African Barrick Gold Bulyanhulu - Site Presentation March 2014

Page created by Jimmie Shelton
 
CONTINUE READING
African Barrick Gold Bulyanhulu - Site Presentation March 2014
African Barrick Gold
 Bulyanhulu – Site Presentation
                       March 2014
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     1
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Biography

            Peter Burger joined ABG in 2011 and having been General
            Manager of Tulawaka and Buzwagi ahead of joining
            Bulyanhulu in October 2013.

            Prior to ABG, Peter has worked for a number of mining
            companies such as Anglo American and Acquarius Platinum
            in numerous managerial roles.

            Peter has over 20 years of operational experience and has
            worked at a range of underground operations. Peter is a
            mining engineer with a degree from the University of
            Johannesburg.

                                                                        2
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Location

           3
African Barrick Gold Bulyanhulu - Site Presentation March 2014
History

                                                               Asset Overview

 High Grade, narrow vein, steeply dipping ore body
 Underground gold mine owned and operated by Bulyanhulu Gold Mine Limited
 Located in Kahama District, in the Shinyanga Region, North West Tanzania, 55km South of Lake Victoria
 Access to Bulyanhulu is by road from Mwanza (155km) or Kahama (55km) and by air through own-operated
  airstrip within the property
 Well established mine site with administration office, a mill, laboratory, warehouse, clinic, security
  installations, housing and other support structures
 Majority of Tanzanian workforce is drawn from surrounding communities

                                                                   Mine History
                                  1983 to 1985: JV with
 1976: Gold First                                                       1994: Prospecting
                                  Outo Kumpu and Kone                                                    2001: Commencement
 discovered at                                                          License granted to
                                  Corp to conduct further                                                of Production
 Bulyanhulu                                                             Sutton Resources
                                  drilling

              1976                1980             1985            1992             1994              1999           2001             2011

                    1980 to 1982: First          1989 to 1992: Placer Dome JV                                       2011: Bulyanhulu celebrates
                                                                                      1999: Acquisition of Sutton
                    Exploration by State         to manage the property and                                         10 years of operations and 3
                                                                                      Resources by Barrick
                    Mining Corporation           conduct exploratory work                                           million ounces of production

                                                                                                                                                   4
African Barrick Gold Bulyanhulu - Site Presentation March 2014
People

                        Who we are

   BGML draws its human capital from various corners of
    the world, with the majority sourced locally or within
    Tanzania

   Total current Bulyanhulu workforce:

       − Tanzanians:          2,237

       − International Staff: 159

       − Contractors:         1,007

   Facilities such as the health centre, underground
    clinic, employee transportation and the Housing
    Scheme are part of what is intended to make BGML
    “an Employer of Choice”

                                                             5
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Safety incident frequency rates 2006 - 2013

                                                                         TRIFR
                                                                         LTIFR

                      Management Commitment – Visible Felt Leadership

                      Employee Involvement – “Stop and Fix”

                      Personal Accountability – Safety Standards
                                                                                 6
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     7
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Geology

          8
African Barrick Gold Bulyanhulu - Site Presentation March 2014
Geological cross-section

                Facing

    Pillow Basalts
                                         Gabbro

                         X                        Y

Mineralized Qtz vn

                             Argillite

                                                      9
Reef 1 long section: grade distribution

 BGMDD0055W1
 1.5m @ 2.27/t Au

BGMDD0054W1
1.29m @ 11.7g/t Au                           UX4700-07
                                             1.04m @ 76.7g/t Au

  BGMDD0054W2
  4.5m @ 8.07g/t Au
  incl. 1.5m @ 16.6g/t Au

                                                                  10
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     11
Reserves and Resources

                                    Mineral Reserve and Resources at 31st December 2013

                                                       2012 YE          2012 YE          2013YE       2013 YE
                                                    contained Mozs       Grade       contained Mozs    Grade
Proven                                                   0.266           10.01            0.149        11.40
Probable                                                10.613           11.38            9.238         9.50
Total Reserve                                           10.879           11.34            9.387         9.53
Measured                                                   -                                -
Indicated                                                3.320           9.68             3.502        8.44
Inferred                                                 3.252           11.95            2.745        12.88
Total Resource                                           6.572           10.68            6.274        11.53

                                                Historical Operating Metrics
                                                       2010                2011             2012        2013
Production (koz)                                        260                262              236         198
Cash Cost ($/oz)                                        539                610              803         875
All in Sustaining Cost ($/oz)                           n/a                 n/a             1245        1323
Head Gold Grades (g/t)                                 9.19                8.47             8.02        7.85

