FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...

Page created by Ryan Lyons
 
CONTINUE READING
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL S24G EIR
COMMENCEMENT OF HOPE VILLAGE
DEVELOPMENT PRIOR TO
ENVIRONMENTAL AUTHORISATION
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
Final Environmental Impact Report

      COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT
        PRIOR TO ENVIRONMENTAL AUTHORISATION
                                    DE DEUR, GAUTENG.

                                         S24G/03/20-21/0515

                      FINAL S24G ENVIRONMENTAL
                            IMPACT REPORT

                                             Prepared for:

                                        Door of Hope Children’s
                                       Mission 8 Copelia Avenue,
                                             Glenvista Ext 3
                                    Johannesburg, 2091 South Africa

                                             Prepared by:

                                              Cape Town
                                      3 Caledonian Road, Mowbray,
                                                 7700

                         Also in Grahamstown, East London, Johannesburg, Port
                                   Elizabeth and Maputo (Mozambique)

                                           www.cesnet.co.za

                                              APRIL 2021
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

                                      REVISIONS TRACKING TABLE

                                      CES Report Revision and Tracking Schedule
     Document Title:                          S24G FINAL EIR S24G/03/20-21/0515

                                              COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR
                                              TO ENVIRONMENTAL AUTHORISATION
     Client Name &                            Door of Hope Children’s Mission
     Address:

     Status:                                  Final

     Issue Date:                              20 April 2021

     Lead Author:                             Amber Jackson

                                              Tarryn Martin
     Reviewer:

     Study Leader/ Registered                 Tarryn Martin
     Environmental Assessment
     Practitioner – Approval:
                                                                           No. of hard   No. electronic
     Report Distribution                      Circulated to
                                                                           copies        copies
                                              Draft:
                                              Library                      1
                                              Website                                    1
                                              Final:
                                              GDARD S24G Department        2             1
                                              Website                                    1
     Report Version                           Date
                                              Draft:
                                              March 2021
                                              Final:
                                              20 April 2021

     This document has been prepared in accordance with the scope of
     CES’s appointment and contains intellectual property and
     proprietary information that is protected by copyright in favour of
     CES. The document may therefore not be reproduced, used or
     distributed to any third party without the prior written consent of
     CES. This document is prepared exclusively for use by CES’s client.
     CES accepts no liability for any use of this document other than by
                                                                                         Info@cesnet.co.za
     its client and only for the purposes for which it was prepared. No
                                                                                          www.cesnet.co.za
     person other than the client may copy (in whole or in part), use or
     rely on the contents of this document, without the prior written
     permission of CES. The document is subject to all confidentiality,
     copyright, trade secrets rules and intellectual property law and
     practices of South Africa.

CES Environmental and Social Advisory Services                                                  Hope Village S24G
                                                                  ii
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
Final Environmental Impact Report

                                    ENVIRONMENTAL TEAM

    The process where the environmental impacts associated with a project are assessed is a
    collective effort from a team of appropriate and independent specialists, as well as an
    independent Environmental Assessment Practitioner (EAP). The BA is required to assess the
    planned development from a holistic perspective, considering all aspects and characteristics
    within the affected natural and social environment. The following consultants have provided
    expert input and a detailed assessment of the project in order to assess the environmental
    and social impacts within the affected environment as well as the acceptability of the
    application.

    Amber Jackson: Project Management and Report Writer

    Amber holds a Masters in Environmental Management from the University of Cape Town and
    has a background in both Social and Ecological work. Her undergraduate degrees focused on
    Ecology, Conservation and Environment with particular reference to landscape effects on
    Herpetofauna, while her masters focused on the environmental management of social and
    ecological systems. With a dissertation in food security that investigated the complex food
    system of informal and formal distribution markets. At CES, Amber has been responsible for
    the management of projects and specialist teams, the preparation and monitoring of project
    budgets in excess of $500 000. She has managed Environmental, Social and Health Impact
    Assessments for projects in the renewable, housing, agri-forestry and mining sectors in
    Mozambique and South Africa to national and international lenders standards including the
    AfDB, EIB, FSC and IFC. Amber specializes in faunal assessments and has conducted a
    number of these in the both South Africa and Mozambique to international standards, the
    majority were assisted by and to Prof Bill Branch. She has recently concluded an
    Environmental and Social Rik management course with the IFC held in Johannesburg over
    2018.

    Ms Tarryn Martin: Project Leader

    Tarryn holds a BSc (Botany and Zoology), a BSc (Hons) in African Vertebrate Biodiversity and
    an MSc with distinction in Botany from Rhodes University. Tarryn’s Master’s thesis examined
    the impact of fire on the recovery of C3 and C4 Panicoid and non-Panicoid grasses within the
    context of climate change for which she won the Junior Captain Scott-Medal (Plant Science)
    for producing the top MSc of 2010 from the South African Academy of Science and Art as well
    as an Award for Outstanding Academic Achievement in Range and Forage Science from the
    Grassland Society of Southern Africa. She conducts vegetation assessments including
    vegetation and sensitivity mapping to guide developments and thereby minimise their impacts
    on sensitive vegetation. Tarryn has undertaken several vegetation and impact assessments
    in Mozambique (to IFC standards) which include the Lurio Forestry Project in Nampula, the
    Syrah Graphite Mine in Cabo Delgado and the Baobab Iron Ore Mine in Tete, Mozambique.
    She has undertaken critical habitat assessments, to IFC standards, for a solar farm in
    Cameroon and a graphite mine in Mozambique. She has co-designed and implemented the
    Terrestrial Monitoring Program for the Kenmare Namalope heavy minerals mine in
    Mozambique and has recently developed a Biodiversity Management Plan and monitoring
    plan for the Kenmare Pilivilli deposit. She has also worked on the Lesotho Highlands
    Development Authority botanical baseline survey for Phase 2 of the Lesotho Highlands Water
    Project.
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

    Contact Details: Project Management and Report Writer

    Name                    Ms Amber Jackson
    Designation             Principal Environmental Consultant
    E-mail                         a.jackson@cesnet.co.za

    Contact Details: Project Leader

    Name                    Ms Tarryn Martin
    Designation             Principal Environmental Consultant
    E-mail                         t.martin@cesnet.co.za

      Role on Study
                                                 Declaration of independence
          Team

     Report Writer     •   I, Amber Jackson, declare that, in terms of the National Environmental
                           Management Act, 1998 (Act No. 107 of 1998), as amended and the Amended
                           Environmental Impact Assessment Regulations, 2017;
                       •   I act as the independent specialist in this application;
                       •   I will perform the work relating to the application in an objective manner, even
                           if this results in views and findings that are not favourable to the applicant;
                       •   I declare that there are no circumstances that may compromise my objectivity
                           in performing such work;
                       •   I have expertise in conducting the specialist report relevant to this application,
                           including knowledge of the Act, Regulations and any guidelines that have
                           relevance to the proposed activity;
                       •   I will comply with the Act, Regulations and all other applicable legislation;
                       •   I have no, and will not engage in, conflicting interests in the undertaking of the
                           activity;
                       •   I undertake to disclose to the applicant and the competent authority all
                           material information in my possession that reasonably has or may have the
                           potential of influencing - any decision to be taken with respect to the
                           application by the competent authority; and - the objectivity of any report, plan
                           or document to be prepared by myself for submission to the competent
                           authority;
                       •   All the particulars furnished by me in this report are true and correct; and
                       •   I realise that a false declaration is an offence in terms of regulation 48 and is
                           punishable in terms of section 24F of the Act.

