Eskom Regulatory Clearing Account (RCA) - FY 2019 NERSA Public Hearings Date:10 February 2020 Klerksdorp, North West

 
CONTINUE READING
Eskom Regulatory Clearing Account (RCA) - FY 2019 NERSA Public Hearings Date:10 February 2020 Klerksdorp, North West
Eskom Regulatory Clearing Account (RCA)
FY 2019
NERSA Public Hearings
Date:10 February 2020
Klerksdorp, North West
Eskom Regulatory Clearing Account (RCA) - FY 2019 NERSA Public Hearings Date:10 February 2020 Klerksdorp, North West
Eskom’s RCA application in accordance with the
Electricity Regulation Act
Legal Basis of the MYPD methodology
The legal basis for the MYPD Methodology is provided in the Electricity Regulation Act (ERA), 2006 (Act
No. 4 of 2006). The Methodology is subordinate to the requirements of ERA and the Electricity Pricing
Policy. The requirements from these two documents will at all times supersede those of the Methodology.

Section 4(a)(ii) of the Act states that ‘the Regulator must regulate prices and tariffs’. Further, section 15(1)
and (2) of the Act prescribes the following tariff principles:

(1) A license condition determined under section 14 relating to setting or approval of prices, charges and
tariffs and the regulation of revenues –
       a) Must enable an efficient licensee to recover the full cost of its licensed activities, including a
       reasonable margin or return;
       b) Must provide for or prescribe incentives for the continued improvement of the technical and
       economic efficiency with which the services are to be provided;
       c) Must give end users proper information regarding the costs that their consumption imposes on the
       licensee’s business;
       d) Must avoid undue discrimination between customer categories; and may permit the cross subsidy
       of tariffs to certain classes of customers.

(2) A licensee may not charge a customer any other tariff and make use of provisions in agreements other
than that determined or approved by the Regulator as part of its licensing conditions.

         Eskom has made this Regulatory Clearing Account (RCA) application to recover
              efficient costs in accordance with the ERA and MYPD Methodology
                                                                                                                   2
Eskom Regulatory Clearing Account (RCA) - FY 2019 NERSA Public Hearings Date:10 February 2020 Klerksdorp, North West
NERSA’s prudency guidelines is the basis of
    Eskom’s RCA application
    (section 3.5 of the RCA application)
Extracts from NERSA’s Prudency Guideline

                                                  Page 5

                                                  Page 5

                                                  Page 8

                                                           3
NERSA’s prudency guidelines is the basis of
    Eskom’s RCA application
    (section 3.5 of the RCA application)
Extracts from NERSA’s Prudency Guideline

                                                  Page 12 & 13

                                                      Page 17
                                                                 4
NERSA’s prudency guidelines is the basis of
    Eskom’s RCA application
    (section 3.5 of the RCA application)
Extracts from NERSA’s Prudency Guideline

                                                                              Page 18

           Eskom has applied the principles of NERSA’s prudency guideline in this RCA
                                           application
                                                                                        5
Eskom fully supports NERSA decision with
addressing matters related to governance failures

  • On 7 March 2019, the NERSA Media statement as confirmed by the NERSA Chairman
    at the media briefing was as follows with reference to previous revenue decisions:
       “The Energy Regulator also considered that Eskom conceded that certain
       governance failures occurred in Eskom, however, at the time of the above decisions
       and although some of the adjustments were effected, the extent of the governance
       failures or amounts associated therewith had not been fully quantified. The Energy
       Regulator may initiate its own investigation into the governance failures in Eskom
       and may effect adjustments to Eskom’s revenue based on the relevant outcome of
       its investigation and/or those undertaken by bodies or entities, including, but not
       limited to, Eskom, National Treasury, the Special Investigating Unit, the South
       African Directorate for Priority Crime Investigation (Hawks), the Parliament of the
       Republic of South Africa or any Commission of Enquiry as and when they are
       concluded or a conclusive outcome is reached and the costs associated therewith
       have been quantified.”
  • Eskom is on record in support of this approach as clarified during previous submissions
  • As an example, the recovery from Mc Kinsey has already been included in the RCA
    balance determination related to the FY 2018

