15 Blackrock Merrion Core Bus Corridor Emerging Preferred Route Public Consultation February 2019
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
BusConnects Core Bus Corridors 1 15: Blackrock > Merrion Contents 1. Introduction 2 1.1 Background 2 1.2 Why does Dublin need a core bus corridor network? 3 1.3 What is BusConnects Dublin? 5 1.4 What are the benefits of this project? 6 1.5 What does the core bus corridor project entail? 8 2. Emerging Preferred Route 10 2.1 The Emerging Preferred Route for Blackrock to Merrion 10 2.2 Blackrock to Merrion 10 2.3 Key Facts 11 3. Challenges and Mitigations 12 3.1 The Challenges 12 3.2 Potential Impacts 12 3.3 How we will address those challenges 12 4. The Process for the Acquisition of Land 16 4.1 How the project will progress 18 5. How to take part in the public consultation 20 5.1 Potential impacted lands 20 5.2 General queries 20 5.3 How to Engage 20 6. Appendices 22 6.1 Index map 23 6.2 Route maps 24
BusConnects Core Bus Corridors 2 15: Blackrock > Merrion 1. Introduction SECTION 1 1.1 Background Separately in July 2018 the Dublin Area Bus Network Redesign, which is the redesign of bus services, started its first public consultation In June 2018 the National Transport Authority (NTA) phase. Around 30,000 submissions including signed petitions and online survey responses were received by the end of September. published the Core Bus Corridors Project Report. The Over the coming months all of these submissions will be reviewed report was a discussion document outlining proposals and assessed. Following that process a revised network design will be for the delivery of a core bus corridor network across published during 2019 for a second public consultation. It is envisaged Dublin. It set out the vision for the provision of 230kms that the implementation of the final network will take place in 2020. of dedicated bus lanes and 200km of cycle lanes/tracks The network redesign can be implemented on the existing road network with some enhancements at key interchange locations. on sixteen key bus corridors. The public consultation for the sixteen radial core bus corridors will Continuous bus lanes and cycle tracks now take place on a phased basis from November 2018 until May 2019. Each phase will be for a set number of corridors to be consulted on over a period of months. These public consultations phases will be the start of a detailed process of engagement and communication. All of which will take place prior to detailed designs being finalised and planning permissions sought. This document is one of a series of sixteen, each dedicated to a single 230kms 200kms core bus corridor. The document provides a written description of the emerging preferred route from start to finish with supporting of continuous of cycle tracks/ route maps. It explains the step by step process for engagement bus priority lanes provided and consultation for potentially impacted property owners and the general public. It also outlines the process for planning and construction of the core bus corridor network including expected timelines.
BusConnects Core Bus Corridors 3 15: Blackrock > Merrion SECTION 1 1.2 Why does Dublin need a core ĤĤ The bus system can deliver – We need to invest in the bus system because the bus system is the main component to meet bus corridor network? our future transport needs. A good bus system has the reach and ĤĤ Congestion – Congestion is one of the most significant flexibility to service all the new housing developments, business challenges facing the Dublin region and needs to be addressed parks, hospitals, colleges and retail shops across Dublin. It is a to safeguard the growth of the Dublin region and keep people proven solution and is the main form of public transport across moving. Ireland’s economic recovery from the recession is Dublin with 67% of public transport journeys each day made by seeing significant increases in the number of people working bus. The bus system carries three and four times the number of and travelling across Dublin. The number of commercial vehicles people who travel on Luas or Dart and commuter rail. continues to rise as does the number of tourists. The commuter areas surrounding Dublin continue to spread and grow in a low Forecast Population Growth in Dublin Region density manner. Growth areas can only be served in the short and medium term by the bus as opposed to long-term projects such as rail and Luas. 1.5 25% At present bus lanes are in place for less than one third of a bus increase journey on the busy corridors. This means buses are competing 1.2 Population (millions) for space with general traffic and so are affected by the increasing levels of congestion. 0.9 ĤĤ Growing Population – It is predicted that the population for 1.2 1.5 the Dublin region will grow 25% by 2040, bringing it to almost million million 1.5m for the region. This huge growth in population has to be 0.6 accommodated with a quality public transport system. 0.3 0 2016 2040
BusConnects Core Bus Corridors 4 15: Blackrock > Merrion SECTION 1 ĤĤ People want to cycle – The core bus corridor project is not Dublin Canal Cordon 2017 Statistics - 7am to 10am just about the provision of bus lanes. Under this project we will also deliver 200km of segregated cycling infrastructure to make 211,416 cycling safer and more attractive than ever before. This initiative is people crossed the canal inbound between 7.00am and 10.00am. the foundation of the overall cycle network for the Greater Dublin Area. Commuting to work by bicycle has increased by 43% since 2011. Over half 107,160 of all journeys into the people came into Again this growth represents a clear choice that people are city in the morning are the city centre by now made on public using bus, train or making to cycle. This project will support that trend and is a transport. Luas. vital component of creating a sustainable transport system for people across Dublin. Safe cycling facilities across the 16 key bus corridors will provide people, families and their children a suitable environment to cycle where they want and when they want 12,447 25,000 ĤĤ People want to use public transport – The need to build people cycled in. The highest number people walked in. Mode share for a core bus network is being driven by increases in congestion ever. walking is 11.8%. and also by the significant shift of people choosing to use public transport. People want to use it and should have a reliable and efficient bus system to travel on. Based on 2017 canal cordon figures over 70% of people travelling into the city each morning 70% Private cars carried do so by sustainable transport modes and mostly by bus. Cars used sustainable under only account for 30% of travel into the city centre each day and modes. 30% of people for the therefore the amount of road space allocated to sustainable first time. transport needs to reflect that position. The more people use Public transport also sustainable modes of reduces the amount transport, the less of greenhouse gases congestion. and other emissions.
