Price Review Submission - covering period 2016 to 2020 (PR4) Distribution System Operator (DSO) PR4 Overview (DF01) Status: Submitted to CER Date: ...

Page created by Helen Elliott
 
CONTINUE READING
Price Review Submission
         covering period
        2016 to 2020 (PR4)

Distribution System Operator (DSO)
      PR4 Overview (DF01)

    Status: Submitted to CER
         Date: 21/11/2014

   Public Submission Document
Table of Contents
TABLE OF CONTENTS                                                          01

 1.    DSO Executive Summary                                               03

 2.    DSO Introduction                                                    06

 3.    DSO PR4 Economic Environment                                        08

3.1.   ESRI’s Medium Term Review 2013-2020                                 08

3.2.   New Connections                                                     08

3.3.   Load Forecasting                                                    9

3.4.   Inflation                                                           10

 4.    Affordability                                                       11

 5.    WACC & Financeability                                               12

5.1.   WACC                                                                12

5.2.   Financeability                                                      13

 6.    DSO Capital Expenditure Programme                                   15

6.1.   Transmission                                                        15

6.2.   Smart Metering                                                      16

6.3.   Prioritisation of Distribution Capex                                16

6.4.   New Business                                                        18

6.5.   Generator Connections                                               18

6.6.   Line Diversions                                                     19

6.7.   Reinforcement                                                       19

6.8.   Non Load Related Network Expenditure                                21

6.9.   Non Network                                                         25

6.10. Electric Vehicles (EVs) & North Atlantic Green Zone Project (NAGZ)   31

 7.    Operating Expenditure                                               33

7.1.   Operation & Maintenance Costs                                       33

7.2.   Asset Management                                                    34

7.3.   Metering                                                            35

7.4.   Customer Services                                                   36

7.5.   Provision of Data                                                   37

                                                         1
Table of Contents
7.6.   Telecoms                     38

7.7.   Sustainability and R&D       38

7.8.   Rates                        38

7.9.   Other                        39

7.10. Efficiencies                  41

7.11. Benchmarking                  41

 8.    Pension Recovery             42

 9.    Asset Life                   43

9.1.   Distribution                 43

9.2.   Transmission                 43

10.    Climate Adaptation           44

11.    Incentives                   46

12.    Customer                     48

13.    Safety & Resourcing          51

13.1. Safety Strategy               52

13.2. Work Practices                53

13.3. Resourcing                    53

14.    DSO Conclusion               55

DSO Appendix                        56

                                2
1. DSO Executive Summary

ESB Networks Objectives & Economic Outlook
Despite the significant challenges that faced ESB Networks (ESB Networks) over the PR3 period of 2011 to 2015 due to
the severe economic downturn, the business successfully and substantially delivered on its licence obligations and key
objectives over the period. Critically, affordability and customer service targets will be maintained as compared to what
was anticipated when the determination was set. This was partially achieved by prioritising and deferring delivery of
elements of the PR3 infrastructure investment programme. As a result ESB Networks is now well placed to continue to
deliver successfully into the period 2016 to 2020 (PR4).

ESB Networks’ high level objectives for PR4 are to :
   • Continue to deliver a safe and reliable electricity distribution network for our customers and the economy through
       delivering key electricity infrastructure. This includes investing to enable renewables integration onto the network
       facilitating the achievement of the Irish Government RES-E target of 40% of energy consumed in the electricity
       sector coming from renewable sources

    •   Ensure safety of staff and the public

    •   Continue to provide excellent customer service and have due regard to customer affordability

    •   Lead the development of the Smart Grids /Networks sector in the Republic of Ireland

    •   Drive efficiencies within ESB Networks to create customer and shareholder benefit.

In contrast to PR3, the economic outlook for the PR4 period is positive. It is anticipated that the economy will return to a
reasonable rate of growth driving an increase in new connections and electricity demand.

Delivery of Networks Objectives In PR4:
    • ESB Networks is proposing a distribution capital expenditure programme of €1.8bn for the PR4 period which ESB
        Networks believes is the minimum expenditure required to support the delivery of a safe and reliable distribution
        system for our customers and the economy. In developing the final programme, ESB Networks was very conscious
        of the affordability impact on our customers. The PR4 plan is broadly in line with expenditure in the PR3 period
        with the exception of asset replacement and reinforcement expenditure which was controlled carefully in
        PR3, resulting in deferral of a large portion of required investment as set out in the historic submissions on
        Reinforcement and Asset Replacement. The base case submission does not include Smart Metering as the final
        investment decision has not yet been taken. However, further development and project costs necessary to take the
        project to the next major milestone in 2017 are included.

    •   ESB Networks is proposing to progress developments in the smart environment and to implement smart grid
        technologies and practices as the cornerstone of the networks business into the future.

    •   ESB Networks is committed to maintaining excellent customer service. ESB Networks is targeting:

        »»   maintaining strong customer satisfaction with service levels at 78%

        »»   Maintaining strong customer satisfaction within the National Customer Care Centre. To meet customers’
             needs to engage in more online and via social media, ESB Networks is proposing to put in place a new website
             to offer additional online services and a dedicated team to deliver services via a range of social media

        »»   Maintaining the reliability of electricity supply for our customers at 2009 levels. This will deliver a 60% improvement
             in the reliability of customers supply as measured by Customer Minutes Lost between 2001 and 2020

                                                                 3
1. DSO Executive Summary

        »»   Providing critical market services to electricity suppliers in line with service level agreements in areas
             including customer switching, meter reading, revenue protection services and providing Pay As You Go Meters
             for electricity customers in financial hardship.

    •   ESB Networks is fully committed to ensuring the health and safety of our staff, contractors, and the public. There
        have been 4 work based fatalities in our business in the last 4 years. In response ESB Networks has put in place a
        strategy to improve safety with the objective of ensuring that we are incident free. Implementation of this safety
        strategy has the potential to be disruptive to the delivery of our work programme. CER’s support in the delivery of
        our strategy will enable us to move forward effectively.

    •   An allowance of €1.5bn in Distribution Opex costs is sought which is €0.4bn greater than the PR3 allowance.
        In ESB Networks’ view, the maintenance allowance in PR3 was too low particularly with regard to the timber
        cutting allowance. ESB Networks spent more on maintaining network assets than was allowed despite, in the HV
        stations area, work completed being less than required and what industry norms would demand. ESB Networks is
        seeking a higher maintenance allowance in PR4 to ensure assets are appropriately maintained to deliver a safe and
        reliable distribution system for our customers. Other increases relate to rates increases, increased metering costs
        associated with the provision of PAYG meters to customers in hardship and increased revenue protection service
        requirements, improvements in customer service and costs associated with complying with increased safety
        and environmental legislation and safety related enhancements to work delivery structures safety management
        systems as well as training and competency assurance.