                                                            Capacity

     Ore Production is currently ±3,300 tpd (~1.0 Mtpa)
     Shaft capacity is ~1.7 Mtpa (waste and ore)
     Mill capacity is currently ~1.1 Mtpa
     LOM is currently 34 years

                                                                                                                12
Reasons for reserve grade drop

                                 1   Reserve Gold Price:                                             Gold
                                          • Reserve 2012: US$ 1,500/Oz                              Price
                                          • Reserve 2013: US$ 1,300/Oz                             (-13%)

                                 2   Mining Method Changes

                                  Increase in Dilution          (Internal Dilution + Overbreak)

                                                                             Reserve Dilution
                                                                                Increase
                                                                                (+28%)

                                 3   Cost Changes                        (Gold Price – Cost)

                                 4   Other contributions:
                                           Additional Drilling in 2013 reduced grade in some areas
                                           Mine Depletion
                                                                                                            13
2012 Reserve
                                                   ORANGE : REEF 2 CENTRAL
PINK: UPPER WEST                                   TONNES: 2,189,037@ 11.36g/t
TONNES: 1,639,361@ 10.80g/t                        Contained Ounces: 799,727
Contained Ounces: 569,380
                                                                                         CCF

                                                                        LIGHT BLUE: UPPER CENTRAL
                                                                        TONNES: 635,127@ 10.20g/t
                                                                        Contained Ounces: 208,222

         LH                                                                                         CCF

 BLUE: DEEP WEST
 TONNES: 6,834,932@ 14.53g/t
 Contained Ounces: 3,193,857                                                           RED: DEEP EAST
                                                                                       TONNES: 1,171,418@ 13.85g/t
                                                                                       Contained Ounces: 521,431

          CCF
                               GREEN: DEEP CENTRAL
                               TONNES: 2,632,798@ 11.56g/t
                               Contained Ounces: 978,176
                                                                                                                     14
2013 Reserve
PINK: UPPER WEST               1.41g/t (-13%)                       ORANGE : REEF 2 CENTRAL
TONNES: 2,276,199@ 9.39g/t                                          TONNES: 3,014,406@ 10.12g/t
                                                                                                     1.24g/t (-11%)
Contained Ounces: 687,633                                           Contained Ounces: 980,670

                                                                                                         CCF

                                                                                         LIGHT BLUE: UPPER CENTRAL
                                                                                         TONNES: 579,188@ 9.131g/t      1.07g/t (-10%)
                                                                                         Contained Ounces: 170,030

                                                                                                                             DnF

 BLUE: DEEP WEST
 TONNES: 9,278,161@ 11.50g/t
 Contained Ounces: 3,431,269

  3.03g/t (-21%)                                                                                        RED: DEEP EAST
                                                                                                        TONNES: 2,338,100@ 7.76g/t
                                                                                                        Contained Ounces: 583,708

                                                                                                                        6.09g/t (-44%)
        LH
                                                GREEN: DEEP CENTRAL
                                                TONNES: 5,777,343@ 7.43g/t         4.13g/t (-36%)
                                                Contained Ounces: 1,380,004
                                                                                                                                         15
Mining operations

                               Mining Overview

           Underground mine with shaft and ramp access

           Life of Mine plan average mining rate of 1 million tonnes
            of ore mined per annum from two reefs

           Mobile equipment fleet includes drill jumbos, scoops,
            dump trucks, utility vehicles and handheld equipment

           Owner Maintenance

           Introducing contractors to undertake critical development

                            Split of Mining Methods                        Kt              2008   2009 2010 2011 2012 2013

          100%
                                                                           Ore Hoisted
           80%                                                             (Kt)             756    967   960 1,048   959   872
                                                            Ore Dev't
           60%                                              Drift & Fill

           40%                                              CCF            Waste Hoisted
                                                            Alimak         (Kt)             372    524   559   556   507   475
           20%
                                                            Long hole
             0%
                     2013         2014           LOM

(Actual for 2013)                                                                                                                16
LOM changes to achieve reserve grade

 2013 LOM Plan

   2013 LOM Plan had CCF Mining in Deep West, Deep Central and Deep East per previous LOM Plans
   CCF targeted the Footwall and Hangingwall Veins with inefficient, labour intensive handheld, stoping with
     minimal dilution

   CCF = Higher Mined Grade but, higher labour requirements, low daily tonnage, requiring +/- 200 stopes
     monthly to sustain LOM production in later years

 2014 LOM Plan

   2014 LOM Plan – No CCF Mining in the Deep areas
   CCF converted to either Underhand Longhole Stoping in the Deep West or Mechanised Drift & Fill in the
     Deep Central and Deep East Zones