            Eskom is committed to complying with the approach decided by NERSA
                with regards to amounts associated with governance failures
                                                                                              6
The Regulatory Clearing Account (RCA) is the
    regulatory mechanism for risk management
RCA is a risk management mechanism to deal with variances between what was determined by
NERSA for purposes of its revenue determination, and what actually materialised (per Eskom’s
audited financial statements) - a backward looking reconciliation

   Landscape for RCA application:
   Focus of this consultation is FY 2019 RCA application. Various forward looking clarifications on Eskom’s
   operations are of interest. However, ample other opportunities are available for addressing these
   1. The submission is based on the MYPD Methodology, published by NERSA during October 2016
   2. It is further influenced by the decision and reasons for decision for MYPD 3 RCA for FY 2014
      published in March 2016
   3. The reasons for decision for MYPD 3 RCA FY 2015, 2016 and 2017 are being reviewed by the
      Eskom Board in a High Court application
   4. Due to uncertainty in the environment at that time, NERSA approved a single year application for
      2018/19
   5. The Energy Regulator decision for FY 2019 was an average nominal increase of 5.23%
   6. The Eskom Board initiated a process of reviewing the NERSA decision for 2019 through an
      application lodged at the High Court. The matter has been heard and a judgement is reserved.
   7. Once this RCA balance for FY 2019 determination has been made by NERSA, by 24 March 2020 in
      terms of the requirements of the ERA, a subsequent liquidation decision will be made
   8. The liquidation decision will inform on the extent and timing of the price adjustment

                                                                                                              7
Key RCA related Changes in MYPD methodology

The methodology as released in October 2016 now allows operating costs to be re-
measurable and the calculation for RAB and return has changed

                                        MYPD 3         MYPD 4
                                        methodology    methodology

            Revenue due to sales
            volume changes

            Primary energy costs

            Regulated Asset Base and    Previously
            Return                      was CECA

            Operating costs

                                                                                   8
RCA application FY 2019
    (Section 2.2 of RCA application)

                                             Decision      Actuals                          RCA          RCA
RCA for FY 2019                                                          Variance
                                             FY 2019       FY 2019                      adjustments     FY 2019
Total Revenue Rm                                190 348       179 892        10 456           (5 006)        5 450
Primary Energy , Rm                               86 094       99 489        13 395             3 392       16 786
Coal                                              39 177        49 903       10 726             1 689       12 416
Open Cycle Gas Turbines (OCGTs)                      345         3 768         3 423                -        3 423
Other                                                782             -         (782)                -        (782)
Other primary energy                               7 595         9 320         1 725                -        1 725
Independent Power Producers                       26 596        24 952       (1 644)            1 369        (275)
International Purchases                            3 216         3 740           524                -          524
Environmental levy                                 8 093         7 805         (288)                -        (288)
Demand Response – Instantaneous                      110             -         (110)              110             -
Demand Response – Supplementary                      162             -         (162)              162             -
Demand Response – Programme administration            18             -           (18)              62            44
Other costs                                     104 254       106 871         2 617             2 221        4 838
Depreciation                                      24 903        26 427         1 524                -        1 524
Return on Assets (ROA)                            28 117        28 107           (10)               -          (10)
Research & Development (R&D)                         112            90           (22)                          (22)
Demand Side Management (EEEDSM)                        -            29             29             (2)            27
Operating costs                                   51 122       52 218         1 096            2 223         3 319
Service Quality Incentives (SQI)                       -           166           166                -          166
FY 2019 RCA Balance Application                                                                             27 240
Nuclear decommissioning from RCA FY
                                                                                                                83
2013/14 decision phased in over 10 years
Total RCA balance                                                                                           27 323
                                                                                                                      9
Clarification of RCA adjustments

1    Revenue - (R5 006m)                              5 IPPs – R1 369m
Adjustments made to the revenue reflected in the      Adjustment related to recognition of capacity
AFS relate to ensuring that all billed revenue is     payments for the Department of Energy IPP Open
included by adjusting for non-electricity revenue,    Cycle Gas Turbine (OCGT) plants as well as
demand response revenue as well as excluding          reversal of provisions
any load shedding volume in the variances

