MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks

Page created by Kenneth Pham
 
CONTINUE READING
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
MICROGENERATION
FRAMEWORK
CONSULTATION
Enabling the Transition
from Consumer to Prosumer
DOC-300420-FSI
May 2020
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation              Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer   Enabling the Transition from Consumer to Prosumer

                                                    CONTENTS
                                                       Section 1     Introduction                                                                                   4
                                                              1.1    Changing Landscape: A Transformation of the Energy System as We Know It                        5
                                                              1.2    About ESB Networks                                                                             6
                                                              1.3    ESB Networks Role in Facilitating Microgeneration                                              7
                                                       Section 2     Microgeneration Grid Connection Process                                                        8
                                                              2.1    Microgeneration Grid Connection Process                                                        10
                                                              2.2    ESB Networks Review of the Connection Process                                                  12
                                                              2.3    Grid Connection Process for Generation Greater than 6 kW (single-phase), 11 kW (three-phase)   12
                                                       Section 3     Legislative Basis                                                                              14
                                                              3.1    Clean Energy Package / Renewable Energy Directive                                              15
                                                              3.2    CRU Regulatory Decisions                                                                       15
                                                              3.3    Government Climate Action Plan                                                                 15
                                                              3.4    Private Member’s Bill                                                                          19
                                                              3.5    Building and Planning Regulation                                                               19
                                                      Section 4      Technical Network Implications                                                                 20
                                                              4.1    Technical Analysis of Solar PV Microgeneration on the Distribution Network                     21
                                                              4.2    Interaction of Electric Vehicle and Heat Pumps Loads                                           23
                                                              4.3    System Impact of PV at MV and Above                                                            23
                                                       Section 5     Microgeneration Support Schemes                                                                26
                                                              5.1    ESB Networks Microgeneration Support Package                                                   27
                                                              5.2    Electric Ireland Microgeneration Pilot Scheme                                                  27
                                                              5.3    FarmGen Solar PV                                                                               27
                                                              5.4    SEAI Grants                                                                                    29
                                                      Section 6      Smart Metering                                                                                 30
                                                              6.1    Benefits of Smart Metering                                                                     33
                                                              6.2    Smart Metering Programme and Microgeneration                                                   33
                                                       Section 7     Enabling the Transition from Consumers to Prosumers                                            34
                                                              7.1    Recommendations                                                                                35
                                                              7.2    Loss Adjustment Factor                                                                         36
                                                              7.3    Interim Solution                                                                               36
                                                              7.4    Next Steps                                                                                     36
                                                      Section 8      Enduring Solution for Microgeneration                                                          38
                                                      Section 9      Safety review                                                                                  40
                                                              9.1    SEAI Domestic Solar Photovoltaic Code of Practice for Installers                               41
                                                              9.2    Electrical Safety                                                                              41
                                                     Section 10      Conclusion and Summary of Questions in Framework Document                                      42
                                                     Acronyms and Glossary – Explanation of Key Terms                                                               46

2                                                                                                                                                                        3
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation              Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer   Enabling the Transition from Consumer to Prosumer

SECTION 1
INTRODUCTION                                        1.1 Changing Landscape: A Transformation
                                                    of the Energy System as We Know It
                                                                                                                   This strong ambition from the Irish government aligns
                                                                                                                   with RED II which brings the prosumer into the centre of
                                                                                                                   EU energy policy. Due to a combination of current building
                                                    The power sector is undergoing transformative change           regulations, SEAI grants, the rise of the active, engaged
                                                    with the growth of low carbon technology and changing          consumer and the future provision of a microgeneration
                                                    consumer preferences. European policy, such as the Clean       support scheme, ESB Networks anticipates increased
                                                    Energy Package (CEP) and the revised Renewable Energy          future levels of microgeneration connecting to the
                                                    Directive (RED II), are driving a change in behaviour and      distribution network. Consumers have been recognised
                                                    supporting the decarbonisation of the European power           as playing a major role in this transition and have been
                                                    sector.                                                        identified as a key player in Ireland’s ability to achieve
                                                                                                                   its 2030 renewable energy goals. The actions relating to
                                                    The Irish Government recently published the Climate
                                                                                                                   microgeneration in the CAP are extracted for review in
                                                    Action Plan (CAP) which sets ambitious targets to facilitate
                                                                                                                   a later section. These actions provide a comprehensive
                                                    and enable the transformation to a low carbon future. This
                                                                                                                   overview of the necessary steps, timelines and relevant
                                                    ambition includes the goal of reaching 70% of electricity
                                                                                                                   stakeholders in order to establish a robust framework to
                                                    generated from renewable energy by 2030. Renewable
                                                                                                                   enable the transition from consumer to prosumer.
                                                    energy of all scales, from large-scale to small-scale
                                                    renewable generation, community energy renewable               It is important to note when considering microgeneration,
                                                    energy projects, and microgeneration, will all play a part     that as there is a capital cost associated with the purchase,
                                                    in contributing to Ireland’s decarbonisation goals. The        installation and future operation and maintenance of the
                                                    CAP1 had a dedicated section to microgeneration where          microgeneration equipment (e.g. solar PV panels), certain
                                                    “The Government strongly supports enabling people to           customer classes i.e. fuel poor customers or vulnerable
                                                    sell excess electricity they have produced back to the         customers may feel that they cannot equitably participate
                                                    grid”. Developments in policy and technologies are likely      in the microgeneration journey. It is vital that any holistic
                                                    to evolve and advance to facilitate this goal, for example     review of microgeneration considers the issue of equity
                                                    the forecasted increasing development of large off-shore       to all users of the electricity network and seeks to identify
                                                    wind generation and the increased roll-out of community        and minimise unintended cross-subsidisation between
                                                    energy schemes.                                                customers i.e. customers with a form of microgeneration
                                                                                                                   and customers without any form of microgeneration. In
                                                    There are many actors involved in delivering Ireland’s
                                                                                                                   this context, relevant stakeholders should be cognisant of
                                                    decarbonisation objectives. ESB Networks is one actor
                                                                                                                   the need to ensure that the range of processes, incentives
                                                    within this group of actors and we seek to proactively
                                                                                                                   and rules relating to microgeneration encourage an
                                                    contribute towards Ireland’s decarbonisation targets. This
                                                                                                                   economically efficient future level of microgeneration.
                                                    framework focuses on microgeneration which is a form of
                                                    renewable energy generation that may be more accessible        As Distribution System Operator (DSO), ESB Networks
                                                    to the ordinary energy customer compared to large scale        has an important role to play in facilitating this
                                                    renewable energy generation. Through this framework,           transformation. We aim to support our customers along
                                                    ESB Networks hopes to inform the energy customer of            each stage of the process as they adopt small-scale low-
                                                    some aspects of microgeneration, to collect and collate        carbon technologies and make the transition towards
                                                    their views regarding this topic and to use this feedback      being active participants in the energy system.
                                                    when considering areas relevant to microgeneration.

