Environmental and Social Monitoring Report - Asian ...

Page created by Rosa Russell
 
CONTINUE READING
Environmental and Social Monitoring Report - Asian ...
Environmental and Social Monitoring Report

Project Number: 51051-001
January–March 2021
May 2021

Thailand: Chonburi Natural Gas Power Project

Prepared by Gulf SRC Company Limited for Asian Development Bank.

The environmental and social monitoring report is a document of the borrower. The views
expressed herein do not necessarily represent those of ADB's Board of Directors, Management,
or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
Environmental and Social Monitoring Report - Asian ...
REPORT

ASIAN DEVELOPMENT BANK
JAPAN BANK FOR INTERNATIONAL COOPERATION
MIZUHO BANK, LTD.
BANGKOK BANK PUBLIC COMPANY LIMITED
SUMITOMO MITSUI BANKING CORPORATION
EXPORT-IMPORT BANK OF THAILAND

Gulf SRC 2,500 MW Combined Cycle Power Plant Project

Lenders’ Technical Advisor Quarterly
Environmental and Social (E&S) Monitoring
Report No. 9
[January 1st 2021 to March 31st 2021]

127000407
10 May 2021
Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 1

Project                                                           Project No.
Gulf SRC 2,500 MW Combined Cycle Power Plant                      127000407
Project
Revision                                                          Date
Revision 0                                                        10 May 2021
Address
AFRY (Thailand) Ltd.
Vanit II Bldg., 22nd Floor, Room No. 2202-2204,
1126/2 New Petchburi Road, Makkasan,
Rajchthewi, Bangkok 10400 THAILAND

Phone
+66 2 108 1000 (THAILAND)

Contact

Mr.Mark Wilson

Mobile
+66 2 108 1000

E-mail

Mark.wilson@afry.com

Client

ASIAN DEVELOPMENT BANK
JAPAN BANK FOR INTERNATIONAL COOPERATION
MIZUHO BANK, LTD.
BANGKOK BANK PUBLIC COMPANY LIMITED
SUMITOMO MITSUI BANKING CORPORATION
EXPORT-IMPORT BANK OF THAILAND

Report

Lenders’ Technical Advisor Quarterly Environmental and Social
(E&S) Monitoring Report No. 9
[January 1st 2021 to March 31st 2021]

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 2

                                                       NOTICE

It is the good faith and belief of AFRY (Thailand) Ltd (“AFRY” or the “LTA”) that the estimates and
conclusions contained in this report are reliable. However, the LTA does not warrant or guarantee
their accuracy. Use of the report and its estimates shall, therefore, be at the user’s sole risk. Such
use shall constitute a release of the LTA from and against any liability in connection with such
use, whether liable for special, indirect or consequential damages, whether such liability is
asserted to arise in contract, negligence, strict liability or other theory of law.
This document has been prepared for Asian Development Bank, Japan Bank for International
Corporation and Bangkok Bank Public Company Limited in relation to the 2,500-megawatt
combined cycle natural gas fired power plant project of Gulf SRC Company Limited in Hemaraj
Eastern Seaboard Industrial Estate, Chonburi Province in Thailand (the “Project”).
AFRY acknowledges and agrees that Asian Development Bank, Japan Bank for International
Cooperation (the international arm of Japan Finance Corporation), and Bangkok Bank Public
Company Limited, and certain other lenders of the Project accepted by the LTA from time to time
(hereinafter jointly the “Lenders”) are entitled to and will rely on this report. The LTA consent to
making this report available to the Lenders is subject to and on the understanding that before
receiving and relying on this report, each Lender has as set out in the Engagement Agreement
signed between the LTA, Gulf SRC Company Limited, Independent Power Development Company
Limited and Bangkok Bank Public Company Limited on July 2018 concerning the LTA’s
engagement (“Engagement Agreement”) either itself signed the Engagement Agreement or
confirmed and accepted in writing that it is aware of, understands and agrees to the scope of the
LTA’s engagement and the liability as well as other terms and conditions which may apply as set
out in the Engagement Agreement and without limitation confirms that it unconditionally agrees
to be bound by the terms of the said Engagement Agreement (including without limitation clauses
9.7 and 11) and any limitations of or exceptions to liability included for the benefit of the LTA,
and subject to the below conditions.
All the above-mentioned Lenders hereby entitled to rely on this report acknowledge and agree
that, prior to any issue becoming litigious, all disputes arising out of or in connection with the
report shall be channelled through one Lender only.
The Lender may not use the contents of this report for any purpose other than:
a) the provision of financial accommodation to Gulf SRC Company Limited in connection with the
Project including disclosing it to external accountants, auditors or lawyers for said purpose on the
basis that they do not rely on the report and keep it confidential;
b) if required by mandatory law or in accordance with an official directive or request of a
governmental authority or agency for its internal purposes which, if not having the force of law,
compliance is in accordance with good practice of responsible banks or financial institutions on
the basis that they do not rely on the report and keep it confidential; or
c) in connection with any litigation or proposed litigation concerning the report.
The opinions and forecasts contained in this report have been prepared in good faith, with
reasonable care and due diligence based on reasonable assumptions. However, no opinion or
forecast in this report is, or should be, relied upon as a promise or representation of the future.
Actual results may be different from the opinion contained in this report, as anticipated events
may not occur as expected and the variation may be significant.
All the above mentioned Lenders hereby entitled to rely on this report acknowledge and agree
that monetary damages may be an insufficient remedy for the LTA if the recipient or Lender
breaches the conditions of disclosure listed in paragraphs a) to c) above and in addition to any
other remedy which may be available in law or equity, the LTA may seek injunctive relief to
prevent any actual or threatened breach of the conditions of disclosure and to compel specific
performance of those conditions of disclosure.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 3

EXECUTIVE SUMMARY

Gulf SRC Company Limited (“GSRC” or the “Owner”) is developing Gulf SRC 2,500 megawatt
(“MW”) Combined Cycle Power Plant (“CCPP”) project in Hemaraj Easter Seaboard Industrial
Estate (“HESIE”), Sriracha District, Chonburi Province, approximately 140 km east of Bangkok.
Natural Gas will be transported to GSRC through a new 2.5 km long gas pipeline (“Interconnecting
Pipeline”) now constructed for the Project. EGAT have constructed a 10.9 km overhead
transmission line to connect GSRC’s switchyard with EGAT’s Pluak Daeng Substation. Raw water
to GSRC will be supplied by East Water via the installed Hemaraj Raw Water Pipeline.
This is the ninth Quarterly Environmental & Social (“E&S”) Monitoring Report of AFRY (the Lenders
Technical Advisor) and covers the period from January 1st, 2021 to March 31st, 2021.
AFRY would like to thank the Owners and EPC Contractor for their valuable support during the
virtual site visit and for providing the documentation requested to prepare this report.

