Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI

Page created by Veronica Wolfe
 
CONTINUE READING
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
infrastructures
Article
Location Allocation of Sugar Beet Piling Centers
Using GIS and Optimization †
Nimish Dharmadhikari 1, *              and Kambiz Farahmand 2
 1    Transportation Modeling Coordinator, 2 West Second Street, Suite 800, Tulsa, OK 74103, USA
 2    Industrial and Manufacturing Engineering, North Dakota State University, Department 2485, PO Box 6050,
      Fargo, ND 58108-6050, USA; Kambiz.Farahmand@ndsu.edu
 *    Correspondence: ndharmadhikari@incog.org; Tel.: +1-918-579-9423
 †    This paper won the Best Student Paper award at the 2019 AASHTO GIS-T Symposium in Kissimmee, FL,
      USA. It has been modified for publishing in the journal.
                                                                                                        
 Received: 8 March 2019; Accepted: 17 April 2019; Published: 23 April 2019                              

 Abstract: The sugar beet is one of the most important crops for both social and economic reasons,
 even though the area under sugar beet cultivation in the Red River valley of North Dakota and
 Minnesota is comparatively smaller that of corn and other crop lands. It generates a large
 economic activity in local and regional level with a greater impact on jobs and stimulation of
 agriculture, transportation, and farm economy. Sugar beet transportation takes place in two stages in
 Red River Valley: the first step is from farms to piling centers (pilers) and the second step from pilers
 to processing facilities. This study focuses on the problem of optimizing piler locations based on
 supply variation. Sugar beet supply and harvest varies significantly due to numerous reasons such as
 weather, water availability, and different maturity dates for the crop. This provides for a variable
 optimal harvesting time based on the plant maturity and sugar content. Sub-optimized pilers location
 result in the high transportation and utilization costs. The objective of this study is to minimize the
 sum of transportation costs to and from pilers and the pilers utilization cost. A two-step algorithm
 based on the geographical information system (GIS) with global optimization method is used to solve
 this problem. This method will also be useful for infrastructure decision makers such as planners and
 engineers to predict the truck volume on rural roads.

 Keywords: optimization; GIS; location; sugar beet; infrastructure decision making

1. Introduction
      The sugar beet is considered as one of the most important crops in Red River Valley of North Dakota
and Minnesota in the United States. According to Farahmand et al. [1] this sugar beet co-op operation
is the largest sugar beet producer in the United States. The co-op is owned by about 2800 shareholders
who raise nearly 40% of the nation’s sugar beet acreage. They also mentioned that the last seeding
usually takes place on June 20 while full stockpile harvest starts on October 1st. This explains the
seasonal nature of sugar beet harvesting. American Crystal Sugar Company (ACSC) manages this
co-op. ACSC has five processing facilities in the Red River Valley as shown in Figure 1.
      Growers are responsible for delivering the crop to the piling centers. ACSC operates the piling
centers for growers to deliver the load to five processing factories. Beets get unloaded at the piling
center (piler) in piles and the responsibility shifts from grower to the ACSC. At the pilers, sugar beets
are cleaned and are piled 300 tall x 2400 long for long term storage through the winter. The beets need
to stay cold and frozen for long term storage or otherwise they will rot. At processing time, these beets
are loaded on the truck using conveyors. Once the truck is full, a new truck takes over loading the

Infrastructures 2019, 4, 17; doi:10.3390/infrastructures4020017              www.mdpi.com/journal/infrastructures
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2019, 4, 17                                                                                                   2 of 15

Infrastructures
beets.          2018, 3, trucks
         The loaded      x FOR PEER REVIEW
                                drive                                                                     2 of 15
                                      to the nearest sugar beet processing plant or receiving station. Figure   2
depicts this logistics system of sugar beet transportation from farms to processing plants.

                     Figure 1. Sugar beet region and processing facilities in North Dakota and Minnesota.

         Growers are responsible for delivering the crop to the piling centers. ACSC operates the piling
    centers for growers to deliver the load to five processing factories. Beets get unloaded at the piling
    center (piler) in piles and the responsibility shifts from grower to the ACSC. At the pilers, sugar beets
    are cleaned and are piled 30′ tall x 240′ long for long term storage through the winter. The beets need
    to stay cold and frozen for long term storage or otherwise they will rot. At processing time, these
    beets are loaded on the truck using conveyors. Once the truck is full, a new truck takes over loading
    the beets. The loaded trucks drive to the nearest sugar beet processing plant or receiving station.
    Figure 2 Figure
               depicts1.
              Figure   1.this
                          Sugar
                          Sugar logistics
                                    beet     system
                                    beet region
                                          region  andof
                                                  and      sugar beet
                                                        processing
                                                        processing       transportation
                                                                     facilities
                                                                     facilities  in
                                                                                 in North      from and
                                                                                     North Dakota
                                                                                             Dakota   farms   to processing plants.
                                                                                                      and Minnesota.
                                                                                                           Minnesota.
         Some beets are directly transported to the processing plants without storing them. This process
    isSome
      Growersbeets
       dependent areare
                     on  directly
                          differenttransported
                      responsible       factors.      to thethe
                                                   Farmers
                                         for delivering        processing
                                                                and  ACSC
                                                                  crop  to theplants
                                                                               decide
                                                                                  pilingwithout
                                                                                         whether
                                                                                           centers.storing
                                                                                                      to    them.
                                                                                                         store
                                                                                                       ACSC     beetsThis
                                                                                                               operates    process
                                                                                                                       or the
                                                                                                                           to take
                                                                                                                               pilingis
                                                                                                                                     them
dependent
centers  for on
    to processing different
              growersplant     factors.the
                              directly.
                          to deliver        Farmers
                                            This      toand
                                                  decision
                                               load       fiveACSC    decide
                                                               isprocessing
                                                                  mainly    based whether     tomaturity
                                                                                      on theBeets
                                                                                factories.        store
                                                                                                      getbeets  or to
                                                                                                            of the
                                                                                                          unloaded    take
                                                                                                                    beets.   them
                                                                                                                            The
                                                                                                                       at the       to
                                                                                                                                  mature
                                                                                                                               piling
processing
center       plant
    beet(piler)
          has the   directly.
                    highest
                in piles          This
                           andsugar      decision    is mainly
                                          content. The shifts
                                  the responsibility        paymentbased   on
                                                                   fromreceived the
                                                                          grower to  maturity
                                                                                       bythe      of
                                                                                           theACSC.  the  beets.
                                                                                                 farmerAtisthe
                                                                                                             basedThe  mature
                                                                                                                     on sugar
                                                                                                                pilers,          beet
                                                                                                                          sugarbeets
                                                                                                                                  content
has  the highest
are thus
     cleaned  and sugar
          farmers   want
                    are      content.
                             to keep
                         piled    30′ tall The
                                         the     payment
                                             x beets
                                               240′   in the
                                                    long      received
                                                            forground     bymaximize
                                                                         to
                                                                 long term     the farmer
                                                                              storage          is based
                                                                                             sugar
                                                                                          through         on sugar
                                                                                                     content.   ACSC
                                                                                                      the winter.     content
                                                                                                                    The desires  thus
                                                                                                                                  to start
                                                                                                                          beets need
farmers   want
    the harvest
to stay          to keep
         cold andatfrozen    the
                       an optimal  beets
                                 for long  in
                                          time the ground
                                                 to storage
                                              term   ensure theto  maximize       sugar
                                                                     processingthey
                                                                 or otherwise             content.
                                                                                      plants
                                                                                          will are     ACSC
                                                                                                 rot.busy      desires
                                                                                                            and remain
                                                                                                       At processing    to  start  the
                                                                                                                             at these
                                                                                                                         time,  capacity
harvest
beets    at an
    throughout  optimal
       are loadedthe        time
                     onseason.
                         the truck to  ensure
                                     This        the
                                            balance
                                        using         processing
                                                       is important
                                                 conveyors.          plants
                                                                        based
                                                                 Once the     are
                                                                             truck  busy
                                                                                  on is    and
                                                                                      thefull,   remain
                                                                                            planting
                                                                                                a new timeat capacity
                                                                                                        truckand
                                                                                                               takes    throughout
                                                                                                                    harvesting
                                                                                                                      over loadingtime in
the  season.
    order  to  This  balance
              minimize       cost  is important
                                    and   maximize   based
                                                        profit ontothe
                                                                    the planting
                                                                         growers.     time   and
the beets. The loaded trucks drive to the nearest sugar beet processing plant or receiving station. harvesting    time  in  order   to
minimize    cost and
Figure 2 depicts       maximize
                    this   logistics profit
                                        system  toof
                                                   the   growers.
                                                      sugar    beet transportation from farms to processing plants.
      Some beets are directly transported to the processing plants without storing them. This process
is dependent on different factors. Farmers and ACSC decide whether to store beets or to take them
            Farm                                                                                          Processing
to processing    plant directly. This decision is mainly      Pilers based on the maturity of the beets. The mature
beet has the highest sugar content. The payment received by the farmer is based                               Plant
                                                                                                                 on sugar content
thus farmers want to keep the beets in the ground to maximize sugar content. ACSC desires to start
the harvest Farm
               at an optimal time to ensure the processing plants are busy and remain at capacity
throughout the season. This balance is important based on the planting time and harvesting time in
order to minimize cost and maximize profit to the growers.
             Farm

