TRIP REPORT HAITI SHELTER CLUSTER ENVIRONMENT ADVISOR FIELD REVIEW

Page created by Sharon Phillips
 
CONTINUE READING
TRIP REPORT HAITI SHELTER CLUSTER ENVIRONMENT ADVISOR FIELD REVIEW
Emergency Shelter Cluster

         Trip Report
    Haiti Shelter Cluster
    Environment Advisor
        Field Review

Developed under the

Integrating Critical Environmental Issues into
Emergency Shelter Cluster Activities Project

           CARE International and ProAct Network
          Funded by the Emergency Shelter Cluster
              (UNHCR Project CLUS-07/ESC04)
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                             Shelter Checklist Review/Gonaives - 30 October 2008

                              Emergency Shelter Cluster

                   Trip Report - Haiti shelter cluster
                  environmental advisor field review
                                C. Kelly (email: 72734.2412@compuserve.com)

Introduction

  The Global Shelter Cluster has funded CARE International and ProAct Network to develop capacities
  necessary for deployment of an Environment Advisor to support cluster activities during emergencies.
  Under this funding, ProAct Network has:
   1. Assembled and developed a set of tools and procedures to support a Environment Advisor in
      their work in Shelter Cluster field operations,
   2. Developed the terms of reference for the Advisor and,
   3. Established a list of individuals who can serve as Advisors in emergency operations.
  This report covers a field review of the existing tools and procedures to understand how well these
  materials would support the work of a Shelter Cluster Environment Advisor during a humanitarian
  emergency. The terms of reference for the field review are provided in Annex A.

Field Review

  Haiti was affected by two hurricanes (Gustav and Ike) and two tropical storms (Fay and Hanna) in
  August and September, 2008 (see Annex B). The storms resulted in destruction to a reported 27,730
  houses and damage to another 103,457 houses. The storms affected much of the country (see Annex
  B), although the flooding and subsequent deposition of up to 1.5 meters of soil in Gonaives gained
  international attention and became the focus of considerable assistance. In response to the impact of
  the four storms, the UN activated the Shelter Cluster, led by IOM Haiti.
  Under the terms of the agreement with the Global Shelter Cluster, the author was seconded to
  the Shelter Cluster in Haiti as an Environment Advisor to conduct a field review of shelter-related
  environmental tools and procedures. The author worked with the Cluster Coordinator and Information
  Officer at the IOM office in Port au Prince from 14 to 31 October 20081 (see Annex C).
  On arrival in Haiti, briefings on the field review and the role of the Environment Advisor were
  provided to the Shelter Cluster Coordinator, the IOM Country Director and the CARE Country Director.
  The following activities were undertaken during the work in Haiti in coordination with the Cluster
  Coordinator (or her temporary replacement):

  1   The period of 17-19 October was spent outside Haiti.

                                                                                                              1
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

Shelter Checklist Review/Gonaives - 30 October 2008

          1. Dissemination of Shelter-related Environmental Information:
               One task of the Environment Advisor is to share environment-related information with Cluster
               members. An “Environmental Toolkit” CD (prepared by ProAct Network) was provided to the
               Cluster Coordinator. Assistance was provided to the Cluster Information Officer on establishing a
               “google groups” web site so that shelter-related environmental information could be provided to
               Cluster members. The site, located at http://groups.google.com/group/emergency-shelter-
               haiti, provides an information base for Shelter Cluster operations in Haiti.

          2. Damage Assessment:
               It was noted that there was no detailed (quantitative or qualitative) assessment of the damage to
               shelter caused by the four storms aside from a cumulative listing of the number of destroyed and
               damaged buildings per administrative area. It was clear that the flooding in Gonaives damaged
               or destroyed many homes. But there was no clear picture of the nature of damage done by the
               storms elsewhere in the country, or quantitatively what assistance was needed to remediate
               this damage. Further, assistance agencies were developing re-sheltering plans but it was not
               apparent that these plans were based on a comprehensive assessment of damage or needs, or
               that these plans took into account the intentions of disaster-affected populations in terms of
               meeting immediate shelter needs 2.
               Following discussions with the Cluster Coordinator, assistance was provided on developing a
               rapid assessment questionnaire to ascertain:
                     •   The nature and level of damage to shelter across the country, and
                     •   What disaster survivors intended to do to address their immediate shelter needs3.

               The assessment tool was launched by the Shelter Cluster on 31 October 2008 following a number
               of reviews and field tests. The results are expected to be available by mid-November.

          3. Rapid Field Assessments:
               Field assessments were conducted in the southwest (Les Cayes, southwest coast to Les Anglais),
               and south center (Jacmel, Marigot and points east) of Haiti as well as to Gonaives (two trips). The
               trips to the south and southwest were intended to more directly ascertain the nature of damage
               caused by the four storms and specifically impacts on the environment and shelter. The Gonaives
               assessment was to advise on shelter issues in the town and test the Shelter Checklist. Summary
               details are provided below, with more extensive field notes provided in Annex D.

               a.	Gonaives
                     i. Shelter Checklist
                     Shelter Checklists were completed for two temporary shelter sites in Gonaives with the
                     assistance of IOM/Gonaives staff (see Annex D, Gonaives Emergency Shelter and Environment
                     Checklist Review). Each checklist took less than 45 minutes to complete through interviews
                     with site managers, including introductions and limited walk-through of the site. The IOM
                     counterpart for the use of the checklists felt that he could conduct similar assessments in
                     the future.

          2 It was reported that the IFRC was conducting household-level assessments, but this information was not available to the
          Cluster at the time of the field work.
          3 French and Creole copies of the assessment form can be found at http://groups.google.com/group/emergency-shelter-
          haiti/files .

