Economic Value of PSPs from a European Perspective - Dr. Klaus Engels, E.ON (Germany) HydroVision International, Sacramento, CA July 20th, 2011

Page created by Maria Yang
 
CONTINUE READING
Economic Value of PSPs
from a European Perspective
Dr. Klaus Engels, E.ON (Germany)
HydroVision International, Sacramento, CA
July 20th, 2011
Management Summary

     Up to date, pumped-storage plants (PSPs) are the only technology to store large
     amounts of energy with reasonable technical and financial efforts.

     Europe in general, but Germany in particular after the retreat from nuclear
     generation, provides strong support for renewables to reduce GHG emissions.

     Rising supply from volatile sources such as wind, PV and other non-controllable
     generation assets increases the demand for storage and reserve capacity.

     To show the real value of PSPs, business cases need to reflect revenues from
     wholesale and reserve market as well as effects within the generation portfolio.

     Applying a sophisticated evaluation method on E.ON’s latest PSP project, an
     increase of more than 90% in contribution margin could be observed.

     This method enables developers to base their business cases on more “realistic”
     scenarios and thereby point out the project’s economic viability – but also its limits.

                                                             Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro   2
PSPs can address three major challenges of the German
generation system – energy storage, reserve and flexibility
                                                                                   German market environment
                Key facts                               Key facts
                                                                          y Germany is Europe’s largest power market and 100%
 y Electricity production:             y Electricity production:            liberalized - strong political support for pumped-
   4,100 TWh                    7:1      590 TWh                            storage plants (e.g. 10 years grace period for grid fees)
 y Installed capacity:                 y Installed capacity:              y Energy: Guaranteed feed-in tariffs for non-controllable
   approx. 1,000 GW                      147 GW (approx. 2/3 thermal)       renewable energies require huge storage capacities
 y 40 PSPs operating                   y 22 PSPs operating                y Reserve: Increasing utilization of volatile renewables,
 y PSP capacity                        y PSP capacity                       rising demand of ancillary services, e.g. reserve energy
   approx. 20 GW                3:1      6.6 GW                           y Flexibility: Generation portfolio dominated by thermal
 y 2% of total installed               y 4% of overall installed            power plants with less flexibility than PSPs
   capacity                              capacity
                                                                          y Most prominent PSP developments:
 y Status-quo: 9% of                   y Status-quo: 16% of
   electricity generation                electricity generation
   from renewables                       from renewables
 y Target: 20% electricity             y Target: 30% electricity
   from wind in 2030                     from renewables in
   (~300 GW)                             2030

                                                                              Riedl 300 MW      Waldeck 2+ 300 MW                  Atdorf 1,400 MW

Source: www.eia.doe.gov, www.hydroworld.com; CIA Factbook, own research
                                                                                                Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro   3
The business case of E.ON’s Waldeck 2+ development is an
example for sophisticated computing of revenues for PSP
                                       Upper storage reservoir
                                            Waldeck 2 and 2+
                                                                           Project Features
                                                                                      y     1 Francis pump-turbine
                                                                   CAPEX              y     M&E equipment
  Upper storage                                 C                                     y     Cavern powerhouse
reservoir Waldeck 1                                               850 €/kW            y     Penstocks
                                 Waldeck 2+
                                     300 MW                                           y     Extension of upper reservoir
                                                            B
                             (exp. COD 2016)                                          y Operation from existing
                     A                               Waldeck 2      OPEX
                                                                                        control center
                                                      480 MW     5 €/kW p.a.          y Only minor effects on IRR
            Waldeck 1                               (COD 1975)
              135 MW
           (COD 2009)                                                                 y 10 years w/o grid fee
                                                                                      y 30 years of project lifetime
                                                                   Project              before major rehabilitation
  Lower storage                                                                       y Synergies through utilization
    reservoir                                                    environment
                                                                                        of existing site (upgrade)
  Waldeck group                                                                       y Geological risk (contingency)
Legend: Existing capacity, new build capacity

                      Need for adequate market models to assess the revenues of PSPs.
                                                                               Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro   4
Modeling needs to address wholesale and reserve market
and must also consider hydro-specifics in a portfolio
Wholesale and reserve market Thermal & hydraulic systems                                                                                                                                                                                                                            Evaluation method1)

Modellbildung                                                                                    1                    Modellbildung                                                                                                              3                          Methodology                                                                                                            5