                                                    In a 2016 briefing from the European Parliament,
                                                    ‘prosumer’ is described as a relatively new term that, in
                                                    the energy field, most often denotes consumers who both
                                                    produce and consume electricity.2 This document refers
                                                    to consumers who wish to install microgeneration and           1 https://www.gov.ie/en/publication/5350ae-climate-action-plan/
                                                    export excess electricity onto the electricity network as
                                                    prosumers.                                                     2 http://www.europarl.europa.eu/thinktank/en/document.
                                                                                                                   html?reference=EPRS_BRI(2016)593518

                                                                                                                                                                                     5
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation                                                                                                      Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer                                                                                           Enabling the Transition from Consumer to Prosumer

1.2 About ESB Networks                                                      We carry out all the functions relating to the electricity      1.3 ESB Networks Role in Facilitating                                 The Commission for Regulation of Utilities (CRU) is
                                                                            distribution system. This includes financing, planning,         Microgeneration                                                       Ireland’s independent energy and water regulator. This
ESB Networks provides the electricity infrastructure
                                                                            construction, maintenance and operation of the high,                                                                                  paper, along with all feedback received, will be provided
that transports electricity to all customers in Ireland.                                                                                    Customer service is at the heart of everything we do at
                                                                            medium and low voltage distribution networks. ESB                                                                                     to CRU to support their decision-making process on
Our assets cover the entire country and include a range                                                                                     ESB Networks. We provide services to every electricity
                                                                            Networks fills a number of different market roles through                                                                             microgeneration. CRU’s aim is to protect the interests of
of overhead lines, underground cables and associated                                                                                        customer irrespective of their electricity supplier. Our
                                                                            the Metering and Registration System Operator (MRSO)                                                                                  energy customers, maintain security of supply, and to
technical equipment to safely convey electricity to                                                                                         countrywide staff are committed to making excellence the
                                                                            function, it is responsible for providing meter registration,                                                                         promote competition covering the generation and supply
more than 2.3 million customers. We have served                                                                                             hallmark of all aspects of our dealings with our customers.
                                                                            data processing and data aggregation services. ESB                                                                                    of electricity and supply of natural gas. This paper will
Irish customers for over 90 years and have provided
                                                                            Networks also delivers the data collector, meter operator                                                                             also be provided to the Department of Communications,
the electrical infrastructure on which our society has                                                                                      We are committed to facilitating the move towards low
                                                                            and DSO roles. ESB Networks finance, build and maintain                                                                               Climate Action and Environment (DCCAE) in the hope
developed. We now have one of the most progressive                                                                                          carbon technologies and want to support our customers,
                                                                            the high voltage transmission system through which                                                                                    that it may provide useful information in achieving the
electricity systems in the world.                                                                                                           not only through the process of installing microgeneration
                                                                            electricity flows from generation stations to bulk supply                                                                             microgeneration goals as set out in the governmental
                                                                                                                                            but also strive to enable them to participate in the energy
                                                                            points near cities and towns across Ireland. ESB Networks                                                                             CAP.3
                                                                                                                                            market. This framework document seeks to examine
                                                                            has connected over 2,000 MW of renewable energy
                                                                                                                                            options available to facilitate the transformation of                 ESB Networks is committed to leading the transition to
                                                                            generation to the distribution network at present.
                                                                                                                                            our customers from consumers of electricity to active                 a low carbon future as evident through ESB Networks
                                                                                                                                            prosumers.                                                            Innovation Strategy which can be found on the ESB
                                                                                                                                                                                                                  Networks website.4
                                                                                                                                            The framework contains a number of questions where we
                                                                                                                                            welcome feedback from you, the customer. This feedback                The ability of electricity networks to adapt and innovate in
                                                                                                                                            will then be studied and incorporated into further                    this changing and uncertain environment will be crucial to
                                                                                                                                            refinement of developing possible solutions to enable the             their future success. This changing environment provides
                                                              155,000km                            23,500   km
                                                                                                                                            transition from energy consumer to energy prosumer.
                                                                                                                                            ESB Networks will incorporate the feedback received to
                                                                                                                                                                                                                  us with challenges but also provides great opportunities
                                                               Overhead Lines                   Underground Cables                                                                                                for innovation. By 2030 our network will support, through
                                                                                                                                            this publication into any review of its microgeneration               the identification of innovative opportunities, huge
                                                                                                                                            processes.                                                            changes in electricity generation and consumption.

                         646                                                                                                                                                                                                                                                            1,300 MW
                     HV Stations                                                                                                                                                                                                                                                    of energy storage
                                                                                                                                                                                                                                                                                    and 2,500 MW of
                                                                                                                                                        1,500 MW                                             up to 30,000                                                          customer flexibility
                                                                                                                                                        of solar PV                                        grid edge devices
                                                              236,000   km                          164,000
                                                          MV Pole Mounted Subs                       Mini Pillars
                                                                                                                                                                                                                               Add in “Forecasted” before both sentences so they read
                                                                                                                                                                                                                               “Forecasted New Domestic Connections over PR4” and
                                                                                                                                                                                                                               “Forecasted New Commercial Connections over PR4”

                       20,000                                                                                                                                                                                                                                                              Circa 1 million
                                                                                                                                                                                                                                                                                          electric vehicles
              MV Ground Mounted Subs
                                                                                                                                                                                                                                                                                            on our roads

                                                          2.2 MILLION                           2.3 MILLION                                             11,700 MW                                                                                                                 2.3 million
                                                                    Poles                        Customer Meters                                                                                                                                                                smart meters
                                                                                                                                                    of wind generation
                                                                                                                                                       (onshore and                                                                                                             in homes and
                                                                                                                                                         offshore)
                                                                                                                                                                                           FORECASTED
                                                                                                                                                                                          NEW DOMESTIC
                                                                                                                                                                                                                FORECASTED
                                                                                                                                                                                                              NEW COMMERCIAL                                                     businesses
3 https://www.dccae.gov.ie/en-ie/climate-action/topics/climate-action-                                                                                                                                         600,000
plan/Pages/climate-action.aspx                                                                                                                                                                           homes equipped with
                                                                                                                                                                                                           e-heat capability
4 https://www.esbnetworks.ie/who-we-are/innovation/our-innovation-
strategy/our-innovation-roadmaps                                                                                                                                Figure 1 ESB Networks Innovation Strategy - What will the Network Support in 2030
6                                                                                                                                                                                                                                                                                                         7
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation              Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer   Enabling the Transition from Consumer to Prosumer

SECTION 2
MICROGENERATION GRID                                ESB Networks5 defines microgeneration as a source of
                                                    electrical energy and all associated equipment, rated up to
                                                    and including:
                                                                                                                         The vast majority of domestic connections in Ireland
                                                                                                                         are single-phase connections. ESB Networks charges a
                                                                                                                         connection fee for all types of business and domestic

CONNECTION PROCESS                                  •    6 kW, when the DSO network connection is single-
                                                         phase
                                                                                                                         connections, and a full list of these regulatory approved
                                                                                                                         charges can be found in the ESB Networks Statement of
                                                                                                                         Charges.8 Each connection is calculated using the least
                                                                                                                         cost technically acceptable connection method.
                                                    •    11 kW, when the DSO network connection is three-
                                                         phase                                                           If a customer wishes to upgrade their connection from
                                                                                                                         a single-phase to a three-phase connection this can be
                                                    and designed to operate in parallel with the ESB Networks
                                                                                                                         done, however, higher connection charges will apply.
                                                    low voltage (LV) system. Full details and conditions can be
                                                                                                                         These arise because the physical conductor connecting
                                                    found on the ESB Networks website.6
                                                                                                                         the customer to the network needs to be replaced and
                                                    This definition makes no explicit reference to any specific          connected to a three-phase circuit. In an urban location
                                                    form of generating technology. The following are examples            this will most likely involve street excavation, but in rural
                                                    of different types of microgenerators:                               areas would most likely involve building some new MV
                                                                                                                         overhead line. The level of network capacity required by
                                                    •    Wind-power (Turbines)                                           the customer will determine the actual connection point
                                                                                                                         the customer wishes to connect to. The distance between
                                                    •    Solar-power (Photovoltaic (PV) panels)
                                                                                                                         the connection point and the network, as well as various
                                                    •    Small hydroelectric schemes                                     other works that may need to be carried out, additional
                                                                                                                         charges will be apportioned to the customer as per the
                                                    •    Micro combined heat-and-power (CHP)                             regulatory approved Basis of Charges for Connection to
                                                                                                                         the Distribution System.9
                                                    •    Combined renewable microgenerator and
                                                         storage systems7                                                ESB Networks is committed to facilitating
                                                                                                                         microgeneration connection applications to the grid.
                                                    This framework consultation is technology agnostic i.e.
                                                                                                                         Since 2016, ESB Networks has facilitated over 15,000
                                                    does not differentiate between microgeneration from
                                                                                                                         microgeneration connection applications to the electricity
                                                    a roof mounted solar PV panel, a wind turbine or small
                                                                                                                         network.
                                                    hydro schemes. For information, please note that there are
                                                    technical differences between inverter based generation
                                                    (e.g. PV), which is inherently less onerous on the network
                                                    than other technologies.

