Economic grid support services by wind and solar PV

Page created by Bonnie Reeves
 
CONTINUE READING
Economic grid support services by wind and solar PV
Economic grid support services
by wind and solar PV
a review of system needs, technology options,
economic benefits and suitable market mechanisms

Final publication of the REserviceS project        Co-funded by the Intelligent Energy Europe
                                                   Programme of the European Union
September 2014
Economic grid support services by wind and solar PV
Economic grid support services by wind and solar PV
Economic grid support services
                by wind and solar PV
                      a review of system needs, technology options,
                   economic benefits and suitable market mechanisms

                                 Final publication of the REserviceS project
                                                          September 2014

RESERVICES PROJECT - Final publication - September 2014
Economic grid support services by wind and solar PV
Project partners

          Principal Authors:                 Frans Van Hulle (XP Wind)
                                             Iván Pineda and Paul Wilczek (The European Wind Energy Association, EWEA)

          Authors (project partners):        Manoël Rekinger (European Photovoltaic Industry Association, EPIA)
                                             Paul Kreutzkamp (3E)
                                             Hannele Holttinen y Juha Kiviluoma (Technical Research Centre of Finland, VTT)
                                             Mariano Faiella y Diana Craciun (Fraunhofer Institute for Wind Energy and Energy System
                                             Technology, IWES)
                                             Gustavo Quiñonez Varela (Acciona Energía)
                                             Andrej Gubina (University College Dublin, National University of Ireland, NUID)
                                             Nicolaos Cutululis (Technical University of Denmark, DTU Wind Energy)
                                             Florian Chapalain (EDSO for Smart Grids)
                                             Joe Corbett (Mainstream Renewable Power)
                                             Bernhard Ernst (SMA Solar Technology)
                                             Stephan Wachtel, Goran Drobnjak, Bart Stoffer (GE Wind Energy)
                                             Pedro Godinho Matos (EDP Distribuição)
                                             Jorge Tello-Guijarro (Union Fenosa Distribución)
                                             Raphael Rinaldi (Enel Distribuzione)

          Project coordination and review:   Sharon Wokke (EWEA)

          Editing:                           Zoë Casey (EWEA)
                                             Adrienne Margolis (freelance proofreader)

          Acknowledgements (other project partners and Advisory Board):
          Justin Wilkes, Jacopo Moccia, Manuela Conconi, Diletta Zeni (EWEA), Dana Dutianu (EASME), Gaëtan Masson, Myrto Papoutsi
          and Scarlett Varga (EPIA), Carlos Diercksens and Aurore Flament (3E), Javier Lasa Garcia (Acciona), Ciara O’Connor and Mark
          O’Malley (UCD), John Shaw (Mainstream), Christoph Frenkel and Oliver Führer (SMA), Christoph Gringmuth (GE), Carlos Costa
          Rausa (Enel).

          Hans Abildgaard (Energinet.dk), Jacobo Alvarez and Pavla Mandatova (Eurelectric), Joachim Balke and Tadgh O’Briain (Euro-
          pean Commission), Miguel de la Torre (Red Electrica), Javier de la Torre (Fenosa), Kristof De Vos (KU Leuven), Yves Langer
          and Thijs Engels (BELPEX), Alejandro Gesino and Andreas Thum (TenneT), Jon O’Sullivan (Eirgrid), Alexandre Torreele and
          Manuel Galvez (ELIA).

          Acknowledgements (workshop speakers and other contributors):
          Ricardo Bessa (INESC TEC), Denis Cagney (CER), Karel De Brabandere (3E), Caitriona Diviney (IWEA), Sophie Dourlens-
          Quaranta (Technofi), Eike Erdmann (Enercon), Pablo Frías Marín (IIT Comillas), Rubén Gutiérrez Otero (EDP Distribuição), Tony
          Hearne (ESB Networks), Riccardo Lama (Enel Distribuzione), Miguel Lorenzo Sotelo (Red Electrica), Antonio Lopez Nicolas
          (European Commission), Jane McArdle (SSE), John Mc Cann (SEAI), Simon Muller (IEA), Sophie Müller-Godeffroy (BMU),
          Luca Colasanti (GSE), Javier Paradinas (EFET), Eckard Quitmann (Enercon), Marcus Merkel (EWE Netz), Ricardo Prata (EDP
          Distribuição), Juan Rivier Abbad (Iberdrola Renovables), Stephanie Ropenus (BWE), Juan Saavedra (Fenosa), Irinel-Sorin
          Ilie (GE), Matti Supponen (European Commission), David Trebolle (EDSO4SG), Andreas Wade (First Solar), Zoltan Zavody
          (RenewableUK).

          Björn Andresen, Frank Martin, and Henrik Kodahl (Siemens), Christian Benz Harald (DanFoss), Philip Carne Kjaer (Vestas),
          Martin Heidl (Fronius), Lourdes Garcia Caballero (Alstom), REpower, Luis Pascual (Sunedison), Michel Ryser (Solarmax), Mads
          Skjelmose (Vattenfall), Paula Souto Perez (WindVision), David Martinez and Javier Villanueva (Gamesa).

          Layout:                            EWEA
          Print:                             Artoos
          Production coordination:           Clara Ros and Zoë Casey (EWEA)
          Cover photo:                       Thinkstock

          4                                                                                      RESERVICES PROJECT - Final publication - September 2014
Economic grid support services by wind and solar PV
Coordinator

Partners

Agreement no.:              IEE/11/814/SI2.616374
Duration:			                April 2012 – September 2014
Coordinator:                The European Wind Energy Association

LEGAL DISCLAIMER
The sole responsibility for the content of this leaflet lies with the REserviceS consortium. It does not necessarily reflect the opinion of
the European Union. Neither this document nor the information contained herein shall be used, duplicated or communicated by any
means to any third party, in whole or in parts, except with prior written consent of the “REserviceS” consortium. Neither the EASME nor
the European Commission are responsible for any use that may be made of the information contained herein.

