GUIDELINES FOR (IPDS) - Integrated Power Development Scheme - MINISTRY OF POWER - nrassuseimmukaut - Rajasthan Energy Department

Page created by Enrique Wilson
 
CONTINUE READING
r..
                  blesnatlftElik
                                                                          nrassuseimmukaut

                                                                GUIDELINES

                                                                            FOR

                   Integrated Power Development Scheme

                                                                          (IPDS)

                                                           MINISTRY OF POWER
                                                              GOVERNMENT OF INDIA

      ...M11111:924121113L=L
                                   4P06'+WallEMME23111111MLAwa.firt4443         tsar, ~r   "   t
INDEX
                        S. No.                                Content                                          Page No.

                                1
                                    THE IPDS SCHEME
                            2
                                    PROJECT FORMULATION AND IMPLEMENTATION
                                3
                                    STAKEHOLDERS ROLES AND RESPONSIBILITIES
                            4
                                    SCHEME OUTLAY AND FUNDING MECHANISM

                                    FORMAT FOR AGREEMENT
                            6       ANNEXURES

                                                                                                                          2I

=4-4.720711611111111110filiat         -21601U.LIZATar   4111.212/E11111=MEMILIBIBUILMMONINIE.M11631101111111114X1:7 iMESSIMINIXIONOIT;411tiV.i.:.W"
177311r1rTAW"          .77e

                  Chapter I - Integrated Power Development Scheme (IPDS)
                1. Background:
                 1.1   Distribution is the most critical segment of the electricity business chain.
                       The real challenge in the power sector today lies in efficient
                       management of the distribution sector. Availability of a robust sub-
                       transmission and distribution network along with adequate metering
                       arrangements is the need of the day for efficient management of the
                       distribution system.
                 1.2 Electricity is the key ingredient for accelerated economic growth and is
                      considered vital for nation's overall development. Providing reliable and
                      quality power supply in an efficient manner is an immediate requirement
                      of the day. Amongst the three major layers of Power Sector i.e.
                      Generation, Transmission and Distribution, the Distribution Sector has
                      direct interface with the end consumers and is largely accountable for
                      consumer satisfaction and also for flow of revenues in the entire value
                      chain of Power Sector. Thus, Distribution Sector plays a significant role
                      in sustenance as well as growth of the Power Sector.
                 1.3 There is a consistent increase in electricity demand, particularly in urban
                      areas, due to increase in customer base, changes in lifestyle and
                      consumption pattern, which requires continual up-gradation and creation
                      of infrastructure for electricity distribution. However, the poor financial
                      health of the distribution utilities has resulted in inadequate investment in
                      the distribution network.
                 1.4 The Government of India has been providing support to State owned
                      Discoms/Power Departments by extending financial assistance through
                      various programmes. However, the State owned Discoms/Power
                      Departments have not been able to keep pace with the growth in
                      demand of electricity, resulting in critical gaps/missing links in the sub
                      transmission and distribution network. The sub-transmission and
                      distribution network has therefore become a bottleneck in ensuring
                      reliable and quality power supply to the consumers.
                 1.5 Apart from bridging the gaps in the requisite distribution infrastructure,
                      there is also a need to focus on metering of consumers. End-to-end
                      metering is a vital need of the power sector. Effective metering of all
                      consumers will ensure proper accounting, billing, load pattern
                      assessment and planning of infrastructure required. It also helps in
                      identifying high loss pockets so as to initiate remedial measures towards
                      reduction of losses.
                1 6 Keeping in view the present financial condition of Discoms/Power Deptt.,
                     Gol has launched the Integrated Power Development Scheme (IPDS) to
                     extend financial assistance against capital expenditure to address the
gaps in sub transmission &distribution network and metering in Urban
                   and Semi-urban areas to supplement the resources of DISCOMs/Power
                   Deptt.
          1.7 In view of ambitious targets for tapping the solar energy potential in our
                country, Utilities are encouraged to take up roof top solar projects,
                installation of solar panels and smart/net-meters in the various offices of
                Discoms/Govt. establishments under IPDS.

     2.      Approval of the scheme

             2.1 Govt. of India has launched Integrated Power Development Scheme
                  (IPDS) for the Urban/Semi-urban areas with the following components:
                   (i) Strengthening of Sub-transmission and Distribution network in
                         urban areas;
                   (ii) Metering of distribution transformers / feeders / consumers in urban
                         areas and,
                   (iii) Rooftop Solar Project, installation of solar panels and smart/net
                         meters as a mandatory component under IPDS
                   (iv) Continuing IT enablement of distribution sector and distribution
                         network strengthening as per the norms of the ongoing scheme of
                         RAPDRP by subsuming the same in IPDS.

             2.2     Part-(i), (ii) and (iii) of IPDS scheme will cover works relating to
                     Strengthening of Sub-transmission & Distribution system, including
                     metering of distribution transformers / feeders / consumers in the
                     urban areas, Rooftop Solar projects and IT enablement of distribution
                     sector. The details scope of works and items excluded from the scope
                     of the scheme has been provided at Annexure-I.
             2.3 The approval has been accorded for components (i), (ii) and (iii)
                  above having scheme cost of Rs.32,612 crore including a
                  budgetary support of Rs.25,354 crore from Government of India
                  during the entire implementation period.
             2.4 Implementation of IT enablement of distribution sector and distribution
                   network strengthening under R-APDRP component of the scheme -
                     The ongoing scheme of R-APDRP will get subsumed in the new
                     scheme of !PDS and will be continued as a separate component of
                     IPDS for IT enablement of distribution sector (Part-A IT & SCADA
                     projects under RAPDRP) and strengthening of distribution network
                     (Part-B projects under RAPDRP) in the urban areas. All ongoing
                     projects under this component of the scheme will be implemented as
                     per MOP Order No.-14101/2011-APDRP dated 08.07.2013 (for
                     continuation of R-APDRP in 12th and 13th Plans and for completion of

                                                                                    -1   I

_L. • MA:4
targets laid down under RAPDRP scheme for 12th and 13th Plan
           periods) and following all the RAPDRP guidelines issued (or to be
           issued in future) in this regard from time to time since inception of the
           scheme in 2008.
           The approved revised scheme outlay of Rs.44011 crores for
           RAPDRP for 12th and 13th Plans will be carried forward to the new
           scheme of IPDS as a separate component so as to ensure that
           commitment made / targets fixed under RAPDRP are achieved.
           Office Memorandum No              dated           regarding
           setting up of Integrated Power Development Scheme (IPDS) is
           enclosed as Annexure-II.