BusConnects Core Bus Corridors 5 15: Blackrock > Merrion 1.3 What is SECTION 1 BusConnects Dublin? E XECUTIVE SUM MARY er Service Strategy 2: Simplify Radial Figure 8: Existing Network. Multiple routes from each corridor cross the city centre in different directions. P&R Services UsingDublin BusConnects Spines to Airport of service categories to Figures 8 and 9 show a schematic of the existing and proposed ons in usefulness. For is Ina themajor investment radial networks. Ballymun existing system, most radial corridors are served by to m all-day services. These programme to ent services from infre- a pile of overlapping routes, each of which goes to a different Bla nc ha Artane rd corridor on the opposite side of the city. This provides direct sto wn Finglas work, and can form the service between many places, but each of the individual routes is rmation. er frequency services improve public not very frequent, so wait times are long. The proposed strategy would put just a single line, called a Phoenix Park transport in Dublin. to Lucan / be easy to identify, spine, on each radial corridor, but would run this service very Liffey Valley frequently. Service would come every 4 to 8 minutes all day, Ringsend a diversity of purposes. so that the next bus is coming whenever you need it. This also ĤĤ Building a network of newCrumlin ĤĤ Develop a state-of-the-art ĤĤ New bus stops and shelters means you could change from any spine to any other with little It aims to overhaul the delay, so that trips across the city would still be easy. Again, total bus corridors to make Harold’s Cross ticketing system. with better signage and travel times are faster because the waiting time saved by the high current bus system in Dublin journey's faster and more information. ĤĤ Implementation of a to frequency is greater than the time spent on the interchange. Bla to ck De reliable. ro Rathgar UCD c an k ĤĤ Provision of bus based sg through a 10 year programme cashless payment system. ran ge of integrated actions to simple map of just its high frequency services, so that people can see ĤĤ New network of cycle lanes/ Park and Ride sites in key g Figure 9: Proposed Network. Each corridor has a single ĤĤ Simpler fare structure. deliver a more efficient, tracks. frequent line crossing the city centre on a single path. TO AIRPORT & SWORDS TO MALAHIDE locations. GOUIN PERRAS 49 -BAPTISTE reliable and better bus system 71e AVENUE RODOLPHE-FORGET 33 48 ARMAND-BOMBARDIE PERRAS SAINT-JEAN LÉGER MAURICE-DUPLESSIS 48 LANGELIER 48 53 MAURICE-DUPLESSIS R 42 e 49 e AV 69 AV . . ER LÉG 44 187 for more people. HENRI-BOUR Y ASSA MARIE-VICTORIN IGN 69 BALLYMUN MONTMORENCY NT URASSA BLANCHARDSTOWN HENRI-BO MO DE LA CONCORDE 69 139 33 DE LACORDAIRE 49 CLONGRIFFIN 48 CLARE REY LAR HALL PIE-IX DU 67 33 TR ICE 132 BOMBARDIER HOWTH NT EN BEAUMONT RIES AIR JUNCTION CARTIER RAI E FINGLAS S-P E NDE TUR 32 44 GRA COU UE A L L A L L DES SQ LAN 121 -LÉ VE E D GELI 69 NÉ TO LACORDAIRE DE VIAU VÉ MA SAU RE ER 141 L'AC RIE 69 193 DU DART N A L L HOWTH RO ADI 139 B SAIN CH E ER BROOMSBRIDGE HENRI-BOURASSA 45 T-M GOUIN N ALO DES KE ICHE N-T OO JEA DES BR GA L PAP WHITEHALL ER LER SH ORM SA INEA RAS IES OU 141 GRENE EAU 187 -D' I-B U NR 33 AN X HE SAUVÉ L.- RY JOU JAR T A L L H.- 171 TOLKA LA 136 A FO 64 67 NT 18 VALLEY A L L AIN N PIE- 55 BIE F E AU LAN 121 BE 193 IX JUL EL N 44 ALO GEL AN ES AB N-T HONORÉ-BEAUGRAND JEA -PO CH IER CRÉMAZIE RAD VÉ ITR CLA SAU 141 AS ISS SA RK ON INT SAINT-MICHEL RADISSON ZIE -LA IN 139 CAVEN MA 197 ERT UR 18 NE 80 CRÉ JEA EN LANGELIER UB EN E CO JARRY NN NS TUR DISH T 171 DE LA CÔTE-VERTU THIME E-D E-M RY D’IBERVILLE RR LUCAN NT 121 JAR EMO PIE AN CÔTE-VERTU CADILLAC ROS CE FABRE VIA 55 DE U 33 CAD 45 O ILL BLO JEAN-TALON N AC DE CASTELNAU UBIE OM 32 DU COLLÈGE BEA HA ASSOMPTION FIE IG A L L LD 136 SAI C PIE NT- PARC BEAUBIEN -IX MIC 165 18 YAL HE T-RO L DU MON HEUSTON ACADIE 197 NT DU VIAU 97 PAR EMO A L L ROS C C PAP PIE-IX INEA ROSEMONT 80 67 DE LA SAVANE NE U A L L HOR NIC G VAN OUTREMONT FR YAL HEL E OLE ON T-RO RIN RAC MON BALLYFERMOT TEN T DU JOLIETTE THE -CA 51 AC 24 LAURIER NTE 161 51 SAI CH. PRÉFONTAINE A L L 97 139 DE D NAMUR RIER IT LAU LA KE PET OO CÔT ONT MONT-ROYAL BR D-M UAR ER E-D PLAMONDON ÉDOUARD-MONTPETIT ÉDO