Strategic Plan 2015-2019 - MAF International

Page created by Eleanor Terry
 
CONTINUE READING
Strategic Plan 2015-2019 - MAF International
MYK
 LOURS

  C: 100 M: 57 Y: 0 K: 40

  C: 5 M: 100 Y: 71 K: 22

  C: 0 M: 1 Y: 0 K: 51

                                       MAF International
                            Strategic Plan 2015-2019
Strategic Plan 2015-2019 - MAF International
CONTENTS
		Our Strategic Journey.......................................          4
 1 Executive summary...........................................         7
 2 Reflections on the existing strategic plan............               9
 3 Important internal trends................................           13
 4 Long-term trends..........................................          19
 5 The starting point..........................................        23
 6 Moving forward (strategic priorities)................               25
 7 Implementation (strategic objectives)..............                 29
 8 Critical success factors.................................           33
 9 Financial implications.....................................         37
10 Risks............................................................   41
11 Final conclusions..........................................         43

2    MAF Strategic Plan 2015 - 2019
Strategic Plan 2015-2019 - MAF International
“A MAF flight can make the
  difference between a healthy
  newborn with a living, loving
      mom and an infant who is
  orphaned. Many literally owe
their lives to a MAF programme”
Beth Elson, Health Alliance International

             MAF Strategic Plan 2015 - 2019   3
Strategic Plan 2015-2019 - MAF International
Our Strategic
                                                                                   This has been possible because
                                                                                 we have a faithful God whom we are
                                                                                committed to serve and seek in prayer.
        Every three minutes                                                          And because we are united
one of our aircraft takes off or lands                                                in purpose and in vision
  bringing help, hope and healing
 to those in need all over the world

                                                                                                                 ies
                                                                                                        sionar
                                                                                           l So uth mis
                                                                                     Globa                                 dustry
                                                                                                              av iation in
                                                                                                     Stab  le
                                                                                                                                      n
                                                                                                                              isolatio
                                                                                                                p o ck ets of
                                                                                                          but
                                                                                                   cture                                ers
                                                                                         in frastru                              disast
                                                                                Impro
                                                                                     ved
                                                                                                                     to n atural
                                                                                                                  e
                                                                                                          spons
                                                                                                   sed re
                                                                                            Increa

           We are a                                    Current
        western-based                             recruitment base
         organisation                             is not big enough
       (funds and staff)

                                We are a
                            ’do it ourselves’
                            type of ministry                  Our partnership
                                                                  strategy
                                                               is not strong

        Good focus
                                            We are not
    on quality and safety
                                            very agile,
      but what about
                                      risk-adverse and slow
        efficiency?
                                            to change

4     MAF Strategic Plan 2015 - 2019
Strategic Plan 2015-2019 - MAF International
Journey
                      Our current strategy
                       has taken us far…

                        RESOURCE         IMPROVED
                      DEVELOPMENT        INTERNAL
                                       ORGANISATION

                      PARTNERSHIP      NEW MINISTRY
                         FOCUS           MODELS

                                                                 But we can go even further…
                                                                  We must chart our course
                                                                  around the current trends
                                                                     and navigate through
                                                                   challenging conditions

                What could MAF
              look like in 20 years?

FROM DOING
                                                                            Together in
TO ENABLING
                                                                          Christ we will be
                                             BECOMING A MORE
                                                                            strategically
                                            AGILE ORGANISATION
                                                                           positioned to
                      BECOMING TRULY
                                                                             transform
                       INTERNATIONAL
                                                                             more lives

                                                                                MAF Strategic Plan 2015 - 2019   5
Strategic Plan 2015-2019 - MAF International
He is before all things, and in
him all things hold together
Colossians 1:17

6   MAF Strategic Plan 2015 - 2019
Strategic Plan 2015-2019 - MAF International
1
                                                                         EXECUTIVE
                                                                         SUMMARY
This strategic plan builds on the previous plan and as such          Rolling out the approved HR strategy with a key focus
represents more changes in emphasis rather than major                on recruitment and reward and the Asia development
changes of direction. It briefly looks at what was achieved          strategy will form integral parts of the new strategy and are
during the past few years and identifies both successes as           considered critical success factors. In addition we plan for
well as key areas where the existing strategy fell short. This,      a greater emphasis on improving financial management in
in combination with a careful analysis of long-term trends,          such a way that operational income and expenses will return
forms the basis of the new strategic plan.                           to a more healthy balance, and with all of our resources
                                                                     focused on making a difference in places of highest need.
That said, with the new plan we are introducing three new
key themes which will run like a thread through the plan and         As we look forward and plan we acknowledge our
which will tie together the different strategic initiatives. These   dependency on the Lord and we commit ourselves to
three themes are:                                                    prayer recognising that He is before all things and in Him all
                                                                     things hold together (Colossians 1:17).
•   From doing to enabling

•   Becoming more international

•   Increasing agility

                         FROM DOING                    BECOMING TRULY                  BECOMING A MORE
                         TO ENABLING                    INTERNATIONAL                 AGILE ORGANISATION

    WE ARE STRATEGICALLY POSITIONED TO TRANSFORM MORE LIVES

                                                                                                    MAF Strategic Plan 2015 - 2019   7
Strategic Plan 2015-2019 - MAF International
“We hope and pray that our good Lord
 will continue to guide us and MAF until
 all those remaining steps are met with
 success and joy”
Villagers of Lailenpi Myanmar looking forward
to MAF commencing operations

8   MAF Strategic Plan 2015 - 2019
Strategic Plan 2015-2019 - MAF International
2
   REFLECTIONS ON THE
EXISTING STRATEGIC PLAN
The 2011-2015 strategic plan introduced four                     Financial support (in terms of grants and SWAP funding)
strategic priorities:                                            was given to Australia, Finland, and Norway to accelerate
                                                                 their growth
•   Resource development
                                                                 Lastly, much effort was put into Asia development and MAF
•   Internal organisational improvement                          was (re-)established in Malaysia, Singapore, Philippines and
                                                                 India. To date, two Asian International Staff members have
•   Partnership focus                                            been accepted into MAF and there are several more in the
                                                                 pipeline. In mid-2014 MAF International Board approved the
•   New ministry and new ministry models                         Asia development plan for further investment in Singapore,
                                                                 Philippines and India, as well as the recruitment of an Indian
2.1 Resource development                                         national to work alongside the International Development
We identified lack of sufficient financial resources and, even   Director in Asian development.
more so, lack of sufficient human resources as issues
which needed to be addressed in order for MAF to be able         2.2 Improving the internal organisation
to respond to both existing and future needs. With this in       Firstly, we recognised that a lot of work had to be done
mind we focused on three key areas: 1) developing a new          for MAF International (operations) to start functioning
HR strategy; 2) developing some of the smaller Resourcing        as one organisation. Secondly, the information flow
Groups; and 3) investing in Asia development. Good               between Resourcing Groups and operations in terms of
progress was made in each of these areas.                        stories, pictures, project proposals and reporting needed
                                                                 improvement. With that in mind we focused on the
A comprehensive HR strategy was developed and                    following areas: 1) creation of a single leadership team; 2)
approved, and implementation is underway. Special                restructuring all support departments so that they would
attention was given to recruitment and I am pleased to say       have a global instead of a regional focus; and 3) creation of
that we are gaining real momentum, with a net growth in          an internal communications department.
number of International Staff forecast for 2015 after three
years of decline. However, whereas recent developments           After the appointment of a single CEO, a new Executive
have been encouraging, a further step change will be             Leadership Team was put together. As time has progressed
required to adequately address our future needs.                 that team has bonded well and has started to work
                                                                 increasingly more strategically.
Regular financial (EON) support from MAF groups other
than MAF UK grew by an average of 6.6% per year, while           All support departments have undergone a complete
MAF UK increased their contribution by an average of 9.6%        restructure whereby most roles have now become global
annually. In other words, our dependency on MAF UK               rather than regional. As a result they have started to work
increased rather than decreased in the past four years. That     much more as virtual teams with team members based in
said, MAF Australia, Netherlands, Norway, Sweden and             Ashford and Cairns as well as in the field. In addition, a new
Finland managed to increase their contributions significantly.   department for Quality, Safety and Security was created.