  Märkte für Fahrplanenergie                                                                                            Hydraulische Erzeugung (I)                                                         Zufluss QZuf                                                      Two‐stage method as mixed whole‐number quadratic problem for
                                                                                                                                                                                                                              QZuf
                                                                                                                                                                                                                                                                             power generation and trading planning
    Spot- / Terminmarkt                                              Preis                                               zeitvariable natürliche Zuflüsse                                    Turbine
                                                                                                                                                                                                           QZuf                 Speicherbecken                                 Objective
       Š   Kauf und Verkauf von elektrischer Energie        Verkauf                                                       Minimal- und Maximaldurchfluss von                                                      Turbine      Pumpe                                             Determination of the maximum contribution margin of a generation pool consisting of thermal
       Š   Spotmarkt: stündliche Produkte                                                                                    Pumpen, Turbinen, Druckstollen u. ä.            Turbine                                 QZuf
                                                                                                                                                                                                                                                                                  and hydro power plants under consideration of spot and reserve markets
       Š   Terminmarkt: beliebige Produktdefinitionen                 Prohibitivpreis                                       zeitabhängige Absenk- und Stauziele
                                                                                                                                                                                                                                                                                                            Input data: generation, trading, load, reserve, control data
       Š   Modellierung über Preis-Absatz-Funktion,                                                                         Anfangs- und Endfüllstand für jedes Speicherbecken                          Turbine             QZuf       QZuf
                                                                        Einkauf
           aggregiert für gesamten Markt                                                                                    Revisionen und Zwangseinsätze                                                   Laufwasserkraftwerk                                                                                                          Decomposition
                                                                                        gehandelte
                                                        Emax,V                Emax,E    Energie                             Vorhaltung von Fahrplanenergie und Reserveleistung                                                                                                                          Lagrange Relaxation Co‐ordination of energy and reserve balance
                                                        K                     K                                                                         Zufluss
                                                                                                                                                                              t=1 t=2        t=n
                                                                                                                                                                                                                                                                            1st stage    thermal units (DP):         hydro units (SLP):               reserve market QP:       spot market LP:
                                                                                                                                        Oberbecken                                                                                                                                      parameters, e.g.:            parameters, e.g.:                 parameters, e.g.:       parameters, e.g.:
           Modellbildung                                                                                                              Modellbildung               Anfangs-                           End-
  Märkte für Reserve (I)                                                                                          2
                                                                                                                                                                  füllstand                          füllstand
                                                                                                                                                                                                                                                                      5                 ‐ min/max capacity
                                                                                                                                                                                                                                                                                        ‐ efficiencies
                                                                                                                                                                                                                                                                                                                     ‐ max capacity
                                                                                                                                                                                                                                                                                                                     ‐ efficiencies
                                                                                                                                                                                                                                                                                                                                                  ‐ capacity & energy prices
                                                                                                                                                                                                                                                                                                                                                   ‐ max salable capacities
                                                                                                                                                                                                                                                                                                                                                                               ‐ market prices
                                                                                                                                                                                                                                                                                                                                                                               ‐market volumes
                                                                                                                                             Turbine      Pumpe
                                                                                                                                                                                                                                                                                        ‐ min/ up‐ and down‐times    ‐ storage volumes           ‐ hourly request of energy
             Märkte für
    Reservebeschaffung     Reserve
                        durch ÜNB              (II)                                                                                     Reservestellung hydraulischer Kraftwerke
                                                                                                                                        Mittelbecken
                                                                                                                                                                                                                                                                                        ‐ cost components            ‐ grid tariffs

                                                                                                                                                                  Anfangs-                           End-
       Š   Für KW-Betreiber: nur Verkauf von Reserve                                                                                          Turbine             füllstand                          füllstand
       Š               Š Kriterium für Zuschlag der Angebote:
           Beliebige Produktdefinition                                                 Preis                                              Beispiel: Pumpspeicherkraftwerk bei Teilnahme an den Märkten für                                                                 2nd stage
                                                                                                                                                                                                                                                                                                               Hydro‐thermal power dispatch (close‐ended solution)
                                                                                                                                        Unterbecken                                                                                                                                                                                   QP
       Š                  Nur Leistungspreis merit-order
           Mindestangebotsmengen                                                           Leistungspreis +                                                  Fahrplanenergie und positive Minutenreserve
                                                                                           prA· gebotener
       Š               Î Modellierung Leistungspreis-Absatz-Funktion
           Aktivierungszeit                                              Verkauf                                                                                                                                                                                                                                    results evaluation: dispatch, contribution margin
                                                                                           Arbeitspreis                               Kontinuitätsgleichung: Vt = Vt-1 + Qt, Zufluss –Topologie
                                                                                                                                                                                       Qt, Abfluss                            hydraulisches Modell
                       Š Kriterium für Anforderung von
                          Reservearbeit: Arbeitspreis merit-order                          Leistungspreis                              Modellierung beliebig vernetzter Gruppen
                                                                                                                                         Mindestenergiemenge, z. B.                                                             V1Anf                V1End
                                                                                                                                      Î Hydraulischer                                                                                                           ...
                       Î Modellierung der Arbeitsanforderung über                                                                                 pos.Network-Flow
                                                                                                                                                      MR:
                                                                                            vorgehaltene
                          vom Arbeitspreis abhängige Anforderungs-                                                                        100 MW · 4 h = 400 MWh           Oberbecken
                          wahrscheinlichkeit (Zeitreihe)             RLmax,VK RLmin.Angebot Leistung
                                                                                                                                                                                                                                       QTu,FE QPu,FE
                                                                                             prA: Anforderungs-                            Leistungsgrenzen, z. B.
                                                                                                                                                                                   Turbine               Pumpe