Financeability
Maintaining Networks financial strength is critical to enable ESB Networks to ensure continued, efficient and competitive
access to funding markets to enable it to fund the electricity infrastructure and activities necessary to deliver its licence
obligations and objectives and to earn an acceptable commercial return for ESB and its shareholders.

The following is ESB Networks’ proposal in relation to some of the main items which significantly contribute to ESB
Networks’ financeability:

    •   ESB Networks is proposing a reduction in the Weighted Average Cost of Capital from 5.2% to 4.98% for the PR4
        period on the basis that this is an appropriate return to enable ESB Networks to efficiently and competitively
        finance its activities. ESB Networks considers that this reduction in the cost of capital is justified by precedent and
        a broad assessment of the evidence. A reduction of WACC from 5.2% to 4.98% reflects market improvements but
        retains a long-term focus in mind for PR4 and reflects the considerable risk and uncertainty that still remains for
        the Irish economy in the medium term. This longer term focus is consistent with various regulatory decisions in
        the UK within the past five years. It also recognises that the Irish sovereign debt crisis has had a material effect on
        the cost at which ESB Networks was able to issue debt which will have an overhang effect over PR4.

    •   ESB Networks is seeking to recover the ESB Networks element (€462m)of the contribution payable by ESB to the
        ESB Defined Benefit Pension deficit as an additional opex allowance for recovery via regulated charges. Regulatory
        precedent followed by the CER and many other regulators including Ofgem, Utility Regulator, CAR, CAA, etc. is to
        allow recovery of deficit funding as incurred, i.e. in the period to 2018, and this indeed is our advisor’s (Oxera)
        recommendation. However, in the interest of managing price, ESB Networks is proposing recovery over a 13 year
        period. ESB Networks considers the pension agreement as a key achievement in the PR3 period that protects the
        customer into the future by reducing the risk profile of the scheme.

    •   ESB Networks has considered whether the 45 and 50 years asset lives for distribution assets and transmission

                                                              4
1. DSO Executive Summary

        assets is appropriate (transmission included in this document for completeness). Whilst ESB Networks considers
        that there are strong arguments for seeking recovery of distribution assets over a shorter timeframe, due to
        affordability concerns, ESB is making no request in this area. However, a core part of the submission is that ESB
        Networks is seeking recovery on transmission assets over a 45 year life in line with UK DNOs.

As CER is aware in the context of Financeability, Free Funds from Operations (FFO) / net debt is the key metric used by
Standard & Poor’s in its credit rating for ESB and as a result ESB Networks. In arriving at an appropriate PR4 revenue
proposal, ESB Networks has carefully considered all aspects of the business - the appropriate WACC, an appropriate period
for pension recovery and asset lives as well as the opex and capex programme. ESB Networks is strongly of the view that
the level of revenue required to enable it to competitively and efficiently finance a sustainable networks business should
deliver an FFO/net debt target of 15% in line with UK DNOs.

Customer Affordability
ESB Networks however is acutely aware of the economic pressures customers are under right now and has given significant
consideration to affordability in developing this proposal. ESB Networks’ final proposal is set to deliver a flat DUoS price
over the 5 year PR4 period. To deliver this end result, ESB Networks has had to accept a trade off between financeability of
the business and customer affordability. Whilst ESB Networks considers that delivery of a 15% FFO/net debt is necessary
to competitively and efficiently finance the business, ESB Networks accepts that in the interest of affordability, that this
target should not be achieved in this regulatory period. ESB Networks’ proposal will deliver an FFO/net debt of 13.4%
(12.5% excluding pension).

The resulting PR4 proposition, from a credit rating metrics perspective places ESB Networks towards the lower end of
the range for an A rated company. ESB Networks is strongly of the view that an FFO/debt level of 13.4% (12.5% excluding
pension) is absolutely critical to enable the business to secure competitive and efficient financing on an ongoing basis, to
facilitate the delivery of key infrastructure investment and delivery of our regulatory obligations for the benefit of our
customers and the economy. As ESB Networks does not believe that this will be sustainable into the future, ESB Networks
would welcome the opportunity to re-consider the higher target in PR5.

As noted above, ESB Networks tempered its pension deficit contribution recovery request, asset life consideration and
financeability target as a result of price pressures facing our customers. ESB Networks’ proposal will facilitate holding
DUoS prices at current levels in real terms over the five year PR4 period 2016 to 2020 (i.e. enable no DUoS price increase
in real terms over PR4).

Summary
In summary, Networks considers that this proposal for the PR4 period is appropriately balanced to ensure ESB Networks
can continue to deliver on its licence obligations to provide a safe and reliable distribution system for our customers and
the economy during PR4, whilst maintaining excellent customer service at an affordable price.

                                                             5
2. DSO Introduction

Despite the challenges over the PR3 period, ESB Networks (ESB Networks) successfully and substantially delivered on its
licence obligations and objectives during PR3. Critically, affordability and customer service targets will be maintained in
line with anticipated performance when the determination was set. As a result ESB Networks is well placed to continue to
deliver successfully into PR4.

ESB Networks’ High Level Objectives for PR4 are to :
    •   Continue to deliver a safe and reliable electricity distribution network for our customers and the economy through
        delivering key electricity infrastructure. This includes investing to enable renewables-integration into the network
        to facilitate the achievement of the Irish Government RES-E target of 40% of energy consumed in the electricity
        sector coming from renewable sources

    •   Ensure safety of staff and the public

    •   Continue to provide excellent customer service and have due regard to customer affordability

    •   Lead the development of the Smart Grids /Networks sector in the Republic of Ireland

    •   Drive efficiencies within ESB Networks to create customer and shareholder benefit.

ESB Networks is committed to bringing Ireland’s electricity networks to a world-class standard while also ensuring that
the networks can support Ireland’s stretching renewables and sustainability targets. Smart metering, intelligent networks
and increased electrification, including electrification of transport and heat, will all play key roles in a very different energy
infrastructure of the future. ESB Networks will play a central role in the successful delivery of this infrastructure. The base
case submission does not include smart metering as the final investment decision has not yet been taken. However, for
completeness, ESB Networks provides sensitivities on all key metrics that reflect the investment proceeding in line with
the Smart Metering Cost Benefit Analysis (CBA).