2    Coal – R1 689m                                   6 Operation costs – R2 223m
                                                      Adjustments are mainly as a result of other
Adjustments from AFS related to application of
                                                      income (adjustment related to McKinsey refund
NERSA’s MYPD methodology
                                                      already included in a previous RCA balance
                                                      decision) and arrear debt (adjustment related to a
3    Other – R782m                                    cap on arrear debt in the revenue decision)
“Other” in the primary energy section illustrates a
mismatch between the NERSA revenue decision           7 EEDSM – (R2m)
and the primary energy decision
                                                      Adjustment related to the application of NERSA’s
                                                      MYPD methodology – i.e. the variance for
4    Demand response – R334m
                                                      programme costs is not a pass-through since
Adjustment related to the application of NERSA’s      Eskom achieved more MW compared to the
MYPD methodology – i.e. the variances for             decision
instantaneous and supplementary is not a pass-
through since Eskom achieved more MW and
GWh compared to the decision
                                                                                                           10
Eskom’s FY 2019 RCA submission is driven
substantially in specific areas – Revenue
Variance
                  The MYPD Methodology refers to the variance between the total actual and
   Legislation    total decision as below:
                  • 17.1.1.5 Adjusting for other costs (7) and revenue variances where the
                    variance of total actual revenue differs from the total allowed revenue

                  •   It would be incorrect to further divide the total actual revenue variance
   Approach           into fixed and variable elements – since the variable elements are already
                      addressed through the volume related aspects of the PE, etc costs. If this
                      is done – results in double counting to the detriment of the consumer
                      (when actual volumes are higher) or the detriment of Eskom (when actual
                      volumes are lower)
                  •   The total approach is in line with the MYPD methodology
                  •   The correction of such initial over-estimation/under-estimation of sales -
                      does not increase/decrease the overall cost to the consumers, but merely
                      represents deferred / advance recovery of the fixed cost as per NERSA
                      revenue decision

    Variance      •   NERSA determined a higher sales volume compared to what actually
                      materailised. Sales volume variances are due to lower international sales
    explanation
                      as well as poor economic conditions for local sales
                  •   Sales is ~3 922 GWh lower than the determination
                  •   Revenue from sales is R10 billion lower than the determination . After
                      various adjustments, revenue variance in RCA calculation is R5 450m

                                                                                                   11
Eskom’s FY2019 RCA submission is driven
substantially in specific areas – Operating
Expenditure
                  •   The new methodology allows for operational expenditure to be re-
   Legislation        measurable for RCA balance applications.
                  •   It requires the most recent prudently and efficiently incurred actual costs
                      when making a decision and adjusting for prudently incurred over or under-
                      expenditure on operating costs as may be determined by the Energy
                      Regulator

                  •   Many remnants of what seems to be a previous decision were abandoned
   Approach           in the final decision.
                  •   In addition, the decision is not made where the licensees and corporate
                      applications are considered. It was determined that the number of
                      employees would be aligned to the sales volume in 2008.
                  •   Recognition of other developments in the industry did not seem to have
                      been considered.

    Variance      •   The FY 2019 determination left Eskom with a funding shortfall. This
                      shortfall needed management intervention and a re-prioritisation of cost
    explanation
                      between the different licensees and cost categories
                  •   Key variances were experienced in employee benefit costs for the benefit
                      of Eskom. Eskom implemented extreme measures, such as an embargo
                      on external appointments to work within the financial constraints. Eskom
                      has assumed in its application that the efficient number of employees
                      would have reached 39 186 for FY 2019 but the actual number was 38 292
                  •   Variances for maintenance costs were in favour of the consumer. Due to
                      the financial constraints, Eskom was required to reprioritise, defer and
                      revise its approach to maintenance
                                                                                                    12
Eskom’s FY2019 RCA submission is driven
substantially in specific areas – OCGT
revenue
                  •   In accordance with the MYPD Methodology, the gas turbine usage should
   Legislation        be allowed as it was incurred to ensure security or supply and was utilized
                      as a last resort before the implementation of load shedding.