                                                                                                                         7 https://www.esbnetworks.ie/new-connections/generator-connections/
                                                                                                                         connect-a-micro-generator

                                                    5 Further information relating to the regulatory basis defining      8 https://esbnetworks.ie/docs/default-source/publications/approved-
                                                    microgeneration is outlined in Section 3.2                           statement-of-charges-2019-2020.pdf?sfvrsn=224533f0_33

                                                    6 https://www.esbnetworks.ie/docs/default-source/publications/       9 https://esbnetworks.ie/docs/default-source/publications/
                                                    conditions-governing-connection-and-operation-of-micro-generation-   basis-of-charges-for-connection-to-the-distribution-system.
                                                    policy.pdf?sfvrsn=ad5c33f0_8                                         pdf?sfvrsn=5e5d33f0_4

                                                                                                                                                                                               9
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation                                                                                                        Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer                                                                                             Enabling the Transition from Consumer to Prosumer

                                                                                                                                                                                                                                                                                                        esbnetworks.ie
                                                                                                                                                                                                                                                                                                                                                        The microgeneration connection application process is the
                                                                                                                                                                                                                                                                                             FORM NC6                                                   same for new builds as it is for customers who choose to
                                                                                                                                                                                                                                                   MICROGENERATION NOTIFICATION
                                                                                                                                                  ESB Networks DAC requires the information requested on this application form to
                                                                                                                                                  enable us to set up and manage your electricity supply connection. As the Distribution          FOR OFFICIAL USE ONLY
                                                                                                                                                                                                                                                  Date received: _____________________________________________________
                                                                                                                                                                                                                                                                                                                                                        add microgeneration to an existing connection.12 There is
                                   6000
                                                                                                                                                  System Operator, this information is also required to enable ESB Networks DAC to
                                                                                                                                                                                                                                                  Planner group: _____________________________________________________

                                                                                                                                                                                                                                                                                                                                                        no application fee or charge to the customer when sending
                                                                                                                                                  manage the electricity network. The data controller is ESB Networks DAC.
     No. of Approved Connections

                                                                                                                                                  Please refer to our privacy policy at https://esbnetworks.ie/privacy                            DUOS group:______________________________________________________
                                                                                                                                                                                                                                                  Supplier: __________________________________________________________
                                                                                                                                                  Please fill in ALL sections in BLOCK CAPITALS
                                                                                                                                                   1. FULL NAME AND CORRESPONDENCE DETAILS
                                                                                                                                                                                                                                                                                                                                                        an NC6 form to ESB Networks for processing. Technical
                                   5000                                                                             5000                                                                                                                                                                                                                                studies are largely not required for microgeneration grid
                                                                                                                                                   Landline:                                                   Mobile number:                                                                                                                           connection applications to date, unlike grid connection
                                   4000                                                    3900                                                    Email:

                                                                                                                                                   2. SITE ADDRESS (IF DIFFERENT FROM ABOVE)
                                                                                                                                                                                                                                                                                                                                                        applications for larger generators, although this does not
                                                                                                                                                                                                                                                                                                                                                        mean that studies would not be required in particular
                                   3000                             3000
                                                                                                                                                   Please provide 11 digit MPRN no:
                                                                                                                                                                                                                                                                                                                                                        circumstances.
                                                                                                                                                   MPRN must be registered in Applicant’s Name. If not please contact your supplier to change.

                                   2000                                                                                                            3. INSTALLER / CONSULTANT NAME AND CORRESPONDENCE DETAILS

                                                                                                                                                                                                                                                                                                                                                        Current Process for Planned Multiple
                                              1600
                                   1000
                                                                                                                                                   Landline:

                                                                                                                                                   Email:
                                                                                                                                                                                                                Mobile number:
                                                                                                                                                                                                                                                                                                                                                        Installations:
                                                                                                                                                   4. MICROGENERATION INTERFACE DETAILS Please attach certified proof as per Conditions Governing the Connection and Operation of Microgeneration - DTIS-230206-BRL

                                                                                                                                                                                                                                                          Unit 1                 Unit 2                 Unit 3                                          The application process for planned multiple installations,
                                     0                                                                                                              Manufacturer
                                                                                                                                                    Manufacturer’s Reference No. / Model                                                                                                                                                                applies to planned (green field) multiple installations
                                              2016                  2017                   2018                     2019
                                                                                                                                                    Rating (kVA)
                                                                                                                                                    Does interface have type test certification as per Conditions Governing
                                                                                                                                                    the Connection and Operation of Microgeneration - DTIS-230206-BRL?                              Yes       No           Yes       No           Yes       No                                          such as new housing schemes, where it is planned to have
                                                                                                                                                                                                                                                                                                                                                        microgeneration installed in every house or premises.
                                                                                                                                                    Does interface have Irish settings installed as per Conditions Governing
                                                                                                                                                    the Connection and Operation of Microgeneration - DTIS-230206-BRL?                              Yes       No           Yes       No           Yes       No

                                                                               Year                                                                5. MICROGENERATOR DETAILS

                                                                                                                                                    Manufacturer
                                                                                                                                                    Manufacturer’s Reference No. / Model                                                                                                                                                                Within an existing housing estate, if the total capacity of
                                                                                                                                                    Type (Wind / Solar / Hydro / CHP / Energy Storage / Other)

                                                                                                                                                   6. SIGNATURE                                                                                                                                                                                         the installed microgeneration on the transformer is 50
                                                                                                                                                    Signed:
                                                                                                                                                                                                                                                                                                                                                        kVA or if the penetration levels is greater than 40% of
                                          Figure 2 ESB Networks Approved Microgeneration Connection Applications                                    Full Name (BLOCK CAPITALS):
                                                                                                                                                    Date:

                                                                                                                                                   7. DID YOU REMEMBER TO?                                                                                                                                                                              the transformer then ESB Networks needs to do a more
                                                                                                                                                                                                                                                                                                                                                        refined network study before connection.13
                                                                                                                                                   • Attach Type Test Certificate for Microgenerator Interface                             Please return completed form to:

                                                                                                                                                                                                                                                                                                                         Rev Oct 2019. DOC-210116-CDD
                                                                                                                                                   • Insert your MPRN number                                                               networkservicesbureau@esb.ie or

The section below outlines the current process and policy                      For sporadic once-off installations in existing premises,
                                                                                                                                                   • Fill in your Microgeneration Interface Rating (kVA) Details in Section 4              ESB Networks DAC, NC6 Microgen Notifications,
                                                                                                                                                                                                                                           New Connections, Sarsfield Road, Wilton, Cork T12E 367

for installing a microgeneration unit.                                         as defined above, the customer shall complete the                                                                                                                                                                                                                        For new connections, application for connection will
                                                                                                                                                                                                                                                       ESB Networks DAC
                                                                                                                                                   PLEASE REMEMBER!                                                                                    DIRECTORS: Jerry O’Sullivan (Chairman), Paddy Hayes,
                                                                                                                                                   DON’T BUILD UNDER OR NEAR POWER LINES                                                               Paul Mulvaney, Caroline Spillane, Ian Talbot .