Health and Safety
The key OHS statistics for the construction monitoring period are 2,081,004 safe man hours
accumulated for the Power Plant Area and Raw Water Pond Area. There were 7 HSE incidents and
131 hazard observations for the Power Plant Area and Raw Water Pond Area. The ratio for number
of safety officers to number of workers is one safety officer per 50 workers which is considered to
be sufficient.

Labour and Working Conditions and Security
The number of workforce personnel as of March 25th, 2021 is 2,037 male workers and 565 female
workers.
Welfare facilities at the Project site includes rest shelters, toilet/bathroom facilities, drinking water
stations and medical facilities which continue to be adequately managed. Hygiene/cleanliness and
the welfare facilities at the workers camp also continue to be adequately managed.
At the workers camp there are a sufficient number of rooms (1,684) for the total number of
persons residing (1,887) i.e. no more than 2 adults to a room.
In general, the hygiene/cleanliness of the workers camp is considered to be adequate in all zones
and the facilities (toilets, bathing and medical) continue to be adequately managed. As part of
the COVID-19 preventative measures the workers camp continues to have dedicated area for new
workers and area of quarantine in case any of the residents are found to have COVID-19
symptoms.
There were no workers grievances / suggestions recorded during the construction monitoring
period.

Stakeholder Engagement
The Environmental Impact Monitoring Committee meeting was held on January 22nd, 2021. The
LTA understands no grievances were reported by the committee members during the meeting.
The Minutes of the Meetings have been requested from the Owner but they are yet to be received.
The Owner reported no stakeholder grievances for the construction monitoring period. A notice
board detailing contact details for complaints or suggestions remains in place at the entrance to
the Project site. The Owner also uses the mobile communication/social media application known
as Line for receiving grievances/concerns via a community group established on the Line
application which has been shared with community representatives. The LTA recommends that
the Owner establishes a Community Relations Activity Register to document community concerns
which aren’t grievances. This should include concerns raised by the community through social
media and those directly made to the Owners Community Relations team

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 4

Environmental and Social Monitoring
The EHS capacity (resources) observed for this construction monitoring period and the training
undertaken was considered to be sufficient. The Owner and Contractor continue to implement
specific HSE procedures and programs, this includes implementing COVID-19 prevention
methods.
It is AFRY’s opinion that the Project was operating in compliance with the Project E&S
requirements during the construction monitoring period.
In addition to establishing the Community Relations Activity Register an additional Corrective
Action for this period is for the Owner to update the Schedule 3 - Environmental and Social
Monitoring Compliance Report (July to December 2020) to address the comments of the LTA and
ADB shared with the Owner prior to and during the virtual site visit.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                            Page 5

Contents
1     Introduction ....................................................................................................... 9
1.1      Project Description ............................................................................................. 9
1.2      Role of AFRY.................................................................................................... 13
1.3      Objectives of the Report .................................................................................... 13
1.4      Construction Monitoring Period ........................................................................... 14
1.5      Project Participants ........................................................................................... 14

1.6      Virtual Site Visit Agenda .................................................................................... 14
1.7      Reports Reviewed............................................................................................. 15

2     Health And Safety ............................................................................................. 16
2.1      Overview ........................................................................................................ 16

2.2      Health and Safety Statistics ............................................................................... 16
2.3      Fatalities......................................................................................................... 19
2.4      Accident / Incident Reporting ............................................................................. 19
2.5      HSE Staff ........................................................................................................ 20
2.6      Low Risk Issues ............................................................................................... 20

3     Labor And Working Conditions And Security ...................................................... 21
3.1      Workforce Profile and Recruitment ...................................................................... 21

3.2      Welfare Facilities at Project Site .......................................................................... 21
3.3      Workers Grievance Mechanism ........................................................................... 23
3.4      Workers Camp and Transportation ...................................................................... 23
         3.4.1       Workers Camp .................................................................................... 23
3.5      Transportation ................................................................................................. 25
3.6      Security .......................................................................................................... 25
         3.6.1       Project Site and Block Valve Station........................................................ 25
         3.6.2       Workers Camp .................................................................................... 25

4     Stakeholder Engagement .................................................................................. 26
4.1      Engagement Activities and CSR .......................................................................... 26
4.2      Stakeholder Grievance Mechanism ...................................................................... 26

5     Environmental And Social Monitoring ................................................................ 27
5.1      EHS Capacity (Resources and Training) ................................................................ 27
         5.1.1       EHS Capacity (Resources) ..................................................................... 27
         5.1.2       EHS Training....................................................................................... 27
5.2      EHS Licenses, Permits, Authorizations and Compliance Status .................................. 28

5.3      EHS Management System and Implementation Status ............................................ 29
         5.3.1       EHS Policies ........................................................................................ 30

