Modifications for hot filling of boiler from
                                                        a running unit
• Combustion Optimization using an Online Coal Flow
  Measurement

                                                                                                       29
Best Practices
• Increased ramp rate with Rapid response for       • N2 blanketing of all DM storage tanks
  frequency control
                                                    • Exploiting the storage capabilities of mills
• The Condensate Throttling
• Advanced process control                          • Automatic plant startup and guide
• Plasma Ignition System                            • Digital Boiler Plus (DB+) Low Load Advisor
• Automatic Mill Scheduler
                                                    • Heating blankets used to keep turbine warm
• Fully automatic operation of all burners/mills      during stand-stills by balancing the upper and
  without manual intervention between a load          lower casing and thus avoiding the bending of
  of 0 and 100 %                                      the shell
• Automatic switching of burners/mills on/off
  • On burner failure automatic selection of the
    best alternative burner
  • Automatic adaptation     to   changed   load
    requirements
  • Plant operators can remove individual burners
    from the regime of the burner and mill
  • scheduler while the remaining burners
    continue to be controlled optimally

                                                                                                     30
In Summary….

• For supporting 175 + GW of RE integration, coal units are required to run on increased cyclic
  mode.
• Units will be required to identify the best value they can provide to the power system.
• There is no “one-fit-for all’ solution for flexibilization. Units need to identify what is best and
  cost effective intervention required on individual level through test runs
• Preparation for flexibilization will need the identification of limitations and the specific
  interventions required to be carried out on units.
• In most of the cases, modification of Operational procedures and upgrades of C&I system can
  unlock substantial flexibility in the units.
Thank You for Your Time

             Stay Safe. Maintain social distancing

We will deliver any information you require at your digital doorstep
•   RISE Contracting Officer
                                                 Representative: Monali Zeya
Anjan Kumar Sinha                                Hazra, USAID India,
Senior Advisor                                   mhazra@usaid.gov

USAID GTG-RISE Initiative                    •   Chief of Party:Tushar Sud RISE,
                                                 tsud@deloitte.com
sinha.anjan@gmail.com | Mob:+91 9650992971
                                                                                   33
You can also read