                                                                                               MAF Strategic Plan 2015 - 2019   9
Strategic Plan 2015-2019 - MAF International
A new internal communications department was created            Collaboration with MAF-US and MAF Canada intensified
to improve the information flow between operations and          in the last couple of years with several joint projects now
Resourcing Groups and to improve overall communications         on the go, including Wingman (IT), Myanmar and disaster
within MAF International. The feedback received suggests        response. Moreover, both groups are seconding more
that this has been a worthwhile development.                    International Staff to our programmes.

Typically while going through a merger process the focus        2.4 New ministry (models)
is on aligning systems, procedures, standards and culture.      Our fourth and last strategic priority area included 1) seeking
MAF is no different in that respect. However, as new            to open up new programmes, 2) introducing cheaper-to-
systems and procedures are being formalised there are           operate aircraft type(s), and 3) introducing different operating
concerns that MAF as a whole has become less flexible and       models.
more bureaucratic. As we move forward this concern needs
to be addressed.                                                After considerable delay due to the Ebola outbreak, we
                                                                have now moved into Liberia and aim to be operational
2.3 Partnership focus                                           before the end of 2015. We also completed our registration
Our third strategic priority area focused attention on          in Myanmar, and indications are that we may become
the importance of partnerships, as it is mostly through         operational sooner than originally anticipated.
partnerships that we are able to achieve our vision of seeing
isolated people being transformed in Christ’s name. The         The C182SMA was successfully introduced into
key priorities in this area were 1) seeking to develop more     Madagascar and Chad and a third one is scheduled to
strategic partnerships both at headquarters level and in the    become operational in South Sudan this year. Due to its low
field; 2) more engagement with networks from the Global         operating costs the aircraft has allowed us to fly a customer
South; and 3) ongoing close collaboration with MAF-US and       group for whom we had become too expensive. On the
MAF Canada.                                                     downside, the dispatch reliability of the aircraft relating to
                                                                engine problems is a real concern.
Several successful partnerships have been forged
at programme level including partnerships with local            Lastly, there was some progress in terms of different
governments. However, to further develop these                  operating models. We are trying the consultancy
partnerships internationally proved to be more challenging.     approach with a flying club in Nigeria, have transferred our
Fortunately we have good access and collaboration with          maintenance operation in Tanzania to local ownership, and
like-minded partners through networks such as EU-CORD           we charter aircraft in South Africa instead of operating our
and Integral. Such networks are particularly valuable during    own. Moreover we are encouraging the introduction of
disaster response. Limited progress was made with regard        technology services into more programmes.
to engaging with networks from the Global South, but
contact was made with the Micah Network. As we move
forward we may need to rethink how to progress in this
area.

10    MAF Strategic Plan 2015 - 2019
RESOURCE DEVELOPMENT

   Asia development
                                                                             Financially
   is starting to gain
                                                                               strong
       momentum
                                                                                                            BUT
                                                                                                       High dependency
  Resourcing Groups                                                                                       on MAF UK
                                                                            Recruitment is
   are growing their                                                                                 Growth in recruitment
                                                                           starting to grow            is not enough to
        income
                                                                                                       address the need

                                           IMPROVE INTERNAL ORGANISATION

                                 Global organisation is well established
             Improved internal communications & info sharing
                          ELT & Board have real strategic focus                                             BUT
 Heightened security management & increased training                                                     streamlining and
                                                                                                       formalising internal
                                                                                                        processes can feel
                Better fleet and engine management                                                      cumbersome and
                                                                                                            bureaucratic
                                       Improved safety

                                                  PARTNERSHIP FOCUS

Some successes:
➔ Rural Airstrip Agency | PNG
➔ ‘Let’s fix it’ initiative | Bangladesh
➔ Mercy Ships | Madagascar
➔ eMi | Uganda                                                                                               BUT
                                                                                                       It is difficult to put
                                                                                                         strategic global
EU-CORD | INTEGRAL                                                                                      partnerships into
                                                                                                       meaningful action

Local partnerships enable
us to achieve our vision

                                                NEW MINISTRY MODELS

Increased focus on training
➔ TC Mareeba
➔ MATC
➔ Engineering Apprenticeship Programme
                                                                                                             BUT
Myanmar                                                                                                 It takes us a long
                                                                                                          time to set up
                                                                                                         something new
Liberia

C182SMA

                                                                                              MAF Strategic Plan 2015 - 2019    11
Programme Manager Emil Kundig and
Pilot Arjan Paas, two of the founder
members of the MAF lifeline in Liberia

12   MAF Strategic Plan 2015 - 2019
3
                                                    IMPORTANT
                                              INTERNAL TRENDS
             3.1 Operations                                                              However, it will be important to monitor this very closely
                                                                               Draft Strategic plan 2015-2019
           Operational activity (measured in hours flown) has reduced year               and take the necessary action if, for whatever reason, that
           on year since 2011, with the most significant drop happening                  growth does not materialise.
           in 2014. The primary reason for this has been the shortage of
RTANT staff,
           INTERNAL
                  particularly TRENDS
                               impacting the three programmes where the                   Driven by our desire to allocate resources where they
ations demand for our service is the highest: Arnhem Land, PNG                            have the greatest ministry impact, we have realigned our
           and South Sudan. Other factors include delays in starting up                   operation in several places. Most notably the following
activity (measured in hours flown) has reduced year on year since 2011, with the most
           the Liberia programme, reduced flying in Uganda following the                  changes were implemented:
rop happening in 2014. The primary reason for this has been the shortage of staff,
           revocation of our permission to fly internationally, lack of staff in
mpacting the   three programmes where the demand for our service is the highest:
           Mongolia, the closure of the flying programme in South Africa                  • ClosureArnhem
                                                                                                       of own flight operations in South Africa
 nd South and
            Sudan.    Other    factors  include    delays     in starting   up
                 the re-directing of existing resources (people and aircraft)    the  Liberia programme,
 g in Uganda  following    the revocation     of ourapermission                           • Restructure
                                                                      to fly internationally,  lack of staffand significant reduction of footprint in Tanzania
           from   programmes     that experienced       decline in demand
  the closure  ofAfrica)
           (East   the flying
                          taking programme       in South and
                                  longer than anticipated      Africa
                                                                   not and
                                                                       alwaysthe re-directing   of existing
                                                                                          • South    Sudan becoming an independent programme
eople and aircraft)   from    programmes      that   experienced      a decline
           resulting in people going to the places of highest need due to         in demand   (East Africa)
  than anticipated   and not
           issues around        alwaysamong
                             schooling   resulting    in things.
                                                  other  peopleMoreover,      the places•of highest
                                                                   going to with              Restructure
                                                                                                      needand refocus of the Kenya programme
           ever increasing
s around schooling      among requirements   from Moreover,
                                   other things.    regulators and    the ever
                                                                   with   effortsincreasing requirements
                                                                                          • Opening Liberia and Myanmar as new programmes
 ors and the efforts we ourselves put into increasing theof quality
           we   ourselves   put into increasing  the   quality and  safety    our       and safety of our
           operations,
he operational           the operational
                  availability  of pilots availability
                                           has reduced. of pilots has reduced.            • Focus on re-staffing the PNG programme