ESB Networks are acutely conscious of the enormous global and national challenge, in terms of environmental and energy
sustainability. The strategies and targets emerging to address climate change in terms of CO2 reduction, renewable energy
and energy efficiency are stretching. Energy networks, and electricity networks in particular, will be at the heart of their
delivery. ESB Networks will play a key enabling role in the integration and penetration of renewable energy sources,
deployment of distributed generation, the roll-out of demand side management (DSM) programmes and transport
electrification. Over the next five to ten years ESB Networks will need to develop the network to be smarter, more accessible,
more flexible and more efficient, while all the time operating them cost-effectively, reliably and safely.

Whilst all efforts have ben made to keep capital investment levels at an affordable level, the capital investment required
in PR4 is still significant. Good financial performance, while not the only measure of success, is critical to ESB Networks’
future as a business. ESB Networks has a mandate to earn appropriate commercial returns for ESB and its shareholders,
while meeting the challenges of regulation and meeting responsibilities to customers, the electricity market, and the wider
national economy and society. To be financially successful in the longer term, ESB Networks must continue to improve
business performance in the form of increasingly efficient delivery of services to customers. This will ensure that the
rising debt levels facing the business can be supported and customer costs minimised.

In that context, ESB Networks’ objectives for PR4 are :
     • Hold DUoS charges at 2015 levels in real terms over the five year period of PR4 while continuing to develop and
         maintain a safe and reliable network for our customers and the economy
     • Increased safety levels for members of the public and employees
     • Address deficiencies such as plant overloading, non-compliance with voltage standards and breaches of safety
         standards (short circuit deficiencies)

                                                                6
2. DSO Introduction

   •   Replace aging and defective assets that are reaching, or have passed the end of their useful technical life
   •   To maintain and improve network continuity performance and safety
   •   To integrate new technologies and systems which reduce the lifetime cost of assets, and allow for performance
       improvement in an informed and effective manner
   •   To maintain excellent customer service cost-effectively delivered across the Customer Service spectrum
   •   The connection of a predicted additional 108,000 new customers as required
   •   Achievement of national renewable energy targets by the connection of significant amounts of renewable
       generation capacity to the distribution system within the gate processing system
   •   To enable an improvement in national energy efficiency through the roll out of a smart metering project subject to
       CER decision to proceed and through ongoing efficiency and loss reduction measures on the network
   •   To implement smart grid technologies and practices as the cornerstone of the networks business into the future.

This document sets out the key facets of ESB Networks’ proposal.

1.		   DSO PR4 Economic Environment
	ESRI in their Medium Term review 2013-2020 consider three possible scenarios or paths for the economy because
  of the uncertainty about the future - Recovery, Delayed Adjustment and Stagnation. ESB Networks has taken the
  Recovery Scenario as a base assumption in developing the PR4 proposal.

1.1.   ESRI’s Medium Term Review 2013-2020 DSO PR4 Economic Environment
	ESRI in their Medium Term review 2013-2020 consider three possible scenarios or paths for the economy because
  of the uncertainty about the future - Recovery, Delayed Adjustment and Stagnation. ESB Networks has taken the
  Recovery Scenario as a base assumption in developing the PR4 proposal.

2.		   DSO PR4 Economic Environment
	ESRI in their Medium Term review 2013-2020 consider three possible scenarios or paths for the economy because
  of the uncertainty about the future - Recovery, Delayed Adjustment and Stagnation. ESB Networks has taken the
  Recovery Scenario as a base assumption in developing the PR4 proposal.

2.1.   ESRI’s Medium Term Review 2013-2020
	ESRI sets out the scenario as follows: (see following page)

                                                           7
3. DSO PR4 Economic Environment

ESRI in their Medium Term review 2013-2020 consider three possible scenarios or paths for the economy because of
the uncertainty about the future - Recovery, Delayed Adjustment and Stagnation. ESB Networks has taken the Recovery
Scenario as a base assumption in developing the PR4 proposal.

3.1 ESRI’s Medium Term Review 2013-2020
ESRI sets out the scenario as follows:
 ‘’In the Recovery scenario, the EU economy is assumed to return to a reasonable rate of growth over the rest of the decade. It
is also assumed that the continuing problems in the Irish financial sector are tackled effectively. Under these circumstances,
the export sector of the economy would see its markets grow, resulting in increases in output and employment. In turn,
growth in foreign demand would help produce a turnaround in domestic demand. As firms increase their sales and their
profitability they would need to invest to continue growing. With rising real personal incomes and growth in employment,
consumption would also begin growing again.

Demographic pressures would mean that more dwellings would need to be built later in the decade and a recovery in
household circumstances would suggest that this investment could in theory, be financed. Overall, this scenario would
see growth in GNP of around 3.5 per cent a year in the second half of the decade (Table 1). While the economy would not
be likely to reach full employment by 2020, the level of unemployment could be more than halved to around 6 per cent.

Finally, the Irish growth model remains vulnerable to shocks from outside Ireland. As a result, it will be important that the
driving force behind the export sector moves gradually away from businesses that are dependent on the low corporate tax
regime to businesses that rely on other aspects of Ireland’s competitive advantage.’’

ESRI Summary table:
                                                2013          2014         2015          2016      2017   2018        15-20
                                                       Recovery Scenario
 GDP, %                                          1.7           3.0          4.0          4.1        4.2     3.7           4.0
 GNP, %                                          1.2           0.5          4.3          3.6       4.0     3.4            3.6
 General Govt. Deficit, % of GDP                 7.3           5.0          3.2          1.2       0.4     0.3            1.0
 Unemployment Rate, % of Labour Force           14.0           13.4         11.8         10.6       9.5    8.2            5.6

                                                       Figure 1: ESRI Summary Table

3.2 New Connections
For 2016 to 2020, the anticipated volume of new connections is expected to grow gradually from the dip of the previous
five years (2011-2015) to the levels as predicted in the table below based on increases in population, declining emigration
and government support in financing programmes for the construction of social and affordable housing units. 2016
2017    2018 2019 2020
 G1 - New housing Schemes                        7,000                    8,500                 9,500             11,500
 G2 - Non-scheme Houses                          5,500                    6,000                 6,500             7,000
 G3 - Commercial/ Industrial Supplies            4,500                    4,500                 5,000             5,500
                                                 17,000                   19,000                21,000            24,000
                                                 Figure 2 - Forecasted New Connections

                                                                  8
3.3 Load Forecasting

Methodology
The essence of load forecasting is to examine the current trends driving growth in demand for electricity, to identify
the key factors involved, to determine how these factors are likely to change over the forecast period and to quantify the
impact of such changes. The fundamental methodology therefore is to obtain as complete and accurate a description of the
existing load composition and behaviour as possible. With this it is possible to identify the key factors driving growth at
present and in the immediate past and then to project load growth based on the expected behaviour of these factors over
the time period of interest.

