PETROPAVLOVSK PLC POX Capital Markets Day and H1 2019 Results 10th September 2019
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Cautionary and forward-looking statements — Some statements contained in this presentation or in documents referred to in it are or may be forward-looking statements, including references to guidance. Such statements reflect the Company’s current views with respect to future events and are subject to risks, assumptions, uncertainties and other factors beyond the Company’s control that could cause actual results to differ from those expressed in such statements. Although the Company believes that such forward-looking statements, which speak only as of the date of this presentation, are reasonable, no assurance can be given that they will prove to be correct. Therefore, you should not place undue reliance on these statements — There can be no assurance that the results and events contemplated by the forward-looking statements contained in this presentation will, in fact, occur. The Company will not undertake any obligation to release publicly any revisions to these forward-looking statements to reflect events, circumstances or unanticipated events occurring after the date of this presentation, except as required by law or by any appropriate regulatory authority. Nothing in this presentation or in documents referred to in it should be considered as a profit forecast. — The past performance of the Company and its securities is not, and should not be relied on as, a guide to the future performance of the Company and its securities — This presentation does not constitute, or form part of or contain any invitation, recommendation or offer to any person to underwrite, subscribe for, buy, sell, otherwise acquire, exchange or dispose of any shares or securities in the Company or advise persons to do so in any jurisdiction, including, but not limited to, the Russian Federation, nor shall it, or any part of it, form the basis of or be relied on in any connection with or act as an inducement to enter into any contract or commitment therefore or engage in any other investment activity. In particular, this presentation and the information contained herein are not an offer of securities for sale in the United States. This presentation does not constitute an advertisement of any securities in the Russian Federation — No reliance may be placed for any purpose whatsoever on the information or opinions contained in this presentation or on its completeness and no liability whatsoever is accepted for any loss howsoever arising from any use of this presentation or its contents or otherwise in connection therewith. — The development and production plans and estimates set out herein represent the current views of the Company's management. The Company’s Board reviews the production estimates on an ongoing basis. All planning is subject, inter alia, to available funding and capital allocation decisions — English law and English courts will have exclusive jurisdiction over any disputes arising from or connected with this presentation 2
A Welcome From The Team Senior Executive Members and the Board of Directors Senior Executive Members Board of Directors Independent NED Harry Kenyon- Dr Pavel Sir Roderic Lyne Slaney Dr Pavel Maslovskiy Non-Executive Sr. Independent Maslovskiy CEO Chairman Director CEO Independent Independent Independent NED NED NED James Cameron Robert Jenkins Damien Hackett Independent Non- Independent Non- Independent Non- Exec Director Exec Director Exec Director Dr Alya Samokhvalova Alexey Dubynin — Board strengthened with 4 x new Independent NEDs CFO Deputy CEO — New Board fully compliant with UK Corporate Governance Code — An additional Board Member to be confirmed 4
Key Themes From Today’s Presentation Petropavlovsk is well-positioned for growth with a strong and sustainable platform OUR CORPORATE OBJECTIVE Delivering sustainable returns above our cost of capital by leveraging our long-life asset-base and technical competence OUR KEY MESSAGES POX is up and running Petropavlovsk has one of only two gold concentrate POX processing plants in Russia growth and value opportunities Pioneer flotation plant to increase concentrate feed to POX from Q4 2020 A 10 year, c.US$400m, investment bearing fruit: a technologically advanced platform for future growth, processing abundant refractory ores Turnaround over past 12 months: H1 profits up, costs down. On track for 2019 production and costs guidance 5
Petropavlovsk: An Overview A leading vertically integrated Russian gold miner 3x gold mines c.15Mtpa 20.5Moz of JORC Resources(1) c.7.3Moz Au Open pit + underground milling capacity incl. 8.2Moz of Reserves Produced to date(2) Mining & Processing Pioneer St Petersburg Albyn - RDC Hydrometallurgy Malomir Pokrovskiy Moscow Blagoveshchensk - Petropavlovsk Moscow - Regis Exploration - PHM Engineering - Kapstroi Construction London - Petropavlovsk Plc - Corporate headquarters Irkutsk Open-pit mine Analytical labs - Irgiredmet Institute Underground mine R&D POX Hub Offices IRC Ltd. (non-core)(3) (1) As at 31 Dec 2018, in accordance with the JORC Code. Resources (M,I&I) are incl. of Reserves (2) As at 30 June 2019 (3) 31.1% equity interest 7