                       ………………………………………..                                           20.04.2021……………

                        SIGNED                                                              DATE

CES Environmental and Social Advisory Services                                                      Hope Village S24G
                                                       1
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

                                          ACRONYM LIST

     BOD          Biological Oxygen Demand
     EAP          Environmental Assessment Practitioner
     EIR          Environmental Impact Report
     ERP          Emergency Response Plan
     GDARD        Gauteng Department of Agriculture and Rural Development
     IAPs         Interested and Affected Parties
     IBR          Inverted Box Rib
     kl           Kilolitre
     km           Kilometre
     LED          Light-Emitting Diode
     MEC          Member of the Executive Council
     NEMA         National Environmental Management Act
     PPP          Public Participation Process

CES Environmental and Social Advisory Services                              Hope Village S24G
                                                    ii
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

                                              TABLE OF CONTENTS

    1. INTRODUCTION ................................................................................................. 2

       1.1     Background ........................................................................................................... 2
    2. 24G PROCESS ................................................................................................... 3

    3. PROJECT DESCRIPTION .................................................................................. 5

       3.1     Project Location .................................................................................................... 5
       3.2     Project details ....................................................................................................... 6
       3.3     Project Need and Desirability............................................................................. 14
    4. DESCRIPTION OF THE AFFECTED ENVIRONMENT ..................................... 16

       4.1     Socio-economic Context .................................................................................... 16
         4.1.1       Population and household profile ................................................................... 16
         4.1.2       Age and Gender Structure ............................................................................. 16
         4.1.3       Level of Education ......................................................................................... 16
         4.1.4       Level of Employment ..................................................................................... 16
         4.1.5       Household Incomes ....................................................................................... 16
       4.2     Archaeology ........................................................................................................ 16
       4.3     Palaeontology ..................................................................................................... 17
       4.4     Vegetation ........................................................................................................... 17
       4.5     Wetland................................................................................................................ 21
    5. MITIGATION MEASURES IMPLEMENTED ..................................................... 22

    6. IMPACT ASSESSMENT ................................................................................... 23

    7. ENVIRONMENTAL IMPACT STATEMENT ...................................................... 26

    8. ANNEXURE A: PLANS FOR THREE CONSTRUCTED HOUSING UNITS ..... 27

    9. ANNEXURE B: IMPACT ASSESSMENT METHODOLOGY ............................ 28

    10. ANNEXURE C: PLANNING APPROVALS ....................................................... 33

    11. ANNEXURE D: APPLICANT AFFIDAVIT ......................................................... 35

    12. ANNEXURE E: STORM WATER MANAGEMENT ........................................... 36

    13. ANNEXURE F: EMERGENCY RESPONSE ..................................................... 38

    14. ANNEXURE G: WASTE DISPOSAL ON SITE ................................................. 42

CES Environmental and Social Advisory Services                                                                               Hope Village S24G
                                                                    1
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

    15. ANNEXURE H: PUBLIC PARTICIPATION ....................................................... 43

    16. ANNEXURE I: FINANCIALS ............................................................................. 73

    17. ANNEXURE J: EMPR ....................................................................................... 79

    18. ANNEXURE K: WASTE MANAGEMENT PLAN .............................................. 80

    19. ANNEXURE L: DUST MANAGEMENT PLAN .................................................. 81

    20. ANNEXURE M: REHABILITATION MANAGEMENT PLAN ............................ 82

    21. ANNEXURE N: STORM WATER MANAGEMENT PLAN ................................ 83

    22. ANNEXURE O: SPECIALIST OPINION LETTERS .......................................... 84

       22.1   Ecological Opinion Letter................................................................................... 84
       22.2   Wetland Opinion Letter....................................................................................... 84
       22.3   Heritage Opinion Letter ...................................................................................... 84
       22.4   Palaeontological Opinion Letter ........................................................................ 84
    23. ANNEXURE P: GDARD DIRECTIVE ................................................................ 85

    24. ANNEXURE Q: ENVIRONMENTAL AUTHORISATION ................................... 86

    25. ANNEXURE R: EAP DECLARATION AND CV ................................................ 87

CES Environmental and Social Advisory Services                                                                     Hope Village S24G
                                                               2
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

                                                         LIST OF TABLES

    Table 3-1: Commencement and completion dates ................................................................ 6
    Table 3-2 :Design specifications .......................................................................................... 9
    Table 4.1: Vegetation transformed ...................................................................................... 17
    Figure 4-7. Sensitivity Map of watercourses surrounding the study area showing the location
    of the disturbed area on site. ............................................................................................... 21
    Table 5.1: Materials for Recycled ........................................................................................ 22

                                                        LIST OF FIGURES

    Figure 1-1: The housing units (white) and vegetation clearing for six proposed housing units.
     ............................................................................................................................................. 2
    Figure 3-1:Project Location, Portion 19 of the farm 332 Hartsenbergfontein in De Deur........ 5
    Figure 3-2: A) Aerial image May 2017. B) Aerial Image August 2019. ................................... 6
    Figure 3-3: Three-bedroom Unit ............................................................................................ 7
    Figure 3-4: New Road ........................................................................................................... 8
    Figure 3-5: Design of 10kl sewerage plant .......................................................................... 10
    Figure 3-6: Effluent/Sewerage lines from new housing units to new 10kl sewerage treatment
    plant .................................................................................................................................... 11
    Figure 3-7: Vegetable garden in 2016 compared to 2020. ................................................... 11
    Figure 3-8: Vegetation clearing for six proposed housing units (white outline) .................... 13
    Figure 4-1: Illustrating the change of vegetation at the site ................................................. 18
    Figure 4-2: Map of the disturbed areas on site. .................................................................. 18
    Figure 4-3: Site specific vegetation community map for the Hope Village Estate and
    surrounds. ........................................................................................................................... 19
    Figure 4-4: Sensitivity map for the Hope Village Estate and surrounds. .............................. 19
    Figure 4-5: Infrastructure on the Ridge. A) Second Proposed Layout. B) Final realigned
    layout .................................................................................................................................. 20
    Figure 4-6: One of six units ................................................................................................. 20
    Figure 7.1: Pre- and Post- Mitigation Impact Summary ....................................................... 26

                                                          LIST OF PLATES

    Plate 3-1: A) Front of unit. B) Back of unit. ............................................................................ 7
    Plate 3-2: Sewage Package Plant. ...................................................................................... 10
    Plate 3-3: Vegetable garden................................................................................................ 12
    Plate 4-1: Proposed house on the south eastern corner of the ridge ................................... 14
    Plate 4-2: Proposed area for 3 of the 6 proposed housing units in the west of the site looking
    onto two 24G housing units. ................................................................................................ 13

CES Environmental and Social Advisory Services                                                                                         Hope Village S24G
                                                                           1
FINAL S24G EIR COMMENCEMENT OF HOPE VILLAGE DEVELOPMENT PRIOR TO ENVIRONMENTAL AUTHORISATION - commencement of hope village development prior to ...
FINAL Environmental Impact Report

    1. INTRODUCTION
    1.1 BACKGROUND
    Environmental Authorisation (GAUT 002/19-20/E0263) was granted for the development of a
    village estate for abandoned and orphaned children in De Deur, Gauteng on the 28th of
    September 2020.