Key load information includes the following:

    •   Sales by customer type (Domestic, Commercial / Institutional and Industrial)

    •   Customer numbers by type including some breakdown of residential customers by level of consumption

    •   Load composition - some forms of electricity use can have significant growth potential in an expanding economy,
        e.g. air conditioning, while others are subject to reducing demand due to technology / efficiency improvements, e.g.
        lighting – fluorescents, compact fluorescents (CFLs), etc

    •   Economic performance - mainly measured by Gross Domestic Product (GDP) and its composition across the major
        sectors of the economy. Inflation is also relevant and is measured to Consumer Price Index (CPI)

    •   Electricity price / tariff data is needed to assess the impact of price changes on consumption

    •   Population data - information is needed on population growth and major population movements, e.g. from rural
        to urban locations

    •   Technology - changes in end use applications and appliances. For example more widespread use of air conditioners
        could increase demand significantly, while the use of more energy efficient motors, lighting, etc. can reduce demand

    •   Weather - changes in average seasonal temperatures.

Analysis & Results
Following analysis of all constituents above, the following trends were noted:

    •   System demand has started to show signs of recovery

    •   Average consumption per customer on residential side has been broadly unchanged through the recession;
        reduction in demand driven instead by the reduction in the number of houses

    •   Economic growth (GDP ) returning from 2012 onwards

    •   Housing construction continued to fall through 2013 but this trend is expected to reverse over time with a forecast
        of annual new connections of 27,000 in 2020.

                                                             9
3.3 Load Forecasting

The overall forecast based on this analysis is that distribution sales are anticipated to gradually increase over the PR4
period. This is exhibited in the graph below:
           35,000

           30,000                                                                                 ■   Adjustments
                                                                                                  ■   110kV Network
           25,000
                                                                                                  ■   38kV Tailed
           20,000                                                                                 ■   38kV Looped
                                                                                                  ■   MV
           15,000
                                                                                                  ■   LV MD
           10,000                                                                                 ■   LV Non MD
                                                                                                  ■   Public Light, Misc.
            5,000
                                                                                                  ■   Rural Domestic
               0                                                                                  ■   Urban Domestic
                    2013     2014     2015       2016      2017        2018       2019    2020
                                                  Figure 3: Distribution Sales Forecast

The overall impact is a 25% increase in sales between 2015 and 2020. It should be noted that a significant portion of this
increase is driven by the major new loads forecast (but not confirmed) to connect over the period. Excluding these loads,
the normalised cumulative growth over the period is closer to 10%.

3.4 Inflation
In PR1 (2001 to 2005) and PR2 (2006 to 2010) the CER used CPI as the index to inflate revenue. During the PR3 review
process the issue arose as to whether CPI or HICP would be more appropriate to use. This was mostly driven by the fact
that CPI (which includes mortgage interest and house prices) was more volatile during a period with exceptional economic
conditions. As a result, CER moved to using HICP for PR3.

Low inflation is a significant risk to ESB Networks due to the fact that revenues are indexed. Added to this is the fact that
debt bears a fixed interest rate which further increases downside risk. Prolonged low inflation can ultimately impact
cashflow and hence credit ratings.

Moody’s in particular have highlighted low inflation as a particular risk to ESB Networks. In its commentary “Low Inflation
is Credit Negative but Exposure Varies by Regulatory Framework” issued in April 2014, it states that regulated energy
network issuers in France, Ireland, Italy and the Netherlands are most affected by low inflation because their asset base
will fall in value, increasing leverage. The report goes on to say that the mechanism for allowing revenue becomes very
significant in low inflation environments because of the risk of fixed debt payments and fixed staff costs for entities that
earn a real return. Regulated entities subject to a nominal return are much more protected because the allowed regulatory
return and the value of the RAB will stay at the same level, thus protecting cash flows and debt serviceability.

ESB Networks is therefore very exposed from a credit rating / financeability perspective by virtue of the fact of having a
real WACC and fixed debt servicing costs. For this reason ESB Networks propose reverting to CPI as the indexation factor
for PR4. This is consistent with RIIO-ED1 which continued the use of RPI by Ofgem.

ESB Networks is using the following indexation assumption in projecting revenues for the PR4 period.

                                          2016          2017                   2018              2019                       2020
    Annual CPI Rate              1.50%                1.50%                   1.50%              1.50%                      1.50%
  Cumulative CPI Rate            1.0252              1.0405                   1.0561             1.0720                     1.0881
                                                    Figure 4: CPI Assumption table

                                                                10
4. Affordability

Affordability has been a key consideration for ESB Networks in the PR3 mid term WAAC review and in developing its PR4
proposal. Key areas of focus have been:

    •   Prioritisation of infrastructure investment expenditure for the PR4 period. This is covered further in Section 6 of
        this submission

    •   A proposed WACC reduction for the period from 5.2% to 4.98%

    •   Efficiency savings of 1% per annum of non-controllable opex are taken into account within the numbers i.e. 5%
        cumulative over PR4

    •   Instead of seeking pension deficit recovery over the period 2016-2018 as regulatory precedent would indicate, ESB
        Networks is seeking recovery over 13 years

    •   Although ESB Networks considers that ESB Networks, as with comparable DNOs, should deliver an FFO/net debt
        performance of 15%, ESB Networks accepts that there is a trade off with customer affordability and than that, in
        this context, it is not possible in this price review period and is seeking more a moderate revenue stream

    •   Although ESB Networks considers that ESB Networks should be recovering investment on distribution asset over
        a shorter lifetime than the UK DNOs, ESB Networks is seeking no change in this respect.

The Average Unit Price (AUP) impact of ESB Networks’ PR4 submission is as set out below:

 Parameter                                 Base Case                                Smart Metering Sensitivity
 DUoS Revenue                                €3.5bn                                              €3.7bn
 AUP % increase                                0%                                                 8.8%
 Impact of DUoS on end user                    0%                                                 2.1%
                                 Figure 5: Average Unit Price (AUP) impact of ESB Networks’ PR4 submission

See further detail on DUoS revenue and AUP in Appendix 1. ESB Networks’ proposal will facilitate holding DUoS prices
at current levels in real terms over the five year PR4 period 2016 to 2020 (i.e. enable no DUOS price increase in real terms
over PR4).

ESB Networks considers that this price review proposal delivers excellent value to the customer at a time when affordability
is an issue.

