CLASS GUIDELINE DNVGL-CG-0058 Edition April 2016 Maintenance of safety equipment The electronic pdf version of this document, available free of charge from http://www.dnvgl.com, is the officially binding version. DNV GL AS
FOREWORD DNV GL class guidelines contain methods, technical requirements, principles and acceptance criteria related to classed objects as referred to from the rules. © DNV GL AS April 2016 Any comments may be sent by e-mail to rules@dnvgl.com If any person suffers loss or damage which is proved to have been caused by any negligent act or omission of DNV GL, then DNV GL shall pay compensation to such person for his proved direct loss or damage. However, the compensation shall not exceed an amount equal to ten times the fee charged for the service in question, provided that the maximum compensation shall never exceed USD 2 million. In this provision "DNV GL" shall mean DNV GL AS, its direct and indirect owners as well as all its affiliates, subsidiaries, directors, officers, employees, agents and any other acting on behalf of DNV GL.
CHANGES – CURRENT Changes - current This is a new document. Class guideline — DNVGL-CG-0058. Edition April 2016 Page 3 Maintenance of safety equipment DNV GL AS
Contents CONTENTS Changes – current.................................................................................................. 3 Section 1 General.................................................................................................... 5 1 Introduction.........................................................................................5 2 Procedure............................................................................................ 5 3 Application........................................................................................... 5 4 Precautions.......................................................................................... 5 5 Records................................................................................................ 5 6 Abbreviations....................................................................................... 6 Appendix A .............................................................................................................7 1 Life-saving appliances......................................................................... 7 2 Fire protection and fire fighting equipment....................................... 13 3 Fixed firefighting systems................................................................. 20 4 Radio and navigational equipment.................................................... 37 5 Others................................................................................................ 39 Historic changes................................................................................................... 41 Class guideline — DNVGL-CG-0058. Edition April 2016 Page 4 Maintenance of safety equipment DNV GL AS
SECTION 1 GENERAL Section 1 1 Introduction The requirements for inspection and maintenance of safety equipment can be found in a large number of statutory instruments. Establishing an easy, user-friendly and practical overview of such requirements has proven to be challenging. DNV GL intends to address this challenge and provides a compact and practical tool in the format of a list of such requirements for ship owners and operators (“Users”) at the time of the issuance of the document. This list includes also requirements and recommendations by DNV GL and IACS. This document does not address additional or more stringent requirements from manufacturers and flag administrations. Users must take these requirements into account. DNV GL reserves the right to amend the content of the document at any time. 2 Procedure Users may use this document to establish or validate inspection and maintenance routines in their Planned Maintenance Systems. When establishing the maintenance and inspection procedures it should be noted that certain jobs may be performed by competent crew members, while others shall be performed by specially trained persons. It should also be noted that certain jobs needs to be scheduled to coincide with a relevant Safety Equipment Class survey. Which parts of the inspections and maintenance shall be completed by competent crew members or specially trained persons or attended by surveyor, are indicated in the list. 3 Application The document does not replace the original equipment manufacturer’s instructions and maintenance requirements. It is not meant to replace or overrule any existing rules, regulations, statutory requirements or technical standards. Finally, it is not meant to replace Users’ individual responsibility to know the applicable requirements and ensure compliance at all points in time. 4 Precautions As a general rule, all inspections shall be carried out in accordance with the system manufacturer’s instructions and safety precautions. If equipment is undergoing maintenance or testing, then suitable arrangements shall be made to ensure safety is not diminished through the provision of alternate equipment or other measures. 5 Records Records of the inspections shall be carried on board of the ship, or be accessible in digital format on board. In cases where the inspections and maintenance are carried out by specially trained persons other than the ship’s crew, inspection reports shall be provided upon the completion of the inspections. Some inspections required by SOLAS shall be entered in the logbook. Class guideline — DNVGL-CG-0058. Edition April 2016 Page 5 Maintenance of safety equipment DNV GL AS
Section 1 6 Abbreviations Table 1 Abbreviations Abbreviations Description SI DNV GL statutory interpretations. These can be found under “Rules and Standards”. Crew Crew members and/or senior ship’s officers qualified and competent in accordance with relevant circulars. It should be stated in the ship’s quality system who is considered competent to carry out service/maintenance of certain equipment. DNV GL In presence of or by DNV GL surveyor. Maker Manufacturer of the equipment or service company approved by the manufacturer SER Service supplier for the type of equipment/service approved by DNV GL or DNV or GL or flag state administration; accredited laboratory/ service company; shore-based maintenance provider. Class guideline — DNVGL-CG-0058. Edition April 2016 Page 6 Maintenance of safety equipment DNV GL AS