Operational and Corporate Achievements Over the last 12 months, a significant business turnaround has been achieved Recent Achievements Flotation Malomir flotation plant fully ramped-up and operating above design parameters Ongoing Pioneer flotation construction to double refractory ore processing capacity POX Hub POX plant commissioned ahead of schedule and successfully ramped-up Financial Performance H1 2019 TCC better than lower end of guided range Debt Convertible bonds refinanced at a lower coupon IRC loan refinanced with a more favorable payment schedule Corporate Third party advisor retained to review and assist with ESG ratings and communication Independent Board constituted 8
H1 2019 Financial Results Highlights Strong set of financials overall: costs and capex down, revenue, EBITDA and profits up 1 Group Revenue (US$m) 2 EBITDA (US$m) 3 Total Cash Costs (US$/oz) 4 Capex (US$m) +13% +37% -6% -33% 83 899 67 305 841 270 61 45 H1 2018 H1 2019 H1 2018 H1 2019 H1 2018 H1 2019 H1 2018 H1 2019 9
H1 2019 Group Total Cash Costs (TCC) Fall in TCC despite underutilised capacity POX , further improvement expected in H2 2019 Avg. RUB:US$ FX Electricity (+5%) Higher grades + End of tax relief on depreciated by 10% Lower stripping in H1 Diesel (+18%) recoveries at Albyn capital investment(1) from 59.3 (H1 2018) to 2019 vs. H1 2018 Materials (+10%) and Malomir 65.2 (H1 2019) 52 30 80 131 56 32 0.5 US$899/oz US$841/oz -6% H1 2018 H1 2019 Inflation POX ramp-up Mining tax Other taxes FX recoveries Deferred Change in stripping related costs grades / (1) The Russian statutory mining tax rate is 6%. Under Russian Federal Law 144-FZ dated 23 May 2016 that introduced certain amendments to the Russian Tax Code, taxpayers who are participants in Regional Investment Projects have the right to apply reduced mining tax rate provided certain 10 conditions are met. Malomir and Albyn met eligibility criteria and applied 1.2% mining tax rate in H1 2019. Pokrovskiy applied full mining tax rate in H1 2019
Liquidity and Debt Overview Recent bond restructuring has strengthened near-term liquidity position Group debt maturity schedule (US$m) Targeting mid-term Net Debt / EBITDA of c.2.0x FY 2018 EBITDA affected by US$500m notes refractory concentrate stockpile build-up during POX 4.0x maturing Nov 2022 commissioning phase 3.7x 3.5x 500 3.0x 3.0x US$125m convertible bond 978 Refractory issue maturing 930 Jul 2024 Target 638 610 611 599 596 585 594 568 Refractory c.2.0x 125 100 2019 2020 2021 2022 2023 2024 2025 2026 2014 2015 2016 2017 2018 2019 - 2022 Total debt Net debt Net debt / Underlying EBITDA 11
Improving Credit Rating An improved credit rating reduces the Company’s cost of capital Key highlights from latest report Key highlights from latest report B- (Outlook Negative) B- (Outlook Positive) (outlook re-affirmed) (upgraded from CCC) Last review: April 2019 Last review: August 2019 – Significant strengthening in liquidity position – POX commissioning to have a positive impact on 2019 – Convertible bond successfully refinanced Highlights financials – Repayment of US$57m bridging loan by IRC – IRC debt refinancing to improve liquidity position – Increased visibility for production following POX commissioning – Development of underground operations – Significant deleveraging by end-2020 – Expanding the Board reinforced corporate governance – Improved corporate governance Successful convertible bond refinancing FFO adjusted gross leverage remaining sustained below 4x 2019 EBITDA growth in line with S&P base case Triggers Upside Sustained FCF margin with funds used for reduction of gross debt Improved credit metrics backed by potential sale of IRC stake Improvement of production volumes and cash costs Building up successful POX track record Improvement in corporate governance Delivery on revised business strategy Downside Triggers 2019 EBITDA may not materially improve vs. 2018 Deterioration of liquidity and / or aggressive dividend distributions Difficulty in refinancing the US$100m convertible bond due Failure to improve production volumes 2020 Source: S&P and Fitch rating reports 12
Mine By Mine TCC And H1 2019 Production Highlights Overall H1 2019 Group Total Cash Costs (TCC) reduced by -6% yoy, with all mines profitable at H1 2019 avg. realised gold price levels H1 production 11koz above plan H1 production 3.6koz above plan H1 production 7.4koz below plan 1,138 971 884 860 843 622 -30% -12% +35% Albyn Malomir Pioneer H1 2018 H1 2019 % change yoy 13
H1 2019 AISC and Capex Decrease in Group AISC and Capex due to strong operating performance and financial discipline H1 2018 vs. H1 2019 AISC (US$/oz) H1 2018 vs. H1 2019 Total Capex Spend (US$m) 1,506 1,186 34.0 1,110 1,116 1,013 731 13.0 10.4 9.1 10.2 -34% -15% +35% 8.5 8.2 6.1 5.6 2.8 3.1 1.1 Malomir Pioneer Albyn Malomir Pioneer Exploration Other POX Albyn H1 2018 H1 2019 % change yoy H1 2018 H1 2019 (1) The majority of Pioneer’s capex (US$10.4m of development + US$2.1m of exploration), is categorised as sustaining, resulting in increased AISC 14 in H1 2019