3.0   These guidelines shall be applicable only for the components (i), (ii)& (iii)
      above of the scheme viz. Strengthening of Sub-transmission & Distribution
      system, including metering of distribution transformers / feeders /
      consumers in the urban areas, Rooftop Solar projects and IT enablement
      of distribution sector. The existing operational Guidelines/ Standard
      documents/ procedures of R-APDRP shall continue to prevail for
      implementation of R-APDRP component. The commitments already made
      under R-APDRP shall be honoured as per the approvals and guidelines.
40    State Government and Utility should work with the concerned State
      Electricity Regulatory Commission (SERC) to ensure that the financial
      benefits of Gol Grant and benefits arising out of the AT&C loss reduction
      are passed on to the consumers.
Ilraitial,7

                      Chapter II Project Formulation and Implementation
                Project formulation: The Discoms will assess the need for strengthening the
                urban distribution networks and will formulate bankable Detailed Project Reports
                (DPRs) for coverage under the scheme as per following:-
                    1 1 The DPRs will be recommended by the existing Distribution Reforms
                         Committee (DRC) at the State level under the Chairmanship of the
                         Chief Secretary/Principal Secretary/Secretary Power/Energy
                         constituted by the State for R-APDRP. The scope of the Committee will
                         be extended to cover IPDS.
                    1.2 The DRC will ensure that there is no duplication of works vis-à-vis any
                         other Gol scheme under implementation in same area, while
                         recommending the projects to the Nodal Agency.
                    1.3 Power Finance Corporation Limited (PFC) will act as the Nodal Agency
                         for operationalization of the scheme. The projects will be appraised and
                         duly recommended by the Nodal Agency for approval of the Monitoring
                         Committee chaired by Secretary (Power), Ministry of Power, Govt. of
                         India.
                    1.4 Utility should commit to inform regarding investment under IPDS to
                        their respective State Electricity Regulatory Commission (SERC) at the
                        time of recommending DPR for IPDS to Nodal Agency.
                    1.5 With a view to operationalise the scheme with ease and manageability,
                        Utility shall prepare the DPRs after consolidating the requirements of
                        strengthening the distribution network preferably Electricity Distribution
                        Circle/Zone/entire Utility wise after excluding the Rural area
                        requirements, so that all the requirements in a Utility are covered in
                        maximum 5 to 6 DPRs.
                      1.6 However, to avoid duplication of works with scope already
                          sanctioned under RAPDRP scheme, Utility shall indicate the
                          additional work component proposed under IPDS DPRs with
                          comparative BOQ for such R-APDRP project area.
                      1.7 Separate DPR for the gaps in NOFN work shall be prepared by
                           respective utility in consultation with BBNL/designated agency like
                           BSNL, RailTel, PGCIL etc. for the NOFN programme in the state and
                          shall include the proposed implementation methodology and
                          milestones along with the cost.
                      1.8 Separate DPR for ERP component shall be prepared by respective
                           utility, in case of requirement of ERP, as many states have already
                           implemented ERP

t'2    .3tiv                                         -,   %tirtervffl
AMMOIF                                                      AMON

            1.9 No cost escalation shall be admissible for the schemes sanctioned
                 under IPDS. Any additional cost on any account whatsoever to
                 complete the project shall be borne by utility.
2.   Scope of Works

The scheme shall be formulated for urban/semi-urban areas only and the details of
scope of works covered under the scheme are:
     a) Sub Transmission & Distribution Infrastructure (New/ augmentation of
        substation, 66,33,22 &11 kV lines, LT lines etc), 1000 Metering of
        Consumer, Feeders & Distribution Transformers, AMR, GIS sub-station,
        Meter Pillar Box, AMI in SCADA towns, AB cable, UG cables. Renovation
        and Modernization of existing sub stations and lines, ERP Implementation &
        customer care services, installation of Capacitors, HVDS etc.
     b) Rooftop Solar projects, installation of solar panels and smart/net meters as a
        mandatory component
     c) The scheme also includes establishment of Missing link of Optic fiber (Up to
        Sub Stations under National Optic Fiber Network-NOFN), establishment of
        National Power Data Hub at CEA, Training & Capacity building and Project
        Management Agency (PMA) for monitoring and timely implementation of the
        projects. The details scope of works and items excluded from the scope of
        the scheme has been provided at Annexure-I.
        Note: Above works shall be eligible under the scheme provided proposed scope of
        works is not covered under any Gol program like R-APDRP/ RGGVY / DDUGJY/NEF
        etc. The projects for which any other grant / subsidy from Government of India has
        already been received / proposed to be received shall not be eligible under this
        scheme. State Level Distribution Reforms Committee (DRC) under the chairmanship
        of Chief Secretary/Principal Secretary/Secretary Power/Energy shall ensure that
        there is no duplication of works while recommending the projects to the Nodal
        Agency.
3.   Eligible entities: All Discoms including private sector Discoms and State Power
     Departments will be eligible for financial assistance under the scheme. In case of
     private sector Discoms where the distribution of power supply in the urban areas
     is with them, the projects under the scheme will be implemented through a State
     Government Agency and the assets to be created under the scheme will be
     owned by the State Government / State owned companies. These assets will be
     handed over to the concerned Discom for their use during the license period on
     mutually agreed terms & conditions. The responsibility of operation and
     maintenance of these assets would be of the Discom concerned.
4.   Submission & Approval of DPRs: The DPRs will be recommended by existing
     Distribution Reforms Committee (DRC) constituted for R-APDRP. The
     submission of DPRs to the Nodal agency shall be Online through a dedicated
     web portal. The eligible projects (DPR) will be approved by the Monitoring
     Committee based on recommendations of the Nodal Agency         .

                                                                                 7!