                                                                                                                                                                                                                                                                          y An integrated algorithm
                                                                                                                                       FE: 80 MW, pos. MR: 100 MW                                                            QTu,RA                    QPu,RA
                                                                                             wahrscheinlichkeit
                   Bilaterale Reserveverträge (z. B. Stundenreserve)
                                                                                                                                                     pos. MR:
                       Š Bezug und Bereitstellung                                                                                       Energetische Berücksichtigung von                                                                                       ...
                                                                                                                                                                                                                               V2Anf                 V2End
                       Š U. U. längere Vertragslaufzeiten                                                                              Reservearbeit, z. B. mit Anforderungs-           Unterbecken
                       Š Ausgestaltung nicht standardisiert
                       Î Modellierung als fest abgesetzte Menge an Reserveleistung
                       Î Abruf und Vergütung von Reservearbeit analog zur Beschaffung durch ÜNB
                                                                                                                                           wahrscheinlichkeit pA = 0,2:
                                                                                                                                          0,2 · 100 MW · 1 h = 20 MWh
                                                                                                                                                         FE:                                                                 QTu,FE + QTu,RL ≤ QTu,max
                                                                                                                                                                                                                                                             Zeit
                                                                                                                                                                                                                                                                            optimizes the power plant
                                                                                                                                             80 MW · 1 h = 80 MWh                                                            Vmin ≥ c ⋅ PRL ⋅ tmin
                                                                                                                                                                                                                              QTu,RA= prA ⋅ QTu,RL
                                                                                                                                                                                                                                                                            scheduling on spot and
y Market simulation through y Detailed modeling of                                                                                                                                                                                                                          reserve market
  supply and demand           technical and hydraulic                                                                                                                                                                                                                     y Results: dispatch of
  modeling on wholesale and   constraints                                                                                                                                                                                                                                   portfolio and contribution
  reserve markets                                                                                                                                                                                                                                                           margin of PSP
                                                                                                                                                                                                                                                                           Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro                                                                        5
1) The applied IT tool was developed in cooperation with RWTH Aachen University
Consideration of all three revenue components leads to a
rise in contribution margin and a project IRR far above 10%
       Rise in contribution margin                                                           Sensitivity analysis of IRR
                                                       Case Scenarios                                                                                         Average deviation to IRR Base Case

                                                       [1] Base case (Capex incl. upfront payment if applicable, 30
                                                                                                                                                                              New Build
                                                       years, no rehab, no capacity tariffs or ancillary services, 75%

                           +92%             IRR >10%   share of concession's revenues)
                                                       [2] CAPEX +20%                                                                   +20%         -1,5%
                                                                                                                                                          -0,8%
                                                                                                                                                                      1

                                                       [3] CAPEX +10%                                                                   +10%                          2

                                                                                                                          CAPEX
200%                                                   [4] CAPEX -10%
                                                       [5] CAPEX -20%
                                                                                                                                        -10%
                                                                                                                                        -20%
                                                                                                                                                                      3

                                                                                                                                                                                  1,3%
                                                                                                                                                                                         2,3%

                                                                                                                                                    Waldeck 1
                                                                                                                                                                      4

                                                                                                                                                                      5

                                                       [6] GWh/a -10%                                                                   -10%             -0,9%        6

                                                       [7] GWh/a -5%                                                                     -5%                 -0,4%    7

                                                                                                                          Energy
                                                       [8] GWh/a +5%                                                                    +5%                           8

                                                                                                                                                                              0,7%

150%                                                   [9] GWh/a +10%                                                                   +10%                                  0,8%
                                                                                                                                                                      9