APPENDIX A Appendix A 1 Life-saving appliances Class guideline — DNVGL-CG-0058. Edition April 2016 Page 7 Maintenance of safety equipment DNV GL AS
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) SOLAS II-1/3-9.3 In accordance with 1.1 Means of SOLAS III/20.4 manufacturer’s embarkation 1.1.1 Maintenance and inspection SOLAS III/20.7.2 All Monthly Crew instructions. on and MSC.1/Circ.1331, Maintenance of wires disembarkation Annex, par. 4 acc. to SOLAS III/20.4. from ships (gangways, SOLAS II-1/3-9.3 accommodation Crew + 1.1.2 Examination MSC.1/Circ.1331, All Annually ladders, incl. winch DNV GL Annex, par. 5 and fittings, as well as use for pilot 1.1.3 Examination and operational SOLAS II-1/3-9.3 Crew + transfer) test with specified max. operational MSC.1/Circ.1331, All 5-yearly DNV GL load Annex, par. 5 1.2.1 Examine cylinder gauges MSC.1/Circ.1432, to confirm they are in the correct All Weekly Crew par. 4.5 pressure range. 1.2.2 Check according to maker’s MSC.1/Circ.1432, DNV GL AS All Annually Crew 1.2 Emergency instructions. par. 7.8.3 escape breathing devices (EEBDs) As specified by the Intervals specified in IACS Rec. No.88 1.2.3 Hydrostatic test and internal manufacturer recognized international SI II-2/14.2 item All SER inspection of cylinders (or every 5 standards (e.g. ISO, EN) 3.11.1.1 g5) years if not are to be observed. specified) At each 1.3 Testing of SOLAS III/19.3.3.9 All abandon ship Crew emergency lighting drill Weekly Crew Inspections according to maker’s maintenance SOLAS III/20.4 Monthly Crew guidelines. 1.4.1 Maintenance MSC.1/Circ.1206/ All Special concern for Rev.1 SER or 1.4 Falls used Annually hidden areas and areas Crew in launching of end terminations. appliances After 5 years at the latest, SER or 1.4.2 Renewal SOLAS III/20.4 All or earlier if Crew necessary due Page 8 to deterioration Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 1.5 Replacement of first-aid outfit and LSA Code, par. Maker’s expiry anti-seasickness All Crew 1.2.3 date medicine of lifeboat equipment 1.6 Replacement LSA Code, par. Maker’s expiry of food rations of All Crew 1.2.3 date lifeboat equipment May be extended to 17 1.7 Maintenance months. of hydrostatic Annually (12 Some flag SOLAS III/20.9.1 All SER release units (non- months) administrations require disposable) that they be consulted for acceptance. SOLAS III/20.7.2 1.8.1 Inspection SOLAS III/36.1 All Monthly Crew DNV GL AS 1.8 Immersion MSC/Circ.1047 suits and anti- exposure suits By crew provided 1.8.2 Air pressure test (seams and SER or MSC/Circ.1114 All 3-yearly suitable equipment is closures) Crew available on board. May be extended to 17 months. Some flag administrations require to be consulted for acceptance. 1.9 Maintenance of SOLAS III/20.8.1.1 Annually (12 Inflatable liferafts: inflatable liferafts, RES. A.761(18) All SER months) Administration can lifejackets (inflatable liferafts) accept specific liferafts for extended service intervals acc. to SOLAS III/20.8.3 and MSC.1/Circ.1328. 1.10 Launching 1.10.1 Launching appliance annual SOLAS SER or All Annually appliances thorough examination III/20.11.1.2 Crew Page 9 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) MSC.1/Circ.1206/ Rev.1/ Appendix of Annex 1, par. 2.8 and 2.9 as applicable SOLAS III/20.11.1.3 1.10.2 Dynamic test of the winch MSC.1/Circ.1206/ brake Rev.1/ Appendix of Annex 1, par. 3.1 and 3.3 as applicable SOLAS III/20.11.2.2 + 1.10.3 On-load release gear/ 20.11.3.2 automatic release hooks thorough DNV GL AS examination and operational test MSC.1/Circ.1206/ incl. free-fall lifeboat release Rev.1/ Appendix system of Annex 1, par. 2.4/2.5/2.6 and 2.7 SOLAS III/20.11.1.3 SER + DNV MSC.1/Circ.1206/ 1.10.4 Dynamic test of the winch GL or Rev.1/ Appendix of All 5-yearly brake Crew + Annex 1, par. DNV GL 3.2 and 3.3 as applicable 1.1 × load test no SOLAS longer required for III/20.11.2.3, 1.10.5 On-load release gear/ free-fall lifeboats (ref. 20.11.2.4 + automatic release hooks five yearly SER + DNV III/20.11.2.4); only 20.11.3.3 All 5-yearly overhaul and operational test incl. GL operational test with MSC.1/Circ.1206/ free-fall lifeboat release system. operating crew or Rev.1/ Appendix of simulated launching Annex 1, par. 4 required after overhaul. Page 10 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) Engine, propulsion, 1.11 Examination MSC.1/Circ.1206/ SER or All Annually manoeuvring and power of lifeboats Rev.1 Crew supply system. 1.12.1 Moving from stowed position SOLAS III/20.6.3 All Weekly Crew 1.12 Lifeboats 1.12.2 Turning out from stowed SOLAS III/20.7.1 All Monthly Crew (except free-fall position lifeboats) 1.12.3 Launched and manoeuvred SOLAS III/19.3.3.3 All 3-monthly Crew in the water (abandon ship drill) 1.13 Free-fall lifeboats abandon SOLAS III/19.3.3.4 All 3-monthly Crew ship drill 1.14 Inspection of SOLAS III/20.7.2 All Monthly Crew lifeboat equipment 1.15 Test run of SOLAS III/20.6.2 DNV GL AS lifeboat and rescue MSC.1/Circ.1206/ All Weekly Crew boat engines Rev.1 Tanker 1.16.1 Examination (incl. external MSC.1/Circ.1206/ SER or Incl. external inspection (chem/ Annually 1.16 Lifeboats with inspection of air cylinders) Rev.1 Crew of air cylinders. gas) self-contained air- support system Tanker 1.16.2 Hydrostatic test of air IACS Rec. No.88 (chem/ 5-yearly SER cylinders gas) 1.17 Examination MSC.1/Circ.1206/ Tanker SER or of lifeboats with Annually Rev.1 (oil) Crew sprinkler system 1.18 Rescue boat 3-monthly (as launching and SOLAS III/19.3.3.6 All far as practical Crew manoeuvring in the monthly) water 1.19 Battery LSA Code, par. Maker’s expiry Annually, if not marked replacement of All Crew 1.2.3 date with expiry date. lifebuoy lights 1.20 Marine Administration may Page 11 Passenger Annually (12 evacuation 1.20.1 Service SOLAS III/20.8.1 SER extend this period to 17 ships months) systems (MES) months. Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) Deployment on rotational basis at intervals to be agreed by flag Passenger 1.20.2 Test SOLAS III/20.8.2 6-yearly SER administration, however ships each system to be deployed at least once every six years. 1.21 Testing of public address SOLAS III/20.6.4 systems and MSC.1/Circ.1432, All Weekly Crew general alarm par. 4.4 systems 1.22 Replacement of rocket parachute LSA Code, par. Maker’s expiry flares and rocket All Crew 1.2.3 date line- throwing appliances DNV GL AS 1.23 Replacement LSA Code, par. Maker’s expiry All Crew of smoke signals 1.2.3 date 1.24 Visual inspection of survival craft, SOLAS III/20.6.1 All Weekly Crew rescue boats and launching appliances Page 12 Appendix A