    Due to the construction of three housing units, the 10 KL sewerage treatment plant and short
    dirt road prior to attaining the environmental authorisation for the clearing of indigenous
    vegetation, a directive (S24G/03/20-21/0515) was issued by Gauteng Department of
    Agriculture and Rural Development (GDARD) on the 21 December 2020 in terms of Section
    24G (1) of NEMA: Unlawful Clearance of Indigenous Vegetation for the Development of an
    Orphanage on Portion 19 of the Farm Hartsenbergfontein 332-IQ, Midvaal Local Municipality.
    This report includes the six housing units which were not granted authorisation due to their
    proximity to the three 24G buildings and thus fall within the ambit of the S24G rectification
    process.

    Figure 1-1: The housing units (white) and vegetation clearing for six proposed housing units.

CES Environmental and Social Advisory Services                                            Hope Village S24G
                                                   2
FINAL Environmental Impact Report

    2. 24G PROCESS
    The requirement for the rectification of ex post facto activities undertaken without authorisation
    is for the unlawful clearance of indigenous vegetation for the development of an orphanage
    on Portion 19 of the Farm Hartsenbergfontein 332-IQ, Midvaal Local Municipality (26° 23'
    8.12"S; 27° 57' 58.39"E). The total size of the area affected by the unlawful activity is
    approximately 2180 square meters.

                                                 Listing Notice 3

     GN R. 324, Activity 12 (c) (ii)

     The clearance of an area of 300 square metres or more of indigenous vegetation.

             c. In Gauteng:
                     ii. Within Critical Biodiversity Areas or Ecological Support Areas identified in
                     the Gauteng Conservation Plan or bioregional plans.

    The process followed is prescribed in Government Notice 40994, No. R. 698 published on 20
    July 2017 referred to as Section 24G Fine Regulations.

    A Section 24G Application Form for the consequences of unlawful commencement or
    continuation of a listed activity/ies was submitted to GDARD on the 25 June 2020.

    Prior to submission of the application a 20-day public participation process was held for the
    review of the application and associated documentation from the 27 February 2020 to 17
    March 2020.

    GDARD then assessed the application and conducted a site visit on 07 October 2020.
    Following this directive (S24G/03/20-21/0515) was issued in terms of section 24G(1)(i-viii) of
    the NEMA on the 21 December 2020.

    A public participation plan was drafted and submitted to GDARD on 15 January 2021 and
    approved on the 22 February 2021.

    Inception public participation process (PPP) was conducted as per Regulation 8 of the Section
    24G Fine Regulations and included compiling a list of interested and affected parties (IAPs),
    sending these IAPs a letter of notification and background information document sent on 09
    March 2021 and erection of a site notice on the boundary fence. For proof of PPP conducted
    to date please refer to (Appendix E).

    An Environmental Impact Report (EIR) (this report) and associated documentation is then
    drafted to retrospectively assess the impacts of unlawful clearance of indigenous vegetation.

    The EIR is then released for public comment for a 30-day period from the 16 March 2021 to
    17 April 2021. An advertisement will be placed in the local newspaper Rising Lenasia Sun on
    the 16 March 2021 and a letter of notification was sent to all IAPs to inform them that the draft
    report is available for review.

    Following the review of the draft reports the environmental assessment practitioner (EAP)
    addressed all IAP comments and include them in the final report (this report) for submission

CES Environmental and Social Advisory Services                                               Hope Village S24G
                                                        3
FINAL Environmental Impact Report

    to GDARD for decision making. The final report was submitted within four months of receiving
    the directive i.e. by the 21 April 2021.

    GDARD will issue an administrative fine, this may be up to a maximum of R5 million. In terms
    of the provisions of section 24G of NEMA, the applicant must pay an administrative fine before
    the MEC/Competent Authority decides on the application.

    The applicant must within 14 days of receipt of the determination of the quantum of the fine,
    ensure that all registered interested and affected parties are notified of the determination of
    the quantum of the fine, including the reasons provided and access to the determination.

    The administrative fine must be paid within the time period stipulated in the administrative Fine
    Letter. Failure to pay the fine within the specified period, will result in the lapse of the
    application and any partial amounts paid in will not be refunded.

    Proof of payment of the fine must be submitted to the Department. Upon payment of the
    administrative fine, the MEC/Competent Authority may-
       ➢ refuse to issue an environmental authorisation; or
       ➢ issue an environmental authorisation to such person to continue, conduct or undertake
           the activity subject to such conditions as may be deemed necessary, which
           environmental authorisation shall only take effect from the date on which it has been
           issued; or
       ➢ direct the applicant to provide further information or take further steps prior to making
           a decision provided for above;
       ➢ together with the above decision the MEC/Competent Authority may direct a person to
           rehabilitate the environment within such time and subject to such conditions as may
           deem necessary or take any other steps necessary under the circumstances.

CES Environmental and Social Advisory Services                                              Hope Village S24G
                                                    4
FINAL Environmental Impact Report

    3. PROJECT DESCRIPTION
    3.1 PROJECT LOCATION
    The project is located approximately 15 km south Johannesburg and 30 km north Vereeniging,
    on Portion 19 of the farm 332 Hartsenbergfontein in De Deur. The property is located within
    the Midvaal Local Municipality and Sedibeng District Municipality of the Gauteng Province
    Figure 3-1). Although zoned as ‘agricultural’ no agricultural activities have taken place in
    recent years.

    Figure 3-1:Project Location, Portion 19 of the farm 332 Hartsenbergfontein in De Deur

CES Environmental and Social Advisory Services                                              Hope Village S24G
                                                  5
FINAL Environmental Impact Report

    3.2 PROJECT DETAILS
    The development included:

        ➢   Three housing units (operational),
        ➢   Dirt road,
        ➢   10kl Sewerage package plant,
        ➢   Vegetable garden and
        ➢   Clearance of indigenous vegetation for the proposed six housing units.

    These are illustrated in Figure 3-2 and the commencement and completion dates of the
    infraction is indicated in the Table 3-1 below.

    Table 3-1: Commencement and completion dates
                 Infrastructure              Commencement Date                   Completion date
    Clearing of indigenous vegetation           August 2017                       October 2018
    Three housing units                         January 2018                     November 2018
    Sewerage Package Plant                      October 2018                     November 2018

                                                            Vegetable Garden &

     Figure 3-2: A) Aerial image May 2017. B) Aerial Image August 2019.

    3.2.1 Housing units

    Three housing units have been constructed. These include two three-bedroom units
    (approximately 170 m2 each which includes the patios) and 1 two-bedroom unit (approximately
    124 m2 which includes patios).

    The walls of each house have been constructed of stumbelbloc and conventional brick
    and are plastered and painted. Chromodek IBR roof sheeting has been used for the roofs.

    General ‘green building principles’ have been applied. This includes rainwater harvesting
    tanks, gas stoves, LED lighting and the use of building materials that require less
    maintenance. The design of the buildings also incorporates natural cross-ventilation (to
    minimise the need for mechanical ventilation), optimisation of sun exposure and the use of
    natural light.