                                                                                                                                                   LINES CAN KILL                                                                                      Registered Office: Clanwilliam House, Clanwilliam Court,
                                                                               Microgeneration Installation Notification Form.                     ESB NETWORKS LTD.
                                                                                                                                                                                                                                                       Dublin 2, D02 CV61, Ireland.
                                                                                                                                                                                                                                                                                                                                                        be made in the normal way but the intention to install
2.1 Microgeneration Grid Connection
                                                                                                                                                                                                                                                       Registered in Ireland No. 465172

                                                                               (Application Form NC6)                                                                                                                                                                                                                                                   microgeneration, shall be flagged by the applicant in the
Process                                                                                                                                                                              Figure 3 NC6 Application Form                                                                                                                                      application form.
                                                                               This should be sent to ESB Networks DAC, NC6 Microgen
Details on the current connection arrangements                                 Notifications, New Connections, Sarsfield Road, Wilton,        If ESB Networks become aware of any other technical
for microgenerators connecting at a domestic level                             Cork, T12E 367. Type-test certification for the interface[s]   or location specific reason why installation should not
are detailed below and further information on                                  associated with the microgenerator[s] in question              proceed, then ESB Networks shall inform the customer
microgeneration connection policy can be found on the                          should also accompany this notification. The equipment         within 20 working days of receipt of the notification.
ESB Networks website.10                                                        supplier is able to provide the relevant certification.
                                                                               Customers can also send their NC6 applications to              If no such notice or request for type test certification
Current Process for a Single Application:                                      NetworkServicesBureau@esb.ie.                                  or instruction to suspend installation is received by the
                                                                                                                                              customer within this time-frame, then the installation can
A sporadic once-off installation is defined as follows:
                                                                               ESB Networks understand that microgeneration is                proceed without any further correspondence with ESB
•    Only one customer is involved                                             primarily for the purpose of self-consumption with excess      Networks.
                                                                               electricity being exported to the distribution network and
•    Only one installation is involved                                         believes that the existing ESB Networks microgeneration
                                                                               export thresholds of 6 kW (single-phase) and 11 kW (three-
•    Where multiple customers on the same site or
                                                                               phase) are sufficient to encourage the transition from
     housing scheme are involved, and the penetration
                                                                               consumer to prosumer.
     level achieved is less than 40%11 of the capacity in
                                                                                                                                              10 https://www.esbnetworks.ie/new-connections/generator-                                                                                                                                                  12 https://www.esbnetworks.ie/docs/default-source/publications/
     kVA of the existing MV/LV substation that supplies the                                                                                   connections/connect-a-micro-generator.                                                                                                                                                                    conditions-governing-connection-and-operation-of-micro-generation-
     site or scheme.                                                                                                                                                                                                                                                                                                                                    policy.pdf?sfvrsn=ad5c33f0_8

                                                                                                                                              11 At a penetration level of 40% of the transformer capacity it is possible
                                                                                                                                              that power quality and loading issues may arise, and consequently such                                                                                                                                    13 https://www.esbnetworks.ie/docs/default-source/publications/
                                                                                                                                              proposed installations would need to be reviewed in advance by ESB                                                                                                                                        conditions-governing-connection-and-operation-of-micro-generation-
                                                                                                                                              Networks                                                                                                                                                                                                  policy.pdf?sfvrsn=ad5c33f0_8
10                                                                                                                                                                                                                                                                                                                                                                                                                           11
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation                                                                                                Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer                                                                                     Enabling the Transition from Consumer to Prosumer

2.2 ESB Networks Review of the                                          The grid connection process for generators greater than
Connection Process                                                      6 kW (single-phase) and 11 kW (three-phase) is outlined
                                                                        under CRU’s Enduring Connection Policy (ECP). 14
To ensure the connection process works for our customers                As per regulated grid connection policy, this range of
and in anticipation of the large increase in the numbers of             export capability is not considered as microgeneration
microgeneration forecasted to connect to the network, we                however, we feel it may be useful information for the
see it appropriate to review the current microgeneration                reader. In 2018, the CRU published a decision on Enduring
application process. We have received initial feedback                  Connection Policy – Stage 1 (ECP-1) with the intent of
from stakeholders that the current NC6 process is working               allowing projects which were ‘shovel ready’ to have an
well, however, we strive for continuous improvement. We                 opportunity to connect to the network. As per ECP-1,
welcome your input and feedback relating to the existing                generators in the range of 12-500 kW are processed
application process.                                                    outside the batch in a non-batch process. At present, as
                                                                        per ECP-1, 30 applications per year in this range as well
Question 1:                                                             as autoproducers and DS3 system services qualifying
Do you have any feedback in relation                                    trial projects are being processed outside the batch in the
to the existing grid connection process                                 non-batch process. The processing of such applications
for microgeneration (up to 6 kW single-                                 required a technical study to be carried out to establish
phase and 11 kW three-phase)?                                           what works and equipment are required to facilitate the
                                                                        connection of those generator applications on to the
2.3 Grid Connection Process for                                         network. CRU published an ECP-2 consultation in Q4 2019.
                                                                        Responses from industry and interested stakeholders
Generation Greater than 6 kW (single-
                                                                        were received by CRU in Q1 2020 and CRU is currently
phase), 11 kW (three-phase)                                             considering Enduring Connection Policy Stage 2 (ECP-
Article 17 of the Renewables Directive requires                         2). Any changes to regulated policy within ECP-2 will be
establishment of simple notification procedure for grid                 implemented by ESB Networks.
connections where installation or aggregated production
units of renewables self-consumers with an electrical
capacity of 10, 8 kW or less are to be connected to the grid.
Member States may allow a simple-notification procedure
for installations or aggregated production units with an
electrical capacity of above 10, 8 kW and up to 50 kW,
provided that grid stability, grid reliability and grid safety
are maintained.

14 https://www.cru.ie/document_group/electricity-connection-policy-2/

12                                                                                                                                                                                        13
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
Microgeneration Framework Consultation              Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer   Enabling the Transition from Consumer to Prosumer

SECTION 3
LEGISLATIVE BASIS                                   3.1 Clean Energy Package / Renewable
                                                    Energy Directive
                                                                                                                                                  3.2 CRU Regulatory Decisions
                                                                                                                                                  As mentioned in the introduction, CRU are the decision
                                                                                                                                                  makers for a wide array of energy related areas.
                                                    The Clean Energy Package (CEP) is a package of measures
                                                    designed to keep the European Union (EU) competitive                                          Existing determinations from CRU that are relevant to
                                                    as the clean energy transition changes the global energy                                      microgeneration are detailed within this section. In 2007,
                                                    markets.15 The package is aimed at keeping the EU a global                                    the CRU published a Decision (CER/07/208) Arrangements
                                                    leader in renewables and, more broadly, helping the EU                                        for Microgeneration which outlined the technical and
                                                    to meet its emissions reduction commitments under the                                         commercial arrangements for microgeneration including
                                                    Paris Agreement.16                                                                            installation, safety, notifications to ESB Networks and
                                                                                                                                                  metering for microgenerators that rate at or below 11
                                                                                                                                                  kW. Within this decision the CRU encouraged electricity
                                                                                                                                                  suppliers to develop payment arrangements for

                                                                                                                                 © Shutterstock
                                                                                                                                                  microgenerators.18
                                                                          EUROPEAN
                                                                          ENERGY
                                                                          DIALOGUE
                                                                                                                                                  In 2008, ESB Customer Supply (ESBCS), as the Public
                                                                                                                                                  Electricity Supplier at the time, made a submission to
                                                                                                                                                  facilitate the payment for output of micro generators. CRU
                                                                                                                       TEN
                                                                                                                       SECTION                    published the ESBCS Domestic Micro-generator Export Tariff
                                                                                                                                                  Decision Paper (CER/09/033) in February 2008 in which
                                                                                                                                                  it published details of the interim export tariff. ESBCS
                                                                            EUROPEAN ENERGY DIALOGUE
                                                                                                                                                  offered a payment of 9.00 cent per kWh of exported
                                                                       «Clean Energy for All Europeans»
                                                                                   package                                                        electricity.19 The scheme was open until 31st December
                                                                                                                                                  2014 and ESBCS (now Electric Ireland) continue to offer
                                                                                                                                                  the payment of 9.00 cent per kWh to those customers who
                                                                              European Economic and Social Committee
                                                                                                                                                  signed up before the closing date.