                                                                                         As far as flight operations are concerned we have identified
                                    Hours Flown                                          the following priorities:
              35000
              30000                                                                      •    Get Liberia and Myanmar fully operational
              25000
                                                                                         •    Complete the strategic re-focus of the Kenya programme
              20000
              15000                                                                      •     urther develop and increase activity in the South Sudan
                                                                                              F
              10000                                                                           programme
               5000
                  0                                                                      •     ebuild and restructure the PNG programme in line with
                                                                                              R
                          2011      2012       2013       2014       2015                     its strategic plan
                                                                  (forecast)
                                                                                         •    e-staff the Arnhem Land programme and clarify its dual
                                                                                             R
urs flown isWhereas
             not a good     measure                                                          (ministry  + training) strategy
                       hours   flown isofnot
                                           ministry
                                             a goodimpact,
                                                     measure it of
                                                                 is aministry
                                                                      good measure of activity        and  it
 ern that aimpact,
             declineitinis operational
                           a good measureactivity has coincided
                                              of activity and it is awith
                                                                       real a significant• investment    on
                                                                                             Review potential   long(er)-term involvement in Nepal
 side. However,     with   a  much    better recruitment    plan    in
            concern that a decline in operational activity has coincidedplace   and  a greater     focus on recent earthquake
                                                                                              following the
 ieve we arewithturning   a corner
                  a significant       and weon
                                 investment    should   see activity
                                                 the support            grow significantly in this next
                                                               side. However,
 od, thus bringing   back better
            with a much      the necessary   balance.
                                    recruitment plan in place and a greater             • Further expand operational activity in West Africa
             focus on training I believe we are turning a corner and we
will be important
           shouldto  monitor
                   see activitythis
                                growvery closely and
                                      significantly    takenext
                                                    in this     necessary action•if, for
                                                            the strategic             Review need for MAF operation in Bougainville
                                                                                         whatever
growth does   not materialise.
           period, thus bringing back the necessary balance.
 r desire to allocate resources where they have the greatest ministry impact, we have
r operation in several places. Most notably the following changes were implemented:                                     MAF Strategic Plan 2015 - 2019    13
3.2 Staffing levels                                             Notes:
As can be seen in the table below, the total number of
International Staff dipped in 2013 and 2014, but is set to      •    he figures focus on staff in programme only and
                                                                    T
recover in 2015. However, due to visa issues some of this           exclude those International Staff working in Cairns,
recovery may not happen until 2016.                                 Ashford or Mareeba;

                                                                •   ‘Other’ refers to International Staff coming from countries
 Programme          2011      2012      2013   2014   2015
                                                                     where there is no MAF Resourcing Group;
 Arnhem Land          34        30      28     28       32
 Bangladesh            4         3       2      2           4   •    he ‘duplicate’ line has been included as some
                                                                    T
 Chad                  4         3       4      5           4       International Staff are counted under 2 Resourcing
 CRMF (PNG)            2         2       3      2           3       Groups. This is the case where husband and wife (and
 Liberia                                                    2       their financial support) come from 2 different countries.
 Kenya                22        24      19     11           9
                                                                3.3 Support costs (regional offices)
 South Sudan         n/a       n/a      n/a     8       11      During the initial part of this strategic period we invested
 Madagascar            4         4       5      5           5   significantly in the support side of the organisation. This
 Mongolia              2         2       1      1           2   was necessary for successful integration, the boosting of
 Myanmar                                                    0   capacity in specific areas of need and for investment in
                                                                some new strategic initiatives. Over the past four years we
 PNG                  32        34      31     28       35
                                                                have successfully globalised the different departments,
 South Africa          2         2       0      0           0
                                                                created a new ELT, added an internal communications
 Tanzania             14        16      17      5           6   department (at the request of the Resourcing Groups),
 Timor-Leste           1         1       2      2           2   increased our recruitment capacity, and created the role of
 Uganda               14        13      13     21       19      an International Development Director to focus on increasing
 TOTAL              135       134       125    118     134      our presence in Asia. Although some ongoing adjustments
                                                                are being made, the structure overall is well established and
When we analyse our 2015 projected number of International      is geared towards being able to handle greater programme
Staff by Resourcing Groups the following figures emerges:       activity. The latter is needed to restore balance between
                                                                support and programme costs.
 Sending Group                                 F’cast 2015
 MAF Australia                                         31
 MAF Canada                                            17
 MAF Denmark                                            0
 MAF Finland                                            3
 MAF France                                             1
 MAF Germany                                            4
 MAF Italy                                              1
 MAF Netherlands                                       11
 MAF New Zealand                                       13
 MAF Norway                                             1
 MAF South Africa                                       3
 MAF Sweden                                             2
 MAF Switzerland                                       11
 MAF UK                                                23
 MAF US                                                 4
 Other                                                 13
 Less: duplicates                                      -4
 TOTAL                                                134

14     MAF Strategic Plan 2015 - 2019
In reviewing the trend forward, Figure 2 demonstrates that we should be able to achieve an
     Acceptable rate over the next few years. If we continue with the improvements in the Safety
     and Quality culture, then MAFI should be able to achieve the target rate by 2018.

                          Flight Accident Rate - MAF I (8 year rolling rate)
          6.00
                 4.98
          5.00          4.61 4.60
                                            4.33 4.37 4.42
                                    3.50                         3.71
          4.00
                                                                                        2.86
          3.00                                                           2.59 2.69 2.77
                                                                                                      1.96 2.01
          2.00                                                                                                    1.54