SH SAIN ES- NE SAIN O UNIVERSITÉ-DE-MONTRÉAL FRONTENAC HOR T-LA NEIG VAN T-UR CÔTE-DES-NEIGES URE ES CÔTE-SAINTE-CATHERINE BAIN NT 24 CA 45 A L L VE 55 F ND SHERBROOKE 161 A L L ISH SNOWDON 51 PAPINEAU CLONDALKIN CRUMLIN A A L L DU Y 165 B PAR MAR BERRI-UQAM BEAUDRY HOSPITAL E EN- CH. DE C DAR C QUE KIMMAGE KIL LPH T-LU CH. LA SAIN CÔT GUE E-D PLACE-DES-ARTS CH. CÔTE ES- SAINT-LAURENT WEN NEI G GES 103 TWO 24 DIN VILLA-MARIA LONGUEUIL – 80 FIEL McGILL UNIVERSITÉ-DE-SHERBROOKE RTH CHAMP-DE-MARS ND PEEL GRA KLA 51 MON ND PLACE-D’ARMES DÉC 103 GUY-CONCORDIA Légende KE BROO UCD ARIE SHER GU DART ATWATER SQUARE-VICTORIA—OACI WE 24 165 JEAN-DRAPEAU Y ST 90 E BONAVENTURE BRO HERIN SHERBROOKE 105 E-CAT LUCIEN-L’ALLIER ADW SAINT 105 105 Réseau 6 h à 21 h AY GEORGES-VANIER 90 CH. UPPER LACHINE VENDÔME LIONEL-GROULX 90 TERENURE PLACE-SAINT-HENRI Réseau 6 h à 14 h A L L DUN CHARLEVOIX E LAOGHAIRE Réseau 14 h à 21 h ANG LASALLE RIGN ON UR NEWMAN LA FLE SAGGART SANDYFORD TALLAGHT 106-406 ANGRIGNON JOLICŒUR MONK DE L’ÉGLISE VERDUN DEANSGRANGE LASAL |9 LE Dublin AreaTOBus Network Redesign TO BRAY & BRIDESGLEN GREYSTONES Public Consultation Report ĤĤ Redesign of the Dublin area ĤĤ New bus livery providing ĤĤ Transitioning to a bus network to provide a more a common style across new bus fleet with efficient network with high different operators. low emission vehicle frequency spines, new orbital technologies. routes and increased bus services.
BusConnects Core Bus Corridors 6 15: Blackrock > Merrion SECTION 1 1.4 What are the benefits of this project? Journey Time Savings ĤĤ Journey Time Savings – The core bus corridor project will deliver journey time savings of up to 40-50% on each corridor. Dedicated bus lanes can significantly increase bus travel speeds and reliability. Improved journey times and reducing the amount of time people spend commuting will make bus travel more attractive and reduce our reliance on car travel. The more convenient the bus system is, the faster the modal shift will be for people from the car Current Journey Times to the bus. Not only will current bus users and cyclists benefit but future commuters will be able to avail of a better system as the improved bus and cycle lanes are built. up to 40-50% ĤĤ Accessibility for all – Accessibility is about people’s ability journey time savings to reach the destinations and services they want to get to. This means both people's level of mobility and the costs of travelling. There are many tens of thousands of people across Dublin who cannot drive a car, do not have a car and are completely reliant on the bus service. The bus lane improvements will enhance accessibility for the elderly and mobility impaired because all buses are accessible and bus stops, bus shelters and footpaths will support easy boarding and disembarking of the buses. BusConnects Future Journey Times ĤĤ Better cycling facilities – This project will see the provision of Journey Times without BusConnects much needed cycling facilities around the city region. Across the 16 radial bus corridors there will be over 200kms of high quality cycling facilities provided. These new or improved cycle lanes will be segregated from bus lanes and general traffic where feasible.
BusConnects Core Bus Corridors 7 15: Blackrock > Merrion SECTION 1 ĤĤ Pedestrians and Local Urban Centres – In addition to bus lanes and cycling facilities this project is an opportunity to enhance and improve local areas. This project is focused on making things better for commuters and communities around the bus corridors. Along each route, improvements and enhancements will be made to footpaths, walkways and pedestrian crossings. Funding and investment for local urban centres with additional landscaping and outdoor amenities will be provided. ĤĤ Building a sustainable city and addressing climate change – By providing a better bus system for Dublin we can make it a more attractive place to live, work and visit. A good public transport system is vital to support the economic activity of any city and can also address the need to improve air quality and reduce CO2 emissions. Tackling the challenges of climate change is a priority for the Government and moving more people to public transport is a key component of the solution.
