COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya

 
CONTINUE READING
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
COUNTRY PRIORITY PLAN
 AND DIAGNOSTIC OF THE
E LECTRICITY SECTOR

Kenya
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
Acknowledgements

This Report is a product of the AfDB’s Power, Energy, Climate Change &
Green Growth (PEVP) Complex, which is directed by Mr Kevin Kariuki, vice
president of the AfDB. It has been produced under the strategic guidance
of Mr Wale Shonibare. The coordinators and lead authors are Mr Callixte
Kambanda and Mrs Rhoda Limbani Mshana. The Tony Blair Institute for
Global Change (TBI) supported the Bank in the preparation of the report.
Thanks go out to NESS Communication S.n.c. for editing and layout.

The AfDB acknowledges the collaboration of the Government of the
Republic of Kenya, which made possible the finalization of this report.

Disclaimer

The findings, interpretations and conclusions expressed in this report
are those of the authors and do not necessarily imply the expression of
any opinion whatsoever on the part of the Management or the Executive
Directors of the African Development Bank, nor the Governments they
represent, nor of the other institutions mentioned in this study. In the
preparation of this report, every effort has been made to provide the
most up to date, correct and clearly expressed information as possible;
however, the authors do not guarantee accuracy of the data.

By making any designation of or reference to a particular territory or
geographic area, or by using the term “country” in this document, AfDB
does not intend to make any judgments as to the legal or other status of
any territory or area.

Rights and Permissions

All rights reserved. Reproduction, citation, and dissemination of material
contained in this information product for educational and non-commercial
purposes are authorized without any prior written permission from the
publisher, if the source is fully acknowledged. Reproduction of material
in this information product for resale or other commercial purposes is
prohibited.

© 2021 African Development Bank (AfDB) Group

                                                                             3
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
CONTENTS

Purpose of this document		                           05

Section 1: Country Priority Plan                     06

Government strategies and targets                    07

Priority areas for the energy sector                 09

Section 2: Diagnostic of the sector                  18

Institutional framework in the sector                19

Generation outlook                                   21

  Challenges                                         22

Transmission and distribution                        24

  Challenges                                         25

Energy access and off-grid electrification outlook   27

  Challenges                                         27

Donors involvement in the power sector               29

Detailed list of donors’ interventions               33

                                                          4
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
Purpose of this document

The Kenya Country Priority Plan (“CPP”) will be the reference document adopted
by the Government of Kenya (“GoK”) and the African Development Bank (“AfDB”) to
summarize the priority reforms and projects that will be presented during the fifth
edition of the Africa Energy Market Place (“AEMP”).

The AEMP is a flagship AfDB forum that is held every year and to showcase investment
opportunities in the energy sector of selected African countries and facilitate
dialogue on key policy and regulatory challenges. AEMP is an output focused event
which leverages AfDB’s convening power to bring together the public and private
sector along with development partners to propose solutions and advance funding
to deliver priority investments and reforms.

In preparation for this event, the AfDB has asked the Tony Blair Institute for Global
Change (“TBI”) to coordinate the development of Priority Plans for the selected
countries. These plans consist of two parts:

•   The identification of AEMP Priorities (investments and reforms) to be advanced
    through the AEMP process.

•   A Sector Diagnostic providing background on the sector including statistics,
    successes and challenges to ensure a common understanding across AEMP
    participants and provide for richer dialogue during the AEMP event.

                                                                                        5
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
1

SECTION 1:
Country Priority Plan
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
Country Priority Plan
Government strategies and targets

The Government of Kenya (GoK) has an overarching Vision 2030 to transform
Kenya into an industrialised middle-income country offering a high quality of life
to all citizens. It Is being implemented through successive five-year medium term
plans, the current of which is the Third Medium-Term Plan (MTP III, 2018-22).
The MTP III has been aligned with the Jubilee Manifesto 2017 to focus on the
“Big Four” initiatives of President Uhuru Kenyatta’s second administration. These
are: industrialisation, manufacturing and agro-processing; affordable housing; food
and nutrition security; and universal health coverage. Underpinning all four Is the
provision of adequate, affordable and reliable electricity. The MTP III also explicitly
states several energy related targets:

•   Power generation: Installed power generation capacity of 5,221MW by 2022,
    and the development of a legislative and regulatory framework as well as site
    identification and capacity building for Kenya’s nuclear power development
    programme.

•   Greening the power sector: Prepare a renewable resource inventory; promote
    use of municipal waste for energy production; develop a strategy for coordinating
    research; develop capacity to manufacture and install bio-digesters, solar
    systems, turbines.

•   Commercial demand stimulation:
        o     Reduce the cost of off-peak power by 50% to heavy industries to
catalyse the manufacturing sector.
        o     Improve power reliability by 20% by 2022 by replacing overhead
distribution power lines across major towns with underground distribution power
lines and by conducting system audits to identify weak points in the network.

•   Power transmission: The construction of 5,121km of power transmission lines
    and 77 high voltage substations, a modern National System Control Centre, and
    construction of transmission lines in off-grid townships.

•   Power trading: Regional interconnector transmission lines to be constructed
    with Ethiopia, Uganda and Tanzania.

•   Energy access:
•   Connection of 5 million households to electricity through grid and off-grid
    solutions, and connection of 15,739 public facilities other than primary schools.
•   Add to the distribution network: Construct 116 new primary distribution
    substations with a distribution capacity of 2,809 Megavolt-Ampere (MVA) and
    1,244 km of associated 66kV and 33kV lines, 20 new bulk supply substations and
    installation of 336.5 Megavolt-Ampere Reactive (MVAR) power compensation
    equipment in 15 transmission substations.

                                                                                          7
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
Since the publication of the MTP III, the power generation target has been suspended
due to concerns that Kenya’s power generation may exceed demand. A Presidential
PPA Taskforce has been established to consider how to manage signed Power
Purchase Agreements.

The Government of Kenya has made rapid progress in greening the power sector,
with 94% of energy purchased by KPLC being generated by a portfolio of hydropower,
geothermal, wind and some solar power.

In terms of demand stimulation, KPLC has halved the off-peak tariff of power to
heavy industries as outlined in the MTP III and we understand has also improved
reliability in certain areas.

In terms of power transmission objectives, KPLC’s annual report for 2020 shows
that 3,800km of medium and high voltage transmission lines have been built since
the financial year of 2017/2018, which gets close to the objective of 5,100km of
power TLs by 2022.

Power trading remains an unresolved issue.

In terms of energy access, KPLC’s website informs us that KPLC was selling electricity
to over 8 million customers as of June 2020.