2
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                                      Shelter Checklist Review/Gonaives - 30 October 2008

           ii. Provisional Shelter
           A pressing issue in Gonaives was the departure of displaced from schools and other
           institutions as the government (and presumably many site owners) wanted to return these
           locations to their normal function. An option proposed was the creation of tented camps for
           the displaced, to which the displace would be moved as quickly as possible. Two tent camps
           were visited and found to be inadequate (see Annex D).
           During discussions in Gonaives it was noted that there was no accurate information on who
           was in the temporary shelters and why they were remaining in these locations (which in
           most cased were poorly served with basic services). Suggestions to better understand the
           reasons behind the continued need for temporary shelters were later implemented in the
           form of a rapid assessment of the shelter sites to better understand why they remained open
           and under what conditions occupants would return to their normal homes.
           It was also noted that the shelter assistance effort in Gonaives did not have an exit strategy
           to return people to their normal housing as quickly as possible and to minimize medium
           term transitional shelter needs. This point was discussed with staff in Gonaives and the
           Shelter Coordinator, leading to a call for additional technical assistance on shelter issues for
           the Cluster4.

           iii. Waste management
           Shortly after the flooding in Gonaives (the second time in 4 years), the WASH Cluster
           requested technical assistance on management of the waste generated. This request was
           later stopped, with UNDP taking over the coordination of the clean-up, an effort which saw
           considerable government and NGO involvement.
           As confirmed with Andrew Morton (UNEP expert working in the post disaster needs
           assessment and asked to review the waste/debris issue in Gonaives), much of the initial
           waste material in Gonaives was composed of silt carried into the city by the flooding. This soil
           was cleared from streets and public areas and disposed outside Gonaives at a “least worst”
           location (see Annex D)5.
           However, once clearing and cleaning of buildings had begun, the proportion of household
           and potentially hazardous waste items in the overall waste stream increased. This changing
           nature of the clean-up waste was not being taken into account in the collection and disposal
           of the waste.
           It is unfortunate that waste management experts were not present at the beginning of the
           Gonaives clean-up operation. The initial clean-up, largely involving the removal of silt from
           roads, wasted considerable resources by dumping this material outside the city and not
           using it for more productive uses (e.g., flood barriers, flood evacuation mounds). Similarly,
           the failure to adjust collection procedures to the changing nature of waste once household
           and other debris became part of the stream, may result in unnecessary future environmental
           damage.

4 This assistance was to arrive o/a 17 November 2008 as a secondment to the Shelter Cluster from CARE International.
5 There was a view expressed that the river silt in the city was (severely) contaminated by contaminants, but this view was
not based on testing. Logically, the volume of flood waters and silt was probably so large as to make a widespread high level
of contamination unlikely. Simply put, the flood waters probably washed most contaminants into the sea or diffused them
across the environment.

                                                                                                                                3
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

Shelter Checklist Review/Gonaives - 30 October 2008

               b.      Southwest
                     Very limited wind damage was reported, with most damage caused by local flash flooding
                     or, in the case of Les Cays, river flooding6. Reconstruction would not likely pose significant
                     additional resource demands on the environment as materials from damaged/destroyed
                     buildings could be salvaged for rebuilding or were in excess supply locally (e.g., river stone
                     for walls). Conditions in designated shelters which were visited in Les Cayes and Cavallion
                     were below Sphere Standards and posed significant environmental issues. (None of the
                     shelters were in use at the time of the visit). Little in the way of shelter-related assistance was
                     reported to have been received in the region.
               c.      South Center
                     Localized wind damage was reported, but the most significant damage agent appears to
                     have been flooding. Relatively little shelter assistance was reported. Damage was severe
                     (destroyed buildings or buildings which had been inundated with floor waters and sediment)
                     but localized. Salvaging materials from damaged homes is possible, but some new resources,
                     particularly timber and zinc, are likely to be needed. Environmental damage from flooding
                     may be significantly greater than from harvesting local resources for rebuilding, particularly
                     since stones are widely available for repairing damaged walls.

          4. Briefings on Environmental Issues:
               Three briefings on environmental issues were provided to Shelter Cluster (twice) and WASH
               Cluster meetings in Port au Prince. Copies of the briefings can be found in Annex E.

          5. Interaction with the Early Recovery Cluster/Post-Disaster Needs Assessment:
               A joint Government/UN/WB/Humanitarian Community post disaster needs assessment was
               underway during the field work. Periodic discussions were held with the Shelter Cluster
               Coordinator, the UNEP staff person involved in the assessment and several assessment participants
               on the integration of shelter-and-environment concerns into recovery planning. However, there
               was a lack of clarity as to the boundary between Shelter and Early Recovery efforts with respect
               to post-emergency assistance, with transitional/temporary shelter efforts at time apparently
               considered as part of the Shelter or Early Recovery Clusters. Raising environmental concerns in
               this confusion was difficult.

      Results

          The results of the field review are divided into two parts, the first dealing with accomplishment of
          the ToR and the second with issues related to the process of providing an Environment Advisor to an
          operational Shelter Cluster.

          Terms of Reference
               Accomplishments under the ToR included:
                    1. The provision of environment-related shelter information to Cluster members (i.e., the
                       Environment-Shelter CD),

          6   Wind is normally a significant damage agent for hurricanes.

4
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                                   Shelter Checklist Review/Gonaives - 30 October 2008

         2. Environmental issues raised at Cluster meetings and in discussions with individuals
            involved in shelter activities,
         3. Practical advice to Cluster members on needs assessments and waste management.
         4. Advice on development of shelter plans in Gonaives.
         5. Advice on developing an understanding of environmental issues related to the provision
            of short and medium term shelter.
         6. Testing of the Shelter Checklist in Gonaives.

     At the same time, the work was not fully successful in several areas. A review of environmental
     policies or tools used by the Shelter Cluster was not possible as, aside from the Checklist test, no
     such tools or policies were in use during the field work and the Checklist was not adopted for use
     by Shelter Cluster members.
     Further, although the Shelter-Environment Toolkit was made available and promoted with Shelter
     Cluster members, there is no evidence that the Toolkit was use by any member. As a result, it was
     not possible to collect feedback on the utility of the Toolkit.
     No modifications were made to existing tool. It was noted that a short review checklist could be
     useful to review the environmental impact of proposed transitional shelter interventions. This
     checklist would assess the impact of the resources inputs for a project and outline ways to limit
     negative impacts. However, this new tool was not developed as there were no shelter project
     descriptions available for review.
     Overall, four issues limited accomplishment of the ToR. First, the Shelter Cluster was not as advanced
     as expected in terms of the collection of damage/needs assessments and shelter planning (e.g.,
     establishment of common shelter assistance packages or plans to provide assistance to all the
     affected populations). This meant that basic information about post-disaster shelter conditions
     was not available, thus limiting the possibilities to conduct environmental reviews of disaster
     impact and response plans7.
     Second, most emergency shelter attention was focused on Gonaives, and to a lesser degree
     areas near St. Mark. Most of the relief effort in Gonaives was focused on clean-up, an effort
     being managed by the Early Recovery Cluster, but with significant involvement of shelter-sector
     actors.
     It appeared that shelter issues were managed on an ad hoc basis and subsidiary to the clean-
     up, rather than the clean-up being a step in the process of addressing shelter needs. The lack
     of an overall shelter plan for Gonaives made it difficult to define and address shelter-related
     environmental issues related to providing adequate shelter. (The decision of UNDP to not follow-
     through on the WASH Cluster request for technical assistance on waste management led to a
     clean-up effort which was largely ignorant of the resulting negative environmental impacts.)
     The focus on Gonaives also meant that other areas of Haiti which suffered shelter losses
     received little assistance. The lack of assessments (as noted), shelter plans and organizations
     providing assistance in the other parts of Haiti significantly limited the options for defining and
     understanding disaster-related environmental impacts and to define environmentally positive
     responses.