RESERVICES PROJECT - Final publication - September 2014                                                                                  5
Economic grid support services by wind and solar PV
6   RESERVICES PROJECT - Final publication - September 2014
Economic grid support services by wind and solar PV
Table of contents
1       EXECUTIVE SUMMARY AND POLICY RECOMMENDATIONS............................................... 11
        1.1       RECOMMENDATIONS - EU ENERGY POLICY AND ELECTRICITY MARKET DESIGN........................... 12
                  1.1.1 Recommendations for policy makers............................................................................ 12
                  1.1.2 Recommendations for market design - frequency support.............................................. 13
                  1.1.3 Recommendations for market design - voltage support.................................................. 14
        1.2       RECOMMENDATIONS - EU NETWORK CODES AND NATIONAL GRID CODES................................... 14
                  1.2.1 Requirements based on identification of system needs.................................................. 14
                  1.2.2 Contents and quality of requirements for generators for service delivery......................... 15
                  1.2.3 Management of grid code requirements........................................................................ 15
                  1.2.4 Harmonisation and standardisation.............................................................................. 15
        1.3       RECOMMENDATIONS - RESEARCH AND TECHNICAL DEVELOPMENT............................................. 15
                  1.3.1 Hardware.................................................................................................................... 15
                  1.3.2 Software and methods................................................................................................ 16
                  1.3.3 System operational procedures, methodologies and GSS deployment strategies............. 16
                  1.4.4 Standards.................................................................................................................. 16

2       INTRODUCTION...................................................................................................................... 17

3       RESERVICES MAIN FINDINGS.............................................................................................. 20
        3.1       SYSTEM NEEDS FOR GRID SUPPORT SERVICES BY WIND AND SOLAR PV.................................... 21
        3.2       TECHNICAL CAPABILITIES OF WIND AND SOLAR PV AS SERVICE PROVIDERS................................ 21
        3.3       ECONOMIC BENEFITS OF GRID SUPPORT SERVICES BY WIND AND SOLAR PV.............................. 22
        3.4       MARKETS AND COMMERCIAL FRAMEWORKS............................................................................. 23
        3.5       KNOWLEDGE GAPS AND NEED FOR R&D................................................................................... 24

4       SYSTEM NEEDS VS. GRID SUPPORT SERVICES FROM WIND AND SOLAR PV............... 25
        4.1       INTRODUCTION....................................................................................................................... 26
        4.2       CHANGING SYSTEM NEEDS WITH INCREASING WIND AND SOLAR PV PENETRATION..................... 26
                  4.2.1 General trend – increasing needs at rising penetration levels of VAR-RES........................ 26
                  4.2.2 Need for frequency support services............................................................................ 28
                  4.2.3 Requirements for voltage support services................................................................... 28
                  4.2.4 Requirements for system restoration services............................................................... 28
                  4.2.5 Regional differences in service requirements................................................................ 28
                  4.2.6 Methods of assessing system needs with VAR-RES are still evolving............................... 29
        4.3       RECOMMENDED KEY SERVICES FROM WIND AND SOLAR PV...................................................... 29
        4.4       HIGH VAR-RES PENETRATION ISSUES AT TRANSMISSION AND DISTRIBUTION LEVEL.................... 30
                  4.4.1 Transmission level...................................................................................................... 31
                  4.4.2 Distribution level......................................................................................................... 31
        4.5       INTERACTION OF NEEDS AND SERVICES AT TRANSMISSION AND DISTRIBUTION LEVEL................ 31
        4.6       CROSS-BORDER ISSUES OF NEEDS AND SERVICES................................................................... 31
        4.7       SPECIFIC NEEDS REGARDING LARGE SCALE OFFSHORE WIND DEPLOYMENT............................... 32
        4.8       SPECIFIC NEEDS REGARDING DISTRIBUTED SOLAR PV.............................................................. 32
        4.9       CONCLUSIONS – SYSTEM NEEDS............................................................................................. 33

RESERVICES PROJECT - Final publication - September 2014                                                                                               7
Economic grid support services by wind and solar PV
Table of contents

          5    CAPABILITIES OF VAR-RES AS GRID SUPPORT SERVICE PROVIDERS............................ 34
               5.1   INTRODUCTION....................................................................................................................... 35
               5.2   TECHNICAL ASSESSMENT OF VAR-RES CAPABILITIES FOR SERVICE PROVISION............................ 35
                     5.2.1 Existing capabilities to provide frequency and voltage support........................................ 35
                     5.2.2 Existing capabilities for system restoration support (SRS) from VAR-RES......................... 36
                     5.2.3 Recent technical developments of capabilities for system services................................. 37
               5.3   POWER SYSTEM IMPACT OF SERVICES PROVIDED BY VAR-RES................................................... 37
                     5.3.1 Frequency Control....................................................................................................... 37
                     5.3.2 Voltage Control........................................................................................................... 37
                     5.3.3 Provision of GSS with offshore wind plants................................................................... 38
                     5.3.4 Impact of aggregation and short term forecasting on GSS provision................................ 39
               5.4   TECHNO-ECONOMIC ASSESSMENT OF SERVICE PROVISION (GENERATOR LEVEL)......................... 39
                     5.4.1 Comparing costs of providing GSS with wind and solar PV.............................................. 39
               5.5   CHALLENGES FOR ENHANCING CAPABILITIES AND SOLUTIONS................................................... 41
                     5.5.1 Enhanced frequency and voltage support with VAR-RES: challenges and solutions........... 41
                     5.5.2 System Restoration Support with VAR-RES: technical challenges and solutions............... 45
               5.6   CONCLUSIONS - CAPABILITIES.................................................................................................. 46

          6    ECONOMIC BENEFITS OF VAR-RES BASED SERVICES....................................................... 47
               6.1   INTRODUCTION....................................................................................................................... 48
               6.2   VAR-RES IN FREQUENCY SUPPORT............................................................................................ 48
                     6.2.1 Cost-benefit of using VAR-RES in frequency support....................................................... 48
                     6.2.2 Cross-border sharing vs. VAR-RES in frequency support.................................................. 49
                     6.2.3 Other options for frequency support............................................................................. 49
               6.3   COST BENEFIT OF VAR-RES IN VOLTAGE SUPPORT...................................................................... 50
                     6.3.1 Cost-benefit of using VAR-RES to support voltage at high voltage levels........................... 50
                     6.3.2 Cost-benefit of using VAR-RES to support voltage at low/medium voltage levels.............. 50
                     6.3.3 Other options for voltage management......................................................................... 51
               6.4   COST-BENEFIT OF USING VAR-RES FOR SYSTEM RESTORATION................................................... 52
               6.5   THE EXCESSIVE COST OF REQUIRING CAPABILITIES FROM ALL GENERATORS.............................. 53
               6.6   CONCLUSIONS – ECONOMIC BENEFITS..................................................................................... 53

