How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements

Page created by Joel Mckinney
 
CONTINUE READING
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
How to Interpret and Implement the Recently
 Updated UFC 4-010-01, Antiterrorism and Force
            Protection Requirements
                  Sponsored by SAME Architectural Practice

Moderator:
• Rad Delaney, AIA, F.SAME, CDM Smith
Speakers:
• Mark P. Gardner, P.E., Blast Security Consultant, Managing Engineer, Hinman
• Jeffrey Nielsen, P.E., Antiterrorism Standards Engineer, Air Force Civil Engineer
  Center (AFCEC)
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS
                      UFC 4-010-01, DOD Minimum
              Antiterrorism Standards For Buildings

                         Jeff Nielsen, P.E.
                          AFCEC/COSC
                     Antiterrorism Engineer
                    jeffrey.nielsen@us.af.mil
                  850-283-6119, DSN 523-6119
1             Integrity - Service - Excellence   UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS
                                          Background of UFC 4-010-01
                                               DoD Min AT Standards

    • UFC 4-010-01 was developed under the authority of DoD Instruction
      2000.16, DoD Antiterrorism Standards and issued by Under Secretary
      of Defense AT&L Memorandum on 20 September 2002.
       » DoDI 2000.16 requires DoD components to adopt and adhere to common
         criteria and minimum construction standards to mitigate antiterrorism
         vulnerabilities and terrorist attack.
       » Mandatory DoD minimum construction requirements for buildings.
       » Applies to DoD inhabited buildings, billeting, expeditionary, and temporary
         structures regardless of funding source.
       » Applies where no known Terrorist activity (threat) exists.
       » Combatant Commands such as CENTCOM and EUCOM have more
         stringent requirements.

2                   Integrity - Service - Excellence                              UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS
                               Security Engineering Working Group
                                                          (SEWG)

    • UFC 4-010-01 falls under the SEWG. The SEWG is Chaired by the
      Office of the Deputy Under Secretary of Defense (Acquisition,
      Technology and Logistics (ODUSD(AT&L))
       » U.S. Army
           • Headquarters, Corps of Engineers (USACE)
           • USACE Protective Design Center (Co-Chair)
       » U.S. Navy
           • NAVFAC Atlantic and Engineering Service Center
           • Chief of Naval Operation (CNO N3AT)
       » U.S. Air Force
           • Air Force Civil Engineer Center (AFCEC - Tyndall)
       » Other Defense Agencies (U.S. Marine Corps , TMA, DECA, AAFES,
         DTRA, DDESB, OUSD (I))

3                    Integrity - Service - Excellence                    UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS
                  Evolution of the Minimum AT Standards for
                                                  Buildings

    • 1999: Interim Department of Defense Antiterrorism/Force Protection
      Construction Standards issued 16 December 1999 by Under Secretary
      of Defense A&T Memorandum (FOUO)
    • 2002: Standards updated and converted to UFC 4-010-01 and issued
      by Under Secretary of Defense AT&L Memorandum on 20 September
      2002
    • 2003: UFC 4-010-01 Standards updated, dated 8 October 2003
    • 2007: UFC 4-010-01 Standards updated, dated 8 October 2003, change
      1 dated 22 January 2007
    • 2012: Major UFC 4-010-01 Standards updated, dated 9 February 2012
    • 2013: Standards updated, current version of the standards is dated 9
      February 2012, change 1 dated 1 October 2013

4                  Integrity - Service - Excellence                          UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS

                                                   Intent is Unchanged

    • Minimum Antiterrorism Standards are for locations where there is
      no defined specific threat
    • Where required minimum standoff distances can be met, conventional
      construction is adequate
    • Where standoff distance cannot be met, an equivalent level of
      protection must be provided through mitigation
    • Minimum standards will provide:
        » Reduced risk of mass casualties due to explosive event
        » Minimized collateral damage from explosives effects and fragmentation
        » Facilitation of future upgrades and increases in THREATCON

5                   Integrity - Service - Excellence                              UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS

                                           Philosophy is Unchanged

    • Comprehensive protection is cost prohibitive
    • Appropriate level of protection can be provided to lessen risk of mass
      casualties for all DoD personnel
    • Implement standards over time as new facilities are built and existing
      facilities receive major renovation
    • No known threat of terrorist activity exists
    • Three key elements -
        » Least expensive time for application is in construction / renovation
        » Master planning: Long term “blueprint” for installations
        » Design Practice: Concepts to be incorporated into standard design
          practice

6                    Integrity - Service - Excellence                            UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS

                                     Assumptions are Unchanged

    • Baseline threat
        » Stationary vehicle, placed, and mail bombs
        » Direct and indirect fire weapons
        » Chemical, biological, and radiological threats
    • Controlled perimeter
    • Levels of protection
    • Minimum standoff distances
        » Design Codes
    • Policies and procedures

7                    Integrity - Service - Excellence       UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS

                       AT Planning Process is Unchanged
      START
                                         YES     Conv constr     YES
    UFC 4-020-01
                         Only min std
                                                 standoff dist            Apply
                           required
                                                    availabl           UFC 4-010-01

                          NO                       NO

                                    UFC 4-020-02

                               Support Manuals
                   UFC 4-020-03, UFC 4-20-04, UFC 4 021-01,
                      UFC 4-022-01, UFC 4-023-03, etc.

                                        FINISH

8                  Integrity - Service - Excellence                              UNCLASS
How to Interpret and Implement the Recently Updated UFC 4-010-01, Antiterrorism and Force Protection Requirements
UNCLASS

                                                What has Changed?

    • The primary reasons for the 2012 edition is to incorporate lessons
      learned since the 2007 edition and to increase the conventional
      construction’s standoff based on wall material type
    • The primary reason for the recent 2013 revision was to incorporate
      the applicability of the Interagency Security Committee (ISC) The
      Risk Management Process for Federal facilities for DoD leased
      facilities in lieu of the UFC
    • The changes implemented will be discussed together since they
      occurred fairly close together
    • The following slide highlights the key updates to the AT minimum
      standards
    • As discussed earlier, there is no change in the intent, philosophy nor
      the assumptions that underpin the Minimum AT Standards

9                   Integrity - Service - Excellence                           UNCLASS
UNCLASS

                                                     What has Changed?
     • The applicability changes
         » DoD Leased facilities must now comply with ISC physical security
           standards and procedures in The Risk Management Process for Federal
           Facilities document http://www.dhs.gov/interagency-security-committee-
           standards-and-best-practices
     • The exemption changes
         » Fisher House with no more than 24 units
         » Town centers with no more than 12 MFH units above commercial space on
           1st floor
         » Enhanced Use Lease facilities outside the base perimeter with non DoD
           occupants
         » Transitional, temporary and relocatable buildings in use for less than 5
           years
         » Mini-marts and commissaries with less than 15,000 SF (standoff only)
     • Installation master plan required for all existing and new facilities
10                    Integrity - Service - Excellence                                UNCLASS
UNCLASS

                                                           Design Submittals

     • Design submittal requirements
         » Narrative of how each applicable standards is met
         » Applicable explosive weights and level of protection provided
         » Standoff distance provided
         » Blast resistant window and supporting structure calculations or test
           results
         » Building element structural analysis or design calculations if the
           conventional construction standoff distance is not used
         » Progressive collapse calculations if required
     • Design submittal, drawings, and specifications that include the
       explosive weight must be handled as FOUO.
     • If referred to only as Explosive weight I, II or III the document may be
       distributed as open source.

11                    Integrity - Service - Excellence                            UNCLASS
UNCLASS

                                            Key Definition Changes

     • The Definition changes
        » Billeting, Family Housing, Fisher Houses
        » DoD personnel
        » Minimum standoff distance
        » Primary gathering building
        » Unobstructed space

12                  Integrity - Service - Excellence            UNCLASS
UNCLASS

                                                  Key New Definitions

     • Additional definitions added for clarity
         » Controlled Parking
         » Change of Occupancy
         » Deviation
         » Plant replacement value
         » Uncontrolled public access
         » Usable building area

13                     Integrity - Service - Excellence            UNCLASS
UNCLASS

                                                                        Standards
     •   Standard 1: Standoff distance           •   Standard 12: Exterior Doors
     •   Standard 2: Unobstructed space          •   Standard 13: Mail rooms
     •   Standard 3: Drive-up / drop-off         •   Standard 14: Roof Access
     •   Standard 4: Access roads                •   Standard 15: Overhead mounted
     •   Standard 5: Parking beneath Buildings       Architectural features
         or on Rooftops
                                                 •   Standard 16: Air Intakes
     •   Standard 6: Progressive collapse
         avoidance                               •   Standard 17: Mail room ventilation
     •   Standard 7: Structural isolation        •   Standard 18: Emergency air
                                                     distribution shutoff
     •   Standard 8: Building overhangs
     •   Standard 9: Exterior masonry walls      •   Standard 19: Utility distribution and
                                                     installation
     •   Standard 10: Windows & skylights
                                                 •   Standard 20: Equipment bracing
     •   Standard 11: Building entrances
                                                 •   Standard 21: Under building access
                                                 •   Standard 22: Mass notification
14                      Integrity - Service - Excellence                               UNCLASS
UNCLASS