Appendix A 2 Fire protection and fire fighting equipment Class guideline — DNVGL-CG-0058. Edition April 2016 Page 13 Maintenance of safety equipment DNV GL AS
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 2.1.1 The compressed-air BCH Code, par. Tanker Monthly Crew equipment shall be inspected. 3.16.8 (chem/ 2.1.2 The equipment shall be IGC Code, par. gas) SER or Annually inspected and tested. 14.2.6 Maker By crew provided a 2.1 Air-recharging suitable measurement system for SCBAs MSC.1/Circ.1432, device is available on 2.1.3 Check breathing apparatus air SER or par. 7.8.1 board. recharging systems, if fitted, for air All Annually Maker or SI II-2/14.2 item The test device is to be quality. Crew 3.11.1.1 g4) agreed with the maker of the air recharging system. 2.2.1 Examine cylinder gauges MSC.1/Circ.1432, to confirm they are in the correct All Weekly Crew par. 4.5 pressure range. DNV GL AS 2.2.2 The breathing apparatus shall BCH Code, par. Tanker Monthly Crew be inspected. 3.16.8 IBC Code, (chem/ 2.2.3 The equipment shall be par. 14.2.6 IGC SER or gas) Annually 2.2 Self-contained inspected and tested. Code, par. 14.2.6 Maker breathing apparatuses 2.2.4 Check that all breathing (SCBAs) apparatus face masks and air MSC.1/Circ.1432, All Annually Crew demand valves are in serviceable par. 7.8.2 condition. Aluminium and MSC.1/Circ.1432, 2.2.5 Perform hydrostatic testing composite cylinders par. 9.4 of all self-contained breathing All 5-yearly SER shall be tested to the SI II-2/14.2 item apparatus cylinders. satisfaction of the 3.11.1.1 g4) Administration. 2.3.1 Verify that all fire detection 2.3 Fixed fire- and fire alarm control panel MSC.1/Circ.1432, detection and indicators are functional by All Weekly Crew par. 4.1 alarm systems operating the lamp/indicator test switch. Page 14 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 2.3.2 Test a sample of detectors and manual call points so that all MSC.1/Circ.1432, All Monthly Crew devices have been tested within par. 5.10 five years. 2.3.3 Test all fire detection systems and fire detection systems used MSC.1/Circ.1432, to automatically release fire- par. 7.2.1 extinguishing systems for proper operation, as appropriate. 2.3.4 Visually inspect all accessible All Annually Crew detectors for evidence of MSC.1/Circ.1432, tampering, obstruction, etc., so that par. 7.2.2 all detectors are inspected within one year. 2.3.5 Test emergency power supply MSC.1/Circ.1432, switchover. par. 7.2.3 DNV GL AS 2.4.1 Test all fire dampers for local MSC.1/Circ.1432, All Quarterly Crew operation. par. 6.3 2.4 Fire dampers 2.4.2 Test all fire dampers for MSC.1/Circ.1432, All Annually Crew remote operation. par. 7.6 2.5.1 Verify that all fire door control panel indicators, if provided, are MSC.1/Circ.1432, All Weekly Crew functional by operating the lamp/ par. 4.3 indicator switch. 2.5 Fire doors 2.5.2 Test all fire doors located in MSC.1/Circ.1432, Passenger main vertical zone bulkheads for Quarterly Crew par. 6.4 ships local operation. 2.5.3 Test all remotely controlled MSC.1/Circ.1432, All Annually Crew fire doors for proper release. par. 7.7 2.6.1 Inspection in accordance with 2.6 Portable fire the manufacturer’s instructions Res.A.951 (23), All Annually Crew extinguishers and based on inspection guide in par. 9.1 Res.A.951 (23), table 9.1.3. Page 15 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 2.6.2 At least one fire extinguisher of each type manufactured in the Res.A.951 (23), same year and kept on board a ship All 5-yearly Crew par. 9.1.1 shall be test discharged as part of a fire drill. 2.6.3 All fire extinguishers together Res.A.951 (23), with propellant cartridges shall be par. 9.1.2 hydraulically tested in accordance All 10-yearly SER SI II-2/14.2 item with the recognized standard or the 3.11.1.1 a3 manufacturer’s instructions. 2.7.1 Verify that all are in place, MSC.1/Circ.1432, properly arranged, and are in All Monthly Crew par. 5.9 proper condition. 2.7.2 Inspection in accordance with MSC.1/Circ.1432, the manufacturer’s instructions. par. 7.12.1 DNV GL AS 2.7.3 Wheeled (mobile) fire extinguishers shall be visually MSC.1/Circ.1432, inspected to check that all par. 7.12.2 accessible components are in proper condition. All Annually Crew 2.7.4 The hydrostatic test date of MSC.1/Circ.1432, 2.7 Wheeled each cylinder is to be checked. par. 7.12.3 (mobile) fire extinguishers 2.7.5 Dry powder wheeled (mobile) fire extinguishers are to be inverted MSC.1/Circ.1432, to ensure that the powder is par. 7.12.4 agitated. 2.7.6 Visual examination of at least one wheeled (mobile) extinguisher MSC.1/Circ.1432, All 5-yearly Crew of each type manufactured in the par. 9.6 same year and kept on board. 2.7.7 All fire extinguishers together MSC.1/Circ.1432, with propellant cartridges shall be par. 10.5 hydraulically tested in accordance All 10-yearly SER SI II-2/14.2 item with the recognized standard or the 3.11.1.1 a3 manufacturer’s instructions. Page 16 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) Verify that lockers providing storage for fire fighting equipment 2.8 Firefighter’s MSC.1/Circ.1432, contain their full inventory and All Monthly Crew outfits par. 5.5 that equipment is in serviceable condition. 2.9.1 Verify that all fire hydrants, hoses and nozzles are in place, MSC.1/Circ.1432, properly arranged, and are in par. 5.1.1 serviceable condition. 2.9.2 Operate all fire pumps to MSC.1/Circ.1432, confirm that they continue to All Monthly Crew par. 5.1.2 supply adequate pressure. 2.9.3 Verify that emergency fire pump fuel supply is adequate and MSC.1/Circ.1432, heating system is in satisfactory par. 5.1.3 condition, if applicable. DNV GL AS 2.9.4 Verify that international shore MSC.1/Circ.1432, connection(s) is/are in serviceable All Quarterly Crew par. 6.1 2.9 Fire mains, fire condition. pumps, hydrants, 2.9.5 Visually inspect all accessible MSC.1/Circ.1432, hoses and nozzles All Annually Crew components for proper condition. par. 7.1.1 2.9.6 Flow test all fire pumps for proper pressure and capacity. Test MSC.1/Circ.1432, emergency fire pump with isolation par. 7.1.2 valves closed. 