African Barrick Gold Bulyanhulu - Site Presentation March 2014
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 1
Biography Peter Burger joined ABG in 2011 and having been General Manager of Tulawaka and Buzwagi ahead of joining Bulyanhulu in October 2013. Prior to ABG, Peter has worked for a number of mining companies such as Anglo American and Acquarius Platinum in numerous managerial roles. Peter has over 20 years of operational experience and has worked at a range of underground operations. Peter is a mining engineer with a degree from the University of Johannesburg. 2
History Asset Overview High Grade, narrow vein, steeply dipping ore body Underground gold mine owned and operated by Bulyanhulu Gold Mine Limited Located in Kahama District, in the Shinyanga Region, North West Tanzania, 55km South of Lake Victoria Access to Bulyanhulu is by road from Mwanza (155km) or Kahama (55km) and by air through own-operated airstrip within the property Well established mine site with administration office, a mill, laboratory, warehouse, clinic, security installations, housing and other support structures Majority of Tanzanian workforce is drawn from surrounding communities Mine History 1983 to 1985: JV with 1976: Gold First 1994: Prospecting Outo Kumpu and Kone 2001: Commencement discovered at License granted to Corp to conduct further of Production Bulyanhulu Sutton Resources drilling 1976 1980 1985 1992 1994 1999 2001 2011 1980 to 1982: First 1989 to 1992: Placer Dome JV 2011: Bulyanhulu celebrates 1999: Acquisition of Sutton Exploration by State to manage the property and 10 years of operations and 3 Resources by Barrick Mining Corporation conduct exploratory work million ounces of production 4
People Who we are BGML draws its human capital from various corners of the world, with the majority sourced locally or within Tanzania Total current Bulyanhulu workforce: − Tanzanians: 2,237 − International Staff: 159 − Contractors: 1,007 Facilities such as the health centre, underground clinic, employee transportation and the Housing Scheme are part of what is intended to make BGML “an Employer of Choice” 5
Safety incident frequency rates 2006 - 2013 TRIFR LTIFR Management Commitment – Visible Felt Leadership Employee Involvement – “Stop and Fix” Personal Accountability – Safety Standards 6
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 7
Reef 1 long section: grade distribution BGMDD0055W1 1.5m @ 2.27/t Au BGMDD0054W1 1.29m @ 11.7g/t Au UX4700-07 1.04m @ 76.7g/t Au BGMDD0054W2 4.5m @ 8.07g/t Au incl. 1.5m @ 16.6g/t Au 10
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 11
Reserves and Resources Mineral Reserve and Resources at 31st December 2013 2012 YE 2012 YE 2013YE 2013 YE contained Mozs Grade contained Mozs Grade Proven 0.266 10.01 0.149 11.40 Probable 10.613 11.38 9.238 9.50 Total Reserve 10.879 11.34 9.387 9.53 Measured - - Indicated 3.320 9.68 3.502 8.44 Inferred 3.252 11.95 2.745 12.88 Total Resource 6.572 10.68 6.274 11.53 Historical Operating Metrics 2010 2011 2012 2013 Production (koz) 260 262 236 198 Cash Cost ($/oz) 539 610 803 875 All in Sustaining Cost ($/oz) n/a n/a 1245 1323 Head Gold Grades (g/t) 9.19 8.47 8.02 7.85 Capacity Ore Production is currently ±3,300 tpd (~1.0 Mtpa) Shaft capacity is ~1.7 Mtpa (waste and ore) Mill capacity is currently ~1.1 Mtpa LOM is currently 34 years 12
Reasons for reserve grade drop 1 Reserve Gold Price: Gold • Reserve 2012: US$ 1,500/Oz Price • Reserve 2013: US$ 1,300/Oz (-13%) 2 Mining Method Changes Increase in Dilution (Internal Dilution + Overbreak) Reserve Dilution Increase (+28%) 3 Cost Changes (Gold Price – Cost) 4 Other contributions: Additional Drilling in 2013 reduced grade in some areas Mine Depletion 13
2012 Reserve ORANGE : REEF 2 CENTRAL PINK: UPPER WEST TONNES: 2,189,037@ 11.36g/t TONNES: 1,639,361@ 10.80g/t Contained Ounces: 799,727 Contained Ounces: 569,380 CCF LIGHT BLUE: UPPER CENTRAL TONNES: 635,127@ 10.20g/t Contained Ounces: 208,222 LH CCF BLUE: DEEP WEST TONNES: 6,834,932@ 14.53g/t Contained Ounces: 3,193,857 RED: DEEP EAST TONNES: 1,171,418@ 13.85g/t Contained Ounces: 521,431 CCF GREEN: DEEP CENTRAL TONNES: 2,632,798@ 11.56g/t Contained Ounces: 978,176 14
2013 Reserve PINK: UPPER WEST 1.41g/t (-13%) ORANGE : REEF 2 CENTRAL TONNES: 2,276,199@ 9.39g/t TONNES: 3,014,406@ 10.12g/t 1.24g/t (-11%) Contained Ounces: 687,633 Contained Ounces: 980,670 CCF LIGHT BLUE: UPPER CENTRAL TONNES: 579,188@ 9.131g/t 1.07g/t (-10%) Contained Ounces: 170,030 DnF BLUE: DEEP WEST TONNES: 9,278,161@ 11.50g/t Contained Ounces: 3,431,269 3.03g/t (-21%) RED: DEEP EAST TONNES: 2,338,100@ 7.76g/t Contained Ounces: 583,708 6.09g/t (-44%) LH GREEN: DEEP CENTRAL TONNES: 5,777,343@ 7.43g/t 4.13g/t (-36%) Contained Ounces: 1,380,004 15