BusConnects Core Bus Corridors 8 15: Blackrock > Merrion SECTION 1 1.5 What does the core bus corridor Bus lanes are needed to make the current and future bus system operate efficiently, reliably and punctually. Our intention is to develop project entail? these bus corridors so that each will have continuous bus priority – in other words, a continuous bus lane in each direction as well as The core bus corridor project proposes the provision of 230 maintaining two general traffic lanes. In addition we also want to kilometres of bus lanes on sixteen of the busiest bus corridors provide safe cycling facilities, segregated where possible from other and 200 kilometres of cycle lanes and tracks as published in the vehicular traffic. This will remove the delays currently experienced discussion document, Core Bus Corridor Project Report June 2018. which will grow worse as congestion increases. The layout below shows the arrangement that we are seeking to achieve on each corridor. However, this optimal layout is difficult to achieve in practice and we have proposed alternative solutions in various places to deliver the required bus and cycling lanes. Optimum Road Layout CYCLE CYCLE FOOTPATH TRACK BUS LANE TRAFFIC LANE TRAFFIC LANE BUS LANE TRACK FOOTPATH
Seafield Lissenhall Farm Lane Newtown Cross Demesne Kilcoscan Mount Nevinstown Ambrose Cullen Lauristown BusConnects Core Bus Corridors Cluthe Coolquay Surgalstown Swords 9 Tyrellstown Knocksedan 15: Blackrock > Merrion Kilbride Killeek Demesne St Margaret’s Golf & Country Club 2 Malahide Kilbrook The Ward Cross Sea Mount Forrest Great The Ward St Margaret’s Cloghran Feltrim Radial Core Bus Corridors Dublin Airport SECTION 1 Kinsealy Emerging Portmarnock Seabrook Manor St Doolagh’s Tyrrelstown Williamsville Dardistown Littlepace Mulhuddart Ballycorden 3 Woodlands Belcamp Balgriffin Belmayne Clongriffin Preferred Routes Grattan Lodge 1 1. Clongriffin to City Centre Cappoge Whitestown Santry Donaghmede Ongar Village Abbotstown Ballymun Baldoyle 5 4 Finglas Coolock Bayside Sutton Howth 2. Swords to City Centre Clonsilla Kilbarrack Blanchardstown Beaumont Dunsink 3. Ballymun to City Centre Artane Whitehall Glasnevin Raheny 4. Finglas to Phibsborough Luttrellstown Donnycarney Castleknock Killester Drumcondra Marino Dollymount Cabra Phibsborough Baily Strawberry Beds Lucan 6 Fairview Clontarf 5. Blanchardstown to City Centre Phoenix Park Palmerstown 7 East Wall Stoneybatter Islandbridge Smithfield Chapelizod Docklands 6. Lucan to City Centre Ballyfermot Kilmainham The Liberties Ringsend 16 7. Liffey Valley to City Centre Inchicore Rialto Irishtown Sandymount Bluebell Portobello 8. Clondalkin to Drimnagh Dolphin’s Barn 8 Rathmines Ranelagh Ballsbridge Drimnagh Harold’s Cross Donnybrook Walkinstown 9. Greenhills to City Centre Clondalkin Crumlin Ballymount Kimmage Rathgar Milltown 14 10. Tallaght to Terenure Booterstown 11 Terenure Perrystown Clonskeagh Belgard Blackrock 11. Kimmage to City Centre Kingswood Windy Arbour Rathfarnham 15 Templeogue Churchtown Goatstown Mount Merrion Monkstown 12 Tallaght 10 Ballyroan Dundrum Stillorgan Dún Laoghaire 12. Rathfarnham to City Centre Knocklyon 9 Firhouse Ballyboden Galloping Green Kill Of The Grange Dalkey 13. Bray to City Centre Leopardstown Deansgrange Aylesbury Ballinteer Sallynoggin 14. UCD Ballsbridge Whitechurch Marlfield Sandyford Cornelscourt to City Centre Foxrock Bohernabreena Woodtown Mount Seskin Killiney Rockbrook Cabinteely The Line Ballyogan Knockannavea Stepaside 15. Blackrock to Merrion Carrickmines Loughlinstown 16. Ringsend to City Centre Kilmashogue Forest Ballybrack Ballinascorney Glenasmole Kilternan Shankill Scalp Glencullen Manor Kilbride Carneystown Old Conna 13 Countybrook Glencree Ballinagee Bray
BusConnects Core Bus Corridors 10 15: Blackrock > Merrion 2. Emerging Preferred Route 2.1 Emerging Preferred Route for cycle tracks. The Blackrock to Merrion Core Bus Corridor connects to the route of the UCD to City Centre Core Bus Corridor at the junction Blackrock to Merrion SECTION 2 of Merrion Road and Nutley Lane, providing a continuous route from Blackrock to the City Centre. The Emerging Preferred Route set out in this consultation document was identified following an assessment of various alternatives. 2.2.1 Nutley Lane to Booterstown Avenue The route selection process involved identification and consideration – Merrion Road, Rock Road of possible options taking account of criteria including local impacts Between the Merrion Road / Nutley Lane junction and the Rock Road on property frontage, existing traffic patterns and broad assessment / Booterstown Avenue junction, it is proposed to provide a single bus of environmental impacts. A Feasibility Report setting out details of lane, a single general traffic lane and segregated cycle tracks in each the assessment work undertaken is available on www.BusConnects.ie. direction. It is intended to undertake some safety improvement works at the junction of Merrion Road and Strand Road. Between Strand Arising from that work an Emerging Preferred Route has been Road and Booterstown Avenue a 2-way cycle track is proposed on identified for this corridor and public feedback on that proposal is the eastern side of the route. To facilitate this layout, landtake from now sought. It is important to know that this option is not adopted the following areas may be required: yet. Only following this public consultation and the review of the submissions received will a decision on the final Preferred Route be ĤĤ Properties at the junction of Merrion Road / Nutley Lane; made. ĤĤ Portion of green space from St. Vincent’s Hospital Campus; ĤĤ Properties between Herbert Avenue and Estate Avenue; ĤĤ Properties between Estate Avenue and Strand Road; and 2.2 Blackrock to Merrion Overview ĤĤ Properties between the entrance road to Elmpark Apartments The Blackrock to Merrion Core Bus Corridor commences on the R118 and Booterstown Avenue. Merrion Road at its junction with Nutley Lane. Buses are proposed The indicative extents of this land take are shown on the maps included to be routed along Rock Road joining the N31 at the Mount Merrion in the Appendix to this brochure. Avenue junction. The proposed scheme terminates at the junction of Temple Hill/ Monkstown Road and Stradbrook Road. Priority for buses and cyclists is provided along the entire route, consisting primarily of dedicated bus lanes in each direction, and continuous segregated
BusConnects Core Bus Corridors 11 15: Blackrock > Merrion 2.2.2 Booterstown Avenue and Stradbrook Road – 2.3 Key Facts Rock Road, Frascati Road, Temple Road, Temple Hill, SECTION 2 Stradbrook Road ĤĤ Approximate number of properties that may be impacted: 51 Between the Booterstown Avenue and Stradbrook Road junctions, ĤĤ Approximate number of on-street parking spaces that may be removed: 33 it is proposed to provide a single bus lane, a single general traffic lane and segregated cycle track arrangement in each direction. To ĤĤ Approximate number of roadside trees that may be removed: 25 accommodate this proposed layout, landtake from the following areas ĤĤ Approximate route length: 4kms may be required: ĤĤ Approximate new cycle lane length: 4kms ĤĤ - Blackrock College; ĤĤ Current bus journey time: up to 30 mins ĤĤ - Car parking area adjacent to Blackrock Park; ĤĤ BusConnects journey time: 13-15 mins ĤĤ - Green space in Blackrock Clinic lands; and ĤĤ Future Bus journey time without BusConnects: 40 mins + ĤĤ - Boundary lands of Blackrock Park. The indicative extents of this land take are shown on the maps included in the Appendix of this brochure.