          1.00

          0.00
                 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

                                      Per 100,000 hours            Target           Acceptable

      3.4Africa
    2.1.2 SafetyRegion                                                     During this next five years the major priorities in terms of fleet
       In terms of safety this strategic period did not start very well,   management include:
     Over the last year no flight accidents were recorded for this region. This has resulted in an
       with  two accidents  in PNG   within a short   period of time. A
     accident rate of 0.00 per 100,000 flight hours over an 8 year rolling rate as shown in the figure
       safety enhancement plan was introduced and safety and
     below.                                                                • Major overhaul and upgrade of second Twin Otter
       quality management systems was further aligned between
       the two regions. These efforts and an increased focus on            • Agree on fleet plan for PNG with the aim of reducing the
                          AR Accident rates per 100,000 flight hour (8 year rolling rate)          Figure 3in PNG to two
       safety and quality appear to have paid off, with all safety             number of types operated
      7
       trends moving in the right direction. The introduction of
       a new reporting system, Mantis, has certainly helped to             • Further phasing out of our C206 fleet
      6
       improve our reporting culture, and5.24credit5.29
                                                     goes to all staff for
       buying into the 4.83
                       system.5.04                                         • Completion of Caravan avionics upgrade
      5
                                     4.13                 4.24    4.28    4.25
            4.00
       If the  current
                   3.92 trend continues, we are likely to meet our                •     Rationalising our fleet of training aircraft in Mareeba
      4
       target of fewer than two accidents per 100,000 hours within
       the time-frame of this strategic plan. For this to happen,                 •     Improve dispatch reliability of C182SMA
      3
       ongoing effort and attention need to be given to promote                  2.18   2.15   2.14
      2
       safety within the organisation. As far as quality is concerned,            3.6 Training
       we are aiming to improve the way we measure the cost                     In response to the ongoing shortage of staff we have put
                                                                                                     1.07 1.09
      1
       associated with (lack of) quality.                                       greater emphasis on training. We invested in MATC in
                                                                                the Netherlands, moved flight training from Coldstream to
                                                                                                                 0.00
    0
     3.5   Fleet                                                                Mareeba, and are in advanced conversation with Prairie,
     During
        1999 the  past2001
               2000     five years
                              2002 we  managed
                                    2003          both 2006
                                           2004 2005     to rationalise
                                                                2007 2008 2009  Canada.
                                                                                     2010 Through
                                                                                            2011 2012  an improved
                                                                                                           2013 2014curriculum we are seeking
     and upgrade our fleet andAccidents
                                    now operate Acc/100k
                                                   a fleet of  60
                                                           hours
                                                                  aircraft.
                                                                         Target
                                                                                to reduce   the
                                                                                       Acceptable
                                                                                                  minimum    requirements for pilots to join MAF
     The PC12 was phased out and good progress was also                         and are working very closely with the Resourcing Groups to
     made with phasing out our Cessna C206s with now none                       reduce the time it takes for pilots to go to the field.
  This  is the  first time  in MAFI   history  that such   a  rate
     remaining in PNG. Further modifications were carried out on   has  been    achieved   and illustrates the hard
  work   that  has  gone    on  behind  the  scenes    by both
     the GA8 to improve its reliability and its STOL performance.staff and   management
                                                                                Following the at struggles
                                                                                                  all levels.at ACMA with regard to their
     One of our three Twin Otters successfully underwent a                      engineering training programme, we have moved to an
     major overhaul. Lastly, progress has been made with the                    apprenticeship model which is now being implemented in
     avionics upgrade of our Caravans and four have now been                    Mareeba.
     completed.
SMS Annual         We are
               Report        waiting for the necessary permission
                          - 2014                                                                          Page 2 of 10
     to upgrade a further two Caravans in 2015. Confirmed                       Both initiatives are in effect examples of vertical integration,
     future aircraft needs include a C208 for Liberia and a C208                whereby we are seeking to engage at an earlier stage with
     Amphibious for Bangladesh. Furthermore we expect to the                    those who have a desire and calling to serve God through
     need for an aircraft in Myanmar.                                           MAF with the aim of improving the future pipeline of pilots
                                                                                and engineers.

                                                                                                                    MAF Strategic Plan 2015 - 2019   15
3.7 Finances
Below you’ll find the overview of the actual income and
costs from 2010 to 2014 compared to the operating
budget as presented in the last strategic plan:

                                                  2011                        2012                             2013                       2014
SUMMARY                              Budget     Actual    Diff    Budget    Actual        Diff     Budget    Actual     Diff   Budget   Actual     Diff
                                       $'000     $'000   $'000      $'000    $'000       $'000       $'000    $'000   $'000     $'000    $'000   $'000
INCOME
Africa Operations                     6,733      6,735       2     7,452     7,501          49      7,676     7,802      126    7,906    5,431   -2,475
Asia Pacific Operations              13,393     14,562   1,169    13,911    15,501       1,590     14,488    11,511   -2,977   15,259    9,111   -6,148
Members (Eons)                        8,132      9,127     995     9,076     9,785         709      9,303     9,384       81    9,541   11,176    1,635
Members (Staff Support)               1,762      1,903     141     1,859     2,186         327      1,963     2,135      172    2,075    2,434      359
Net Benefit Asian Fund Raising            0          0       0         0         0           0         25         0      -25      140        0     -140
Institutional Funding increase            0          0       0         0         0           0        100         0     -100      200        0     -200
Sub-total                            30,020     32,327   2,307    32,298    34,973       2,675     33,555    30,832   -2,723   35,121   28,152   -6,969

EXPENSES
Africa Programmes                     7,991      8,379     -388    9,183     9,314         -131     9,459     9,706    -247     9,742    8,910     832
Asia Pacific Programmes              15,742     16,520     -778   16,474    18,933       -2,459    16,968    14,289   2,679    17,477   12,452   5,025
Support offices                       5,630      5,693      -63    6,046     5,733          313     6,840     5,945     895     7,046    6,504     542
Transfers to/from designated funds      -10          0      -10     -200        84         -284      -200       714    -914      -100      236    -336
Additional staff                                     0        0      395         0          395       404         0     404       413        0     413
New initiatives                          25          0       25      200         0          200       200         0     200       300        0     300
Sub-total                            29,378     30,592   -1,214   32,098    34,064       -1,966    33,671    30,654   3,017    34,878   28,102   6,776

Result                                    642    1,735   1,093       200        909        709       -116      178      294       243      50     -193

Annual perc increase in income                    20%                          8%                             -12%                         -9%
Annual perc increase in expenses                  16%                         11%                             -10%                         -8%
Tot number of International Staff                  135                         134                              125                        118
Tot flying hours                                30,031                      28,890                           26,143                     21,258

A number of conclusions can be drawn from this:                             •          sia development has not yet resulted in funding
                                                                                      A
                                                                                      income, but has resulted in recruitment of new
•      rogramme income is significantly down in 2013
      P                                                                               International Staff.
      and dramatically down in 2014 in line with the lower
      hours as a result of lower staffing levels. Consequently              •         In spite of investments made at regional level (i.e.
      programme expenses have also been down.                                          support offices), overall costs were significantly below
                                                                                       budget.
•      esourcing Group income has been consistently above
      R
      budget, but most notably in 2014. This is the reason
      why we did not end up with a deficit in 2014.

16       MAF Strategic Plan 2015 - 2019
As always we separate our operational budget from our
capital budget. Concerning the latter the comparison
between budget and actual was as follows:

                               2012                2013                 2014                     Total
        SUMMARY           Budget      Actual    Budget     Actual    Budget      Actual     Budget       Actual
                           $`000       $`000     $`000      $`000     $`000       $`000      $`000        $`000

Aircraft                    2,200       784        980      5,800       800         538      3,980        7,122
Aircraft upgrades             400       -          600        187       600         991      1,600        1,178
Property                      500       821        500        427       500       1,190      1,500        2,438
Vehicles & equipment          440       570        440        309       440         347      1,320        1,226

TOTAL                       5,552      2,175     2,520      6,723      2,340      3,066      8,400       11,964

This includes:                                                  •    urchase of four houses in South Sudan, a house
                                                                    P
                                                                    + annex in Arnhem Land, Mareeba Training Centre
•    he purchase of two Cessna Caravans, a C182SMA,
    T                                                               building, and part of the costs of the Kajjansi office
    and five GA8s (now known as Project Croc)
                                                                Thanks to the hard work of our Resourcing Groups and the
•    our avionics upgrades and the refurbishment of one
    F                                                           generous donations of our supporters the actual capital
    Twin Otter                                                  project income far exceeded the budgeted income.