Legislation, plans and strategies supporting these overarching goals include the:

•   Energy Act 2019

•   Least Cost Power Development Plan (LCPDP) 2021-2030Kenya National Energy
    Policy 2018

•   Kenya National Electrification Strategy 2018

•   Kenya National Energy Efficiency and Conservation Strategy (KNEECS) 2020

•   Bioenergy Strategy 2020-2027

•   National Climate Change Action Plan II (2018-2022)

•   Renewable Energy Auctions Policy 2021

•   Feed-in-Tariffs Policy on Renewable Energy Resource Generated Electricity
    (Small Hydro, Biomass and Biogas) 2021

•   PPP Bill 2021

                                                                                         8
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
Session 1 – Generation and demand

    #                Project and importance                                Potential donor intervention

                                                 Generation project

        Using auctions to contract renewable energy             Policy dialogue on:
    1                                                           •   The short and medium-term needs for
        Under Kenya’s Renewable Energy Auctions Policy              additional intermittent power domestically
        2021, all wind and solar projects >20MW without a           and in countries with which Kenya shares
        signed PPA will transition to the Renewable Energy          interconnections.
        Auction framework. Qualified wind, solar and other
        RE projects will bid on a USD/kWh basis and will be     Secure funding for:
        stacked in ascending price order until KPLC’s target
        volume is achieved.                                     •   Study on the additional intermittent energy
                                                                    load a) the grid can take as it is and as it will be
                                                                    with the PPAs the Presidential PPA Taskforce
                                                                    recommends continuing to execute and b) KPLC
                                                                    will be able to sell.
    2   How can KPLC and captive power coexist to drive         Policy dialogue on:
        development in Kenya?
                                                                •   How captive power and KPLC can best be
                                                                    leveraged in harmony to deliver the lowest cost
                                                                                                                                                                                                                                                                                      Priority areas for the energy sector

        Because in the past KPLC has failed at delivering its       reliable power to drive economic growth while
        customers reliable energy, private developers are           maintaining KPLC’s solvency.
        offering cheap renewable captive power solutions.
                                                                Secure funding for:
        But this eats into the demand KPLC was forecasting
        and threatens its financial sustainability.             •   Identifying future prospective customers for
                                                                                                                           TABLE 1 LONG LIST OF PRIORITY AREAS FOR KENYA’S ENERGY SECTOR
                                                                                                                                                                                           Based on these, we suggest AEMP panel discussions in section 2 of this report.

                                                                    captive power. On the basis of this, addressing
                                                                    their needs through the grid.
                                                                                                                                                                                           could help with developing reliable, affordable and sustainable energy for all in Kenya.
                                                                                                                                                                                           The table below sets out in detail reforms and enabling environment priorities that

9
COUNTRY PRIORITY PLAN AND DIAGNOSTIC OF THE ELECTRICITY SECTOR - Kenya
#                             Project and importance                                                            Potential donor intervention

                                                                           Stimulating demand

     3   Stimulating industrial demand.                                                        Policy dialogue on:
         Stimulating industrial demand is key to achieving Kenya’s Vision 2030                 •   How to stimulate industrial demand?
         and has the benefit of helping reduce KPLC’s unit cost-recovery tariff
         for delivered energy. This would feed into the cost of service and tariff             Secure Funding for:
         study focused on positioning Kenya for industrial growth.
                                                                                               •   Lines of finance for power consuming industrial equipment.
         A Ministry of Energy official thought increasing industrial demand and
         powering EVs had the greatest potential for increasing demand, rather
         than rural electrification.

     4   Executing planned flagship projects.                                                  Policy Dialogue on:

         At the same time, energy supply has been predicated to some extent           •            Should the Standard Gauge Railway still take budget priority in a post
         on Vision 2030 flagship projects being executed. Where these projects                     COVID19 world?
         still make economic sense and are still a priority, these should be followed
         through with.

     5   Support Kenya to accelerate exporting low-cost renewable power.                       Dialogues on:

                                                                                               •   Potential benefits, outstanding challenges, and what is required
         The Ethiopia-Kenya-Tanzania interconnection projects’ objectives were to                  to advance trade (e.g. open access transmission, revenue risk
         improve the supply, reliability, affordability and carbon efficiency of electricity       mitigation); how can Kenya play a leadership role in the region in
         in the partner countries as well as in the region through power trade. The                this.
         Ethiopia-Kenya and Kenya-Tanzania electrical interconnections were to be
         completed by 2017 at the time that the AfDB approved their loans.

10
#                               Project and importance                                                                  Potential donor intervention

     5   Other potential power deficit markets exist in the region and could help KPLC
         achieve financial sustainability, especially if the credit rating of counterparty utilities
         can be enhanced and green finance can incentivise utilities to not use domestically
         available fossil fuels.

         Officials in Treasury and the Ministry of Energy still believe there is potential to
         export power (e.g. they cited a long standing export agreement to Rwanda which is
         not required).

         Support Kenya to accelerate exporting low-cost green commodities.                             Secure funding for:
     6
                                                                                                       •   To establish a forum through which Kenya can engage with
         KenGen is proposing to create energy park at Olkaria-Naivasha near its                            purchasers of green commodities.
         geothermal power plants to offer industry affordable, renewable and
         reliable power, steam and brine in order to facilitate industry in meeting
                                                                                                       •   For a study on the market potential of mineral extraction,
         growing demand for green commodities.
                                                                                                           hydrogen production and industrial process potential of the
                                                                                                           Olkaria geothermal power plants.

     7   Cost of service and tariff study focused on positioning Kenya for                             Secure funding study of what is and what will be the cost-of-service
         industrial growth.                                                                            under various scenarios and what an optimal tariff structure would
                                                                                                       look like that drives industrialisation while also safeguarding KPLC’s
                                                                                                       financial viability.
         A tariff review is due. A current and prospective cost-recovery tariff
         review will better inform policy on how to drive demand while helping                         •   Supply scenarios: Align with PPA Taskforce recommendations.
         KPLC achieve financial sustainability.
                                                                                                       •   Demand scenarios: Various growth rates of domestic demand:
         Director of Economic Regulation at EPRA flagged the need for this.                                latent demand from industrial parks, latent market from abroad;
                                                                                                           SWOT analysis against competition; price elasticities by customer
                                                                                                           segments. Revenue implications of increasing last-mile grid
                                                                                                           connections.

                                                                                                       •   Exogenous variables: Foreign exchange rate, price of oil.

11
Session 2 – T&D, sector structure, implementation of new laws

     #                           Project and importance                                                       Potential donor intervention

                                                                 Transmission and distribution

     8   Reduce transmission & distribution losses.                                     Policy Dialogue on:

                                                                                        •   How to tackle aggregate technical and commercial losses.
         T&D losses are as high as a quarter of power generated and cost KPLC
         KSH 16B in revenue. This represents huge inefficiencies:                       Secure funding for a T&D loss reduction programme:
         it results in a higher cost-recovery tariff, in higher required capacity, in
         higher emissions.                                                              •   Study to assess the extent to which metering, billing systems and
                                                                                            CRM is/will still be inadequate; offer options analysis of costs vs
         The World Bank’s KE Electricity Modernization Project aims in part to              benefits of installing differing qualities of metering by customer
         address non-technical losses by accurately metering consumption by                 segments. Follow-up funding to act on recommendations.
         medium and large customers.
                                                                                        •   Study to identify transmission infrastructure that should be
         USAID Power Africa is also providing advisory and technical support to             upgraded to reduce technical losses.
         reduce aggregated technical, commercial and collection losses through
         improvements in energy accounting and energy balancing, business
         intelligence and data analytics and improved commercial business
         processes
     9   Aligning preconstruction and construction stages of transmission               Policy Dialogue on:
         infrastructure; improving procurement and contract management of
         contract work                                                                  •   How to better align preconstruction and construction work.