CES Environmental and Social Advisory Services                                                Hope Village S24G
                                                   6
FINAL Environmental Impact Report

    Figure 3-3: Three-bedroom Unit

    Plate 3-1: A) Front of unit. B) Back of unit.

CES Environmental and Social Advisory Services          Hope Village S24G
                                                    7
FINAL Environmental Impact Report

    3.2.2 Dirt Road

    A new dirt road of approximately 110m long and 4.5m wide has been constructed.

    Figure 3-4: New Road

    3.2.3 Sewerage package plant

    There is no municipal bulk sewerage infrastructure currently on-site. A 10KL sewer treatment
    plant has been installed to service the existing infrastructure. Underground sewerage lines
    connecting the houses to the sewer treatment plant have been installed.

    The main process used by the sewerage treatment plant is a standard activated sludge
    system, where the BOD is broken down using air and bacteria, which grow in this medium.
    The bacteria grow naturally, and no additional bio-chemicals have to be added in the process.

    The effluent specification is General Standard in accordance with the terms of the current
    South African Legislation. (Government Gazette 20526 of 8 October 1999, Department of
    Water Affairs publication No.1191 in terms of Section 39 of the National Water Act No 36 of
    1988) this excludes both phosphate removal and special denitrification. This effluent is
    suitable for irrigation.

    The system is based on the activated sludge process. The use of a single fibreglass tank,
    which gives the advantage of the much stronger fibreglass construction as well as being a
    single tank, installation is easy and can be done quickly.

    The raw sewage is introduced into a series of zones, where it is contacted with air, blown into
    the tanks by means of a special blower so that the natural aerobic bacteria break down the
    sewage. A coarse bubble aeration system, which does mix the liquor strongly and has proven
    to be very effective.
    The plant is based on a continuous treatment of the sewage and flow through the plant is
    based on gravity. These rather basic design considerations have however significant effect on
    the operation of the plant:

CES Environmental and Social Advisory Services                                            Hope Village S24G
                                                   8
FINAL Environmental Impact Report

          ➢ The design can cope with fluctuating flows during the day. As the flow is attenuated
            through the plant, peaks can be handled very effectively. The series of zones used
            ensure that peak flows reduce through the plant even if we have allowed for the high
            peak values.
          ➢ No pumps are used in the main sewage flow inside the plant. These normally need to
            be designed for peak flows so that the plant operates generally at peak flow conditions.
            In the plant itself, flows are by gravity only.
          ➢ Because of the fact that the system operates continuously, the effluent is of a constant
            nature. It is thus easier to maintain a good effluent quality with little or no operator
            interference.
          ➢ Because of the series of zones used, the system can also cope with high and low input
            levels.

    In addition to the normal installation of this plant, it has been installed below Natural Ground
    Level (NGL) within sealed vinyl housing surrounded by river sand on each side. Two
    inspection pipes have been installed within the housing to the tank floor level to monitor for
    any spillages. The effluent water from the treatment plant is of agricultural quality and will be
    used for irrigation of the gardens. The external and internal sewer drainage
    network operates as a gravity system.

    The design will be based on the specifications in table 3-2 below.

    Table 3-2 :Design specifications
    Design Standards
     1 Sewerage outflow per day                   10 kℓ/day
     2 Peak factor                                2.5
     3 Sewer capacity                             Pipes Shall be designed to run at 70% full,
                                                  measured in terms of flow depth
      4    Provision of stormwater infiltration   15%
      5    Flow formula                           Manning n = 0.013
      6    Minimum velocities in sewers           0.75 m/s at full flow
      7    Minimum pipe size for reticulation     145 mm internal diameter
      8    Minimum gradients
              Nominal       Minimum grade with depth of     Minimum grade with depth of flow =
              o (mm)        flow = 1/5 D and V = 0.6m/s            1/2 D and V = 0.82m/s
                 160                     1/80                              1/100
                 200                    1/120                              1/200
                 250                    1/160                              1/240
                 300                    1/200                              1/300
      9    Fall through manholes                  80 mm
      10   Depth of sewer
               • In mid-blocks                    1.2m depth to invert
               • In street reserves               1.5m depth to invert
      11   Maximum manhole spacing                110m
      12   Placement of sewers in road reserve 1m from erf boundary on high side of street
      13   Placement of sewer inside midblock 1m from boundary
      14   Dolomitic risk category                None
      15   Pipe material
               • Type                             uPVC
               • Class                            Class 400
               • Supply Lengths                   12 m minimum
               • Joints                           uPVC
      16   Sewer manholes                         Concrete Manhole rings with steps

CES Environmental and Social Advisory Services                                              Hope Village S24G
                                                    9
FINAL Environmental Impact Report

    Figure 3-5: Design of 10kl sewerage plant

    Plate 3-2: Sewage Package Plant.

    No formal municipal bulk water infrastructure exists, nor could be found in the near vicinity of
    the development. Water is currently being supplied by existing borehole on site. An existing
    borehole can provide a constant daily supply of 10.5kl/hour/day, resulting in a constant daily
    supply of 252kl/day which can accommodate the development’s water demand. The water
    quality falls within the minimum standards of the South African National Drinking Water
    Standards (SANS 241:2015).

CES Environmental and Social Advisory Services                                             Hope Village S24G
                                                  10
FINAL Environmental Impact Report

    The water reticulation consists of a pipe network varying in diameter from 90mm to
    110mm. Currently the new pipes connecting to the new houses are lying on top of
    the ground. Each housing unit also has a 5000L rainwater tank to ensure that rooftop
    rainwater runoff can be collected.

    Figure 3-6: Effluent/Sewerage lines from new housing units to new 10kl sewerage treatment
    plant

    3.2.3 Vegetable Garden

    The vegetable garden is approximately 0.1ha (869m2) and is currently a productive area
    fenced off (Plate 3-3).

    Figure 3-7: Vegetable garden in 2016 compared to 2020.

CES Environmental and Social Advisory Services                                          Hope Village S24G
                                                 11
FINAL Environmental Impact Report

    Plate 3-3: Vegetable garden.

CES Environmental and Social Advisory Services        Hope Village S24G
                                                 12
FINAL Environmental Impact Report

    3.2.4 Clearance of Indigenous vegetation for six housing units

    Six housing units were not granted authorisation due to their proximity to the three 24G
    buildings and thus fall within the ambit of this S24G rectification process (Figure 3-8, Plate
    4-1, Plate 4-2).

    Figure 3-8: The six proposed housing units are illustrated in black.

    Plate 4-1: Proposed area for 3 of the 6 proposed housing units in the west of the site looking
    onto two 24G housing units.
CES Environmental and Social Advisory Services                                             Hope Village S24G
                                                   13
FINAL Environmental Impact Report

    Plate 4-2: Proposed house on the south eastern corner of the ridge

    3.3 PROJECT NEED AND DESIRABILITY
    The applicant received local planning approvals and was under the impression that they could
    start construction. However, the applicant realised that they have made a mistake and began
    the rectification process (24G). All further construction stopped at this time. Proof of planning
    approvals are included in Annexure C. As per the directive (point 13) the applicant has a
    signed affidavit explaining this and has committed to not undertake any listed activities without
    prior approval Annexure D.