7 The lack of one or more technical shelter specialists in the Haiti Shelter Cluster probably contributed to the lack of
damage/needs assessments and the slow development of common shelter packages. A technical specialist was deployed in
late November, but with a mandate limited to transitional shelter in Gonaives.

                                                                                                                           5
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

Shelter Checklist Review/Gonaives - 30 October 2008

               Third, the division of responsibilities for transitional shelter between the Shelter and Early
               Recovery Clusters was not clear. At one point, it appeared that the Early Recovery Cluster would
               take responsibility for transitional shelter, although later this responsibility was apparently passed
               back to the Shelter Cluster. Assessing and planning appropriate responses to environmental
               issues is a challenge when it is not clear which Cluster has responsibility for coordinating the
               underlying assistance effort.
               Finally, NGO participation in the Shelter Cluster (and in overall shelter assistance) appears to have
               been limited. IOM appeared to be the dominant shelter assistance provider in terms of funding
               and operations. (Some organizations appeared to attend Shelter Cluster meetings in search of
               IOM funding and the perception that Shelter Cluster meetings were actually IOM meetings may
               have limited involvement of some NGOs.)
               CRS, Habitat for Humanity, and IFRC/Haitian Red Crescent were reported to be involved in shelter
               activities. However, they did not appear to be active participants in the Shelter Cluster based
               on the meetings attended during the field work and from information provided by the Shelter
               Cluster Coordinator8. The weak participation in Shelter Cluster coordination and information
               sharing efforts reduced the effectiveness of the Shelter Cluster, as well as limited the use of
               the Shelter Cluster as a base for incorporation of environmental issues into emergency and
               transitional shelter operations.

          Environment Advisor Posting
               There was initial confusion over the incorporation of an Environment Advisor into the Shelter
               Cluster coordinating structure. These issues were worked out quickly and the support provided
               on the ground in Haiti was excellent.
               There was also a lack of clarity in task allocations and reporting once the (initial) Shelter Cluster
               Coordinator left country and her position was assumed by an individual also handling operational
               management of agency-specific relief operations. As learned from previous Cluster operations,
               the “co-hatting” of an individual with Cluster Coordination and operational responsibilities will
               negatively impact cluster operations.

          Recommendations
               1. The terms of reference and length of assignment of a Shelter Cluster Environment Advisor
                  need to take into account the level of development of a field Cluster operation. If needs/
                  damage assessments have not been undertaken and/or if assistance plans (including
                  common shelter packages) have not been developed, the Advisor will need to either
                  contribute to developing these materials as a prerequisite for further work specifically on
                  environmental issues, or defer field work with the Cluster until (at the least) assessments
                  have been completed.
               2. The role of the Environment Advisor within the Shelter Cluster Coordination Team needs to
                  be clear. This is particularly necessary where a Cluster Coordinator is also responsible for relief
                  operations, a situation where experience indicated that the division (and potential conflict)
                  between broad Cluster issues and agency-specific operational issues can be problematic.
               3. The Environment Advisor needs to take a more proactive and take on a stronger advocacy
                  roll with respect to environmental issues, including out-reach to agencies involved in shelter
                  assistance actors who are not fully participating in the Shelter Cluster.

          8   IFRC participation in meetings increased with the arrival of shelter unit staff from Geneva.

6
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                      Shelter Checklist Review/Gonaives - 30 October 2008

4. Procedures for reporting to the Global Shelter Cluster need to be clarified, if only to limit
   appearances that Environment Advisor is inappropriately sharing information about Cluster
   operations, or on individual Cluster members, outside the local Cluster management.
5. Responsibility between Clusters for transitional shelter needs to be defined early, and clearly,
   so that it is clear which Cluster is responsible for environmental issues related to transitional
   shelter.
6. Consideration should be given to developing an additional checklist focusing on assessing
   the environmental impacts of shelter assistance packages. This (short) checklist could be
   built off of the work by the Shelter Centre on classifying shelter sector inputs
   (Shelter Sector Items, see http://www.sheltercentre.org/sites/default/files/Shelter%20
   Sector%20Items%20PART%20DRAFT%20Nov%202008.pdf

                                                                                                       7
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

                                                               Annexes

      Annex A – Terms of Reference
      		        Haiti Terms of Reference Field Review of Emergency
      		        Shelter-Environment Toolkit

      Background

          Disasters are often associated with environmental damage from the impact of the disaster event
          itself, as the result of poor pre-disaster environmental conditions or from the impact of relief and
          recovery activities. Unfortunately, avoidable environmental damage still occurs despite knowing how
          to prevent or minimize this damage. This outcome generally occurs because of:
                 1. A lack of dedicated technical support at the disaster site to provide practical guidance on
                     how to minimize of avoid negative environmental impacts,
                2. A weak application of existing policies on environmental issues and disasters and/or,
                3. A lack of access to tools to assess and address negative environmental impacts associated
                   with relief and recovery activities.
          Recognizing these limitations, the Global Emergency Shelter Cluster commissioned the development
          of tools and capacities to more effectively identify and address post-disaster shelter-related
          environmental issues. This effort, being implemented by ProAct Network and CARE International with
          funding provided by the Global Emergency Shelter Cluster, focuses on three activities:
                1. Developing a set of policies and tools which can be used in the post-disaster provision of
                   shelter to minimize immediate and long term negative environmental impacts9.
                2. Creating a cadre of environmental experts who can serve as environmental advisors in
                   emergency shelter operations and use the policies and tools developed.
                3. Developing training materials to reinforce the capacities of the shelter-and-environment
                   experts (and others as the occasion may arise) to better assessment emergency shelter
                   related environmental impacts and assist in the implementation of shelter relief and recovery
                   activities which have the least possible negative impact on the environment.
          A toolkit of policies and tools based on the experiences of a number of disasters has been developed
          under the first activity. This toolkit requires a field review to both validate the materials developed to
          date and gain greater understanding as to how the existing tools can be used in different disasters,
          and whether any additional tools which may be needed.