          7    MARKET CONCEPTS (COMMERCIAL FRAMEWORKS)........................................................ 54
               7.1   INTRODUCTION....................................................................................................................... 55
               7.2   THE ELECTRICITY MARKET – INTERFACE TO RESERVICES........................................................... 55
                     7.2.1 Differences in self-dispatch market types...................................................................... 55
                     7.2.2 Markets for reactive power for voltage support.............................................................. 55
                     7.2.3 GSS market in Europe in monetary terms..................................................................... 56
               7.3   IDENTIFICATION OF BEST PRACTICES IN DIFFERENT COUNTRIES................................................. 56
                     7.3.1 Frequency support services......................................................................................... 56
                     7.3.2 Voltage support services............................................................................................. 57
               7.4   KEY MARKET DESIGN/PRODUCT ADAPTATIONS TO OFFER ON GSS MARKETS.............................. 57
                     7.4.1 Suitable product characteristics for frequency support services...................................... 57
                     7.4.2 Suitable product characteristics for voltage support services......................................... 59
                     7.4.3 Procurement models enabling TSO/DSO coordination of GSS......................................... 59
               7.5   CONCLUSIONS – MARKET CONCEPTS....................................................................................... 59

          8                                                                                                 RESERVICES PROJECT - Final publication - September 2014
Economic grid support services by wind and solar PV
8      KNOWLEDGE GAPS AND FURTHER RESEARCH................................................................. 61
       8.1        INTRODUCTION....................................................................................................................... 62
       8.2        KNOWLEDGE GAPS.................................................................................................................. 62
                  8.2.1 System needs for GSS................................................................................................ 62
                  8.2.2 Technology................................................................................................................. 62
                  8.2.3 Markets/costs/economics.......................................................................................... 63
       8.3        R&D NEEDS............................................................................................................................ 64
                  8.3.1 System needs............................................................................................................ 64
                  8.3.2 Technology................................................................................................................. 64

9      THE RESERVICES PROJECT – A SYNOPSIS......................................................................... 65

10 REFERENCES......................................................................................................................... 67

11 LIST OF RESERVICES REPORTS (DELIVERABLES)............................................................. 69
       System needs for GSS...................................................................................................................... 70
       Wind and PV GSS capabilities and costs............................................................................................. 70
       Wind and PV GSS in future systems – Case Studies............................................................................ 70
       Recommendations for a future EU market for GSS.............................................................................. 70

RESERVICES PROJECT - Final publication - September 2014                                                                                                 9
Economic grid support services by wind and solar PV
Symbols and abbreviations

         BESS      Battery Energy Storage System              NPV       Net Present Value
         CAPEX     Capital Expenditure                        NWP       Numerical Weather Prediction
         CCGT      Combined Cycle Gas Turbine                 OCGT      Open Cycle Gas Turbine
         CHP       Combined Heat and Power                    OEM       Original Equipment Manufacturer
         DC        Direct Current                             OPEX      Operational Expenditure
         DEV       (project) Developer                        OS        Operating System
         DFIG      Doubly Fed Induction Generator             OLTC      On Load Tap Changer
         DG        Distributed Generation                     OTC       Over The Counter
         DS        Distribution System                        P         Power
         DSO       Distribution System Operator               PF        Power Factor
         eBOP      Electric Balance of Plant                  POC       Point of Connection
         ENTSO-E   European Network of Transmission System    PQ        Active versus Reactive Power
                   Operators for Electricity
                                                              PV        Photovoltaic
         ETS       Emission Trading Scheme
                                                              REG       Regulator
         FACTS     Flexible AC Transmission Systems
                                                              RM        Ramping Margin
         FCR       Frequency Containment Reserve
                                                              RMSE      Root Mean Square Error
         FFR       Fast Frequency Response
                                                              RoCoF     Rate of Change of Frequency
         FRCI      Fast Reactive Current Injection
                                                              RR        Replacement Reserves
         FRR       Frequency Restoration Reserves
                                                              SCR       Short Circuit Ratio
         GC        Grid Code
                                                              SET Plan Strategic Energy Technology Plan
         GCR       Grid Code Requirement
                                                              SNSP      System Non-Synchronous Penetration
         GCT       Gate Closure Time
                                                              SO        System Operator
         GSS       Grid Support Services
                                                              SRS       System Restoration Support
         HV        High Voltage
                                                              SSVC      Steady State Voltage Control
         ICT       Information and Communication Technology
                                                              SVC       Static Var Compensator
         IEM       Internal Electricity Market (EU)
                                                              TS        Transmission System
         LCOE      Levelised Cost of Electricity
                                                              TSO       Transmission System Operator
         LV        Low Voltage
                                                              VAR       Volt Ampere Reactive
         MPP       Maximum Power Point
                                                              VAR-RES Variable renewable generation
         MV        Medium Voltage
                                                              WF        Wind farm
         NC        Network Code
                                                              WPP       Wind Power Plant
         NCR       Network Code Requirements
                                                              WT        Wind Turbine

         10                                                                     RESERVICES PROJECT - Final publication - September 2014
© Shutterstock

EXECUTIVE SUMMARY AND POLICY RECOMMENDATIONS

RESERVICES PROJECT - Final publication - September 2014   11
Executive summary and policy recommendations