FY2019 Outlook On track to meet FY 2019 guidance of 450Koz – 500Koz gold with lowered cost guidance Malomir — c.160Kt – 165Kt of refractory concentrate at 28g/t – 29g/t to be processed this year, of which: Concentrates — c.35Kt of concentrate at 28g/t produced / stockpiled in 2018 (at POX) — c.125Kt – 130Kt of refractory concentrate at 28g/t – 29g/t produced in FY2019e(1) 3rd party — 38Kt at 40g/t – 75g/t Au secured H1 2019(2) Concentrates — Additional c.20Kt at 49g/t - 75g/t Au currently under negotiation (at POX) — Concentrate is from Russia and Kazakhstan — TCC revised downwards to US$750 – US$850/oz due to strong operational achievements including a Costs smoother-than expected ramp-up of the POX Hub (RUB : US$ FX of 66) — US$45m - US$55m, consisting of sustaining, exploration + remaining POX capex Capex — Additional Pioneer flotation spend of c.US$30m (a portion of which falls into 2019) — Elginskoye (Albyn) – currently open in all directions with drilling expected to increase resource of ore body extensions Exploration — NE Bakhmut pit (Pioneer) high grade material identified below pit with extensions of mineralisation to increase open pit and underground reserves — Khabarovsk assets (greenfield) showing highly promising results (1) c.125Kt – 130Kt processed from 125Kt – 145Kt of concentrate produced at Malomir during FY2019e (2) Material secured under contract, but not necessarily shipped to site 15
POX: Technology Driven Growth Dr Pavel Maslovskiy 16
POX: Introduction To Refractory And Double Refractory Gold Ores POX – one of the most efficient and environmentally-friendly ways to extract gold from refractory ore Refractory + Double Refractory Ore Refractory Reserves(1) Refractory Resources (1) — “Refractory” ore contains gold encapsulated in sulphides which resists recovery via standard methods — Sulphides need to be broken down chemically or Albyn Pioneer Albyn Pioneer open-pit 1.1Moz open-pit open-pit mechanically 0.4Moz open-pit 2.0Moz 4.2… 0.4Moz 2.0Moz 1.1Moz 4.2Moz — “Double refractory” ore also contains carbon, which impacts recoveries special measures are required to 9% 8% neutralise carbon’s effect 38% 34% Main Options to Treat Gold Bearing Refractory Ores 5.3Moz 12.3Moz Total Total 51% 54% 2% 3% Pressure 1. POX: oxidation in an Oxidation autoclave: high pressure (POX) + temperature Malomir 2.7Moz Pioneer Malomir Pioneer 2. Roasting: oxidation 0.2Moz 6.7Moz 0.3Moz Roasting open-pit U/G open-pit U/G via high temperature 2.7Moz 0.2Moz 6.7Moz 0.3Moz High Grade roasting Concentrate 3. BIOX: oxidation using Bio bacteria ‒ 65% (5.2Moz) of the Group’s total Reserves (8.2Moz) are refractory Oxidation (BIOX) 4. UFG: fine grinding ‒ 60% (12.3Moz) of the Group’s total Resources (20.5Moz) are releases gold refractory Ultra- Fine encapsulated in sulphides Grinding or other minerals By design, our POX Hub is able to treat the most technologically complex refractory ore concentrates (1) As at 31 Dec 2018, in accordance with the JORC Code 2012. Reserves are shown as Proven + Probable. Resources are inclusive of Reserves 17
The POX Hub Concept The POX Hub is well positioned in terms of easy access and well developed infrastructure Concentrate Transportation: Km Malomir to POX Truck: Malomir to Fevralsk 166 Rail: Fevralsk to Tygda 1,134 Truck: Tygda to POX Hub 18 Total 1,318 Albyn Malomir Tygda(1) Pioneer Pokrovskiy POX Hub CHINA Transportation route Fevralsk(1) Railway Operating mines Underground mine Pilot POX Plant POX Analytical labs Blagoveshchensk Hydro power plant (1) Fevralsk and Tygda are rail loading facilities 18
POX: A World Class Team A world class research and development expertise lead by a world class team Gidrometallurgia: Petropavlovsk’s Scientific Research Centre, established to support the POX project — Unique laboratory, created the concept of the POX project for the Group, including key technological parameters — Equipped with state of the art autoclave laboratory facilities (laboratory + pilot testing, feasibility work + audits) — Unique team of 40 specialists incl. PhD holders, who have undertaken a range of work for c.30 third party companies in addition to POG Irgiredmet: The Irkutsk Research Institute of Precious and Rare Metals and Diamonds — Founded in 1871, over 140 years of expertise in R&D, design + engineering — Helped to develop flotation process / testing, laboratories performed autoclave leaching tests — 10 specialised technological laboratories with c.300 highly qualified staff, more than 25 patents in the fields of mining / metallurgy — Annually carries out more than c.200 researches assignments for third party companies, incl. R&D activities to help develop new deposits Pilot Test Plant: Petropavlovsk’s experimental industrial model pilot processing plant — Launched in 2009, the plant is the first and only of its kind in Russia — Small scale autoclave to test all parameters of the process — Unique asset giving Petropavlovsk the flexibility to test any type of gold recovery process on a smaller scale — Also carries out test work / scenario analysis for external third party companies PHM Engineering: engineering and construction supervision of the Group’s processing assets, including the POX Hub — Responsible for new project feasibility work, technical design, permitting, equipment selection, oversight of manufacturing process, installation, commissioning — Over 50 employees including PhD holders Our partners and industry specialists: over 20 leading industry companies contracted to help us successfully develop / launch the POX Hub — Shanghai Morimatsu (autoclaves), LOTERIOS SpA (pressure pipe lines), DSB Säurebau GmbH (titanium inner gear + autoclave linings), Outotec (flotation, control / automation equipment), Feluwa Pumpen GmbH (acid resistant high-pressure slurry pumps), MOGAS Industries (valves), Red Mountain Energy Corporation (oxygen plant) 19