                                                                                                                                                                     10

                                                       [10] Capacity Tariff/Ancillary Services 50 €/kW                                50 €/kW                        11

                                                                                                                                                                                      1,9%
                                                       [11] Capacity Tariff/Ancillary Services 75 €/kW                    Tariffs     75 €/kW                        12

                                                                                                                                                                                             2,8%
                                                       [12] Capacity Tariff/Ancillary Services 100 €/kW                               100 €/kW                       13

                                                                                                                                                                                                    3,7%

                                                                                                                                       Waldeck
                                                                                                                                                                      1

                                                       [13] Lifetime 20 years                                                          20 years      -1,6%
100%
                                                                                                                                                                     15

                                                       [14] Lifetime 40 years                                            Lifetime      40 years                      16

                                                                                                                                                                             0,7%
                                                       [15] Lifetime 50 years                                                          50 years                                0,9%

                                                                                                                                       2 & 2+
                                                                                                                                                                     17

                                                                                                                                                                     18

                                                       [16] OPEX +50%                                                                   +50%             -0,9%       19

                                                       [17] OPEX +20%                                                      OPEX         +20%                 -0,4%   20

                                                       [18] OPEX -20%                                                                   -20%                               0,3%
50%
                                                                                                                                                                     21

                                                                                                                                                                     22

                                                       [19] Start of construction +1 years                                              + 1 year             -0,3%   23

                                                       [20] Start of construction +2 years                               Execution     + 2 years                      2

                                                                                                                                                                          0,1%
                                                       [21] Start of construction +3 years                                             + 3 years                     25

                                                                                                                                                                           0,2%
                                                                                                                                                                     26

                                                       [22] Rehab (after 31 years) 5% of CAPEX, lifetime = 50 years                   5% of CAPEX                    27

                                                                                                                                                                               0,9%

 0%                                                    [23] Rehab (after 31 years) 10% of CAPEX, lifetime = 50 years
                                                       [24] Rehab (after 31 years) 20% of CAPEX, lifetime = 50 years
                                                                                                                          Rehab      10% of CAPEX
                                                                                                                                     20% of CAPEX
                                                                                                                                                                     28

                                                                                                                                                                     29
                                                                                                                                                                              0,9%
                                                                                                                                                                              0,8%

       Sole wholesale        Wholesale + reserve
       market trading          market trading
                                                                                        The sensitivity analysis confirms that
        Portfolio effect                                                                upfront CAPEX, plant availability, and
        Reserve market                                                                  tariffs have the most significant
        Wholesale market                                                                impact on IRR.

                                                                                                                    Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro                                   6
Finally, additional PSP supply affects market prices, an
inevitable consequence that limits development potentials
                              Scenarios (renewables, nuclear, etc.)                                                                                                                                                                                                      Results
Übersicht Szenarien                                                                                                                                         2

  Betrachtete Markt‐ und Ausbauszenarien
                           Marktszenarien
                      Š   M1.          Kraftwerkspark 2015
                      Š   M2.          Kraftwerkspark 2020 bei Kernenergieausstieg
                      Š   M3.          KraftwerksparkEingangsdaten   ‐ Marktsimulation
                                                      2020 ohne Kernenergieausstieg                                                                                                                      6

                     Betrachtete Ausbauvarianten
                                                            Eingangsdaten Marktsimulation ‐ Kraftwerkspark
                      Š In Basisvariante Ausbau hydraulischer Kraftwerke übriger Marktteilnehmer enthalten
                      Š Abtastung des Ausbaus hydr. Kraftwerke
                                                            Installiertevon
                                                                         Kraftwerksleistung   Deutschland
                                                                            E.ON in 10 Varianten     je Marktszenario
                      Š Unterschiedliche Ausbaustufen für Tagespeicher (+/‐300 MW bis +/‐1500 MW) mit/ohne
                          Kombination eines Jahresspeichers (2015: +386/‐122MW 2020: +456/‐189MW)                            Anstieg der installierten Kraftwerkskapazitäten in
                                Ausbaustufen 2015 (M1)                               Ausbaustufen 2020Bewertung
                                                                                                           (M2/M3) ‐ Marktsimulation
                                                                                                                              Deutschland durch Ausbau erneuerbarer Energien                                 10
                                                                GW
                                                                                                                              (insbesondere durch zusätzliche
                                                       Installierte Erzeugungskapazität

                    MW                                                      MW
                                                                                                        Einfluss zusätzlicher                Turbinenleistung
                                                                                                                              Windenergieanlagen       On‐/Offshore)      in Abhängigkeit
                                                                                                  Zubau Leistun g
 Zubau Le is tung