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 6

         5.3.2       Organisational Structure and Staffing ...................................................... 30
         5.3.3       HSE Procedures and Programs ............................................................... 30
         5.3.4       Training Requirements.......................................................................... 32
         5.3.5       EHS Monitoring and Reporting ............................................................... 32
5.4      Compliance with EHS National Laws and Regulations .............................................. 32
         5.4.1       Construction Environmental Monitoring ................................................... 32
         5.4.2       Ambient Air Quality .............................................................................. 32
         5.4.3       Noise ................................................................................................. 33
         5.4.4       Wastewater from Workers ..................................................................... 33
         5.4.5       Waste ................................................................................................ 36
5.5      Compliance with ESIA/EMP, ADB Safeguards, IFC Performance Standards and IFC EHS
         Guidelines ....................................................................................................... 38
         5.5.1       IFC EHS Guidelines .............................................................................. 71
         5.5.2       Land Acquisition and Involuntary Resettlement ......................................... 72
5.6      Associated Facilities .......................................................................................... 72
         5.6.1       Hemaraj Raw Water Pipeline.................................................................. 72
         5.6.2       500 kV Overhead Transmission Line........................................................ 72

6     Corrective Action Plan....................................................................................... 74

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 7

Figures and tables

Figures
Figure 1-1 Location of GSRC Project Site ......................................................................... 9
Figure 1-2 Project Area within HESIE ............................................................................ 10
Figure 1-3 Interconnecting Pipeline Start Point and End Point............................................ 11
Figure 1-4 Proposed Alignment of the 500 kV Overhead Transmission Line (Red Line) ........... 11
Figure 1-5 Alignment of Hemaraj Raw Water Pipeline(Yellow Line) ..................................... 12

Tables
Table 2-1 HSE Statistics 1 ........................................................................................... 16
Table 2-2 HSE Statistics 2 ........................................................................................... 17
Table 2-3 HSE Incidents ............................................................................................. 17
Table 2-4 HSE Staff for the Power Plant Area and Raw Water Pond Area ............................. 20
Table 3-1 Workforce Number ....................................................................................... 21
Table 3-2 Labour Protection Act Requirements and Compliance for Welfare Facilities ............. 22
Table 3-3 Owner Workers Camp Checklist ...................................................................... 24
Table 5-1 EHS Training During the Construction Monitoring Period ..................................... 27
Table 5-2 Status of EHS Related Permits ....................................................................... 28
Table 5-3 Status Approval for Interconnecting Pipeline..................................................... 29
Table 5-4 Status of EHS Polices.................................................................................... 30
Table 5-5 Status of Existing HSE Procedures and Programs for the Power Plant .................... 30
Table 5-6 Water Quality Monitoring Results at the Project Site .......................................... 34
Table 5-7 Water Quality Monitoring Results at the Workers Camp ...................................... 35
Table 5-8 Waste Monitoring Results .............................................................................. 37
Table 5-9 Status of Project Against Project E&S Standards of the ESIA/EMP......................... 38
Table 5-10 Project Compliance with IFC EHS Guidelines ................................................... 71
Table 6-1 Corrective Action Plan for the Construction Monitoring Period (January to March 2021)
            ............................................................................................................. 75

 Appendices
Appendix 1          – Virtual Site visit Photos ...................................................................... 76

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Environmental and Social Monitoring Report - Asian ...
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 8

GLOSSARY OF TERMS

 ADB                                   Asian Development Bank
 CSR                                   Corporate Social Responsibility
 E&S                                   Environmental and Safety
 EHS                                   Environmental, Health and Safety
 EMP                                   Environmental Management Plan
 EPC                                   Engineering, Procurement and Construction
 ESIA                                  Environmental and Social Impact Assessment
 GT                                    Gas Turbine
 HESIE                                 Hemaraj Easter Seaboard Industrial Estate
 HSE                                   Health, Safety and Environment
 IFC                                   International Finance Corporation
 JBIC                                  Japan Bank for International Cooperation
 LTS                                   Lenders’ Technical Advisor
 MHPS                                  Mitsubishi Hitachi Power Systems Project (Thailand)
 MOI                                   Ministry of Interior
 MW                                    Megawatt
 OHS                                   Occupation Health and Safety
 ONEP                                  Office of Natural Resources and Environmental Policy and Planning
 PPA                                   Power Purchase Agreement
 SCOD                                  Schedule Commercial Operation Date
 SPS                                   Safeguard Policy Statement
 WBG                                   World Bank Group
 WHO                                   World Health Organisation

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                         copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                           Page 9

1             Introduction

1.1             Project Description

Gulf SRC Company Limited (“GSRC” or the “Owner”) is developing Gulf SRC 2,500 megawatt
(“MW”) Combined Cycle Power Plant (“CCPP”) project in Hemaraj Easter Seaboard Industrial
Estate (“HESIE”), Sriracha District, Chonburi Province, approximately 140 km east of Bangkok.
The site location is shown in Figure 1 1 and location within the HESIE is shown in Figure 1-2

Figure 1-1 Location of GSRC Project Site

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 10

Figure 1-2 Project Area within HESIE

GSRC is being developed on an IPP basis and a 25-years Power Purchase Agreement (“PPA”) has
been signed with EGAT. The Commercial Operation Date (COD) of Unit 1 was achieved on of Unit
1 was achieved on March 31st, 2021. The Schedule Commercial Operation Date (“SCOD”) Unit 2,
Unit 3 and Unit 4 are October 1st, 2021, March 31st, 2022 and October 1st, 2022 respectively.
Natural Gas is transported to GSRC through a new 2.5 km long 28 inches diameter gas pipeline
(“Interconnecting Pipeline”) which is now fully constructed. The Interconnecting Pipeline connects
to the power plant from PTT’s 5th pipeline. The Interconnecting Pipeline start point and end point
is shown in Figure 1-3

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 11

Figure 1-3 Interconnecting Pipeline Start Point and End Point

EGAT will build a new 10.9 km long 500 kV double circuit 4 x 1272 MCM ACSR Overhead
Transmission Line to connect GSRC’s switchyard with EGAT’s Pluak Daeng Substation. The 500 kV
Overhead Transmission Line is considered an “associated facility” in accordance with Asian
Development Bank (“ADB”) Safeguard Policy Statement (“SPS”) 2009 and the International
Finance Corporation (“IFC”) Performance Standards 2012 as this facility will not be funded as part
of the Project. The alignment of the 500 kV Overhead Transmission Line from the GSRC’s
switchyard to EGAT’s Pluak Daeng Substation is shown in Figure 1-4 (red line).