         KETRACO has indicated that because of a misalignment between                   Secure funding for:
         construction and preconstruction in terms of timelines, ownership and
         financing sources, there are delays to the start of construction.              •   Capacity building at KETRACO in procurement and contract
                                                                                            administration of projects, e.g. support the establishment of a
                                                                                            project management office.

12
#                          Project and importance                                                  Potential donor intervention

     10   Improving procurement and contract management at KETRACO.               Policy Dialogue on:

                                                                                  •   Learning from procurement and contract management challenges
          We have heard and read about gaps in procurement of reliable                faced.
          contractors and project management of their contracts.
                                                                                  Secure funding for:

                                                                                  •   Enhancing existing capacity at KETRACO in procurement and
                                                                                      contract administration of projects, e.g. support the establishment
                                                                                      of a project management office.

                                                                     Sector structure

     11   Creation of an independent system operator for all transmission         Policy Dialogue on:
          infrastructure and transfer of transmission assets from KPLC to it.
                                                                                  •   The envisaged benefits of the wider sector reform, and what is
                                                                                      needed to complete the reform and realise these benefits.
          Introducing an independent system operator could allow for impartial
          arbitration between power generation and distribution, rationalise    Secure funding for:
          resources in one system operator and allow them to focus on upgrading
          the entire system, and could allow for the breaking up of KPLC’s      • Implementing separation of assets and accounts.
          monopoly if desired in the later future.
                                                                                  •   Any remaining upgrading of systems required and capacity
          For KPLC, offloading its transmission would mean that it can focus on       building to manage dispatch centres to enhance planning and
          reducing distribution losses.                                               deliver efficiencies.
          The Energy Act 2019 allows for EPRA to designate a system operator      •   Developing a roadmap for the creation of a wholesale market.
          responsible for matching consumer requirements with electrical energy
          supply and arranging for dispatch.

13
#                          Project and importance                                                  Potential donor intervention

     11   The Director of Economic Regulation at EPRA and Director of
          Renewable Energy at the Ministry of Energy seem keen on KETRACO
          taking over as the system operator to move to a UK grid model of
          creating a wholesale market. The Head of Legal for PPPs at Treasury
          seemed to indicate that KPLC might take up low voltage transmission
          from KETRACO in the separation of assets.

                                                                  Operationalising laws

     12   Operationalising the Energy Act 2019.                                   Policy Dialogue on:

                                                                                  •   Update from the Energy Act Task Force with a schedule for
          Implementing the Energy Act is key to Kenya achieving its Vision 2030       implementation of the various subsidiary legislations and
          and in meeting SDG7.
                                                                                      identification of the necessary support to develop/ implement
          Beyond what has been mentioned elsewhere in this table re REREC,            them.
          transmission and capacity building at the county level, GoK may         •   Potential technical assistance to
          require assistance in other domains.
                                                                                  •   Kenya Bureau of Standards, KPLC and EPRA on metering
          An introduction to William Mbaka, Chairman of the Energy Taskforce on       equipment and guidelines.
          the Implementation of the Energy Act 2019 would be helpful.
                                                                                  •   EPRA with development of an energy efficiency and conservation
                                                                                      programme, and operationalising and implementation of the Grid
                                                                                      Code, and all other outstanding regulations to support the Act.

     13   Operationalising the PPPs Bill 2021.                                    Secure funding for

                                                                                  •   Advisory to the Cabinet Secretary on regulations regarding the
          The Head of Legal for the Treasury’s PPP Directorate said they would        new PPP Project Facilitation Fund; on guidelines on how to set
          like assistance with implementing the PPP Bill 2021.                        limits on contingent liabilities; on regulations prescribing a code of
                                                                                      conduct for members, officers, employees of the PPP Committee
                                                                                      and PPP Directorate.

14
#                           Project and importance                                                     Potential donor intervention

     11   The new PPP law allows for rapid implementation of PPPs, non-                •   Capacity building of PPP Directorate in determining value-for-
          competitive procurement.                                                         money through direct procurement; of PPP Committee on what
                                                                                           constitutes a sensible PPP and contingent liability; of county
                                                                                           governments in how to appraise and execute PPPs.

                                                                   Session 3 – Electricity access

     #                           Project and importance                                                     Potential donor intervention

                                                           Institutional support at the local level

     14   Capacity building at the county level                                        Secure funding for

                                                                                       •   Assessing capacity gaps in energy planning, industrial park
          The National Energy Policy 2018 identified inadequate institutional              planning, street light planning, disaster management plans,
          capacity to negotiate energy contracts.                                          regulation; identifying private investment
          The Energy Act 2019 requires Kenya’s 47 counties to develop county
                                                                                           barriers (e.g. securing rights of
          energy plans outlining their energy requirements. It is likely that county
          governments require assistance in energy planning, in facilitating private       way, licensing processes).
          investment and in negotiating off-grid investments.
                                                                                       •   Delivering capacity building interventions to address those gaps
                                                                                           and barriers.

15
#                       Project and importance                                             Potential donor intervention

                                                                                                                                               Coordination on last-mile responsibilities

                                                                                                   15   Addressing the negative financial impact of low consumption          Policy dialogue on:
                                                                                                        rural connections on KPLC.
                                                                                                                                                                             •   How to efficiently expand access and link access with
                                                                                                                                                                                 economic development.

     prioritisation conversations.
                                                                                                        The Energy Act 2019 established the Rural Electrification and            a. How to manage existing rural low-consumption customers on
                                                                                                        Renewable Energy Corporation to succeed the Rural Electrification    KPLC’s balance sheet.
                                                                                                        Authority. REREC’s responsibilities for overseeing implementation    • Potential for increased consumption with electric cooking?
                                                                                                        of the Rural Electrification Programme will be funded by the Rural   • Potential for Rural Electrification Programme Fund to compensate
                                                                                                        Electrification Programme Fund, which will consist of electricity        KPLC for losses on rural customers?
                                                                                                        sales levy of up to 5%, as well as other sources.                    • How to advance with receivables overdue from the GoK under the
                                                                                                                                                                                 RES?
                                                                                                        KPLC’s continued responsibility for last mile grid extension to          b. How will REREC, county governments and KPLC work
                                                                                                        unprofitable customers is not going to help it achieve financial
                                                                                                                                                                             together? How can financial risk for KPLC be minimised?
                                                                                                        sustainability as T&D capex and O&M costs rise greatly while
                                                                                                        revenues increase only incrementally per added customer. At the
                                                                                                        same time, OGS companies would want certainty of where they          Secure funding for:
                                                                                                        can operate.
                                                                                                                                                                             •   A study on KPLC’s losses incurred from its existing and
                                                                                                                                                                                 forecast base of rural low-consumption customers.