    Variance      •   The system operator was required to dispatch more OCGTs (both
                      Eskom’s and IPPs) than in the NERSA determination or assumed in
    explanation
                      Eskom’s application
                  •   The dispatch was undertaken in accordance with NERSA’s scheduling
                      and dispatch rules
                  •   The utilisation of OCGTs contributed towards minimising load shedding. In
                      accordance with the MYPD Methodology, the gas turbine usage should be
                      allowed as it was incurred to ensure security of supply and was done so
                      as a last resort before implementing load shedding
                  •   OCGTs were used during peak and emergency periods throughout the
                      year. OCGT and IPP usage reduced load shedding by providing additional
                      capacity. The use of OCGTs must be considered in combination with all
                      other available options to manage the power system
                  •   Reduced usage of the OCGTs would increase the incidents, duration and
                      severity of load shedding. The knock on effect of this would be worsening
                      plant performance and longer time periods to return to operation
                  •   Variance between determination and actuals for FY 2019 illustrate the
                      need to use OCGTs to minimise impact of load shedding on SA economy
                  •   The variance between NERSA’s decision and actuals for Eskom’s OCGTs
                      was ~R3.4 billion

                                                                                                    13
Eskom Regulatory Clearing Account (RCA)
FY 2019

Coal Cost variances
Coal accounts for 74% of the Primary Energy
       variance

                                                •   The Primary energy variance accounts for
   Coal cost              12, 416                   ~61% of the RCA balance. Of this coal
                                                    accounts for 74% of primary energy
      OCGT                 3,423                •   A large portion of the variance is due to the
                                                    R11 billion lower decision from NERSA of
   Other PE                         1, 725          which coal was the most impacted.
                                                •   The significant use of OCGTs was used to
       IPPs                           (275)         alleviate a constrained system and avoid
                                                    load shedding.
International
  Purchases
                                       524      •   OCGT IPPs where offset by the
                                                    Renewable IPPs.
        Levy                           (288)
                                                •   Variance in other PE is mainly due to start
                                                    up fuel and oil due to additional start-ups
       DMP                              44          that occurred

                                                •   The other reflected here is due to a
       Other                         (782)
                                                    mismatch between the NERSA revenue
                                                    decision table and the primary energy
       Total                           16,787       decision table in the reasons for decision
                                                    (R782 m)

                                                                                                 15
Eskom has applied the legislative framework
in arriving at the Coal cost variance

• The Energy Regulator will approve the coal benchmark price (i.e. average
  R/ton) per contract type (Cost Plus, Fixed Price, Medium-Term and Short-
  Term) and Alpha for each contract type in the final MYPD decision (MYPD
  Methodology par 12.2.1).

• The R/ton coal price and R/ton/km transport cost (rail and road) shall be
  escalated using the formula in the contracts. (MYPD Methodology 12.2.2)

• The coal benchmark price is determined by the Energy Regulator in order to
  be used in comparison with the actual coal cost for the purpose of determining
  pass-through costs.

• The coal benchmark price will be compared to Eskom’s actual cost of coal
  burn (R/ton) using a Performance Based Regulation (PBR) formula. The PBR
  formula is the maximum amount to be allowed for pass-through, calculated by
  applying the following formula per contract type:

• PBR cost (Rand) = (Alpha x Actual Unit Cost of Coal Burn + (1 – Alpha) x
  Coal burn Benchmark price) X Actual Coal Burn Volume.

                                                                                   16
Due consideration needs to be given to the
  Prudency criteria
  (section 3.5 of RCA application)

Apart from the MYPD Methodology, when assessing coal costs the Guidelines for
Prudency Assessment are key in terms of the extract below:

     Extracts from the Guidelines for Prudency Assessment:

     8.3 In assessing prudency, it is also necessary to make a distinction between
          forecast and committed costs, as explained below:

         a)   Forecast costs are costs that the utility has not yet paid, and which it still retains its
              discretion as to whether the disbursement thereof will be made

         b)   Committed costs are costs that the utility has already spent or has entered into a
              binding commitment to pay or is subject to other legal obligations that leave it with
              no discretion as to whether to make the payment in the future. The disallowance
              of committed costs is particularly problematic for a regulated utility because
              the utility and its shareholders will have no choice but to bear the burden of
              those costs themselves which in Eskom’s case shifts to the tax payer.