Figure 1-4 Proposed Alignment of the 500 kV Overhead Transmission Line (Red Line)

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 12

Raw water to GSRC is supplied by East Water at a maximum flow rate of 63,000 m3/day. East
Water is managing the raw water supply source within the eastern region area of Thailand. GSRC
will have three raw water ponds located adjacent to the power plant area. The GSRC raw water
ponds have a total capacity of 189,000 m3. The Hemaraj Raw Water Pipeline to supply the raw
water during construction and operation is also considered an associated facility under ADB SPS
2009 and the IFC Performance Standards 2012. The alignment of the Hemaraj Raw Water Pipeline
is shown by the yellow line in Figure 1-5

Figure 1-5 Alignment of Hemaraj Raw Water Pipeline(Yellow Line)

Wastewater from GSRC will be discharged back into the wastewater discharge of HESIE at an
interface point located north west of the power plant.
GSRC will consist of four separate power blocks, all consisting of one gas turbine, one steam
turbine and one HRSG in a 1-1-1 single shaft arrangement. The gas turbine (“GT”) model selected
for GSRC is MHPS M701JAC gas turbine.
GSRC will be cooled through the user of an indirect “recirculating” wet cooling water system using
mechanical draft cooling towers.
GSRC will use natural gas as primary fuel with diesel oil used as back-up fuel.
The Engineering, Procurement and Construction (“EPC”) arrangement for GSRC consists of the
following contracts:

·    The Supply Contract between Gulf SRC Company Limited (“GSRC” or the “Owner”) and
     Mitsubishi Hitachi Power System, Ltd, as Supplier, for design and engineering services
     performed outside of Thailand and for the supply of equipment and materials to be imported
     into Thailand date February 8th, 2018;

·    The Construction Contract between Gulf SRC Company Limited (“GSRC” or the “Owner”) and
     the consortium of Mitsubishi Hitachi Power Systems Project (Thailand) Company Limited
     (“MHPS-PTC”) and Sino-Thai Engineering and Construction Public Company Limited (the
     “Contractor”) dated February 8th, 2018; and

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                            Page 13

·      The Coordination Agreement between the Owner, the Supplier and the Contractor (the
       Supplier and the Contractor are jointly referred to as the “EPC Contractor”) dated February
       8th, 2018.

For design review and construction management purpose for the EPC contract, GSRC has entered
into an Owner’s Engineer agreement with Black and Veatch. For construction site supervision
(including environmental & safety), GSRC has entered into an Owner’s Engineer agreement with
EGAT.
The Notice to Process for the EPC contractor was issued on December 3rd, 2018, with the Limited
Notice to Proceed issued in July 2018.
The financial close for GSRC was achieved in Q4/2018.

1.2               Role of AFRY

AFRY (Thailand) Ltd. (“AFRY” or the “LTA”) has been appointed in the role of Lenders’ Technical
Advisor for the construction and operating and maintenance phases of the Project up to the third
year of the operational phases of all Units.
During this time the LTA will monitor the progress of GSRC and advise the Lenders in all technical,
management and environmental and social (“E&S”) issues that may have a material effect on the
financial standing and success of GSRC. During the construction period the LTA will make
quarterly site visits and meetings with the Owner and relevant parties.

1.3               Objectives of the Report

The objectives of the quarterly E&S monitoring are as follows:
       ·    To assess the Projects compliance with the following Project E&S standards during
            construction:
                 -    Applicable Thailand Laws, legislation and regulations;
                 -    ADB SPS (2009);
                 -    World Bank Group (“WBG”) General Environmental, Health and Safety (“EHS”)
                      Guidelines (2007);
                 -    WBG EHS Guidelines for Thermal Plants (2008);
                 -    IFC Performance Standards (2012)1 , including:
                           §    PS1: Assessment & Management of Environmental & Social Risks &
                                Impacts;
                           §    PS2: Labour and Working Conditions;
                           §    PS3: Resource Efficiency and Pollution Prevention;
                           §    PS4: Community Health, Safety, and Security;
                           §    PS5: Land Acquisition and Involuntary Resettlement;
                           §    PS6: Biodiversity Conservation and Sustainable Management of Living
                                Natural Resources;
                           §    PS8: Cultural Heritage.
                 -    Japan Bank for International Cooperation (JBIC) Guidelines for Confirmation of
                      Environmental and Social Considerations, 2015.

1
    FC PS7 (Indigenous Peoples) is not considered applicable to the Project

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                            copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 14

     ·    To review the implementation of the mitigation and monitoring programmes specified in
          the Environmental Management Plan (“EMP”) developed as part of the Environmental and
          Social Impact Assessment (“ESIA”) for ADB dated October 2018;
     ·    To review the status of EHS management onsite, including the Company’s EHS
          Management System, procedures and training and to identify areas for improvement;
     ·    To review the Projects EHS records and compliance with respect to the site specific
          management system by the Owners, EPC Contractor and sub-contractors;
     ·    To provide objective reports to the Lenders confirming compliance and if not, recommend
          corrective actions, as appropriate to the Project during construction.

1.4             Construction Monitoring Period

This E&S Monitoring Report is the ninth Quarterly E&S Monitoring Report of the LTA and covers
the period from January 1st, 2021 to March 31st, 2021. The report is based on inputs received
from the Owner, the EPC Contractor and discussions held via virtual site visit (due to the COVID-
19 pandemic) on April 22nd, 2021.

1.5             Project Participants

This virtual site visit was attended by the following LTA representatives:
     ·    Mr. Mark Wilson (LTA’s Senior Environmental Consultant);
     ·    Mr. Ilkka Lassila (LTA’s Project Manager);
     ·    Mr. Pramual Numsong (LTA’s Senior Project Engineer); and
     ·    Mr. Tanawat Chaiwatanarat (LTA’s Senior Project Engineer).