                                                                                      .:Z4,4,11L
5. DPR for NOFN component: Government of India has already approved the
   setting up of National Optical Fiber Network (NOFN) to provide connectivity to
   2,50,000 Gram Panchayats spread over 6,600 Blocks and 641 Districts of the
   country, which would ensure broadband connectivity with adequate bandwidth.
   The existing optical fiber will be extended up to the Gram Panchayats. The
   Programme is being implemented through Bharat Broadband Network Limited
   (BBNL), which is a Special Purpose Vehicle set up by Government of India with
   the mandate to create the National Optical Fiber Network (NOFN) in India.
    The IPDS scheme envisages to connect all the 33 KV or 66 KV grid sub stations
    by extending optic fiber network being established under NOFN. Provision of
    100% grant has been made under the scheme for the missing links if any.
    The separate DPR for the said work shall be prepared by respective utility in
    consultation with BBNL/designated agency like BSNL, RailTel, PGCIL etc. for
    the NOFN programme in the state and shall include the proposed
    implementation methodology and milestones along with the cost. DPRs
    recommended by the DRC shall be submitted to the Nodal Agency.
6. Time frame for approval of projects: Approval of the project shall be accorded
   during the balance period of 12th& 13th Plan, or till cumulative value of approval
   within budgetary provision of the scheme, whichever is earlier.
7. Eligible Cost for determining grant: The project cost approved by the
   Monitoring Committee or Award cost of the project, whichever is less, shall be
   the eligible cost for determining the Grant (including additional grant) under the
   scheme. Any cost overrun during implementation of the project due to any
   reasons whatsoever shall not be eligible for any grant and shall be borne by the
   utility / respective State Government.
8. Tripartite/ Bipartite agreement: Tripartite agreement will be executed between
   PFC as the Nodal Agency on behalf of Ministry of Power, the State Government
   and the Discom for undertaking and agreeing to their stipulated
   roles/responsibilities and to ensure implementation of the scheme in accordance
   with the guidelines prescribed under the scheme. Bipartite agreement will be
   executed in case of State Power departments between PFC as the Nodal
   Agency and the State Government. The format for agreement is as per chapter 5
   of these guidelines.
9. Mode of Implementation: The projects shall be implemented on turn-key/
   partial turnkey or departmental in line with Part-B of R-APDRP.
10. Execution Period: Utility has to ensure that the projects after sanction by
    Monitoring Committee are awarded within a period of three (03) months. Projects
    under the scheme shall be completed within a period of 24 months from the date
    of issue of Letter of Award (LoA) by the utility in case of turnkey execution or
    date of declaration by utility for start of work in case of departmental execution.

                                                               •   -:•••••
11. Dedicated team for implementation of projects: Discoms shall create a
    dedicated team for implementation of projects at field & HQ levels including
    necessary manpower and requisite infrastructure like office, logistics etc. to
    strengthen the implementation and monitoring.
12. Project Management Agency (PMA):
   a) In order to complement the utility's expertise and effort, a Project
      Management Agency (PMA) will be appointed by the utility for various
      activities including monitoring of projects and ensuring timely implementation
      of the project.

   b) 100% grant will be provided by Gol towards expenditure incurred on Project
      Management Agency (PMA) as per provision in the scheme, which will be
      limited to 0.5% of cost of works or approved PMA allocation.
   c) The PMA allocation shall be disbursed to utilities/ state at the time of award
      of such agency by respective utilities
13. National Power Data Hub at CEA: National Power Data Hub at CEA shall be
    established under IPDS. CEA is expected to maintain data repository of all
    Utilities and SERCs. This data hub shall primarily be a nodal information centre
    for data and information related to power distribution systems and will broadly
    collate the state wise updated status of distribution system in the country.
    Modalities and guidelines for implementation of the data hub shall be worked out
    by CEA and shall be put up to monitoring committee for approval.

                                                                             91   ,
I=E=61:mme-9•7^"I              - .7771       ,011."1C-orrZ: "7/P1^-11-,"--

                               Chapter III-Stakeholders of the scheme- Roles and responsibilities

                             Power Finance Corporation Limited (PFC) shall be the Nodal Agency for
                             operationalization and implementation of the scheme under the overall
                             guidance of the Ministry of Power (MoP).                    rtcrOMAIMS
                                                el* 4       elg:      The role of the Nodal agency is as
                             below:

                       1.1      The projects will be appraised and duly recommended by the Nodal
                                Agency for approval of the Monitoring Committee chaired by Secretary
                                (Power), Ministry of Power, Govt. of India.
                       1.2      PFC will act as a single window service under IPDS and will coordinate
                                with the main stakeholders involved such as MoP, Monitoring
                                Committee, Central Electricity Authority (CEA), Financial Institutions,
                                utilities and consultants, if any. PFC would be expected to take the
                                initiative for speedy and timely completion of projects and thus assist the
                                Utilities in achieving loss reduction targets and other parameters of the
                                scheme.
                       13       It will monitor the implementation of projects sanctioned under the
                                scheme by periodic review with utility against identified milestones &
                                deliverables including physical and financial progress and generate
                                exception reports for the consideration of Ministry of Power.
                       1.4      The Gol funds under the programme will be provided to the State Power
                                Utility/ Distribution Company/Other agency through PFC, the Nodal
                                Agency. Budget provision for the funds shall be made annually by MoP,
                                Gol.
                       15       PFC along with REC / other financial institutions shall be providing
                                counterpart funding of the schemes covered under IPDS. Claim for
                                conversion of 50% Fl loan into grant shall be examined by PFC
                                irrespective of source of loan funding. Thereafter the approval of R-
                                APDRP Monitoring Committee will be obtained for conversion of loan
                                into grant.
                       1.6      PFC shall provide secretarial support to Monitoring Committee and also
                                make arrangements for workshops / seminars etc. under guidance of
                                MoP for capacity building of utilities and for disseminating information on
                                best practices in electricity distribution and arranging publicity of the
                                scheme etc.
                       17       Develop a dedicated web portal for submission of DPRs and for
                                maintaining the MIS of the projects.
                       18       Receive the Grant Component and other charges from the Government
                                of India and keep the same in separate Bank account for disbursement