                                               Figure 2. Sugar beet processing.
        Farm                                                                   Processing
                                                       Pilers
                                                  Figure  2. Sugar beet processing.
                                                                                  Plant
      Pilers are considered as natural refrigerators to save beets from rotting. The colder temperatures
         PilersValley
in Red River    are considered
                      in winteras natural
                                helps the refrigerators
                                          beets to staytoatsave  beets
                                                            pilers for afrom  rotting.
                                                                          longer  timeThe
                                                                                        aftercolder temperatures
                                                                                               harvest. Sugar
        Farm
beetinroots
       Red  River Valley
            should        in winter
                    be cleaned fromhelps  the beets
                                    excessive        to stay
                                               dirt, and     at pilers
                                                          properly      for a longer
                                                                    defoliated        time after
                                                                                 and cleaned       harvest.
                                                                                                from  weed Sugar
                                                                                                            or
leaves to allow for proper ventilation while stored in piles. Sugar beets may be stored up to 4 months,
and during this storage period the roots will decay and ferment. As a result, the sugar beet roots
will heat up and the respiration leads to around 70% loss of sucrose. Decay and fermentation during
        Farm
storage could also cause sucrose loss of up to 10% and 20%. Some of the sucrose losses caused by the
storage have been reduced through the utilization of forced-air ventilation, cooling in hotter areas and
                                               Figure 2. Sugar beet processing.

     Pilers are considered as natural refrigerators to save beets from rotting. The colder temperatures
in Red River Valley in winter helps the beets to stay at pilers for a longer time after harvest. Sugar
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2019, 4, 17                                                                           3 of 15

subsequent freezing of storage piles after mid-December in colder areas. Ensuring the root temperature
never reaches 55◦ F will keep the roots from decay. During harvest, if air temperature is rising and the
root temperature increases past 55◦ F, the harvest will stop, and no sugar beets will be accepted at the
pilers. This will prevent storage rot. Cold weather and frost could also damage the roots. Foliage and
leaves have proven to provide a natural barrier to frost conditions thus protecting the roots and the
crown area. Exposed roots during a frost shutdown, experience a higher degree of frost damage.
     This situation is ideal for a location allocation problem. The locations of the pilers are to be
optimized to minimize the transportation and storage cost.
     It is really hard for planners and engineers to predict the truck volume on the rural roads.
For infrastructure decisions such as where to add lanes or which road needs widening needs data
for the truck volume. This method will help to predict the truck volume thus it will be an important
method for infrastructure decision makers.
     This article is organized as follows. Section 2 studies the literature available for location allocation
problems in agriculture and other settings. Section 3 describes the methodology and algorithm used
for solution. Section 4 discusses a case study. Section 5 presents sensitivity analysis. Section 6 presents
conclusions along with the path to future research.

2. Literature Review
      Kondor [2] presented the initial problem of the sugar beet transportation. They tried to find the
economic optimum results using the mathematical modeling of the problem. They established the
relation between the processor starting date and the scheduling of the beet arrival. They provide
the case study of Hungary. Scarpari and de Beauclair [3] developed a linear programing model for
sugarcane farm planning. Their model delivered profit maximization and harvest time schedule
optimization. They used GAMS® programing language to solve the problem. They solve this problem
based on the case study of sugarcane farming in Brazil.
      The location problem in a different setting is solved by Esnaf and Küçükdeniz [4]. They presented
the multi-facility location problem (mflp) in logistical network. Their objective is to optimally serve set
of customers by locating facilities. They studied the fuzzy clustering method and developed a hybrid
method. Their method is a two-step method in which the first step uses fuzzy clustering for mflp
and the second step further determines the optimum location using single facility location problem
(sflp). The fuzzy clustering step uses MATLAB® for geographical clustering based on plant customer
assignment. They compared their method with other clustering methods. Costs generated by the
hybrid method are less than other methods. Zhang, Johnson, and Sutherland [5] presented a two-step
method to find the optimum location for biofuel production. Step one uses Geographical Information
System (GIS) to identify feasible facility locations and step two employs total transportation cost model
to select the preferred location. They presented a sensitivity analysis of location study in the Upper
Peninsula of Michigan.
      Houck, Joines, and Kay [6] present the location allocation problem and its solution methodologies.
They examine the applications of genetic algorithm to solve the problem. They propose that these
problems are difficult to solve by traditional optimization techniques thus requiring the use of heuristic
methods. Zhou and Liu [7] propose different stochastic models for the capacitated location allocation
problem. They also propose a hybrid algorithm which integrates network simplex algorithm, stochastic
simulation, and genetic algorithm. They test the effectiveness of this algorithm with numerical
examples. In the further research Zhou and Liu [8] study the location allocation problem with fuzzy
demands. They model this problem in three different minimization models. They propose another
hybrid algorithm to solve these models.
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2019, 4, 17                                                                           4 of 15