         Wind power and solar PV technologies can provide              transition of electricity networks. Revised governance
         ancillary or grid support services (GSS) for frequency,       for DSO/TSO interaction to properly coordinate fre-
         voltage and certain functions in system restora-              quency and voltage support, as well as restoration
         tion. The REserviceS project confirmed that variable          services provided by VAR-RES, is needed.
         renew­ able energy sources like wind and solar PV
         generation (VAR-RES) meet most of the capability                 If the political goal of achieving a truly inte-
         requirements for delivering such services, as pre-               grated Internal Energy Market goes beyond
         scribed in Grid Codes. Where enhanced capabilities               the energy-only market model, the roll-out of
         would be required, tech­nical solutions exist, but are           GSS market models throughout the EU must
         not used today because of economic reasons due                   be considered. Therefore, the following pro-
         to additional costs, of which REserviceS has made                ject recommendations need to be taken into
         an assessment. While in some countries financial                 account, in particular in the revision of the EU-
         incentives for VAR-RES with enhanced capabilities                wide Target Model and more specifically in the
         exist, this remains the exception rather than the                relevant network codes as well as in national
         rule in Europe. Appropriate operational and market               grid connection requirements.
         frameworks are therefore needed for enhanced par-
         ticipation of VAR-RES in GSS.
                                                                       1.1 Recommendations - EU energy
         The need for VAR-RES’ participation in GSS provision,         policy and electricity market design
         especially at high penetration levels, depends on the
         power system characteristics (for example its size and        These recommendations relate to regulatory frame-
         resilience) and how VAR-RES are integrated into it (for       works at national and EU level directly affecting
         example its dispersion and technical characteristics).        GSS provision from VAR-RES. These frameworks
         As GSS come with a cost, requirements for genera-             include present and future energy market design, the
         tor capabilities and service provision should demand          EU-wide target model, commercial frameworks, etc.
         only what is needed by the system to avoid exces-             The recommendations are primarily addressing the
         sive system costs. Importantly, REserviceS analyses           European Network of Transmission System Operators
         found that frequency management can be adequately             for Electricity (ENTSO-E), national TSOs and DSOs,
         and economically achieved with only a fraction of             market operators, the EU Agency for the Cooperation
         all installed VAR-RES generators participating in fre-        of Energy Regulators (ACER) and national regulators
         quency support.                                               as well as the European Commission and national
                                                                       energy policy makers.
         Therefore, preparing for future for future electricity sys-
         tems with large shares of VAR-RES requires detailed           1.1.1    Recommendations for policy makers
         studies and simulations to make well-founded esti-            • The role of GSS in the electricity market should
         mates of the needs and technical requirements.                  be expanded in the context of an increased share
         Moreover, detailed and clear specifications, as well as         of VAR-RES, and as part of a truly integrated Inter-
         market designs and products taking into account the             nal Energy Market (IEM). In order to reap the full
         characteristics of VAR-RES, are crucial for their partici-      benefits from GSS provided by VAR-RES, adequate
         pation in GSS provision.                                        market frameworks and technical requirements are
                                                                         needed;
         An increase of VAR-RES means that generating                  • The right balance between a market system (which
         capacity is increased in Distribution System Opera-             is harder to predict and controlled by the system
         tor (DSO) networks. Hence, DSO/TSO (Transmission                operators responsible for power system stability)
         System Operator) interaction will also be increasingly          with multiple participants (to encourage competition
         important in the ­future with large shares of VAR-RES.          and drive innovation) and the provision of GSS must
         DSOs in particular will have an increasing role in the          be found in each power grid;

         12                                                                               RESERVICES PROJECT - Final publication - September 2014
• Commercial provision of some GSS as alternative              investments, prices — be they related to bid-based
  market-based revenue streams for all generators              markets, auctions or capability payments to genera-
  should be considered. This would increase inves-             tors — should capture both the benefits provided to
  tors’ interest in power generation and help tackle           the system in terms of system operation cost sav-
  any potential generation gap in the electricity sector       ings and the value of such services;
  in a market-based way, as opposed to a subsidy in        •   To ensure adequate stakeholder involvement, a
  the form of capacity remuneration mechanisms;                regular multi-year consultation on the appropriate
• Recommendations on frequency and voltage support             regulatory regime for GSS should be established
  need to be considered when implementing a revised            including:
  EU-wide Target Model in the relevant network codes.          –– Governance and financial arrangements
  Existing network codes must be amended or revised            –– Power system studies
  in light of the findings in this study and new ones          –– Technical capabilities - definition and assessment;
  considered to enable GSS provision from VAR-RES;         •   National and EU policy makers should require the
• The functioning of existing day ahead and intraday           relevant system operators and ENTSO-E to deliver
  markets must be improved with shorter gate closure           mandatory cost-benefit analyses when EU network
  and more cross border integration in order to give           codes or national grid connection requirements are
  VAR-RES producers (short term) opportunities to              determined. Policy makers should also establish a
  trade their imbalances. A shorter forecasting time           clear framework for how to carry out a cost-bene-
  horizon would not only help to set up a level playing        fit analysis (CBA) in conjunction with a functional
  field for balancing conventional and variable gen-           commercial framework determining how GSS are
  eration, but would also lower the system operation           procured and remunerated;
  costs;                                                   •   In addition to working out precise network codes,
• Commercial provision of GSS should be taken into             which encompass the market design provisions laid
  account in the revision of the EU-wide Target Model.         out in the Target Model, a proper implementation and
  Today GSS provision from VAR-RES is not considered           roll-out of GSS markets by the Member States and
  in either intraday or balancing markets. Moreover,           facilitated by ACER and national regulators is key;
  the development of GSS markets is not envisaged          •   Using GSS will require extensive cooperation and
  in the Target Model, even if GSS would constitute            clear boundaries between TSOs’ and DSOs’ rights
  part of the IEM, alongside trading electricity;              and duties. With regards to the TSO/DSO interface,
• The revision of the EU-wide Target Model should              guidelines should be developed on how the distri-
  be accompanied by an implementation roadmap                  bution system can contribute to grid reliability and
  describing the capabilities and GSS needed with              stability. Guidelines on implementing the results of
  increasing VAR-RES levels. There should also be a            system studies in grid code requirements should
  set of pre-qualification and procurement methods             also be drawn-up.
  pointing at requirements to be included in existing
  and future network codes;                                1.1.2 Recommendations for market design -
• Compulsory GSS requirements that are not remuner-        frequency support
  ated should be minimised or replaced by remuneration     • VAR-RES’ capability to provide frequency support,
  schemes, as it is neither cost-efficient nor necessary     in particular Frequency Containment and Frequency
  to request services from all connected generators in       Restoration Reserve (FCR and FRR), to the extent
  most systems. Market based remuneration provides           that it is beneficial (reliability vs. cost) to the system
  incentives for cost-reduction irrespective of whether      should be financially compensated, as well as its
  these are VAR-RES or conventional plants;                  readiness and utilisation costs;
• Policy makers should properly evaluate the cost/         • Characteristics of products such as low minimum
  benefit ratio of the proposed solutions for market         bid sizes, separation of up- from downwards bids,
  based frameworks and assign appropriate price              inclusion of confidence intervals and aggregated
  ranges for the provision of GSS. To incentivise            bids and offers are important for allowing VAR-RES