                                                                 11
5. WACC & Financeability

5.1 WACC
Recent European regulatory precedent has seen a decline in allowed returns for regulated utilities. This is concerning as
Eurelectric research shows that lower returns result in lower investment. ESB Networks believes that it is critical that the
business earns an adequate return over the PR4 period to ensure that revenues are maintained at a level that will attract
debt investment. Both the distribution and transmission systems are in need of significant investment over the period
2016-2020.

ESB Networks has engaged Frontier Economics (Frontier) to carry out an independent assessment of the appropriate level
of allowed WACC for PR4 to enable ESB Networks to efficiently and competitively finance its activities. On Frontier’s
advice ESB Networks is proposing a reduction in the Weighted Average Cost of Capital from 5.2% to 4.98% for the PR4
period on the basis that that this is an appropriate return to enable ESB Networks to efficiently and competitively finance
its activities.

The WACC components for the 4.98% proposal are summarised in the following table:

                                            Mid-Term Review                              Estimate for ESB Networks PR4
 Gearing                                            55%                                              55%
 Risk-free rate                                      2%                                               2%
 Debt premium                                       2.2%                                            1.75%
 Cost of debt                                       4.2%                                            3.75%
 ERP                                                 5%                                              4.6%
 Asset beta                                          0.3                                             0.36
 Equity beta                                        0.67                                              0.8
 Cost of equity (post-tax)                         5.35%                                            5.68%
 Corporate tax                                     12.5%                                            12.5%
 Cost of equity (pre-tax)                           6.1%                                            6.49%
 WACC (pre-tax)                        5.05% (5.2% with aiming up)                                  4.98%
                                          Figure 6: Weighted Average Cost of Capital Components

ESB Networks considers that a reduction in the cost of capital is justified by precedent and a broad assessment of the
evidence. The reduction proposed reflects market improvements but does not, in determination of appropriate WACC
parameters, follow that market to the all time low levels evidenced right now. It is important to have a long-term focus
in mind for PR4 and as a result we consider that the CER should take a cautious approach in any downward adjustment
as considerable risk and uncertainty still remains for the Irish economy in the medium term. This longer term focus is
consistent with various regulatory decisions in the UK within the past five years. It also recognises that the Irish sovereign
debt crisis has had a material effect on the cost at which ESB Networks was able to issue debt which will have an overhang
effect over PR4.

ESB Networks believes that this balance will provide important clarity and consistency to debt investors at a time when
economic conditions remain weak and future prospects remain uncertain across the Eurozone. This may be expected to
increase investor confidence and ultimately lower the cost of capital in future to the benefit of customers.

                                                                12
5.2 Financeability

CER has an obligation to ensure that ESB Networks is capable of financing its operations. The CER has interpreted this
clause such that the obligation is to ensure that an efficient licence holder is capable of financing its activities.

Rationale for Targeting a Strong, Investment-Grade Credit Rating
It is imperative that ESB Networks achieves a strong, investment-credit rating to ensure continued access to funding
markets. The reasoning behind this is as follows:

a)   ESB Networks has significant funding requirements as it is consistently in a cash-negative situation due to its long
     term electricity infrastructure investment programme. The business has larger capex programmes than most peers
     relative to size of company which is currently predominantly driven by transmission spend. In addition, approx. €2.5bn
     of ESB debt is maturing during the PR4 period.

b)   As a state-owned entity, ESB is entirely dependent on debt markets for funding. If markets are not available to raise
     cash, without action, available funds would run out and capex would have to be constrained (as in 2011).

c)   ESB (and by extension, ESB Networks) competes for capital from the same investor pool as its UK and European peers.
     The majority of ESB Networks peers are rated at BBB+/Baa and above, however for a number of reasons ESB could be
     perceived as a more risky credit. These reasons are as follows:

             •   ESB Networks is inextricably linked to the Irish economy both by virtue of being state-owned and because
                 of the geographic focus of the business. During the recent economic crisis ESB’s rating (and ESB Networks’
                 rating were it rated) was constrained by the Irish sovereign credit rating and financial markets were
                 effectively closed to ESB at this time. Although this risk has receded somewhat over the last 18 months, it
                 is still a consideration for investors, who see Irish credits as more risky than UK peer credits, for example.

             •   The majority of ESB Networks’ peers have access to equity, either through being listed companies or through
                 shareholders which are willing to commit capital. The ability to raise equity, or to retain cash within the
                 business through reducing dividends allows companies to maintain credit quality, however these options are
                 not open to ESB. In investors’ eyes, therefore, there are fewer sources of funds open to ESB to service debt.
                 ESB therefore needs to be perceived as a stronger credit than its listed peers in order to offset this risk.

d)   ESB Networks’ advisors have indicated that a strong investment grade rating is essential to refinance maturing debt
     and to raise funding for additional capital expenditure at optimal rates. Bond yields have been volatile over the years
     of the financial crisis and investors will expect to see certainty on credit ratings over the medium term prior to
     committing to purchasing long-dated bonds. Higher interest costs, shorter maturities and onerous financial covenants
     could result if a lower credit rating is received.

Appropriate Target Credit Rating Metrics for ESB Networks
ESB Networks has carefully considered financeabiity and has determined that the appropriate rating for a stand alone
networks company situated in Ireland would be an A- /A3 rating from S&P and Moodys respectively to ensure Financeability
on an ongoing basis. This rating is required to protect ESB Networks against the Irish sovereign credit risk premium and
ensure consistent access to funding throughout PR4.

In the context of Financeability, Free Funds from Operations (FFO) / net debt is the key metric used by Standard & Poor’s in
its credit rating for ESB and as a result ESB Networks. Having considered all of the evidence, ESB Networks believes that
an appropriate FFO/Net debt target for ESB Networks for PR4 is 15%. This level of performance is in line with the UK DNOs
(rated BBB+ / Baa) and ensures that ESB Networks can maintain a level of headroom over the target that Standard & Poors
sets for an A rated entity (13%). This headroom is consistent with all UK DNOs and Rating agency practice.

                                                              13
5.2 Financeability

Having considered the still relatively low levels of growth anticipated over PR4 and having due regard for customer
affordability, ESB Networks considers that this is this FFO/Debt target of 15% should not be achieved in this regulatory
period. The overall proposal will deliver an FFO/net debt of 13.4% (12.5% excluding pension). The resulting PR4 proposition,
from a metrics position places ESB Networks towards the lower end of the range for an A rated company. As ESB Networks
does not believe that this will be sustainable into the future, ESB Networks would welcome the opportunity to re-consider
the higher target in PR5.