                                                                                                  10 P

rurr4.7: -   ,rsriar
from time to time to Borrower, payment of service charges and other
                            incidental costs etc.
                  1 a       PFC shall issue necessary Guidelines or it amendments for
                            operationalization of the scheme after due approval by Monitoring
                            Committee. It shall also issue Advisories/ Best Practices/ Standard
                            documents/formats etc. for ease of implementation.
                  1.10 PFC may engage consultants for some or all of the activities, as and
                        when required for effective and smooth implementation of the scheme.
                  1.11 PFC shall carry out all the activities related to media, public relation,
                        training (capacity building) of human resources in distribution sector.
                  1.12 PFC shall compile utility wise AT&C loss data in "Report on Performance
                        of State Power Utilities" submitted to MoP annually. PFC will assess
                        reduction in AT&C losses as per Utility wise loss reduction trajectory
                        finalized in consultation with State Governments.
                  1 13 Similarly, PFC shall compile the data for upfront release of grant by state
                        government to Utilities against admissible subsidy. The certification may
                        be obtained from the respective Dir (Finance) of Discoms/ secretary (E)
                        of Power Deptt. Same will be used for conversion of 50% Fl loan into
                        grant
                  1.14 The Nodal Agency will be paid @0.5% of the total project cost as their
                        fee for operationalization of the scheme. The Fee shall be claimed as
                        follows   :

                        •     40% of Fee On sanction of Project by Monitoring Committee
                        •     30% of Fee On award/ start of work in-house implementation
                        •     20% of Fee after 1 year of award/ start of work in-house
                        •     10% of Fee On Closure/ Part Closure of project

              2     Distribution Reforms Committee (DRC) at the State level: The scope of
                    existing Distribution Reforms Committee (DRC) at the State level under the
                    Chairmanship of the Chief Secretary/Principal Secretary/Secretary
                    Power/Energy constituted by the State for R-APDRP, will be extended to
                    cover IPDS. The DRC will-
                           a) Recommend the project DPRs (including DPRs for NOFN
                              component, and Roof top solar projects) proposals of the Utilities to
                              the Ministry of Power/ Nodal Agency after due-diligence like need
                              assessment of works, cost, bankability of the project etc and
                              ensuring that all the required formalities have been complied with
                             b) To ensure non-duplication / overlapping of works with any other Gol
                                / State scheme like R-APDRP, RGGVY, DDUGJY, NEF etc.

Aint-   vt.
c) To monitor achievement and target under the scheme and resolving
                  issues relating to implementation of the approved projects viz.
                  allocation of land for sub-stations, right of way (ROW), forest
                  clearance, railway clearance, safety clearance etc.
               d) Monitor the compliance to conditionality
               e) Monitor the achievement of milestones and targets under the
                  scheme
               f) Allocate fund to Utilities within State out of total allocated fund for
                  the state under IPDS,
 3   Monitoring committee: The DPRs will be approved by the Monitoring
     Committee under the Chairmanship of Secretary (Power). The Committ6e will
     consist of representatives from Ministry of Power, Ministry of Finance, Ministry
     of Urban Development, Ministry of Housing &Urban Poverty Alleviation,
     Central Electricity Authority (CEA) and Planning Commission. Chairman&
     Managing Director, PFC will be the Member Secretary & Convener of the
     Committee. Further,
          a) The Committee will be empowered to approve operational guidelines
              prepared by the Nodal Agency for implementation of the scheme and
              to amend these guidelines from time to time within the overall
              approval granted by CCEA.
          b) The Committee will also monitor and review implementation of the
              scheme and approve conversion of loan into grant upon fulfillment of
              the necessary conditions.
          c) The Committee shall have powers to amend/ modify the scope of
             work / timelines under the scheme from time to time.
The Office rile.r9.9rPOcIPM115.$1.1.edlnAhis,lregarls -,enclosed as Annpxure.JY:

     Utility (Discom/Power Department): The Utility shall be responsible for the
     following functions-
         a)        Online submission of DPRs duly recommended by the Distribution
                   Reforms Committee (DRC) to the Nodal Agency;
         b)        Implementation of the scheme within the scheduled completion
                   period as per guidelines;
         c)        Appointment of Project Management Agency (PMA)
         d)        Establishment of a dedicated project implementation cell at field &
                   HQ levels
         e)        Submission of updated progress of the project to the Nodal Agency
                   including its periodic updation on the web portal;
          f)      Any other related information to the Nodal Agency to be provided,
                  as and when required             .

                                                                                I2

                             716tax   Viv"" ""It
4. State Government
  a)    To extend the role of the existing DRC for R-APDRP projects to
        empower the committee for recommendation of projects under IPDS;
  b )= , ; Minimum contribution to Discom(s) @ 10% (5% in case of Special
            Category States) to be arranged by State as per phasing in
        maw
  0)    State to commit for adjusting any excess release made earlier (to limit
        the subsidy amount to 60% of the completed project cost), incase utility
        fails to refund
  d)    To make upfront payment of revenue subsidy to the utility
  e)    To provide support on policy issues on distribution of power in the state;
   f)   To provide required land for sub stations and facilitate in obtaining other
        statutory clearances (ROW, forest etc.)
  p)    State commits to refund grant component released to Utility In case of
        default or poor progress resulting to short-closure/cancellation. MoP,
        Gol/PFC reserves the right to recall the grant (if not recovered
        otherwise) by way of deduction from Central Plan Allocation of the
        State.
  l)    To furnish guarantee for the loan component under the scheme in case
        the utility is not able to provide any other mode of security

                                                                          1311'
3        "niat331111M13■

                 Chapter IV- Scheme Outlay and Funding mechanism

        1. Categorization of States: The states have been categorized in two groups (i)
           Special Category States (All North Eastern States including Sikkim, J&K,
           Himachal Pradesh, Uttarakhand) and (ii) Other than Special Category States
           (all other states).
        2 Funding pattern: The funding mechanism under the scheme shall be as
           under:

