Guide to applying for a building consent (residential buildings) - Second Edition October 2010
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
About this guide 1 Introduc tion 2 1.0 The building consent proc ess 3 2.0 Pl ans and specifications 10 3.0 Design summary 13 4.0 Design summary check sheet 16 5.0 Dr awings 19 5.1 Site plan 20 5.2 Location plan 22 5.3 Foundation plan 24 5.4 Roof framing plan 26 5.5 Floor plan 28 5.6 Exterior elevations 30 5.7 Sections 32 5.8 Construction details 34 5.9 Door/window schedule 38 5.10 Plumbing layout or schematic plan 40 5.11 Electrical plan 42 5.12 Wet area details 44 5.13 Additional drawings 46 6.0 Rel ated building consent application mat ters 47 7.0 Rel ated Building Act mat ters 52 8.0 Project pl anning 55 9.0 Glossary of terms 57 This guide was prepared by the Department of Building and Housing (the Department) as guidance information in accordance with section 175 of the Building Act 2004. It is not a substitute for professional or legal advice, and should not be relied on as establishing compliance with the New Zealand Building Code. It is not an Acceptable Solution under the Building Act, and may be updated from time to time. Visit www.dbh.govt.nz for the latest version. References to products, brands or trade names are provided as examples only. The Department does not endorse or confirm compliance of these products with the New Zealand Building Code. Cover illustration by Geoff Walker Architecture Ltd, Blenheim.
About this guide AIM OF THE GUIDE Uncertainty for owners and their contractors can The information in this guide may also be useful be frustrating, inefficient and costly. This guide to people in the construction sector (eg, product Getting the planning, design and documentation right therefore aims to bring more consistency and manufacturers, suppliers, retailers and subcontractors) is the first step in ensuring a building is built right, standardisation to the sector, and set minimum and providers of specialist technical services first time. To build well and achieve a good outcome, expectations for owners and building consent (eg, building consultants, building surveyors, all parts of the building process need to work – from authorities on the form, content and quality of and property managers). the initial design and consent approval process, building consent documentation. through to construction, inspection, final sign-off It is also expected that the information provided and ongoing maintenance of the finished building. This guide covers building consent applications will prove beneficial to building consent authorities for residential buildings, such as new dwellings. by providing them with a guide for an acceptable The building consent is the foundation document for However, the principles can be applied to all minimum standard of consent application any significant building project. The building consent building consent applications, including those for documentation. allows the owner, or owner’s agent, to carry out commercial projects. building work in accordance with the plans and Because readers are expected to have a reasonable specifications approved by the building consent level of knowledge of the Building Code, construction authority. The building consent also provides formal WHO SHOULD READ THIS GUIDE? processes and building control systems, this guide is recognition that the plans and specifications meet not intended for homeowner (DIY) consent applicants. If you are a building practitioner (designer, builder, the requirements of the New Zealand Building Code. developer, engineer, architect) and you are planning Building work carried out in accordance with the a building consent application for a residential approved plans and specifications will meet building, such as a new dwelling, or completing an minimum performance standards. You and your application on behalf of the owner, this guide is for you. designer may, of course, aim for higher standards. This guide will help consent applicants prepare The basic requirements for a building consent and plans, specifications and documentation for a for meeting the performance standards under the building consent application by explaining the Building Code are generally the same around New minimum information requirements. Zealand. However, different building consent authorities may process applications differently. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 1
Introduction Section 45 of the Building Act 2004 (the Building Although these requirements are not related to Good planning and proper preparation of consent Act) sets out in broad terms how to apply for a the Building Code or Building Act, it is useful documentation provides a solid foundation for building consent, but does not detail all the to ask the BCA about any specific requirements they everyone involved in the building process to make information needed to support an application. have before lodging a building consent application. well-informed, efficient and cost-effective decisions. A complete and accurate consent application should This guide recommends the appropriate form and This guide focuses on information a building consent help speed up consent processing and approval minimum content (including its quality) for a building authority needs to assess compliance with the time. It should also provide an accurate historical consent application. This includes the drawings, Building Code. However, information on tendering, record that can be used later when further building specifications and other documents (eg, engineering contractual issues, project management and work, alteration, repair or maintenance is needed, calculations and design reports). The guide discusses construction processes, and on those parts of or the property is sold to a new owner. associated issues, such as the role of