1.6           Virtual Site Visit Agenda

Discussions and interviews were undertaken with representatives of GSRC, EGAT and the EPC
Contractor. The following topics were discussed for the construction monitoring period and
findings are presented in this report.
     ·    Safety Statistics;
     ·    Safety Incidents and Reports;
     ·    Environmental Compliance;
     ·    Environmental Monitoring;
     ·    EHS Management Plans;
     ·    EHS training;
     ·    Stakeholder engagement and grievance records;
     ·    EHS capacity (resources);
     ·    Updates to COVID-19 prevention measures/emergency plan;
     ·    Land acquisition/completion of payment status for remaining plots of the NTF. Any
          ongoing landowner/community grievances concerned with the NTF;
     ·    Review of comments on ADB E&S Monitoring Compliance Report July to December 2020.
There were no consultations undertaken with communities during the virtual site visit due to the
COVID-19 pandemic.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 15

1.7             Reports Reviewed

The relevant Project documents pertaining to E&S have also been reviewed. This was aimed at
understanding the ongoing implementation, record maintenance, internal monitoring and
reporting and mandatory regulatory compliances required for the Project.
The following documents were reviewed by AFRY for this construction monitoring period:
     ·    GSRC Progress Technical Reports, January 2021, February 2021 and March 2021;
     ·    EGAT Progress Technical Report for NTF, January 2021, February 2021 and March 2021;
     ·    Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation
          (EHS), April 22nd, 2021;
     ·    Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation (Site
          Progress), April 22nd 2021;

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                               Page 16

2               Health And Safety

2.1             Overview

Occupational Health and Safety (“OHS”) for the Power Plant continues to be principally managed
through the Health, Safety and Environment (“HSE”) Management Plan (GSRC-ST-MPS-G/S-
0988) Revision C1.
Other HSE Procedures implemented are described in Section 5.3.3.

2.2             Health and Safety Statistics

The Health and Safety statistics for the Power Plant for this construction monitoring periods are
shown in Table 2-1 and Table 2-2. The Health and Safety statistics are no longer shown for the
Interconnecting Pipeline since the works are completed.
A description of the HSE incidents are provided in Table 2-3.
Table 2-1 HSE Statistics 1

                                                                                                Power Plant

 Man-Power            Total Man-Hours Record                                                    2,081,004
 Data

 Accident        /    TIRR                                           Report table (3            (0)
 Incident                                                            days or more
 Records                                                             absence    from
                                                                     work)

                                                                     Lost time (0.5             (0)
                                                                     days or more
                                                                     absence   from
                                                                     work)

                      First Aid (Medical Treatment at Site)                                     0

                      Property Damage                                                           0

                      Potentially Serious Incident                                              7

Source:         Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation (EHS), 22nd April 2021.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                               copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                              Page 17

Table 2-2 HSE Statistics 2

                                    Item                                                          Number

 A: Fatalities                                                                                         0

 B: Lost time incidents (including vehicular)                                                          0

 C: Incidents and near-misses                                                                          7

 D: Hazard observations                                                                              131

 E: Total number of lost workdays resulting from                                                       0
 incidents

 F: Total person-hours worked this reporting period                                              2,081,004

 G: Incident during this reporting period                                                              7

 (Note: Incidence = total lost workdays/total hours                                                    0
 worked)

 H: Lost Time Injury Frequency Rate                                                                    0

 (Number of lost time accidents x 1,000,000 total                                                      0
 person-hours worked – lost workdays per million
 hours worked)

 J: Lost Time Severity Rate                                                                            0

 (Total Lost workdays x 1,000,00 hours/total                                                           0
 person-hours worked – lost workdays per million
 hours worked).

 K: Security Loss                                                                                      0
Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation (EHS), 22nd April 2021.

Table 2-3 HSE Incidents

      HSE Incident                         Date                       Corrective Action                           Status

 Fire fighting system           -                              Corrective Actions:                       Closed
 was activated
                                                                ·   Stop fuel oil unloading;
 during fuel oil
                                                                ·   Stop fire fighting
 unloading.
                                                                    system;
                                                                ·   Check for water
                                                                    contamination in oil
                                                                    transport truck.
                                                               Preventative Actions:
                                                                ·   Work in commissioning
                                                                    area retraining;
                                                                ·   Lessons learned to all
                                                                    supervisors;
                                                                ·   Supervisor safety talk.

 Steel bar fell from            -                              Corrective Actions:                       Closed
 scaffolding in HRSG
                                                                ·   Stop work;
 building #2 striking
 a workers shoulder.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                              copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 18

      HSE Incident                     Date                       Corrective Action                         Status
                                                            ·   Check scaffolding
                                                                condition and rectify
                                                                immediately.
                                                          Preventative Actions:
                                                            ·   Scaffolding supervisor
                                                                to recheck scaffolding
                                                                condition before
                                                                starting work;
                                                            ·   Safety talk;
                                                            ·   Restrict areas under
                                                                which work at height
                                                                activities are being
                                                                performed and provide
                                                                watchman.

 Scaffolding pipe fell         29th January 2021          Corrective Actions:                      Closed
 from mobile
                                                            ·   Stop work and prohibit
 scaffolding striking
                                                                work with scaffolding
 workers resulting in
                                                                with red tag.
 injury.
                                                          Preventative Actions:
                                                            ·   Safety stand down for
                                                                scaffolding team;
                                                            ·   Retraining of
                                                                scaffolding team;
                                                            ·   Scaffolding condition to
                                                                be checked prior to use

 Intermediate bulk             2nd February 2021          Corrective Actions:                      Closed
 container (IBC)
                                                            ·   Stop work in area;
 explosion at
                                                            ·   Chemical cleaning.
 HRSG#2.
                                                          Preventative Actions:
                                                            ·   Review and revise
                                                                procedure/method
                                                                statement JSA for safe
                                                                work condition;
                                                            ·   Install and setup new
                                                                drain system;
                                                            ·   Measure ambient
                                                                conditions by gas
                                                                detector for toxic gas
                                                                and flammable every 1
                                                                hour.