                                                                                                                                                  3.3 Government Climate Action Plan
                                                         Figure 4 Clean Energy for All Europeans package
                                                                                                                                                  In June 2019, the Irish Government published a CAP20
                                                    The CEP contains specific provisions dealing with the                                         which sets out an ambitious course of action to address
                                                    issue of ‘renewable self-consumers’ and microgeneration.                                      the issue of climate change.
                                                    Further details on the CEP can be found on the European
                                                    Commission’s website here.

                                                    In December 2018, the revised Renewable Energy Directive
                                                    2018/2001/EU (RED II) entered into force, as part of the                                                              CLIMATE
                                                    Clean Energy for all Europeans package. The Directive
                                                    establishes a new binding renewable energy target for the                                                              ACTION
                                                                                                                                                                             PLAN
                                                    EU for 2030 of at least 32%, with a clause for a possible
                                                    upwards revision by 2023.17
                                                    15 http://europa.eu/rapid/press-release_IP-16-4009_en.htm                                                                 2019
                                                                                                                                                                               To Tackle Climate Breakdown

                                                    16 https://ec.europa.eu/energy/en/topics/renewable-energy/renewable-
                                                    energy-directive

                                                    17 https://ec.europa.eu/energy/en/topics/renewable-energy/renewable-
                                                    energy-directive

                                                    18 https://www.cru.ie/wp-content/uploads/2007/07/cer07208.pdf

                                                    19 https://www.cru.ie/wp-content/uploads/2009/07/cer09033.pdf                                      Figure 5 Government Climate Action Plan 2019

                                                    20 https://www.cru.ie/wp-content/uploads/2007/07/cer07208.pdf
                                                                                                                                                                                                             15
MICROGENERATION FRAMEWORK CONSULTATION - Enabling the Transition from Consumer to Prosumer DOC-300420-FSI - ESB Networks
ocean energy opportunity (wind, wave and tidal) within 100 km of the Irish coastline. The
                       development of offshore renewables will be plan-led and aligned with the National Marine
                       Planning Framework. We will also develop an offshore electricity grid, in tandem with
                       new interconnection. This will allow Ireland to balance its significant renewables potential
Microgeneration Framework Consultation
                       with security of electricity supply and develop long-term ambitions to export its offshore                   Electricity
                                                                                                                                  Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer                                                                                 Enabling the Transition from Consumer to Prosumer
                       renewable resources
                  • Examine the increased use of cross border joint cooperation mechanisms for funding
                       renewables, particularly offshore wind, to reduce the cost impacts on Irish consumers
                       and businesses, including for hybrid assets as part of the North Seas Energy Cooperation
                       Initiative
                  • Put in place a planning and consenting regime and a grid connection framework for offshore
                       wind that aims to deliver offshore wind projects. Prioritise the passage of the MPDM
                       legislation and the new consenting model, as well as implementation of a new offshore grid
                       connection policy that lines up with the RESS auction timeframes
                                                                                                                                    Micro-generation
                  •
Figure 6 is an extract In from
                          line with  our commitment
                                 Section                in Future Jobs Ireland 2019, establish a pilot Top Team in
                                          7.3 of the governmental
                       offshore   renewables
CAP, entitled, “Measures to Deliver Targets”.  to provide
                                                    21     a multi-organisational response to leveraging the industrial/
                       employment     opportunities
The snippet outlines the government’s plan for        arising from the operationalisation of the offshore energy                      Action 30: Develop an enabling framework for micro-generation which tackles existing barriers and
                       policy framework
supporting microgeneration         over theunder
                                             comingtheyears.
                                                       Marine Planning and Development Management Bill (MPDM)                         establishes suitable supports within relevant market segments
                       legislation
                                                                                                                                                                                                       Timeline by              Other Key
                                                                                                                                     Steps Necessary for Delivery                                                    Lead
                                                                                                                                                                                                       Quarter                  Stakeholders
                  3. Micro-generation
                                                                                                                                     Establish a working group on micro-generation and
             The Government strongly supports enabling people to sell excess electricity they have produced                                                                                                                     CRU, SEAI,
                                                                                                                                     renewable self-consumption and agree terms of reference e.g.
             back to the grid To enable this, we will have to make a number of changes                                                                                                                 Q3 2019       DCCAE      DHPLG,
                                                                                                                                     appropriate definitions, policy objectives, engage with the CEP
                                                                                                                                                                                                                                ESBN
                  •   We have established a pilot micro-generation grant scheme for solar Photovoltaics (PV),
                                                                                                                                     transposition project etc.
                      targeting self-consumption, which provides a grant of circa 30% of the installation costs for                  Begin review of requirements for resolving market settlement
                      individual homes Building on the pilot, we will put an ongoing support scheme in place for                                                                                       Q3 2019       CRU
                                                                                                                                     issues for renewable self-consumers exporting to the grid
                      micro-generation by 2021 at the latest, focusing on a number of key pillars, including: equity
                      and accessibility for all, ongoing technology cost and remuneration analysis, addressing                       Conclude review of the current exemptions relating to solar
                      technical barriers and planning constraints, a clear grid connection policy, and supporting                    panels as provided for in the Planning and Development
                      community participation in micro-generation. This will be further supported by measures in                     Regulations, in consultation with the Department of               Q4 2019       DHPLG      DCCAE
                      building regulations                                                                                           Communications, Climate Action and the Environment and
                  •   Mechanical electricity meters will be replaced in every house by 2024 under the Smart                          implement amendments arising from review
                      Metering Programme. This will facilitate better demand management and cost savings for
                      consumers, particularly when closely aligned with the ambitious roll-out of retrofitting                       Determination of appropriate grid connection policy to
                      programmes and micro-generation capacity for homes and small enterprises                                       facilitate renewable self-consumers and access for micro-         Q4 2019       CRU        ESBN
                  •   Change the electricity market rules in early 2020 in order to enable micro-generated
                                                                                                                                     generation
                      electricity to be sold to the grid. This should include provision for a feed-in tariff for micro-              Assess potential implications for distribution network of
                      generation to be set at least at the wholesale price point                                                                                                                       Q4 2019       ESBN
                                                                                                                                     defined higher penetrations of distributed generators
                  •   Design market mechanisms, network tariffs, competitive auctions for renewables and
                      the public service obligation in a way that distributes costs fairly, including in terms of                    Assess possible support mechanisms for micro-generation/
                      competiveness                                                                                                  renewable self-consumption differentiated by segment (public
                                                                                                                                                                                                                                SEAI, DBEI,
                                                                                                                                     sector, including schools, residential, community, farming,       Q1 2020       DCCAE
                                                                                                                                                                                                                                DAFM
                                                                                                                                     commercial and industrial etc ), ensuring principles of equity,
             58
                                        Figure 6 Government Climate Action Plan Section                                              self-consumption and ‘energy efficiency first’ are incorporated