          9    Note that shelter here is used in the broad sense and includes physical protection from weather and other natural and
          social hazards, the water, sanitation and hygiene needed for a minimally adequate life and the basic livelihoods activities
          associated a minimally adequate level of life and wellbeing.

8
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                  ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

Haiti Field Review

  As part of the project support to the Global Emergency Shelter Cluster, the Haiti Field Review will
  focus on the application of existing Shelter-Environment Toolkit items in the recent hurricanes and
  floods which have affected the country. This review will involve:
       1. 1. A mapping of relief/recovery and environmental stakeholders involved in the hurricane/
          flood response in Haiti.
       2. 2. A review of any applicable environmental policies or tools used by the Shelter Cluster
          response to the floods/hurricanes.
       3. 3. Awareness raising about the existing Shelter-Environment Toolkit as it applies to Haiti.
          (This awareness raising will be through the Shelter Cluster or directly with humanitarian
          personnel, as circumstances allow).
       4. 4. Use of items in the Shelter-Environment Toolkit through the Haiti Emergency Shelter
          Cluster in the context of relief and recovery activities in Haiti.
       5. 5. The collection of stakeholder feedback as to the utility of the items included in the Shelter-
          Environment Toolkit. (“Success” of the toolkit items will be assessed based on their perceived
          utility of the tool by shelter sector and environmental stakeholders.)
       6. 6. Modification of existing tools, or development of new tools, to respond to specific shelter-
          environment needs in Haiti.
  While the prime focus of the Haiti Field Review is to demonstrate, review and refine the existing
  Shelter-Environment Toolkit, this work is expected to be accomplished in the context of direct
  involvement in Shelter Cluster activities to the extent permitted by Cluster members and operational
  considerations.
  It is recognized that emergency shelter-related activities may have transitioned from immediate
  relief to transitional shelter and recovery. The application of the toolkit will take this transition into
  account. If requested, assessment outputs from the field review will be provided for consideration in
  the development of post-disaster recovery and reconstruction planning.

Schedule

   The tentative schedule for the field review is as follows:
            •   7-8 October: Consultations in Geneva with IOM, CARE, UNEP, IUCN, OCHA and others on
                the field review.
            •   14 October: Arrival of consultant in Port au Prince
            •   14-16 October: Briefings with key Shelter Cluster members and other stakeholders.
            •   17-21 October: Field application of Shelter-Environment Toolkit, including field
                assessments and development and application of new/modified tools.
            •   22 – 25 October: Briefings and review of use of the Toolkit.
            •   26 October: Departure
            •   9 November: Draft report on review provided to stakeholders.

                                                                                                               9
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

      Logistics Support

          The consultant will have funds to cover per diem, communications and local travel costs. Haiti
          Emergency Shelter Cluster members are requested to provide:
               1. Administrative support (lodging reservations and other local support arrangements).
               2. Security briefing and security support, as required by local condition.
               3. Assistance in securing transport and travel to field sites.
               4. Assistance in making contacts with Government and humanitarian actors, including the
                  United Nations, USAID and other parties involved in shelter, environmental or related
                  activities. (Note that some preliminary contacts will be made during the visit to Geneva, and
                  a list of possible contacts will be provided before the consultant arrives in Haiti.)

      Annex B – Map of Haiti

          (Note: Hurricane Ike passed north of Haiti, but resulted in heavy rainfall in the northern part of the
          country.)

10
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                            ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

Annex C – Schedule of Activities

      Date
                                                       Activity
 (October 2008)

                     Meeting with IOM/Geneva (Ricio Sanz)
       7
                     Briefing on Haiti Assignment with ProAct Network staff
                     Review of ToR with ProAct Network
       8
                     Briefings with CARE and UNHCR
      14             Arrival in Port au Prince
                     Briefing with IOM: Mary Giudie (Cluster Coordinator) and Emmanuelle Laloum
                     (Cluster Information Officer)
                     Briefings on Shelter Cluster activities and development of draft damage/
      15             needs assessment tools. HRC/IFRC/Oxfam meeting on “emergency markets”.
                     Participation in Early Recovery/PDNA meetings.
                     Shelter Cluster meeting/briefing on environmental issues. Discussions on
      16
                     needs assessment and work plan. Depart PaP.
                     Return to PaP. Cluster meeting, review of needs assessment form and process.
      20
                     Briefing with IOM Country Director Vincent Houver.
      21             Field trip – Gonaives
                     Gonaives, Gonaives-PaP travel, review of Gonaives field work, UNICEF/WASH
      22
                     meeting.
      23             Shelter Cluster meeting. Drafting of Gonaives reports.
      24             Travel to Les Cayes. Field visits to shelter sites in Les Cayes and Cavallion.
      25             Field visit to Southwest Coast
      26             Report drafting
                     Travel to PaP, briefing of IOM, onward travel to Jacmel and travel east of
      27
                     Marigot.
      28             Travel to PaP. Presentation to WASH Cluster.
                     Travel to/from Gonaives for application of Shelter Checklist. Shelter Cluster
      29
                     meeting.
                     Report drafting, briefing with Cluster Coordinator, Meeting with Handicap on
      30
                     waste management.
                     Report drafting, handover and exit briefing with Cluster Coordinator. Depart
      31
                     PaP.