   Accelerated Development focused on the Deep West to open up more productive mechanised stopes
   Mechanised Underhand Longhole Stoping employed in Deep West to bring in stopes earlier, and bring
     ounces forward

   Monthly stoping: Alimak – 4, Long Hole – 10, CCF - 12

                                                                                                                17
2015 LOM – in progress

      2014 - 2030
                                             2030 - 2046

      Contract miners engaged to accelerate waste development specifically on the main decline and ore drives

      Underhand long hole mining will be used to ensure earlier production from stoping areas

      Areas non-economical for long hole is being reviewed for drift and fill

      Trial mine will be done in Upper East in 2014 for 1.5m wide long hole stopes

      Re-focusing next 5 years to areas with high grade (West Deeps)

      Grade control in place to reduce overbreak

      Exploration plan to add ounces in Reef 1 and 2 (starting in 2014 in both reefs)
                                                                                                                 18
Underhand Long Hole

                      19
KPI review – reducing long hole overbreak

                        Improving trend in reducing overbreak                                                                             What is being done?

45%
                                                   OVERBREAK                                    TARGET                         Geology and Survey assessment every 2
40%
                                                                                                                                weeks
35%
                                                                                                                               Weekly discussion between BI, TS and Ops
30%                                                                                                                            Drill hole surveys to improve drilling
                                                                                                                                accuracy
25%
                                                                                                                               Long hole machines were brought back to
20%                                                                                                                             standard
15%                                                                                                                            Use right explosives – emulsion vs ANFO

10%                                                                                                                            Training of Long hole drillers

5%                                                                                                                             Reducing Alimak tonnes in the LOM

0%
                                          Sep-12

                                                                                                 Sep-13
      Jan-12

                                                            Jan-13

                                                                                                                   Jan-14
                                 Jul-12

                                                   Nov-12

                                                                                       Jul-13

                                                                                                          Nov-13
               Mar-12

                                                                     Mar-13
                        May-12

                                                                              May-13

                                                                                                                                                                           20
Upper East Zone

    The Bulyanhulu Upper East Zone is approximately 2.5 km east of the main Bulyanhulu shaft

    The Zone contains approximately 6.5 million ore tonnes at an average 9.05g/t containing
      approximately 1.8 million gold ounces within Reef 1 and Reef 2 from surface to 1km depth

    The mineralisation in the “Zone” is included in current reserves, but it was not scheduled for
      mining until later in the mine life

    However, following model and study reviews we may accelerate mining within the overall life of
      mine

    This would make use of an existing 1.8 km decline to this zone, which has been dewatered and
      rehabilitated, and would look at developing a second access decline from a box-cut at surface
      between Reefs 1 & 2 to allow flexibility in mining

    The material mined from the Upper East Zone would initially use excess milling capacity in the
      process plant, followed by debottlenecking of plant to increase capacity

    We are conducting an updated feasibility study on this area to incorporate both Reef 1 and Reef
      2 and are planning “early works” development of test stopes on Reef 1

    Mining Methods proposed are:
           − Reef 1 - Mechanised Drift & Fill
           − Reef 2 - Underhand Longhole Stoping
                                                                                                       21
Upper East Zone Reefs 1 and 2

 Existing Box Cut   Shaft   Paste Fill Hole   Potential Box Cut

                                                    Upper East Reef 1&2

                                                                          22
Upper East

                               Next Steps

              Feasibility and Board approval expected
                in Q2 2014

              Development expected to commence in
                H2 2014

              First gold in early 2015

              2-3 year ramp up to full production

                                                         23
Route to 350koz

                               Sources of Production Growth
       400

       350
                                                                              350
                                                                  60
       300

                                                    40
 Koz

       250
                          52          250
       200                                                       290
              198                                   250
       150               198

       100
             2013A      Grade &    Existing U/G CIL Expansion Upper East   2015E exit
                      Productivity Mine (2015                                 rate
                     Improvements exit rate)
                                                                                        24
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     25
Processing Operations

                  Processing Key Points

   The following processes are utilised; Crushing,
    Grinding, Gravity, Flotation, Carbon-In-Leach,
    Thickening, Cyanide destruction, Filtration and Paste
    Backfill

   ICMI Cyanide code compliant

   Bulyanhulu produces two saleable products: dore
    and copper concentrate

   Dore bars are produced from Gravity and CIL plants

   Copper Concentrate is produced from the flotation
    plant and sold to copper smelters mainly in China
    and Japan