 HRSG manholes                 1st February 2021          Corrective Actions:                      Closed
 opened during start
                                                            ·   Check condition of all
 of Gas Turbine
                                                                manholes;
                                                            ·   Restart Gas Turbine.
                                                          Preventative Actions:
                                                            ·   All commissioning work
                                                                (outage work) will be
                                                                list for all of job and all
                                                                work in list will be

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 19

      HSE Incident                     Date                       Corrective Action                         Status
                                                                completed before start
                                                                up plant;
                                                            ·   Conduct safety walk
                                                                down before starting
                                                                activities.

 Condensate Water              1st February 2021          Corrective Actions:                      Closed
 Flushing Leakage
                                                            ·   Stop condensate pump
                                                                and check condition
                                                                before restart.
                                                          Preventative Actions:
                                                            ·   Cross check with
                                                                construction and
                                                                commissioning team
                                                                before starting the
                                                                system.

 Ring main pipe F/F            17th February 2021         Corrective Actions:                      Closed
 broken by a
                                                            ·   Stop work;
 backhoe.
                                                            ·   Pumping the water in
                                                                area for repaired pipe;
                                                            ·   Standby by fire truck in
                                                                area for emergency
                                                                case during pipe repair.
                                                          Preventative Actions:
                                                            ·   Before start excavation
                                                                work related parties
                                                                will verify UG system
                                                                and inform to
                                                                excavator.
                                                            ·   Submit excavation
                                                                permit as early as
                                                                possible(at least 1 day
                                                                earlier)

2.3             Fatalities

There were no fatalities reported during the construction monitoring period.

2.4             Accident / Incident Reporting

The accident / incident reporting procedure is specified in the HSE Management Plan. It specifies
that all accidents and incidents shall be reported to the HSE Managers of the EPC Contractor who
will take the necessary steps in investigating and adopting corrective measures. Immediate
reporting is required in the case of the following:
               -    Personal Injuries;
               -    Damage to Property or Equipment;
               -    Near Miss Incident; and
               -    Environmental – Non-conformance Report.
The incidents / accidents which occurred during the construction monitoring period as described
in Table 2-3 have been documented and recorded.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                             Page 20

2.5              HSE Staff

The HSE staff of Sino-Thai and MHPS-PTC responsible for HSE management/supervision in the
Power Plant Area and Raw Water Pond Area are shown in Table 2-4. The ratio for number of safety
officers to number of workers is one safety officer per 50 workers which is considered to be
sufficient.
In addition, the Owner currently has an EHS Manager and EHS Officer. EGAT also has a dedicated
HSE Manager.
Table 2-4 HSE Staff for the Power Plant Area and Raw Water Pond Area

                                Position                                                      Number of Staff

 Senior Officer Management Level                                                                        3

 Safety Officer Professional Level                                                                      7

 Safety Officer Technical Level                                                                        50

 Nurse                                                                                                  2

 Myanmar Translator                                                                                     1

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 22th April 2021.

2.6              Low Risk Issues
There were no low risk issues identified during the construction monitoring period.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                             copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 21

3               Labor And Working Conditions And Security

3.1             Workforce Profile and Recruitment

The number of male workers and female workers as of March 25th, 2021 is shown in Table 3-1.
The number of STECON male workers comprise 79% of the workforce, while the number of female
workers comprise 21% of the workforce.
Table 3-1 Workforce Number

         Company                  Number of Male Workers                           Number of Female Workers

 Owner                                          60                                                   7

 EGAT                                           36                                                   5

 MHPS-PTC                                       122                                                  9

 STECON                                       1,513                                                397

 STECON                                         288                                                143
 Subcontractors

 STECON                                         18                                                   2
 Subcontractors –
 Security

 STECON                                          0                                                   2
 Subcontractors -
 Nurse

 Total                                        2,037                                                565

3.2             Welfare Facilities at Project Site

The welfare facilities at the Project site comprises of the following:
     ·    Toilet/bathroom facilities. There are 231 toilets installed in the Project site (181 male
          toilets and 50 female toilets). According to GSRC Progress Technical Report - EIA
          Checklist Report male workers comprise of 2,573 persons and female workers comprise
          of 550 persons as of March 10th, 2020. The ratio of toilet/bathroom to number of workers
          complies with the ESIA and The Ministry of Interior (“MOI”) ministerial law No. 63 (BE
          2551) issued under the Building Control Act BE 2522 requirement of at least one (1) toilet
          for 15 workers or less, two (2) toilets for 40 workers or less, three (3) toilets for 80
          workers or less, and additional one (1) toilet for additional 50 workers;
     ·    Sufficient number of drinking water tanks with water analysis complying to the Thailand
          drinking water standards;
     ·    Four (4) main rest shelters in the Power Plant Area and One (1) rest shelter in the Raw
          Water Pond Area;
     ·    Medical facilities including ambulance. Two (2) qualified nurses are employed by the
          Project and are based on site 7 days per week (8:00am to 5:00pm).
The applicable requirements of the Labour Protection Act B.E. 2541 concerning welfare facilities
and Project compliance during the construction monitoring period is shown in Table 3-2.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 22

Table 3-2 Labour Protection Act Requirements and Compliance for Welfare Facilities

             Requirement                                   Project Compliance at the Project Site

 Section 96 “In a place of                  The Project has established a Welfare Committee as of 1st
 business with fifty Employees              June 2019 comprising of five (5) employee representatives
 or more, an Employer shall                 whose remit also covers the welfare facilities.
 arrange for the establishment
                                            MHPS has appointed one (1) welfare auditor (male) and two
 of a welfare committee at the
                                            (2) designated welfare officers representatives (female) to
 place of business, comprising
                                            monitor labor and welfare requirements. The welfare auditor
 of at least five Employee
                                            and officers are identified in the EPC Contractor
 representatives”. The welfare
                                            organizational chart.
 committee duties are
 described in the Land                      Safety Induction material includes details of the welfare
 Protection Act and the                     officers and the methods of communication.
 employer must hold a meeting
 with the welfare committee
 every 3 months and whenever
 half of its members requests a
 meeting.