                                    SUMMARY OF INTERNAL TRENDS

Operations
•   Hours flown down year on year since 2011
•   Staff shortages especially in programmes where service demand high
•   Change programme implemented to realign operations to maximise ministry impact
•   Globalisation of support functions
•   Enhanced safety and quality processes

Fleet
•   Rationalisation and upgrade of fleet over last 5 years
•   Greater emphasis on training to grow our own pilots and engineers including new facility at Mareeba

Finances
•   Programme income down but Resourcing Groups income consistently above budget
•   Generous donations and supporter base has enable significant capital investment including acquiring 8 aircraft

                                                                                             MAF Strategic Plan 2015 - 2019   17
“This is a miracle that has happened. When I received the call from you
 guys, this was like this is a game changer for us. We haven’t been able to
 reach so many communities because of the roads, the weather conditions,
 many days of driving or hiking and this is changing everything. Thanks to
 you guys we will be able to reach communities that haven’t been reached
 yet with medicine, clean water, clothes, food supplies so this is amazing.
Thank you so much. Today everything changed – we met MAF!”
Diego Traverso – Operation Blessing – Nepal 2015 Disaster Response

18   MAF Strategic Plan 2015 - 2019
4
                                                                      LONG-TERM
                                                                         TRENDS
4.1 Introduction                                                      Fourthly, the need for MAF services in relief and disaster
Any new strategy not only builds on the strength of the               situations remains high. The ongoing high demands for
existing strategy whilst addressing its weaknesses; it also           our service in South Sudan, the East Africa famine relief
needs to take into account the long-term trends that impact           intervention, and our involvement in the Nepal earthquake
MAF in both a positive and negative way. Significant time             disaster response are good examples of that. We have
was spent identifying these trends.                                   been working very closely with MAF-US in this area and
                                                                      have successfully set up a joint structure. The speed with
4.2 Trends related to needs                                           which we have been able to respond to the earthquake in
Research1 suggests that poverty on the whole is on the                Nepal has been encouraging and demonstrates that the
decline. However, there are still over 1 billion people living in     joint approach is working. As we look forward we anticipate
extreme poverty. Moreover there remain many people and                that our involvement in similar situations is likely to increase
people groups that have limited or no access to the Gospel,           rather than decrease.
and the need for nurturing existing churches in remote areas
remains high.                                                         Fifthly, as we look forward we anticipate that there will be
                                                                      greater need for MAF services in so-called closed countries,
Secondly, in many (but not all) of the countries were we              i.e. in countries where Christianity is a minority faith. This will
operate the infrastructure is improving, but pockets of               have an impact on the way we train and equip missionaries
isolation remain. Effectively this means that in the long run         to serve effectively in those countries; for example putting
more of our programmes are likely to become smaller and               greater emphasis on the need for personal witness and
more focussed on specific isolated areas within a country.            discipleship.

Thirdly, with the ongoing world-wide population increase,             Lastly, we see opportunities for MAF to get involved in
urbanisation continues to be a major trend. However,                  consultancy-type work whereby some of the knowledge we
research2 suggests that the number of people living in rural          have gained over many years can be shared with others,
areas is likely to remain fairly stable.                              such as local operators and aviation authorities. This would
                                                                      create other opportunities for witness.

1
 World Bank, Remarkable declines in global poverty, but major
challenges remain, April 17, 2013
2
 United Nations, World Urbanization Prospects, (revised) 2014, esa.
un.org/unpd/wup/Highlights/WUP2014-Highlights.pdf

                                                                                                     MAF Strategic Plan 2015 - 2019   19
4.3 Trends related to our                                               4.4 Trends related to our resources
external environment                                                    Most of our resources come from Western countries
We operate in a highly regulated and conservative industry              (Europe, Australia and New Zealand, and North-America)
where changes tend to be incremental and slow. The slow                 and we are thankful for the many faithful and committed
development of a diesel alternative to our piston engines is a          supporters we have in those countries. At the same time we
good example of this. Although there are several companies              know that our donor base is ageing and that the Church in
working on this development, we still seem to be several years          the West is in decline. Although these may not impact us
off a suitable solution for our fleet of piston aircraft. At the same   in the short to medium term, we anticipate that in the long
time we are operating in an ever faster changing world with             term financial support from our existing supporter base will
pressure on us to be increasingly more flexible and to continue         decline. This can be counterbalanced by increasing our
reducing costs. There is an inherent tension between these              presence in Western countries where MAF has been under-
two worlds which we are grappling with day by day.                      represented so far and by focusing more on Asia and the
                                                                        Global South where the Church is growing, in some places
One of the challenges we are facing is that we are seeing               even quite dramatically.
needs changing in countries where we operate, but we are
relatively slow in our ability to move aircraft and people. As          It is for this reason that we appointed an International
we look forward there is a need for us to be able to respond            Development Director to focus on Asia development, and it
more quickly to changing needs. Likewise, whereas we                    is encouraging to see that this is now gaining momentum.
continue to focus on a long-term commitment to serve the                With regard to recruitment in particular, we believe there
needs of the isolated peoples in the countries where we                 is great potential and we anticipate that Asian and Global
operate, we anticipate that in future the length of time we             South missionaries will become an important part of MAF’s
will serve in some countries will reduce. This means that in            missionary force.
some of the new places where we plan to start operating,
we should start with an exit strategy in mind.                          Other trends to be mindful of are the generation gap and
                                                                        different attitudes of younger missionaries (Gen Y) starting
Lastly, many missions have moved from doing to enabling                 to join MAF, as well as concerns around obtaining visas and
whereby much of the work has been handed over to the                    work permits. The latter was already identified in the previous
Church and/or local partners. This has not only changed                 strategic plan as an area of concern and we can only expect
the need for our service and whom we serve, but also begs               this to become more difficult in the years to come.
the question whether and how this might apply to MAF. Our
main focus has continued to be on ‘doing’ and as a result               Lastly, donor transparency and a need to be able clearly
we have largely remained a Western mission in our outlook               to demonstrate impact are ongoing trends and we need to
and in the way we work. Of course the fact that we are a                make sure that our information systems are robust enough
highly technical ministry is an important factor in that.               to meet those demands.