   The concentrate requires processing in a copper
    smelter with a gold refinery

                                                            26
CIL Expansion Project

      New Carbon In Leach (CIL) Plant 2.4 Mtpa

         ‒ 1.0 Mtpa ROM + 1.4 Mtpa Hydraulic Reclamation

         ‒ Including SMBS Detoxification

         ‒ New Tailings Storage Facility (TSF 4) and Return Water Dam (RWD)

      Total cost of the project of $167 million (majority funded by debt facility)

      Will add over 40koz per annum over the next 6 years and 10Koz per annum from rougher tailings for
       the remaining LOM

         ‒ AISC for reclaimed tailings will be below $800 per ounce

         ‒ Will increase overall recoveries from 91% to 94%

                                                                                                           27
Site activity progress

  Description                   Actual

  Overall Completion            96.6%

  Construction Progress         92.9%

  Commissioning Progress         12%

  Completion of Commissioning   Q2 2014

                                          28
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     29
Cost Savings

                    Progression of Total Site Costs                                   Key 2014 cost savings initiatives:
350,000
                                                                                           Labour cost reduction – expat reduction focus &
                                                                                            improvement of controls regarding T&A
300,000
                                                                                           Maintenance – improved condition based monitoring
                                                                                            & root cause analysis processes
250,000

                                                                                           Mining Consumables – focused on tyre life
                                                                                            management program and underground support
200,000
                                                                                            supplier management

150,000
                                                                                           Processing Consumables – trialing of more cost
                                                                                            efficient grinding media in progress and optimisation
                                                                                            of gravity control processing
100,000
                                                                                           External services – focus has been centered around
                                                                                            contract management (rates and fixed cost reduction)
 50,000
                                                                                           G&A – reduced travel and accommodation costs
                                                                                            together with improved camp service contact
    -
              2012A                           2013A                   2014E
                                                                                            management

-50,000
                                                                                           Grade control – focused on Alimak and Long Hole
                                                                                            grade control improvement programs
          Labour                                      Energy/Diesel
          Consumables                                 Maintenance
          Contracted services                         G&A costs
          Sales related costs                         Sustaining Capital
          Activity/One-off cost adjustment            Total Direct Costs - Absolute
          Total Direct Costs - Activity adj
                                                                                                                                                    30
Cost Savings: Workforce requirements

                                               Split between
            Overall Workforce
                                Plan*   Underground vs Support Staff

* Excluding Upper East

                                                                       31
Business Improvement projects planned for 2014 and 2015

 Integrated planning – improve co-ordination of planning between departments

 Overall equipment effectiveness

 Maintenance management system

 Improved “live” dispatch system

 Cultural and behavioural intervention

 People / Organisation – installation of an Accountable Management System (AMS)

 Safety culture – revamp of the mine safety culture “We care programme” in Q2 14

                                                                                    32
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     33
Community Relations

                          CSR Highlights

   Involvement of communities in project appraisals

   Health: Investment in a clinic in Bugarama, Kakola VCT and
    support health programs at district level

   Education: Schools and supporting facilities, support of IMTT

   Utilities: Support road maintenance, electrification and
    provision of water at various points

   Pipeline to supply sufficient water to the community from
    Lake Victoria

   Employee Assistance: Support of the employees living in the
    community through the housing scheme, the counseling
    services and loans through BUIKA SACCOS

   Enterprise development: Supporting commercialisation of
    small ventures to supply Bulyanhulu

   Sports and Culture: Support community in sports events

                                                                    34
Government Relations and Stakeholder Engagement

 Conducted at Regional (Shinyanga), District (Msalala) and at
  Village (14 villages of immediate impact) levels

 Conducted with government, political, commercial, civil society
  and community sectors , amongst others

 Offers mine site’s social license to operate while addressing
  top priority risks

 Addresses key CR and BGML areas of interest - fulfillment of
  Social Obligations, Grievance Management, Influx
  Management, Trespassing and Illegal Mining Management,
  Community Safety, Local Procurement (Alternative Livelihood
  programs) and Local Employment

 Work with various departments to attain goals – Security, HR,
  Supply Chain, OH, Safety, Environment , among others

 Informed by Stakeholder Perception Monitoring (last major
  one undertaken in 2012, however, perception is gathered
  periodically through various engagements)

                                                                    35
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     36
Cultural Transformation Program
                                                The Revolution Model, getting it right

 Liberating the capability of our people

 Increasing leadership and membership skills

 Driving key behaviours throughout the
  business to deliver our strategy

 Our key people including all our leaders,     Managing Culture: Cultural Change Curve
  influencers, and key operational personal
  both from ABG and our major contractors