BusConnects Core Bus Corridors 12 15: Blackrock > Merrion 3. Challenges and Mitigations 3.1 The Challenges If we don’t decide to make these changes now, then we need to accept that Dublin will become increasingly congested and a less attractive It’s important to acknowledge that the choices required to deliver place to live and work, both for us now and for future generations. this step-change in the performance of the bus system will be difficult. However, the decision-making needs to be done now and 3.2 Potential Impacts not postponed until the problem is far greater. Some of the decisions may be hard but they are being made because we believe that these 3.2.1 Traffic changes plans have the potential to fundamentally transform the way public SECTION 3 By creating more priority for buses and cycling there will be changes transport works in Dublin. to how traffic currently moves around the streets. On some corridors, certain roads may become one-way, new bus-only sections will be Our challenge now is to respond to the needs of a modern city by introduced and in some places general traffic will have to take new providing a fit-for-purpose bus system, built on a streetscape that routes in and out of the city. Additional cycle routes will be built, dates back centuries. Needless to say the streets were not designed generally segregated from vehicular traffic, and pedestrian crossings to move the number of people that now need to travel in and out will be added and moved in some areas. of the city each day. Some of the city’s inner suburbs date back to Victorian times, with road layouts suited to more modest levels of 3.2.2 Land take traffic than we see today. Because there is so little unused space along these busy roads, it will ĤĤ We will need to widen roads; often not be possible to accommodate the bus lanes and cycle lanes ĤĤ We will have to convert current traffic lanes to bus lanes; in the width available. In order to achieve the required space it will be necessary, in places, to acquire parts of front gardens, driveways ĤĤ We will need to restrict on-street parking; and land in front of commercial properties to allow the bus and cycle ĤĤ We will need to remove trees or parts of front gardens. lanes to be provided. This would require rebuilding new garden walls and driveways a short distance back from the existing road boundary. Not all the impacts will be felt equally and some locations will require more changes than others. Over the years those modifications that 3.2.3 Reduction of On-Street Parking and Loading were easier to implement - the ones that caused little or no disruption Facilities - have been made. This means that there are no longer any simple changes which we can make that would generate meaningful benefits. Because the roads that need widening travel through residential and business areas there will be a need to reduce the amount of on-street parking and loading facilities to accommodate the new layout.
BusConnects Core Bus Corridors 13 15: Blackrock > Merrion 3.2.4 Removal of Trees There are principles for mitigation, statutory compensation and reparation which will be adhered to by the NTA as part of the As with the need to remove some parts of front gardens and statutory planning process. However, below are some of the measures footpaths there will be also be a need to remove trees along some of that we envisage will be included. This list is not exhaustive and we the corridors. anticipate that there will be other measures that will need to be put in place. 3.2.5 Road Works and Construction Sites Widening roads, and building bus and cycle lanes, requires 3.3.1 Traffic Changes SECTION 3 construction work. There will be excavation of the existing roads, Where general traffic is diverted and re-routed, adequate signage plus parts of gardens and footpaths where needed. There will be and road markings will be provided for people to find their way. resurfacing, kerbing, replanting and landscaping. As with any work Measures will be implemented to ensure that “rat-runs” do not emerge site and road works, there will be a certain level of noise, dust and as a consequence of the re-routed traffic. Also, local access will be temporary traffic diversions. maintained where new bus-only sections or one-way systems are brought in for residents and commercial properties. 3.3 How we will address those challenges 3.3.2 Land take Obviously these challenges and impacts are significant. Every feasible option is being looked at to minimise the disruption to people, their Where lands, such as parts of gardens and driveways, are being acquired property and the wider local community. Where there is simply no for widening we will purchase the portion of front gardens and driveways viable alternative, and where we know we have to remove trees, from property owners; ensure new landscaping and replanting of the portions of gardens, driveways or parking, we will ensure appropriate gardens, reinstatement of driveways as well as providing compensation mitigation measures are put in place, wherever practicable. for the garden and driveway portion loss and disruption. As part of this public consultation potentially impacted property Where private and public walls or fencing are removed we will rebuild owners will be contacted directly by the NTA and a direct dialogue new garden walls and replace fencing where gardens have been will commence. As each individual property owner will have specific affected and shortened. Also, where public or commercial walls and and personal issues there will be a dedicated liaison team to engage fencing have been taken they will be rebuilt and replaced. with this group on an individual basis.