    The infrastructure which has already been constructed forms part of Phase 1 of the Door of
    Hope Village Estate. Each housing unit has the capacity to accommodate between 6 and 8
    orphans. Considering that there is no bulk sewerage infrastructure on site, it was necessary
    to install the 10kl sewerage plant to service all existing infrastructure.

    Three permanent jobs were created on site as well as temporary jobs during the construction
    phase. The temporary jobs equated to an average of 10 people for 1 year.

CES Environmental and Social Advisory Services                                              Hope Village S24G
                                                   14
FINAL Environmental Impact Report

    Door of Hope receives support from USA and European organizations and the money directly
    received from overseas for the site has easily exceeded R2 000 000 to date. This is direct
    foreign capital flowing into the area and country and was used to pay staff and buy materials
    used on site to build the homes and infrastructure. Additional funds will be received in future
    to further develop the site.

    Mitigation measures for the remainder of the site (not part of the Section 24G application)
    include conservation of the remaining ridge areas. The proponent has indicated that this will
    be done, with these areas utilised only for conservation comparable activities such as hiking,
    bird watching and environmental education.

    Approved Environmental Authorisation:

    Environmental Authorisation (GAUT 002/19-20/E0263) was granted for the development of a
    village estate for abandoned and orphaned children in on Portion 19 of the farm
    Hartsenbergfontein 332 IQ, De Deur, Gauteng on the 28th of September 2020.

    The development is for a private village estate for a possible 300 abandoned and orphaned
    children. The village estate will include 70 Housing Units (which includes a baby house), an
    early childhood development centre, a large dining hall, a school, sports and recreational
    facilities, storage facilities, medical clinic and therapy offices, maintenance workshops and
    storerooms, indoor and outdoor private gym, a library, administrative offices, green spaces,
    subsistence farming gardens, a multipurpose hall / church, four attenuation ponds, a sewerage
    treatment plant and internal access roads and parking areas. Electricity, water and sewerage
    lines will also be laid to support the new infrastructure.

    Applicant motivation:

    Door of Hope Children’s Mission has been running for 20 years and has taken in over 1650
    abandoned babies during that time. They generally run at capacity and at any time have
    around 175 babies and toddlers in their care. Their vision is to expand their operation to care
    of many more orphaned children at the village. They are well respected amongst the local and
    international community and always strive towards the highest possible level of ethical
    behavior.

    Money is always an issue in an organization like theirs which is why an experienced developer
    with many years of experience was not hired upfront. They are therefore learning in many ways
    as they go along with the development and were therefore unaware of the need to apply for
    an environmental authorization for certain of our development activities. At the time they
    received the official approval from Midvaal Municipality to build the homes and had the signed
    house and site plans.

    They have however since contracted experienced Town Planners and Environmental
    Consultants to take them through the full authorization process. Construction of the homes
    was halted when they found out about the contraventions from their Environmental
    Consultants and remains as such until they are given the go ahead which they hope will be
    received soon. They are also committed to complying with all the recommendations made by
    the consultants going forward.

    They will not make any profits from the homes that were built. Their only intention is to give
    more children a better start at life by giving them a home. Their staff are all very passionate
    about saving children’s lives and none are there to profit from the venture. A fine will set them
    back significantly and remove income that would have been used to build children’s homes. It
    is for that reason that they ask for a favorable consideration when reviewing their application.

CES Environmental and Social Advisory Services                                             Hope Village S24G
                                                   15
FINAL Environmental Impact Report

    4. DESCRIPTION OF THE AFFECTED
       ENVIRONMENT
    4.1 SOCIO-ECONOMIC CONTEXT
    The study area falls under the administrative area of the Midvaal Local Municipality (MLM) in
    the Sedibeng District Municipality.
    4.1.1   Population and household profile

    Midvaal Local Municipality has a population of about 111 612 (Statistics SA community survey,
    2016). This is an increase from 95 301 recorded by the 2011 Statistics SA census. The number
    of households has increased from 29 964 in 2011 to 38 046 in 2016 (27%). The population is
    generally concentrated in areas close to the R59 road. The remaining areas have relatively
    low population densities, increasing towards the local municipal border with the Emfuleni
    municipality.
    4.1.2   Age and Gender Structure

    A majority of Midvaals’s population (70.5 %) falls within the economically viable 15-64 age
    group, indicating a large supply of labour. The dependency ratio within Midvaal is 42 %,
    meaning that every person comprising this age group supports 0.42 people comprising the
    economically inactive age groups (youth and elderly). The gender profile of the Midvaal Local
    Municipality indicates that there are slightly more males (52%) than females (48%) within the
    population.
    4.1.3   Level of Education

    Only 5.2% of the total population of people aged 20 years or older living within the Midvaal
    Local Municipality have not received any schooling. 34.4% have some secondary education,
    32.3% have completed matric and 15.3% have some form of higher education.
    4.1.4   Level of Employment

    The unemployment rate in the Midvaal Local Municipality is 18.8%. This means Midvaal has
    an employment rate of 81.2%, which is among the highest when compared to the provincial
    and district situation.
    4.1.5   Household Incomes

    There is a wide distribution of income per household within the Midvaal Local Municipality.
    The weighted average household income is R 15,794 per month. 13.9 % of all households
    earn no income.

    4.2 ARCHAEOLOGY
    The archaeological specialist was consulted regarding the constructed infrastructure. The
    specialist provided an opinion letter stating that the clearing of vegetation and other
    construction activities did not have a significant impact on heritage resources or the larger
    heritage landscape and it is recommended that the developer be exempted from further
    Phases of heritage and / or archaeological impact assessments for the S24G application area,
    subject to Minimum Standards: Archaeological and Paleontological Components of Impact
    Assessment as set out by the South African Heritage Resources Agency (SAHRA).

CES Environmental and Social Advisory Services                                          Hope Village S24G
                                                 16
FINAL Environmental Impact Report

    4.3 PALAEONTOLOGY
    No features were identified. The Paleontological Specialist noted that the likelihood that fossils
    are preserved in the study site are slim due to the thermal metamorphosis this formation would
    have experienced during the intrusion of the syenite dyke.

    4.4 VEGETATION
    The study area comprises both ridge open thicket (4.11ha) and grassland (12.97ha). Tree and
    shrub species are found exclusively in the rocky ridge areas.

    The ridge comprises sections that form a Class 3 ridge, and some areas of the ridge that are
    transformed. The study area also falls within a CBA and ESA identified by the Gauteng C-
    Plan. The study area comprises Gauteng Shale Mountain Bushveld (Vulnerable) according
    to Mucina and Rutherford (2012). No protected areas or National Protected Areas Expansion
    Strategy areas lie within 10kms of the site.

    The ridge vegetation forms an open thicket, with a grassy understory with some herbaceous
    species and geophytes. It is about 5m tall at its tallest. The indigenous trees dominating this
    vegetation community type are Vachellia caffra, Celtis africana and Dombeya rotundifolia as
    relatively large trees and Euclea crispa and Erhetia rigida forming the shorter trees and
    shrubs stratum. The basal layer comprised grass species (either dry or burnt) with exposed
    rocky areas supporting Boophone disticha, Kohautia amatymbica, Pentanisia angustifolia,
    Asparagus sp., Ipomoea bathycolops, Scadoxis punicens and Aloe zebrina, among others.