RESERVICES PROJECT - Final publication - September 2014                                                            13
Executive summary and policy recommendations

             to participate cost-effectively in GSS provision;         • If a tendering or auctioning process is applied, it
         •   Clear procurement rules together with clear techni-         should involve:
             cal specifications are of crucial importance for the        –– An analysis of the need for reactive power carried
             participation of VAR-RES in GSS provision;                     out by the relevant network operator (TSO/DSO)
         •   Frequency support related GSS provided by VAR-RES              and a forecast for future locational needs;
             require harmonised gate closure times as close as           –– Based on such an investigation, a tender for
             possible to delivery and minimised time frames                 reactive power within a certain perimeter should
             (less than one hour);                                          be published or an auctioning system should be
         •   For cost-efficient offers to be provided with high cer-        put in place to receive the lowest cost reactive
             tainty, the market design should encourage PV and              power provision;
             wind to offer reserve products from aggregated port-        –– The best offer (or best offers) is awarded with
             folios of several PV and wind power plants, which              a fixed reimbursement for the reactive power
             can be spread across wider areas. Alternatively, the           provided to the system and a minimum off-take
             uncertainty can be aggregated over all units par-              guarantee to ensure investment security.
             ticipating in the reserve. This function should be
             facilitated by the system operator and would elimi-       1.2 Recommendations - EU net-
             nate the need for overlapping safety margins due to       work codes and national grid codes
             forecast inaccuracy, unexpected power plant failure
             and performance compliance;                               Recommendations in this section are addressed to
         •   Market participants should be incentivised to be in       network operators, TSOs and DSOs. Some may spe-
             balance in the Balancing Responsible Party’s (BRP)        cifically address ENTSO-E and its working groups.
             perimeter after gate-closure time. Flexibilities of
             VAR-RES could then be used by the BRP manager             1.2.1 Requirements based on identification
             when they prove to be the most cost-efficient. This       of system needs
             would also reduce the need for reserve power for          • System studies should constitute the principal
             balancing by the TSO.                                       basis for network codes and grid codes in their for-
                                                                         mulation of requirements for VAR-RES. The studies
         1.1.3 Recommendations for market design -                       and their implementation in grid codes should con-
         voltage support                                                 sider frequency support needs and voltage needs
         • Voltage support induces costs for VAR-RES but can,            at the appropriate system level (system wide and
           in some cases, help system operators to manage                cross-border versus localised needs);
           their network in the most efficient way. In areas           • Requirements based on system studies should take
           with only a small amount of VAR-RES plants provid-            into account (expected) VAR-RES penetration. Net-
           ing the service needed by the network operator, a             work operators should not ask for more than needed
           non-remunerated mandatory band requirement as                 but, as a unit can last more than 20 years, expected
           part of the grid code could be complemented with              renewable energy penetration should also be taken
           payment for additional support to grid operation,             into account when defining capabilities (to avoid
           provided such costs are recognised by the regula-             costly retrofit and/or burdening new generators);
           tor and recoverable by the system operator. If the          • Frequency control (FCR and automatic FRR) capabil-
           number of service providers is large enough to                ity should not be required from all VAR-RES plants
           create a competitive market, voltage support could            connected to the network as it would not be cost-
           be reimbursed in a competitive process, either in             effective. How much is needed and where, should
           a regular bidding process or an auctioning arrange-           be based on system studies and further research;
           ment, irrespective of whether the contracting is for        • Voltage control capability should only be required
           short time horizons i.e. from days to weeks, or for           from VAR-RES when the analysis of the expected
           longer time horizons up to several years;                     costs compared to all other voltage control provision

         14                                                                               RESERVICES PROJECT - Final publication - September 2014
methods shows it is the most cost-effective solution      distributed generators;
   for the particular combination of generator type and    • Market frameworks should take into account the
   primary energy source, considering the likely future      characteristics of available and future power sources
   expansion of generation, demand and grids.                and their capabilities: the requirements should be
                                                             clear, precise and based on market design taking
1.2.2 Contents and quality of requirements                   existing capabilities into account;
for generators for service delivery                        • TSOs and regulators should establish clear proce-
• Network Codes and Grid Codes should provide                dures and reporting rules distinguishing balancing/
  detailed specifications for minimum technical              congestion management and curtailment for system
  capabilities for generators to participate in GSS.         security. They should coordinate the implementation
  Requirements should be function-oriented in                of these rules with the DSOs.
  addressing design capabilities and delivery per-
  formance. They should not prescribe technical            1.2.4    Harmonisation and standardisation
  solutions to reach a certain performance;                • TSOs and DSOs should contribute to the develop-
• State of the art forecast methods should be imple-         ment of European product standards (e.g. IEC,
  mented in the operation of VAR-RES. TSOs should            Cenelec) to avoid costly mismatches between grid
  improve their forecasting utilising state of the art       connection requirements and product standards.
  techniques during operations, while increasing             Standardisation is based on best practices and is
  cross-border cooperation to reduce unexpected situ-        essential for LV and MV connected systems. The
  ations due to forecast errors;                             EN 50438 European Standard and the Technical
• Requirements for generators should take into               Specification TS 50549 have to be considered when
  account their specific technology and the primary          specifying new grid connection requirements;
  source driving it. Only by doing so can system           • Exchange of data (including forecasts) between gen-
  service provision be optimised. Different types of         erating facilities and the relevant network operators
  generators (e.g. wind turbine conversion Type 3 and        (TSOs, DSOs) should be standardised. Common
  Type 4) and different energy sources (PV vs. wind)         forecast platforms, procedures and file formats will
  need different levels of investment to roll-out their      improve information exchange and reduce errors;
  GSS provision. In order to create a level playing        • Prequalification processes and testing procedures
  field for all of them, these specifications need to be     for generators providing GSS should be harmonised.
  included in the requirements for specific GSS;
• When designing the requirements and the frame-           1.3 Recommendations - research
  work for the procurement of GSS at the distribution      and technical development
  level, the spatial distribution should also be taken
  into account to avoid cost inefficiencies that could     REserviceS identified technology and process gaps
  result from a one size fits all approach;                that could be addressed by focused R&D efforts ena-
• Grid codes should consider the formulation of tech-      bling improved (technically/economically) provision of
  nical requirements for extremely fast frequency          services by VAR-RES. The recommendations consist
  response (e.g. full response faster than ¼ second)       of research topics in four categories: hardware, soft-
  for situations in the power system with low inertia;     ware and methods, system operation procedures and
• Requirements at the European and national level          standards. Stakeholders for these recommendations
  should, where possible, make reference to speci-         include the VAR-RES industry, TSOs, ENTSO-E and the
  fications in existing or upcoming European or            research community.
  international standards.
                                                           1.3.1    Hardware
1.2.3         Management of grid code requirements         Further development of hardware including designs
• In order to enable proper implementation and             enabling VAR-RES to provide GSS:
  monitoring of requirements, network operators            • Communication infrastructure for the provision of
  should organise the data exchange and visibility of        services by portfolios of MV/LV connected systems