       Lucas and Chhajed [9] provided a detailed review of literature in the field of location allocation
involving agricultural problems. They express that there are a lot of location allocation problem
solutions available but there is a lack of application-based research articles. They study six real world
examples. Pathumnakul et al. [10] considered the different maturity times of sugarcane to find the
optimal locations of the loading stations. They modify the fuzzy c-means method to consider cane
maturity time as well as cane supply. Their objective is to minimize the total transportation and
utilization cost. They compare the performance of their method with the traditional fuzzy c-means
method to conclude their method provides a better solution for the problem. They test these methods
with the help of a case study in sugarcane farming in Thailand.
       Another location problem of sugarcane loading stations is studied by Khamjan, Khamjan, and
Pathumnakul [11]. They compare the solution times of the mathematical model and the heuristic
algorithm. Their objective function includes minimization of various costs such as investment cost,
transportation cost, and cost of the sugarcane yield loss. They also applied their model to a case study
to solve the industrial problem. In a recent study Kittilertpaisan and Pathumnakul [12] present a
multiple year crop routing decision problem. Their model includes heuristic algorithm for a three-year
period of sugarcane harvesting. They solve their problem to design the planting and routing such as
sugarcane becomes mature in three years for harvesting.
       Yeh and Chow [13] present an integrated location allocation approach for public facilities planning.
They discuss integration of GIS and location allocation model. They use Hong Kong as an example.
They provide an extensive review of earlier GIS and other location allocation studies. They also provide
an alternating heuristic algorithm.
       Church [14] discusses role of GIS in the location modeling. He presents the history of the use of
GIS in location modeling. He states that GIS provide a richer dataset which can be used to find the
optimal solution of location modeling.
       Murray [15] enlists the contribution of GIS to location science in terms of input data, visualization,
problem solution, and advances in theories. His focus is to showcase the contribution of GIS towards
the advancements of the location allocation modeling theories. He reviews numerous studies showing
the usefulness of GIS in the case of location allocation problem solutions.
       Tolliver et al. [16] present a methodology to estimate the flows from crop zones to elevators and
plants. They also forecast improvement and maintenance costs for roads. They provide a model
with nodes, links, and paths. They provide a simplified grain distribution system. They provide an
exhaustive GIS analysis. They describe the creation of the travel time matrix. They also discuss how
the shortest path between origins and destinations is calculated in GIS using Dijkstra’s algorithm.
       This literature study shows that there are very few articles about sugar production and location
problems and there are nearly zero articles about sugar beet harvesting and location problems involved
in it. The use of GIS is well established for the solution of the location allocation problems as shown in
the literature review. As the numbers of sugar beet fields are large, optimization algorithms suggested
in some of the articles are not applicable in this situation. Also, there are very few articles studying
the seasonal nature of the sugar beet harvest. Based on these problems this article tries to solve the
location allocation problem for sugar beet harvesting using a two-stage GIS based Multi Facility Fuzzy
Clustering (MFFC) algorithm.

3. Methodology
     As stated earlier we use a two-stage method to solve a sugar beet piler location allocation problem.
It involves stage one of GIS analysis with clustering and stage two of optimization. The solution
algorithm is depicted in Figure 3.
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2018, 3, x FOR PEER REVIEW                                                                   5 of 15
Infrastructures 2019, 4, 17                                                                                  5 of 15

                                              Estimate sugar beet
                                                    Supply

                                             Add weights to farms
                                              based on maturity

                                                                                               Stage 1
                                                     Cluster
                                                     Farms

            Road network                     Add Pilers to clusters

                                                  Generate OD
                                                    matrix

            Weights of
             Farms

          Transportation
                                                  Optimization
               cost                                                                                Stage 2

           Set up and
          operating cost
                                                 Optimized piler
                                                   locations

                              Figure 3. Solution algorithm. O–D: origin–destination.

3.1. Stage 1: GIS Analysis with Clustering
                           Figure 3. Solution algorithm. O–D: origin–destination.

      Stage 1 involves GIS analysis. As stated by Pathumnakul [10] clustering of farms is carried out in
3.1. Stage 1: GIS Analysis with Clustering
this stage. The goal of this stage is to generate an origin–destination (O–D) matrix. A GIS dataset is
      Stage
created      1 involves
          with  different GIS   analysis.
                          shapefiles.  TheAsfarm
                                              stated  by Pathumnakul
                                                   location               [10] clustering
                                                             shapefile is then             of farms
                                                                                added in the        is carried
                                                                                              dataset.         out
                                                                                                       Along with
in
thethis stage.ofThe
     location        goalthis
                 farms,    of this stagealso
                               shapefile  is tohas
                                                generate  an origin–destination
                                                   data about                       (O–D)
                                                               planting dates at each      matrix.
                                                                                        farm,       A GIS
                                                                                               weather     dataset
                                                                                                        conditions,
is
andcreated
      yield. with  different
             Weights          shapefiles.
                       are assigned        The
                                      to the    farm location
                                              locations          shapefile
                                                         of the farms  basedis then added
                                                                               on the       in the
                                                                                      different    dataset.
                                                                                                harvest     Along
                                                                                                         times due
with the location of farms, this shapefile also has data about planting dates at each farm, weather
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2019, 4, 17                                                                             6 of 15

to different planting dates and weather conditions. In this study the weights are expressed in the
preference of the harvest time. This method provides four harvest times: week group 1 is pre-harvest
time which is earlier than peak harvest time, week group 2 and 3 are the peak harvest times, and week
group 4 is post-peak harvest times. To form a complex model these weights in harvest times can be
distributed in more than four groups. The farms are clustered in the groups of four based on these
assigned weights in terms of harvest times. Farms which are planned to be harvested earlier because
of earlier planting dates, weather conditions, or historical preference are clustered in the week group 1,
farms late in the planting date or based on farmers and ACSC’s preference, are clustered in week group
4. These clustered farms are origins. The locations of pilers are also added to this dataset which are
designated as the destinations.
     Finally, the road network is added in the dataset. The road network needs to have distances of
each segment in miles, speed limits or observed speed over these segments, and time taken to travel
the distance of each segment (travel time). The GIS software uses a shortest path algorithm to create the
O–D matrix. This method is similar to the method in Dharmadhikari, Lee, and Kayabas [17]. The O–D
matrix can be generated in two ways—1) distance in miles or 2) travel time between O–D pair. For
this process we prefer to use shortest distance in miles which will be used as one of the inputs for
optimization stage.