BusConnects Core Bus Corridors 14 15: Blackrock > Merrion 3.3.3 On street parking and Loading Facilities Where there is a loss of on-street parking and loading facilities we will seek to provide, where feasible, alternative arrangements close by for residents and businesses. 3.3.4 Trees Where trees are removed from roadsides and footpaths we will put SECTION 3 in place a comprehensive replanting programme. This programme will use mature or semi-mature ready-grown trees where appropriate and, where it is feasible, plant them as close as possible to the original locations. 3.3.5 Urban Centre Improvements We will look for areas along the busy corridors where it is possible to improve the existing local spaces and the existing landscaping. It is important to use this opportunity to not only replace what is removed but to enhance the local areas. To do so, we will consult with the local authorities on such urban centre improvements and collectively seek to create attractive local environments. 3.3.6 Road Works and Construction Sites During the construction stages the construction sites will be localised and managed on a road by road basis. The size of each work site and the hours of working will have to take into consideration the residential nature of many of the roads. Traffic management will be very important to keep the traffic moving and ensuring local access for people and deliveries is always maintained.
BusConnects Core Bus Corridors 15 15: Blackrock > Merrion SECTION 3
BusConnects Core Bus Corridors 16 15: Blackrock > Merrion 4. The Process for the Acquisition of Land Where the potential for impacts on private lands have been identified, During 2020 An Bord Pleanála will consider the planning the following process applies: application. There will be a period of statutory public consultation to allow those notified as being subject to CPO, and the public at large, Q4 2018 – Q2 2019 NTA will issue information letters (not formal to make submissions and/or objections to An Bord Pleanála. This compulsory purchase order (CPO) notifications) to potentially will be followed by an Oral Hearing by An Bord Pleanála if deemed impacted land owners and/or occupiers along each Core Bus necessary. The statutory process will conclude with a decision by An Corridor. Potentially impacted includes for example, the acquisition Bord Pleanála on whether to: of parts of front gardens, walls, fences, gates, driveways and the rebuilding of same to make way for street widening. The intention 1. approve the application, approve with conditions, or refuse the of this is to start a direct dialogue between NTA and the potentially application; and impacted parties. 2. confirm, amend, or reject the CPO. During 2019 to prepare the statutory planning documentation, From 2021 onwards if An Bord Pleanála grants approval NTA will the project design and environmental impact assessment will be commence valuations and negotiations to acquire the lands in the SECTION 4 progressed. During this time NTA will endeavour to minimise impacts CPO, and progress construction of the project. The construction of on private lands. Direct dialogue between NTA and potentially each core bus corridor will take up to two years to complete. The impacted parties will continue to understand the likely impact of construction start dates for each of the 16 corridors will be managed the proposed development and what arrangements can be made to over the period 2021 through 2027. minimise and where possible avoid those impacts. End of 2019 / start of 2020 NTA will finalise the statutory planning documentation and will serve formal notice on the actual impacted owners of land proposed to be compulsorily purchased for the project. It will make a formal application to An Bord Pleanála for confirmation to compulsorily purchase necessary lands for purposes of constructing upgraded bus-lanes and bike-lanes.
BusConnects Core Bus Corridors 17 15: Blackrock > Merrion SECTION 4
BusConnects Core Bus Corridors 18 15: Blackrock > Merrion 4.1 How the project will progress How & when to get involved 2018 2019 2020 SECTION 4 ENGAGEMENT STATUTORY PROCESS Confirmation of Emerging Preferred Route An Bord Pleánala Application Consultation on Emerging Preferred Route (Q4 2018-Q2 2019) Submission of Statutory Planning Finalisation of Emerging Preferred Route (Q2 2019) Application to An Bord Pleanála Statutory Consultation in accordance with the legislative requirements An Bord Pleanála deliberations including Preparation of Statutory Application an Oral Hearing where required Optimise Engineering Design An Bord Pleanála to: Prepare Environmental Impact 1. approve the application, approve with Assessment Report conditions, or refuse the application; and Define property requirements and prepare 2. confirm, amend, or reject the CPO. CPO.
BusConnects Core Bus Corridors 19 15: Blackrock > Merrion 2021 2027 SECTION 4 ACQUISITION Construction Commences on a Phased Basis - Each corridor upgrade will take up to 2 years to complete Start of Property Acquisition and Construction NTA formally requests a compensations claim from the CPO affected parties and discussions commence about valuation Affected party appoints professional valuer to prepare and submit a compensation claim to NTA On reaching agreement, compensation is paid, otherwise the matter may be referred by either party to the property arbitrator to assess compensation Acquisition is finalised In parallel NTA will progress the construction of the Core Bus Corridors.