2.9.7 Test all hydrant valves for MSC.1/Circ.1432, proper operation. par. 7.1.3 2.9.8 Pressure test a sample of fire All Annually Crew hoses at the maximum fire main MSC.1/Circ.1432, pressure, so that all fire hoses are par. 7.1.4 tested within five years. 2.9.9 Verify that all fire pump relief MSC.1/Circ.1432, valves, if provided, are properly par. 7.1.5 set. Page 17 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 2.9.10 Examine all filters/strainers MSC.1/Circ.1432, to verify that they are free of debris par. 7.1.6 and contamination. 2.9.11 Verify that the nozzle size/ MSC.1/Circ.1432, type is correct, maintained and par. 7.1.7 working. 2.10 Galley Verify that galley exhaust ducts and MSC.1/Circ.1432, All Annually Crew exhaust ducts filters are free of grease build-up. par. 7.6.2 2.11.1 Verify that all portable foam applicators are in place, MSC.1/Circ.1432, All Monthly Crew properly arranged, and are in par. 5.8 proper condition. 2.11.2 Verify that all portable foam applicators are set to the correct MSC.1/Circ.1432, proportioning ratio for the foam par. 7.11.1 DNV GL AS concentrate supplied and that the equipment is in proper order. 2.11.3 Verify that all portable All Annually Crew containers or portable tanks 2.11 Portable foam containing foam concentrate MSC.1/Circ.1432, applicator units remain factory sealed, and that par. 7.11.2 the manufacturer’s recommended service life interval has not been exceeded. 2.11.4 Portable containers or portable tanks containing foam concentrate, excluding protein- based concentrates, less than 10 The foam control tests MSC.1/Circ.1432, years old, that remain factory All Annually Crew are to be conducted by par. 7.11.3 sealed can normally be accepted SER or maker. without the periodical foam control tests required in MSC.1/Circ.1312 being carried out. Page 18 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 2.11.5 Protein-based foam concentrate portable containers and portable tanks shall be thoroughly checked and, if more than five MSC.1/Circ.1432, years old, the foam concentrate par. 7.11.4 shall be subjected to the periodical foam control tests required in MSC.1/Circ.1312, or renewed. All Annually Crew 2.11.6 The foam concentrates of any non-sealed portable containers and portable tanks, and portable containers and portable tanks MSC.1/Circ.1432, for which production data is not par. 7.11.5 documented, shall be subjected to the periodical foam control tests required in MSC.1/Circ.1312. Test all ventilation controls DNV GL AS 2.12 Ventilation MSC.1/Circ.1432, interconnected with fire protection All Annually Crew systems par. 7.6.3 systems for proper operation. Page 19 Appendix A
Appendix A 3 Fixed firefighting systems Class guideline — DNVGL-CG-0058. Edition April 2016 Page 20 Maintenance of safety equipment DNV GL AS
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.1.1 Verify that all electrical connections and/or manual operating stations are properly arranged, and are in proper condition. MSC.1/Circ.1432, All Monthly Crew par. 5.7 3.1.2 Verify that the actuation system/control panel circuits are within manufacturer’s specifications. 3.1.3 Verify that condensed or dispersed aerosol generators have 3.1 Aerosol fire- not exceeded their mandatory MSC.1/Circ.1432, extinguishing replacement date. Pneumatic All Annually Crew par. 7.10 systems or electric actuators shall be demonstrated working, as far as practicable. DNV GL AS Passenger 2-yearly ships 3.1.4 Maintenance by approved SI SER On each intermediate/ service supplier. Cargo 2.5-yearly periodical and renewal ships survey. 3.1.5 Condensed or dispersed aerosol generators are to be MSC.1/Circ.1432, All 10-yearly SER renewed in accordance with par. 10.4 manufacturer’s recommendations. 3.2.1 Verify that all fixed fire- extinguishing system control MSC.1/Circ.1432, panel indicators are functional by par. 4.2.1 operating the lamp/indicator test All Weekly Crew 3.2 Equivalent gas switch. fire-extinguishing 3.2.2 Verify that all control/section MSC.1/Circ.1432, systems (e.g. FM valves are in the correct position. par. 4.2.1 200, NOVEC 1230 or Halon) 3.2.3 Verify that containers/ cylinders fitted with pressure MSC.1/Circ.1432, gauges are in the proper range and All Monthly Crew par. 5.2 that the installation is free from Page 21 leakage. Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.2.4 Visually inspect all accessible components for proper condition. 3.2.5 Externally examine all high pressure cylinders for evidence of damage or corrosion. 3.2.6 Check the hydrostatic test date of all storage containers. 3.2.7 Functionally test all fixed system audible and visual alarms. 3.2.8 Verify that all control/section MSC.1/Circ.1432, All Annually Crew valves are in the correct position. par. 7.3 3.2.9 Check the connections of all pilot release piping and tubing for tightness. DNV GL AS 3.2.10 Examine all flexible hoses in accordance with manufacturer’s recommendations. 3.2.11 Test all fuel shut-off controls connected to fire-protection systems for proper operation. 3.2.12 The boundaries of the protected space shall be visually inspected to confirm that no modifications have been made to the enclosures that have created uncloseable openings that would render the system ineffective. MSC.1/Circ.1432, All Annually Crew 3.2.13 If cylinders are installed par. 7.3 inside the protected space, verify the integrity of the double release lines inside the protected space, and check low pressure or circuit integrity monitors on release cabinet, as applicable. Page 22 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) Passenger 2-yearly SER SI II-2/14.2.2 item ships 3.2.14 Maintenance by approved 3.11.1.1 c3) and On each intermediate/ service supplier. Cargo c4) 2.5-yearly SER periodical and renewal ships survey. 