                                                                                                                                     Public consultation/call-for-evidence on basis of above
                                                                                                                                                                                                       Q3 2020       DCCAE      CRU
The CAP requires changes to the electricity market rules               The CAP contains actions to assist Ireland in meeting         assessment
to allow for a “feed-in-tariff for microgeneration to be set           its ambitious objectives for climate action. The actions
at least at the wholesale price point”. This makes provision           relating to microgeneration in the CAP are extracted for      Assessment of the impact of the current structure of electricity
for payment to prosumers who export electricity                        review in the following table. These actions provide a        bill charges (including PSO and standing charges) on renewable Q3 2020          CRU        DBEI, DCCAE
produced from microgeneration to the grid.                             comprehensive overview of the necessary steps, timelines      self-consumers and other consumers
                                                                       and relevant stakeholders in order to establish a robust      Functionality to enable smart services in place, subject to initial
                                                                       framework to enable the transition from consumer to                                                                               Q2 2021     CRU
                                                                                                                                     review
                                                                       prosumer.
                                                                                                                                     Launch finalised policy and pricing support regime for micro-
                                                                                                                                                                                                       Q2 2021       DCCAE      SEAI
                                                                                                                                     generation

21 https://www.cru.ie/wp-content/uploads/2009/07/cer09033.pdf

16                                                                                                                                                                                                                                             17
Microgeneration Framework Consultation                                                                                             Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer                                                                                  Enabling the Transition from Consumer to Prosumer

                                                                                                                 Electricity

                                                                                                                                   3.4 Private Member’s Bill                                       3.5 Building and Planning Regulation
     Action 31: Deliver pilot solar PV micro-generation scheme with a view to commencement of enduring                             The Microgeneration Support Scheme Bill 2017 is
     support scheme by 2021, at the latest, to ensure that people can sell excess electricity they produce back
                                                                                                                                                                                                   Solar Planning Exemptions:
                                                                                                                                   currently before Dáil Éireann. The bill is entitled “An Act
     to the grid                                                                                                                   to provide for the growth of electricity production from        Currently rooftop solar PV installations (across all rooftop
                                                                                                                                   micro-generators through a Supplier obligation to provide       installations including domestic, industrial, agricultural
                                                                           Timeline by                       Other Key
     Steps Necessary for Delivery                                                           Lead                                   a tariff for electricity exported to the grid”. If introduced   etc.) are subject to planning requirements with an
                                                                           Quarter                           Stakeholders
                                                                                                                                   as proposed, the bill would see electricity suppliers above     exemption for installations up to 12sq. m (domestic),
     Review of scheme (incl. budget) and potential for new                                                                         10 per cent market share obliged to provide a payment for       50sq.m (industrial or agricultural) or 50% of the total roof
                                                                           Q3 2019          SEAI
     technologies and sectors to be included in broadened scope                                                                    kWhs of electricity exported to the grid from domestic          area, whichever is the lesser.23 A review of Building and
                                                                                                                                   microgenerators. There would also be an obligation on           Planning Regulations could be considered timely given
     Decision following review of pilot scheme                             Q4 2019          DCCAE            SEAI                                                                                  the publication of the CAP and the desire to facilitate
                                                                                                                                   suppliers to provide at least 5 per cent of their electricity
     Allocation of appropriate budget                                      Q4 2019          DCCAE            SEAI                  from microgeneration.22                                         microgeneration.

                                                                                                                                                                                                   22 https://www.oireachtas.ie/en/bills/bill/2017/155/?tab=debates

     Action 32: Deliver Smart Metering Programme in line with current planned timelines that will support the                                                                                      23 https://www.housing.gov.ie/planning/legislation/solar-panelsmicro-
     market for micro-generation                                                                                                                                                                   renewable-technology/exemptions-solar-panels-and-other-micro

                                                                           Timeline by                       Other Key
     Steps Necessary for Delivery                                                           Lead
                                                                           Quarter                           Stakeholders

     Commence review of requirements for resolving market
                                                                           Q3 2019          CRU
     settlement issues for renewables self-consumers

     Support research and demonstration projects with a focus
     on enabling the ‘smart home’ (e g demand side management,             Q3 2019          SEAI             EirGrid, ESBN
     storage, communication protocols, automated control, etc.)

  Carbon Capture and Storage
ESB Networks has been assigned actions in the CAP               •   Support research and demonstration projects with
(either  as lead  entity or as key stakeholder) with respect to
    Action 33: Establishment of a Steering Group to examine and     a focus on enabling
                                                                       oversee             the “smart
                                                                                the feasibility       home”
                                                                                                  of the      (e.g. demand
                                                                                                         utilisation   of
microgeneration.     These  actions  are:                           side management,
    CCS in Ireland, and report to the Standing Committee on Climate Action as appropriatestorage,  communication      protocols,
                                                                    automated control, etc.)
•     Assess what are the implications for the distribution
                                                                        Timeline by                         Other Key
    Steps   Necessary
      network            forhigher
                of defined   Delivery
                                   penetrations of distributed  ESB Networks    is activelyLead
                                                                                             contributing toStakeholders
                                                                                                             the DCCAE led
                                                                        Quarter
      generators.                                               microgeneration working group which seeks to remove
    Establish Steering Group                                    existingQ2  2019and establish
                                                                         barriers          DCCAE  suitable supports for
•     Assess whether there is appropriate grid connection       microgeneration.
      policy to facilitate renewable self-consumers and                                                     DHPLG, CCS
    Agree appropriate research investment by Ervia/Gas Networks
      access  for microgeneration.                                      Q3 2019            DCCAE            Steering
    Ireland in CCS feasibility
                                                                                                             Group

     Monitor progress of Ervia proposal in Cork                            Q2 2020          DCCAE

     Draft necessary legislation and regulatory regime if CCS
                                                                           Q3 2020          DCCAE
     research is positive

18                                                                                                                                                                                                                                                                     19
Microgeneration Framework Consultation              Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer   Enabling the Transition from Consumer to Prosumer

SECTION 4
TECHNICAL NETWORK                                   4.1 Technical Analysis of Solar PV
                                                    Microgeneration on the Distribution
                                                                                                                               There are significant differences between urban and rural
                                                                                                                               networks – in broad terms, urban networks tend to have
                                                                                                                               large numbers of customers (around 200) connected to a

IMPLICATIONS
                                                    Network
                                                                                                                               ground mounted substation housing a transformer with a
                                                    PV based microgeneration potentially impacts on LV                         typical capacity of 400 kVA and connected to customers
                                                    distribution networks principally in terms of:                             using large underground cables. In contrast, rural
                                                                                                                               networks typically consist of small pole mounted 15 kVA
                                                      (a) Voltage Rise
                                                                                                                               transformers feeding up to 8 customers, but with about
                                                      (b) Thermal Loading on Network infrastructure                            50% feeding only one or two customers.