                                     Minimum AT Standards Changes

     Standard 1. Minimum Standoff Distances
     • No longer one conventional construction standoff distance for each
       explosive weights I and II
         » Conventional construction standoff is now in a matrix with ten different
           wall materials and two different wall loadings and two different levels of
           protection. See UFC 4-010-01, Table B-2
         » Some conventional construction standoff distances got worse.
         » Conventional construction standoff still based on typical construction
           materials, application, and details
         » Still have the option to design structures that perform better than the
           conventional constructed wall system
         » Standoff from base perimeter at ECF measured to the ID check point

15                   Integrity - Service - Excellence                                UNCLASS
UNCLASS

                           Minimum AT Standards Changes

     Standard 1. Minimum Standoff Distances (cont.)

                                  GLAZING STANDOFF
                                  MAY DETERMINE THE
                                  BUILDING STANDOFF
                                  NOT THE WALLS

16               Integrity - Service - Excellence   UNCLASS
UNCLASS

                                        Minimum AT Standards Changes

     Standard 2. Unobstructed Space
     • No longer a set distance of 10 m (33 feet)
         » Unobstructed space is based on the hand carried explosive weight II.
           Therefore the unobstructed space is the same as the facility standoff for the
           given wall type.
             • Unobstructed space will extend from the building to the edge of the non
               controlled parking
             • Pedestrian access control (fence/wall) required for controlled parking area

17                     Integrity - Service - Excellence                                      UNCLASS
UNCLASS

                                   Minimum AT Standards Changes

     Standard 3. Drive-Up / Drop-Off
     • Child Care Centers removed from the list of facilities allowed to have a
       drive-up/drop-off

     Standard 5. Parking Beneath Building or on
     Rooftops
     • The new UFC stipulates the explosive standoff of 4 feet horizontally
       and 2.5 feet above the structural component. Follow the design criteria
       within Protective Design Center Technical Report 06-08

18                   Integrity - Service - Excellence                        UNCLASS
UNCLASS

                                   Minimum AT Standards Changes

     Standard 10. Windows and Skylights
     • There is no longer a prescriptive window /glazing design for
       conventional construction standoff
     • All windows, skylights, and other glazing must be designed for the
       applicable explosive weight and standoff.
     • Within 200 feet of the base perimeter both explosive weight I and II
       must be calculated to determine which pressure and impulse is
       greatest
     • Frames other than steel and aluminum may be used provided they
       meet the testing requirement

       GLAZING STANDOFF MAY DETERMINE THE
       BUILDING STANDOFF NOT THE WALLS
19                  Integrity - Service - Excellence                          UNCLASS
UNCLASS

                                         Minimum AT Standards Changes

     Standard 10. Windows and Skylights (cont.)
     • Static design method (ASTM F2248)
         » Allowable design deflection of the window frame member is increased to
           1/60 of the member length in lieu of 1/160 in the previous edition
         » New design procedure for calculating supporting structural elements
            • The design load no longer needs to be 8 times the glazing resistance found in
              ASTM E1300

     • Skylights designed for medium level of protection (laminated glass
       may break but cannot level the frame)

20                    Integrity - Service - Excellence                                        UNCLASS
UNCLASS

                                     Minimum AT Standards Changes

     Standard 10. Windows and Skylights (cont.)
     • For a project only required to comply with standard 10, design the
       new windows or skylights based on the existing parking and roadway
       standoff or the facility standoff identified in the installation AT master
       plan
     • For a building exempt from minimum standoff distances (Burger
       King, Bank, Mini Mart) must use the prescriptive window described in
       para. B-3.1.7
     • Exterior stairways and breezeways may be classified as non occupied
       areas. Therefore , glazing in exterior stairways and breezeways are
       not required to be blast resistant. However, any glazing at the building
       entrance inside the stairwell must provide blast and debris resistance.