The POX Plant Flowsheet POX processing is a series of standard and well understood technologies Regrinding 1 Re-grinding via two separate lines ensures a fine, 1 homogenous feed – Two parallel lines allow for separate feedstocks: treatment Acid pre- 2 – Line 1 has two ball mills – Line 2 has a single ball mill for finer grinding Chlorine washing 3 – Both lines have optionality to feed material through acid pre-treatment section (if ore requires this) or to by-pass Pressure Oxidation 2 Acid pre-treatment section removes carbonates and other minerals which can affect pressure oxidation 4 3 Chlorine washing removes chlorine ions to minimise gold losses at the POX stage 4 Pressure oxidation via 4 autoclaves to break down Conditioning & thickening sulphides and liberate refractory gold 5 5 Conditioning (cooling) and thickening of the oxidised pulp Neutralisation 6 Liquid (comprising of sulphuric acid) is separated at a 6 dewatering stage and neutralised before discharge to POX tailings pond(1) 7 Solid pulp is neutralised/ filtered using lime, before To RIP 7 being sent for conventional RIP processing to RIP (1) A large water storage allows the use of fresh water in quantities sufficient to prevent chlorine ion concentration build-up, thus optimising gold recovery 20
Malomir And Pioneer Flotation Concentrate Parameters Design vs. actual performance Malomir Pioneer Design Parameter Design H1 2019a H2 2019e FY 2019e Comments (Stage 1) H1 throughput on target, up to 10% increase in Ore 1.8Mt (6m) 1.81Mt 1.8-2.0Mt 3.6-3.8Mt H2 due to better equipment utilisation and 3.6Mtpa processing 3.6Mtpa (FY) optimisation of processing operations Flotation performance exceeded initial design parameters, affording the opportunity to test 1.25g/t - Scheduled process low grade ore at c.0.7g/t in Q1 2019 1.35g/t 0.97g/t(1) 1.25-1.30g/t 1.10g/t 1.1g/t ROM grades The tests confirmed its feasibility, hence lower than design processed grades in H1 2019 Concentrate 5.5% 3.3% 3.5% 3.4% Up to 40% improvement in concentrate yield 2.90% yields vs. design: lower transportation and POX Concentrate processing costs and higher grade concentrate 24g/t 26g/t 31g/t 28g/t 24.0g/t grades 61-70kt (6m) Up to c.40% decrease in processed tonnage Concentrate 100kt (6m) 59kt (6m) 120-140ktpa 125-130kt due to a positive decrease in yield: more gold 110ktpa volumes 200ktpa (FY) 120ktpa (FY) (FY) extracted into a smaller volume of concentrate Recoveries 86% 87% 86% 86% Stable recoveries in line with the design 82% — Stage 2 flotation expansion will increase capacity of Malomir and Pioneer flotation from 3.6 to 5.4 – 6.0Mtpa — Similarly to Malomir, it is entirely possible that Pioneer flotation may outperform initial design parameters (1) H1 2019a Malomir ROM grades included trial processing of lower grade refractory stripping material to understand the ability of the plant to treat lower grade ore and the potential for lower cut-off grades 21
POX Plant Capacity vs. Sulphur Content Sulphur affects oxygen consumption and hence affects processing capacity Autoclave Capacity vs. Sulphur Content of Various Concentrates Autoclave capacity varies according to 1. Sulphur content (and to lesser extent arsenic + 25 antimony) – Higher sulphur consumes oxygen which increases costs and reduces capacity Expected 3rd party range 20 2. Residence time Single Autoclave Capacity (t/hour) – A function of concentrate properties, Malomir = c.28% S temperature and pressure 15 – Graph plateaus on left side when it hits residence time limit Current capacity 3. Feeding pump capacity – Affects physical tonnage of concentrate that can 10 be pumped into autoclave Kazakh 1 c.20% S Pioneer = c.23% S – Function of pump + connecting pipework capacity 5 – Currently c.13t/hour, with measures being taken to increase to c.24t/hour – Shown on graph as current capacity and upper threshold of capacity 0 Potential exists to reduce residence time by increasing 15 20 25 30 35 the fineness of the feed by additional grinding, Sulphur Grade (%) temperature, pressure Malomir concentrate Pioneer concentrate Kazakh Concentrate 1 Currently POX is running at 30 bar / 220oC (1) Assumes 7,500 operation hours per annum and increased capacity constraints on solids from c.13 to c.24 t/hour 22
POX: The Heart Of Our Future POX to reach its full potential by 2021(1): contribution from refractory ore to increase up to c.65% Contribution of Refractory Ores at Malomir + POX ramp-up (ktpa)(1)(2) Pioneer (Mtpa)(1) 500 18 % 70 Capacity Range(2) % of total which is 450 refractory 16 60 4 autoclaves 400 14 350 Albyn 50 12 300 Concentrate (kt) 10 40 250 Refractory Refractory Malomir 8 Refractory Refractory 30 200 2 autoclaves 150 6 Refractory 20 100 4 Pioneer 50 Refractory Refractory 10 2 0 2018 2019e 2020e 2021e 2022e - 0 2019e 2020e 2021e 2022e Pioneer Malomir Albyn 3rd Party Pioneer non-refract Pioneer flotation Malomir non-refract Pioneer Malomir 3rd Party Ore Malomir flotation Albyn non-refract % Refractory (RHS) (1) Assumes 3rd flotation line at Malomir from 2021 (2) Capacity ranges depend on concentrate parameters, particularly sulphur content 23