3.2.15 All high pressure extinguishing agent cylinders and pilot cylinders shall be weighed or have their contents verified by other reliable means to confirm MSC.1/Circ.1432, that the available charge in each is par. 8.1.1 above 95% of the nominal charge. Cylinders containing less than 95% of the nominal charge shall be Crew or All 2-yearly refilled. SER 3.2.16 Blow dry compressed air DNV GL AS or nitrogen through the discharge piping or otherwise confirm that MSC.1/Circ.1432, the pipework and nozzles are clear par. 8.1.2 of any obstructions. This may require the removal of nozzles, if applicable. 3.2.17 Perform internal inspection MSC.1/Circ.1432, All 5-yearly SER of all control valves. par. 9.1 If permitted by the flag 3.2.18 Perform a hydrostatic test administration, visual and internal examination of 10% of inspection and non- the system’s extinguishing agent MSC.1/Circ.1432, destructive testing (NDT) and pilot cylinders. If one or more par. 10.1 All 10-yearly SER of halon cylinders may cylinders fail, a total of 50% of the SI II-2/14.2.2 item be performed in lieu of on-board cylinders shall be tested. 3.11.1.1 c3) hydrostatic testing. DNV If further cylinders fail, all cylinders GL is to be contacted shall be tested. prior to the NDT. Page 23 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) To be replaced at the intervals MSC.1/Circ.1318, recommended Hose assemblies are to par. 6.1.2 by the be delivered on board 3.2.19 Flexible hoses (replacement) All Crew SI II-2/14.2.2 item manufacturer with a Recognized 3.11.1.1 b2) and not Organisation certificate. exceeding every 10 years 3.3.1 General visual inspection of MSC.1/Circ.1318, the overall system condition for par. 4.1 obvious signs of damage. 3.3.2 Verify that all stop valves are MSC.1/Circ.1318, in the closed position. par. 4.1.1 3.3.3 Verify that all releasing controls are in the proper MSC.1/Circ.1318, position and readily accessible for par. 4.1.2 DNV GL AS immediate use. All Monthly Crew 3.3.4 Verify that all discharge MSC.1/Circ.1318, piping and pneumatic tubing is par. 4.1.3 intact and has not been damaged. 3.3.5 Verify that all high pressure 3.3 CO2 fire- MSC.1/Circ.1318, cylinders are in place and properly extinguishing par. 4.1.4 secured. systems 3.3.6 Verify that the alarm devices MSC.1/Circ.1318, are in place and do not appear par. 4.1.5 damaged. 3.3.7 Verify that the pressure MSC.1/Circ.1318, gauge is reading in the normal par. 4.2.1 range. 3.3.8 Verify that the liquid level MSC.1/Circ.1318, indicator is reading at the proper For low pressure systems par. 4.2.2 All Monthly Crew level. only. 3.3.9 Verify that the manually operated storage tank main service MSC.1/Circ.1318, valve is secured in the open par. 4.2.3 Page 24 position. Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.3.10 Verify that the vapour MSC.1/Circ.1318, supply line valve is secured in the par. 4.2.4 open position. 3.3.11 The boundaries of the protected space shall be visually inspected to confirm that no MSC.1/Circ.1318, modifications have been made to par. 5.1 the enclosures that have created uncloseable openings that would render the system ineffective. 3.3.12 All storage containers shall be visually inspected for any signs of damage, rust or loose MSC.1/Circ.1318, mounting hardware. Cylinders that par. 5.2 are leaking, corroded, dented or 3.3 CO2 fire- bulging shall be hydrostatically extinguishing retested or replaced. All Annually Crew DNV GL AS systems 3.3.13 System piping shall be visually inspected to check for damage, loose supports and corrosion. Nozzles shall be MSC.1/Circ.1318, inspected to ensure they have not par. 5.3 been obstructed by the storage of spare parts or a new installation of structures or machinery. 3.3.14 The manifold shall be inspected to verify that all flexible MSC.1/Circ.1318, discharge hoses and fittings are par. 5.4 properly tightened. Page 25 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.3.15 All entrance doors to the protected space shall close properly and shall have warning signs, which indicate that the space is protected by a fixed carbon dioxide system MSC.1/Circ.1318, and that personnel shall evacuate par. 5.5 immediately if the alarms sound. All remote releasing controls shall be checked for clear operating instructions and indication as to the space served. Only if requirements MSC.1/Circ.1318 As per 3.3.16 Maintenance by approved SER or from the manufacturer SI II-2/14.2.2 item All manufacturer’s service supplier. Maker are available in addition 3.11.1.1 a3) instructions to those in this table. 3.3.17 All high pressure cylinders MSC.1/Circ.1318, Passenger 2-yearly Crew and pilot cylinders shall be weighed par. 6.1.1 ships DNV GL AS or have their contents verified by other reliable means to confirm that the available charge in each is above 90% of the nominal charge. Cylinders containing less than 90% of the nominal charge On each intermediate/ SI II-2/14.2.2 item Cargo shall be refilled. The liquid level 2.5-yearly Crew periodical and renewal 3.11.1.1 a3) ships of low pressure storage tanks survey. shall be checked to verify that the required amount of carbon dioxide for protection against the largest hazard is available. Passenger 2-yearly Crew 3.3 CO2 fire- 3.3.18 The hydrostatic test date ships MSC.1/Circ.1318, extinguishing of all storage containers shall be On each intermediate/ par. 6.1.2 Cargo systems checked. 2.5-yearly Crew periodical and renewal ships survey. Page 26 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.3.19 The discharge piping and Passenger 2-yearly Crew nozzles shall be tested to verify ships MSC.1/Circ.1318, that they are not blocked. The test par. 6.1.3 shall be performed by isolating the SI II-2/14.2.2 item On each intermediate/ discharge piping from the system Cargo 3.11.1.1 c1) and 2.5-yearly Crew periodical and renewal and blowing dry air or nitrogen ships c2) survey. from test cylinders or suitable means through the piping. 