 The Company shall arrange                  Based on the number of toilet/bathroom facilities described
 the following:                             in Section 3.2 the Project is complying with these
                                            requirements.
 Clean drinking water and
 restrooms as follows:                      Raw water supplied by HESIE and drinking water supplied in
                                            tankers. Drinking water analysis report provided on each
 ≤ 15 employees: 1 restroom,
                                            tanker to show compliance with Thailand drinking water
 1 toilet, 1 drinking point;
                                            standards.
 ≤ 40 employees; 1 restroom,
 2 toilers, 1 drinking point;
 ≤ 80 employees; 1 restroom,
 3 toilets, 2 drinking point.
 Over 80 employees: for every
 additional 50 employees;
 additionally, 1 restroom, 1
 toilet, 1 drinking point.

 First aid service and medical              Two (2) permanent nurses are employed by the Project and
 supplies for employees injuries            adequate first aid facilities are still located at the medical
 or sickness.                               facilities and within the first aid kits provided in the
                                            construction areas. Ambulances to transport workers to
 If the company has more than
                                            hospital are located onsite.
 10 employees it must have a
 first-aid kit (including e.g.
 scissors, cotton, alcohol 70%,
 medicines, etc.) available at
 the work place.
 In case of industrial work
 place, the following additional
 facilities have to be provided:
 For the place with more than
 100 employees, a ward with
 one bed, 1 permanent nurse
 and 1 doctor who visits
 occasionally;
 For the place with more than
 1,000 employees, a ward with

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 23

             Requirement                                   Project Compliance at the Project Site
 2 beds, 2 permanent nurses, 1
 doctor who is scheduled to
 visit regularly at least for 2
 hours, and transportation to a
 hospital.

3.3             Workers Grievance Mechanism

There were no workers grievances / suggestions recorded during the construction monitoring
period.

3.4             Workers Camp and Transportation

3.4.1         Workers Camp

There are currently sufficient rooms (1,684) for the current total number of persons residing
(1,887) i.e. no more than 2 adults to a room.

Workers Camp Living Conditions
Based on the photographs observed, the hygiene/cleanliness of the workers camp is considered
to be adequate in Zones 1, 2 and 3 of the workers camp.
The Owner and Contractor continues to undertake monthly inspections at the workers camp and
no non-compliances against the Owners Camp Checklist shown in Table 3-3 have been reported
during the construction monitoring period.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 24

Table 3-3 Owner Workers Camp Checklist

 Item                 Action

 1                    Dimension of the room, total area should be not less than 9 m2 (width greater
                      than 2 metre and height greater than 2.4 metre), with personal space not less
                      than 3 m2 /person.

 2                    If the building is longer than 45 m in width, then there need to be a 2.5 m gap
                      between buildings, along the building depth.

 3                    Natural ventilation. Room is equipped with door or ventilation with total area of
                      not less than 10% of the room area, excluding the door and window.

 4                    Number of toilets are sufficient for the total residents residing at the camp.

 5                    Separate bathing area and toilet. Separated male and female toilets.

 6                    The waste generated shall be managed in accordance to the law. Wastewater
                      discharge shall not impact persons surrounding the workers camp.

 7                    When areas of the camp area are occupied by more than 10 people, basic medical
                      kits shall be made available. Emergency contact number of the nearest health
                      care centre needs to be displayed.

 8                    Electrical wire and equipment should be in good condition and a protection
                      system in place. The installation needs to follow the standard code for outdoor
                      (THW, MEA TYPE A) and indoor (300V 70oC VAF).

 9                    An appropriate number of fire extinguishers should be installed and of the correct
                      type.

 10.                  An appropriate emergency alarm system should be installed, covering all of the
                      workers camp.

 11.                  There should be sign placed at the workers camp entrance to inform that the
                      workers camp is a residential area.

 12                   Fencing should be in place to secure the workers camp with a designated
                      entrance and exit.

 13.                  There should be warning signs prohibiting drug usage.

 14.                  For every 10 persons residing at the workers camp one camp watchman needs
                      to be allocated to ensure the camp operates in accordance with the site rules.

Workers Camp Welfare Facilities and Amenities
The following is observed concerning the welfare facilities at the workers camp:
      ·   154 toilets are now installed in the workers camp (98 male toilets and 56 female toilets)
          and number of males residing comprises of 1,360 persons and number of female workers
          residing comprises of 527 persons as of March 21st, 2021. Ratio of toilet/bathroom to
          number of workers complies with the ESIA and The MOI ministerial law No. 63 (BE 2551)
          issued under the Building Control Act BE 2522 requirement of at least one (1) toilet for
          15 workers or less, two (2) toilets for 40 workers or less, three (3) toilets for 80 workers
          or less, and additional one (1) toilet for additional 50 workers;

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 25

     ·    Based on photographs, the bathrooms and toilets were found to be of good hygiene with
          privacy. Regular inspections/cleaning of the facilities continues;
     ·    Medical facilities. Adequate medical/first aid facilities are still in place. The Project site
          nurses are still used to attend any medical matters at the workers camp;
     ·    As part of the COVID-19 preventative measures the workers camp continues to have a
          dedicated area for new workers and area of quarantine in case any of the residents are
          found to have symptoms of COVID-19.

Wastewater Treatment System
Wastewater from the workers camp continues to be discharged to an onsite wastewater treatment
system comprising of an aerated pond and sedimentation pond. The wastewater treatment
system remains at a capacity based on a maximum number of 3,200 persons residing at the
workers camp during the construction period and wastewater rate of 200 litres/person/day. The
wastewater treatment system was observed to be in good condition.
Water quality monitoring continues to be undertaken at a sampling location adjacent to the
sedimentation pond prior to discharge on a monthly basis and the results are provided in
Section 5.