                                                                  Quantum of support
                                                               (Percentage of project cost)
                                            Nature of
                     Agency
                                            support         Other than        Special Category
                                                          Special Category         States
                                                               States
          Go Jt. of India                    Grant                60                 85
          Dis corn Contribution*            Own Fund              10                  5
          Le r 'der (Fls/ Banks)              Loan                30                  10
         Ad iitional Grant from              Grant        50% of total loan   50% of total loan
         GO I on achievement of                           component (30%)     component (10%)
         pre scribed milestones                               i.e. 15%            i.e. 5%
         Ma :Kimum Grant by GOI              Grant               75%                90%
         (in r :luding additional
         gra nt on achievement of
         pre scribed milestones)

           *Minimum contribution by Discom(s) is 10% (5% in case of Special Category States).
           However, Discom(s) contribution can go up to 40% (15% in case of Special Category
           States), if they do not intend to avail loan. In case, the Discom(s) do not avail loan,
           the maximum eligible additional grant would be 15% (5% in case of Special Category
           States) on achievement of prescribed milestones. The loan component would be
           provided by PFC or by other FIs / Banks.
           Note: 100% grant will be provided by Gol towards expenditure incurred on activities
           for bridging the missing links of National Optical Fibre Network (NOFN), Training &
           Capacity Building, Establishment of National Power Data Hub at CEA and Project
           Management Agency (PMA) as per provision in the scheme.

       3. Release I Disbursement of funds by Gol:

    The grant support from Gol is proposed to be released as per following conditions:

                                                                                          14    ,

                               : 77,a   a      LAENEVABIONL.
Tranche    Conditions for release of grant              Release of Grant       Release of Grant
   no.      support by Gol                              component of GOI          component of
                                                        for partial funding       GOI for 100%
                                                           components               funding
                                                                                 components of
                                                                                   NOFN gaps
            (i) Approval    of    DPRs           by                10%          10% of respective
                Monitoring Committee                                                 project
                                                    (i.e. 6% of project
                                                                                   component
            (ii) Bipartite / Tripartite agreement  cost for normal state
                                                     / 8.5% of project
                 between       Discoms,      State
                                                       cost for sp cat
                 Govt& Nodal Agency on behalf              states)
                 of MoP.
            Placement of Letter of Award                           20%          20% of respective
            (LoA) by the utility in case of                                         project
                                                        (i.e. 12% of project
            turnkey or declaration by utility to       cost for normal state      component
            start in-house implementation (*)            / 17.0% of project
                                                            cost for sp cat
                                                               states)
     3      Utilisation of 90% of grant                            60%          60% of respective
            released by GOI (1st and 2nd                                             project
                                                         (i.e. 36% of project
            Tranche) , 100% release of                                            component
                                                       cost for normal state
            Discom contribution and Tie up of                                       (Discom
                                                       / 51% of project cost
            entire Fl loan /own resources                                       component is Nil)
                                                          for sp cat states)
            After completion of works [by                          1 0 `)/0     10% of respective
            obtaining certificate by Chartered                                      project
                                                        (i.e. 6% of project
            Accountant (CA) for Project                                           component
                                                       cost for normal state
            Closure / Short Closure duly                 / 8.5% of project
            certified by Utility]                          cost for sp cat
                                                               states)
            Release of additional Grant on             50% of Fl loan/ Own
            conversion of 50% of Fl loan/              fund component (i.e.
            Own fund component subject to               15% of project cost
            complying with conditions                  for other States /5%
            mentioned at para 7.0 below                  of project cost for
                                                         special category
                                                               States)

*In case the turnkey award cost is lower vis-a-vis the approved project cost, 2nd
tranche shall be suitably adjusted. In case of partial turnkey/departmental, any
adjustment shall be done at completion of project or based on declaration by utility

                                                                                    151H

                                 -...LIIESEIBIEL.V.17.42411611E4
11111111111EM291111NEX-MM,

             4. Allocation of available funds under IPDS:
                 4.1   In order to ensure that the benefit of the scheme in the form of Gol
                       grant is not passed on to only few states, who poses their DPR in the
                       initial period of launch of scheme, the available fund under the scheme
                       may be allocated State wise in an appropriate ratio.
                 4.2 The detail state wise allocation has been done on the basis of
                      population of Urban areas of States, Energy loss of the Discom, per
                      capita energy consumption of States etc. and enclosed at Annexure-V.
                          a) In case balance of the allocation (not sanctioned fully), the same
                             can be reallocated within these utilities as per requirement (not
                             sanctioned due to capping) on prorate basis.
                          b) State level DRC has to finalize the allocation of fund (out of
                             allocated amount far the entire state) among the utilities within
                             their State.
                 4 3 No cost escalation shall be admissible for the schemes sanctioned
                      under IPDS. Any additional cost on any account whatsoever to
                      complete the project shall be borne by utility.
                 4.4 In the case of cost over-run at the award stage, there is a possibility
                       that eligible utility may opt for reducing the scope of work or BoQ due
                       to financial constraints. In such cases, the Nodal Agency shall have the
                       power to approve revised DPRs in the manner so that the Gol grant
                       commitment is limited to original approval. Nodal Agency can also
                       approve any increase in revised project cost provided that the Gol
                       grant commitment is limited to original approval. All such revisions in
                       project cost approved by Nodal Agency will be placed in the Monitoring
                       Committee periodically.
             5. Completion of works:
                5.1 A Project Completion Certificate shall be furnished by the utility, signed by
                    Director/Member in case of Utility and Chief Engineer in case of Power
                    Department, which shall contain the information regarding date of
                   completion, details of major items of works approved and completed,
                   justification for non-completion or shelving of any project component,
                   expenditure against the project with item wise breakup certified by a
                    practicing CA etc.
                5 2 Project Closure: The projects needs to be closed in one of the following
                   manner so that closure is co-terminus with releasing/ adjusting final
                   tranche of grant, or recalling unutilized grant;
                       • On completion of sanctioned scope of work and expenditure
                          against sanctioned cost.
•   On completion of sanctioned scope of work at reduced cost of
                sanction and expenditure against sanctioned cost, project will be
                closed at such reduced cost and sanction & Gol grant will be
                revised by Nodal Agency accordingly.
            •   Excessive delay in award and implementation beyond Execution
                period may lead to part completion of sanctioned scope of work at
                reduced cost (not less than 30% of sanctioned cost) and
                corresponding expenditure against sanctioned cost. Such projects
                will be closed at such reduced cost and Nodal Agency is
                authorized to suo-moto short close at revised cost & Gol grant
                accordingly.
            •   Excessive delay in award and poor progress of implementation
                (expenditure less than 30% of sanctioned cost) beyond Execution
                period may lead to cancellation of project. Such projects will be
                suo-moto cancelled by Nodal Agency and entire Gol fund
                released to utility/ state will be recovered accordingly.
    5 3The project completion certificate/Closure /Short-closure need to be
       submitted to nodal agency. The format for Project Completion
       Report/short-closure/closure report shall be provided by Nodal Agency.
6   Eligibility for release of final installment: The date of completion as
    mentioned in the project Completion Certificate shall be within the execution
    period of 24 months in case of turnkey execution and 27 months in case of
    partial turnkey/ departmental execution to become qualified for the release of
    final tranche of 10%. The expenditure as per the Project Completion
    Certificate or the cost approved by the Monitoring Committee whichever is
    lower shall be considered as the final cost of the project for the release of the
    last installment of 10%, after adjusting any excess release made earlier (to
    limit the subsidy amount to 60% of the completed project cost).
7   Release of additional grant: Additional grant (i.e. conversion of 50% of loan
    component) under the scheme will be released subject to achievement of
    following milestones:
     (a) Timely completion of the scheme as per laid down milestones
     (b) Reduction in AT&C losses as per trajectory finalized by MOP in
         consultation with State Governments (Discom-wise)
      (c) Upfront release of admissible revenue subsidy, if any, by State Govt.
         based on metered consumption