Mining operations Mining Overview Underground mine with shaft and ramp access Life of Mine plan average mining rate of 1 million tonnes of ore mined per annum from two reefs Mobile equipment fleet includes drill jumbos, scoops, dump trucks, utility vehicles and handheld equipment Owner Maintenance Introducing contractors to undertake critical development Split of Mining Methods Kt 2008 2009 2010 2011 2012 2013 100% Ore Hoisted 80% (Kt) 756 967 960 1,048 959 872 Ore Dev't 60% Drift & Fill 40% CCF Waste Hoisted Alimak (Kt) 372 524 559 556 507 475 20% Long hole 0% 2013 2014 LOM (Actual for 2013) 16
LOM changes to achieve reserve grade 2013 LOM Plan 2013 LOM Plan had CCF Mining in Deep West, Deep Central and Deep East per previous LOM Plans CCF targeted the Footwall and Hangingwall Veins with inefficient, labour intensive handheld, stoping with minimal dilution CCF = Higher Mined Grade but, higher labour requirements, low daily tonnage, requiring +/- 200 stopes monthly to sustain LOM production in later years 2014 LOM Plan 2014 LOM Plan – No CCF Mining in the Deep areas CCF converted to either Underhand Longhole Stoping in the Deep West or Mechanised Drift & Fill in the Deep Central and Deep East Zones Accelerated Development focused on the Deep West to open up more productive mechanised stopes Mechanised Underhand Longhole Stoping employed in Deep West to bring in stopes earlier, and bring ounces forward Monthly stoping: Alimak – 4, Long Hole – 10, CCF - 12 17
2015 LOM – in progress 2014 - 2030 2030 - 2046 Contract miners engaged to accelerate waste development specifically on the main decline and ore drives Underhand long hole mining will be used to ensure earlier production from stoping areas Areas non-economical for long hole is being reviewed for drift and fill Trial mine will be done in Upper East in 2014 for 1.5m wide long hole stopes Re-focusing next 5 years to areas with high grade (West Deeps) Grade control in place to reduce overbreak Exploration plan to add ounces in Reef 1 and 2 (starting in 2014 in both reefs) 18
Underhand Long Hole 19
KPI review – reducing long hole overbreak Improving trend in reducing overbreak What is being done? 45% OVERBREAK TARGET Geology and Survey assessment every 2 40% weeks 35% Weekly discussion between BI, TS and Ops 30% Drill hole surveys to improve drilling accuracy 25% Long hole machines were brought back to 20% standard 15% Use right explosives – emulsion vs ANFO 10% Training of Long hole drillers 5% Reducing Alimak tonnes in the LOM 0% Sep-12 Sep-13 Jan-12 Jan-13 Jan-14 Jul-12 Nov-12 Jul-13 Nov-13 Mar-12 Mar-13 May-12 May-13 20
Upper East Zone The Bulyanhulu Upper East Zone is approximately 2.5 km east of the main Bulyanhulu shaft The Zone contains approximately 6.5 million ore tonnes at an average 9.05g/t containing approximately 1.8 million gold ounces within Reef 1 and Reef 2 from surface to 1km depth The mineralisation in the “Zone” is included in current reserves, but it was not scheduled for mining until later in the mine life However, following model and study reviews we may accelerate mining within the overall life of mine This would make use of an existing 1.8 km decline to this zone, which has been dewatered and rehabilitated, and would look at developing a second access decline from a box-cut at surface between Reefs 1 & 2 to allow flexibility in mining The material mined from the Upper East Zone would initially use excess milling capacity in the process plant, followed by debottlenecking of plant to increase capacity We are conducting an updated feasibility study on this area to incorporate both Reef 1 and Reef 2 and are planning “early works” development of test stopes on Reef 1 Mining Methods proposed are: − Reef 1 - Mechanised Drift & Fill − Reef 2 - Underhand Longhole Stoping 21
Upper East Zone Reefs 1 and 2 Existing Box Cut Shaft Paste Fill Hole Potential Box Cut Upper East Reef 1&2 22
Upper East Next Steps Feasibility and Board approval expected in Q2 2014 Development expected to commence in H2 2014 First gold in early 2015 2-3 year ramp up to full production 23
Route to 350koz Sources of Production Growth 400 350 350 60 300 40 Koz 250 52 250 200 290 198 250 150 198 100 2013A Grade & Existing U/G CIL Expansion Upper East 2015E exit Productivity Mine (2015 rate Improvements exit rate) 24
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 25
Processing Operations Processing Key Points The following processes are utilised; Crushing, Grinding, Gravity, Flotation, Carbon-In-Leach, Thickening, Cyanide destruction, Filtration and Paste Backfill ICMI Cyanide code compliant Bulyanhulu produces two saleable products: dore and copper concentrate Dore bars are produced from Gravity and CIL plants Copper Concentrate is produced from the flotation plant and sold to copper smelters mainly in China and Japan The concentrate requires processing in a copper smelter with a gold refinery 26