                                                                                                      11
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

      Annex D – Field Notes
          		             Prepared by: C. Kelly10, ProAct Network/Haiti Shelter Cluster Environmental Advisor

      Notes on Gonaives Visit, 21-22 October 2008

          The following notes cover a field trip to Gonaives on 21 and 22 October to review environmental
          issues related to the shelter cluster response to the flooding of the city by Hurricane Hanna. The notes
          are for discussion and are solely the views of the author.
                1. Little flooding or wind damage was noted on the road from Port au Prince to Gonaives, with
                   the exception of flood damage to one bridge near Augier. (Wind damage would be expected
                   from a hurricane, but this does not appear to have been a problem in the areas traveled.)
                2. Large areas of Gonaives remain covered by deposits from flooding with depositions over
                   1 meter in some locations. Most of the deposited material appears to be relatively uniform
                   clay, with few stones/boulders or organic matter noted.
                3. This deposit needs to be removed from roads, drainage systems and housing areas, schools
                   and commercial locations to allow people to move back into their homes and resume normal
                   activities.
                4. Official clean-up operations are underway with a focus on clearing roads and schools and (it
                   appears) some houses.
                5. Private house/building owners are clearing household debris and clay deposits and placing
                   these materials in roadways for removal.
                6. It is unclear if some or all house cleaning is taking place with government funding, and how
                   decisions are made as to which houses are to be cleared.
                7. Clearing soil/debris is an Early Recovery Cluster task although Shelter Cluster members (e.g.,
                   IOM) are involved.
                8. Links between Early Recovery, Shelter and WASH Clusters on debris management are not
                   clear, although the clean-up process is moving forward on a daily basis.
                9. Household debris is being added to the flood deposited soil from cleaned houses, increasing
                   the hazardousness (i.e., potential for contamination) of the debris and dumping site11.
                10. Within the flood debris are a number of vehicles, which are likely to be unrecoverable and
                    increase the hazardousness/contamination of the dump site.
                11. It can be expected that more waste from households will be dumped on roadways for clean-
                    up as access to homes becomes possible due to (initial) road clearing. In other words, there
                    will be a need to clear most roads at least twice, once to open the roads and again to clear
                    the debris from within houses.

          10 Email: 72734.2412@compuserve.com
          11 Comments from Morton/UNEP indicate that the dump site, west of Gonaives near a tidal flat, is the least worst option for
          fast disposal of the largely clay sediments deposited by the flood, but see point following on waste composition.

12
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                          ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

      12. In discussions with Morton/UNEP (who also looked at the soil disposal/waste issues), it was
          noted that it may be too difficult to remove most of the organic/hazardous materials from the
          cleared soil/debris combination due to the viscosity of the clay when we, and the solidness
          of the clay when dry.
      13. However, it may be possible to recover and recycle vehicles and other “white goods”, such
          as computers and appliances, either through a separate collection process or separation at
          the dump site.
      14. Elements of a complete shelter response plan, with the goal of getting people back to their
          homes, exist for Gonaives, but an overall analysis of the current shelter situation (e.g., who
          has not returned to their homes and why), needs and gaps, and way forward, appear to be
          lacking.
      15. Considerable pressure exists to move a reported 23,000 displaced out of schools, with tents
          proposed (or already used) as a “solution”.
      16. The local Dept. of Education would like to re-open all schools by 10 November, implying that
          all IDS should be out of the schools by this date.
      17. There is agreement that no IDP will be forced out of shelter, but there are also suggestions/
          action taken to move IDPs from schools to tents.
      18. While moving the IDPs to tents “solves” the problems for schools, it does not result in people
          moving back to their homes.
      19. Some IDPs have moved into tents in a transitional shelter site (i.e., “Eben-ezer” site). The site
          is transitional because IDPs cannot move back to their flooded homes, but will/want to when
          the Savanne Jonc/Savanne Desole lake level drops. (The lake grew with run-off from the
          floods.)
      20. Eban-ezer site and services are far below minimum standards. There is significant
          overcrowding (approx. 225 families for 45 tents). Residents cutting wood for shelter at the
          site, and there are other clear unmet needs for minimum shelter in a hot (+38c) environment
          at risk of flooding. Residents have little option other than cutting local vegetation for shelter
          and other needs if additional assistance is not provided to meet minimum standards for
          shelter and other needs (e.g. latrines, sustainable water, waste management, etc.)
      21. Because the Eben Ezer site needs to continue in operation for up to 2 years (the estimated
          time it may take for the lake level to retreat sufficiently for all site occupants to return to their
          homes), a longer term/comprehensive approach to transitional shelter is needed.
      22. There appears to be agreement that clearing home sites of debris, and clearing roads to get
          access to home sites, is important in returning people to their homes, and in moving people
          out of the shelters.
      23. There does not appear to be a clear plan on what to do with IDPs who are too poor to clean
          their houses (i.e., the classic vulnerable groups12), who have had their homes destroyed or
          who rent, and thus cannot move until rental property is available.
      24. A possible outcome of the current situation is for the less well endowed IDPs to remain in
          worsening environmental conditions (e.g., overcrowded, poorly services camps in at risk
          locations) as relief assistance peters out 13.

12 Note, this is a protection as well as Shelter and cross-cutting (e.g. age) issue.
13 Also a protection issue.

                                                                                                                    13
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

               25. It is hard to assess the future environmental impacts of the IDP situation without
                         a.      Knowing why people are in shelters,
                         b.      Having a plan for moving IDPs back to their homes, and
                         c.      Clearly defining how to deal with the classic vulnerable populations, and those
                                 who need new housing or rental housing.
               26. While the focus of discussions during the field visit was on IDPs, there are possibly a greater
                   number of flood-disposed who are living with host families and for whom the issue of cleared
                   roads and house cleaning are also critical for a return to their normal living situation.
               27. To assess the environmental impacts of re-sheltering flood-displaced in Gonaives, it appears
                   necessary to:
                       a.     Understand why people remain in the shelters,
                       b.     Develop a plan for addressing these reasons and,
                       c.     Assess the environmental impacts and impact minimization options available.
                    This plan would likely focus on:
                              • Clearing access (on-going)
                              • Clearing house locations (inside and out) of debris (partially on-going)
                              • Providing special assistance to families who cannot afford to clear their homes
                                 for re-occupation.
                              • Plan and properly develop transitional shelter sites for IDPs who cannot move
                                 back to their former house sites in the near term.
                              • Provide on-site transitional shelter (following site clearance) where houses
                                 have been destroyed or need significant rehabilitation. (Both rehabilitation
                                 and reconstruction may be covered as part of early recovery activities.)
               28. An operational flood warning system is necessary for existing and new IDP sites. Such
                   a warning system would partially address the use of tents in during the remainder of the
                   hurricane season. (It is understood that a warning system does exist for Gonaives as a whole,
                   but this could not be verified.)
               29. There appears to be little direct action to reduce the risk posed by flooding to Gonaives and
                   the surrounding areas (e.g., Eban Ezer).