RESERVICES PROJECT - Final publication - September 2014                                                        15
Executive summary and policy recommendations

             such as solar PV systems and wind farms;                  (especially using probabilistic forecast methods) in
         •   Metering devices for the provision of services by         power system operation;
             portfolios of MV/LV connected VAR-RES;                •   Optimisation strategies for the provision of GSS by
         •   Reliable communication hardware for very fast             portfolios of MV/LV connected systems such as PV
             system services;                                          systems or small wind farms;
         •   Monitoring systems to enable HVDC connected wind      •   Common methodology for assessing system needs
             farms (WF) and/or WF clusters to provide reliable         of GSS with large amounts of VAR-RES;
             frequency support;                                    •   Developing methods and tools power system
         •   Study of the effect of sustained GSS provision on         models able to capture different operational time
             wind turbine loads and possible impacts on its            scales, i.e. models focusing on electromechanical
             design.                                                   dynamics (20ms to 30s), focusing on system bal-
                                                                       ancing (5 min to 24h), focusing on frequency quality
         1.3.2     Software and methods                                for services such as FCR and FRR (s to min), for
         Further development of software tools to improve              power systems with high variability;
         technical and operational capabilities for the deploy-    •   Definition (technical and economic) of new GSS and
         ment of GSS by VAR-RES:                                       study of their impact on the system;
         • Improvement of probabilistic forecasts to be used in    •   Practices and tools for system planning and volt-
           system operation;                                           age profile simulations including the use of services
         • Control and coordination algorithms to enable HVDC          provided by inverters and novel components. This
           connected WF and/or WF clusters to provide reliable         would make the best of existing or future capabili-
           frequency support;                                          ties available at the distribution level;
         • Advanced control strategies for improved grid           •   Investigation of technical requirements and opera-
           friendliness of VAR-RES and enhanced capability of          tional practices for VAR-RES to be included in power
           providing system services;                                  system restoration processes.
         • Better understanding of technical requirements and
           control strategies for VAR-RES operating in hybrid AC   1.3.4      Standards
           and DC multi-terminal networks.                         Development of further standards required for large
                                                                   scale deployment of GSS by VAR-RES:
         1.3.3 System operational procedures,                      • IT standards to assure the secure and reliable
         methodologies and GSS deployment strategies                 operation of the power system’s infrastructure;
         Further development of methodologies and opera-           • Communication protocols for very fast system
         tional procedures for deploying GSS and improving           services.
         system operation:
         • Probabilistic planning and operational procedures

         16                                                                             RESERVICES PROJECT - Final publication - September 2014
© Shutterstock

INTRODUCTION

RESERVICES PROJECT - Final publication - September 2014   17
Introduction

          The anticipated high shares of wind and solar PV in           in terms of network codes covering market design
          the European electricity system will require fundamen-        and network management rules. So far network
          tal changes in the way transmission and distribution          codes have only marginally covered intraday and
          network operators use grid support services (GSS)             balancing market design and have not yet been con-
          from generators to manage network frequency, volt-            sidered for GSS;
          age and system restoration. These changes will be           • Rapid developments in control and communication
          twofold: the power system needs for GSS will change           technologies with profound impact on control of gen-
          as VAR-RES increase, and the technical and economic           eration plants (including VAR-RES) and management
          characteristics of VAR-RES change the way these ser-          of electricity systems in general;
          vices can be provided. The REserviceS study was set         • An increased electrification of society, electricity
          up to assess the provision of GSS by VAR-RES, in order        consumers increasingly become “prosumers” by
          to help design market mechanisms that would enable            installing Distributed Generation (DG) at their facil-
          power systems in Europe to function safely, reliably          ity (household PV, industrial PV and CHP etc.).
          and cost-efficiently with very high shares of VAR-RES.
          The study carried out by the REserviceS consortium          The REserviceS study has made a technical-eco-
          has focused on wind and solar PV because these are          nomic assessment of the provision of GSS — notably
          expected to jointly produce the lion’s share of renewa-     frequency and voltage support — as well as
          ble electricity needed to reach the EU’s 2020 targets.      preliminary analysis of system restoration by VAR-RES
                                                                      themselves. The study adds to existing knowledge to
          The setting for GSS in future European electricity          establish costs and values for GSS that can be pro-
          systems is characterised by the following important         vided on a large scale by wind power and solar PV,
          developments:                                               installed both at transmission and distribution level in
          • Fundamental changes in the generation mix, result-        the power system. The REserviceS project aims to con-
            ing in fewer traditional providers of GSS, the entry      tribute to the development of effective market-based
            of large numbers of decentralised renewable plants,       approaches for GSS in Europe and to the design of
            predominantly at low and mid voltage level, driven by     electricity market mechanisms that enable the power
            national and European climate and energy policies,        systems in Europe to function safely, reliably and cost-
            increased competitiveness of VAR-RES and chang-           efficiently with very high shares of VAR-RES.
            ing business cases for non-VAR-RES conventional
            plants;                                                   Research questions in this report address five themes:
          • The political aim to create an integrated Internal        • System needs for GSS (frequency, voltage and
            Energy Market (IEM) in the EU and creating competi-         system restoration) to develop when the shares of
            tion in wholesale and retail energy markets following       VAR-RES are very high;
            the unbundling of vertically integrated utilities. This   • Technical and economic issues for VAR-RES to pro-
            includes facilitating the entrance of new market            vide the necessary services;
            players and the integration of electricity markets        • Economic benefits of large scale provision of ser-
            throughout Europe on all timescales which would             vices by VAR-RES;
            entail GSS markets;                                       • Suitable market conditions and commercial
          • A regulatory framework at EU level for power market         frameworks;
            integration enshrined in the EU-wide target model         • Knowledge gaps and needs for R&D.
            outlining principles of cross-border capacity allo-
            cation and market coupling, as well as increased          These topics have been analysed at several stages
            TSO cooperation through European bodies such as           of the project. In the first stage, REserviceS analysed
            ENTSO-E;                                                  how system needs for grid services change in the grow-
          • A new legislative layer through binding EU regulations    ing presence of wind and solar PV, and identified key