                                                                                                                                                                             •    A study on the potential for uptake of electric cookstoves in
                                                                                                                                                                                 rural, low-consumption, grid-electrified households.

     it will take to deliver this impact in figure below. This is intended to facilitate further
     Each of these priorities has been assessed for the impact it will deliver and the time

16
FIGURE 1 - PRIORITY PROJECT MAPPING

              High
                                                                                                                8
                                                                                                          13 15
                                                                                                 6          14 1
                                                                                          2                   3 7
                                                                                        11
            Feasibility

                                                                                                          12
                                                                                10
                                                                                                 5
                                                                                4
                                                                                                                                  9
               Low

                             Low                                                                                                      High
                                                                                Impact

                                         Longlist of priority reform and projects                                                     Key
       1. Using auctions to contract renewable energy | 2. Captive power coexist with KPLC | 3. Simulating industrial demand
       4. Executive planned flagship projects (railway) | 5. Support Kenyan power exports | 6.Support Kenyan green commodity             Electricity access
        exports | 7.Cost of service and tariff study | 8. Reducing T&D losses | 9. Aligning preconstruction and construction of          Generation and demand
       transmission infrastructure | 10. Enhance capacity at KETRACO on procurement and project managment of contractors                 T&D, sector structure,
              11. Unbundling transmission from KPLC | 12. Operationalising Energy Act | 13. Operationalising PPPs Act |                  operationalising
       14. Capacity building at the country level | 15. Addressing negative financial impact of last mile customers on KPLC              new laws

                                                                                                                                      Source: TBI elaboration

                                                                                                                                                                  17
1

SECTION 2:
Sector Diagnostic
Section 2: Diagnostic of the sector
     Institutional framework In the sector

FIGURE 2 KENYA’S ELECTRICITY SECTOR INSTITUTIONAL STRUCTURE AND KEY ACTORS

                                                                                         Source: TBI

     Kenya’s Ministry of Energy is the overarching government body responsible for the
     energy sector. The Ministry is responsible for developing and implementing policies that
     create an enabling environment for the efficient operation and growth of Kenya’s energy
     sector1. Policy pertaining to nuclear power research and development is delegated under
     the Energy Act 2019 to the Nuclear Power and Energy Agency, formerly known as the
     Nuclear Electricity Project Committee2.

     The Ministry of Energy is accountable for the use of natural resources to the rest of
     government through the Renewable Energy Resource Advisory Committee (RERAC).
     RERAC is an inter-ministerial committee established by the Energy Act 2019 that
     advises the Cabinet Secretary on matters concerning the allocation of renewable energy
     resources, management of water catchment areas and development of multi-purpose
     projects such as dams and reservoirs. It is constituted of the principal secretary (PS)
     of the Ministry of Energy, the CEO of Kenya Power and Lighting Company (KPLC), the
     Managing Director of Geothermal Development Company, the MD of Kenya Electricity
     Generating Company (KenGen), the Attorney General, the PS for the Treasury and the PS
     for natural resources3. Regulating, monitoring and assessing activities do not degrade
     Kenya’s environment is the National Environment Management Authority (NEMA).

     Regulating the energy sector is the Energy and Petroleum Authority (EPRA). The Energy
     and Petroleum Tribunal arbitrates disputes between parties in the sector, succeeding

                                                                                                 19
the Energy Tribunal under the Energy Act 2019.

The are several actors in the power generation subsector. Leading them is Kenya
Electricity Generation Company (KenGen), which is 70% owned by the Government of
Kenya and 30% publicly listed on the Nairobi Stock Exchange4. With 1,818MW of installed
capacity as at the time of writing its 2020 annual report, it represented 65% of Kenya’s
installed capacity, operating primarily across four modes of generation: hydro (826MW),
geothermal (713MW), thermal (254MW) and wind (26MW)5. Geothermal Development
Company (GDC) is another state-owned actor in the generation sub-sector, tasked
with developing steam fields and selling geothermal steam for electricity generation
to KenGen and private investors. Its mission is to develop 1,065MW of geothermal
resources by 20306. GDC does not sell energy directly to the power utility Kenya Power
and Lighting Company (KPLC); instead, its generated energy is sold to KenGen which
sells it onto KPLC. The Rural Electrification Programme established under the Energy
Act 2019 is overseen by REREC and also sells generated energy to KPLC7. Besides state-
owned actors within the space, almost a quarter of energy sold in 2019/20 to KPLC was
from Independent Power Producers8.

There is also power generation at the premises of customers, where the power is being
sold directly to customers without KPLC as an intermediary. Direct B2B energy sales
are occurring with captive power. B2C sales are occurring mainly to rural domestic
customers with off grid solar home systems and mini-grids.

To assist KPLC in contracting with IPPs, Treasury’s Public Private Partnerships (PPP)
Directorate offers transactions support. Under the PPP Bill 2021, the PPP Committee
will approve contingent liabilities, the limit of which will be set by the Cabinet Secretary9.

In electricity transmission, there are two actors: Kenya Electricity Transmission Company
(KETRACO), a 100% state owned corporation established in 2008 responsible for
planning, designing, constructing, owning, operating and maintaining the high voltage
electricity transmission grid and regional power interconnectors; and KPLC, which has
retained its transmission network prior to the establishment of KETRACO10.

In distribution, KPLC has a monopoly. KPLC is 50.1% government owned and 49.9%
publicly listed on the Nairobi Securities Exchange11. It has over 8 million customers
according to its website12.

In terms of rural electrification efforts, KPLC is the management agent for the Rural
Electrification Scheme (RES) on behalf of the Ministry of Energy. Since the RES’ operational
and maintenance costs generally exceed the RES’ revenues, the accumulated deficit is
recoverable from the Government of Kenya under the 1973 Mercado agreement signed
between KPLC and the Ministry of Energy (KPLC, 2020, p.113). KPLC has also mentioned
in its 2020 annual report that restructuring its business operations into county business
structures is expected to enhance business performance and efficiency.

The Rural Electrification and Renewable Energy Corporation (REREC) was established
under the Energy Act 2019 and has been charged with responsibilities for increasing
electricity access in implementing the Rural Electrification Programme, in managing
the Rural Electrification Programme Fund, in developing and updating the rural
electrification master plans in consultation with County governments, and in developing
and updating the renewable energy master plan. REREC is contracting projects to
KPLC13.

                                                                                                 20
Generation outlook
       Power generation in Kenya has rapidly grown in the past decade. In 2020, generation
       capacity stood at 2,753MW, with peak demand of 1,976MW in 2020 as compared to
       1,533MW installed capacity and with peak demand of 1,178MW in year 2010. KPLC
       purchases power from several sources: KenGen, directly from IPPs, from the Government
       of Kenya Rural Electrification Programme (REP) and the Rural Electrification and
       Renewable Energy Corporation (REREC) which manages the REP, and from Emergency
       Power Producers (EPPs). It has also consistently been importing 150-180GWh of energy
       over the past four years from Uganda’s power utility UETCL and to a lesser extent from
       the Ethiopian utility EEU 1.8-4.5GWh energy from Moyale.

       Renewable energy generation has shown significant improvement of the total generation
       mix. In the FY 2019/20, renewable energy (hydro, geothermal, solar, wind, cogeneration
       and biomass) accounts for 94% of total energy generated by KenGen, IPPs, the REP,
       REREC and EPPs in comparison to the 68.5% of the total energy generated in 2010. This
       increase has been driven by an increase in the contribution of geothermal from 20% in
       2010/11 to 47.4% in 2019/20 and wind from 0.2% in 2010/11 to 11.4% in 2019/20. All
       these increases have dropped the contribution of thermal (heavy fuel oil (HFO)) plants
       from 31.4% 2010/11 percent in to 7.8% in 2019/20. Power losses remain a significant
       challenge for the sector as they stood at 23.5% as at June 2020.