      Southeast Trip Notes (27 Oct 2008)14

               1. More damage appears to have occurred in Southeast than in Southwest.
               2.    Local conversations indicate a combination of flooding and wind as caused of damage tov
                     shelter.
               3. Little shelter assistance appears to have reached areas.
               4. Also a need for clean-up of locations such as Marigot.
               5. People from destroyed/severely damaged houses are reported to be living with neighbors/
                  relatives.

          14 Disseminated by email on 28 Oct 08 to Judy Dacruz, (Acting Shelter Cluster Coordinator, IOM Haiti) Emmanual – (Cluster
          Information and Reports Officer, IOM Haiti), David Stone (ProAct Network) and Karen Walker (ProAct Network)

14
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                 ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

      6.   Large scale debris flows noted in some areas, but these may be more of one-off events.
      7.   Flooding also occurred in lower areas of Jacmel, but this is also likely a recurrent event.
      8.   Housing in flood areas subject to recurrent risk.
      9.   Displaced who where in schools were told to leave when the schools opened. Where these
           populations are at present is not clear. However, it does not appear that they have begun
           rebuilding.
      10. Most damage noted was from flood debris (mud, rocks, ect.) in houses and damage to walls
          from flood waters/debris.
      11. Some damage noted in upper reaches of rivers (e.g., Peredo), which may indicate that flood
          damage is not only located along the coast.
      12. Local coordination capacity exists, but there is no shelter cluster leader, not did it appear many
          NGOs involved in shelter activities. (Plan is reported to be planning a kitchen kit
          distribution.)
      13. Local DPC contact reported that they have more detailed assessment reports and have made
          them available to local NGO offices.
      14. Shelter/reconstruction impacts on the environment are unclear as there is no overall
          assessment of damage, assistance provided and planned, and local recovery plans are not
          known.
      15. Appears that shelter activities in the South East need to be better coordinated with assistance
          allocations made in PaP and transitional shelter assistance increased.
                                                                                                  Regards,
                                                                                                         Kelly
                                                   ProAct Network/Shelter Cluster Environment Advisor

Gonaives Emergency Shelter and Environment Checklist Review

  Introduction
      This report covers rapid assessments of shelter conditions in Gonaives using the Emergency
      Shelter Environmental Impact Assessment and Action Checklist (the “Checklist” – see http://
      www.benfieldhrc.org/disaster_studies/rea/checklist_guides.htm). The Checklist is part of
      an environmental toolkit developed for use by Shelter Cluster members in emergency and
      transition shelter operations. The focus of the Checklist is on defining environmental issues from
      an operational perspective with the expectation that improving environment-related conditions
      also improves the overall provision of emergency shelter.

  The Assessments
       The assessments were conducted on 29 October 2008 at two locations in Gonaives, Praville
      Camp (a new tent site outside Gonaives with approximately 190 families resident) and Saint
      Valarie Public School (725 residents), located in the center of Gonaives. IOM assisted in selecting

                                                                                                                 15
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

              the sites, with contacting site management authorities and in translations. The questions in the
              Checklist were translated orally into French by the author and, where necessary, retranslated
              into Creole. In most cases, the questions in the Checklist generated more extensive discussions
              on the operations of each shelter site. This additional information was passed on to IOM staff in
              Gonaives.
              It is worth noting that the Praville camp is a new site in the process of being developed. The Saint
              Valarie site is normally a school, and is expected to be close as a shelter in the near future. As a
              result, the assessment results for
                  •   Praville indicate actions which are needed to improve the camp, and for
                  •   Saint Valarie indicate actions which are needed to bring this temporary shelter site up to
                      minimum standards if the site is to be used in the future.

          Summary of Results
              The following lists present the issues identified for each site. The issues are prioritized based on
              whether they pose:
                  1. An immediate threat to human life,
                  2. A threat to livelihoods or
                  3. A threats to the environment.
              Note that threats to human life or livelihoods usually also include a threat to the environment.

              Praville Camp
                  •   The site facilities should be reviewed to ensure they meet Sphere Standards.
                  •   A plan for the evacuation of the camp in the case of a hurricane threat is required.
                  •   A fire safety plan is required.
                  •   Steps need to be taken to lessen the impact of flash flooding and landslides on the camp
                      site, as well as effective draining of rain and waste water.
                  •   A sustainable source of water needs to be provided.
                  •   Plans, installations and procedures need to be put in place for the management of
                      latrines/sewage and (human and clothes) washing sites and disposal of the resulting
                      waste.
                  •   Plans, installations and procedures need to be put in place for the management and
                      disposal of solid waste.
                  •   Seismic safety measures should be incorporated into the construction of fixed or semi-
                      fixed facilities in the camp (e.g., clinic, camp office, school).
                  •   Steps need to be taken to ensure that camp residents are safe from traffic accidents on
                      the road which passes in front of the camp.
                  •   The use of the site as a camp needs to be officially established.
                  •   Consultations are needed with populations inhabiting the camp on the management of
                      the site.
                  •   Consultations are needed with populations neighboring the camp on the management
                      of the site.
                  •   Tents in the camp need to be reoriented to take advantage of natural ventilation and
                      reinforced to limit the impact of high winds.
                  •   Procedures should be put in place to repair shelters/tents and to improve the living
                      environment of the camp.

