FY2021 High Hazard Potential Dams Rehab Grant - July 28, 2021 1:00 PM - SCDHEC
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Your Presenter John M. McCain, P.E. Section Manager SC Dam Safety Program (803) 898-8178 mccainjm@dhec.sc.gov 2
Agenda • Background and available funds • Dam eligibility • Applicant eligibility • Eligible/allowable activities • State and Federal requirements of a grant award • Grant application process and timeline • DHEC’s application review and award selection process • Questions and Answers 3
Background • National High Hazard Potential Dams (HHPD) Rehabilitation Grant Program created December 16, 2016 with passage of the Water Infrastructure Improvements for the Nation (WIIN) Act • While authorized in Calendar Year 2016 (Fiscal Year 2017), no money appropriated until Federal Fiscal Year 2019 ($10,000,000) • Subsequent Appropriations: • FY20 $10,000,000 • FY21 $11,640,000 This grant • WIIN Act authorizes up to $60,000,000 for Fiscal Years 2021- 2026 4
Background, Cont’d • State HHPD Rehab Grant administered by SCDHEC for owners of SC dams • First year, FY19, SCDHEC utilizing grant funds to perform risk analysis on state and local government- owned dams • $301,821 FEMA grant, $162,519 state match • Second year, FY20, SCDHEC started a sub-award program, and issued a Notice of Funding Opportunity on October 2, 2020 • $585,694 Federal grant, $315,374 non-Federal match 5
Available Funds for FY21 • Too early to know for sure • Total Federal appropriation: $11,640,000 • 1/3 divided evenly among all state applicants • $3,880,000 / 15(?) = $258,667(?) • 2/3 divided among states based on application’s share of eligible dams (our application had 9 eligible dams) • $7,760,000 x (9 dams / ??? dams) = ??? 6
Dam Eligibility • Regardless of ownership, a dam is eligible for grant funding if: 1. The dam meets the Federal definition of “dam” found in the US Code of Laws, Title 33, Chapter 9, Section 467(3); 7
Source: https://www.law.cornell.edu/uscode/text/33/467 8
Dam Eligibility, Cont’d 2. It is a non-Federal dam; 3. The dam is located in a state with a State dam safety program; 4. The dam is classified as “high hazard potential” by the State dam safety agency; 5. The dam has an Emergency Action Plan (EAP) approved by the State dam safety agency; 6. The dam fails to meet minimum state dam safety standards and poses an unacceptable risk to the public; 9
Dam Eligibility, Cont’d 7. The dam is NOT a licensed hydroelectric dam; 8. The dam was not built under the authority of the Secretary of Agriculture; 9. The dam’s deficiencies are not solely the result of a lack of or deferred maintenance; and, 10
Dam Eligibility, Cont’d 10. (New for FY21) The dam meets FEMA’s risk-based eligibility criteria. “Likelihood of Dam must plot in the Failure” = Red boxes to be eligible Condition Rating from DHEC inspection “Consequences – Population at Risk” is estimate of lives at-risk 11 from dam failure
Dam Eligibility, Cont’d • Currently 9 dams that (Unsatisfactory) are eligible based on DHEC inspection (Poor) condition and the Population-at-Risk from DSS-WISE Lite (Fair) software (Satisfactory) • Does not mean other dams cannot prove eligibility! Will need documentation of deficiencies that DHEC inspection does not reveal 12
Applicant Eligibility • If a dam is eligible for the grant, who can submit a grant application? • A non-Federal government (e.g., State Agency, County, Municipality, Tribal government, Special Purpose District) • A non-profit organization • From FEMA: “Eligible nonprofit organizations are those organizations that are described under section 501(c)(3) of the Internal Revenue Code of 1986 (IRC) and exempt from tax under section 501(a) of such code.” 13
Applicant Eligibility, Cont’d • So what is a private dam owner to do? • An individual/private citizen cannot apply directly • Must find a Project Sponsor (eligible applicant willing to apply on dam owner’s behalf) • As applicant, the Project Sponsor is assuming responsibility for the project, to include compliance with grant requirements and Federal laws and regulations, receiving and spending grant funds, and more (to be revisited later in this presentation) 14
Eligible/Allowable Activities • “Rehabilitation” includes repair, replacement, reconstruction, or removal of a dam. • What activities can be funded under this grant? FEMA HAS • Planning EXCLUDED CONSTRUCTION • Preliminary Engineering FROM THE FY21 • Final Design* GRANT *For final design to be considered, a complete risk analysis must have been performed that identifies all dam deficiencies with a completed evaluation of alternative remediation actions. 15