20    MAF Strategic Plan 2015 - 2019
TRENDS: NEED

                                  Poverty overall is on the decrease,
                                    but urgent needs remain

                              Increased needs in response to natural disasters

                                                           Improved infrastructure,
                                                             but pockets of isolation
                                      Highest need for MAF likely to be
                                          in so-called ‘closed countries’
                                               Ministry opportunities to share our
                                                 aviation knowledge in different ways

TRENDS: THE EXTERNAL ENVIRONMENT

                          A relatively stable and only
                            slowly-changing aviation industry

                                       Decreasing maintenance
                                        costs and aircraft downtime

                                               Shorter and more clearly
                                                defined programme cycles

                                              Need to become quicker and more
                                               agile in responding to changing needs

                                     Missions moving from ‘doing’ to ‘enabling’
                                       – mutuality and partnership

TRENDS: OUR RESOURCES

                    Declining church in the West, but
                      growing church in the South and East
                                            Global South has become
                                             part of the mission force
                                                             Changing expectations
                                                               of younger missionaries

                                    Increasing difficulties with placing International Staff

                                            Increased scrutiny from supporters/donors
                                            and need to demonstrate impact

                                                                           MAF Strategic Plan 2015 - 2019   21
MAF’s unique ministry is to use aircraft
and technology to physically and
spiritually transform the lives of those
living in isolated areas

22   MAF Strategic Plan 2015 - 2019
5
                                                      THE STARTING
                                                             POINT
5.1 Our identity in Christ                                          Throughout the years this unique mandate has been worded
As we reflect on 70 years of history we are encouraged that         in different ways in mission, vision and purpose statements,
the desire and calling that moved our founders to create            but its core essence hasn’t changed. As we move forward
Mission Aviation Fellowship and use aircraft (and technology)       we believe that this unique mandate should remain.
to transform the lives of those living in isolated areas still
lie at the very heart of the organisation. While we continue        5.3 Aviation as core competency
to experience change in terms of where we operate, how              Our aviation ministry has been and will continue to be our
we operate and the types of services we offer, the Great            core ministry. Nonetheless, we have recognised that other
Commandment and the Great Commission and a desire to                technology solutions further increases our transformational
follow Jesus and to make Him known remain the principle             impact. It is for this reason that several years ago ‘and
motivation for why we do what we do.                                technology’ was added to our purpose statement. Where
                                                                    we implement technology services we seek these services
For this reason it is vital that we continue to seek Him in all     to be complementary to our core aviation ministry and to
we do and prayer is therefore such an important part of our         serve the same vision of transforming the lives of people
ministry. We expect Him to direct us as an organisation,            living in isolated areas.
recognising that we are involved in a spiritual battle.

5.2 Transformation of remote
communities
MAF’s unique ministry is to use aircraft and technology to
physically and spiritually transform the lives of those living in
isolated areas. MAF is unique in that it is a technical mission,
but also because of its focus on reaching isolated areas.

                              AFFIRM OUR CORE IDENTITY IN CHRIST
            TRANSFORMATION OF REMOTE COMMUNITIES TO REMAIN
                 AT THE CORE OF OUR VISION AND STRATEGY
                       AVIATION TO REMAIN OUR CORE COMPETENCY

                                                                                                MAF Strategic Plan 2015 - 2019   23
Our staff are our greatest asset and one of
the biggest challenges we have faced in
recent years is recruiting enough suitably
qualified people to enable us to do all the
crucial work our partners and customers
need. Recruitment and training remain key
priorities for the organisation

24   MAF Strategic Plan 2015 - 2019
6
                           MOVING FORWARD
                                                           (STRATEGIC PRIORITIES)

6.1 Introduction
Our strategic plan has been developed through detailed
SWOT (Strengths, Weaknesses, Opportunities, Threats)
analysis, which is summarised in the table below:

   S        Our identity in Christ
            Commitment to prayer                                W         Shortage of staff
                                                                          Cost of operation (efficiency)
            United in purpose, vision and values                          Slow changing
            Financial strength                                            Inability to respond quickly
            Global presence                                               Western based and Western led
            Excellence (including safety)

  O                                                             T
                                                                          Visas / work permits
            Global South / Asia development                               Security
            Strategic partnerships                                        Declining Church in the West
            Sharing our aviation knowledge in different ways              Ageing donor base
            Need for MAF in countries where we                            Generational issues
            are currently not present                                     Donor expectations
                                                                          Placing staff in remote locations

Through our new strategic priorities we will be seeking         rural airstrip agency (RAA) in PNG is a good example of local
to build on our strengths and seize opportunities whilst        capacity building and we will be seeking to identify capacity
addressing some of the weaknesses and safeguarding              building projects in other countries as well.
against threats. Through analysis and discussion three
major themes were identified: 1) from doing to enabling; 2)     We will look out for opportunities for our staff to be involved
becoming more international; and 3) increasing our agility.     in consultancy type ministry where we share our knowledge
                                                                and expertise with others. This and the fact that we are
6.2 From doing to enabling                                      likely to be doing more ministry in so-called closed countries
Enabling others has always been at the heart of our             mean that we need to better equip and enable our staff to
ministry and will continue to be in the years to come.          be effective in discipleship.
However, we aim to become more intentional in terms of
local and international partnerships in order to increase our   Lastly we see a need to train and enable more of our local
transformational impact. Moreover we want to put a greater      staff to take on senior roles. Not only is this a positive
emphasis on local capacity building and supporting local        development is itself, it also addresses the concerns we
initiatives. The way that MAF was involved in setting up the    have in terms of work permits and visas.

                                                                                               MAF Strategic Plan 2015 - 2019   25
6.3 Becoming more international                                 6.4 Increasing agility
Becoming more international means that we continue              In an ever faster changing world and with the increased
our strategy of Asia development and we expect more             need to respond to natural and man-made disasters, there
people from Asia to join MAF as missionaries in the years       is a need for MAF to be able to respond quickly. Moreover,
to come. Moreover we would like to see more of our local        we need to address the internal perception that MAF has
staff become missionaries with MAF as well. For this we         become more bureaucratic and slow to change as a result
will need to create new pathways for recruitment and think      of the integration process. We should therefore explore ways
through issues such as support raising. Likewise, the staff     to improve the mobility of our staff and our assets (aircraft) so
survey once again highlighted the perception of a glass         that we are better able to respond to changing partner needs
ceiling for local staff where senior roles are concerned.       in the places where we work. Likewise, we should aim to
As we find ways for local staff to join as missionaries, this   further shorten the time it takes for International Staff to get to
issue needs to be addressed as well and is likely to include    the field. Finally we see national regulators increasingly taking
a leadership development programme. Lastly, to become           a prescriptive approach, thus reducing our flexibility. As MAF
more international we need to increase diversity at every       we need to find the right balance between a prescriptive and
level within the organisation and we recognise that this will   principle-based approach in the way we write our standards
only happen if we are intentional about this.                   and policies to optimise our flexibility within the constraints in
                                                                which we operate.

                                       WHAT COULD MAF LOOK LIKE...