CIL Expansion Project New Carbon In Leach (CIL) Plant 2.4 Mtpa ‒ 1.0 Mtpa ROM + 1.4 Mtpa Hydraulic Reclamation ‒ Including SMBS Detoxification ‒ New Tailings Storage Facility (TSF 4) and Return Water Dam (RWD) Total cost of the project of $167 million (majority funded by debt facility) Will add over 40koz per annum over the next 6 years and 10Koz per annum from rougher tailings for the remaining LOM ‒ AISC for reclaimed tailings will be below $800 per ounce ‒ Will increase overall recoveries from 91% to 94% 27
Site activity progress Description Actual Overall Completion 96.6% Construction Progress 92.9% Commissioning Progress 12% Completion of Commissioning Q2 2014 28
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 29
Cost Savings Progression of Total Site Costs Key 2014 cost savings initiatives: 350,000 Labour cost reduction – expat reduction focus & improvement of controls regarding T&A 300,000 Maintenance – improved condition based monitoring & root cause analysis processes 250,000 Mining Consumables – focused on tyre life management program and underground support 200,000 supplier management 150,000 Processing Consumables – trialing of more cost efficient grinding media in progress and optimisation of gravity control processing 100,000 External services – focus has been centered around contract management (rates and fixed cost reduction) 50,000 G&A – reduced travel and accommodation costs together with improved camp service contact - 2012A 2013A 2014E management -50,000 Grade control – focused on Alimak and Long Hole grade control improvement programs Labour Energy/Diesel Consumables Maintenance Contracted services G&A costs Sales related costs Sustaining Capital Activity/One-off cost adjustment Total Direct Costs - Absolute Total Direct Costs - Activity adj 30
Cost Savings: Workforce requirements Split between Overall Workforce Plan* Underground vs Support Staff * Excluding Upper East 31
Business Improvement projects planned for 2014 and 2015 Integrated planning – improve co-ordination of planning between departments Overall equipment effectiveness Maintenance management system Improved “live” dispatch system Cultural and behavioural intervention People / Organisation – installation of an Accountable Management System (AMS) Safety culture – revamp of the mine safety culture “We care programme” in Q2 14 32
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 33
Community Relations CSR Highlights Involvement of communities in project appraisals Health: Investment in a clinic in Bugarama, Kakola VCT and support health programs at district level Education: Schools and supporting facilities, support of IMTT Utilities: Support road maintenance, electrification and provision of water at various points Pipeline to supply sufficient water to the community from Lake Victoria Employee Assistance: Support of the employees living in the community through the housing scheme, the counseling services and loans through BUIKA SACCOS Enterprise development: Supporting commercialisation of small ventures to supply Bulyanhulu Sports and Culture: Support community in sports events 34
Government Relations and Stakeholder Engagement Conducted at Regional (Shinyanga), District (Msalala) and at Village (14 villages of immediate impact) levels Conducted with government, political, commercial, civil society and community sectors , amongst others Offers mine site’s social license to operate while addressing top priority risks Addresses key CR and BGML areas of interest - fulfillment of Social Obligations, Grievance Management, Influx Management, Trespassing and Illegal Mining Management, Community Safety, Local Procurement (Alternative Livelihood programs) and Local Employment Work with various departments to attain goals – Security, HR, Supply Chain, OH, Safety, Environment , among others Informed by Stakeholder Perception Monitoring (last major one undertaken in 2012, however, perception is gathered periodically through various engagements) 35
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 36
Cultural Transformation Program The Revolution Model, getting it right Liberating the capability of our people Increasing leadership and membership skills Driving key behaviours throughout the business to deliver our strategy Our key people including all our leaders, Managing Culture: Cultural Change Curve influencers, and key operational personal both from ABG and our major contractors Social process literacy and role clarity 37
Contents 1. Introduction 1 2. Asset Overview 7 3. Mining Overview 11 4. Processing Overview 25 5. Business Improvement 29 6. Social Licence to Operate 33 7. Cultural Transformation 36 8. Summary 38 38
Key priorities going forward Improve on our excellent safety record Re-engineer and right size the mine to deliver potential Drive leadership transformation and accountability Which will drive production of 350Koz at AISC of around $900 per ounce by the end of 2015 39