The key credit rating metrics resulting from ESB Networks’ proposal are as follows:

                              PR4 Submission                                 Sensitivity with Smart Metering
 FFO/debt                          12.5%                                                      12.3%
 FFO/Interest                      3.2%X                                                       3.2%
 Net Debt/RAV                      52.7%                                                      54.2%
                                 Figure 7: Key credit rating metrics resulting from ESB Networks’ proposal

ESB Networks is strongly of the view that for PR4 this 13.4% (12.5% excluding pension) FFO/debt level is the minimum
performance required that will enable the business to secure financing competitively and efficiently to facilitate the
delivery of key infrastructure investment and ESB Networks’ regulatory obligations in PR4.

Further detail on this area is set out in a separate submission, DF57 WACC & Financeability.

                                                                 14
6. DSO Capital Expenditure Programme

ESB Networks is proposing a capital spend for PR4 that is broadly in line with PR3 with the exception of asset replacement.
The following summarises ESB Networks’ planned capital expenditure (before capital contributions) for the price review:

                                             PR4 Projected (2014 real)                     PR3 Projected (nominal)
 New Business                                            305                                        229
 Generation Connections                                  109                                         87
 Line Diversions                                          92                                         52
 Distribution Reinforcement                              318                                        321
 Asset Replacement                                       596                                        392
 NAGZ                                                     88                                          -
 IT, Telecoms, Fleet & Premises                          172                                        103
 Smart Metering                                           23                                         15
 Dismantling                                              71                                         53
 Total Distribution                                     1,774                                       1,252
 Transmission *                                         1,239                                      1,048
 Total                                                  3,013                                      2,300
 * Transmission CAPEX is included for completeness
                                             Figure 8: DSO Capital Expenditure Programme

Capital contributions from distribution and transmission customers are estimated to be €214m and €116m respectively.

Distribution capex is forecast to be €1.77bn compared to a final outturn for PR3 of €1.25bn. The main elements of the
increase are due to the following reasons:

    •    €0.1bn as a result of increased new connections and associated line diversions due to pick up in the economy. This
         is largely outside of the control of ESB Networks and may increase or decrease based on customer behaviour

    •    €0.3bn in Asset Replacement to meet the required investment that was deferred during PR3

    •    €0.1bn Non-network investment to meet the systems requirements that were deferred during PR3.

6.1 Transmission
As noted above, the transmission capex is included for completeness of the capital expenditure. This expenditure is driven
by EirGrid and a separate submission TF01 Transmission Capex Overview sets out this expenditure in more detail from
the TAO perspective.

                                                                15
6.2 Smart Metering

As mentioned in the introduction, the base case PR4 submission does not include the full Smart Metering capex as the
decision to proceed has not yet been taken. The next phase of the National Smart Metering Program (NSMP) involves :

    •    Designing the regulatory framework to support policy decisions

    •    Designing the changes to the retail market to support implementation of policy decisions

    •    Designing the approach to timing and sequencing of delivery of decisions

    •    Launch of ESB Networks procurement of the high cost products and services, once sufficient information is made
         available.

ESB Networks will not award any contracts from this procurement process or proceed with full roll out as it is the intention
of CER to reassess the case for smart metering at that point, before the CER go/no go decision.

ESB Networks estimates that the cost of this next phase of work which will be completed in Q2 2017 at a cost in PR4 of €23m.
As per the current Cost Benefit Analysis (CBA) the expected capital spend on smart metering in the 2016-2020 period is €798m.

6.3 Prioritisation of Distribution Capex
In developing the final programme, ESB Networks was very conscious of the affordability impact of PR4 plans, particularly
in relation to the larger asset replacement and reinforcement programmes. As a result, a number of steps were taken to
reach the final programme:

    1.   An initial assessment of required expenditure was carried out (Safety, Reliability, Policy & Environment)

    2.   A Risk & Cost Benefit analysis was carried out on each element of the Asset Replacement programme

    3.   An independent high level review of initial assessment was commissioned

    4.   An independent unit cost benchmarking was commissioned.

Step 1: Initial Assessment
ESB Networks set out all proposed programmes on a prioritised basis. The following categories were used:

 Priority            Programmes
 Mandatory             •   New Connections
                       •   Response CAPEX
 Priority 1          Safety driven programmes
                       •   Plan to keep safety risks at a level that is in line with UK DNOS and European DSOs
 Priority 2          Security of Supply Driven Programmes
                      •    Expenditure mainly driven by requirement to meet planning standards
                      •    Based on forecast loads adjusted for SMART metering impact
                      •    Include also “Elevated” N - 2 Risks
 Priority 3          Renewal CAPEX
                       •   Programmes that reduce risk and improve continuity

                                               Figure 9: Prioritisation of Distribution Capex

                                                                  16
6.3 Prioritisation of Distribution Capex

Step 2 Risk & Cost Benefit Analysis
All proposed programmes were then considered from a risk and cost benefit perspective using a methodology developed
with EA Technology as part of the PR3 process. This is a similar method to that used by DNOs in GB and elsewhere. The
following formula is applied:

                                                   Benefit (∆ Risk , ∆Cost)
                                                              Cost
                        Where Risk = Probability of Failure / Event X Consequence f ( s, r, c, e )
                                                   s = Safety
                                                   r = Continuity of Supply
                                                   c = Cost
                                                   e = Environment

Each programme was essentially considered in context of ways the asset could fail and the impact of those failures.
A lower programme of work developed following this process.

Step 3 Independent High Level Review of Initial Assessment
ESB Networks requested Parsons Brinckerhoff (PB) to consider and review the strategies, policies and practices adopted in
assessment of load related and renewal expenditure forecasts for the PR4 period by comparison with GB DNO practices.

The review concluded that expenditure planned is broadly in line with that of UK DNOs. The following extracts from the
report support this:

            •   ‘An initial ‘order of magnitude’ benchmarking assessment against DNO companies with similar customer
                numbers or line length shows that this sum is of the right order of magnitude if not low.’

            •   ‘The basis of the forecast is sound and is unlikely to lead to stranded network capacity. If anything it exposes
                ESB network to a level of risk since load growth will undoubtedly take place and there may be little benefit
                gained for some time from the introduction of SMART metering or from legislation intended to introduce
                efficiency initiatives’ .

            •   ‘Bearing in mind that the submission as a whole appears low and since the load related content of
                the submission is proportionally high compared to the ratio of DNO load related expenditure to asset
                replacement expenditure, there appears to be prima facie evidence that the asset replacement expenditure
                has already been minimised’.

The review has given ESB Networks significant confidence that the programme proposed is in line with peers, is unlikely to
result in stranded assets and is investing in asset replacement at a level that is adequate yet affordable.