manufacturers’ a building project not relating directly to Building technical data, alternative design, engineering and Code compliance, can be included as well. Having Complete, accurate and good quality consent design calculations, product appraisals, and other a single set of documents suitable both for consent documentation helps everyone involved in a building technical statements, warranties or opinions. and for construction allows everyone to work off project play their part in ensuring the work is carried a ‘buildable design’ set of documentation. out and built right, first time. This can help avoid Some building consent authorities have specific costly time delays and rework. requirements for building consent documentation, The documentation even for a simple new building including: project passes through many hands, including It is important to understand that building consent designers, builders, plumbers, drainlayers, home- authorities verify compliance with the Building • the specific size, form and scale of drawings owners or developers and, within the building Code. They do not design or correct insufficient and their elements consent authority, their administration, consent consent documentation. They do not ensure quality • requirements for certain line types or processing, inspection, engineering and town and aesthetic requirements are met, unless thicknesses, and/or fonts. planning staff. compliance with the Building Code is affected. Often these requirements arise from the building consent authority’s process for storing and retrieving building consent information (eg, digital storage). 2 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
1.0 The building consent process A building project starts during the planning and The project information memorandum (PIM) is a A PIM also provides information about legislative design stage, not on site after a building consent very useful tool for this, particularly if obtained early or regulatory requirements, including other has been issued and construction begins. It ends in the design phase of a significant project such as authorisations that could be relevant to the proposed when the building work is completed and the a new residential dwelling, as it can help you identify building work such as a resource consent required building consent authority issues a code other compliance requirements, and so avoid costly under the Resource Management Act 1991, or compliance certificate (CCC). delays during the consent process. whether the territorial authority needs to notify the New Zealand Historic Places Trust. It is important to know about and plan for these as early as 1.1 PRE-LODGEMENT OF BUILDING 1.2 PROJECT INFORMATION MEMORANDUM possible in the design process. CONSENT APPLICATION (PIM) Understanding potential site issues and designing Early consultation with the building consent An owner, or their agent on their behalf, may apply to accommodate them can also help speed up the authority helps reduce misunderstandings at the for a PIM if they are considering carrying out building consent process. The building consent time of consent application and processing, and building work. review process is then likely to face fewer helps ensure the application is as complete as A territorial authority (your local city or district requirements for further information, and so can possible prior to lodgement. Specific documentation council) issues a PIM. be processed more quickly and cost effectively. requirements of the building consent authority can be taken into account at the planning stage. A PIM provides information about the land on which As at 31 January 2010, you can choose whether you plan to carry out building work and any other or not to apply for a PIM when considering carrying Compliance with other requirements (eg, council land likely to affect or be affected by the building out building work that requires a building consent. bylaws or district planning rules) may be critical to work. This information might include special features the design of the project, even though not part of For significant projects, such as a new residential such as natural hazards (eg, erosion, subsidence, the building consent process. Therefore, you should dwelling, it is highly recommended to obtain a PIM falling debris, inundation or slippage), corrosion consider these requirements early in your project early on in the design phase and well in advance issues, high wind zones, or the likely presence of management and preliminary design work. of applying for a building consent. hazardous contaminants. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 3
Pim content PIM application Your PIM application should include enough information to help the territorial authority determine Section 35 of the Building Act provides for the content The territorial authority provides the application form if there are any associated planning issues under of a PIM, which will include information about: (you should be able to download one from your local the Resource Management Act. For example, council’s website). Information required includes • any heritage status of the building you should include information such as land contours applicant details, the location of the building project, • whether the territorial authority considers that and drawings showing the sunlight access plane and a description of the building project outlining: notification to the New Zealand Historic Places height in relation to boundary lines. Trust is likely to be required • any change of building use You should include preliminary design plans with • any special feature of the land • the intended life of the building the PIM application, but do not need to include • relevant information that another statutory • previous consents the comprehensive, technically detailed drawings authority has notified