16
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                       ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

   •   Sustainable fuel sources and fuel efficient stoves need to be provided to camp
       residents.
   •   Construction in the camp should minimize the volume of resources used and, where
       possible, use renewable resources.
   •   Where possible, rainwater harvesting should be incorporated into building design.
   •   Further construction at the camp should minimize the removal of vegetation.
   •   Steps should be taken to limit air and water pollution from the camp.
   •   A system for monitoring environmental conditions in and near the camp should be
       established.
   •   A decommissioning plan for the site is needed and should include steps to recycle and
       reuse the resources in the camp

Saint Valarie Public School
   •   Steps need to be taken to ensure that camp residents are safe from traffic accidents on
       the roads which pass in front of the site.
   •   The site facilities should be reviewed to ensure they meet Sphere Standards.
   •   Provisions should be put in place for standards-compliant provision of shelter at the
       school.
   •   A site management plan is required.
   •   A sustainable supply of potable water for the site is required.
   •   A flood response plan, including warning and evacuation should be developed for the
       site.
   •   A fire safety plan is required.
   •   Plans, installations and procedures need to be put in place for the management of
       latrines/sewage and (human and clothes) washing sites and disposal of the resulting
       waste.
   •   The current 6 place latrine needs to be cleaned and properly maintained.
   •   Regular cleaning of the site and appropriate disposal of waste is required.
   •   Plans and procedures need to be put in place for the management and disposal of solid
       waste.
   •   Consultations are needed with populations inhabiting the camp on the management of
       the site.
   •   Consultations are needed with populations neighboring the camp on the management
       of the site.
   •   Sustainable fuel sources and fuel efficient stoves need to be provided to camp
       residents.
   •   The seismic design of the school building needs to be reviewed to ensure it meets
       appropriate standards.
   •   Rainwater harvesting should be incorporated into building design.
   •   The drainage from the school yard needs to be improved.
   •   A system for monitoring environmental conditions in and near the camp should be
       established.
   •   Provisions need to be made for repairs to the school after it has been used as a shelter.
   •   A plan for closing the shelter site and transitioning back to the normal function as a
       school needs to be developed.

                                                                                                   17
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

          Detailed Results
               The following tables list the issues which were identified as not being adequately addressed from
               an operational or environmental perspective for each location based on the Checklist questions.
               The tables include a description of the issue as well raised as the general type of remedial actions
               which are needed. Additional and more specific guidance on addressing the issues identified can
               be found in the original assessment form (see http://www.benfieldhrc.org/disaster_studies/rea/
               checklist_guides.htm).

                                  Emergency Shelter Site Selection Checklist
        (To be completed before a site is chosen for use as a shelter site, or when reviewing an existing site.)

                                        •   Person/s Completing the Checklist: C. Kelly
                                        •   Date: 29 Oct o8
                                        •   General Location (e.g., District): Gonaives
                                        •   Specific Location: Praville Camp

                             Question                              Answer                    Guidance

        Has the community near or surrounding the site
        been consulted about the site selection?                                 Communities near or surrounding
                                                                     No         the site should be involved in the
        Consultation with the community near a shelter site                     site selection process.
        is important in minimizing conflict over resources.
        Have the prospective site inhabitants been
        consulted about the site and types of shelter to                        Prospective inhabitants of a
        be constructed?                                                         transitional shelter site should be
                                                                     No
        The resources and effort made to establish a site                       involved in the site selection and
        will be wasted if the prospective inhabitants are                       shelter design process.
        not willing to use the site.
                                                                                Seismically active or volcanic zones
                                                                                should be avoided is possible. If
        Is the site located in an area subject to earthquakes,       Yes        these sites must be used, then
        or other geological hazards?Although earthquakes                        seismically resistant construction
        and similar events can be rare, establishing             Construction   should be used in all construction
        settlements in at risk sites can increase the risk of    non-seismic    activities, and early warning systems
        future disaster for the disaster survivors.                (tents)      established (with strong community
                                                                                participation) from the initial
                                                                                planning of the site.

18
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                     ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

                     Question                                Answer                     Guidance

                                                                           Flood-vulnerable sites should be
                                                                           avoided. When such sites must be
Is the site located in an area subject to flooding?                        used, then provisions for raising
                                                               Yes         ground level under structures,
Flooding can come from rivers/streams, lagoon
overflow, heavy rains and poor drainage, or from          Flash flooding   drainage and protective dikes
sea waves, e.g., at high tide or during storms. Note        from local     are necessary. Such interventions
that sites should have a slope of 2 to 4% to facilitate       rainfall     may need to be removed during
natural drainage.                                                          decommissioning. A local flood
                                                                           warning      system     should     be
                                                                           established.
                                                                           Landslide and erosion prone
                                                                           sites should be avoided. If not
Is the site subject to landslides or heavy                                 possible, natural vegetation should
erosion?                                                                   be maintained in the landslide-
Sites with a slope of more than 10% may be prone                           vulnerable slopes and throughout
                                                               Yes
to severe erosion. The steeper the site the more                           the site, the site should be terraced
likely landslides will occur, particularly during the                      to limit run-off, and structures
monsoon.                                                                   should not built on landslide-prone
                                                                           slopes. A local landslide warning
                                                                           system should be established.
Is there potable water available on a sustainable
basis for the site?                                            No
                                                                           A site should not be selected until a
The water can come from wells, stand pipes, bowers/          Efforts       sustainable source of potable water
tanks or other sources. “Sustainable” means that          underway to      is available.
15 liter of potable water per person per day will be        address
available throughout the life of the shelter site.
                                                                           Sites should not be located within
                                                                           50 meters of main roads. If such
Is the site located near a major road with heavy                           locations cannot be avoided, the
traffic?                                                                   site area nearest the road should be
Shelter sites in these locations expose inhabitants            Yes         allocated to non-residential/non-
to air pollution and well as an increased risk of                          school activities and barriers should
accidents.                                                                 be placed along the road side of
                                                                           the site to reduce the chance for
                                                                           accidents.
Are the cooking fuels used by the shelter
inhabitants available at the site without requiring
unsustainable harvesting of local natural                      No
                                                              Identify the cooking fuels to be used
resources?                                                    as the site and plan for adequate
                                                     Plans to
Note that women are often responsible for provide cooked supplies which do not overtax local
collecting fuel. The more time, cost or effort        meals.  resources.
involved in collecting fuel, the less time for other
recovery tasks.