Step 4 Independent Unit Cost Benchmarking
Results to date from unit cost benchmarking indicates that ESB Networks’ construction costs are well within comparable
DNO costs for lines and cables and comparable with equivalent DNO’s costs for substations.

Expenditure in this area is expected to rise from a forecast of €229m in PR3 to €305m in PR4. The PR4 period is expected
to see modest customer growth. For 2016 to 2020, the anticipated volume of new connections is expected to grow gradually

                                                                17
6.4 New Business

from the dip of the previous five years (2011-2015) to the levels as predicted in the table below based on increases in
population, declining emigration and Government support in financing programmes for the construction of social and
affordable housing units.

                                            2016              2017              2018         2019            2020
 G1 - New housing Schemes                   7,000             8,500              9,500       11,500           13,500
 G2 - Non-scheme Houses                      5,500            6,000              6,500       7,000            7,500
 G3 - Commercial/ Industrial Supplies        4,500            4,500              5,000       5,500            6,000
                                            17,000            19,000            21,000       24,000          27,000
                                                Figure 10: New BusinessForecast PR4

Supply of new housing (G1 & G2 connections, especially in regions around the greater Dublin area, is short and prices are
beginning to rise. ESB Networks expects to see a rise in completions in the forthcoming PR4 period due to this correlation.
The significance of this rise is expected to be modest as the current rates of price rises are believed to be unsustainable,
therefore, dampening the supply growth levels.

Non-Domestic connections cover a wide variety of types of connections. Therefore, it is more difficult to link/correlate
these new connections to external factors such as house prices. It is forecast that these G3 connections are likely to remain
at approximately 5,500 for the duration of PR4.

See DF05 New Connections for further detail.

6.5 Generator Connections
The PR4 period covering years 2016-2020, will cover the majority of the construction of the Gate 3 projects that have
contracted in mid-2013, and the remainder of the Gate 2 projects which have not connected to date.

A projected renewable generation capacity of 1,250MW has been estimated to be connected to the distribution system
in this 5 year time period. This is less than the current level of contracted generation, as it is generally expected and
acknowledged that not all the contracted Gate 2 and Gate 3 connections will progress through to connection, for various
reasons. Currently, ESB Networks’ best estimate of renewables that will connect to the distribution system is as follows

                                                                 Distribution Connected
 PR2                                                                         600
 PR3                                                                        1200
 PR4                                                                        1250
                                                                            3,050
                                            Figure 11: Generator Connections Forecast PR4

ESB’s estimate of capital expenditure in this area for the PR4 period is €109m. Given the expectations of receipts towards
the close of PR3 to meet the REFIT deadline, it is driving most of the PR4 expenditure into the early years with almost 75%
(€82m) of the total amount forecast to be incurred in the first two years (2016 and 2017), and the remaining 25% (€27m)
spread out over the latter three years as further projects progress to completion.

ESB Networks provides non-chargeable line diversions for customers in return for use of land, whereby if the customer

                                                              18
6.6 Line Diversions

decides to develop his or her land, line diversions are carried out at no charge to the customer. Therefore, line diversions
are strongly correlated to land development or “New Demand Connections” .

In PR3 the sum allowed for line diversions was based on 11.4% of the cost of New Demand Connections whilst the outturn
is forecast to be 22%. This rising percentage is due to the fact that there is a portion of line diversions that arise from
developments not needing a new connection, e.g. farm sheds. With new connections being at a such a low level, these now
represent a higher proportion of the line diversion cost.

The Line Diversions forecast of €92m has been based on a long term historical performance from 2006 to 2013. This
long term approach has been taken due to the recent variance in the PR3 period. Based on these recent lower outliers in
PR3, an objective method of determining a true reflection of the forecast costs is to apply a linear trend to the average of
all costs from the PR2 and PR3 periods inclusive. Further detail on this proposal can be found in DF28 Line Diversions.

6.7 Reinforcement
                                                PR4 Proposal                                  PR3 Forecast
 HV Reinforcement                                   €252m                                        €227m
 MVLV System Improvements                           €41m                                          €34m
 20kV Conversion                                    €25m                                          €60m
 Total Reinforcements                               €318m                                        €321m
                                                Figure 12: Reinforcement PR4 & PR3

HV Reinforcement
Two major studies have been carried out by ESB Networks to identify the HV load related investments required over the
next ten years, i.e. the National HV Network Investment Plan and the Dublin HV Investment Plan. These documents set
out in a very detailed way how the 110kV and 38kV Distribution Networks will need to be reinforced in order to bring these
networks within Distribution Planning Standards.

The Network load related reinforcements that have been proposed for delivery during the PR4 period are based on a zero
cumulative load growth forecast for peak demand from 2013 -2020. Although there is uncertainty in relation to the timing
of Smart Metering roll-out, the submission has been further refined to take account of the introduction of Smart Meters
which is expected to reduce the contribution of domestic load to system peak by 8%. On the basis that domestic load
comprises approximately 50% of the total load the total peak is expected to be reduced by 4%.

Following an increase in electricity consumption of 70% between 1995 and 2010, demand electricity reduced by 3% in 2011
to 2013. In this context even though there has been significant expenditure on the networks over the three previous price
reviews, there are still deficiencies on the network. These are present due to the high load growth that occurred since the
early nineties through to the second half of the last decade when the economy went into recession. The level of investment
in the Distribution Networks during the nineties was minimal when the principal objective during that pre-regulation
period was to contain the price of electricity while ensuring that there was adequate generation capacity available.

The PR4 programme will address deficiencies such as plant overloading, non-compliance with voltage standards and

                                                             19
6.7 Reinforcement

breaches of safety standards (short circuit deficiencies). A programme of network reinforcements is proposed to address
these breaches of planning and safety criteria and includes:

    •    Provision of additional 110kV, 38kV and MV and LV circuits

    •    Development of new 110/38kV, 110kV/MV, 38kV/MV or MV/LV Substations

    •    Installation of 110kV and 38kV and MV/LV transformer capacity.

The planned expenditure programme is as follows:

 Voltage                              PR4 Submission €m                                    PR3 Expected Spend €m
 110kV                                        165.6                                                142.7
 38kV                                          85.9                                                84.4
 MV/LV                                         40.9                                                33.5
 Total                                        292.4                                                260.6
                                              Figure 13: HV reinforcement forecast spend

The increase in the projected expenditure on 110kV reinforcements in PR4 over the expected expenditure in PR3 reflects
the deferral of projects in the last price review. Examples include new 110kV substations to replace existing overloaded 38kV
substations or to provide relief to the existing 38kV Network. The projected level of expenditure on 38kV reinforcements
in PR4 reflects the reduction in the numbers of overloaded 38kV Substations but provides for the uprating of those
substations that remain overloaded. There has been significant reduction in MV/LV expenditure over the past three price
reviews, reducing from €139m in PR1 to a projected expenditure of €40.8m in PR4.