FIGURE 3 THE EVOLUTION OF ENERGY GENERATED OVER THE PAST DECADE

   Generated energy in 2010/2011: 7,272GWh; in 2019/2020: 11, 462GWh. Source: Document
shared by AfDB. Similar figures to what we find in KPLC’s annual report for the year ended in 30th
  June 2020. For the FY 2019-20, KPLC’s annual report shows that KenGen, IPPs, the REP and
           REREC generated 11,098GWh energy, 94% of which was from renewables.

                                                                                                21
Kenya has an ambitious climate strategy, encompassing renewable energy penetration,
emissions reductions, and energy access. The intention of Kenya’s National Climate
Change Action Plan II (2018-2022), which is the implementation framework for the
country’s Nationally Determined Contributions (NDC) under the Paris Agreement, is to
reduce greenhouse gas (GHG) emissions by 30% from 2030 business as usual (BaU)
levels. This is equivalent to a total emission limit of 100 MTCO2e since in 2015, BAU
emissions were predicted to reach 143 MTCO2e by 2030. Further, Kenya’s LCPDP
(2020-2040) envisages the gradual replacement of thermal power with renewable
energy sources in line with the country’s strategy of diversifying its energy mix as well as
Kenya’s National Climate Change Action Plan II (2018-2022). Kenya has the capacity to
meet its commitments due to its advanced energy mix, excellent renewable resource,
and ambitious expansion plans.

Challenges
There are concerns14 that the current pipeline of generation investments may lead to
a power surplus that KPLC is unable to sell, which will either result in KPLC’s increased
financial distress or an increased electricity tariff that makes Kenyan manufacturing less
cost competitive, or both.

Concerns about future excess power capacity have resulted in the creation of a Presidential
Taskforce to Review PPAs (power purchase agreements)15. The taskforce has been
charged with a broad remit, including to assess the compliance of PPAs with Kenyan
laws, to review their sustainability, and reviewing the take-or-pay model. A moratorium
was placed on all PPAs not concluded by 29 March 202116, and it is understood that
the Taskforce is also considering postponing PPAs under which construction has not
yet commenced. At least one equity investor expressed a willingness to negotiate their
capacity charge17.

What should be of particular concern is that growth in KPLC’s sales has declined to
its largest customer segment, commercial and industrial customers who account for
more than half of energy sales. While COVID19 may be an explanation for the most
recent decline, a decline in energy consumption was not observed for small commercial
customers during the same period, and the commercial and industrial segment also
consumed less energy in FY 2017/18 than it did in FY2016/17 (this was not the case for
other customer segments).

A key competitor for C&I power consumption is captive power, which is able to operate
without the need for licenses and permits by structuring through leases (interview with
a private developer). During daylight hours, contracted solar power is proving cheaper
than the grid. It is understood that captive power is now costing KPLC USD 2 million in
lost revenues per year. As of February 2019, there were 22 captive power plant license
holders with a combined Installed capacity of 152MW of power from solar, solar and
diesel hybrid, diesel, hydro and diesel, hydro, cogeneration, biomass, geothermal and
coal power plants18. Captive power was being used by food processing firms, flower
farms, tourist lodges. Six schools and five shopping malls had also been identified as
using captive power19.

Looking at KPLC’s revenues20, less than 1% has been generated from exports, with the sales in
2019/20 being the lowest they have been in five years. This represents a potential growth area.

                                                                                                  22
TABLE 2 KPLC SALES OF ENERGY IN GWH BY CUSTOMER CATEGORY

                                                   Source: KPLC, 2020 annual report, p.144; TBI
                                                                                       analysis

      Type of challenge            Description                    Bridging the Gap

           Power          Power generation capacity        Support measures on both the
         oversupply       and take-or-pay contracts        demand and supply side to keep
                                                           supply and demand in line.
                          forecast to exceed demand
                          and put KPLC into financial
                          difficulties.

      Allowing homes      Captive power solutions can      Analytical, policy and regulatory
        and business      help industry and domestic       work to clarify the respective
                          users mitigate the negative      roles of KPLC and providers of
          to benefit
                                                           captive power.
        from captive      impacts of power outages and
       power without      reduce their energy costs. But
       compromising       they can also contribute to
      KPLC’s financial    oversupply of power by KPLC
           viability      since lead times to commission
                          extra power lag more agile
                          captive power solutions.

                                                                                               23
Transmission and distribution outlook

      The total length of the transmission and distribution network was 243,207 kilometers
      for all voltage levels in 2019/20, up from 59,322 kilometers in 2014/15. This growth
      has been greatly influenced by Kenya Electricity Transmission Company (KETRACO),
      who have accelerated the development of transmission infrastructure within their
      mandate, consisting of 132kV, 220kV and 400kV lines. Table 3 provides transmission
      and distribution line lengths between 2014/15 and 2019/20.

TABLE 3 TRANSMISSION AND DISTRIBUTION LINE LENGTHS IN KILOMETRES, FY 2014/15-2019/20

                                                       Source: KLPC 2020 annual report, Table 19.21

      From 2015 to 2020, generation substations increased in capacity from 3,025MVA to
      3,878MVA, transmission substation capacity increased from 3,144MVA to 4,942MVA,
      while distribution substation capacity increased from 3,572MVA to 4,563MVA.
      Distribution transformers increased in capacity from 6,384MVA to 8,174MVA.

TABLE 4 TRANSFORMERS IN SERVICE, TOTAL INSTALLED CAPACITY IN MVA AS AT 30TH JUNE, 2020

                                                         Source: KLPC 2020 annual report, Table 20.

                                                                                                24
Challenges
      Kenya’s commercial and technical transmission and distribution losses have been rising
      since 2015 to almost a quarter of power generated in 2020, and a loss of KSH 16 billion
      in revenues22. This might in part be explained by KPLC’s rapid growth in connections.

      “KPLC’s losses are due to poor equipment; lack of insight into what is happening on the
      grid because of a lack of metering; stretched out transmission lines; transmission lines
      with lower voltage than they should have to reduce losses because of lack of substations
      to step-up and step-down the voltage; theft; and functionaries taking payments to reduce
      customers’ bills.”

FIGURE 4 KENYA POWER, TOTAL LOSSES 2012/13 TO 2019/20 (%)

                                                              Source: Mercados-Aries International, 2021

      Incomplete transmission infrastructure is stifling economic activity by preventing higher
      quality, lower cost power and are also stifling greener power from being evacuated to
      places such as Laikipia and western Kenya. In the case of the 132kV Nanyuki – Rumuruti
      underground cable, this has been caused by issues with contractors23. With completion
      of the project, Laikipia County would be less beset by power outages (it is currently at the
      end of an 80km 33kV line), which would benefit its horticultural sector (interview with a
      private developer, 20th August 2021). The AfDB has financed the project24.

      Challenges in aligning necessary incentives and regulations at the regional level
      (e.g. transmission charging and third party transmission access) and rigidly drafted
      agreements (the Kenya Ethiopia Power Purchase Agreement and Transmission System
      Agreement) not being signed are causing delays in the integration of the Eastern African
      Power Pool (EAPP), which could deliver customers in the power pool greener, lower
      cost and more climate resilient energy, and which could earn Kenyan utilities foreign
      exchange.