          18                                                                             RESERVICES PROJECT - Final publication - September 2014
services that should be provided by these VAR-RES.              This publication also contains references to specific
In a second stage a technical and economic assess-              reports (Project Deliverables) where detailed analyses
ment was performed on the capabilities of wind and              and results can be found. A list of these Deliverables
solar PV for the provision of such services. The third          can be found at the end of this publication.
stage consisted of case studies looking at technical
and economic impacts in transmission and distribu-              Policy recommendations are aimed at EU Network
tion grids — simulating effects of large deployment of          Codes (RfG, balancing, DCC, operation etc.), the
services and assessing costs and benefits. In the last          EU-wide Target Model and related (regional) market
stage the findings have been integrated into a com-             models, energy policy processes and scenarios, (grid)
bined report as well as a separate recommendations              infrastructure (e.g. ICT), energy regulation and SET
report1. The integration of the project findings included       Plan and R&D (see D7.2 Recommendations3). The
an initial exploration of procurement methods of fre-           proposals have been made by the REserviceS con-
quency and voltage support services by TSOs and                 sortium, consisting of wind and solar energy industry
DSOs. It outlined possible market mechanisms in                 associations and industrial companies, knowledge
the context of the further integration of the European          institutes specialising in VAR-RES energy markets and
electricity market. The study also helped to identify           power system studies, as well as a European associa-
knowledge gaps and topics for further research into             tion of distribution system operators.
the provision of GSS by variable generation.
                                                                The REserviceS consortium also interacted with
This publication presents a summary of the key find-            stakeholders (industry and network operators) during
ings and recommendations of the project. More detail            workshops4, through surveys and discussions with the
can be found in D7.1 REserviceS Synthesis Report2.              Advisory Board.

                                                                                                                         © Acciona Energía

1
    REserviceS D7.2
2
    REserviceS D7.1
3
    Available at http://www.reservices-project.eu/wp-content/uploads/140724_REserviceS_D7.1_Synthesis-report.pdf
4
    For more information, please consult: http://www.reservices-project.eu/events/

RESERVICES PROJECT - Final publication - September 2014                                                            19
Introduction
© Acciona Energía

                          RESERVICES MAIN FINDINGS

                              20                     RESERVICES PROJECT - Final publication - September 2014
3.1 System needs for grid support                           DSO/TSO interaction will be increasingly important in
services by wind and solar PV                               the future with large shares of VAR-RES, and DSOs
                                                            will have a growing role in the transition process in
REserviceS’ assessment of needs in European power           electricity networks. Data exchange and ability to con-
systems focused on frequency and voltage support as         trol a multitude of small generation units should be
the main categories of grid support services (GSS) that     structured. Roles and responsibilities for coordinating
wind and solar PV generation can provide. Frequency         frequency and voltage support as well as restoration
and voltage control constitute several services with dif-   services need to be clarified.
ferent response times.

Generally, the system needs for identified frequency        3.2 Technical capabilities of wind
support services will increase with high shares of VAR-     and solar PV as service providers
RES. There is a need for enhanced frequency support
in the system especially for manually activated system      Technology analysis of wind power and solar PV con-
reserves or Frequency Restoration Reserves (FRR) with       firmed their technical and operational capabilities
activation times of less than 15 minutes. VAR-RES may       to provide GSS for frequency, voltage and certain
increase the need for voltage support because reac-         functions in system restoration. This analysis was
tive power sources, both steady state and dynamic,          validated through industry enquiries and assumes
that are available today to the system operator are         adequate operational and economic frameworks are
likely to be reduced in the future. Also, the voltage       put in place. The technical and operational functionali-
profile management will become more complex with            ties required are either state of the art using existing
increasing shares of VAR-RES. New services will be          hardware, or can be implemented at a reasonable
needed, mainly to achieve faster responses to devia-        cost. The feasibility of providing services by enhanced
tions of normal operation conditions or faults as well      plant capabilities is confirmed by TSOs, for example
as services/capabilities provided by synchronous gen-       in Spain where voltage control by wind power plants
eration (for example mitigation of negative sequence        on specific transmission nodes leads to a signifi-
voltages and damping of harmonics). The contribution        cant improvement with fast response. Case studies
from wind and PV for system restoration services may        performed by REserviceS in Spain and Germany dem-
need further assessment.                                    onstrate that letting the DSO use GSS from VAR-RES
                                                            generation connected to its own system contributes to
The need for GSS with VAR-RES depends on the power          cost-efficient voltage management. The participation
system studied (for example its size and resilience),       of VAR-RES in system restoration has not yet been
and how VAR-RES are integrated into the system (for         practiced.
example it dispersion, penetration levels and technical
characteristics). GSS come with a cost, so require-         For wind power, potential technical enhancements for
ments for generator capabilities and service provision      frequency and voltage support services include: faster
should demand only what is needed by the system in          and reliable communication (a.o. between wind farms
order to avoid excessive costs. Preparing for future        and system operators’ control rooms), dedicated con-
systems with a large share of VAR-RES thus requires         trol tuned for delivering the required performances,
studies and simulations to make well-founded esti-          estimation of available power/forecasting. Further-
mates of the needs and technical requirements. But          more, structural, mechanical and electrical design
there is a lack of a common methodology to include          changes in wind turbines need to be implemented to
VAR-RES in estimating system needs for services and         take into account the changes in loading involved with
limited information on the combined effects of wind         grid service oriented operation. Specifically for off-
and solar PV. As the method of assessing system             shore wind power, service provision needs to consider
needs for GSS with VAR-RES is still evolving, new tools     the differences between connection technologies
are needed.                                                 (HVAC or HVDC) as these have a fundamental impact

RESERVICES PROJECT - Final publication - September 2014                                                          21
REserviceS main findings

          on the provision of voltage services and fast frequency   services along with a set of pre-qualification and pro-
          support. AC connected offshore wind plants can pro-       curement methods including proper attention to the
          vide active power reserve and frequency response          characteristics of the sources.
          (in all time domains: FCR, FRR, RR, FFR) in the same
          manner as onshore AC wind plant projects. GSS can         Implementing enhanced capabilities will involve addi-
          be augmented by aggregating multiple offshore wind        tional investment, and the deployment of the services
          plants or clusters of wind plants. Regional coordi-       will also involve costs. For both wind and solar PV the
          nation of offshore wind plants in providing reactive      additional investment costs (CAPEX) for enhanced pro-
          power and voltage control at their respective onshore     vision are relatively low and — provided appropriate
          POC would strengthen system reliability. In the case      cost recovery and market mechanisms are in place
          of HVDC offshore grids, the onshore VSC HVDC can          — their deployment should be commercially feasible.
          provide reactive power/ voltage GSS regardless of         Only for small PV systems today the impact of required
          the offshore wind condition. Technical standards and      communication components will result in high addi-
          Network Codes currently in preparation are important      tional CAPEX costs. In general, both for wind and PV,
          enablers of offshore wind GSS.                            OPEX costs notably upward readiness cost represent
                                                                    the highest costs to make frequency services avail-
          For solar PV, potential enhancements of capabilities      able. However, the enhanced capabilities should not
          include: estimation of available power/forecasting,       be required if there is no need for them as this would
          faster and reliable communication and control within      incur unnecessary additional cost. In general, fre-
          the plant, control strategies for portfolios composed     quency related GSS can be provided by a portion of
          of numerous small and medium sized units, improving       VAR-RES units and not all units need the capability.
          interoperability of different networks and enhancing      Utilising VAR-RES in voltage related GSS depends on
          compliance to a multitude of non-harmonised grid          their location in the network and should be judged on
          code requirements.                                        a case by case basis.