               FROM DOING
               TO ENABLING

                                                                                                      BECOMING A MORE
                                                                                                     AGILE ORGANISATION

                                                          BECOMING TRULY
                                                           INTERNATIONAL

26    MAF Strategic Plan 2015 - 2019
We have been sharing our aviation
        expertise in a partnership with the
 Timor-Leste government where MAF has
  provided in-country flight experience to
Timorese pilots as well as flight training at
   our Australian flight school in Mareeba

                    MAF Strategic Plan 2015 - 2019   27
“This is the second time I have flown with MAF
 and I think it is a reminder that MAF just keeps on
 taking the presence of Christ into some of the most
 difficult places on earth”
 The Most Reverend Justin Welby, Archbishop of Canterbury

28   MAF Strategic Plan 2015 - 2019
7
                                  IMPLEMENTATION
                                           (STRATEGIC OBJECTIVES)

7.1 From doing to enabling

In order to move from doing to enabling      We are going to make this work by…
 we are going to focus on…

1. D
    eveloping strategic international     •B
                                             ecoming more intentional in working with partners that will enable
   and local partnerships                   holistic transition to happen
                                           •E
                                             nsuring that all our activities are focused on achieving maximum
                                            transformational impact
                                           •R
                                             eviewing and updating our ministry effectiveness tool to improve
                                            the way we measure ministry impact

                                           • Being more actively involved in strategic alliances and networks

                                           •P
                                             utting greater emphasis on identifying and working with key local
                                            partners in our programmes
2. F
    acilitating local capacity building   • Identifying specific projects within existing programmes that would
   and supporting local initiatives           build local capacity

                                           • Actively offering our service and expertise externally

3. E
    ncouraging and equipping staff        •A
                                             ctively seeking and distributing resources to encourage and equip
   for effective discipleship               staff in this area
                                           •C
                                             ontinuing to promote prayer within the organisation and allowing
                                            opportunities for retreats
                                           • Identifying suitable training courses, particularly for staff working in
                                              spiritually hard places

                                           • Developing and implementing a staff well-being strategy

4. E
    mphasising training and development   •D
                                             eveloping and implementing a pathway for national staff with
   of national staff                        potential to become MAF pilots

                                           • Further developing our maintenance apprenticeship programme

                                           • Increasing our in-house training resources and integrating this with
                                              our performance management system

                                                                                     MAF Strategic Plan 2015 - 2019      29
7.2 Becoming more international

In order to become more international             We are going to make this work by…
we are going to focus on…

1. Accelerating Asia development                 • Implementing the approved Asia development strategic plan

                                                 • Earmarking sufficient financial resources to implement the strategy

                                                 •H
                                                   aving the Asia Development Executive (working alongside the
                                                  International Development Director) fully operational
2. E
    ncouraging national staff to become         •D
                                                   eveloping a support structure model specifically geared towards
   missionaries with MAF                          Global South missionaries

                                                 • Creating opportunities for national staff to work in other programmes

3. Leadership development                        • Developing a management mentorship programme

                                                 •B
                                                   ecoming more structured in the way we develop and mentor
                                                  those with potential for future leadership
4. Increasing diversity at every level within
                                                 • Appointing at least one trustee from a Global South background
   the organisation

                                                 • Actively seeking to increase diversity at the senior management level

30   MAF Strategic Plan 2015 - 2019
7.3 Increasing our agility

In order to increase our agility              We are going to make this work by…
we are going to focus on…

 1. Improving the mobility of people and
                                             •F
                                               urther simplifying and standardising our aircraft fleet and flight
     aircraft to become more responsive to
                                              training
     changing partners needs

                                             •D
                                               eveloping creative solutions for some of the major stumbling
                                              blocks that prevent staff from moving (e.g. schooling)

                                             •F
                                               urther developing our disaster response capability in close
                                              collaboration with MAF-US

                                             • Implementing our recruitment strategy

                                             •C
                                               ontinuing to critically review our programmes on a regular basis
 2. Increasing operational effectiveness
                                              in terms of their ministry effectiveness and implementing changes
    and efficiency
                                              accordingly

                                             • Developing KPIs that help us to monitor operational efficiency

                                             • Improving stock and inventory management

                                             •P
                                               utting greater emphasis on operational efficiency within our QMS
                                              and as we review new standards and policies

                                             •R
                                               eviewing effectiveness and efficiency of a centralised versus a
                                              de-centralised approach

                                             •C
                                               arrying out a feasibility study of going to a single HQ (as opposed
                                              to two regional offices)

                                             •C
                                               ontinuing to invest in MAF’s specialised flight training
 3. Shortening recruitment time
                                              programmes (i.e. Mareeba TC, MATC, Prairie)

                                             • Improving forward manpower planning

                                             •W
                                               orking with the Resourcing Groups to make improvements to
                                              our support raising system

 4. B
     alancing prescriptive and              • Include this in the review process as we develop and set
    principle-based approach                    standards and policies

                                             •R
                                               eview whether the right balance is achieved between devolved
                                              decision making and centralised services

                                                                                     MAF Strategic Plan 2015 - 2019   31
“I know that MAF is not just a charter airline, but a
 true partnership in sharing the love and hope of our
 saviour Jesus”
 Gillian Parker, Reaching The Light Mongolia

32   MAF Strategic Plan 2015 - 2019
8
                                     CRITICAL
                            SUCCESS FACTORS
8.1 Prayer                                                            •   In close collaboration with MAF-US welcoming more
Unless the Lord builds the house, the builders labour in                   staff from the USA
vain (Psalm 127:1). As a mission we want and need to
be guided by God. That’s why prayer is such an integral               •   Improving our capacity to recruit and process staff from
part of what we do and why organisationally we put such                    countries where there is no MAF group
great emphasis on this through things like morning prayers,
pre-flight prayer, international days of prayer, weekly               •   Improve our manpower forward planning
PrayerPoints, and programme retreats. As we move forward,
in addition to the above, we intend to put greater emphasis           •   Implementing our reward strategy, which is aimed
on the spiritual well-being and growth of our staff3 for                   at getting greater parity among International Staff
effective discipleship.                                                    and which may, subject to ongoing discussion and
                                                                           consensus, see us move away from a 100% support
8.2 Recruitment                                                            level target. The latter is likely to mean an increase in the
Recruitment is an integral part of the strategy and elements               number of people willing/able to join MAF.
can be found under each of the three themes. However,
as there is such a close correlation between overall                  An indicative projection of staffing levels per programme can
ministry activity and number of International Staff it is worth       be found on the next page.
separating this out. The success of our recruitment strategy
is a key critical success factor, whereby acknowledging that          8.3 Programme effectiveness & efficiency
it is the Lord who calls people into ministry. Key elements of        With increased donor expectations on us to demonstrate
our recruitment strategy include:                                     ministry impact, it is key that we ensure that our resources are
                                                                      used in places of highest need and in the most efficient way.
•        ontinuing to work very closely with the Resourcing
        C                                                             Key activities to make ongoing improvements in this area are:
        Groups and encouraging them to actively find new staff
                                                                      •    eviewing and ‘upgrading’ our ministry effectiveness
                                                                          R
•        elcoming staff from Asia into MAF. In the Asia
        W                                                                 tool and using this tool to review our programme ministry
        Development Strategy we project that by 2019 we will              plans
        have 13 International Staff from Asia (India, Philippines,
        Singapore, and Malaysia) working in our programmes.           •    eveloping KPIs that help to us to monitor and improve
                                                                          D
                                                                          ministry efficiency
•        ecruitment and development of national staff into
        R
        missionary roles                                              •    nsuring that our management information systems are
                                                                          E
                                                                          fit for purpose and are meeting donor requirements

3
    See paper ‘Prioritising prayer in MAF’ for more details on this

                                                                                                    MAF Strategic Plan 2015 - 2019   33
Forecasted total number of International Staff in programme:

                         2011          2012     2013       2014       2015     2016     2017     2018     2019
 Programme
                       Actual         Actual   Actual    Actual      F’cast   F’cast   F’cast   F’cast   F’cast