                                                      (c) Harmonics                                                            Urban:
                                                    For the impact to be of significance it is the cumulative                  In general terms, most housing estates in the last 30 years
                                                    impact of all connected generation on that section of                      have been planned for using an After Diversity Maximum
                                                    network which is important, as the effect of an individual                 Demand (ADMD)25 of 2.5 kW per customer so that typical
                                                    PV microgeneration unit ­­­­­­up to 6 kWP, acting alone                    PV installations of 2 kWP should neither create voltage
                                                    connected under ESB Networks The Conditions Governing                      rise or thermal issues. Harmonics could become an issue,
                                                    the Connection and Operation of Microgeneration (DTIS-                     although voltage rise and thermal loading would normally
                                                    230206-BRL) 24 should not cause material disturbance.                      be expected to arise in advance, and the reinforcement
                                                                                                                               to address these issues would largely alleviate any
                                                    Note: The principal impact to voltage and thermal loading
                                                                                                                               harmonics issues.
                                                    arises from microgeneration exports, not from self-
                                                    consumption. Harmonic generation arises from installed                     At over 2 kWP PV per house on a modern housing estate the
                                                    capacity but is a much less significant effect.                            issue is what cumulative value of PV exists i.e. the number
                                                                                                                               (penetration rate) of PV x Size of PV unit. In general,
                                                    The impact of PV microgeneration export on the network
                                                                                                                               installations of up to 3 – 4 kWP PV on up to 50% of houses
                                                    therefore depends on the strength of the network and the
                                                                                                                               would not in be expected to cause any significant issues
                                                    amount of PV microgeneration connected in terms of
                                                                                                                               on the local LV network. However if there is sufficient
                                                    PV unit size and numbers (penetration level). Typically,
                                                                                                                               LV microgeneration in an area it will accumulate on the
                                                    the worst-case scenario is a hot summers day with the
                                                                                                                               upstream higher voltage networks feeding these areas and
                                                    PV generating fully, load being at minimum and network
                                                                                                                               could driver reinforcement there, particularly if it added to
                                                    already operating at a high summer ambient temperature.
                                                                                                                               existing generation already present.
                                                    Unlike domestic loads there is no diversity with PV, that
                                                    is within a local area maximum generation from each                        With the predicted future electrification of heat and
                                                    microgenerator will tend to occur simultaneously. This                     transport, ESB Networks has examined the ADMD
                                                    typically occurs around midday where solar irradiance is                   requirements of domestic units (in keeping with Action
                                                    greatest on a clear day.                                                   174 of the CAP). Future housing schemes will be designed
                                                                                                                               to an ADMD of 5.5 kW per customer and it is currently
                                                    There are also variations in the strength of networks to                   believed that greater penetrations of PV of 3 – 4 kWP (up
                                                    which customers are connected so that what might not                       to near 100%) would not be expected to cause issues of
                                                    cause problems on one area of the network could be an issue                voltage rise or thermal issues on the local LV network,
                                                    on another (likely older) network. This is the reason why                  although there might be issues with some higher harmonic
                                                    ESB Networks reviews connection groups where planned                       frequencies which would require harmonic filtering. ESB
                                                    capacity is 50 kVA or 40% of transformer capacity in more                  Networks understands that CRU will review this item in
                                                    detail than smaller groups of individual connections.                      late 2020.

                                                    24 The Conditions Governing the Connection and Operation of                25 After diversity maximum demand (ADMD) is used in the design of
                                                    Microgeneration (DTIS-230206-BRL) is currently under review to reflect     electricity distribution networks where demand is aggregated over a
                                                    the changes necessitated by the adoption of European Network Code          large number of customers. ADMD accounts for the coincident peak
                                                    on the Requirement for Generators and the resultant transition from I.S.   load a network is likely to experience over its lifetime and as such is an
                                                    EN50438:2013, which has been withdrawn, and the introduction I.S.          overestimation of typical demand http://www.networkrevolution.co.uk/
                                                    EN50549:2019                                                               project-library/diversity-maximum-demand-admd-report/

                                                                                                                                                                                                        21
Microgeneration Framework Consultation                                                                                                     Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer                                                                                          Enabling the Transition from Consumer to Prosumer

In practice the size of the suitable roof space available                   Typically, it would be expected that up to 2 kWP of PV         Question 2: Do you have any feedback                          In summary, at 2-3 kWP PV per rural house it is unlikely
and suitable for PV would itself determine the quantity of                  per customer would seldom cause problems, but once             in relation to the examination of                             that PV would force significant reinforcement, but at
PV installed per house e.g. a typical semi-detached house                   the amount of PV exceeds the transformer rating there                                                                        higher levels on transformers with over 4 customers,
                                                                                                                                           possible export limiting controls to
might have 21m2 of roof space and assuming no legislative                   will be an impact, especially because with solar PV the                                                                      either PV or electrification of heat and transport will drive
                                                                                                                                           facilitate self-consumption?
restrictions (currently 50% of areas or 12m2) could                         transformer will be operating in high summer ambient                                                                         reinforcement. The nature of the reinforcement will either
support about 2 kWP of PV. A larger detached bungalow                       temperatures when this generation occurs. For self-                                                                          be the installation of a larger transformer of the splitting
might have a roof area of 30m2 and support 4 kWP of PV.                     supply and installation of 2-3 kWP most networks would         4.2 Interaction of Electric Vehicle (EV) and                  of the group by dividing the group into two using an
                                                                            be able to cope, but at 4 kWP per customer, then four          Heat Pumps (HP) Loads                                         additional transformer. Further consideration is likely to
Obviously if PV were installed on the opposite side of                      customers with PV begin to overload the transformer,                                                                         be required as to the most equitable means of recovering
the roof, which by definition will be less exposed to the                                                                                  Customers mainly install PV to use the electricity
                                                                            and at 6 kWP over two such customers will overload the         generated to feed their own household loads. It is            these additional costs.
sun, then there would be physical space for more panels                     transformer and result in reinforcement being required.        expected that household load will increase appreciably
although less economic to install as they generate less.                    Potential resulting implications of this may include the       with additional electrification of heat and transport.
                                                                                                                                                                                                         4.3 System Impact of PV at MV and Above
In the UK, PV is typically less than 4 kW per house as the                  requirement to add additional transformers or source           Consequently, in any community the mix of PV and              In system terms and for high penetration rates:
G98 process,26 which is ‘fit and inform’, applies to unit                   larger transformers than are currently used. Additionally,
with generation less than 16A per phase. Units larger than                                                                                 additional load will tend to net off against each other and
                                                                            the MV rural network is not designed to cope with                                                                            •   PV microgeneration at LV may at times displace
this are subject to evaluation by Distribution Network                                                                                     on average usually reduce the load on the transformer at
                                                                            significant single-phase loading as this causes unbalance                                                                        imports of electricity from MV connected generators
Operators (DNOs), the UK equivalent of the DSO, and                                                                                        these times.
                                                                            when feeding into the three-phase network. These would                                                                           upstream, requiring them to export more of their
cannot be connected until they are approved by the                          have an associated potential increase in costs and future      However, this will not prevent network reinforcement              generation upstream. This could cause an increase
DNO. Additionally, whilst the Irish conditions allows up                    consideration will need to be given to the distributional      being required when there is extra PV or electrification.         in voltage at MV above required limits. However, this
to 6 kWP PV on single-phase (which is much larger than                      impacts of these costs and options surrounding how             This is because the worst-case conditions for each                would require high penetration levels at LV which
the 3.68 kWP limit in the UK), once this is exceeded the                    these costs will be recovered from both existing and new       technology occur at separate times – the determining              could take a significant time to develop.
protection requirements become more complex and                             customers of the network.                                      scenario for PV is a hot summers week day with
expensive. There can obviously be older urban networks                                                                                                                                                   •   Additionally, significant PV export from widespread
                                                                                                                                           customers at work, and low loads so that PV generated is
which have less capacity and can accommodate less PV                                                                                                                                                         microgeneration may also interact with other larger
                                                                            Export Limiting Schemes:                                       at a maximum and all is exported through the transformer.
without reinforcement, which is why ESB Networks                                                                                                                                                             scale generation exports on associated upstream
                                                                                                                                           In contrast, for electrification of heat and transport the
require notification of any significant groups of planned                   As technical issues with generation arise generally from                                                                         high voltage networks and hence require significant
                                                                                                                                           worst-case scenario is likely to be in winter during the
installations.                                                              the export of power onto the grid, it should be possible                                                                         reinforcement.
                                                                                                                                           later afternoon/evening when PV is at minimum but
                                                                            to increase the size of generation installed if the export
In summary, if customers are generally installing PV for                                                                                   electrified heat and EV loads are a maximum.                  •   PV microgeneration protections settings may be
                                                                            were restricted. This would facilitate greater levels of
own use, the amount installed will be about 2 – 4 kWP                       self-consumption and could be arranged through the                                                                               difficult to change in the future (if required) as there
                                                                                                                                           Consequently, the interaction between PV and
per customer and unlikely to move the system outside of                     development of an export limiting scheme. There are such                                                                         would be so many small generators that it would be
                                                                                                                                           electrification of heat and transport arises as a result
operational limits in general up to penetrations of 50%                     schemes in operation in the UK but require an analysis                                                                           impractical to each domestic residence and change
                                                                                                                                           of either one or both of them stressing the system and
and possibly beyond.                                                        of the network before installation. Voltage control by                                                                           the protection settings. This is an issue for the EU in
                                                                                                                                           requiring reinforcement – once the system has been
                                                                            limitation on kW exports to avoid excessive voltage rise                                                                         general and ESB Networks Conditions Governing the
                                                                                                                                           reinforced for either, then there is some extra network
Rural:                                                                      (as in Australia) is also being considered. For maximising     capability to cope with the other. It is also likely that
                                                                                                                                                                                                             Connection and Operation of Microgeneration specifies
                                                                            self consumption it could be possible to develop an export                                                                       these for Ireland. These settings are generally set
About 40% of customers live in rural areas and supplied                                                                                    areas likely to require reinforcement will have both
                                                                            limiting scheme which prevented export of more than                                                                              by the DSO however some e.g. Rate of Change of
mainly from 15 kVA single-phase pole mounted                                                                                               PV and electrification of heat and transport, simply
                                                                            3-4 kWP but allowed more PV to be installed by the                                                                               Frequency (RoCoF) are determined in conjunction
transformers, so it is much easier to encounter limits as                                                                                  because reinforcement will only be required where
                                                                            customer to facilitate self-consumption.                                                                                         with the TSO. A possibility could be that each PV unit
the size of the transformer is small, the distance to the                                                                                  there are enough customers to load the transformer
                                                                                                                                                                                                             has a facility to accept a remote-control device, (which
customer could be large and there could be a relatively                                                                                    sufficiently and sufficient numbers to then add Low
                                                                            ESB Networks is now examining the use of an export                                                                               might also be used to control export levels) although
large number of customers and associated PV per                                                                                            Carbon Technologies such as PV or Electrification (EV/
                                                                            limiting control which would facilitate larger installed                                                                         the associated economics and practicalities are not
transformer.                                                                                                                               HP). However, the uprating on networks to accommodate
                                                                            capacity as long as the export was limited. In addition, ESB                                                                     established.
                                                                                                                                           LCT will only provide modest additional capacity for
                                                                            Networks is considering the use of type tested equipment
                                                                                                                                           extra microgeneration export, as LCT loads are spread
                                                                            to simplify connections of packaged installations up to 50
                                                                                                                                           throughout the day/week and hence require less peak
                                                                            kW installed on three-phase network conections.
                                                                                                                                           capacity than the same amount of installed PV, which has
26 Engineering Recommendation G98 - Requirements for the                                                                                   no diversity. The addition of LCT loads would provide
connection of Fully Type Tested Micro-generators (up to and including 16
                                                                                                                                           greater scope for self-consumption of microgeneration
A per phase) in parallel with public Low Voltage Distribution Networks on
or after 27 April 2019                                                                                                                     but not for additional export.