21                   Integrity - Service - Excellence                          UNCLASS
UNCLASS

                                   Minimum AT Standards Changes

     Standard 12. Exterior Doors
     • Within 200 feet of the base perimeter both explosive weight I and II
       must be calculated to determine which pressure and impulse is
       greatest
     • New ASTM F2247 and ASTM F2927 design testing standards for
       doors is incorporated.
     • The inner door of foyers or vestibules must provide the protective
       boundary for the occupants.
     • Overhead doors are required to be tethered to prevent them from
       translating into inhabited spaces

22                  Integrity - Service - Excellence                          UNCLASS
UNCLASS

                                   Minimum AT Standards Changes

     Standard 16. Air Intakes
     • Existing building must now comply with the minimum air intake
       height of 10 feet
     • HVAC replacement project must now comply with the minimum air
       intake height of 10 feet requirement regardless of the 50% major
       renovation trigger
     • Where mechanical room louvers allow blast pressure on the internal
       building walls and doors, those walls and doors must be designed as if
       they were exterior walls and doors

23                  Integrity - Service - Excellence                        UNCLASS
UNCLASS

                                   Minimum AT Standards Changes

     Standard 17. Mail Room and Loading Dock
     Ventilation
     • The requirements for mail rooms now also includes internal loading
       dock areas
     • Walls and doors separating mail rooms and loading docks from
       inhabited portions of the building must be sealed and weather stripped

24                  Integrity - Service - Excellence                        UNCLASS
UNCLASS

                                     Minimum AT Standards Changes

     Standard 18. Emergency Air Distribution Shutoff
     • Locations of the manual shut off switch was revised to comply with a
       travel distance to each switch not to exceed 200 feet
     • UFC allows the engineer to determine if shutting off the some exhaust
       systems violates the fire code or creates another unsafe condition
     • Special provision added for fan coil unit heaters and air conditioners
         » Leak proof dampers not required
         » Emergency shut off only recommended for existing facilities
     • HVAC replacement project must now comply with the air
       distribution shutoff requirement regardless of the 50% major
       renovation trigger

25                  Integrity - Service - Excellence                        UNCLASS
UNCLASS

                                     Minimum AT Standards Changes

     Standard 19. Utility Distribution and Installation
     • Deleted former standards 19
        » Maintaining critical facilities utility systems or providing redundant
          utilities is not part of the minimum AT standards and not required for life
          safety and prevention of mass casualties

26                   Integrity - Service - Excellence                              UNCLASS
UNCLASS

                     Wrap-Up

27             Integrity - Service - Excellence   UNCLASS
LESSONS LEARNED FROM IMPLEMENTING
   ANTI-TERRORISM/FORCE PROTECTION
                                                     WITH
         2013 UNIFIED FACILITIES CRITERIA
                (UFC 4-010-01)
   MARK GARDNER, MANAGING ENGINEER
   HINMAN CONSULTING ENGINEERS, INC.

   June 12, 2014

Copyright © 2014 Hinman Consulting Engineers, Inc.          1
LESSONS LEARNED FROM IMPLEMENTING ANTI-TERRORISM/FORCE PROTECTION
                  WITH 2013 UNIFIED FACILITIES CRITERIA (UFC 4-010-01)

 Agenda

                                                     • Overview
                                                     • Pre-design Examples
                                                     • Design Examples
                                                     • Construction Examples

Copyright © 2014 Hinman Consulting Engineers, Inc.                                    2
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  OVERVIEW

   • What were some overarching goals of the changes?

         –Reduce misunderstandings of its provision.

         –Address situations not previously addressed.

         –Improve the consistency of interpretation.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         3
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  PRE-DESIGN – DESIGN BASIS THREAT / LEVEL OF PROTECTION

   • This requirement is consistently ignored.
   • Multiple projects just assume there is no project specific DBT
      and/or LOP is minimum per UFC 4-010-01. In reality, the UFC
      4-020-01 process needs to be completed.
   • It is imperative to clarify this during the bidding process to make
      sure 1391 was properly developed.
   • 4 Projects recently have increased their DBT after the 1391 was
      developed causing funding issues.
   • Ensure the RFP is clear on threat size and location and level of
      protection.
Copyright © 2014 Hinman Consulting Engineers, Inc.                                         4
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  PRE-DESIGN – WHICH STANDOFF                                 IS   REQUIRED

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         5
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  PRE-DESIGN - WHICH STANDOFF                                IS   REQUIRED?

                                                                            • Many project design teams
                                                                               see the “minimum” standoff
                                                                               and want to design site plan
                                                                               around this.
                                                                            • The minimum does not
                                                                               mean cost effective.
                                                                            • Many times at pre-design
                                                                               stage the design team does
                                                                               not know building
                                                                               limitations; need provide
                                                                               flexibility for standoff to
                                                                               reduce costs.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                                            6
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - SUBMISSIONS

      • Multiple projects have reached 95% phase without any blast
         calculations submitted.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         7
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - PARKING GARAGES

      • If new or existing garage is taller than your facility, make sure the
         roof design of the new facility accounts for the line of sight for the
         design threat.