3.2. Stage 2: Optimization
     The aim of the Stage two is to perform the optimization to find the pair of operating pilers
and farms at the given harvest times. This will be a cost optimization process. The objective of the
optimization function is to minimize the cost of logistics. Following are the important inputs for
this process:

1.     O–D matrix generated in Stage 1
2.     Weights of farms from Stage 1
3.     Transportation cost of sugar beets
4.     Set up and operating cost of piler

      The optimization is performed based on following assumptions:

1.     Sum of all shipments should not exceed the total yield at farms
2.     Piler is either open or closed at any given time
3.     Quantity of sugar beets harvested should not be greater than piler capacity
4.     Each sugar beet farm is assigned to one piler only
5.     All pilers have the same capacity

     The cost of logistics is expressed in terms of addition of different costs involved in the process
such as the cost of transportation, the cost of yield loss if not harvested at the right time, and the cost of
piler operation. These costs are further simplified in terms of the tangible variables which are easy to
measure. These variables are piler set up cost, storage cost, distance, number of trucks, cost per mile
for the truck, and yield loss cost. This gives us Equation (1) for the cost of logistics.

                   Cost of logistics = (set up cost) + (storage cost) + (distance × number of
                                                                                                           (1)
                                    trucks × cost per mile) + (yield loss cost)

     The objective function is represented in Equation (2). The objective function states the minimization
of the cost of logistics. It is subject to the sum of all shipments being less than the total yield at
farms (Equation (3)); A Piler can be open or closed (Equation (4)); number of trucks should be greater
than or equal to zero (Equation (5)); yield at the given farm should be greater than or equal to zero
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2019, 4, 17                                                                            7 of 15

(Equation (6)); and quantity of sugar beets harvested should not be greater than total piler capacity
(Equation (7)). The explanation of data sources is presented in the case study section.

                                     n X
                                     X m X
                                         4                                                  
           Minimize Cl = Minimize                     Suj × Pj + Stj × Pj + Syi + Xijk × Tij × Cd         (2)
                                      i=1 j=1 k=1

Subject to :
                                          n X
                                          X m                    
                                                      Tij × Pj × t ≤ Y                                    (3)
                                           i=1 j=1

                                                Pj ∈ {0, 1} ∀ j                                           (4)

                                                    Tij ≥ 0 ∀ i, j                                        (5)

                                                     yi ≥ 0 ∀ i                                           (6)
                                               m
                                               X
                                                      Ij × Pj ≥ Y                                         (7)
                                                j=1

Where,

      Xijk = distance (miles)
      i = number of farms (1, 2, . . . n)
      j = number of pilers (1, 2, . . . m)
      k = number of distance (1, 2, 3, 4)
      yi = yield at farm ‘i’ (tons)
      Y = total yield from all farms = yi
                                         P

      t = sugar beet truck capacity (tons)
      Tij = number of trucks from farm i to piler j = yi/t
      Cd = cost per mile
      Ij = capacity of the piler
      Suj = set up cost of piler j
      Stj = storage cost at piler j
      Syi = yield loss cost at farm i
      Pj = 0 or 1 = Piler is used or not used
      Cl = cost of logistics

4. Case Study
       Red River Valley of North Dakota and Minnesota is the study area. This area involves sugar beet
production in nearly 30 counties as depicted in Figure 1. The sugar beet processing is handled by
American Crystal Sugar Company (ACSC). They have five processing plants at locations Moorhead,
Hillsboro, Crookston, East Grand Forks, and Drayton. As explained earlier, sugar beets are transported
first to the piler locations by farmers for storage until ACSC transports them to one of the five processing
plants. These piler locations are shown in the Figure 4 with the road network.

4.1. Data Sources
     ACSC provided locations of the plants, pilers, and farms. These are the most important locations
for the GIS analysis. ACSC also provided data related to the plant dates, costs, and yields at each
farm. The road network was built upon using TIGER shapefiles from American Census Bureau [18].
Two shapefiles for road networks in North Dakota and Minnesota are downloaded. The road networks
are then combined and cleaned. The boundary between these two states is defined by the Red River.
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2019, 4, 17                                                                                       8 of 15

    There are numerous bridges on the river. The cleanup process involved finding locations of the bridges
    and connecting the road network where an existing bridge is present. This helps to provide a combined
    network to use in the GIS analysis. The process followed in this step is similar to the process in
    Dharmadhikari, Lee, and Kayabas [17]. Sugar beet truck fuel efficiency is assumed to be 10 miles per
    gallon and
Infrastructures    average
                2018, 3, x FORfuel
                               PEERcost is assumed to be $3.00 per gallon for the study period.
                                    REVIEW                                                         8 of 15

                                 Figure 4. Red
                                    Figure      River
                                            4. Red    Valley
                                                   River     road
                                                         Valley   network
                                                                road      andand
                                                                     network  piler locations.
                                                                                 piler locations.

4.2.4.2.
     GISGIS Analysis
         Analysis
        Following
     Following   thethe  algorithmshown
                      algorithm        shownin in Figure
                                                  Figure 3,3,GIS
                                                              GISanalysis
                                                                    analysisis is
                                                                               thethe
                                                                                   firstfirst
                                                                                          partpart
                                                                                               of the
                                                                                                    ofstudy.   This analysis
                                                                                                       the study.    This
   involves
analysis     combining
          involves          all dataallsources
                    combining                   and performing
                                         data sources               a clustering
                                                       and performing              model with
                                                                             a clustering     modelthewith
                                                                                                       goal the
                                                                                                              of generating
                                                                                                                  goal of
   origin–destination
generating                (O–D) matrix.
            origin–destination               The road
                                     (O–D) matrix.    Thenetwork     of Red of
                                                            road network      River
                                                                                  RedValley
                                                                                       River is   added
                                                                                                Valley  is in the database.
                                                                                                           added   in the
database. This road network is cleaned and combined as stated in data sources section. Thecontains
   This road  network   is cleaned    and  combined   as stated  in data  sources  section.    The road   network   road
   attributes
network        such attributes
          contains   as name, roadsuch type,   androad
                                         as name,   distance
                                                          type,inand
                                                                  miles   whichinare
                                                                       distance         important
                                                                                     miles           for the
                                                                                              which are        GIS analysis.
                                                                                                          important   for
   Distance  in miles  is  used  in  creation  of the network    dataset.
the GIS analysis. Distance in miles is used in creation of the network dataset.
    Clustering
Clustering
          The sugar beet harvest starts late in months of September and October. Thus, clustering of farms
       The sugar beet harvest starts late in months of September and October. Thus, clustering of farms
    is carried out based on the harvest days. Harvest weeks are divided into four groups. These weeks are
is carried out based on the harvest days. Harvest weeks are divided into four groups. These weeks
    shown in Table 1. The farms are selected based on the harvest days falling within these four categories.
are shown in Table 1. The farms are selected based on the harvest days falling within these four
    Four separate clusters are formed for farms. The selection is carried out using select by attribute tool.
categories. Four separate clusters are formed for farms. The selection is carried out using select by
   These clusters are shown in Figure 5. By visual inspection, week group 2 and week group 3 have
attribute tool. These clusters are shown in Figure 5. By visual inspection, week group 2 and week
    the largest number of farms in the cluster. The locations of the pilers are also added in this database.
group 3 have the largest number of farms in the cluster. The locations of the pilers are also added in
   The small green pins in Figure 5 are the locations of the pilers.
this database. The small green pins in Figure 5 are the locations of the pilers.
                                                  Table 1. Week group division.
                                                Table 1. Week group division.
                              Harvest Weeks
                   Harvest Weeks                                       Days Days
                                                                            of Year
                                                                                  of Year
                   Week Group Week
                              1    Group 1                             Lessorthan
                                                                 Less than        or equal
                                                                               equal to 280 to 280
                   Week Group Week
                              2    Group 2                               281–287281–287
                   Week Group Week
                              3    Group 3                               288–294288–294
                   Week Group Week
                              4    Group 4                                  More294
                                                                      More than    than 294
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures  2018, 3, 2019,
           Infrastructures x FOR   PEER REVIEW
                                4, 17                                                                                   9 of 15   9 of 15