to the territorial authority in • the estimated value of building work and specifications required for building consent terms of any other Act • matters involved in the proposed project, applications. Normally, a good site plan, floor plan • details of stormwater or wastewater utility for example: and elevation drawings are sufficient. You must pay systems/services that relate to the proposed – subdivision the fees set by the territorial authority when you building work – land contour alteration apply for the PIM. • details of any authorisations required by the – new/altered public utility connections territorial authority or on behalf of a network The territorial authority must issue the PIM within – changes to building locations or dimensions utility operator, including any conditions 20 working days of receiving your application. – changes to vehicle access • whether the territorial authority considers a fire However, they can suspend this period if they – work over or adjacent to roads or public places evacuation scheme is required require further information from you about any – disposal of stormwater or wastewater • whether section 75 of the Building Act applies authorisations or requirements (eg, intended use, – building work over drains or sewers, or near (construction of a building on two or more location and dimensions, vehicle access and roading, wells or water mains allotments). stormwater and wastewater disposal, proximity to – any other matters that may require territorial drains, or proposed connections to public utilities). authority authorisation. For more information on PIMs, visit www.dbh.govt. nz/project-information-memoranda 4 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
1.3 Lodging a building consent PIM application. 1.4 PROCESSING A BUILDING CONSENT application APPLICATION The description of the proposed work should be When applying for a building consent, you will clear and precise. For example: The building consent authority checks that the need to complete an application form. The building documents you submit show the building work • ‘Addition of lounge, kitchen alterations and new consent authority will provide you with one. You would comply with the Building Code, if properly conservatory’ rather than ‘Additions and might also be able to download one from their completed in accordance with the plans and alterations’ website. Your building consent application must: specifications included. See section 49(1) of the • ‘New 100 m2 dwelling with two-car garaging, Building Act. • be in the prescribed form associated earthworks, retaining walls and • include plans and specifications swimming pool’, rather than ‘New dwelling.’ You will help the assessment process greatly if • include any other information the building you ensure your building consent documentation: consent authority reasonably requires Rules covering restricted building work are expected • includes a clear summary or report, such as a • include the applicable building consent to start in March 2012. design summary (see section 3.0) explaining lodgement fee. A building consent application for restricted building how compliance with each relevant clause of work will need to include the names of the licensed Information required on the application form includes building practitioners carrying out or supervising that the Building Code will be achieved, including a brief description of how your project will comply work. See section 45(1)(e) of the Building Act and 7.6 any waiver or modification sought with the Building Code. Including a design summary of this document. Also refer to www.dbh.govt.nz/lbp • differentiates between items relating to Building will help explain your choice of a particular means As part of good practice, applicants are encouraged Code requirements and those relating to to start providing details of practitioners involved in of compliance. See section 3.0 of this document the project now. contractual matters (eg, conditions of contract, for more information. tender documents, dispute resolution) • includes a schedule or schedules of the You can find much of the property information materials, products and systems (and their you need from a rates demand, lease agreement, maintenance requirements) to be used in the certificate of title held by Land Information constructing the building New Zealand, or from local council property • provides the details (including licence numbers) archives. Charges may apply if you seek information of which practitioners have been engaged to from local council records separately or in your carry out building work. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 5
The processing of the building consent may 1.6 GRANT OR REFUSAL OF BUILDING 1.8 AMENDMENTS TO BUILDING CONSENTS be suspended if the building consent authority CONSENT If you wish to formally amend an approved building requires clarification or further additional information. Once the building consent authority is satisfied that consent, which must be done when considering See section 1.5 below. Building Code compliance is verified, and you have significant changes to the work previously If you change your design during the processing paid all associated fees and levies, the building approved, your application must be made in the stage, you must inform the building consent authority consent authority must grant the building consent. prescribed form provided by your building consent of the proposed changes. This will allow them authority, and should include details of what was The building consent authority may refuse or decline to assess Building Code compliance, and update originally approved, and how it will change. to approve your application if the consent the consent file and council records. For more Your application must also demonstrate that the documentation does not adequately