BusConnects Core Bus Corridors 20 15: Blackrock > Merrion 5. How to take part in the public consultation Please remember that the plans that we are publishing are proposals 5.3 How to engage and that no final decision has been made on these matters in advance of the public consultation. We welcome all of your views. We are inviting submissions in relation to the proposals set out in this Public Consultation Document. Where you do not like a proposal, please consider suggesting an alternative solution or other option for consideration. But do bear in Written submissions and observations may be made by: mind that bus transport is, and will continue to be, the main form of public transport for most areas of the Dublin region and an alternative Online: of providing an underground rail system is simply not a viable option Through the online form in the ”Public Consultation” section of the for most parts of Dublin. Core Bus Corridor page on our website: www.busconnects.ie 5.1 Potential impacted lands Or by email to: If your property is potentially impacted by the proposals, a letter cbc@busconnects.ie will have been hand delivered to the property and details of how to engage with the NTA are detailed in that letter. A dedicated property Or by post to: liaison representative will be available to meet with individual Core Bus Corridor Project property owners and provide regular updates on the project. National Transport Authority Dún Scéine 5.2 General queries Harcourt Lane SECTION 5 Dublin 2 The project website www.busconnects.ie has a dedicated section D02 WT20 for the Core Bus Corridor project. Users can access the site to find out more about the project and download copies of the key studies that have been carried out. General queries can be directed to a dedicated Freephone - 1800 303 653 or by email to cbc@busconnects.ie
BusConnects Core Bus Corridors 21 15: Blackrock > Merrion SECTION 5
BusConnects Core Bus Corridors 22 15: Blackrock > Merrion 6. Appendices Index map Route maps
Sa Angle onnybrook Blackrock Merrion BusConnects Core Bus Corridors 15: Blackrock > Merrion 23 Index Map Par M er kA rio ve n Rd d Do aR nn lese yb Strand Rd ro Ang ok Rd Rd Ailesbury Rd on lint 1 ow rR ve ea B St ill or ne 2 ga La n Rd y Rd le ut ch Hill N 3 Ro ck Rd 4 Booterstown St ill or ga 5 n Rd 6 gh Ave 7 n Ro tow ck Ro ters Rd eb uc Boo kR 8 d St ill or ga Blackrock Cro n ss Rd e Av Av e r’s ste Ro Fo 9 eb uc k Ne Rd wto wn N3 Ave No Te 1 rth m pl Av e Call 1 Rd N3 ary e Rd 10 11 Go N3 Carysfort Ave Avoca Av ats e 1 SECTION 6 tow Mon nR ksto Mount Merrion wn Rd d Goatstown Monkstown Ave le Rd Mount Anvil South Stradbro Grove Ave d yR ne Kil Carrickbrennan Rd Ta e ma Av N1 ok Rd k cu ar 1 e dR np an D w So sL dL rk to ut n Pa ew che wr rga hA Stillorgan lo N NOTE: The Emerging Preferred Route shown on the following drawings is indicative only Stil and is subject to change following consultation and as part of the design development process. Bir ve St ra Fleurville Rd db Kilmacud Rd Lwr Lwr Moun ttown Rd ro R ok
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 1: Emerging Preferred Route MERRION AVENUE BUS STOP LÁNA BUS EXCEPT BUSES BUS LÁNA LÁNA BUS PROPOSED SCHEME LÁNA BUS to City Centre CBC BUS UCD, Ballsbridge BUS LÁNA BUS LÁNA BUS MERRION STOP LÁNA BUS STOP ROAD LÁNA BUS LÁNA BUS BUS BUS ESTATE AVENUE HERBERT AVENUE ST. VINCENTS HOSPITAL LÁN BUS A BUS LEGEND: BUS BUS LANE CYCLE TRACK SECTION 6 FOOTPATH CARRIAGEWAY GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) © Ordnance Survey Ireland Government of Ireland. All rights reserved. BAR SCALE Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 2: Emerging Preferred Route TYPICAL CROSS SECTION City Centre An Lár 00 00 18 D --- 18 D --- (Varies) 1.50m 3.00m 3.00m 3.00m 3.00m 1.50m (Varies) ST FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH RA ND 0.30m RO ROAD MARKING AD LÁNA BUS BUS BUS LÁNA BUS LÁNA LÁNA LÁNA BUS BUS BUS BUS BUS BUS LÁNA STOP STOP LÁNA BUS BUS LÁNA BUS ESTATE AVENUE BUS BUS BUS LÁNA BUS ME RR RO ION AD LÁNA BUS BUS LÁNA LÁNA BUS LEGEND: BUS LANE CYCLE TRACK SECTION 6 FOOTPATH CARRIAGEWAY GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 3: Emerging Preferred Route TYPICAL CROSS SECTION City Centre An Lár 00 00 18 D --- 18 D --- 3.50m 2.00m TWO WAY 3.00m 3.00m (Varies) 3.00m 3.00m 2.00m (Varies) FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE MEDIAN TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH BUS LÁNA MERRION ROAD NOTE: LÁNA WAYFINDING SIGNAGE BUS LÁNA BUS FOR CYCLISTS REQUIRED BUS LÁNA BUS LÁNA LÁNA BUS BUS LÁNA MERR LÁNA BUS ION ROAD BUS LÁNA LÁNA BUS LÁNA BUS BUS BUS BUS BUS BUS LÁNA LÁNA BUS STOP AV VIEW BE EN L UE LEGEND: BUS LANE CYCLE TRACK SECTION 6 FOOTPATH CARRIAGEWAY GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 