                                      Figure 5. Sugar beet farm clusters based on Week groups.
                                Figure 5. Sugar beet farm clusters based on Week groups.
          Closest Facility

Closest facility
             As stated in the methodology section, the clustered farms are connected to the pilers using closest
          facility method from ArcGIS® . This method uses the road network prepared in the data sources section.
      As The
           stated
                cost in  the methodology
                     of travelling                 section,
                                    for this analysis         theonclustered
                                                        is based                  farms
                                                                       the distance        arebetween
                                                                                     in miles    connected
                                                                                                         farm to    the pilers
                                                                                                                (incident)  and using
closest facility     method
          piler (facility).  Thisfrom
                                  method  ArcGIS
                                            finds the. closest
                                                    ®   This method        uses
                                                                piler to any farm.the   roadofnetwork
                                                                                    A total     four closestprepared      in the data
                                                                                                              pilers are found
          for  each farm   to generate   origin–destination    cost matrix.  This  gives us four  distances
sources section. The cost of travelling for this analysis is based on the distance in miles between          in  miles for each farm
(incident)farm.
              andThe   closest
                    piler       facility solution
                            (facility).            routes are
                                         This method            shown
                                                            finds   the in  Figurepiler
                                                                         closest    6. This
                                                                                          tocost
                                                                                             anymatrix
                                                                                                   farm.initially
                                                                                                           A totalconsists
                                                                                                                      of four of closest
          distances in miles, which is later converted in the transportation cost matrix. The transportation cost is
pilers are found for each farm to generate origin–destination cost matrix. This gives us four distances
          calculated using following method. This method states that the maintenance cost is assumed as seven
in milesmiles
            for each    farm. The closest facility solution routes are shown in Figure 6. This cost matrix
                 per gallon. The total fuel plus maintenance cost is calculated by multiplying O–D distance matrix
initially by
           consists    of distances
              two (for truck            in miles,
                               roundtrips)   and thenwhich    is by
                                                        divided   later  converted
                                                                     seven             in the
                                                                            to get gallons     transportation
                                                                                           of fuel                  cost matrix.
                                                                                                   used. The resulting    value     The
transportation      cost by
          is multiplied    is calculated
                               average cost using      following
                                               of diesel per gallonmethod.       This year.
                                                                       for the related   method
                                                                                              Thesestates
                                                                                                      costs that   the maintenance
                                                                                                            are added    for all
          four-week groups.
cost is assumed        as seven miles per gallon. The total fuel plus maintenance cost is calculated by
multiplying O–D distance matrix by two (for truck roundtrips) and then divided by seven to get
gallons of fuel used. The resulting value is multiplied by average cost of diesel per gallon for the
related year. These costs are added for all four-week groups.
Location Allocation of Sugar Beet Piling Centers Using GIS and Optimization - MDPI
Infrastructures 2018, 3, x FOR PEER REVIEW                                                                            10 of 15
       Infrastructures 2019, 4, 17                                                                                  10 of 15

                                            Figure 6. Closest facility solution routes.
                                         Figure 6. Closest facility solution routes.
             For further analysis, piler capacity is calculated from the ACSC data [19]. It states that Hillsboro
      For  further
       factory  has analysis,
                     seven pilerpiler  capacity
                                  locations.       is calculated
                                               Total  beets producedfrominthe
                                                                            theACSC   dataarea
                                                                                catchment   [19].ofItthe
                                                                                                      states  that Hillsboro
                                                                                                         Hillsboro   factory
factoryarehas  seven piler
            1,402,421        locations.
                       tons per  year. ThisTotal  beets produced
                                              is divided    by seven into the catchment
                                                                          get the capacityarea  of the
                                                                                           of each        Hillsboro
                                                                                                      piler.          factory
                                                                                                             This comes    to
       around   200,346  tons.  We   assume   capacity    of each  piler as 200,000 tons.
are 1,402,421 tons per year. This is divided by seven to get the capacity of each piler. This comes to
             Piler set
around 200,346          upWe
                    tons.  costassume
                                 and storage     cost of
                                           capacity    areeach
                                                            calculated
                                                                piler asfrom   Farahmand
                                                                          200,000  tons. et al. [1] The set-up cost is
       calculated   with  the help  of overhead     expenses.   It is
      Piler set up cost and storage cost are calculated from Farahmandcalculated  with the addition
                                                                                           et al. [1]ofThemachinery    leaseis
                                                                                                               set-up cost
       cost, building
calculated    with thelease
                         helpcost,  utilities per
                               of overhead        acre, and It
                                                expenses.     labor  and management
                                                                is calculated           charges.
                                                                                 with the addition Theofset-up   cost comes
                                                                                                           machinery     lease
       to nearly $120 per acre. The Hillsboro pilers have an area of around 35 acres. Total Set up cost is
cost, building lease cost, utilities per acre, and labor and management charges. The set-up cost comes
       calculated by multiplying area by the per acre cost, which comes to $4,200. This set up cost is assumed
to nearly $120 per acre. The Hillsboro pilers have an area of around 35 acres. Total Set up cost is
       to be the same for all pilers. The storage cost is assumed to be $0.01 per ton of sugar beets. A piler
calculated by multiplying area by the per acre cost, which comes to $4,200. This set up cost is assumed
       capacity is 200,000 tons so storage cost of a piler is $2,000. Sensitivity analysis is performed based on
to be the   same
       set up  costfor
                    andall  pilers.cost.
                         storage     The storage cost is assumed to be $0.01 per ton of sugar beets. A piler
capacity is 200,000 tons so storage cost of a piler is $2,000. Sensitivity analysis is performed based on
set up cost and storage cost.