Disclaimer Important Notice This presentation has been provided to you for information purposes only. It does not constitute an offer, solicitation, invitation or inducement to purchase, subscribe or otherwise acquire or to sell or otherwise dispose of any securities of African Barrick Gold plc ("ABG") or engage in any investment activity in connection with the capital of ABG in any jurisdiction. The information or opinions contained in this presentation shall not form the basis of, or be relied on in connection with, or act as any inducement to enter into, any contract or commitment or investment decision whatsoever in connection with ABG. The information and opinions contained in this presentation are provided as of the date of this presentation and are subject to change without notice. ABG explicitly disclaims any responsibility, obligation or undertaking to update or revise any information contained in this presentation after its date, whether as a result of new information, future events or otherwise. No reliance may be placed for any purpose whatsoever on the information or opinions contained in this presentation or on its completeness and no liability whatsoever is accepted for any loss howsoever arising from any use of this presentation or its contents. Certain information, statements, beliefs and opinions in this presentation are forward looking. Forward-looking statements are statements that are not historical facts. These statements include, without limitation, financial projections and estimates and their underlying assumptions, statements regarding plans, objectives and expectations with respect to future production, operations, costs, products and services, and statements regarding future performance. Forward-looking statements are generally identified by the words "plans," "expect," "anticipates," "believes," "intends," "estimates" and other similar expressions. All forward-looking statements involve a number of risks, uncertainties and other factors. Although ABG’s management believes that the expectations reflected in such forward-looking statements are reasonable, investors are cautioned that forward-looking information and statements are subject to various risks and uncertainties, many of which are difficult to predict and generally beyond the control of ABG, that could cause actual results and developments to differ materially from those expressed in, or implied or projected by, forward-looking information and statements contained in this presentation. Factors that could cause or contribute to differences between the actual results, performance and achievements of ABG include, but are not limited to, political, economic and business conditions, industry trends, competition, fluctuations in the spot and forward price of gold or certain other commodity prices, changes in regulation, currency fluctuations (including the US dollar, South African rand and Tanzanian shilling exchange rates), ABG’s ability to successfully integrate future acquisitions, to recover its reserves or develop new reserves, including its ability to convert its resources into reserves and its mineral potential into resources or reserves and to timely and successfully process its mineral reserves, trespass, theft and vandalism, changes in its business strategy, as well as risks and hazards associated with the business of mineral exploration, development, mining and production. Accordingly, investors should not place reliance on forward-looking statements contained in this presentation. Any forward-looking statements in this presentation speak only as of the date of this presentation and only reflect information available at the time of preparation. Subject to the requirements of the Disclosure and Transparency Rules and the Listing Rules or applicable law, ABG explicitly disclaims any obligation or undertaking publicly to update or revise any forward-looking statements contained in this presentation, whether as a result of new information, future events or otherwise. No statements made in this presentation regarding expectations of future profits are profit forecasts or estimates, and no statements made in this presentation should be interpreted to mean that ABG’s profits or earnings per share for any future period will necessarily match or exceed the historical published profits or earnings per share of ABG or any other level. You are reminded that you have received this presentation subject to the disclaimer and important notices contained herein and on the basis that you are a person to whom this presentation may be lawfully made and delivered in accordance with the laws of the jurisdiction in which you are located. You may not and are not authorised to: (i) reproduce or publish this presentation; or (ii) distribute, disclose or pass on this presentation to any other person, in whole or in part, by any medium or in any form, whether electronically or otherwise. ANY FORWARDING, DISTRIBUTION OR REPRODUCTION OF THIS PRESENTATION IN WHOLE OR IN PART IS UNAUTHORISED. FAILURE TO COMPLY WITH THIS NOTICE MAY RESULT IN A VIOLATION OF APPLICABLE SECURITIES LAWS. 40