Mediclinic Vergelegen Flood November 2013
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Index Background Event August 2013 Event November 2013 Study Lourens River Damage Difference – Flood level Risk Mitigation Lessons Learnt Future 2
Mediclinic Vergelegen Background 1. Mediclinic Vergelegen is single story 199 bed multi disciplinary hospital, which includes a heart unit, large radiology practice, regional pathology unit and several doctors suites 2. The hospital is situated in the beautiful town of Somerset West in the Western Cape, within close proximity to the Lourens River 3. Since the late 90’s, several reports highlighted shortcomings with regards to the carry capacity of the Lourens River 4. Several proposals have been tabled. Due to cost constraints, only some of these recommendations were attended too 5. During 2013 the area was flooded twice 6. The first flood occurred in August, when 100 beds and four theatres were effected 7. On 15 November a low pressure system passed over the Western Cape region which caused substantial damage to property 8. The same day the hospital was completely flooded and evacuated
Helderberg Basin Lourens River and History 4 Helderberg Basis constitutes out off 1. Gordons Bay 2. Sir Lowry’s Pass Village 3 2 3. Strand 4. Somerset West 1 Medi-Clinic Corporation Limited | Presentation file name.ppt | 7-Sep-2010 4
Event - August Severity • Partial flooding of hospital took place • Water depth less than 100mm throughout • Theatres 1, 2, 3 & 4, wards E, F, G and H had to be evacuated and was accommodated in hospital Clean-up • Started same evening and was completed within 5 days Business Interruption • Minimal Impact Risk Mitigation • Cleaned all storm water systems with high pressure • Excavate emergency trench • Appoint Civil Engineer 10 September 2013 • Report furnished on 11 November 2013
Event - November Severity • Extreme low pressure system over greater Western Cape Region • Entire hospital was flooded • Water depth more than 1 000 mm in certain areas • On average between 400 mm to 700 mm throughout Clean-up • Started following day • Focussed on doctors rooms and less impacted areas • Reinstated rooms with emergency repairs within 5 days • Reinstated 90 beds, 10 ICU beds, 4 theatres and EC within 10 days • Rest of the hospital was completed within 72 days, 80 beds, cath lab, 11 CC ICU, 7 CT ICU, 4 NICU, 3 theatres, radiology and pathology • MRI was completed by March 2014
Event - November Business Interruption • Major impact on operation of greater medical village • Hospital was evacuated and all services suspended Risk Mitigation • Cleaned all storm water systems with high pressure • Built a temporary culvert/berm, December 2013 • Appointed land surveyor to measure surrounding contours • Appoint civil engineer and designed retention system • Obtain permission from council to build a retention dam on public space, have a public road reshaped and to discharge 12 m3/s hydraulic culvert water onto a public road • Appointed contractor and work commenced during February after all approvals was obtained; • Project committee • Local authorities
Event - November Material Damage • Extensive damage to wall finishes, joinery, services and equipment • Damage to ceilings – high level of moisture deformed boards • Water ingress into walls, service ducts, conduit • Discolouring of grout and water retention in walls, dry as well as masonry • Many services are integrated into joinery, pedestals, head boards, etc.