POX Processing Costs: Fixed vs. Variable Overall POX processing costs decline rapidly to c.US$100/t as throughput is increased Unit cost of processing and throughput rates Comment 250 H1 to H2 2019 FY 2019 to FY 2020 – Through the ramp-up period in H1 the proportion 76kt of fixed costs was c.2/3 of total POX processing costs; the share of fixed costs is expected to Fixed costs decrease rapidly 200 on a per tonne basis as decrease with the increase of the plant’s utilisation 220kt throughput is increased – H1 2019 processing cost equated to around US$230/t concentrate 144kt 150 – 144Kt – 149Kt of refractory concentrate is US$/t expected to be processed in H2 2019, comprising: 340kt – 84Kt - 89Kt of our own concentrate 450kt 450kt 100 – 60Kt from 3rd party sources – As a result FY 2019 processing costs are expected to be c.US$175/t concentrate 50 – Going further the unit processing cost declines rapidly to c.US$100/t as throughput is increased as designed 0 H1 2019 H2 2019 FY 2019 FY 2020 FY 2021 FY 2022 Throughput (ktpa) Fixed Cost Variable Cost 24
A Comparison Between POX Projects There are only two gold POX processing plants in Russia, with a third under construction Polymetal Amursk POX 1 Polymetal POX 2 Pokrovskiy POX Hub Commissioned 2012 Q3 2023 Q4 2018 Number of autoclaves 1 1 4 Concentrate processing 225Ktpa 250 - 300Ktpa 400 - 500Ktpa capacity Capex US$272m US$431m US$310m Capital intensity US$1,210/t US$1,437/t - US$1,724/t US$620/t - US$775/t Operational temperature 200 ˚С 240 ˚С 225 ˚С Pressure 22 bar 43 bar 35 bar POX recovery rate 97% 96% 93% - 98% — A comparable amount of development capex was spent to develop the Pokrovskiy POX Hub vs. the Amursk POX 1 project despite significant difference in processing capacity — As such, the new Pokrovskiy POX facility has a low capital intensity (1) The Pokrovskiy POX Hub achieved pressure of 30 bar and temperature of 220˚С. Ramp-up to design parameters continues 25
Autoclave Peer Analysis POX technology around the world Project Start POX Feed POX Capacity Autoclaves Temp Pressure ~S Feed Reserves Pueblo Viejo 2012 Whole Ore 24,000tpd 4 230C 3,450kPa 6.8% 2.8g/t Goldstrike 1990 Whole Ore 16,000tpd 6 220C 2,900kPa 2.5% 3.9g/t Copler 2018 Whole Ore 6,000tpd 2 220C 3,150kPa 4.8% 2.8g/t Whole Ore & Lihir 1997 25,000tpd 4 205C 2,650kPa 6.0% 2.3g/t Concentrate Whole Ore & Twin Creeks 1997 10,400tpd 2 225C 3,170kPa 4.5% 1.8g/t Concentrate Kittila 2008 Concentrate 870tpd 1 207C 2,500kPa 18.0% 4.7g/t Amursk 2012 Concentrate 616tpd 1 200C 2,170kPa 6.5% 5.2g/t Porgera 1990 Concentrate 16,400tpd 4 197C 1,750kPa 14.0% 4.8g/t Macraes 1999 Concentrate 650tpd 1 225C 3,140kPa 9.0% 1.1g/t Corrego do Sitio 2011 Concentrate 240tpd 1 230C 3,600kPa 7.8% 4.1g/t Pokrovskiy 2018 Concentrate 1,370tpd 4 225C(1) 3,500kPa(1) 23.0% 1.0g/t Stibnite (Project) 2023E Concentrate 20,000tpd 1 220C 2,400kPa 5.5% 1.6g/t Donlin (Project) 2025E Concentrate 8,500tpd 2 220C 3,250kPa 7.0% 2.1g/t Lagunas Norte 2026E Concentrate 6,000tpd 1 - - 8.0% 2.9g/t (Project) Certej (Project) - Concentrate 2,600tpd 2 230C 3,547kPa 13.0% 1.7g/t (1) Pokrovskiy POX Hub achieved autoclave pressure of 3,000kPa and a temperature of 220˚С, as ramp-up to design parameters continues 26
Corporate Strategy Dr Pavel Maslovskiy 27
Strategic Priorities Asset rationalisation, organic and inorganic growth options Opportunities Goal Implementation ‒ Disposal of a 31.1% controlling stake to a ‒ the business Streamlining Eliminate IRC loan guarantee strategic investor alongside a transfer of the ‒ Improve credit rating loan guarantee(1) IRC sale ‒ Improve balance sheet metrics ‒ Alongside subsequent sale of the IRC stake, an ‒ Focus on gold agreement with Gazprombank to eliminate IRC ‒ Achieve higher market multiples guarantee ‒ Extend mine life at Albyn ‒ Construction of mine at Elginskoye Elginskoye ‒ Utilise existing infrastructure ‒ Construction of road to Albyn plant Organic Growth ‒ Maximise IRR ‒ Transportation of ore to Albyn RIP ‒ Optimise POX utilisation ‒ Construction of Pioneer flotation plant (initially 2 Increase feed of POX ‒ Secure concentrates with the best lines) with further expansion (3rd flotation line) plant by processing margins ‒ Expansion of flotation plant at Malomir (3rd own concentrates ‒ Maximise IRR flotation line) ‒ Identification of higher grade refractory assets Inorganic Growth ‒ Improve grade of POX feed material which can’t be developed at this moment M&A ‒ Increase POX utilisation ‒ Identification of the most effective way to bring ‒ Expand margins + increase production together synergies of these assets and the processing capacity of the POX Hub ‒ Fully benefit from POX facilities and ‒ Financed by JV partner Autoclaves POG’s comprehensive in-house R&D ‒ Adjustment of the technological process to 5 + 6 (JV option) capabilities process complex material (eg. triple refractory) (1) Petropavlovsk is a 31.1% holder of IRC. Gazprombank has been mandated to assess Petropavlovsk’s options 28
Organic Growth: Elginskoye to Replace Albyn Pit Ore body shape is favourable for a low strip-ratio / low dilution operation – Elginskoye is predominantly a non-refractory ore body, located c.30km west of Albyn plant – 2.8Moz of JORC Resources including 1.5Moz of JORC Reserves (at avg. 1.1g/t) – Shallow dipping mineralised zones suitable for low cost open pit mining – Preparation started to commence production in 2020 – Access road completed – First mining equipment has been transferred from Albyn to site – Estimated gold production of c.156koz in 2020 29