4.3. Optimization Results
      After the GIS analysis, the following are the variables known:
Infrastructures 2019, 4, 17                                                                                                          11 of 15

4.3. Optimization Results
      After the GIS analysis, the following are the variables known:

1.     Shortest distances from each farm to nearest 4 pilers. This gives a distance matrix for each farm location.
2.     Plant date
3.     Yield
4.     Storage cost
5.     Set up cost
              Infrastructures 2018, 3, x FOR PEER REVIEW                                                                 11 of 15

     Complete 1.   listShortest
                        of the variables         used in the optimization model is given in Equations (1) and (2).
                                   distances from each farm to nearest 4 pilers. This gives a distance matrix for each
For performing thefarm   optimization,
                              location.        the   distance matrix is converted into the cost matrix by multiplying
the distances with      the cost
                   2. Plant    date of fuel. In this case, we assume cost of the diesel fuel as $3.00 per gallon
                   3. YieldInformation Administration data. The optimization model is developed in the
based on U.S. Energy
                   4. Storage cost
LINGO software        from LINDO systems. The optimization results are presented in Table 2. It shows
                   5. Set up cost
that the number      of pilers
                 Complete          required
                             list of             to be
                                     the variables    usedopen    inoptimization
                                                             in the   week group     model1, 2,   and 3inare
                                                                                               is given          41. The
                                                                                                             equations      number
                                                                                                                        1 and 2. For of pilers
needed to performing
           be open inthe   week     group 4the
                              optimization,     aredistance
                                                       16. This    is depicted
                                                               matrix  is converted in into
                                                                                        Figure       7. It
                                                                                              the cost     is also
                                                                                                         matrix     observed that
                                                                                                                 by multiplying  the for week
           distances  with   the  cost of fuel. In  this case,  we  assume   cost  of the   diesel   fuel as
group 1 to 3, the total cost is increasing but as week group 4 has less sugar beet to harvest, the total cost$3.00 per gallon based
           on U.S. Energy Information Administration data. The optimization model is developed in the LINGO
is then greatly   reduced. The validation of the model is carried out by testing Week group 1. One or
           software from LINDO systems. The optimization results are presented in Table 2. It shows that the
two pilersnumber
            in Week      group
                     of pilers     1 are termed
                                required   to be open   closed
                                                          in week ingroup
                                                                      the input
                                                                            1, 2, anddata.
                                                                                        3 areIt 41.isThe
                                                                                                      expected
                                                                                                          number ofthat  theneeded
                                                                                                                      pilers  model will not
supply anytovolume
              be open intoweek
                             these    pilers.
                                   group  4 are Model
                                                 16. This isperformed       as expected
                                                              depicted in Figure                 and
                                                                                     7. It is also      it did that
                                                                                                     observed   notfor
                                                                                                                     supply    any volume to
                                                                                                                        week group
           1 towhile
closed pilers   3, the total  cost is increasing
                         increasing      the total  butcost.
                                                         as week group 4 has less sugar beet to harvest, the total cost is
           then greatly reduced. The validation of the model is carried out by testing Week group 1. One or two
     Truckpilers
             volume      on the road network is predicted based on the optimization results. Based on the
                   in Week group 1 are termed closed in the input data. It is expected that the model will not
optimal farm-piler
           supply anypairsvolume trucks    from
                                    to these        each
                                              pilers.  Modelfarm    are assigned
                                                                performed    as expectedto theandroute      between
                                                                                                    it did not          saidvolume
                                                                                                                supply any    farm-piler pair.
           to closed
Figure 8 shows        pilers while
                    a snippet      ofincreasing    the total cost.
                                       truck volumes           on the road network. This figure shows the volume near
                 Truck volume on the road network is predicted based on the optimization results. Based on the
Crookston Yard       pilers for week group 4. It shows that the roads near pilers are experiencing higher
           optimal farm-piler pairs trucks from each farm are assigned to the route between said farm-piler pair.
truck volume.      At  the same time, it shows some other roads with higher truck volumes. This truck
           Figure 8 shows a snippet of truck volumes on the road network. This figure shows the volume near
volume data     can   be
           Crookston Yard  plotted      forweek
                               pilers for    the group
                                                    complete       Redthat
                                                           4. It shows    riverthe valley
                                                                                   roads near   road     network
                                                                                                    pilers           for each
                                                                                                           are experiencing      week group.
                                                                                                                             higher
           truck volume.
The total number             At thefor
                      of trucks       same   time,
                                          each       it shows
                                                  week          someisother
                                                            group             roadsinwith
                                                                        plotted          Figurehigher 9.truck
                                                                                                          Thisvolumes.
                                                                                                                followsThis    truck pattern of
                                                                                                                           similar
           volume data can be plotted for the complete Red river valley road network for each week group. The
the total cost.  It can be seen that as the truck volume is higher for week group 3, total costs are higher
           total number of trucks for each week group is plotted in Figure 9. This follows similar pattern of the
for that week
           total too.
                 cost. It can be seen that as the truck volume is higher for week group 3, total costs are higher for
              that week too.
                                                    Table 2. Optimization Results.
                                                           Table 2. Optimization Results.
                                               Week               Open Pilers          Total Cost
                             Week          Week Group 1               41Open Pilers    1,624,895           Total Cost
                          Week Group 1     Week Group 2               41   41          3,696,831           1,624,895
                          Week Group 2     Week Group 3               41   41          6,662,072           3,696,831
                          Week Group 3     Week Group 4               16   41           304,630            6,662,072
                          Week Group 4                                      16                              304,630

                                                       Figure 7. Optimization Results.
                                                    Figure 7. Optimization Results.
Infrastructures 2019, 4, 17                                                                      12 of 15
             Infrastructures 2018, 3, x FOR PEER REVIEW                                                       12 of 15

                 Figure 8.Figure
                           Truck    volume on the road network near Crookston Yard for Week group 4.
                                 8. Truck volume on the road network near Crookston Yard for Week group 4.
                           Figure 8. Truck volume on the road network near Crookston Yard for Week group 4.

                                    Figure 9. Truck volume during week groups 1–4 after optimization.