3.3.20 Where possible, all Passenger 2-yearly activating heads shall be removed ships from the cylinder valves and tested for correct functioning by applying full working pressure through the pilot lines. In cases where this is not possible, pilot lines shall be disconnected from the cylinder valves and DNV GL AS blanked off or connected together and tested with full working pressure from the release station MSC.1/Circ.1318, SER and checked for leakage. par. 6.2.1 Cargo 5-yearly In both cases, this shall be carried ships out from one or more release stations when installed. If manual pull cables operate the remote release controls, they shall be checked to verify that the cables and corner pulleys are in good condition and freely move and do not require an excessive amount of travel to activate the system. Page 27 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.3.21 All cable components Passenger 2-yearly should be cleaned and adjusted as ships necessary, and the cable connectors shall be properly tightened. If the remote release controls are operated by pneumatic pressure, the tubing shall be checked for MSC.1/Circ.1318, leakage, and the proper charge of SER par. 6.2.2 Cargo the remote releasing station’s pilot 5-yearly gas cylinders shall be verified. All ships controls and warning devices shall function normally, and the time delay, if fitted, shall prevent the discharge of gas for the required time period. 3.3.22 After completion of the Passenger 2-yearly work, the system shall be returned ships DNV GL AS to service. All releasing controls shall be verified as being in the proper position and connected MSC.1/Circ.1318, SER to the correct control valves. All par. 6.2.3 Cargo pressure switch interlocks shall be 5-yearly ships reset and returned to service. All stop valves shall be in the closed position. 3.3.23 Perform internal inspection SI II-2/14.2.2 item 3.3 CO2 fire- All 5-yearly SER of all control valves. 3.11.11 b2) extinguishing systems 3.3.24 High pressure cylinders shall be subjected to periodical tests at intervals not exceeding 10 years. At the 10-year inspection, at least 10% of the total number provided MSC.1/Circ.1318, shall be subjected to an internal par. 6.1.2 inspection and hydrostatic test. If All 10-yearly SER SI II-2/14.2.2 item one or more cylinders fail, a total of 3.11.1.1 c1) 50% of the on-board cylinders shall be tested. If further cylinders fail, all cylinders shall be tested. Page 28 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) Hose assemblies are to 3.3.25 Flexible hoses shall MSC.1/Circ.1318, be delivered on board be replaced at the intervals par. 6.1.2 At least 10- All Crew with a Recognized recommended by the manufacturer SI II-2/14.2.2 item yearly Organisation test and not exceeding every 10 years. 3.11.1.1 b2) certificate. 3.3.26 Low pressure CO2 bulk If content has storage containers are subject to SI II-2/14.2.2 item been released SER + DNV internal survey if the content has All 3.11.1.1 c2) and is more GL been released and the container is than 5 years old more than 5 years old. MSC.1/Circ.1432, 3.4.1 In accordance with the par. 7.13 All Annually Crew manufacturer’s instructions. SI II-2/14.2.2 item 3.4 Deep fat 3.11.1.1 g6) cooking fire- extinguishing 10-yearly systems (from date of 3.4.2 Overhaul and hydrostatic SI II-2/14.2.2 item SER or DNV GL AS All manufacture testing 3.11.1.1 g6) Maker of pressure vessels) 3.5.1 Verify that all control and section valves are in the proper MSC.1/Circ.1432, open or closed position, and that all All Monthly Crew par. 5.6 pressure gauges are in the proper range. 3.5.2 Visually inspect all accessible MSC.1/Circ.1432, components for proper condition. par. 7.9.1 3.5 Dry chemical powder systems 3.5.3 Verify that the pressure MSC.1/Circ.1432, regulators are in proper order and par. 7.9.2 within calibration. All Annually Crew Due to the powder’s 3.5.4 Agitate the dry chemical affinity for moisture, any powder charge with nitrogen MSC.1/Circ.1432, nitrogen gas introduced in accordance with system par. 7.9.3 for agitation must be manufacturer’s instructions. moisture-free. Page 29 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) Only if requirements As per 3.5.5 Maintenance by approved SI II-2/14.2.2 item SER or from the manufacturer All manufacturer’s service supplier. 3.11.1.1 e4) Maker are available in addition instructions to those in this table. 3.5.6 Blow dry nitrogen through the discharge piping to confirm that the MSC.1/Circ.1432, pipework and nozzles are clear of par. 8.2.1 any obstructions. 3.5.7 Operationally test local and MSC.1/Circ.1432, If permitted by the flag remote controls and section valves. par. 8.2.2 state administration, the interval can be extended 3.5.8 Verify the contents of to/harmonized with MSC.1/Circ.1432, propellant gas cylinders (including All 2-yearly SER every intermediate/ par. 8.2.3 remote operating stations). periodical and renewal survey according to DNV 3.5.9 Test a sample of dry chemical MSC.1/Circ.1432, GL SI II-2/14.2.2 item powder for moisture content. par. 8.2.4 3.11.1.1 e4). DNV GL AS 3.5.10 Subject the powder containment vessel, safety valve MSC.1/Circ.1432, and discharge hoses to a full par. 8.2.5 working pressure test. 3.5.11 Subject all powder containment vessels to hydrostatic In case of NDT, contact MSC.1/Circ.1432, or non-destructive testing (NDT) All 10-yearly SER DNV GL prior to the par. 10.3 carried out by an accredited service testing. agent. 3.6.1 Verify that all control and section valves are in the proper MSC.1/Circ.1432, open or closed position, and that all All Monthly Crew par. 5.3 pressure gauges are in the proper range. 3.6 Foam fire- extinguishing 3.6.2 Verify that the proper systems quantity of foam concentrate MSC.1/Circ.1432, All Quarterly Crew is provided in the foam system par. 6.2 storage tank. 3.6.3 Visually inspect all accessible MSC.1/Circ.1432, All Annually Crew components for proper condition. par. 7.4.1 Page 30 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.6.4 Functionally test all fixed MSC.1/Circ.1432, system audible alarms. par. 7.4.2 3.6.5 Flow test all water supply and foam pumps for proper pressure and capacity, and confirm MSC.1/Circ.1432, flow at the required pressure in par. 7.4.3 each section (ensure all piping is thoroughly flushed with fresh water after service). 3.6.6 Test all system cross MSC.1/Circ.1432, connections to other sources of par. 7.4.4 water supply for proper operation. 3.6.7 Verify that all pump relief MSC.1/Circ.1432, valves, if provided, are properly par. 7.4.5 set. DNV GL AS 3.6.8 Examine all filters/strainers MSC.1/Circ.1432, to verify that they are free of debris par. 7.4.6 and contamination. 3.6.9 Verify that all control/section MSC.1/Circ.1432, valves are in the correct position. par. 7.4.7 All Annually Crew 3.6.10 Blow dry compressed air or nitrogen through the discharge piping or otherwise confirm that This may require the MSC.1/Circ.1432, the pipework and nozzles of high removal of nozzles, if par. 7.4.8 expansion foam systems are clear applicable. of any obstructions, debris and contamination. 