Guideline for conversion of 50% of Fl loan/ Own fund component (i.e. 5% of
project cost for special category States and 15% of project cost for other States)
into additional grant based upon achievement of milestones is described below:

                                                                            1711
7.1 The conversion will take place in the period subsequent to the
            financial year, in which all the sanctioned works of IPDS are
            completed in the Discom to ensure availability of AT&C loss report
            of Discom.
       7.2 The performance parameters of the financial year in which all the
            sanctioned works of IPDS are completed in the Discom, shall be
            considered for conversion of loan into grant.
       7.3 Based on AT&C loss data in "Report on Performance of State
            Power Utilities" submitted to MoP annually, PFC >will assess
            reduction in AT&C losses as per Utility wise loss reduction
           trajectory finalized in consultation with State Governments and
            circulated vide MoP OM 14/5/2011-APDRP dated 28-7-2014.
       7.4 Dir (Finance) of Discoms/ Secretary (E) of Power Deptt. of
           respective States shall certify the amount of admissible revenue
           subsidy in the respective Discom area based on metered
           consumption along with upfront release of same to Discom by
           respective State Govt.
       7.5 Conversion of Fl loan/ Own fund component will take place only if-
               a) The sanctioned project has been completed within time
                  schedule of 27 months (3 month for Award and 24 months for
                  Execution) from the date of sanction of project by Monitoring
                  Committee.
               b) 100% subsidy has been released upfront to Discom by State
                  Govt. in the financial year in which IPDS scheme is completed
                  in respective Discom.
              c) AT&C loss of the Discom in the financial year in which IPDS
                 scheme is completed in respective Discom is equal or less
                 than the AT&C loss trajectory figure as finalized by MOP as
                 1::40A2nnWtiti6Y1 in consultation with State Governments
                 (Discom-wise).
         7.6 In case utility does not achieve 7.5(b) or 7.5(c) above in the year
               of completion of project, they can submit claim for conversion on
               achieving these conditions in subsequent years up to 2022 for
               which the targets have been defined in the AT&C loss trajectory.
8. AT&C loss in a Utility: The methodology for calculation of Aggregate
  Technical and Commercial Losses (AT&C loss) has been defined by PFC in
  the "Report on Performance of State Power Utilities" in consultation with CEA
  as below:
  The AT&C losses represent the difference between energy available for sale
   adjusted for transmission losses and trading in energy, Mkwh) and energy
  realized, Mkwh). Energy realized is the energy billed (adjusted for trading in

                                                                         N

                                                                                   •   •;Zir.ark:,1
enegy, Mkwh) factored by the collection efficiency. The collection efficiency is
   an index of efficiency in realization of billings, current as also previous years
   and essentially focuses on the year-to-year movement of receivables. The
   same is defined in table below:
        AT&C Losses CYO for SEBs/PDs/Discoms
    h• Net input energy (Mkwh)        =     Total input energy (adjusted for transmission
                                            losses and energy traded)
    ' • Net sale of energy (Mkwh)     =     Total energy sold (adjusted for energy
                                            traded)
    I   • Net revenue from sale of    =     Revenue from sale of energy (adjusted for
         energy (Rs. Crs.)                  revenue from energy traded)

                                      [II
        • Collection efficiency (%)         (Net revenue from sale of energy-Change in
                                            Debtors for sale of power)•100/(Net revenue
                                            from sale of energy)
        • Energy realized (Mkwh)      III   Net sale     of   energy   (Mkwh)"collection
                                            efficiency
        • AT&C Losses (%)             =     (Net input energy, Mkwh - Energy realized,
                                            Mkwh)'100/( Net input energy, Mkwh)

9 IPDS Bank Account: The utility shall open a separate bank account for
   IPDS, which shall be dedicated to the project, where in all the funds from Gol
   Grant shall be routed. All expenditure against the project shall be regulated
   through this account. The Nodal agency shall release all funds to
   beneficiaries Discoms through RTGS/NEFT/ET to the IPDS separate bank
   a ccount.
10.Supporting/ Enabling activities of Ministry of Power
        a. A provision of 0.5°A, of the total project cost has been kept for the
           supporting/ enabling activities of Ministry of Power relating to
           implementation of the scheme such as capacity building, awareness
           creation, monitoring, field inspections, evaluation studies, interaction
           with stakeholders, workshop, training etc.
        b. MoP shall make necessary budget provisions for release of Gol grant
           for release to Utility by PFC under IPDS. Moreover, MoP shall make a
           provision of rolling advance to PFC upto 20% of budget provision to be
           recouped on monthly basis.
        c. National Power Data Hub at CEA shall be established under IPDS.
           CEA is expected to maintain data repository of all Utilities and SERCs
(On Stamp paper of Rs. ......)