                                                                                                        unterschiedlich             hoher Einspeisung
                                                                                                                             Kernenergieausstieg                    regenerativer
                                                                                                                                                      in M2 (2020) wird durch            Energien
                                                                                                                              neue Kohle‐ und Gaskraftwerke kompensiert
                                                                                                          Exemplarische       Betrachtung
                                                                                                                             Anstieg        einer Spitzenlaststunde
                                                                                                                                       der installierten Leistung in

                         Ohne Jahresspeicher Mit Jahresspeicher                  Ohne Jahresspeicher
                                                                                                         Merit order bei Gaskraftwerken
                                                                                                        Mit Jahres speicher
                                                                                                                                                zw. 2008 u. 2020
                                                                                                                               geringer WEA‐Einspeisung                 Merit order bei hoher WEA‐Einspeisung
                                                                                                                             Zusätzlicher Zubau von PSKW in Deutschland der
                                                                                                                              übrigen Marktteilnehmer berücksichtigt
                                                                                                                                                     Š    2015: Blaubeuren,
                                                                                                                               spez.                      SWU 45 MW Pump‐/Turbinenleistung
                                                                                                                                                                                       spez.
                                                                                                                           Erzeugungs‐               Š    2020: Atdorf,             Erzeugungs‐                             Nachfrage
                                                                                                                              kosten                Kostreduktion
                                                                                                                                                          EnBW 1000 MW Pump‐/Turbinenleistung            Kostenreduktion    (ohne ausgebaute
                                                                                                                                                    durch
                                                                                                                                                                       Nachfrage         kosten
                                                                                                                                                                       (ohne ausgebaute                  durch              Turbinenleistung)
                                                                                                                                                    Turbinenleistung
                                                                                               Weitere Rahmenbedingungen:                                              Turbinenleistung)                 Turbinenleistung
                                                                                                                                                                                                                                                Nachfrage
                                                                                           Netznutzungsentgelte für bestehende Wasserkraftwerke berücksichtigt           Nachfrage                                                             (inkl. ausgebaute
                                                                                                                                                                   (inkl. ausgebaute       Zus. Wind‐                                           Turbinenleistung
                                                                                              (D: 0,60 €/MWh (pumpen) / A: 2,17€/MWh (pumpen), 2,065 €/MWh (turbinieren)
                                                                                                                                                                          Turbinenleistung einspeisung

                                                                                                                                                                                                                                                                    Expansion stages
                                                                                                                                 installierte therm. Erzeugungsleistung                         installierte therm. Erzeugungsleistung

                                                                                                                                Î Zusätzliche Turbinenleistung führt zu Kosten‐ und somit Marktpreisreduktion
                                                                                                                                Î Verschiebung der Merit Order nach rechts bei hoher WEA‐Einspeisung führt zu geringerer
                                                                                                                                  Kostenreduktion der zusätzlichen Turbinenleistung durch flachere Steigung im relevanten Bereich
                                                                                                                                Î Aufgrund des stark nichtlinearen Verlaufs der Merit Order sind generell keine proportionalen
                                                                                                                                  Zusammenhänge in den Ergebnissen zu erwarten

                    Conclusion
                                          Economically viable PSP developments in Germany possible.
                                          Shifting of revenues between technologies due to portfolio effect.
                                                                                                                                                                                                                                                                    Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro   7
BACKUP
Contact details and CV
          Contact                                         Curriculum Vitae

           Dr. Klaus Engels               y University Degree in Electrical Engineering,
           VP Asset Risk and Governance     RWTH Aachen University, Germany
           T +49 871 694-4010             y University Degree in Economics,
           F +49 871 694-4008               FernUni Hagen, Germany
           M +49 170 8562698
           klaus.engels@eon.com           y 1997 – 2002    Academic assistant and PHD studies at
                                                           Department for Power Systems and
           E.ON Generation Fleet                           Economics (Prof. Haubrich),
           E.ON Wasserkraft GmbH                           RWTH Aachen University
           Luitpoldstraße 27              y 2002 – 2004    Asset Manager Transmission Grid
           84034 Landshut                                  RWE Energy AG, Dortmund
                                          y 2005 – 2008    Project Manager
                                                           Roland Berger Strategy Consultants,
                                                           Dusseldorf/Munich
                                          y 2008 – 2010    Head of Business Development
                                                           E.ON Wasserkraft, Landshut
                                          y since 2010     Vice President Asset Risk and
                                                           Governance Hydro, E.ON Fleet
                                                           Management Generation

                                                            Value of PSPs 20.07.2011 E.ON Generation Fleet Hydro   9
You can also read