Eligible/Allowable Activities, Cont’d • Period of Performance • Activities must be completed within the Period of Performance: End Date: 9/14/2024 All activities must be completed by this date; however, extensions are possible, but are subject to FEMA review and approval. 16
Eligible/Allowable Activities, Cont’d • Examples of Planning Activities that are allowable: • Development of evacuation plans, flood management plans, emergency action plans, etc. • Studies and investigations designed to determine and quantify risks associated with different dam failure modes • Environmental studies for NEPA compliance • Public education and awareness activities regarding flood risks associated with the dam 17
Eligible/Allowable Activities, Cont’d • Examples of Preliminary Engineering activities that are allowable: • Dam risk and consequence assessments • Surveys/mapping • Geotechnical investigations • Hydrologic and dam breach inundation modeling • Rehabilitation Alternatives Analysis 18
Eligible/Allowable Activities, Cont’d • Examples of Final Design Engineering: • Development of engineering plans/drawings for a chosen rehabilitation method • Development of technical and material specifications • Unless the dam has already been well studied, all deficiencies are known, and a risk analysis completed, a grant app for final engineering design is likely to be denied • Better to apply for the planning and preliminary engineering now, and final design in a future grant cycle 19
Eligible/Allowable Activities, Cont’d • What is required for a final design project to be approved? • The dam must be completely investigated (i.e., geotechnical, hydrologic, hydraulic, structural) so that all deficiencies and potential failure modes are known • The consequences of dam failure must be clearly understood (may require dam breach modeling) • All practical alternatives to rehabilitate the dam must be evaluated, and cost estimates for each alternative established • Alternatives analysis to include removing downstream populations or infrastructure instead of rehabilitating the dam 20
Eligible Allowable Activities, Cont’d • Once the failure modes, consequences, and rehabilitation alternatives are known: D1, D2, D3 are all dams that have applied for a grant D2P1 and D2P1 are two potential rehabilitation projects for Dam 2 21
Eligible Allowable Activities, Cont’d • Likelihood of Failure • Remote: Annual Probability < 1:1,000,000 • Low: >1:1,000,000 but 1:100,000 but 1:10,000 but 1:1,000 22
Eligible Allowable Activities, Cont’d • Consequence of Failure • Temporary: Loss of Life = 0, Temporary minor flooding • Limited: Loss of Life not expected, but life- threatening release occurs • Moderate: Loss of Life 1,000 23
Example Alternatives Evaluated: • D2P1 – Spillway Upgrades ($10 million) • D2P2 – Reduce height of dam ($15 million) • D2P3 – Relocate 15 homes downstream ($5 million) 24
Eligible/Allowable Activities, Cont’d • Examples of Non-structural Activities that are allowed: • Purchasing downstream property(ies) for the purpose of removing/relocating at-risk populations or infrastructure • Must be supported by an alternatives analysis that shows this alternative represents most cost- effective risk reduction 25
Eligible/Allowable Activities, Cont’d • Examples of Construction Activities that are authorized by the Law but NOT ALLOWED for this grant opportunity: • Structural repair or rehabilitation of a dam • Dam removal • Construction monitoring • Installation of early warning systems associated with the eligible dam project 26
Eligible/Allowable Activities, Cont’d • Examples of Activities that are NOT Allowable by Law: • Rehabilitate a Federal dam • Rehabilitate a breached dam • Perform routine maintenance and operation of a dam • Modify a dam to produce hydroelectric power • Increase water supply storage capacity • Make any other modification that does not also improve the safety of the dam 27
State and Federal Requirements • As with any Federal grant, there is a long list of laws, regulations, Executive Orders, and programmatic requirements that must be met either before, during, after (or all of the above) a grant-funded project • The Project Sponsor is responsible for compliance with all State and Federal Requirements, even if Project Sponsor is not the dam owner 28
State and Federal Requirements, Cont’d • Federal requirements: • Environmental and Historic Preservation • Non-Discrimination in the Workplace • Procurement • Cost Principles, Audit Requirements, Administrative Requirements • Debarment and Suspension Rules • Drug-Free Workplace 29