       Cha pters Format for4tVirtire7g31 aftite 41..t          VEireiii ttO,StfifeVf011ra)

717-                               :11111MMIVENISMEZZE.V.;',    "•"''''' =fii4.37111" 77111r,"—"'   PT' s.   a:ran"'
Annexure-I

                          Scope of works under IPDS
    1. Strengthening of sub-transmission and distribution network
       The following works shall be eligible to be covered under the scheme
       based on study/assessment carried by the respective State Discoms /
       Power Departments for identifying critical gaps in sub-transmission and
       distribution network considering all relevant parameters (such as voltage
       regulation, HT & LT ratio, optimum loading of transformers & lines,
       reactive power management, power factor improvement, standard of
       performance, ongoing works under other schemes etc.):
         (i)      Creation of new sub stations including GIS along with associated
                  66 KV / 33 KV/ 22 KV/ 11 KV lines
         (ii)     Augmentation of existing sub-stations capacity by installation of
                  higher capacity/additional power transformer along with
                  associated equipment/ switchgear etc.
         (iii)    Erection of HT lines for reorientation/re-alignment including
                  augmentation of existing lines
         (iv)     Installation of new distribution transformers and augmentation of
                  existing distribution transformers along with associated LT lines
         (v)      Installation of capacitors
         (vi)     Renovation and Modernization of existing sub-stations and lines
         (vii)    Laying of under-ground cables in densely populated areas and
                  areas of tourism and religious importance
         (viii)   High voltage distribution system (HVDS)
         (ix)     Aerial Bunched Cable for theft prone areas
         (x)      Rooftop Solar projects, installation of solar panel and smart/ net
                  meters as mandatory component
         (xi)     IT Applications
                    (a) ERP
                    (b) Customer Care Services

             Metering
        (i) Installation of suitable static meters for feeders, distribution
                transformers and all categories of consumers for existing un-
                metered connections, replacement of faulty meters & electro-
                mechanical meters.
        (ii)Installation of Pillar Box for relocation of meters outside the premises of
                consumers including associated cables and accessories
        (iii) Installation of prepaid / smart meters in Govt. establishment
        (iv) AMI, Smart meters in the towns where SCADA being established
                under R-APDRP.
        (v)     Boundary meters for ring fencing of Non-RAPDRP Towns with
                population more than 5000
        (vi) AMR for feeders, Distribution transformer and high load consumers

                                                                             21

;
3. "IT enablement of distribution sector and distribution network
      strengthening under R-APDRP" component as per ongoing RAPDRP
      scheme in accordance with MOP Order No.-14/01/2011-APDRP dated
      08.07.2013for continuation of scheme in 12th and 13th Plan and
      applicable guidelines
   4 Completion of optical fiber missing links to connect all the 33 KV or 66
      KV grid sub stations under the establishment of National Optical Fiber
      Network (NOFN)
   5 Establishment of National Power Data Hub at CEA
   6. Training & Capacity Building
Above works shall be eligible under the scheme provided proposed scope of
works is not covered under any Gol program like R-APDRP/ RGGVY /
DDUGJY/ NEF etc. The projects for which any other grant / subsidy from
Government of India has already been received / proposed to be received
shall not be eligible under this scheme. State Level Distribution Reforms
Committee (DRC) under the chairmanship of Chief Secretary shall ensure that
there is no duplication of works while recommending the projects to the Nodal
Agency.
List of items not eligible to be covered under the scheme
     Works already covered under other schemes of Govt. of India.
     AMI in the towns where SCADA is not planned under R-APDRP
     Civil works other than sub station
4    Service lines to consumer
     GIS survey of assets and consumers
     Cost of land for sub-stations
     Compensation towards right of way
     Distribution automation and IT applications (except ERP and Customer
     Care Services)
     Office equipment / fixtures
10. Spares (Other than mandatory spares prescribed by the manufacturer)
  1. Tools and Plants (T&P)
  2. Vehicles
1:3. Salaries and Establishment Expenditure

                                                                    22 F'

                                               .
Annexure-II
Office Memorandum No               dated             regarding setting up
            of Integrated Power Development Scheme (IPDS)

             r_trzerw_
Annexure-III
                         Office Memorandum No               dated               for designating
                            Power Finance Corporation as Nodal Agency for Integrated Power
                                            Development Scheme (IPDS)

                                                                                         2-11i

11111KESIREE.:‘,...iff
-
e)

                                                              Annexure-IV
Office Memorandum No                 dated            for setting up of
Monitoring Committee for Integrated Power Development Scheme (IPDS)