demonstrate information refer to section 1.8. new proposal complies with the Building Code compliance with the Building Code. The building and will not affect the Building Code compliance consent authority has 20 working days in which to of other work. 1.5 REQUESTING FURTHER INFORMATION refuse or approve a building consent application. All amendments to a building project that relate to The building consent authority may request the Building Code must be notified to the building clarification or seek further information about your 1.7 ISSUING A BUILDING CONSENT consent authority so they can approve and record consent application within 20 working days from the The building consent is issued in the prescribed them. Your application for amendments must be date they receive the application. The 20 working form and may have the following attachments: made and approved before the change takes place. day period will then be suspended until they receive this information, in full. • a PIM (if applied for) Note: Building consent authorities have 20 working • a development contribution notice issued days in which to refuse or approve formal amendments by a territorial authority under section 36 to building consents. of the Building Act (if any) • a certificate providing information on resource consent requirements (if any). 6 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
Minor variations to building consents Note: To avoid doubt, a minor variation does not 1.9 INSPECTION OF CONSENTED include any building work in respect of which BUILDING WORK A minor variation is a minor modification, addition compliance with the Building Code is not required or change to consented building work that does not The approved building consent will inform you of by the Building Act. For example, changing water deviate significantly from the approved plans and any inspections the building consent authority needs taps from chrome to gold plated is not considered specifications to which the building consent relates. to undertake during construction, based on their a minor variation as the tap finish does not need evaluation of the plans, specifications and other Section 45A of the Building Act enables a building to comply with the Building Code. These types information. These may include inspections by your consent authority to grant a minor variation prior to of changes can just happen during construction nominated engineer. Inspections allow the building or during construction without having to go through as of right. See section 9.0 Glossary of terms for consent authority to be satisfied on reasonable the formal process of issuing an amendment to the more information. grounds that the building work complies with the building consent. However, the building consent If the building consent authority does not record building consent and Building Code. Building authority must record the granting of the minor or approve the changes, they could issue a notice consent authorities do not verify the quality of the variation in writing. to fix for the amendment, and may also refuse to issue building work beyond checking it complies with the Minor variations only apply to issued building the CCC upon completion of the work because they Building Code. Issues such as aesthetics and quality consents, where the code compliance certificate cannot establish compliance with the building consent. of workmanship fall outside the building consent (CCC) has not been issued. In addition, minor authority’s jurisdiction. Defining a change on site during construction as variations must neither adversely affect compliance a minor variation is at the building consent authority’s Building consent authority inspection requirements with the Building Code nor the granting of a CCC. discretion. Building consent authorities determine will vary with the size and complexity of each project. what are minor variations and what are formal amendments to the consent. Practitioners are encouraged to engage early and have a conversation with building consent authority staff as soon as possible to clarify these issues as they arise. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 7
Common inspections by building consent authorities Make sure you understand what inspections are Note: Building consent authorities may refuse for residential dwellings can include: needed and when. Talk with the building consent to undertake an inspection if a copy of the approved authority to discuss the sequence of inspections. building consent documentation is not on site • pre-pour (before concrete is poured, for example, Missed inspections may prevent the building consent during the inspection. These should always be for piles, footings, slabs, in situ walls or authority from being able to establish compliance on site anyway to be used as the ‘building plans’ blockwork infill) with the building consent, and therefore prevent by practitioners. • tanking/waterproofing (before back-filling them from issuing the CCC. This can have significant retaining walls, covering membranes on decks or consequences for the owner and contractors. laying tiles in wet areas such as showers) • pre-clad (before wrapping the building in building You must request inspections once the building paper or building wrap and installing the cladding) work specified in an inspection list is ready. • post-clad (before applying coatings to fibre Provide information about the type of inspection cement or polystyrene systems, possibly required, a contact name, phone number, building including inspections during plastering) consent number, and a clear project address. If the • pre-line (with insulation installed but before property is isolated or hard to find, give directions. installing internal linings. This inspection may include checking the plumbing installation under When booking an inspection, try to give the building pressure test) consent authority as much notice as possible. • drainage (before filling in trenches and covering Many building consent authorities can take the in-ground pipework). Pipework should be inspection bookings for the next day. under test for this inspection. Drainage testing When on site, a building inspector will need copies can include smoke, air or water testing of the approved building consent documentation and • final inspection for plumbing, building and other approvals and relevant information. Ensure the drainage work (once the work described in the site is clean, tidy and safe, and that someone with building consent is complete). adequate knowledge of the project is on site to answer any questions. This is usually the relevant contractor who is undertaking the building work. 8 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