             5. Sensitivity Analysis
                            FigureFigure 9. Truck
                                   9. Truck       volume
                                              volume     during week
                                                       during   week groups
                                                                      groups1–41–4
                                                                                afterafter
                                                                                      optimization.
                                                                                           optimization.
                 The sensitivity analysis is carried out to check if the model is performing as expected. It is also
            important to examine the assumed values and how they perform. Week group 4 model is used to
5.   Sensitivity  Analysis
            perform two types of sensitivity analyses. First analysis is carried out to test the changes in the yield
            whereas the second analysis is performed to check the effects of changing piler set up costs.
     The sensitivity analysis is carried out to check if the model is performing as expected. It is also
important to examine the assumed values and how they perform. Week group 4 model is used to
perform two types of sensitivity analyses. First analysis is carried out to test the changes in the yield
Infrastructures 2019, 4, 17                                                                                                                       13 of 15

5. Sensitivity Analysis
       The sensitivity analysis is carried out to check if the model is performing as expected. It is also
important to examine the assumed values and how they perform. Week group 4 model is used to
perform two types of sensitivity analyses. First analysis is carried out to test the changes in the yield
whereas       the second
   Infrastructures   2018, 3, xanalysis
                                  FOR PEERis      performed to check the effects of changing piler set up costs. 13 of 15
                                                REVIEW
       Different 2018,
     Infrastructures    percentages
                              3, x FOR PEER  of REVIEW
                                                  yield changes are assumed for performing the sensitivity 13analysis.                               of 15
          Different       percentages        of   yield     changes      are   assumed      for  performing
The optimization model is run for these different yield values. The results of running these models                 the  sensitivity      analysis.    Theare
            Different      percentages         of yield     changes       areyield
                                                                               assumed      for The
                                                                                                performing         therunning
                                                                                                                        sensitivity     analysis.    The
shown in Figure 10. The number of open pilers reduces as the yield at each farm is reduced byare
   optimization          model      is  run   for   these      different             values.           results    of                these    models      50%
     optimization
   shown                  model       is run   for these        different    yield   values.   Theyield
                                                                                                      results at of  running      these    models by are
and    75%.inAtFigure
                    the same  10. Thetime, number
                                             the number  of open   of pilers    reduces
                                                                       open pilers          as the
                                                                                        increases      as the     each
                                                                                                                 yield   farm
                                                                                                                          at each is reduced          50%
                                                                                                                                      farm is increased
     shown
   and    75%.inAtFigure
                       the same 10. Thetime,number
                                               the number of open   of pilers   reduces
                                                                       open pilers         as the yield
                                                                                       increases      as the at yield
                                                                                                                each farm
                                                                                                                        at each is reduced      by 50%
                                                                                                                                    farm is increased
from original yield to 300%. But this piler opening is not immediate and happens as a gradual increase.
     and    75%.    At   the   same     time,   the   number        of open    pilers  increases
   from original yield to 300%. But this piler opening is not immediate and happens as a gradual     as  the   yield   at each     farm   is increased
Number        of open pilers
     from original          yield
                                      are constant
                                      to 300%.      But
                                                           for original       yield including       a 10%–25%          yield   increase.      As the yield
   increase.      Number         of open     pilers     arethis     piler opening
                                                               constant     for originalis not    immediate
                                                                                              yield   includingand        happens yield
                                                                                                                      a 10%–25%         as a gradual
                                                                                                                                                increase.
increases
     increase.  from
                   Number25% toof50%,  open  the number            remains   forthe  same yield
                                                                                              as it does     for yield increases           from 50% and
   As   the yield      increases        frompilers
                                                25% to   are50%,constant
                                                                     the number   original
                                                                                      remains the    including
                                                                                                          same asa it10%–25%
                                                                                                                         does foryield yieldincrease.
                                                                                                                                               increases
100%.As A the gradual       increasefrom   in the    total    cost is    also   seen remains
                                                                                      in the Figure        10. as it does for yield increases
   from    50%yield
                  andincreases
                          100%. A gradual        25%     to 50%,
                                                      increase      inthe
                                                                        thenumber
                                                                              total cost   is alsotheseensamein the Figure 10.
       Figure
     from          11   shows      the    effects    of   changes       in  the   piler  set  up   costs    onthethe number    10.ofofopen
                                                                                                                                        open pilers and
          Figure 11 shows the effects of changes in the piler set up costs on the Figure
             50%    and     100%.      A  gradual      increase      in the   total cost   is also  seen    in        number                  pilers and
total   cost.    As
            Figure
   total cost.
                      the
                  As 11
                            setup
                        theshows
                              setupthe
                                       cost  reduces,
                                        costeffects
                                              reduces,
                                                             the
                                                        of changes number
                                                              the number in theof  open
                                                                                ofpiler
                                                                                   open
                                                                                            pilers
                                                                                         setpilers   increases.
                                                                                              up costs    on the Even
                                                                                                    increases.
                                                                                                                      Eventhough
                                                                                                                     number   though
                                                                                                                                 of open   thenumber
                                                                                                                                                number
                                                                                                                                        thepilers    andofof
open     pilers
     total   cost. increases,
                    As    the   setupthe   total
                                          cost     cost
                                                reduces,   decreases.
                                                               the  number    Asofthe
                                                                                   opensetup    cost
                                                                                           pilers       increases
                                                                                                   increases.
   open pilers increases, the total cost decreases. As the setup cost increases the number of open pilers          Eventhe   number
                                                                                                                           though     the  of  open
                                                                                                                                            number     pilers
                                                                                                                                                        of
is isopen pilers
   reduced.        Thereincreases,
                              is  a      the total
                                     gradual         cost decreases.
                                                  pattern        in  this     As the setup
                                                                           decrease.      But  cost
                                                                                                it    increases
                                                                                                   settles     at    the number
                                                                                                                   eight   for   the   of  open pilers
                                                                                                                                       number      of   open
      reduced. There is a gradual pattern in this decrease. But it settles at eight for the number of open
     is
pilers   reduced.
         finally.      There
                     Eight       is
                               is is a
                                   the   gradual
                                          minimum   pattern       in  this  decrease.     But  it settles    at eight   for  the    number      of open
   pilers   finally.     Eight        the   minimumrequired  requirednumbernumberofofopen  openpilers
                                                                                                   pilerstotosatisfy
                                                                                                                 satisfyallallsupply
                                                                                                                                supplyat    atthe
                                                                                                                                               thefarms
                                                                                                                                                    farmsin
week pilers
         4.    finally.
             The    total  Eight
                             cost   is  the minimum
                                     increases      as   the  required
                                                                setup      number
                                                                         cost          of open pilers to satisfy all supply at the farms
                                                                                 increases.
   in week 4. The total cost increases as the setup cost increases.
     in week 4. The total cost increases as the setup cost increases.

                                              Figure  10.
                                               Figure10.
                                             Figure       Sensitivity
                                                          Sensitivity analysis
                                                      10.Sensitivity           for
                                                                      analysisfor  yield
                                                                                foryield  change.
                                                                                    yieldchange.
                                                                                           change.