                 -   BILLIk-11114
                        47 '`- qi.E3=1.              •          -
Annexure-V
                              Allocation of IPDS Funds among Various states
         Name of State / UT           (%)          Partial Gol         NOFN (100%         PMA (100%        Maximum
 No                               Allocation         funding           Gol funding)       Gol funding)   Limit of state
                                       #tt         component            Component         Component          Share
                                                    (Rs.Cr.)             (Rs.Cr.)          (Rs.Cr.)         (Rs.Cr.)
          Total Allocation                            31902                120                 160             32182
        l Andhra Pradesh
  1       (including                5.55%            1724.85               6.66                8.62        1740.13
          Telangana )
12        Arunachal Pradesh         0.87%            326.08               1.04                1.63         328.75
  3       Assam                     2.13%            799.17               2.56                4.00         805.72
  4       Bihar                     4.52%            1404.74              5.42                7.02         1417.18
  5    T Chhatisgarh                 1.77%           549.90               2.12                2.75         554.77
  6      Goa                        0.18%              54.45              0.21                0.27          54.93
  7       Gujarat                   5.01%            1557.41              6.01                7.79         1571.21
  8       Haryana                   2.56%             797.18              3.08                3.99         804.24
  9    1- Himachal Pradesh          0.54%            200.76               0.64                1.00         202.41
 10       Jammu & Kashmir            1.70%           635.40               2.03                3.18         640.61
C1 1   , Jharkhand                  2.57%             797.56              3.08                3.99          804.63
  12      Karnataka                 5.08%            1579.01              6.10                7.90         1593.00
  13      Kerala                    3.35%            1039.81              4.01                5.20         1049.02
  14      Madhya Pradesh            5.34%            1660.44              6.41                8.30         1675.15
  15      Maharashtra               9.99%            3106.16              11.99               15.53        3133.68
  16      Manipur                    1.32%            493.31               1.58               2.47          497.36
  17      Meghalaya                 0.94%             352.09               1.13                1.76         354.97
  18     Mizoram                     1.01%            376.99               1.21                1.88         380.09
  19     Nagaland
            ..                       1.21%           453.53                1.45               2.27          457.25
 20      Odisha                     2.76%             856.64              3.31                4.28          864.23
 21      Punjab                     2.20%             683.79              2.64                3.42          689.85
 22      Rajasthan                  4.23%            1316.02              5.08                6.58         1327.68
 23      Sikkim                     0.69%            257.56               0.82                 1.29         259.67
 24      7amilnadu                  6.96%            2164.98              8.36                10.82        2184.16
 25      Tripura                     1.29%           482.53                1.54               2.41          486.49
 26      UttarPradesh               12.35%           3837.60              14.81               19.19        3871.60
 27      Uttaranchal                 1.09%            407.88               1.31               2.04          411.22
 28      West Bengal                7.37%            2290.67              8.84                11.45        2310.97
         UTs
         Chandigarh                 0.58%             180.28               0.70                0.90            181.88
         NCT of Delhi               2.75%             855.04               3.30                4.28            862.61
         Daman & Diu                0.05%              15.68               0.06                0.08             15.82
         D & N Haveli               0.05%              14.87               0.06                0.07             15.01
         Lakshadweep                0.92%             284.95               1.10                1.42            287.47
         Puducherry                 0.14%              44.74               0.17                0.22             45.14
         A&N islands                0.96%             299.94               1.16                1.50            302.60
         Grand Total                100%              31902                120                 160             32182

  ## RE(. imure based on various parameters
  Note
            Share of AP & Telangana to be divided based on latest census population.
            State DRC has to decide the distribution of fund among the utilities within their State

                                                                                                         26I

                                                         11-':X12/3"
MiereMi trannlitelViihitiscOMVIMIatirel
         AT&C loss Reduction trajectory finalized by MOP in consultation with State
         Government (Discom-wise)
                         Source:
    SI
                                                            Year wise projection
                           PFC
               State
    No                    2012-
                            13      14      15       16      17      18      19      20      21      22
           A -idhra
     1   P -adesh
                           13.63   13.38   13.13    12.88   12.58   12.28   12.00   12.00   12.00
       .1 A -unachal
     2 P -adesh
                          60.26    56.76   53.26    49.76   46.26   42.76   39.26   36.00   33.00
     3 A ssam             31.85    29.85   28.35    26.85   25.35   23.85   22.00   20.00   18.50
     4     Bi har         54.63    50.63   46.63    42.63   38.13   34.00   30.00   27.00   24.00
     5 C hattisgarh       25.12    24.48   22.37    20.66   19.07   17.49   16.17   15.11   14.52
        D alhi            15.22    14.72   14.22    13.97   13.72   13.22   13.00   12.50   12.25   12.00
     7 G oa               14.14    13.89   13.64    13.39   13.14   12.64   12.00   12.00   12.00   12.00
     -  --
    8 G ujarat            19.87    18.87   17.87    16.87   15.87   15.37   15.00   14.50   14.25   14.00
    9 H 3ryana            32.55    30.05   27.55    24.55   21.55   19.55   18.00   17.00   16.00   15.00
       Hi machal
                            9.53   14.50   13.50    12.50   11.50   10.50   10.00   10.00   10.00   10.00
    10 P 'adesh
            ammo &
                          60.87    55.87   51.87    47.87   43.87   39.87   35.00   30.00   26.00   22.00
    11    K   )shmir
    12    .1  larkhand    47.49    43.49   39.49    36.49   32.49   29.49   27.00   24.00   21.00   18.00
    13    K   3rnataka    20.78    18.25   17.90    17.43   16.86   16.29   15.72   15.15   14.57   14.00
    14    K   .rala       10.53    11.15   10.80    10.50   10.25   10.00   10.00   10.00   10.00
              adhya
                          31.15    27.65   25.15    23.15   21.15   19.15   17.00   16.00   15.00
           P adesO
    16 M aharashtra       21.95    20.45   18.95    17.45   16.45   15.45   15.00   14.50   14.25
    17 M =Intpuf          85.49    78.49   71.49    64.49   56.49   48.00   40.00   34.00   28.00
    18 M aghalaya         26.60    33.11   31.29    29.79   28.29   26.79   25.29   23.79   22.29
    19 Mi zoram           27.55    27.02   26.14    25.77   24.59   23.49   22.13   21.13   19.75
    20 N igaland          75.30    67.21   64.21    59.21   53.21   47.21   41.21   35.21   29.21
    21 0 tisha            42.94    38.94   37.00    35.00   33.00   30.50   28.00   25.50   23.00
    22 t P rducherry       9.13    19.00   18.00    17.00   16.00   15.00   14.00   13.00   12.00
    23P injab             17.66    17.16   16.66    16.16   15.66   15.16   15.00   14.50   14.25
        '1                                                                          15.00   15.00
    24 R ijasthan         20.00    19.00   18.00    17.00   16.00   15.50   15.00
r      4
    25 Si ckim            53.51    49.51   45.51    41.51   37.51   33.51   29.00   26.00   23.00
    26 T a  . mil Nadu    20.72    20.22   19.72    19.22   18.97   18.72   18.47   18.22   18.00
    27 1 tangana                                                                            12.00
    28 Tr pura            33.85
           Ut tar
                          42.85                                             22.85   20.00   17.00   15.00
    29 Pr adesh
    30' Ut tarakhand      23.18                                             16.00   15.00   14.50   14.00
    31 VV est Bengal      34.43    30.51   29.00    28.00   26.00   24.00   23.00   22.00   21.50   21.00
                          25.38                             19.52   18.31   17.27   16.36   15.57   14.95

                                                   WM=
You can also read