                                                                                                                   19
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

                            Question                            Answer                   Guidance

        Are fuel efficient stoves available, and are users
        familiar with the proper operation of these
        stoves?                                                             Incorporate the provision of fuel
                                                                  No        efficient stoves and training in their
        Properly used fuel efficient stoves reduce demands                  use into site management plans.
        on the environment. Different types of stoves may
        be needed depending to domestic activities.
        Is there a clear and legally established agreement
        to use the shelter site?
        This agreement can be in the form of government         No
        decree, lease or other legal arrangement.                           No site should be selected without
                                                           Government       a legal agreement for use and
        Agreement terms should cover (1) land
                                                          decision to use   decommissioning.
        ownership,(2) the conditions for the use of the
                                                               land
        site, (3) decommissioning of the site and (4) any
        payments or services due during the occupation or
        decommissioning of the site.
        Does the site physical plan meet the requirements
        set out in Sphere?                                                  Review and incorporate appropriate
        All site plans should comply with the appropriate                   Sphere standards into the site
                                                                  No
        Sphere standards, including having sufficient space                 plan (see the Sphere web site for
        for social activities and be based on consultations                 information on Sphere).
        with the site users.
        Does the shelter site plan reference a larger area                  Determine whether the site plan
        spatial plan, if one exists?                                        can be adjusted to fit the larger
                                                                  No
        Where possible, shelter sites should not conflict                   plan, or if a temporary modification
        with long term development spatial plans.                           is needed.
        Has the removal of existing trees and vegetation
        been minimized?
                                                                            As much existing vegetation should
        Leaving as much vegetation as possible reduces            No
                                                                            be left on the site as possible.
        erosion and the need to replant vegetation during
        decommissioning.
        Does the site plan and management plan provide            No        Incorporate fire safety into physical
        for fire safety?                                        Planned     site and management plans.
        Do the physical and management plans for toilet
        and wash facilities incorporate procedures (1) to
        limit excessive water use, (2) limit groundwater
        pollution, (3) to avoid waste water run-off, and (4)                A waste water management plan
        for the safe and environmentally sound disposal           No        should be developed. The plan
        of liquid waste?                                                    needs provide for the collection
                                                                 Toilets
        For sites in areas with high ground water levels,      improperly   of waste water and sewage at
        local infiltration of waste water and sewage may          sited.    the site and later disposal in an
        lead to groundwater pollution or to the creation                    environmentally sound manner.
        of stagnant water pools. These outcomes are to
        be avoided because of their environmental and
        health impacts.

20
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

                                                 ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

                    Question                           Answer                   Guidance

                                                                   Develop a solid waste management
                                                                   system for the site, including
Have provisions been made for the collection                       recycling and environmentally
and environmentally sound disposal of solid                        sound disposal, including the use of
waste?                                                             composting to limit the need for land
                                                         No
The safe and environmentally sound disposal                        filling. (Landfills should be approved
of solid waste reduces negative environmental                      by the appropriate government
impacts and promotes good health conditions.                       authority). Local environmental
                                                                   NGOs can provide advice and
                                                                   assistance on composting.)
                                                                   Only designs which have been
                                                                   assessed as resistant to high winds
Are the buildings planned for the site designed                    should be constructed in the
to be resistant to high winds?                                     emergency shelter sites. Upgrading
The disaster affected area may be subject to                       sub-standard structures may be
cyclones and severe thunderstorms with strong            No        necessary in existing shelter sites.
winds. This storm activity can damage or destroy                   Wire or metal straps to connect roof
buildings which are not constructed to appropriate                 members together and to connect
standards.                                                         roof structures to walls can be an
                                                                   effective way to increase wind
                                                                   resistance.
Do all building designs include provisions for
harvesting rainwater?
Rainwater collection (1) reduces the need for                      All structures should include gutters
groundwater supplies, (2) increases the volume of        No
                                                                   and provision for rain water storage.
water available to each site inhabitant at limited
additional cost, and (3) can reduce the workload
on women.
Do building designs minimize the volume of
construction materials used and use materials
drawn from renewable resources when
possible?                                                          Evaluate the quantities and types
                                                                   of materials being used in building
To limit the impact on the environment, buildings                  designs to minimize the total
should use as few resources as possible while            No
                                                                   amount of materials used and to
meeting cost criteria and Sphere standards. Use                    maximize the use of renewable
of renewable resources (e.g., vegetative matter) is                resources.
preferred over non-renewable (e.g., sheet metal)
on the basis of the environmental sustainability of
renewable resources.
Can 100% of the materials used in building
construction be reused or recycled once a                          Building design should use materials
building is no longer needed?                                      and construction methods which
Planning for reuse allows emergency shelter                        allow all the materials initially used
                                                         No
occupant to “carry over” the building materials                    to be reused for permanent housing
as assets when they move to their new housing.                     or other uses after the site closes or
Materials which cannot be reused should be                         recycled (e.g., through composting).
recycled.

                                                                                                            21
Integrating Critical Environmental Issues into Emergency Shelter Cluster Activities Project

ANNEXES - Shelter Checklist Review/Gonaives - 30 October 2008

                             Question                            Answer                      Guidance

        Does building siting and design take advantage
        to natural ventilation?
                                                                               Where     practicable,     buildings
        Maximizing the use of natural ventilation reduces          No          should be designed and oriented to
        the need for fans and improves user satisfaction                       maximize natural ventilation.
        with the building, making it more likely the building
        will be used in hot weather.
        During construction at the site have steps been
                                                                   No          Develop plans to limit pollution.
        taken to limit air and water pollution?

                                          Shelter Site Management Checklist
                             (To be used to reviewing the operation of an existing shelter site.)

                              Question                           Answer                      Guidance

                                                                                Solid waste collection should take
         Is there a regular collection and sustainable                          place at least weekly, or more often
         disposal of solid waste?                                               if necessary. Specific collection sites
         Regular collection of solid waste aids in maintaining                  should be established. Disposal
                                                                    No
         overall environmental sanitation and health                            methods       should      incorporate
         conditions at a site. Sustainable disposal limits the                  recycling and composting. These
         impact of waste on the environment.                                    activities should be managed by
                                                                                community members.
                                                                                Sewage collection should take place
                                                                                as dictated by local circumstances,
         Is there a regular collection and sustainable                          including toilet use, ground water
         disposal of sewage?                                                    levels and surface water inflows.
                                                                                Disposal of sewage should not
         Regular collection of sewage supports good overall         No          lead to ground or surface water
         environmental sanitation and health conditions                         pollution and should be approved
         at a site. Sustainable disposal limits the impact of                   by the appropriate government
         waste on the environment.                                              authority. These activities should be
                                                                                managed by community members
                                                                                to the degree possible.
         Are drainage systems well maintained?
         Drainage systems need to be maintained,                                Establish a community-based
         particularly during the monsoon, to limit flooding         No          system for maintaining and
         and ponding of water, which can contribute to                          improving drainage systems.
         health problems.

22
You can also read