3.6.11 Take samples from all foam concentrates carried on board MSC.1/Circ.1432, Except for protein-based (including the foam in sealed par. 7.4.9 alcohol-resistant foam 3.6 Foam fire- transport containers more than 10 concentrates, the first SI II-2/14.2.2 item SER + DNV extinguishing years old) and subject them to the All Annually test should be performed 3.11.1.1 b3) and GL systems periodical control tests in MSC.1/ not more than 3 years e1) Circ.1312, for low expansion foam, after being supplied to or MSC/Circ.670 for high expansion MSC.1/Circ.1312 the ship. foam. Page 31 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.6.12 Alcohol-resistant fluorine- protein-based foam concentrates are subjected to a chemical stability DNV GL rules for test with acetone before being classification RU Tanker poured into foam tank, and a new SHIP Pt.7 Ch.1 (chem) chemical stability test is performed Sec.2 [3.2.1] after installation on board (not less MSC.1/Circ.1312 than 14 days after installation on board). 3.6.13 Test all fuel shut-off controls MSC.1/Circ.1432, connected to fire-protection All Annually Crew par. 7.4.10 systems for proper operation. 3.6.14 Perform internal inspection MSC.1/Circ.1432, of all control valves. par. 9.2.1 MSC.1/Circ.1432, 3.6.15 Flush all high expansion par. 9.2.2 foam system piping with fresh DNV GL AS SI II-2/14.2.2 item water, drain and purge with air. 3.11.1.1 c5) 3.6.16 Check all nozzles to prove MSC.1/Circ.1432, All 5-yearly Crew they are clear of debris. par. 9.2.3 3.6.17 Test all foam proportioners or other foam mixing devices to confirm that the mixing ratio MSC.1/Circ.1432, tolerance is within +30 to -10% of par. 9.2.4 the nominal mixing ratio defined by the system approval. 3.7.1 Verify that all control MSC.1/Circ.1432, panel indicators and alarms are par. 4.7.1 functional. 3.7 Water mist, 3.7.2 Visually inspect pump unit MSC.1/Circ.1432, water spray and All Weekly Crew and its fittings. par. 4.7.2 sprinkler systems 3.7.3 Check the pump unit’s valve MSC.1/Circ.1432, positions if valves are not locked, par. 4.7.3 as applicable. Page 32 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.7.4 Verify that all control, pump MSC.1/Circ.1432, unit and section valves are in the par. 5.4.1 proper open or closed position. 3.7.5 Verify that sprinkler pressure MSC.1/Circ.1432, tanks or other means have correct par. 5.4.2 levels of water. 3.7.6 Test automatic starting All Monthly Crew MSC.1/Circ.1432, arrangements on all system pumps par. 5.4.3 so designed. 3.7.7 Verify that all standby pressure and air/gas pressure MSC.1/Circ.1432, gauges are within the proper par. 5.4.3 pressure ranges. The valves selected for 3.7.8 Test a selected sample of testing shall be chosen to MSC.1/Circ.1432, DNV GL AS system section valves for flow and All Monthly Crew ensure that all valves are par. 5.4.4 proper initiation of alarms. tested within a one-year period. 3.7.9 Assess system water quality MSC.1/Circ.1432, in the header tank and pump unit par. 6.5 (as All Quarterly Crew against the manufacturer’s water amended by quality guidelines. MSC.1/ Circ.1516) 3.7 Water mist, water spray and MSC.1/Circ.1432, sprinkler systems par. 7.5.1 3.7.11 Visually inspect all 3.7 Water mist, MSC.1/Circ.1432, accessible components for proper water spray and par. 7.5.2 condition. sprinkler systems 3.7.12 Externally examine all high MSC.1/Circ.1432, All Annually Crew pressure cylinders for evidence of par. 7.5.3 damage or corrosion. 3.7.13 Check the hydrostatic test MSC.1/Circ.1432, date of all high pressure cylinders. par. 7.5.4 3.7.14 Functionally test all fixed MSC.1/Circ.1432, system audible and visual alarms. par. 7.5.5 Page 33 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.7.15 Flow test all pumps for MSC.1/Circ.1432, proper pressure and capacity. par. 7.5.6 3.7.16 Test all antifreeze systems MSC.1/Circ.1432, for adequate freeze protection. par. 7.5.7 3.7.17 Test all system cross MSC.1/Circ.1432, connections to other sources of par. 7.5.8 water supply for proper operation. 3.7.18 Verify that all pump relief MSC.1/Circ.1432, valves, if provided, are properly par. 7.5.9 set. 3.7.19 Examine all filters/strainers MSC.1/Circ.1432, to verify that they are free of debris par. 7.5.10 and contamination. All Annually Crew 3.7.20 Verify that all control/section MSC.1/Circ.1432, valves are in the correct position. par. 7.5.11 DNV GL AS 3.7.21 Blow dry compressed air or nitrogen through the discharge This may require the piping of dry pipe systems, or MSC.1/Circ.1432, removal of nozzles, if otherwise confirm that the pipework par. 7.5.12 applicable. and nozzles are clear of any obstructions. 3.7.22 Test emergency power MSC.1/Circ.1432, supply switchover, where par. 7.5.13 applicable. MSC.1/Circ.1432, par. 3.7 Water mist, 3.7 Water mist, water spray and 7.5.14 (as water spray and sprinkler systems All Annually Crew amended by sprinkler systems MSC.1/Circ.1516) 3.7.24 Check for any changes that may affect the system, such as MSC.1/Circ.1432, obstructions by ventilation ducts, par. 7.5.15 pipes, etc. Page 34 Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) The sections tested shall be chosen so that all sections are tested within a five-year period. 3.7.25 Test a minimum of one MSC.1/Circ.1432, Other test and section in each open head water par. 7.5.16 SI inspections as All Annually Crew mist system by flowing water II-2/14.2.2 par. per maker’s through the nozzles. 1.3.7 recommendations and type approval certificate. Test or record of the test shall be presented to the attending surveyor 3.7.26 For automatic sprinkler MSC.1/ systems of less than 5 years, test a Circ.1432, .par. Test in accordance with minimum of two randomly selected 7.5.17 (as the basic and extended sprinkler heads/nozzles of each All Annually Crew amended by testing (when applicable) type. If five years or more, test a MSC.1/ Circ.1516) in MSC.1/Circ.1516. DNV GL AS minimum of 20 heads/nozzles (2 × SI Appendix A 10 sections) for each type. 3.7.27 During basic testing, Should a tested and extended testing when sprinkler fail, assessing MSC.1/Circ.1432 applicable, of automatic sprinkler the corresponding par. 7.5.18 heads/nozzles as outlined in All Annually Crew water quality at that (as amended by subparagraph .17, water quality time would assist in MSC.1/ Circ.1516) testing should be conducted in each determining the cause of corresponding piping section. failure. 