 Social process literacy and role clarity

                                                                                          37
Contents

 1. Introduction                1

 2. Asset Overview              7

 3. Mining Overview             11

 4. Processing Overview         25

 5. Business Improvement        29

 6. Social Licence to Operate   33

 7. Cultural Transformation     36

 8. Summary                     38

                                     38
Key priorities going forward

        Improve on our excellent safety record

        Re-engineer and right size the mine to deliver potential

        Drive leadership transformation and accountability

                               Which will drive production of 350Koz at AISC of around $900 per ounce

                               by the end of 2015

                                                                                                        39
Disclaimer

 Important Notice

 This presentation has been provided to you for information purposes only. It does not constitute an offer, solicitation, invitation or inducement to purchase, subscribe or otherwise acquire or
 to sell or otherwise dispose of any securities of African Barrick Gold plc ("ABG") or engage in any investment activity in connection with the capital of ABG in any jurisdiction. The information
 or opinions contained in this presentation shall not form the basis of, or be relied on in connection with, or act as any inducement to enter into, any contract or commitment or investment
 decision whatsoever in connection with ABG.

 The information and opinions contained in this presentation are provided as of the date of this presentation and are subject to change without notice. ABG explicitly disclaims any
 responsibility, obligation or undertaking to update or revise any information contained in this presentation after its date, whether as a result of new information, future events or otherwise.
 No reliance may be placed for any purpose whatsoever on the information or opinions contained in this presentation or on its completeness and no liability whatsoever is accepted for any
 loss howsoever arising from any use of this presentation or its contents.

 Certain information, statements, beliefs and opinions in this presentation are forward looking. Forward-looking statements are statements that are not historical facts. These statements
 include, without limitation, financial projections and estimates and their underlying assumptions, statements regarding plans, objectives and expectations with respect to future production,
 operations, costs, products and services, and statements regarding future performance. Forward-looking statements are generally identified by the words "plans," "expect," "anticipates,"
 "believes," "intends," "estimates" and other similar expressions. All forward-looking statements involve a number of risks, uncertainties and other factors. Although ABG’s management
 believes that the expectations reflected in such forward-looking statements are reasonable, investors are cautioned that forward-looking information and statements are subject to various
 risks and uncertainties, many of which are difficult to predict and generally beyond the control of ABG, that could cause actual results and developments to differ materially from those
 expressed in, or implied or projected by, forward-looking information and statements contained in this presentation. Factors that could cause or contribute to differences between the actual
 results, performance and achievements of ABG include, but are not limited to, political, economic and business conditions, industry trends, competition, fluctuations in the spot and forward
 price of gold or certain other commodity prices, changes in regulation, currency fluctuations (including the US dollar, South African rand and Tanzanian shilling exchange rates), ABG’s ability
 to successfully integrate future acquisitions, to recover its reserves or develop new reserves, including its ability to convert its resources into reserves and its mineral potential into resources
 or reserves and to timely and successfully process its mineral reserves, trespass, theft and vandalism, changes in its business strategy, as well as risks and hazards associated with the
 business of mineral exploration, development, mining and production. Accordingly, investors should not place reliance on forward-looking statements contained in this presentation. Any
 forward-looking statements in this presentation speak only as of the date of this presentation and only reflect information available at the time of preparation. Subject to the requirements of
 the Disclosure and Transparency Rules and the Listing Rules or applicable law, ABG explicitly disclaims any obligation or undertaking publicly to update or revise any forward-looking
 statements contained in this presentation, whether as a result of new information, future events or otherwise.

 No statements made in this presentation regarding expectations of future profits are profit forecasts or estimates, and no statements made in this presentation should be interpreted to mean
 that ABG’s profits or earnings per share for any future period will necessarily match or exceed the historical published profits or earnings per share of ABG or any other level.

 You are reminded that you have received this presentation subject to the disclaimer and important notices contained herein and on the basis that you are a person to whom this presentation
 may be lawfully made and delivered in accordance with the laws of the jurisdiction in which you are located. You may not and are not authorised to: (i) reproduce or publish this
 presentation; or (ii) distribute, disclose or pass on this presentation to any other person, in whole or in part, by any medium or in any form, whether electronically or otherwise. ANY
 FORWARDING, DISTRIBUTION OR REPRODUCTION OF THIS PRESENTATION IN WHOLE OR IN PART IS UNAUTHORISED. FAILURE TO COMPLY WITH THIS NOTICE MAY RESULT IN A
 VIOLATION OF APPLICABLE SECURITIES LAWS.

                                                                                                                                                                                                         40
You can also read