Organic Growth: Pioneer Is A High Return Strategic Project At spot gold prices, Pioneer has an IRR of greater than 130% Key Project Metrics – After more than 10 years of production Pioneer is Total capex spend over 2 yrs US$30m transitioning to become a mainly refractory deposit – Project looks attractive in terms of profitability + cash Construction timeframe 12 - 14 months flow generation under various macroeconomic scenarios First production H2 2020 Processing capacity 3.6Mtpa Mine life >10 years Project Sensitivities Gold Price (US$/oz) Gold Price (US$/oz) IRR NPV 1,250 1,300 1,400 1,450 1,250 1,300 1,400 1,450 61 86% 99% 126% 140% 61 137 167 226 256 RUB:US$ FX RUB:US$ FX 67 119% 134% 165% 182% 67 191 221 281 310 70 136% 152% 186% 204% 70 215 245 304 334 30
Pioneer’s Transition to Become a Principally Refractory Mine Understanding the transition to processing non-refractory to refractory gold Current non-refractory processing Future refractory processing: flotation lines 2 + 3 — 6.7Mtpa current(1) RIP plant comprising of crushing + — Construction of flotation facilities totalling 3.6Mtpa grinding sections capacity is underway — 3 x 1.8Mtpa(1) (“large”) crushing + grinding lines — The crushing + grinding lines will be gradually switched plus to the flotation circuit as ore transitions from non- refractory to refractory — 1 x 0.6Mtpa (“small”) crushing + grinding line — Tailings storage will be in a conventional tailings dam — RIP section will remain available after plant switched to flotation to provide optionality Heap Leach Pioneer flotation building (10 Aug 2019) Grinding Section (SAG RIP Section 0.6Mtpa line & Ball Mills) 1.8Mtpa lines Flotation Building (1) 1.8Mtpa is the nominal crushing capacity. Recently, Pioneer has been crushing 2.0Mtpa of softer oxidised (fresh) near-surface material, thus exceeding capacity 31
Inorganic Growth: 3rd Party Refractory Concentrates Market Concentrate markets in Russia and Kazakhstan 1. Russia: 40% of gold resources are refractory — Only limited refractory treatment capacity exists including two POX plants — The majority of concentrates are exported to China — Russia has declared gold as strategic asset and intends to prohibit exports of concentrates — For environmental reasons, China is shutting down roasters - particularly those treating high arsenic / antimony(1) 2. Kazakhstan: another source of refractory concentrates — Four refractory mines currently produce flotation concentrate, with potential to expand further. — Petropavlovsk has secured 20Kt grading 40g/t to 50g/t which it is currently processing at recoveries of 95% Refractory Mines in Russia and Concentrate Availability (Ktpa) Own Tonnes Potential Tonnes Mine Owner Exports Facilities Available (Kt) Available (Kt) Olimpiada (Au)(2) Polyus ✘ ✔ 50 Olimpiada (Au,Sb)(2) Polyus ✘ ✔ 150 Bogolyubovskoye NGOK ✘ ✔ 30 Udereyskoye NGOK ✘ ✔ 35 Drazhnoe GV Gold ✘ ✔ 20 Badran Zapadnaya ✘ ✔ 10 Mayskoye(3) Polymetal ✘ ✔ 57 Total available volumes 145 207 (1) Petropavlovsk’s process can stabilise arsenic as scorodite which offers a more environmentally-friendly approach to roasting (2) Olimpiada produces two types of flotation concentrates: 150Ktpa of concentrate is sold with an antimony content of up to 30% and 50Ktpa of gold 32 concentrates containing some antimony (3) 57Ktpa of Mayskoye concentrate, which is not processed at the Amursk POX plant, may be available
Autoclaves 5 + 6 (JV Option) Potential for a JV with another refractory producer or developer – Existing onsite infrastructure enables two additional autoclaves lines (5 + 6) to be added, although some expansion of oxygen capacity will be required – Given the large number of refractory ore bodies in the region, the Company believes the development could be funded via a JV with another refractory developer or producer – Adjustment in technology can be made to process very complex refractory materials, including: – Pyrrhotite-containing concentrates – Bio-cakes – Cuprous gold-bearing concentrates – Carbonaceous concentrates from other deposits – Concentrates obtained from the tails of existing mills 33
R&R / Exploration Dr Alya Samokhvalova 34
Proven Track Record Of Resource Growth As at 31 Dec 2018, Group Reserves & Resources totalled 20.5Moz, with Reserves of 8.2Moz(1) Moz 12.3 13.8 10.1 11.7 14.0 14.4 8.2 10.4 11.2 2.1 6.0 13.0 12.8 12.1 12.0 12.3 9.3 9.3 9.3 9.6 6.8 5.2 1.4 1.9 2.4 3.8 5.1 5.9 6.6 7.2 11.2 11.7 12.5 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Refractory Resources Non-Refractory Resources Depletion + Disposals (1) As at 31 Dec 2018, in accordance with the JORC Code 2012. Reserves are shown as Proven + Probable. Resources are inclusive of Reserves 35
Mine By Mine JORC Resource Breakdown New Resources at Pioneer, Albyn, Malomir + Pokrovskiy Total JORC Resources (as at 31/12/2018) Non-refractory Resources Refractory Resources New Resources - Explanation 8.2Moz 20.5Moz(1) 12.3Moz 40% 60% Malomir Pioneer Albyn Pokrovskiy 6.7Moz 4.5Moz 4.2Moz 97% 76% 79% 6.9Moz 5.9Moz 5.3Moz 0.9Moz 1.1Moz 1.4Moz 21% 24% 0.9Moz 0.2Moz 100% 3% RIP tailings for Katrin Decrease due to reprocessing via Albyn main ore body + Nikolaevskya disposals + sterilisation flotation + POX and Unglichikanskoye Ulunginskaya due at POX facility Quartzitovoye (1)Total JORC Resources include Tokur asset, not shown in the split below. Tokur contains non-refractory Resources of 1.4Moz. For full details 36 please refer to the 2018 Petropavlovsk AR