 Arnhem Land                34           30       28           28       32       34       36       38       40
 Bangladesh                  4            3        2            2        4        4        5        5        5
 Chad                        4            3        4            5        4        4        5        5        5
 CRMF (PNG)                  2            2        3            2        3        3        4        4        4
 Liberia                   n/a           n/a      n/a          n/a       2        3        4        4        4
 Kenya                      22           24       19           11        9        8        8        8        8
 South Sudan               n/a           n/a      n/a           8       11       14       16       20       22
 Madagascar                  4            4        5            5        5        6        6        6        6
 Mongolia                    2            2        1            1        2        2        3        3        3
 Myanmar                     0            0        0            0        0        1        2        2        3
 PNG                        32           34       31           28       35       37       40       42       45
 South Africa                2            2        0            0       n/a      n/a      n/a      n/a      n/a
 Tanzania                   14           16       17            5        6        6        5        5        5
 Timor-Leste                 1            1        2            2        2        3        3        3        3
 Uganda                     14           13       13           21       19       18       17       16       15
 West-Africa               n/a           n/a      n/a          n/a      n/a      n/a      n/a       1        1
 Bougainville              n/a           n/a      n/a          n/a      n/a      n/a      n/a       1        1
 TOTAL                    135           134      125           118     134      143      154      163      170

It is assumed that 170 International Staff represents a
full complement of staff and that we will have achieved
this target no later than 2019. With attrition rate hovering
around 14%, we will need to recruit between 30 to 35 new
International Staff members each year. This is considered to
be an ambitious but achievable target. Furthermore, we will
also review what measures could be taken to decrease our
attrition rate at the same time.

34   MAF Strategic Plan 2015 - 2019
“We’ve been blessed more than we could have ever
     imagined. We’ve experienced God’s strength and
     comfort as we’ve moved our little family halfway
    across the world. And we’ve found joy amidst the
hardships and disappointments of this missionary life”
        Chris and Karyn Ball – Pilot family based in South Sudan

                                   MAF Strategic Plan 2015 - 2019   35
“I’m not trying to make our operation more efficient to earn more money
 for a faceless corporation; my team and I are trying to make our flying
 programme more efficient to allow more people to take MAF flights so that
 remote bush communities will have a better lifeline to the outside world,
 women will not die needlessly in childbirth and people will be able to read
 the Bible in their heart language. Nowhere else can you get that level of job
 satisfaction from sitting behind a desk”
 Siobhain Dales, Ground Operations Manager, MAF in Papua New Guinea

36   MAF Strategic Plan 2015 - 2019
9
                                                        FINANCIAL
                                                     IMPLICATIONS
9.1 Operational budget forecast
                                                 2014       2015        2016       2017         2018         2019
SUMMARY                                        Actual   Forecast     Budget      Budget      Budget       Budget
                                                $'000      $'000       $'000      $'000        $'000        $'000
INCOME
Africa Operations                               5,431      6,524       7,000       7,500      7,800        8,000
Asia Pacific Operations                         9,111      8,732      11,000      12,000     13,000       14,000
Members (Eons)                                 11,176     10,725      11,000      11,250     11,500       11,750
Members (Staff Support)                         2,434      2,294       2,400       2,500      2,600        2,700
Asia development - fundraising                      0          0          35          45        100          130
New technology services (incl consultancy)          0          0          25          25         50           50
Sub-total                                      28,152     28,275      31,460      33,320     35,050       36,630

EXPENSES
Africa Programmes                               8,910      8,384       9,000       9,500      9,800       10,000
Asia Pacific Programmes                        12,452     12,204      14,000      14,750     15,500       16,500
Support offices                                 6,504      7,271       7,200       7,400      7,600        7,800
Transfers to/from designated funds                236        110
Asia development                                    0        240         260         160        160          120
Seed-funding member groups                          0        300         250         250        250          250
New technology services (incl consultancy)                     0         100         200        300          400
Sub-total                                      28,102     28,509      30,810      32,260     33,610       35,070

Result                                            50          -234       650       1,060       1,440        1,560

Notes to the financial forecast:                                 3. Income and expenses for Asia development to be in
                                                                     accordance with the approved strategic plan for Asia
1. W
    e aim for the deficit between operational income and            development. This plan assumed EON funding would
   expenses for the Africa region to settle at $2m annually          rise to $130k in 2019 and a further $580k would be
   by having staff in the right place and through greater            raised for capital projects;
   efficiency.
                                                                 4. W
                                                                     e will continue to reserve $250k annually for
2. W
    e aim for the deficit between operational income and           Resourcing Group development.
   expenses for the Asia Pacific region to reduce from
   $3.5m in 2015 to $2.5m in 2019 through having more            5. W
                                                                     e will allow support office costs to increase with
   staff in AL and PNG and through greater efficiency;              inflation only.

                                                                                              MAF Strategic Plan 2015 - 2019   37
6. T
    he costs of new technology services and consultancy          This includes:
   type projects is expected to rise to $400k by 2019,            1. A Cessna Caravan for Liberia (2016) and one for
   but with only limited service income expected to be                Bangladesh (2017). Both are already approved projects;
   received for these services.
                                                                  2. T
                                                                      he purchase and development of land in South Sudan
7. R
    esourcing Group EON contributions from the bigger               (2015-2017);
   groups are forecasted to level out, but smaller groups
   continue to increase. It is recognised that this may be a      3. Completion of the Kajjansi office (2015);
   conservative assumption.
                                                                  4. B
                                                                      uilding additional houses on our compound in Kenya
The strategic plan aims for us to make an operational                (2016/2017);
surplus of around $1.5m annually by 2019. This will be
done primarily through increase programme ministry                5. Refurbishment/rebuild of 2 maisonettes in Chad (2016)
(resulting from having more staff) and bringing back a
healthier balance between operational activities and              6. P
                                                                      urchase of a house (from the Nazarenes) in PNG
expenses (including support office costs).                           (2015)

The forecasted surplus can/will be used in the                    7. A
                                                                      Cessna Caravan for Myanmar (2018) and one (their
following possible ways:                                             second one) Caravan for Arnhem Land (2019). Both are
                                                                     not approved projects at this stage;
•     ngoing investment in fleet renewal and other critical
     O
     capital items (e.g. hangars, housing, etc.) where these      8. Hangar in Juba, South Sudan (2017);
     are not funded with restricted funding;
                                                                  9. Two Cessna Caravan avionics upgrades per year;
•    Increased topping-up of International Staff as we move
      away from a 100% target;                                    10. Refurbishment of one more Twin Otter (2016);

•     llow for more highly-subsidised flying to take place for
     A                                                            11. Implement solar energy project across most
     high-impact flying and/or allow for more consultancy              programmes (2016 – 2019)
     type projects which don’t increase programme activity
     (in terms of hours flown), but would be considered high-
     impact ministry.

9.2 Capital budget
The following capital investments are planned:

                                    2014       2015       2016       2017       2018        2019       TOTAL
        SUMMARY                   Actual   Forecast     Budget     Budget     Budget      Budget      Budget
                                   $'000      $'000      $'000      $'000      $'000       $'000        $'000

Aircraft                             538        300       2,000     2,500       2,000       2,000       8,800
Aircraft upgrades                    991        350       1,350       350         350         350       2,750
Property                           1,190      2,000         750     1,000         500         500       4,750
Vehicles & equipment                 347        400         400       400         400         400       2,000

TOTAL                              3,066      3,050       4,500     4,250       3,250       3,250      18,300

38    MAF Strategic Plan 2015 - 2019