3.7.28 Test additives in water mist SI II-2/14.2.2 item After 3 years and then All Annually SER system water sample 3.11.1.1 a3) annually. Competent crew member 3.7.29 Fixed local-application fire- (with an advanced extinguishing system for engine As per maker’s firefighting training rooms SI II-2/14.2.2 item instructions and course) or person trained All Crew 3.7 Water mist, Tests and inspections as per 3.11.1.1 d2) type approval in the maintenance of water spray and maker’s recommendation and the certificate such system or as per sprinkler systems Society’s type approval certificate maker’s instructions and type approval certificate. 3.7.30 Flush all ro-ro deck deluge MSC.1/Circ.1432, Crew or Page 35 system piping with water, drain and All 5-yearly par. 9.3.1 SER purge with air. Appendix A
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) 3.7.31 Perform internal inspection of all control/section valves. Water quality testing should be conducted MSC.1/Circ.1432, in all corresponding piping sections, par. 9.3.2 if not previously tested as outlined (as amended by in MSC.1/Circ.1432 par. 7.5.18 MSC.1/ Circ.1516) (as amended by MSC.1/Circ.1516) within the last five years. 3.7.32 Check condition of any batteries, or renew in MSC.1/Circ.1432, accordance with manufacturer’s par. 9.3.3 recommendations. 3.7.33 For each section where the water is refilled after being drained or flushed, water quality should meet manufacturer’s MSC.1/Circ.1432 guidelines. Testing of the renewed par. 9.3.4 DNV GL AS All 5-yearly SER water quality should be conducted (as amended by and recorded as a new baseline MSC.1/ Circ.1516) reference to assist future water quality monitoring for each corresponding section. 3.7.34 Perform internal SI II-2/14.2.2 item Crew + examination of water pressure 3.11.1.1 c7) and All 5-yearly DNV GL cylinders. item 3.11.1.2 a3) 3.7.35 Fixed local-application fire- Passenger Annually extinguishing system for engine ships Automatic release (Crew or rooms full flow test of minimum SI II-2/14.2.2 item is not applicable for SER) + one section and spot check of fire 3.11.1.1 d3) Cargo continuously manned 5-yearly DNV GL detection/automatic release system ships engine rooms. shall be carried out. MSC.1/Circ.1432, 3.7.36 Perform hydrostatic test and par. 10.2 internal examination for gas and SI II-2/14.2.2 item All 10-yearly SER water pressure cylinders. 3.11.1.1c7) and item 3.11.1.2 a3) Page 36 Appendix A
Appendix A 4 Radio and navigational equipment Class guideline — DNVGL-CG-0058. Edition April 2016 Page 37 Maintenance of safety equipment DNV GL AS
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec. 1 [6]) 4.1 Testing of Test report shall be the automatic SOLAS V/18.9 All Annually SER retained on board the identification ship. system (AIS) 4.2 Checking of SOLAS IV/13.6.2 All Annually SER Not by radio surveyor. radio battery 4.3 Satellite Testing according to MSC.1/ SOLAS IV/15.9.1 All Annually SER emergency Circ.1040/Rev.1. position-indicating SER (Shore- Certificate of compliance radio beacons Testing according to MSC/ SOLAS IV/15.9.2 All 5-yearly based or test report shall be (EPIRBs) Circ.1039. maintenance) issued. Determination of magnetic compass STCW Code/Sec. All Once a watch Crew error A-VIII/2.34.2 Table or curve of residual deviation to be available DNV GL AS at all times and compass 4.4 Standard deviation book to be magnetic compass Individual Individual Adjustment, incl. curve of residual Flag state properly maintained, All flag state flag state deviation requirements will be checked annually requirements requirements during safety equipment surveys. Res.A.1053(27), item (EA) 1.2.1.27 12 hours Testing SOLAS V/26.1 All before Crew 4.5 Steering gear departure Emergency steering drill SOLAS V/26.4 All Quarterly Crew Certificate of compliance 4.6 Voyage data and maintenance report SOLAS V/18.8 All Annually SER recorder (VDR) shall be retained on board the ship. Page 38 Appendix A
Appendix A 5 Others Class guideline — DNVGL-CG-0058. Edition April 2016 Page 39 Maintenance of safety equipment DNV GL AS
Maintenance of safety equipment Class guideline — DNVGL-CG-0058. Edition April 2016 By (see Equipment/requirement Regulation Ship type Interval Remark Sec.1 [6]) SER + DNV 5.1 Lightweight SOLAS II-1/5.5 Passenger 5-yearly GL or Crew survey IS Code VIII/8.1.5 ships + DNV GL Verify that the low-location lighting systems are functional by switching MSC.1/Circ.1432, Passenger Weekly Crew off normal lighting in selected par. 4.6 ships 5.2 Low-location locations. lighting systems Test the luminance in accordance MSC.1/Circ.1432, Passenger with the procedures in resolution par. 9.5 5-yearly SER ships A.752(18). Res.A.752(18) According National to national pharmaceutical pharmaceutical DNV GL Replacement of oxygen. All Maker regulations, if regulations or Recommendation applicable maker’s expiry date DNV GL AS 5.3 Medical oxygen As per maker’s instructions Scope of inspection as and/or specified by the flag Hydrostatic test and internal Flag state, if international administration and/or All SER inspection of cylinders. applicable standards recognized international (e.g. ISO, EN) standards (e.g. ISO, EN) and/or flag’s are to be observed. requirements Page 40 Appendix A
HISTORIC CHANGES Historic changes There are currently no historical changes for this document. Class guideline — DNVGL-CG-0058. Edition April 2016 Page 41 Maintenance of safety equipment DNV GL AS
DNV GL Driven by our purpose of safeguarding life, property and the environment, DNV GL enables organizations to advance the safety and sustainability of their business. We provide classification and technical assurance along with software and independent expert advisory services to the maritime, oil and gas, and energy industries. We also provide certification services to customers across a wide range of industries. Operating in more than 100 countries, our 16 000 professionals are dedicated to helping our customers make the world safer, smarter and greener. SAFER, SMARTER, GREENER