    This vegetation type is heavily invaded by a variety of invasive species including Melia
    azedarach, Agave sisalana, Agave Americana, Pinus sp., Opuntia ficus-indica,
    Cercus jamacara and Jacaranda mimosifolia.       The       most      dominant        invasive
    is Acacia mearnsii which forms a dominant tree species on the northern part of the ridge.

    Although the infrastructure has been built within a CBA and on a ridge, historical imagery
    indicates that two of the three housing units were built in an area that was previously covered
    by lawn, indicating low impacts on the indigenous vegetation. However, the third housing unit,
    the road and the 10kl sewerage package plant resulted in the clearing of approximately
    2180m2 of vegetation on the category 3 ridge. Ridge vegetation forms valuable and sensitive
    habitat, indicating that impacts here are moderate.

    Table 4.1: Vegetation transformed
    Indicate the physical spatial size of the activity as well as associated
                                                                                           1355 m2
    infrastructure (footprints):
    Indicate the area that has been transformed / cleared to allow for the activity as
                                                                                           4185 m2
    well as associated infrastructure
    Total area (sum of the footprint area and transformed area)                            5540 m2

CES Environmental and Social Advisory Services                                               Hope Village S24G
                                                   17
FINAL Environmental Impact Report

    Figure 4-1: Illustrating the change of vegetation at the site

    Figure 4-2: Map of the disturbed areas on site.

CES Environmental and Social Advisory Services                      Hope Village S24G
                                                     18
FINAL Environmental Impact Report

    Figure 4-3: Site specific vegetation community map for the Hope Village Estate and surrounds.

    Figure 4-4: Sensitivity map for the Hope Village Estate and surrounds.

CES Environmental and Social Advisory Services                                           Hope Village S24G
                                                  19
FINAL Environmental Impact Report

    The Gauteng Ridges Policy is aimed at the conservation of ridges and the 200m buffer area
    surrounding the ridges. These areas provide habitat for a wide variety of fauna and flora, some
    of which are Red List, rare or endemic species or, in the case of certain plant species, are
    found nowhere else in South Africa or the world. The proposed development falls within a
    Class 3 Ridge, which is governed and managed under the framework and guidelines stipulated
    in this policy. Following discussions with the applicant regarding the proposed infrastructure
    located on the ridge, the second proposed layout was revised and updated further to avoid
    the ridge as far as possible.

    As seen in the Figure 4-5B above, there is still some infrastructure that has been proposed
    on the ridge.
    The land has already been disturbed and is well away from the rocky outcrop and tree line.
    The photos below show the proposed area. The white posts are the old fence line which
    demarcates the edge of the ridge.

    Figure 4-5: Infrastructure on the Ridge. A) Second Proposed Layout. B) Final realigned layout

    Figure 4-6: One of six units

CES Environmental and Social Advisory Services                                            Hope Village S24G
                                                  20
FINAL Environmental Impact Report

    4.5 WETLAND
    Based on desktop analysis of the site, the infrastructure developments and construction
    activities that took place on site, appear to be more than 240m from the nearby watercourses
    outside of moderate and high sensitivity areas (Figure 4-7).
    The specialist’s opinion is that there were no impacts on the aquatic and wetland environment
    surrounding the development and all activities took place within the low sensitivity areas.

                                                         Disturbed
                                                         areas on
                                                         site

    Figure 4-7. Sensitivity Map of watercourses surrounding the study area showing the location of
    the disturbed area on site.

CES Environmental and Social Advisory Services                                           Hope Village S24G
                                                  21
FINAL Environmental Impact Report

    5. MITIGATION MEASURES IMPLEMENTED
    The directive issued on the 21 December 2020 instructed the applicant to draft a surface or
    storm water management plan and an Emergency Response Plan (“ERP”). The applicant had
    a storm water management plan drawn up in July 2018 and (Annexure E). Evacuation plans,
    firefighting equipment and emergency signs have been placed on site (Annexure F).

    The directive also instructed that the following additional plans be drafted and kept on site
    Within thirty (30) days of the date of receipt of the directive:

    ➢    Waste Management; and
    ➢    Dust Management; and
    ➢    Rehabilitation Plan.

    A copy of these plans can be found in Annexure K, L, M, N and on site.

    Waste measurements in place on site include a designated and cordoned off general waste
    area and building rubble has been sectioned off with shade cloth. Refer to Annexure G for
    photographs.

    During the construction phase, construction solid waste generated 300m3 by the
    project was gathered and stored in an appropriate, central area on site. Where possible the
    construction waste was reused on site. The remainder has been kept on site and will be used
    as backfill in future construction within the property. This is a continuous and ongoing process.

    Currently all domestic waste produced (5m3/month) is collected and stored in weather and
    scavenger proof containers on site. Where possible it is recycled. The remainder is collected
    by the local municipality.

    All users of the property participate in recycling by using standard procedures. Colour coded
    and labelled bins at focal points will be used to easily identify recycling options.

    Table 5.1: Materials for Recycled
    Metal                  Partnership in place with a metal recycling company to collect and take
                           for recycling
    Paper and Cardboard Paper bins
                           Cardboard and paper to be recycled
                           Large paper bins when volume allows
    Biodegradable    plant Compost bins
    waste                  Worm farms
                           Reuse on property in vegetable gardens and as compost
    Hard Plastic           Partnership with owl box manufacturers who collect for recycling into
                           owl boxes
    Soft Plastic           Partnership with Ecobrick Exchange to create Eco bricks as building
                           material
    Construction Waste     Construction waste to be used as backfill in future construction within
                           the property. This is a continuous and ongoing process.
    Glass                  Recycled at glass stations
    Other                  Recycled when possible

CES Environmental and Social Advisory Services                                              Hope Village S24G
                                                   22
FINAL Environmental Impact Report

    The following additional mitigation measures were implemented for the 24G alliable activities:

    Visual
        •     Vegetation has been incorporated into the design of each house
        •     Houses have been painted natural colours to fit in with the landscape
        •     Construction activities only took place during daylight working hours (i.e. 7am – 5pm)
        •     Construction activity and equipment was restricted to the site footprint

    Noise
        •     Construction activities only took place during daylight working hours (i.e. 7am – 5pm)

    Fire Risk
        • Flammable substances were stored in demarcated dry areas
        • Smoking was not allowed on site
        • Cooking was restricted to demarcated areas were fire risk was low
        • No open fires were allowed, unless in the demarcated areas
        • Fire extinguishers were available on site

    Sanitation
       • During the construction phase adequate sanitary facilities were provided for
           construction workers.
       • The facilities were regularly serviced to reduce the risk of pollution.
       • The facilities were located far away from any watercourses.

    Topsoil
        •    Topsoil and subsoil were separated during stockpiling.
        •    Areas that were rehabilitated/landscaped were covered with 150-200mm of topsoil on
             top of the subsoil.
        •    Topsoil was not stockpiled higher than 2m or for longer than 1 year.

    Vegetation
       • The footprint of the construction was kept as small as possible.
       • The construction area was demarcated.
       • Construction vehicles were not permitted beyond the demarcated construction site.

    Invasion of Alien Species
        • Many Seringa trees have been removed at the site where construction took place.