                                             Figure 11.Sensitivity
                                           Figure       Sensitivity analysis
                                                                    analysis for
                                                                              forpiler
                                                                                  pilerset
                                                                                        setup
                                                                                            upcost.
                                                                                                cost.
                                            Figure11.
                                                   11. Sensitivity analysis  for piler set up  cost.
     6. Conclusion
   6. Conclusion
           This study shows that a two-step method using GIS and optimization can be used to allocate the
         This study shows that a two-step method using GIS and optimization can be used to allocate the
     sugar beet piler locations. This method can be used to save the total transportation cost. This method
   sugar   beet
     is also    piler
             useful forlocations. This method
                         transportation plannerscan
                                                 andbeengineers
                                                       used to save  the total
                                                                to predict the transportation
                                                                               truck volume oncost. This method
                                                                                               the rural roads.
Infrastructures 2019, 4, 17                                                                                14 of 15

6. Conclusions
      This study shows that a two-step method using GIS and optimization can be used to allocate the
sugar beet piler locations. This method can be used to save the total transportation cost. This method
is also useful for transportation planners and engineers to predict the truck volume on the rural roads.
It is hard to predict the truck volume so this will be one of the useful tools to make the infrastructure
funding decisions.
      As the farm to the piler cost is incurred by the farmers, this method can be helpful for farmers to
save more money and reduce overall cost. At the same time this method considers the maturity period
of sugar beets thus helping ACSC to transport beets at the peak of their maturity and receive highest
sugar content. As seen in the sensitivity analysis as yield changes the number of pilers changes which
can attribute to the supply variation. This method is also useful to find the optimal piler locations
in this scenario. A reduced time interval such as half a week or less can be used for clustering to get
better assessment of piler locations.
      This study does not consider the computational time saving by comparing different studies,
but it can be done in the future. While designing this type of study, additional consideration of the GIS
component needs to be taken in to account. This study is a starting point which can be expanded into
a complex model with additional steps of piler to processing plant, and processing plant to market.
In the future, this method can be used with the results from Dharmadhikari et al. [20]. Their research
performs yield forecasting which can be used as inputs for this study. Yield forecasting can become
a very useful tool for predicting the harvest times and the yield at each farm, which can be used for
weight assignment and clustering in GIS analysis. This study can also be a part of a comprehensive
economic model of sugar beet production suggested in Farahmand et al. [1]. This model can be
modified to be used as a base model for crops other than sugar beet.

Author Contributions: Conceptualization, N.D. and K.F.; Data curation, N.D.; Funding acquisition, K.F.;
Methodology, N.D. and K.F.; Software, N.D.; Supervision, K.F.; Validation, N.D.; Writing—Original Draft, N.D.;
Writing—Review & Editing, N.D.
Funding: This research is based on work supported by the National Science Foundation under Grant No. 1114363.
Acknowledgments: Authors would like to thank Poyraz Kayabas and LINDO® Support for their help with
LINGO optimization modeling. Authors would also like to thank to Barbara Albritton for reviewing the draft and
suggesting valuable corrections. Authors are grateful to ACSC for providing a significant portion of the data used
in this analysis.
Conflicts of Interest: The authors declare no conflict of interest.

References
1.    Farahmand, K.; Khiabani, V.; Dharmadhikari, N.; Denton, A. Economic Model Evaluation of Largest
      Sugar-beet Production in U.S. States of North Dakota and Minnesota. Int. J. Res. Eng. Sci. 2013, 1, 11–24.
2.    Kondor, G. Elaboration of an optimum transportation and processing program for sugar-beet. Econ. Chang.
      Restruct. 1966, 6, 43–52. [CrossRef]
3.    Scarpari, M.S.; de Beauclair, E.G.F. Optimized Agricultural Planning of Sugarcane Using Linear Programming.
      Investig. Oper. 2010, 31, 126–132.
4.    Esnaf, Ş.; Küçükdeniz, T. A fuzzy clustering-based hybrid method for a multi-facility location problem.
      J. Intell. Manuf. 2009, 20, 259–265. [CrossRef]
5.    Zhang, F.; Johnson, D.M.; Sutherland, J.W. A GIS-based method for identifying the optimal location for a
      facility to convert forest biomass to biofuel. Biomass Bioenergy 2011, 35, 3951–3961. [CrossRef]
6.    Houck, C.R.; Joines, J.A.; Kay, M.G. Comparison of genetic algorithms, random restart and two-opt switching
      for solving large location-allocation problems. Comput. Oper. 1996, 23, 587–596. [CrossRef]
7.    Zhou, J.; Liu, B. New stochastic models for capacitated location-allocation problem. Comput. Ind. Eng. 2003,
      45, 111–125. [CrossRef]
8.    Zhou, J.; Liu, B. Modeling capacitated location–allocation problem with fuzzy demands. Comput. Ind. Eng.
      2007, 53, 454–468. [CrossRef]
Infrastructures 2019, 4, 17                                                                                    15 of 15

9.    Lucas, M.T.; Chhajed, D. Applications of location analysis in agriculture: A survey. J. Oper. Soc. 2004, 55,
      561–578. [CrossRef]
10.   Pathumnakul, S.; Sanmuang, C.; Eua-Anant, N.; Piewthongngam, K. Locating sugar cane loading stations
      under variations in cane supply. Asia-Pac. J. Oper. 2012, 29, 1250028. [CrossRef]
11.   Khamjan, W.; Khamjan, S.; Pathumnakul, S. Determination of the locations and capacities of sugar cane
      loading stations in Thailand. Comput. Ind. Eng. 2013, 66, 663–674. [CrossRef]
12.   Kittilertpaisan, K.; Pathumnakul, S. Integrating a multiple crop year routing design for sugarcane harvesters
      to plant a new crop. Comput. Electron. Agric. 2017, 136, 58–70. [CrossRef]
13.   Yeh, A.G.-O.; Chow, M.H. An integrated GIS and location-allocation approach to public facilities
      planning—An example of open space planning. Comput. Environ. Urban Syst. 1996, 20, 339–350. [CrossRef]
14.   Church, R.L. Location modelling and GIS. Geogr. Inf. Syst. 1999, 1, 293–303.
15.   Murray, A.T. Advances in location modeling: GIS linkages. J. Geogr. Syst. 2010, 12, 335–354. [CrossRef]
16.   Tolliver, D.; Dybing, A.; Lu, P.; Lee, E. Modeling Investments in County and Local Roads to Support
      Agricultural Logistics. J. Transp. Res. Forum 2011, 50, 101–115.
17.   Dharmadhikari, N.; Lee, E.; Kayabas, P. The Lifecycle Benefit–Cost Analysis for a Rural Bridge Construction
      to Support Bridge Construction to Support. Infrastructures 2016, 1, 2. [CrossRef]
18.   United States Census Bureau. TIGER/Line Shapefiles and TIGER/Line Files, 15 April 2018. Available online:
      https://www.census.gov/geo/maps-data/data/tiger-line.html (accessed on 15 April 2018).
19.   American Crystal Sugar Company; Hillsboro Factory Specs: Hillsboro, ND, USA, 26 April 2018. Available online:
      https://www.crystalsugar.com/sugar-processing/factories/hillsboro-nd/ (accessed on 26 April 2018).
20.   Dharmadhikari, N.; Farahmand, K.; Lee, E.; Vachal, K.; Ripplinger, D. Yield Forecasting to Sustain the
      Agricultural Transportation under Stochastic Environment. Int. J. Res. Eng. Sci. (IJRES) 2017, 5, 51–60.

                              © 2019 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access
                              article distributed under the terms and conditions of the Creative Commons Attribution
                              (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
You can also read