MVLV System Improvements
MV/LV network reinforcements are carried out to address deficiencies that arise on any part of the MV or LV network.
The work carried out under this programme is response in nature, driven by growth in the networks where network is
overloaded, voltage needs to be improved and protection systems upgraded.

While other programmes for asset replacement or capital work on the medium and low voltage networks deal with specific
concerns on these networks such as the replacement of MV switchgear or the LV renewal programme, the MV/LV Network
reinforcement budget addresses the operational performance of the MV and LV network in the area of continuity and
voltage. The programme is comprised of a large volume of small individual jobs.

20kV Conversion
20kV conversion is the optimum and most effective means of addressing the major voltage problems associated with long
rural networks but also provides significant additional capacity and strengthening of local rural networks without the
requirement for HV Substation reinforcement.

Significant progress has been made on the conversion of the rural 10kV overhead networks to 20kV operation. By the end
of PR3 47,000km of MV Networks will have been converted to 20kV operation which represents 57% of the total length of
MV Overheard Network. For PR4 it is proposed to convert a further 4,000km to 20kV operation at a cost of €25.3m. These
proposals are being driven by the need to address significant voltage issues on the identified networks.

ESB Networks has adopted a clear and focussed strategy in developing its asset renewal plan for the period 2016 – 2020.

                                                               20
6.8 Non Load Related Network Expenditure

This enshrines the safety of our assets, in their reliability when staff are called upon to operate or work on them, and in
the exposure of the public to this extensive system which reaches right onto streets and into homes across the country.
The capital plan presented has been distilled to the works which are considered absolutely necessary if safety is to be
maintained, with a small number of other works included either to meet legal and environmental obligations, or where they
are deemed fundamental to security of supply in critical locations. The complimentary body of maintenance interventions
planned are necessary to ensure that the existing assets, old and new, continue to deliver a reliable supply and that their
associated safety and other risks are contained.

This plan was developed by the asset management experts in ESB Networks, in conjunction with the delivery and operational
organisations who come into daily contact with these assets and whose safety relies on their integrity. Through extensive
assessments, sampling and testing, intra organisational debate, and consultation with experts, the risks associated with our
assets were identified and quantified, and a range of activities proposed. Subsequently these activities were scrutinised
in the context of their necessity to maintaining safety. Only the programmes strictly required to maintain safety to an
acceptable level were retained for presentation in this plan, with the exception of a small number of programmes where
there are particularly critical issues of environmental impact or security of supply which must be addressed.

The table below sets out the Asset Replacement programme for PR4:

 Programme                                               PR4 Proposal 2014 real €m          PR3 Forecast €m (nominal)
 HV Stations asset replacement                                      126.4m                            69.7m
 HV cables asset replacement                                         24.6m                             6.9m
 HV overhead lines renewal                                           46.5m                            15.3m
 MV Substations replacement and refurbishment                        23.3m                            29.0m
 MV cables replacement s                                              0.2m                             1.8m
 MV Overhead Lines refurbishment                                    131.9m                            61.9m

 LV Cables and minipillars replacements                              16.2m                             6.0m
 LV Urban lines renewal                                              46.4m                            34.6m
 LV Rural overhead networks renewal                                  74.7m                            91.5m
 Cutout replacements                                                 14.3m                             4.1m
 Meters & time switches                                              14.1m
 Response capex                                                      51.4m                            53.5m
 Continuity                                                          13.5m                            13.8m
 System Control                                                      12.9m                              4.0
 Total                                                              596.4m                            392.1m
                                           Figure 12: Asset Replacement programme for PR4

                                                              21
6.8 Non Load Related Network Expenditure

HV Stations Asset Replacement
Specific projects contributing significantly to this overall cost of €126.4m are as follows:
    •   €11.5m Replacement of components with type defects and deficiencies including Reyrolle Type ‘C’ bulk oil
        switchgear, Sprecher & Schuh 38kV switchgear, porcelain support insulator on a 38kV ASEA disconnect, Kyle
        Cooper LBFM switches, Oil filled Balteau current transformers at 38 kV and 110 kV.

    •   €24.0m HV Substation Security including the installation of CCTV, power fencing, palisade fencing, locks with
        programmable keys is intended to address the high number of costly and dangerous incidents of theft from HV
        stations which occurs each year. It is hoped that these measures will allow ESB Networks control the cost and
        hazards arising.

    •   €6.4m in Environmental Activities including continued bunding activities, flood protection measures at stations
        which are in known flood risk locations, air quality monitoring and the development of a storage facility for oil
        filled equipment.

    •   €1.0m of Condition monitoring in conjunction with a significant shift towards condition monitoring in HV Stations
        maintenance, a modest investment in condition monitoring equipment for circuit breakers and transformers.

    •   €9.9m Siemens Stations to complete this programme.

    •   €5m to replace Convoy Wood Pole 38kV station.

    •   €21.5m Switchgear replacements at four critical substations.

    •   €8.6m Replacement of aging 38kV & 10kV Circuit Breakers.

HV Cable Replacements
The main programmes of work in this area at a proposed cost of €24.6m are as follows:
    •   €0.8m Replacement of Pfisterer 110kV terminations following three catastrophic failures of 110kV cable
        terminations that occurred in 2011, 2012 and 2013, with the expulsion of debris up to 30m from the installations.

    •   €0.8m for Replacement of 5 fluid filled indoor cable terminations. Although relatively infrequent, with 2 catastrophic
        failures recorded in the past 15 years, the failure of fluid filled cable terminations is an exceptionally dangerous
        occurrence, associated with explosion and fire in the enclosed environment of an indoor substation.

    •   €12.6m for Replacement of fluid filled cables - The replacement of 8.9km of 110kV gas compression cables, 5.7km
        of 110kV fluid filled cables and4km of 38kV fluid filled cables is being undertaken, primarily driven by concerns as
        to the environmental impact of 40,000L of fluid lost into the ground each year.

    •   €2.2m Adoption of PFT technology to address cable fluid leaks to address high level of oil leakage as compared to peers.

HV Overhead Lines
The main programmes of work in this area at a proposed cost of €46.5m are as follows:
    •   €29.4m 38kV overhead line refurbishment - over a period of 9 years it is necessary to complete a programme of
        inspection and refurbishment of the >5,700km of 38kV overhead network.

    •   €16.4m Refurbishment Program for 4 110kV DSO Double Circuit Lines in Dublin.

                                                              22
You can also read