      The Energy Act 2019 allows EPRA to designate a system operator for Kenya’s
      transmission infrastructure. It is understood that the government is minded to house
      the independent system operator at KETRACO. EPRA is in the process of preparing the
      regulations required for this to happen. Having an independent system operator would
      allow for the creation of a wholesale market in the long term and would alleviate KPLC

                                                                                                     25
of the pressure to reduce transmission losses. Costs may be cut as functions between
KETRACO and KPLC are rationalised. KenGen and IPPs would also benefit from an
impartial arbiter between power generation and distribution.

Type of challenge             Description                      Bridging the Gap

    T&D losses      Commercial and technical            Tackle technical losses, power
                    T&D losses have grown to            theft resulting in lost revenues by
                                                        improving monitoring at a more
                    almost a quarter of energy
                                                        granular level.
                    generated and a loss of KSH         Segregation of technical losses
                    16B in revenues.                    in the system, identifying the
                                                        gaps and methodology for
                                                        intervention. Improving the
                                                        accounting, energy balance and
                                                        accountability for energy in the
                                                        distribution side.

   Incomplete       Hold-ups on key transmission        KETRACO to be supported in
  transmission      infrastructure is preventing an     the procurement and project
                    increased quality and reduced       management of contractors.
  infrastructure
                    cost of power for Kenyan
                    populations.

    Incomplete      Challenges aligning necessary       Flexible market arrangements to
 interconnection    incentives and regulations at a     better align with the commercial
                    regional level (e.g. transmission   and technical needs of Kenya
  infrastructure
                                                        and Ethiopia for these hold ups
       with         charging and third party
                                                        to be resolved.
   neighbouring     transmission access); rigidly
     countries      drafted agreements not being
                    signed (PPA, TSA).

                                                                                              26
Energy access and off-grid electrification outlook

     In the Kenya National Electrification Strategy of 2018, the Government of Kenya
     committed itself to achieving universal electricity access by 2020 (KNES, 2018), which
     was modified to 202225. One of the Government of Kenya’s last mile connectivity
     strategies is to use the existing distribution transformers and extend the low voltage
     network to customers located in the vicinity of these transformers.

     Over the period 2013/14 to 2019/20, the number of KPLC and Rural Electrification
     Programme customers increased by 4 million, at a compounded annual growth rate
     of 16%.

FIGURE 5 NUMBER OF CUSTOMERS WITH ACCESS TO ELECTRICITY THROUGH KPLC AND REP

                                                          Source: KLPC 2020 annual report, Table 15.

     Challenges

     While passing through the costs of the price of oil and foreign exchange losses help
     maintain KPLC’s financial sustainability, they create uncertainty in forecasting utility
     costs for customers, and make captive power more attractive.

     The onset of COVID-19 pandemic in the second half of the 2019/20 financial year
     and subsequent government containment measures created economic shocks,
     adversely affecting the energy sector. During this period, peak electricity demand
     declined from 1,926MW in February 2020 to 1,765MW in April 2020, a decline of 9.1%.
     The steep decline was followed by a gradual recovery as the government eased the
     containment measures enabling resumption of various economic activities. Peak
     electricity demand increased to 1,938MW in October 2020.

     On top of exacerbating losses, there are concerns about the impact last mile
     connections are having on KPLC’s profitability. KPLC is the management agent for
     the Rural Electrification Scheme (RES) on behalf of the Ministry of Energy. Since

                                                                                                 27
the operational and maintenance costs of rural low-consumption customers
served by KPLC under RES generally exceed revenues26, the accumulated deficit
is recoverable from the Government of Kenya under the 1973 Mercado agreement
signed between KPLC and the Ministry of Energy27. However, KPLC’s receivables
from last-mile debtors increased from 2019 to 202028, while KPLC liabilities for the
last-mile project increased from 2019 to 2020 (Note 28b, p.118). KPLC is petitioning
the government to release funds owed to KPLC for the management, operations,
and maintenance of the RES network29. The Auditor-General has warned that KPLC
risks losing KES 16B (approximately USD 146M) owed by the government under the
RES since the balance is long outstanding30. Compounding the government’s failure
to meet KES liabilities are various other government departments and agencies are
also neglecting their payments to KPLC31.

The Rural Electrification and Renewable Energy Corporation (REREC) was created out of
the Rural Electrification Authority under the Energy Act 2019 to intensify the expansion
of electricity access. It is using KPLC to implement projects on a contract basis32.

KPLC has mentioned in its 2020 annual report that restructuring its business
operations into county business structures is expected to enhance business
performance and efficiency.

With all of this in the background, there is also an issue of what is a cost-recovery
tariff, versus what tariff would help stimulate demand if appropriate accessories
such as right-sized electric cookstoves were made available.

Type of challenge             Description                    Bridging the Gap

   Complicated       Several charges appear on an     Public awareness campaign,
                     electricity bill.                clarifying language.
  tariff structure

     COVID19         Containment measures reduced Ensure that containment
                     demand                       measures go as far as they need
    impacting
                                                  to and not beyond.
     demand

    Decreasing       Decreasing consumption per       Assess going forward potential
                     capita with rural customers as   KPLC customers’ commercial
    profitability
                     opex per capita remains steady   viability. Assist demand
   with last mile                                     stimulation.
   connections

                                                                                           28
Donors involvement in the power sector

 Name of active Donors in the country   Activities there are mostly involved
                                                         into

AfDB                                    Development of renewable energy
                                        resources and Transmission Infrastructure,
                                        Electricity Access (on grid & off-grid
                                        systems), Regional Integration and
                                        Technical assistance
AFD                                     Development of Generation,
                                        Transmission & Substation
                                        Infrastructures, Electricity Access (on
                                        grid & off-grid systems) including last
                                        mile connection, Regional Integration
                                        and Technical assistance
Australia                               Technical assistance in development of
                                        renewable energy resources
Belgium                                 Reinforcement of transmission system
                                        and distribution network for electricity
                                        access and technical assistance
China                                   Renewable energy (Solar, Geothermal),
                                        transmission lines and oil sector
Department for International            Electricity access (Green Mini-grid
Development (DFID)                      facility), Renewable Energy and
                                        Adaptation to Climate Technology,
                                        Promote low carbon private sector
                                        development through award of co-
                                        financing, Provide targeted financing
                                        and capacity building support to
                                        entrepreneurs and SMEs to scale up
                                        and deploy innovative clean technology
                                        solutions and technical assistance
European Investment Bank (EIB)          Development of renewable energy
                                        generation resources, transmission
                                        lines, Electricity Access (off-grid
                                        systems), Support private sector
                                        actors through jointly investing in
                                        off grid solar projects, and technical
                                        assistance
European Union (EU)                     Development of renewable energy
                                        resources (wind, solar etc.),
                                        community-based electricity access
                                        (off-grid systems), technical assistance
                                        network control & transmission system
                                        reinforcement, support private sector
                                        actors (enterprises) through jointly
                                        investing in solar project, alternative
                                                                                     29
Name of active Donors in the country   Activities there are mostly involved
                                                        into