3.5             Transportation
The Contractors continue to be transported to site by shuttle buses. The shuttle buses are able
to accommodate up to 25 persons. The location of the pickup point for the transportation remains
an approximate 5 to 10 minute walk from the workers camp.

3.6             Security

3.6.1           Project Site and Block Valve Station
Security continues to be provided by the security contactor GIANT. Site Security Plan Rev A has
been approved by the Owner and is still considered to be appropriate.
The security contractor continues to monitor the control points and the Project site 24 hours per
day. The security guards work 12 hours per day on a shift basis. The security guards continue
to be positioned at the following locations:
     ·    Main entrance gate at Power Plant Area. Dayshift is two (2) security guards and nightshift
          is (two) 2 security guards.
     ·    Emergency gate at Power Plant.
     ·    Main office area: No Security guard for dayshift and one (1) security guard positioned at
          night shift; and
     ·    Raw Water Pond area: One (1) security guard positioned at day shift and one (1) for night
          shift.
The number of security guards required continues to be reviewed periodically and shall be
increased if necessary.

3.6.2           Workers Camp
The Site Security Plan also includes security rules and regulations for the workers camp. Security
is provided 24 hours per day at the workers camp entrance. Security guards continue to monitor
the incoming/ outgoing of people and vehicles at the main entrance gate.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 26

4               Stakeholder Engagement

4.1             Engagement Activities and CSR
The Environmental Impact Monitoring Committee meeting was held on January 22nd, 2021. The
LTA understands no grievances were reported by the committee members during the meeting.
The Minutes of the Meetings have been requested from the Owner but they are yet to be received.

4.2             Stakeholder Grievance Mechanism
The Owner reported no stakeholder grievances for construction monitoring period. A notice board
detailing contact details for complaints or suggestions remains in place at the entrance to the
Project site. The Owner also uses the mobile communication/social media application known as
Line for receiving grievances/concerns via a community group established on the Line application
which has been shared with community representatives. The LTA recommends that the Owner
establishes a Community Relations Activity Register to document community concerns which
aren’t grievances. This should include concerns raised by the community through social media
and made directly to the Owners Community Relations team.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 27

5               Environmental And Social Monitoring

5.1             EHS Capacity (Resources and Training)

5.1.1          EHS Capacity (Resources)

The EHS staff employed for the construction monitoring period are described in Section 2.5. The
EHS capacity observed at site for this construction monitoring period is considered to be
appropriate.
The HSE Committee continues to meet every month to review the overall safety at site and
develop guidelines to improve E&S.

5.1.2          EHS Training

The EHS training undertaken during the construction monitoring period is shown in Table 5-1.
The LTA considers the training to be appropriate based on the construction activities.
The gender based violence training continues to be incorporated into the safety induction and re-
inductions.
Table 5-1 EHS Training During the Construction Monitoring Period

         No.                   January 2021                       February 2021                        March 2021

 Safety                               83                                  247                               195
 Induction
 Training

 Safety                               21                                  117                               230
 Induction
 Training (Re-
 Induction)

 PTW Worker                           83                                  247                               195

 Working at                           79                                  235                               187
 Height

 Rigger                                0                                   0                                  0

 Hot Working                           6                                  11                                  0

 Fire Watch                            6                                  12                                  0

 Job Safety                            0                                   0                                  0
 Analysis

 Supervisor                            0                                   0                                  0
 Training

 Scaffolding 1                         0                                  27                                 20

 Scaffolding 2                         0                                   0                                  0

 First Aid                             0                                   0                                  0

 Basic Fire                            0                                   0                                  0
 Fighting

 Lifting                               0                                   0                                  0
 Supervisor

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 9

                                                                                                                          Page 28

           No.                 January 2021                       February 2021                        March 2021

 Banks Man                             0                                   0                                  0

 Confined                              2                                  17                                 41
 Space

 Hazard                               83                                  247                               195
 Observation

 Commissioning                       124                                  376                               209
 Training

 Safety                                0                                   0                                214
 Training of
 COD

Source: 2021-01, 2021-02, 2021-03 GSRC Progress Technical Report_CC

The following EHS training also continued as reported in the previous construction monitoring
period:
      ·     Contractor provides Safety Talks two times per week for all workers; and
      ·     Daily tool box talks for all workers.

5.2              EHS Licenses, Permits, Authorizations and Compliance Status

The status of the EHS related permits are provided in Table 5-2
Table 5-2 Status of EHS Related Permits

          No.                  Permits                    Authorization Authority                        Status

 1                EIA Power Plant                       Office of Natural                     Approved December
                                                        Resources and                         2nd, 2015
                                                        Environmental Policy and
                                                        Planning (ONEP)

 2.               EIA Gas Pipeline                      Office of Natural                     Approved October 5th,
                                                        Resources and                         2017
                                                        Environmental Policy and
                                                        Planning (ONEP)

 3.               EIA Power Plant                       Office of Natural                     Approved August 23rd,
                  (Amendment)                           Resources and                         2018
                                                        Environmental Policy and
                                                        Planning (ONEP)

 4.               Report of Environmental               Office of Natural                     Ongoing. Owner
                  Mitigation Measures and               Resources and                         required to submit
                  Monitoring Programs                   Environmental Policy and              mitigation and
                  during construction and               Planning (ONEP)                       monitoring reports to
                  commissioning.                                                              ONEP every 6 months
                                                                                              during construction.
                                                                                              The report for July
                                                                                              2020 to December
                                                                                              2020 was submitted to
                                                                                              ONEP in January 2021.

 5.               Registration of Plant                 Industrial Works                      Registration will be
                  Pollution Control System              Department (IWD)                      after COD.
                  Supervisor prior to

Gulf SRC 2,500 MW Combined Cycle Power Plant Project
127000407                                                                                                          copyright©AFRY

Date 10 May 2021, Revision 0
You can also read