    Rehabilitation of Disturbed Areas
       • Some impacted areas were rehabilitated with species indigenous to the area.
       • Only topsoil from the immediate area was used for rehabilitation.
       • Many of the indigenous plants were removed from the construction areas and re-
          planted in gardens around the new buildings.

    Socio-Economic
       • Access was controlled to ensure no unauthorised people entered the site
       • Where possible, construction materials were bought locally
       • Where possible, local people were employed to help with construction

    6. IMPACT ASSESSMENT
    The impact assessment for the project is assessed in detail below.

CES Environmental and Social Advisory Services                                              Hope Village S24G
                                                    23
FINAL Environmental Impact Report

                                                                                                                                                                                     IRREPLACEABLE
                                                                                           SPATIAL SCALE

                                                                                                                                                                    REVERSIBILITY
                                                                                                                                       BENEFICIAL
                                                                                                                        (LIKELIHOOD)

                                                                                                                                       SEVERITY /
                                                                               NATURE OF

                                                                                                                          CERTAINTY

                                                                                                                                                                                                                  MITIGATION
                                                                                                                                                                                                                  POTENTIAL
                                                                                                            DURATION
                                                                                                                                                    SIGNIFICANCE

                                                                                                                                         SCALE
                                                                                IMPACT
                                                                                                                                                                                                                                                                                             SIGNIFICANCE

                                                                                                                            SCALE

                                                                                                                                                                                          LOSS
         THEME                      DESCRIPTION OF IMPACT                                                                                               PRE-                                                                                    MITIGATION MEASURES                               POST-
                                                                                                                                                     MITIGATION                                                                                                                                MITIGATION

                       Ridge vegetation lost                                                                                                                                                                                    •   The footprint was kept as small as possible.
                       (Moderate Sensitivity)                                                                                                                                                                                   •   The construction area was demarcated.

                                                                                                                                                                   Reversible
                                                                                                           Permanent

                                                                                                                                                                                    will be lost
                                                                                                                                                                                    Resource
                                                                                                                                                      MODERATE                                                                      Construction vehicles were not permitted beyond the        MODERATE

                                                                                                                                         Moderate
                                                                                           Localised
                                                                                                                                                                                                                                •

                                                                                                                                                                                                                   Difficult
                                                                                                                           Definite
                       The development of one of three housing unit, road,                                                                            NEGATIVE                                                                      demarcated construction site.                              NEGATIVE

                                                                                Direct
                       vegetable patch and Sewage packaging plant removed                                                                                                                                                       •   Many Seringa trees have been removed at the site
                       2180m2 of Ridge vegetation.
                                                                                                                                                                                                                                    where construction took place.
                       Degraded vegetation lost                                                                                                                                                                                 •   The footprint was kept as small as possible.

                                                                                                                                                                   Reversible
                                                                                                           Permanent

                                                                                                                                                                                                                   Achievable
                                                                                                                                                                                    will be lost
                       (Low Sensitivity)

                                                                                                                                                                                    Resource
                                                                                           Localised
                                                                                                                                                        LOW                                                                     •   The construction area was demarcated.                         LOW

                                                                                                                           Definite
                       The development of two of three housing units                                                                                  NEGATIVE                                                                  •   Construction vehicles were not permitted beyond the         NEGATIVE

                                                                                Direct

                                                                                                                                         Slight
                       removed degraded (infrastructure) vegetation.                                                                                                                                                                demarcated construction site.
     Loss of
     Vegetation                                                                                                                                                                                                                 •   Keep the footprint of the construction as small as
                       Loss of Moderately Sensitive Ridge vegetation for the                                                                                                                                                        possible, the area of construction should be

                                                                                                                                                                   Reversible
                                                                                                           Permanent

                                                                                                                                                                                    will be lost
                       proposed 6 housing units.

                                                                                                                                                                                    Resource
                                                                                                                                                      MODERATE                                                                      demarcated, and personnel not allowed to heavily           MODERATE

                                                                                                                                         Moderate
                                                                                           Localised

                                                                                                                                                                                                                   Difficult
                                                                                                                           Definite
                       The development of 6 housing units will remove 2,110                                                                           NEGATIVE                                                                      use the surrounding natural vegetation.                    NEGATIVE

                                                                                Direct
                       m2 of Ridge vegetation.                                                                                                                                                                                  •   Avoid any construction or related activity occurring
                                                                                                                                                                                                                                    within the grasslands outside of the property.
                                                                                                                                                                                                                                •   Keep the footprint of the construction as small as
                       Loss of Low Sensitive                                                                                                                                                                                        possible, the area of construction should be

                                                                                                                                                                                                                   Achievable
                                                                                                                                                                   Reversible
                                                                                                           Permanent

                                                                                                                                                                                    will be lost
                       Degraded vegetation for the proposed 6 housing units.

                                                                                                                                                                                    Resource
                                                                                                                                                        LOW                                                                         demarcated, and personnel not allowed to heavily              LOW

                                                                                           Localised

                                                                                                                           Definite
                       The development of 6 housing units will remove                                                                                 NEGATIVE                                                                      use the surrounding natural vegetation.                     NEGATIVE
                                                                                Direct

                                                                                                                                         Slight
                       degraded (infrastructure) vegetation.                                                                                                                                                                    •   Avoid any construction or related activity occurring
                                                                                                                                                                                                                                    within the grasslands outside of the property.
                                                                                                                                                                                                                                •   During the construction phase sanitary facilities were
                                                                                                                                                                                                                                    provided for construction workers.

                                                                                                           Short Term

                                                                                                                                                                                    achievable
                                                                                                                                                                   Reversible

                                                                                                                                                                                    will not be
                                                                                                                                                                                    Resource
                                                                                                                                                       LOW                                                                          The facilities were regularly serviced to reduce the         LOW
                                                                                           Localised
                                                                                                                                                                                                                                •
                       Construction crew sanitation

                                                                                                                           Definite
                                                                                                                                                     NEGATIVE                                                                       risk of pollution.                                         NEGATIVE

                                                                                                                                                                                    Easily
                                                                                Direct

                                                                                                                                         Slight
                                                                                                                                                                                                                                •   The facilities were located far away from any

                                                                                                                                                                                    lost
     Sanitation                                                                                                                                                                                                                     watercourses.

                                                                                                                                                                                                                   Achievable
                                                                                                                                                                                                                                    The packaging plant is fiberglass and sealed within a
                                                                                           Study Area

                                                                                                                                                                   Reversible
                                                                                                           Long Term

                                                                                                                                                                                                                                •

                                                                                                                                                                                    will not be
                                                                                                                                                                                    Resource
                                                                                                                                         Moderate
                                                                                                                                                     MODERATE                                                                       vinyl housing so that if any leaks should occur these        LOW
                                                                                                                           Definite
                       Operational use of the Sewage packaging plant
                                                                                                                                                     NEGATIVE                                                                       will be contained, and the two inspection pipes were       NEGATIVE
                                                                                Direct

                                                                                                                                                                                    lost
                                                                                                                                                                                                                                    installed to monitor any spillages.

                                                                                                                                                                                                                                •   Waste measurements in place on site include a
                                                                                                                                                                                                                                    designated and cordoned off general waste area and
                                                                                                                                                                                                                                    building rubble has been sectioned off with shade
                                                                                                                                                                                                                                    cloth.
                                                                                                                                                                                                                                •   During the construction phase, construction solid
                                                                                                                                                                                                                                    waste generated 300m3 by the project was gathered
                       Development and operation of the 24G activities                                                                                                                                                              and stored in an appropriate, central area on site.