                                                                                          Page 17

                                                                                                           17
Lower base cost of coal in determination and impact of
 mining PPI index resulted in major RCA variance

In Eskom’s view, NERSA did not consider principles in MYPD methodology and guideline for
Prudency assessment in relation to committed costs, committed contracts and escalation of coal
costs of committed contracts

  NERSA’s assumptions in revenue decision                Why a different approach should have been
                                                         adopted by NERSA
  NERSA validated its approach of using a simple         A theoretically calculated composite index applied
  indexing of FY 2014 RCA R/t. The FY2014 R/t was        from 2014 may not have been applicable
  escalated using a mining index and coal transport
  costs were escalated using CPI.                        Coal costs and escalations are determined by the
                                                         underlying cost drivers of the colliery and through
                                                         negotiated outcomes. Thus, the escalation
                                                         mechanisms of the various contracts require rigorous
                                                         analysis

                                                         Expectation of coal to increase/decrease by mining
                                                         PPI and transport of coal to move by CPI without
                                                         considering underlying cost drivers which are
                                                         generally stipulated within contracts (as required by
                                                         the methodology) could result in major variances.
  Expectation for coal price to decrease in 2015 year.   Eskom’s cost from underlying contracts did not
                                                         decrease mainly because of the already committed
                                                         contracts.

                                                                                                                 18
Characteristics and basis of Mining PPI Index
 reflects a selling price output rather than a cost
 index - Coal and gas only weigh 25% of index
• The PPI is based on the mine gate price, i.e. first selling price from the mine.

• The mining PPI, as published by Stats SA, is a consolidated index, which is not representative of
  Eskom’s coal costs and therefore cannot be directly used to evaluate the escalation.

• Other components of index, e.g. gold & PGM, are influenced by basket of cost drivers that is different
  from that of coal.

• The index fluctuates based on the selling price of the commodity rather than the input or production
  price of that specific commodity.

Stats SA PPI for Mining:

                                                   19
NERSA’s decision for coal costs for FY 2019 period was
lower than its own decision and actual for FY 2018

      R/t
650
600                                                      • Revenue allowed for coal cost for
550                                                        FY 2019 decreased sharply from
                                                           FY 2018 to FY 2019.
500
450                                                      • On the coal side, this resulted in
400                                                        the benchmark R/t for FY 2019
                                                           being almost on par with FY 2017
350                                                        and falling below the benchmark
300                                                        R/t for FY 2018.
250
                                                         • NERSA has not clarified why it
200                                                        was considered reasonable that
150                                                        the R/t cost for FY 2019 would
                                                           decrease compared to the
100                                                        previous year, apart from stating
50                                                         that a composite index was
                                                           applied to the FY 2014 RCA R/t.
  0
 FY2017     FY2018   FY2019   FY2020   FY2021   FY2022

                                                                                                20
Decision to close Arnot Power Station also impacted
  RCA variance

NERSA’s assumptions in revenue decision               Why a different approach should have been
                                                      adopted by NERSA
All electricity generation related to Arnot Power     Arnot replacement power would have been
Station was removed by NERSA from the production      generated by a marginal cost power station with a
plan.                                                 coal cost probably higher than the weight average
                                                      cost determined by NERSA, as the production plan
Reduction in production at Arnot Power Station will   is derived on a least cost basis.
be transferred to other cheaper coal fired stations
where coal procured at a lower average R/t (36%       The practicality of change in generation mix and
lower than Eskom’s application);                      improvement of EAF must also be considered (as
                                                      per paragraph 12.1 of the methodology)

With regards to coal burn costs, NERSA disregarded    However, the existing coal contracts were
the MYPD methodology requirement to consider          considered in arriving at the revenue decision for FY
existing coal contracts when making the FY 2019       2020 in MYPD4- where the exact R/ton was
revenue decision.                                     determined to be prudent

The fuel procurement costs were considered as         The fuel procurement costs were not duplicated in
duplicated and therefore disallowed.                  the FY 2019 revenue decision and thus should not
                                                      have been disallowed

           Eskom had provided all the information related to coal contracts to NERSA.