      • The roofs in the conventional construction tables assume threat
         below roof line

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         8
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - UNOBSTRUCTED SPACE FOR EXISTING BUILDINGS
      For existing building - to mitigate the introduction of hand delivered
      explosives into the controlled parking areas those areas will have
      some means to control pedestrian access as well as vehicular
      access, such as fencing or walls. \1\ Fences or walls will be a
      minimum of 6 feet (2 meters) high. Specific fence, wall, and access
      control requirements will be coordinated with physical security and
      antiterrorism personnel /1/.

     • Need to coordinate with local personnel to determine if this is
        feasible for building operations inside a controlled perimeter or if
        the existing building should be hardened for a WII threat.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         9
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - FAÇADE (METAL PANEL / BRICK)
       How do you handle façade materials not in the
       Conventional Construction Standoff Distance Chart?
         Per PDC Forum: The assumption is that the face material is not a
         structural material, only mass to help resist the blast. That said
         the face material does not require a blast analysis, but if the
         supported weights of the face materials differed from the EIFS and
         brick veneer assumptions, then the metal or wood studs would
         need to be dynamically designed using the appropriate supported
         weight.
         However, if you need to provide higher LOP's or have identified
         threats larger than those assumed by the Minimum Standards,
         then the façade needs to be investigated.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         10
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN – CONVENTIONAL CONSTRUCTION STANDOFF DISTANCE (CCSD) LIMITATIONS

      Pay attention to strength, span, and support conditions

      Note 9: Shear will need to be checked when using
      higher than minimum material strengths.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         11
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - INCREASE SHEAR

     Attention to increase requirement for shear capacity in
     concrete and CMU walls is regularly missed but is critical
     to ensure the wall meets the requirements of the UFC.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         12
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - ROOFS

   • PDC Forum: “We can only vouch for the properties we’ve investigated. Things get
     complicated in dynamic systems. Shorter span walls may have increased shear stress
     issues. Longer spans will have greater deflections. Roof spans are less likely to
     make a difference, but we’d have to do a parameter investigation to see at what
     point they would start to make a difference. The same goes for other material
     properties.
      The bottom line, therefore, is that any properties outside those in Table 2-
      3 will have to be analyzed.”
Copyright © 2014 Hinman Consulting Engineers, Inc.                                         13
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN – VESTIBULES

 •Need to remember to properly support the inner system head condition.

 •Can use higher level of protection on outer door and sidelights to prevent
 debris

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         14
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  DESIGN - PROGRESSIVE COLLAPSE – TIE FORCE

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         15
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  CONSTRUCTION - SPECS
 • Develop Performance Specs for vendors

        – Eliminates the guess work / interpretation by vendors

        – Ensures that the right standoff / design pressure is being utilized

        – Avoids disagreements over interpretation issued.

 • UFGS Specs are not 100% up to date with latest criteria. Make sure
     they are edited for project specific requirements before submission.

 • On drawings and specs, reference the applicable version of UFC 4-010-
     01.

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         16
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  CONSTRUCTION - STANDOFFS

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         17
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  CONSTRUCTION - STANDOFFS

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         18
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  CONSTRUCTION - STANDOFFS

• Short standoffs do not allow static approach as they are out of ASTM F 2248
   range
• 1 15/16” Glass does not work for Low LOP
• Glass too thick for “typical” manufacturers.
Copyright © 2014 Hinman Consulting Engineers, Inc.                                         19
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  CONSTRUCTION - STANDOFFS

Copyright © 2014 Hinman Consulting Engineers, Inc.                                         20
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

  CONSTRUCTION - STANDOFFS

  • Short standoffs do not allow static approach as they are out of ASTM
      F 2248 range
  • 1 5/16” Glass does not work for Low LOP
  • Required glass too thick for Conventional Construction
  • Door will require center astragal
  • Vertical Mullion needs to be deeper
  • Post installed anchorage will be challenging

                                                                     Ductility               Rotation (deg)
                 Mullion                        Threat                                                            Reaction (kips)
                                                           Analysis          Criteria   Analysis       Criteria

          7.5" depth w/ Inserts               W2@13ft        13.31               -       19.89           10            14.8

          10.5" depth w/ Inserts              W2@13ft        9.59                -         9.13          10           32.33

Copyright © 2014 Hinman Consulting Engineers, Inc.                                                                                  21
Anti-Terrorism Force Protection Design using Unified Facilities Criteria
                2013 DoD Minimum Anti-Terrorism Standards for Buildings: UFC 4-010-01

    Contact:
    Mark Gardner: mgardner@hce.com
    703-416-6780
    http://www.hce.com/blog/
    http://www.hce.com/contact/community.php
                                                                                           Feedback on Presentation is Welcome

Copyright © 2014 Hinman Consulting Engineers, Inc.                                                                               22
You can also read