                                                                                                                                                                                      Resource will not be lost
                                                                                                                                                     MODERATE                                                                       Where possible the construction waste was reused             LOW
     Waste             would have resulted in construction solid waste and
                                                                                                                                                     NEGATIVE                                                                       on site. The remainder has been kept on site and           NEGATIVE
                       general waste
                                                                                                                                                                                                                                    will be used as backfill in future construction within
                                                                                                                                                                                                                                    the property.
                                                                                                                                                                                                                                •   Currently all domestic waste produced (5m3/month)

                                                                                                                                                                                                                   Achievable
                                                                                                                                                                   Reversible
                                                                                                           Short-term

                                                                                                                                                                                                                                    is collected and stored in weather and scavenger
                                                                                                                                         Moderate
                                                                                           Regional

                                                                                                                                                                                                                                    proof containers on site. Where possible it is
                                                                                                                           Definite
                                                                                Direct

                                                                                                                                                                                                                                    recycled. The remainder is collected by the local
                                                                                                                                                                                                                                    municipality.

CES Environmental and Social Advisory Services                                                                 Hope Village S24G
                                                      24
FINAL Environmental Impact Report

                                                                                                                                                                                     Resource will
                       The construction of three housing unit, road,

                                                                                                                                                                      Irreversible

                                                                                                                                                                                                         Achievable
                                                                                                                                                                                     not be lost
                       vegetable patch and Sewage packaging would have

                                                                                                          Short-term
                                                                                                                                                            LOW                                                           Construction activities only took place during daylight     LOW

                                                                                              Localised
                                                                                                                                                                                                                      •

                                                                                                                        Probable
     Noise pollution   increased the ambient noise levels and could’ve been                                                                               NEGATIVE                                                        working hours (i.e. 7am – 5pm).                           NEGATIVE

                                                                                 Direct

                                                                                                                                      Slight
                       a nuisance for surrounding residents.

                                                                                                                                                                                     Resource will
                                                                                                                                                                                                                      •   No dust reduction measures were in place during the

                                                                                                                                                                      Irreversible

                                                                                                                                                                                                         Achievable
                       Development of the 24G activities may have resulted

                                                                                                                                                                                     not be lost
                                                                                                          Short-term
                                                                                                                                                            LOW                                                           construction process; however, this impact may not          LOW

                                                                                              Localised

                                                                                                                        Probable
     Dust              in dust generation during construction activities.                                                                                 NEGATIVE                                                        have been felt as there would be little impact due to     NEGATIVE

                                                                                 Direct

                                                                                                                                      Slight
                                                                                                                                                                                                                          lack of neighboring residents and little wind.

                                                                                                                                                                                                                      •   Some impacted areas were rehabilitated with species

                                                                                                                                                                                     Resource will not
                                                                                                                                                                                                                          indigenous to the area.
                       During the development and operation of the 24G
                                                                                                                                                                                                                          Only topsoil from the immediate area was used for

                                                                                                          Medium-term
                                                                                                                                                                                                                      •
                       activities Hope Village implemented rehabilitation                                                                                 MODERATE                                                                                                                  MODERATE

                                                                                                                                                                                                         Achievable
                                                                                                                                                                      Reversible
     Rehabilitation                                                                                                                                                                                                       rehabilitation.
                                                                                                                                                          NEGATIVE                                                                                                                   POSITIVE

                                                                                              Localised
                       measures to disturbed areas.

                                                                                                                        Definite
                                                                                                                                                                                                                          Many of the indigenous plants were removed from the

                                                                                                                                                                                     be lost
                                                                                                                                                                                                                      •

                                                                                 Direct

                                                                                                                                      Slight
                                                                                                                                                                                                                          construction areas and re-planted in gardens around
                                                                                                                                                                                                                          the new buildings.
                                                                                                                                                                                                                      •   Where possible, local people were employed to help

                                                                                                                                                                                     Resource will
                                                                                                                                                                                                                          with construction

                                                                                                                                                                      Irreversible

                                                                                                                                                                                                         Achievable
                                                                                                                                                                                     not be lost
                       Job creation during construction and operation of 24G                                                                              MODERATE                                                                                                                  MODERATE

                                                                                                          Long-term
                                                                                                                                                                                                                          Three permanent jobs were created on site as well as

                                                                                                                                      Beneficial
                                                                                                                                                                                                                      •

                                                                                                                        Probable
                                                                                              Regional
                       activities.                                                                                                                         POSITIVE                                                       temporary jobs during the construction phase. The          POSITIVE

                                                                                 Direct
                                                                                                                                                                                                                          temporary jobs equated to an average of 10 people
                                                                                                                                                                                                                          for 1 year
      Socio-economic

                                                                                                                                                                                     Resource will

                                                                                                                                                                                                         Achievable
                                                                                                                                                                      Reversible

                                                                                                                                                                                     not be lost
                                                                                                          Long-term
                       Increased housing and care for orphaned and                                                                                          HIGH                                                                                                                      HIGH

                                                                                                                                    beneficial
                                                                                                                                                                                                                          No mitigation required.

                                                                                              Regional
                                                                                                                                                                                                                      •

                                                                                                                        Definite
                       abandoned children during the operational phase.                                                                                   POSITIVE                                                                                                                  POSITIVE

                                                                                                                                    Highly
                                                                                 Direct

                                                                                                                                                                                                                      •   It is recommended that to optimize the benefit a
                       During the operational phase materials and products

                                                                                                                                                                                     Resource will
                                                                                                                                                                                                                          procurement policy should be put in place to ensure
                       that are needed to run facility will be sourced from

                                                                                                                                                                      Irreversible

                                                                                                                                                                                                         Achievable
                                                                                 Cumulative

                                                                                                                                                          MODERATE                                                                                                                  MODERATE
                                                                                                                        May Occur
                                                                                                                                                                                                                          that the local people and businesses benefit as much

                                                                                                                                                                                     not be lost
                                                                                                          Long-term

                                                                                                                                      Beneficial
                       local businesses and this will result in a boost of the
                                                                                              Regional

                                                                                                                                                           POSITIVE                                                       as possible.                                               POSITIVE
                       local economy of the immediate vicinity
                       and surrounding areas.                                                                                                                                                                         •   Where possible, construction materials were bought
    Cumulative                                                                                                                                                                                                            locally
    Impacts

                                                                                                                                                                                     Resource will not
                                                                                                                                      Highly beneficial
                       During the operation phase there will be an increase
                       in housing for orphaned and abandoned children. In                                                                                   HIGH                                                                                                                      HIGH

                                                                                                                                                                                                         Achievable
                                                                                 Cumulative

                                                                                                                                                                      Reversible
                                                                                                                                                                                                                      •   No mitigation required.
                                                                                                          Long-term

                       doing so the resources burden will be slightly reduced                                                                             POSITIVE                                                                                                                  POSITIVE
                                                                                              Regional

                                                                                                                        Definite

                                                                                                                                                                                     be lost
                       by ensuring private care of orphans.

CES Environmental and Social Advisory Services                                                                 Hope Village S24G
                                                      25
You can also read