4: Emerging Preferred Route LEGEND: 0 5.0 10.0 20.0 30.0 40.0 50.0m TYPICAL CROSS SECTION BUS LANE BAR SCALE CYCLE TRACK 00 City Centre An Lár 00 FOOTPATH 18 D --- CARRIAGEWAY 18 D --- GRASS AREA / VERGE 3.50m (Varies) TWO WAY 3.00m 3.00m 3.00m 3.00m 2.00m (Varies) SHARED AREA FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH BUS STOP LOCATIONS EXISTING BOUNDARY PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) LÁNA BUS LÁNA BUS BUS LÁNA ROCK BUS LÁNA ROAD BUS BUS LÁNA BUS LÁNA LÁNA BUS BUS LÁNA BUS BUS LÁNA BUS LÁNA BUS BUS LÁNA LÁNA BUS LÁNA STOP BUS BUS STOP BUS EXCEPT BUSES LÁNA BUS LANA BUS AV VIEW BE EN L STOP UE ST RO HE AD TRIMLESTON LE ST HELE AVENUE N' ROAD S N'S SECTION 6 © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 5: Emerging Preferred Route FUTURE 2-WAY CYCLE TRACK STOP LÁNA BUS BUS LÁNA LÁNA BUS LÁNA BUS BUS LÁNA BUS BUS ROCK ROAD LÁNA LÁNA BUS LÁNA BUS LÁNA BUS BUS BUS BUS BUS LÁNA BUS BUS STOP STOP BO AV OT EN ER UE ST OW N LEGEND: BUS LANE CYCLE TRACK SECTION 6 FOOTPATH CARRIAGEWAY GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 6: Emerging Preferred Route LEGEND: 0 5.0 10.0 20.0 30.0 40.0 50.0m TYPICAL CROSS SECTION BUS LANE BAR SCALE CYCLE TRACK 00 City Centre An Lár FOOTPATH 00 18 D --- CARRIAGEWAY 18 D --- GRASS AREA / VERGE (Varies) 2.00m 3.00m 3.00m 3.00m 3.00m 2.00m (Varies) SHARED AREA FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH BUS STOP LOCATIONS EXISTING BOUNDARY PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BUS LANA BUS BUS LANA BUS BUS LANA BUS BUS LANA BUS LANA BUS STOP CK STOP RO D BUS LANA A RO STOP LANA BUS BUS LANA LÁNA BUS ROCK ROAD BUS LÁNA BLACKROCK BUS STOP SECTION 6 COLLEGE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 7: Emerging Preferred Route SEAFORT PARADE PHOENIX TE RRACE STOP BUS LANA NO ENTRY LÁNA BUS LANA LÁNA BUS BUS ROCK STOP BUS LANA ROAD BUS BUS LANA BUS LANA BUS LANA BUS BUS BUS LÁNA BUS LANA BUS LANA BUS STOP LANA BUS LANA BUS STOP STOP LEGEND: BUS LANE CYCLE TRACK CA ST VENU FOOTPATH SECTION 6 LE A DA E CARRIAGEWAY WS GRASS AREA / VERGE N O SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 8: Emerging Preferred Route TYPICAL CROSS SECTION City Centre An Lár 00 00 18 D --- 18 D --- (Varies) 2.00m 3.00m 3.00m 3.00m 3.00m 2.00m (Varies) FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH LÁNA BUS LÁNA LÁNA BUS BUS ROCK BUS LÁNA LÁNA BUS ROAD LÁNA BUS BUS LÁNA BUS LÁNA LÁNA BUS LÁNA BUS LÁNA BUS LÁNA BUS LÁNA BUS LÁNA BUS BUS LÁNA BUS BUS STOP STOP LÁNA BUS LEGEND: BUS LANE CYCLE TRACK SECTION 6 FOOTPATH EN N AV RIO UE CARRIAGEWAY R ME GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 9: Emerging Preferred Route TYPICAL CROSS SECTION (Varies) (Varies) City Centre An Lár 00 00 18 D --- ROAD ROAD MARKING MARKING 18 D --- (Varies) 2.00m 3.00m 3.00m 3.00m 3.00m 2.00m (Varies) FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH L HIL CAR CK AVE ORT RO YSF NUE GEORGES AVENUE BUS LÁNA LÁNA BUS BUS LÁNA FRA SCA BUS LÁNA LÁNA ROA TI BUS LÁNA BUS D BUS LÁNA BUS STOP LÁNA LÁNA BUS LÁNA BUS LÁNA BUS LÁNA BUS LÁNA BUS LÁNA BUS LEGEND: BUS LANE CYCLE TRACK SECTION 6 FOOTPATH CARRIAGEWAY GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 10: Emerging Preferred Route LEGEND: 0 5.0 10.0 20.0 30.0 40.0 50.0m BUS LANE BAR SCALE CYCLE TRACK FOOTPATH CARRIAGEWAY GRASS AREA / VERGE SHARED AREA BUS STOP LOCATIONS EXISTING BOUNDARY PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) TEMPLE ROAD STOP BUS LÁNA STOP LÁNA BUS TEMPLE ROAD LÁNA BUS BUS LÁNA BUS BUS BUS LÁNA BUS BUS BUS LÁNA LÁNA SW VENU BUS EE A TM E BUS LÁNA AN TI CA S AS FR OAD R LÁNA BUS STOP BUS LÁNA STOP SECTION 6 © Ordnance Survey Ireland Government of Ireland. All rights reserved. Licence Number EN 0082119 National Transport Authority.
BusConnects Core Bus Corridors 15: Blackrock > Merrion MAP 11: Emerging Preferred Route © Ordnance Survey Ireland Government of Ireland. All rights reserved. TYPICAL CROSS SECTION Licence Number EN 0082119 National Transport Authority. City Centre An Lár 00 00 18 D --- 18 D --- (Varies) 2.00m 3.00m 3.00m (Varies) 3.00m 3.00m 2.0m (Varies) FOOTPATH CYCLE TRACK BUS LANE TRAFFIC LANE MEDIAN TRAFFIC LANE BUS LANE CYCLE TRACK FOOTPATH AVE PARK NUE PLE TEM STOP LÁNA BUS TEMPLE ROAD LÁNA BUS LÁNA BUS BUS LÁNA D LÁNA OA BUS TEM NR STOP OW PL HIL E N KST L MO LÁNA BUS ST RA DB RO OK LÁNA RO BUS AD BUS BUS LEGEND: BUS BUS LANE BUS CYCLE TRACK P STO SECTION 6 FOOTPATH ME CARRIAGEWAY HE ing GRASS AREA / VERGE SC ist D SHARED AREA ex E OS to BUS STOP LOCATIONS OP in EXISTING BOUNDARY PR Tie 0 5.0 10.0 20.0 30.0 40.0 50.0m PROPOSED NEW BOUNDARY (POSSIBLE LAND ACQUISITION) BAR SCALE
National Transport Authority Dún Scéine Harcourt Lane Dublin 2 D02 WT20 www.busconnects.ie
You can also read