                                                                                                              21
Nersa disallowed 20% of Eskom’s costs while Eskom’s
actual costs were 8% higher than that applied for

                    +7.82%                       • NERSA disallowed almost 20% of the coal
                                                   burn cost for which Eskom applied.

                                                 • NERSA’s allowed coal cost (R/t) for FY19
                 -19.34%               +33.67%
                                                   was lower than the FY18 projected R/t at
                                                   the time of application.

                                                 • Most of the coal in the application was
                                                   already contracted for.

                                                 • Even if Eskom removed all uncontracted
                               52                  coal from its application, Eskom would
R bn   49
                                                   not have met the allowed cost.
                      39
                                                 • Assumptions in the application regarding
                                                   coal production and removal of burn from
                                                   Arnot Power Station did not materialise.

                                                 • Additional ST/MT coal was purchased to
                                                   bring stock days to acceptable levels
                                                   which was the main reason for the actual
   Application     Decision   Actual               costs being 8% higher than the
                                                   application.

                                                                                              22
Eskom follows a defined contracting process for
coal as per Eskom’s procurement procedure
 1              2                3                     4                 5                6
A need /            Develop          Competitive
                                                         Evaluation of
                                                    Enquiry                                   Contract
requirement         Commercial       Tenders issued (RFP)                 Negotiations
                                                         tenders                              Award
is identified       Strategy         to the market

• The starting point for procurement is when a need for coal is identified, usually from the electricity
  production plan.

• A mandate is obtained from the appropriate governance committees to issue either an RFI or an RFP to
  the open market, giving respondents a duration within which to respond.

• Thereafter, responses are evaluated by the relevant teams and a shortlist compiled of potential suppliers
  with whom negotiations will be held.

• Depending on the mandate, negotiations may be concluded and contracts signed.

• Closed enquiries to be issued to the market in cases of urgent or emergency enquiries.
  Conditional upon National Treasury prior approval and is ratified by Eskom’s governance
  committees including board.

              The process is governed by Eskom’s procurement procedure 32-1034 which
           incorporates but not limited to the principles of the PFMA, PPFA, National Treasury
               Procurement Instructions, RSA Constitution, B-BBEE Act amongst others
                                                                                                              23
As part of an ongoing improvement process,
Eskom has identified levers to improve
efficiencies in the business
• Optimisation of coal stockholding to release working capital.
• Reducing the coal road haulage rate on the new transportation contracts
• Optimisation of coal prices in line with Long Term strategy
• Reinvestment of capital in Cost Plus mines
• Extension of currently favourable coal contracts where possible.
• TFR to provide own, build & operate rail solutions, so Eskom can focus on
  core business
• Re-negotiation of Majuba rail transportation rates with Transnet Freight Rail
• Renegotiation of some of the coal contracts on the higher end of the price
  spectrum.

                                     24
Conclusion
Conclusion on Eskom FY 2019 RCA application

 •   Eskom’s RCA application is based on MYPD Methodology and NERSA RCA FY 2014 reasons
     for decision

 •   Eskom’s revenue is determined by NERSA through a revenue application process and then the
     RCA process which this submission addresses. The RCA is meant to ensure that Eskom can
     recover its full efficient costs as the actual realities have occurred differently than assumed
     during the revenue decision

 •   Eskom’s RCA application is for R27 240m

 •   None of the financial ratios and free cash flow outcomes determined by NERSA has
     materialised

 •   Eskom has not yet recovered revenues, determined by NERSA to be efficient and prudent,
     incurred as far back as FY 2015, by FY 2020

 •   In addition, NERSA has decided that this trend would continue for revenues previously
     determined to be efficient and prudently incurred during the FY 2017 to only be recovered in the
     FY 2023. The methodology does not allow for the time value of money to be included

 •   In light of NERSA’s mandate to balance the impact on sustainability of Eskom with the impact of
     consumers, Eskom proposes that this RCA balance for FY 2019 be recovered as soon as
     possible
                                                                                                        26
27
You can also read