Resource Potential Significant potential to convert resources into reserves plus add future discoveries Long Term Potential N 8Moz Operating Mines Development & Satellites Projects 7Moz 6Moz 5Moz 4Moz 3Moz 2Moz 1Moz Malomir Tokur&Osipkan Albyn 0Moz 20km Reserves Resources Exploration – Total exploration potential estimated at c.4Moz in addition to the existing 20.52Moz of JORC Resources(1) – Significant potential to extend mine life of the Group’s operating mines via conversion of Resources into Reserves – Most promising exploration and development project outside existing operating mines is Tokur (together with Osipkan) – Strong regional exploration potential outside existing licence holdings (1) As at 31 Dec 2018, in accordance with the JORC Code. Resources (M,I&I) are incl. of Reserves 37
Responsible Business Dr Alya Samokhvalova 38
Sustainable Development Maintaining leading ESG Practices Health and Safety Corporate Governance — Full compliance with UK Corporate Governance Code — Full compliance with applicable health and safety legislation — Safety, Sustainability and Workforce Committee formed in Nov — H&S management systems 2018 — Regular external + internal audits / inspections — Annual review + publication of a revised Modern Slavery — Development of safety culture Statement — Risk management to mitigate impact — Remuneration disclosure — High quality task specific training — Established Code of Conduct and Business Ethics Social Responsibility Environmental Management — Major tax payer in Amur region — Environmental Management system compliant with GOST R ISO 14001- 2016 (ISO 14001:2015) — Active engagement with Indigenous communities — Optimisation of energy consumption, water recycling, GHG — Establishment of POX Hub part of government’s policy to develop monitoring + reporting in line with international standards Russian Far East — Strict control cyanide management — Accessible and effective grievance procedure — Fully compliant + insured tailing management facilities — Trade Union: 1,616 members, 18% of employees — Ongoing land rehabilitation + conservation of biodiversity — Equal career opportunities regardless of gender — Effective waste management (31% of all waste is reused) — Pokrovskiy Mining College Petropavlovsk is not only fully compliant with regional, national + international legislation, but is striving to perform in line with best industry practices 39
Sustainability Management and Governance The Board of Directors has appointed committees at Board level to oversee different aspects of business, risks and performance Board of Directors The Executive Committee — Consists of both Executive Directors + key operational management — Responsible for overseeing implementation of strategy, business targets + decisions made at Board level, including decisions made by SS&W Committee — Reviewing internal control and risk management Mr Harry Kenyon - Structure for the Monitoring + Reporting of Dr Pavel Maslovskiy Sustainability Performance Data Slaney Chief Executive Officer Chairman 5 Recommendations 1 are given to key HSE Performance operational data is collected Dr Alya management, which by key operational Mr Damien Hackett then provides BoD management Samokhvalova NED Deputy CEO with feedback 4 2 A summary is Data + summary made to the reports are The newly formed Safety, Sustainability & Workforce Committee Board of submitted to the (SS&W) is responsible for: Directors CEO + Deputy 3 — Reviewing + monitoring health, safety, environmental, sustainability Data + summary CEO processes + procedures reports submitted by Deputy CEO to — Assisting with the community relations + workforce engagement Executive + HSE Committees 40
Key Performance Indicators H1 2019 Reporting in line with international standards Lost Time Injury Frequency Rate (LTIFR) Energy Consumption Accidents per million manhours Million GJ +75% -55% 2.8 2.84 1.6 1.29 H1 2018 H1 2019 H1 2018 H1 2019 — Significant decrease in LTIFR due to more rigorous — Increase in energy consumption attributable to POX hub implementation of health and safety procedures commissioning(1) Greenhouse Gas Emissions (GHG) intensity Water Used Normalised per ounce of gold produced, t CO2e/oz Million m3 +19% -2% 1.08 11.5 1.06 9.7 H1 2018 H1 2019 H1 2018 H1 2019 — Despite increased energy consumption, GHG intensity — Water usage increase in line with increase in gold output decreased due to higher gold production (1) Oxygen plant electricity needs contribute the increased energy consumption 41
Health, Safety and Environment (HSE) Continuous commitment to a safe working environment HSE And CSR Reporting Structure H1 2019 H&S Progress / Initiatives — Introduction of “near-hits” record system Chief Executive Officer — Road Safety Campaign (Jan - Mar 2019) Petropavlovsk PLC — Stricter monitoring of the equipment effect on employees’ health in the work zones — More rigorous medical examinations exclusively by medical Head of Welfare and General Director contractor Community Liaison — Medical treatment of diseases pre-requisites via Trade Union programmes Road Safety Campaign 2019 Head of Environmental Chief Engineer Safety Department General Directors of General Directors of Pioneer, Pokrovskiy, Albyn, BRMZ, Regis, Transit, Kapstroy, Malomir AVT – Amur (2-3 HSE specialists per (2-3 HSE specialists per rotation) rotation) Production Facilities Ancillary Facilities 42