State and Federal Requirements, Cont’d • Federal requirements, cont’d: • Fair Wages and Labor Standards (applies to construction) • Federal Funding Accountability and Transparency Act (FFATA) • Single Audit Act • Uniform Relocation Assistance and Real Property Acquisition Act (for purchasing property) 30
State and Federal Requirements, Cont’d • Programmatic Requirements (from FEMA): • Maintenance and Operations agreement for the life of the rehabilitated dam (only applies to construction) • Local Hazard Mitigation Plan that addresses “all dam risk” (if not in place at time of application, must request 12 month extension) • Flood Plain Management Plan that addresses flooding risks in the downstream area protected by the dam (must be developed within 12 months of award, and implemented within 12 months of completion of construction project) 31
State Requirements • Grant Program provides reimbursement only (no funds in advance of work being performed and paid for) • State Procurement Code 32
Application Process • What constitutes an Application for this grant opportunity? 1. Completed Application Form 2. Eligibility Narrative 3. Project Narrative 4. Plan to advance project to final design and construction 5. Project Milestones (for the proposed scope of work) 33
Application Process, Cont’d 6. Detailed Budget (for the proposed scope of work) 7. Procurement Policy 8. Description of Match (i.e., where will non- Federal funds come from) 9. Match Commitment Letter 10.FEMA Approval of Local Haz Mitigation Plan or Copy of Extension Request to FEMA (will be the latter) – will need to coordinate with County 34
Application Process, Cont’d 11. Copy of Dam’s Floodplain Management Plan (N/A if applicant certifies one will be developed within 12 months of award) 12.Completed Environmental and Historic Preservation Checklist 13.Signed Statements of Assurance/Certifications 35
Application Process, Cont’d • Application must be created with the assistance of a licensed Professional Engineer registered in South Carolina 36
Estimated Application Timeline • Sept 15 - FEMA grant award to DHEC • Sept 22 - DHEC issues its Notice of Funding Opportunity and begins accepting grant applications from dam owners • Nov 12 - application deadline • Nov 19 - initial application screening completed (by DHEC) / list of finalists created / first meeting of review panel • Nov 20 - Nov 30 - review panelists rank applications on "Finalists list" • Dec 1 - second meeting of review panel / review total rankings and available funds / vote on "Cut off" i.e., what applications will be funded • NO LATER THAN DEC 15 - DHEC submits amended grant application with proposed sub- awards to FEMA for approval • Feb 1 - FEMA approves amended grant app and proposed sub-awards / notice of approval received in ND grants • NO LATER THAN MAY 1 - Execute sub-awards 37
Application Review and Selection • DHEC’s Screening Level Risk Analysis (SLRA) will constitute 50% of the project’s score • A review panel of 5 members will individually rank all applications – rankings will constitute 50% of project’s score • Ties will be broken by vote of the review panel • Applications for Dam Removal Projects will take priority (no other project can achieve as much risk reduction) • List of awards to be based on available funds. Review panel to decide on the cut-off 38
Application Review and Selection, Cont’d • What is SLRA? • A system developed by DHEC to assign a risk score to every high hazard dam • Each dam gets a score from 0-500. Higher score = greater risk posed by the dam. • Risk is a function of three things: hazards that may act on the dam, dam’s ability to withstand the hazards, the consequences of the dam’s failure • Factors that influence the score: • The dam’s design, age, current condition - i.e., risk factors • Any defensive design features that may exist - i.e., risk reduction factors (e.g., dam is armored against erosion from overtopping) • The population-at-risk in the event of dam failure - i.e., consequence risk factors 39
Application Review and Selection, Cont’d • Review Panel • John McCain, P.E., Manager, Dam Safety Section • Jill Stewart, P.E., Director, Dam Safety and Stormwater Permitting Division • Denise Bunte-Bisnett, P.E., Engineer with Santee-Cooper and former President, US Society on Dams • Stephen Whiteside, P.E., Sr. Vice President, CDM Smith • Representative from SC Emergency Management Division 40
Question and Answer • If your question isn’t addressed during the webinar, we will follow-up with you afterwards. • A summary of all questions and answers will be provided to all attendees after the event. 41
John M. McCain, PE, Manager SC Dam Safety Program 803-898-8178 mccainjm@dhec.sc.gov
You can also read