European Union (EU)                    energy, energy efficiency and technical
                                       assistance. Also support for county energy
                                       planning.
                                       Through the ElectriFI financing instrument,
                                       the EU is supporting private companies
                                       offering captive power solutions to C&I.
                                       Energy efficiency is part of this. As for demand
                                       stimulation, the EU is fostering productive
                                       usage of energy under the Green Mini-Grid
                                       Facility Kenya. The EU-supported BRT project
                                       will also contribute to increase electricity
                                       demand through e-buses. In the framework
                                       of the Green Hydrogen Working group, the
                                       EU works in close coordination with GIZ
                                       and other partners to support the Ministry
                                       of Energy in developing a green hydrogen
                                       agenda, through technical assistance and
                                       studies. Through the Reinforcement of the
                                       Electricity Transmission Network (RETNet)
                                       project, in blending operation with AFD, the EU
                                       will provide technical assistance / capacity
                                       building to Ketraco and the future system
                                       operator to strengthen their capacities in
                                       operation and maintenance of transmission
                                       lines and more specifically of the new national
                                       System Control Centre (NSCC). The EU is
                                       supporting Kenya to reach universal access to
                                       electricity, both on-grid (Last Mile connectivity
                                       Project, in blending with AFD and EIB) and
                                       off-grid (ElectriFI, Green Mini-Grid Facility).
                                       Clean cooking (including e-cooking, which
                                       may indeed stimulate domestic demand)
                                       and biogas (bio-digesters) are also eligible
                                       to our support to the private sector. Under
                                       the Sustainable Energy Technical Assistance
                                       (SETA) programme, the EU is strengthening
                                       capacities in County Governments through
                                       capacity building / training programme
                                       in the SEforAll areas (renewable energy,
                                       energy efficiency, energy access) and in the
                                       elaboration of their County Energy Plan.

                                                                                           30
Name of active Donors in the country Activities there are mostly involved
                                                      into

German GIZ                           Development of solar hybrid mini-grids,
                                     access to modern energy services,
                                     specifically improved cookstoves and small
                                     solar systems and technical assistance
German KfW                           Development of renewable energy
                                     resources (geothermal), Electricity
                                     Access (off-grid systems), and
                                     technical assistance
Japan International Cooperation      Development of renewable energy
Agency (JICA)                        resources (geothermal, hydro),
                                     Transmission system, regional
                                     integration, and technical assistance
Netherlands                          Support private sector actors through
                                     jointly investing in solar project, access
                                     to modern energy services, specifically
                                     improved cookstoves and small solar
                                     systems
Norway & Norfund                     Equity investment in Generation
                                     (wind, solar), Access to modern
                                     energy services, specifically improved
                                     cookstoves and small solar systems
                                     and technical assistance
Spain                                Expansion of wind generation plant and
                                     electricity access to public utilities

Sweden                               Access to modern energy services,
                                     by supporting SMEs on renewable
                                     Energy, adaptation and climate change
                                     technology and technical assistance.
United Nations Development Program   Climate change in the area of low
(UNDP)                               Emission and Climate resilient
                                     development , establishing energy
                                     efficiency standards for appliances,
United Nations Environment Program   Development of renewable energy
(UNEP)                               resources, energy efficiency &
                                     conservation and technical assistance
United Nations International         Off-grid decentralized electrical
Development Organization (UNIDO)     energy service on renewable energy
                                     technologies standalone and hybrid
                                     systems, technical assistance
                                     in energy efficiency and cleaner
                                     production

                                                                                  31
Name of active Donors in the country   Activities there are mostly involved
                                                        into

USAID/PA                               Development of Generation Infrastructure
                                       , Electricity Access (on grid & off-grid
                                       systems), and Technical assistance
                                       for PPP’s, cross-border trade, gender,
                                       community engagement, environmental
                                       management and institutional
                                       performance.
UN                                     Development of renewable energy
                                       resources (small hydro, cogeneration
                                       etc.), regional project targeting
                                       promotion of geothermal energy
                                       development in several countries in the
                                       rift system
World Bank (WB/IDA)                    Development of renewable energy
MIGA (WB/IFC)                          resources and Transmission
                                       Infrastructure, Electricity Access (on
                                       grid & off-grid systems), Regional
                                       Integration and Technical assistance
                                                -      MIGA Guarantee to
                                       Geothermal Generation

                                                                                  32
PROJECT                  FUNDER            VALUE              STATUS                   GAPS

                                               Generation

     Capital Investment

     Aperture Green Power
     50MW wind, Limuru,
     Kiambu County
     Quantum Power            AfDB            UA 21,586,260.89   Approved
     Menengai 35 MW
     Geothermal IPP
     Partial Risk Guarantee   AfDB            UA 9,071,428.56    Pending according to AfDB   Would only become
                                                                 staff                       effective once all
     for the Menengai                                                                        three power plants
     Geothermal Power                                                                        have achieved
     Project                                                                                 their Commercial
                                                                                             Operations Dates

     Lake Turkana Wind        AfDB                               Pending KPLC looking to
     Project PRG                                                 change PPA.
     KenGen Guarantee         World Bank      USD 180M           Closed                      To support
                                                                                             investment in
     Project                                                                                 Kenyan renewable
                                                                                             energy power
                                                                                                                      Detailed list of donors’ interventions

                                                                                             generation

     Electricity Expansion    World Bank      USD 330M of USD    Closed in 2017              4 components:
                                              1,390M                                         i. expansion of
     Project                                                                                 capacity of existing
                                                                                             first Olkaria
                                                                                             geothermal power
                                                                                             station by 140M,
                                                                                             new fourth Olkaria
                                                                                             geothermal power
                                                                                             station of 140MW;
                                                                                             ii. transmission;
                                                                                             iii. distribution; iv.
                                                                                             operational support.

33
PROJECT                      FUNDER                       VALUE                                 STATUS                                    GAPS

                                                                         Generation

     Capital Investment

     Garissa 50MW solar PV       Chinese Exim Bank           USD 136M                 Commissioned in 2016

     Geothermal exploration      Chinese Exim Bank           USD 382.5M               Closed: 2012-2016. Maturity year 2033, KenGen Integrated   89 wells drilled
                                                                                      report 2020end of 2021

     Kipevu 1 diesel HFO         Japan Bank for              JPY 2.1B                 Maturity year 2025, KenGen Integrated report 2020
     plant, 6x 12.5MW            International Cooperation
     Sondu Miriu, 60MW           Japan Bank for             JPY 2.37B, JPY 8.3B       Maturity years 2027, 2044, KenGen Integrated
     hydropower station          International Cooperation,                           report 2020
                                 JICA
     Sangoro hydropower          Japan Bank for             JPY 3.8B                  Maturity year 2047, KenGen Integrated report 2020
                                 International Cooperation
     Olkaria I & IV geothermal   JICA , KfW, IDA, AFD,       JPY 21B, EUR 31.3M,      Maturity year 2040, 2026,
                                 EIB,                        USD 27.9M, EUR 66.7M,    2035, 2031,
                                 IDA                         EUR 4.8M, USD 52.7M      2037, 2041 KenGen Integrated report 2020
     Olkaria V geothermal        JICA                        JPY 27.4B                Maturity year 2046, KenGen Integrated report
                                                                                      2020
     Kindaruma hydropower        KfW                         EUR 15.6M                Maturity year 2024, KenGen Integrated report
                                                                                      2020