ESG Performance Benchmarking(1) Petropavlovsk vs. major gold companies Energy consumption Greenhouse gas emissions (СО2) LTIFR(2) Women employees (GJ / US$m of revenue) (tonnes / US$m of revenue) (cases per million working hours) (share of the total number of employees) Polyus Sibanye 1,776 Sibanye 1.18 Petropavlovsk 24.6% 10,343 New Gold Incorporated 7,080 Polyus 1,101 Anglogold Ashanti 1.14 Polymetal 20.0% Anglogold Ashanti 6,652 Anglogold Ashanti 795 Petropavlovsk 0.50 Gold Fields 16.0% Sibanye 6,053 Petropavlovsk 759 Gold Fields 0.45 Polyus 15.4% Kinross 5,813 Centamin 612 Eldorado Gold Company 0.33 New Gold Incorporated 15.2% Petropavlovsk 5,316 Gold Fields 566 Centamin 0.26 Sibanye 13.0% Barrick Gold 5,105 Polymetal 480 New Gold Incorporated 0.24 Barrick Gold 12.1% Gold Fields 4,387 New Gold Incorporated 464 Barrick Gold 0.15 Anglogold Ashanti 12.0% Polymetal 4,362 Kinross 460 Polyus 0.09 Kinross 11.0% Eldorado Gold Eldorado Gold Company 4,338 Company 450 Polymetal 0.09 Eldorado Gold Company 10.0% Centamin 2,073 Barrick Gold 397 Kinross 0.07 Centamin 2.0% Well positioned among peers in terms of implementing ESG standards, with some social aspects better vs. peers (eg. share of female employees). Room for further improvement to obtain an improved ESG rating in the mid-term Sources: Thomson Reuters, company data (1) Data for full year 2018 43 (2) Reporting standards vary, it is not always apparent whether all accidents are reported by a company. Petropavlovsk reports accidents at all facilities while Russian legislation dictates to report the accidents at hazardous facilities only
Sustainable Ratings Well positioned among peers in the framework of Environmental responsibility and sustainability disclosure The Transparency Rating of Environmental ESG/CSR Rating(2) Responsibility Project for M+M Companies of Russia(1) (out of 100) 80 79 1.59 74 73 73 72 69 1.43 68 67 64 1.33 1.04 0.53 0.48 0.38 Kinross Petropa Nordgol Polymet Kamcha Polyus Highlan Gold of d Gold vlovsk tka al d Overall Rating Environmental Impact — Well positioned among the peers 22 place — Second best group (60-79) 2018 (0.27) 22-34 place 22-34 place Community 24 place 2017 (0.13) 2018 (0.36) 2017 (0.53) Employees Ecological Management Information Disclosure Score of 69 (out of 100) based on Petropavlovsk’s 17 place 23-31 place disclosure of information 2018 (0.71) 2018 (0.50) Environment 25-26 place 18 place 2017 (0.13) 2017 (0.56) Improved rating in every category, with the exception of Governance Information Disclosure, an area where the Company has the opportunity to improve in 2019 (1) World Wide Fund for Nature Russia 2018 44 (2) CSR Hub 2018
Case Studies Continuous participation in environmental and social programmes Reforestation Biodiversity Protection — c.255,000 of pine seedlings — c.300,000 of carp planted during 2017 - 2018 hatchlings released into Zeya river during 2017- — Pine seedlings are known 2018 for high survival rate — Aimed to stimulate — Seedlings are planted on reproduction of aquatic an artificial surface for long biological resources + term prevention from preservation of wildlife in wildfires Amur region Avoiding Forest Fires Sustaining Future Workforce — 24/7 dedicated fire brigade — More than 10,500 students with specially trained fire graduated from Pokrovskiy fighters at each mine Mining College over 10 years — Regular safety briefings + drills — Majority have found employment at — Group’s fire teams help Petropavlovsk local villages to fight the house fires coming from — College training tailored to nearby forests the Group’s HR needs including H&S + POX 45
Closing Remarks / Q&A Sir Roderic Lyne 46
Investment Highlights Our long term goal is to increase shareholder returns 1 Leveraging our technical expertise to become a leading refractory gold producer in Russia 2 Three large-scale mines in Russia producing 450koz+ per annum 3 Monetising our 12.3Moz of refractory resources + profitable processing 3rd party refractory material 4 Proven track record of exploration, development, expansion and asset optimisation 5 Strategic location + access to developed infrastructure 47
Summary: A Conservative Strategy Focused on Shareholder Returns A holistic strategy directed at improving long-term shareholder returns Cost optimisation + — Focus on operational efficiencies and cost optimisation at existing operations 1 margins — Gold price hedging / forward sales agreements are complementary measures Increase production — Construction of new Pioneer flotation to double existing flotation capacity (Q4 2020 launch) 2 of our own refractory concentrate — Malomir 3rd flotation line planned for 2023, but may be accelerated Balance sheet — Improved cash generation via POX ramp-up 3 strengthening — Targeting Net Debt / EBTIDA of 2.0x IRC: 4 — Options include: improvements to existing guarantee structure, outright disposal , payment of a realising value from dividend to Petropavlovsk non-core assets — Addition of 2 more autoclaves to the existing 4 5 POX capacity — 50% total processing capacity uplift from 400 – 500Ktpa to 500 – 750Ktpa expansion — Autoclaves 1 to 4 to process own refractory ore, while 5 + 6 to process 3rd party material (JV opportunities) — Continue to generate maximum value from core assets via ongoing exploration both surface + Committed to underground 6 exploration — Potential licence acquisitions adjacent to the existing infrastructure 48
You can also read