Study Lourens River Hydrology, Hydrodynamic modelling and Evaluation of Mitigation measures • The Institute for Water and Environmental Engineering, Department of Civil Engineering, of the University of Stellenbosch was appointed on 15 December 2013 to carry out an investigation on the flood hydrology and river hydraulics of the Lourens River. • Final report was submitted on February 2014 • Slides 11 to 18 is abstracts from the above report
Study Lourens River
Study Lourens River Medi-Clinic Corporation Limited | Presentation file name.ppt | 7-Sep-2010 12
Study Lourens River
Study Lourens River
Study Lourens River
Study Lourens River
Study Lourens River Neighbourhood below hospital
Study Lourens River Damming effect, walls, old bridge, railway, N2 Lie within flood plane
Damage
Damage
Damage
Damage
Damage
Damage Damage to ceilings, tiles, joinery, services
Damage Note: Floor Services Vacuum system X-ray tube Top heavy trolleys toppled
Difference – Flood Level
Difference – Flood Level Nov Aug
Risk Mitigation
Lessons Learned: City of Cape Town 1. Too many people responded 2. Social Media – A new challenge 3. Control Centre – SAP Somerset West, but that night present at hospital 4. Doctors were not controlled by Control Centre 5. Overall – Everything worked out very well
Lessons Learned: Corporate Office 1. Who takes control (Commander) if on site 2. Media relations – Impact of social media and the control thereof 3. Control Centre at hospital – Was flooded - Relocated 4. Management – Commanders were not available at all times 5. Traffic control – Was not done or possible 6. Security – During and after disaster 7. Board of Directors – Poor communication
Lessons Learned: Corporate Office 8. Treating doctors were not called out soon enough to come and assist 9. Radiology / Pathology – To be integrated part of Hospital Emergency Plan 10. Receiving hospitals did not activate their external emergency plans 11. Nursing Care – Was sufficient care given to patients during evacuation? 12. Bed availability – How did we keep track of available beds at other facilities and the transfers – Centralized system
Lessons Learned: Hospital COMMUNICATION and INFORMATION!!! 1. Cell phones do not work – Need radio’s 2. Commanders to stay in Command Centre 3. Command Centre requires regular updates 4. Megaphone
Lessons Learned: Hospital 1. Crowd control – Was impossible to manage - Lack of security (2 guards at night) 2. Command Centre flooded – Situated at EC, ground. Did not anticipate the severity of the situation 3. Asset control – No control on what was sent with patient to other hospitals 4. Loss of control over the transfer of patients due to multiple exits 5. Insurance of X-ray department: A potential risk to our business
Lessons Learned: Hospital 1. Enough staff to assist – Accessibility of hospital was a problem 2. Clinical Care - Doctors were not called out soon enough 3. Care to patients waiting to be transferred - Could we have done more? 4. Accurate list of patients in hospital – Bed state vs AS400 5. Number of ICU vs HC patients – Level of care needed 6. Receiving hospitals did not activate their external emergency plans – Experienced their own disaster with number of patients being admitted
Lessons Learned: Hospital 1. Not enough of the following equipment: Bibs and Torches 2. The lights stayed on – power reticulate from above with sufficient redundancy – Our saving grace 3. Escape routes – Were compromised lack of communication 4. Missing keys – A number of keys were missing or the location of key unknown 5. Storm water system inadequate – This will happen again if we do not put an alternative system in place
Lessons Learned: Hospital If you do not see or smell it, do not assume it is dry – picture taken on 2014-03-28
Lessons Learned: Greater Community 1. During the flood and evacuation how people pulled together in a calm and “organised” manner 2. People from various walks of life assisting without request 3. Contractors, suppliers, civilians arriving without request and offering help the morning after the flood 4. Past colleagues and colleagues from sister hospitals offering help and taking charge of specific areas 5. Contractors that seconded staff from other sites as far as Bloemfontein, that drove through the evening and started with the clean up process for days on end on arrival 6. Leave was cancelled and some even was called back from the camp site with their families so that deadlines could be met 7. Commitment from all working extremely long hours. It was noted as some where looking extremely sleep deprive while executing duties 8. Postponing of other contracts to pool resources 9. Suppliers pulling all stops, verifying all medical devices in a short period of time 37
Lessons Learned: Greater Community 10.Redirecting deliveries from other clients to replace written off equipment 11.What stood out: • Commitment from all • Unselfishness of offering time and working long hours • Positive spirit that prevailed after many days of working very close to 24/7 for an extended period of time 12.The ownership and willingness of all to get the facility up and running 13.A hospital is not a facility with equipment, but a central nerve centre for the greater community 38
Future 39
Future 40 Medi-Clinic Corporation Limited | Presentation file name.ppt | 7-Sep-2010
Questions? 41
You can also read