          The implementation of better and faster communica-
          tion systems together with the development of more        3.3 Economic benefits of grid
          accurate forecasts are essential for both wind and        support services by wind and solar PV
          solar PV technologies. In general, aggregation of mul-
          tiple VAR-RES power plants is desirable because it        The REserviceS simulations of power systems of vari-
          improves performance when providing a service and         ous sizes across Europe and with shares of VAR-RES
          reduces the relative implementation costs. However,       up to 50% showed that it is beneficial to utilise wind
          for very fast responses aggregation could cause addi-     and solar PV in frequency support. Moreover, system
          tional communication delays. Also, both for wind and      benefits increase as the share of VAR-RES increases.
          solar PV, control strategies should be tuned to obtain    The greatest benefits in simulations were observed
          the maximum power performance and flexibility from        in downward Frequency Containment Reserves (FCR)
          VAR-RES.                                                  with delivery times of less of five minutes and in auto-
                                                                    matic FRR. The benefits for the system operator in
          A precondition for provision is to have clear and well-   the simulations are higher than the cost of equipping
          defined requirements and procedures to integrate          all VAR-RES with the capability to participate in the
          wind and solar PV as GSS providers. In this respect,      frequency support, especially for wind power plants.
          poorly defined or non-existent technical specifications
          in grid codes or pre-qualification procedures to allow    Also, economic benefits were achieved even when only
          VAR-RES to provide GSS constitute a significant barrier   some VAR-RES participated in frequency support. In
          that needs to be overcome. This is exacerbated by the     a sensitivity analysis, the frequency response and its
          lack of standardisation and harmonisation of proce-       corresponding economic benefits remain adequate
          dures across Europe. A clear GSS roadmap should be        with 25% of the total installed wind power partici-
          established describing the required capabilities and      pating in frequency support services. Thus it should

         22                                                                            RESERVICES PROJECT - Final publication - September 2014
be sufficient to only equip part of the VAR-RES with       necessary regulatory frameworks, the specific project
capabilities for FCR and automatic FRR services.           recommendations on commercial frameworks in this
Cross-border sharing of frequency reserves creates         section need to be considered in the revision of the
similar benefits as VAR-RES, but there are additional      so-called EU-wide target model and more specifically
benefits when both VAR-RES and cross-border sharing        in the relevant network codes. In order to enshrine the
are utilised.                                              necessary market design in enabling legislation, exist-
                                                           ing network codes should be amended or revised and
REserviceS also performed case studies on volt-            new ones considered, in light of these findings.
age support at different voltage levels (HV/MV/
LV) and with different VAR-RES shares. It concluded        Not all generators in a system have to provide GSS to
that the cost/benefit ratio of voltage support from        ensure safe system operation. Mandatory capability/
VAR-RES is case-specific and that the provision of         provision for GSS is often not cost-efficient. Market
voltage support by VAR-RES should be compared to           based remuneration, on the one hand, stimulates cost
other technology alternatives. As there will be a high     reductions by incentivising provision by plants with the
number of locations where voltage support can be           lowest costs, irrespective of whether these are VAR-
sourced, common and robust methods to assess               RES or non-VAR-RES plants. On the other hand, in a
decisions of voltage sourcing with reproducible and        market based approach it is more difficult to control
comparable results are needed. The case studies            where the VAR-RES units with enhanced capabilities
demonstrate that voltage control capabilities from all     are located. This can be crucial when utilising grid sup-
VAR-RES generators are not always the best choice          port services. As a consequence, particular GSS could
and, therefore, an across the board requirement may        be required in locations where the capability would be
lead to excessive costs.                                   needed the most.

                                                           Detailed and clear specifications are of crucial impor-
3.4 Markets and commercial                                 tance for the participation of wind and solar PV in GSS
frameworks                                                 provision. Without these, market participation and pro-
                                                           curement of such services is delegated to incumbent
In today’s energy-only markets the contribution of         generators with long-term contracts already in place.
GSS in the system costs and revenues to generators         Requirements should be defined in close cooperation
is very low compared to energy and capacity pay-           between the TSOs and VAR-RES industry via consulta-
ments. As it is clear that VAR-RES can provide GSS         tions, as is the case in Ireland5.
and their utilisation can decrease operational costs
of the power system, there should be sufficient incen-     To enable the provision of GSS by VAR-RES, a multi-
tives to obtain these benefits along with the capability   level procurement process should be defined involving
and availability requirements for VAR-RES. Currently,      TSOs, DSOs and generators connected to their net-
only a few markets (e.g. Ireland, Great Britain) provide   works. On the one hand, the participation of VAR-RES
arrangements for enhanced services where VAR-RES           in a GSS market — run by the TSO — could breach
are incentivised to participate. In future systems with    certain operational limits in the distribution grid. On
high shares of VAR-RES, revenue from GSS is bound          the other hand, by solving local issues (congestion or
to increase, even if it remains a small part of total      voltage management) with GSS provided by VAR-RES,
system costs and revenues.                                 the actions of DSOs could have repercussive effects
                                                           on the transmission grid operation. Given the complex-
However, if the political goal of achieving a truly        ity of coordinating the respective tasks, a hierarchical
integrated Internal Energy Market goes beyond the          definition of the supervision and control actions is
energy-only market model, the roll-out of GSS markets      necessary. A clear hierarchy of functions between TSO
throughout the EU must be envisaged. In terms of           and DSOs should be established.

5
    http://www.eirgrid.com/operations/ds3/

RESERVICES PROJECT - Final publication - September 2014                                                          23
You can also read