22                                                                                                                                                                                                                                                                 23
Microgeneration Framework Consultation                      Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer           Enabling the Transition from Consumer to Prosumer

•    Note under/over frequency, under/over voltage
     and RoCoF are protection requirements for
     microgenerators under ESB Networks Conditions
     Governing the Connection and Operation of
     Microgeneration.

•    The provision of a digital input to cease generation
     from microgeneration is part the EU Network Code
     Requirements for Generators (RfG) which is now
     in force for all generators. However, to enable this
     capability the DSO requires communications at the
     microgenerator.

There may also be Transmission System Operation (TSO)
implications of high levels of microgeneration which
would impact on the TSO and are outside the scope of this
paper, however, we welcome engagement with the TSO at a
future date to review this issue in more detail.

24                                                                                                              25
Microgeneration Framework Consultation              Microgeneration Framework Consultation
Enabling the Transition from Consumer to Prosumer   Enabling the Transition from Consumer to Prosumer

SECTION 5
MICROGENERATION                                     ESB Networks is committed to leading the transition to
                                                    a low carbon future. As evident through ESB Networks
                                                    Innovation Strategy, we have set out a clear vision of how
                                                                                                                           The scheme has been closed to new customers since the
                                                                                                                           31st December 2014, however customers already signed
                                                                                                                           up for the scheme continue to receive payment. Under the

SUPPORT SCHEMES                                     we intend to deliver a world class electricity network for
                                                    the future.

                                                    We are aware of three microgeneration support schemes
                                                                                                                           scheme, payment is made to the prosumer within their
                                                                                                                           Electric Ireland bill. In 2018, Electric Ireland announced
                                                                                                                           that it would extend the payment rate of 9.0 cent per kWh
                                                                                                                           to its existing domestic customers already signed up to
                                                    which were at one stage operational or currently                       the scheme until 31st December 2020. This is the tenth
                                                    operational in the market – one historic support scheme                year that Electric Ireland continue to pay its Microgen
                                                    from ESB Networks, one current support scheme from                     Pilot Scheme customers the prevailing Electric Ireland
                                                    Electric Ireland and a recent introduction to the market               rate once their contract continues to be active.27
                                                    from Glanbia and SSE Airtricity. Under these schemes,
                                                    prosumers received payment for electricity they exported               5.3 FarmGen Solar PV
                                                    to the grid. While the Electric Ireland and ESB Networks
                                                                                                                           Glanbia Ireland and SSE Airtricity have recently launched
                                                    schemes are now closed to new applicants, in some cases
                                                                                                                           a microgeneration scheme, FarmGen, in July 2019. This
                                                    customers who signed up to these schemes before the
                                                                                                                           renewable energy initiative is based around bringing
                                                    closing date continue to receive payment for any excess
                                                                                                                           solar powered energy solution to Glanbia Ireland farmers
                                                    electricity they export.
                                                                                                                           only. FarmGen’s 6 kW solar PV system will assist in
                                                    Further details on these schemes can be found below.                   powering energy intensive processes in order to reduce
                                                                                                                           the costs to the farmer. Farms will also have export meters
                                                    5.1 ESB Networks Microgeneration                                       installed that will measure their exported electricity to
                                                    Support Package                                                        the distribution network. SSE Airtricity are providing an
                                                                                                                           annual export rebate to FarmGen customers.28 Farmers
                                                    As an initiative to support microgeneration, ESB Networks
                                                                                                                           can receive financing for the FarmGen initiative through
                                                    offered a support package for microgenerators which
                                                                                                                           the existing Glanbia Ireland FundEquip scheme and can
                                                    launched in February 2009. Customers who signed up for
                                                                                                                           also apply for TAMS II (Target Agricultural Modernisation
                                                    the scheme got a complimentary import/export meter
                                                                                                                           Schemes) or SEAI.
                                                    installed free of charge and a support payment 10 cent/
                                                    kWh applied to the first 3,000 kWh exported annually. This             We have had some initial engagement with various
                                                    payment lasted for a period of five years and ended on                 suppliers and are not aware of any other pilot
                                                    the 5th anniversary of the contract start date. The scheme             programmes or feed-in-tariff schemes that are
                                                    closed to new applicants on the 29th February 2012.                    currently or were historically available to prosumers.

                                                    5.2 Electric Ireland Microgeneration Pilot
                                                    Scheme
                                                    Electric Ireland (formerly ESB Customer Supply) launched
                                                    its microgeneration support scheme in February 2009.
                                                    Customers who signed up for the scheme received an
                                                    export payment rate of 9.0 cent/kWh.

                                                    27 https://www.electricireland.ie/residential/help/micro-generation/
                                                    electric-ireland-micro-generation-pilot-scheme

                                                    28 https://www.sseairtricity.com/news/glanbia-announce-farmgen-
                                                    sseairtricity-activ8-solar/
                                                                                                                                                                                    27
You can also read