     Ngong Phase II, 13.6MW      Spanish loan                EUR 17.5M                Maturity year 2030, KenGen Integrated report
     wind                                                                             2020

     Ngong Phase I, 6.8MW        National Bank of            EUR 6M                   Maturity year 2020, KenGen Integrated report
     wind                        Belgium                                              2020

     KenGen - various projects Public infrastructure         Reached maturity         Maturity year 2019, KenGen Integrated report
                               bond                                                   2020

34
PROJECT                           FUNDER                      VALUE                              STATUS                      GAPS

     KenGen term loan                   Cooperative Bank              KES 2.3B as of         Maturity year 2022, KenGen Integrated report
                                                                      30/6/2020              2020

     Olkaria II Unit 3                  AFD                           EUR 6.7M               Maturity year 2024,
                                        Standard Chartered            USD 6.5M               2021, KenGen Integrated report 2020
                                        Bank
     Rigs                               HSBC                          USD 13.5M              Maturity year 2024, KenGen Integrated report
                                                                                             2020

     Wellheads 75MW                     CBA                           USD 78.4M              Maturity year 2027, KenGen Integrated report
                                                                                             2020

     Kopere 40MW solar PV +             AfDB, Scaling-Up Renewable    USD 64M                Envisioned
     33/132 kV substation +             Energy Program (SREP –
                                        funded by FCDO and Gov.
     1.8km transmission line            Netherlands+), European DFI

     Kipeto Wind                        DFC – reinsurance by          USD 50 M of total      Commissioned
                                        OPIC                          project of USD 320 M

     Feasibility Studies:               USTDA                         $8.85 M between 2016 Studies completed
     - Siaya Solar Project Battery                                    – 2019
     Storage Integration
     - Olkaria Geothermal Power Total
     Flow Topping Unit
     - Saigrene Energy 17MW Small
     Hydropower Projects
     - Virunga Hydropower Project
     - Siruai 50 MW Wind and Battery
     Storage Project
     - Gitaru 10 MW Solar Power Plant
     - Lamu Gas-to-Power
     - Isiolo 40 MW Power Plant
     Akiira Geothermal

35
PROJECT               FUNDER             VALUE                               STATUS          GAPS

                                                       Power trade

     Capital Investment

     Ethiopia – Kenya      AfDB            UA 75M of UA 134M           Implementation             Lack of court
     Electricity Highway                   Remainder from the                                     precedents to
                                           Government of Kenya                                    guide wayleave
     Project                               + EUR 26.51M                                           and compensation
                                           supplementary financing                                payments on
                                                                                                  transmission lines,
                                                                                                  which has affected
                                                                                                  the disbursement
                                                                                                  rate and the
                                                                                                  completion date.
                           AFD             USD 101.3M for electrical   Started in 2016            Additional financing
                                           interconnection                                        because of an
                                                                                                  underestimation of
                                                                                                  the required system
                                                                                                  reinforcement
                                                                                                  works identified by
                                                                                                  the initial feasibility
                                                                                                  study and design.
                                                                                                  A 500 kV high-
                                                                                                  voltage direct-
                                                                                                  current transmission
                                                                                                  line with a total
                                                                                                  length of 1,068 km
                                                                                                  and converters at
                                                                                                  substations. There
                                                                                                  is also a component
                                                                                                  to strengthen the
                                                                                                  Kenyan transmission
                                                                                                  system, as well as
                                                                                                  provide technical
                                                                                                  assistance and
                                                                                                  capacity building for
                                                                                                  management and
                                                                                                  maintenance of the
                                                                                                  DC network.

36
PROJECT                   FUNDER            VALUE                                     STATUS                              GAPS

     Kenya-Tanzania             AfDB            51% of UA 199.86M
     Interconnection Project                    Remainder from the
                                                Governments of Tanzania and
                                                Kenya

             PROJECT                   FUNDER            VALUE                                     STATUS                              GAPS

                                                Transmission and Distribution

     Capital Investment

     Mombasa – Nairobi         AFD              USD 66.6 M                    Started in 2009 to construct the HV line between
     Transmission line project                                                Nairobi and Mombasa

     Nairobi Ring Project       AFD             USD 87.1 M                    Started in 2012 to construct key substations in    .
                                                                              Nairobi area

     Kenya - Last Mile          AfDB            UA 90M of UA 99.2M            Completed according to AfDB staff
     Connectivity Project - 1
     Kenya - Last Mile          AfDB            UA 94,390,151.57              Implementation according to AfDB staff
     Connectivity Project II

     Kenya - Last Mile          AfDB                                          Not yet approved according to AfDB staff
     Connectivity Project III
     KE Electricity             World Bank      USD 200M + USD                Active                                             Also include off-
     Modernization Project                      250M                                                                             grid interventions
                                                                                                                                 and T&D TA. Aims:
                                                                                                                                 to increase access
                                                                                                                                 to electricity; to
                                                                                                                                 improve reliability;
                                                                                                                                 to reduce revenue
                                                                                                                                 losses.

37
PROJECT                   FUNDER             VALUE                       STATUS                       GAPS

     438km Loiyangalani-                           USD 271M      Completed In 2018                           Capacity to
     Suswa transmission line                                                                                 transmit 1,200MW.
     connecting north Kenya
     to national grid
     KETRACO/PT/010 /2012- Indian Exim Bank        USD 61.6M     Consolidated in KETRACO's 2019-20 (latest
     LOT 1A                                                      available) annual report
     KETRACO/PT/010 /2012-
     LOT 1B
     KETRACO/PT/010 /2012-
     LOT 3A
     KETRACO/PT/010 /2012-
     LOT 3B
     KETRACO: Olkaria-Lessos- JICA                 JPY 12.41B    Consolidated in KETRACO's 2019-20 (latest
     Kisumu transmission line                                    available) annual report

     KETRACO: Nanyuki-        KBC Bank, Belgium    EUR 14M       Consolidated in KETRACO's 2019-20 (latest
     Isiolo-Meru transmission                                    available) annual report
     line
     KETRACO: Sondu-          KBC Bank, Belgium    USD 16M       Consolidated in KETRACO's 2019-20 (latest
     Homabay-Ndhiwa-Awendo                                       available) annual report

     KETRACO: Kenya Power      Chinese Exim Bank   RMB 677M      Consolidated in KETRACO's 2019-20 (latest
     Transmission Expansion                                      available) annual report
     Project
     KETRACO: Mariakani        ADB                 USD 24M       Consolidated in KETRACO's 2019-20 (latest
     Substation                                                  available) annual report

     KETRACO: Nairobi Ring     AFDB                EUR 78.5M     Consolidated in KETRACO's 2019-20 (latest
     (Suswa – Isinya and                                         available) annual report
     substations)
     KETRACO: Lessos -         AfDB                UA 21.4M      Consolidated in KETRACO's 2019-20 (latest
     Tororo (Equatorial Nile                                     available) annual report

38
     lake grids)
You can also read