1.10 CODE COMPLIANCE CERTIFICATE (CCC) Even if the owner has not applied for a CCC, the building consent authority must decide whether An application for a CCC must be complete, precise to issue a CCC within two years of granting building and an accurate record of what was actually built consent or any further period agreed between the on the site. A building consent authority will owner and the building consent authority. If the normally require: building consent authority is not satisfied that • energy work certificates for any electrical compliance with the consented documents has or gas work carried out been achieved, they must refuse to issue the CCC. • an as-built services plan (eg, plumbing and The BCA must provide the reason for the refusal drainage) to the owner in writing. However, we recommend • roof truss installation certificate and plan that building consent authorities give applicants the • other installation certificates (eg, cladding, opportunity to resolve any non-compliance issues waterproofing, tanking) first. The building consent authority’s refusal to issue • producer statements (eg, from a Chartered a CCC does not prevent an applicant from applying Professional Engineer for some specific for one at a later stage after addressing issues design or construction elements). of non-compliance. The owner must apply for a CCC as soon as practicable after the building work described in the Sale by a residential property developer building consent, with any subsequent approved Under section 364 of the Building Act, residential property amendments, has been completed. See section 92 developers (anyone building, or arranging to have built, of the Building Act. a household unit for the purpose of selling it) must get a CCC before completing the sale, or allowing a purchaser The building consent authority must issue a CCC to take possession of the household unit. An exception applies when the property developer and buyer sign Form when it is satisfied that the building work complies 1 of the Building (Forms) Regulations 2004 (Agreement with the approved building consent. They have between residential property developer and purchaser). 20 working days from receipt of the application to do this. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 9
2.0 Plans and specifications 2.1 INTRODUCTION References to Standards and Compliance Documents should be specific. Some Standards are cited (in Compliance Documents and Acceptable Solutions Plans and specifications show how you intend to whole or in part) in the Acceptable Solutions, while The Building Code is performance-based, and so requires construct, alter, demolish or remove a building. a certain level of performance to be achieved in buildings. other Standards offer advice only. Some Standards Most building consent authorities provide guidance contain several options. Unlike prescriptive bylaws that existed before the Building Act 1991, the Building Code allows more than one way on any additional documentation they require with to achieve performance. The Acceptable Solutions in the References to other industry guides, such as a building consent application (eg, check sheets). Compliance Documents show you one way of complying BRANZ publications, should also be specific. with the Building Code. A building consent authority must The Building Act provides for ‘other documents’, accept plans that are based on a Compliance Document References need to: as demonstrating compliance with the clause(s) of the along with plans and specifications. These include: Building Code to which that Compliance Document relates. • uniquely identify documents with titles and dates • design calculations (eg, for some specifically Compliance Documents automatically comply with • be specific about the paragraphs/clauses/ engineered design element) the Building Code. Designers can provide an alternative sections to be followed. solution, as long as they demonstrate to the BCA that • manufacturers’ data the proposal will comply with the Building Code. • technical opinions or appraisals Note: The Government is looking to change the term For more information, visit www.dbh.govt.nz/blc- • codes of practice. ‘Compliance Documents’ as part of the Review of compliance-documents and read the following the Building Act 2004. The proposed new terms are Department guidance on alternative solutions at: www. See section 6.0 for more information. dbh.govt.nz/UserFiles/File/Publications/Building/ ‘Acceptable Solutions’ and ‘Verification Methods’. Guidance-information/pdf/alternative-solutions.pdf 2.2 BUILDING CONSENT INFORMATION Information in the plans and specifications should be project-specific. General phrases, such as ‘refer to manufacturer’s specification and/or requirements’ or ‘installed in accordance with best trade practice’ are insufficient. Manufacturers’ specifications can change, and views on ‘best trade practice’ vary between practitioners. 10 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
2.3 DRAWINGS 2.5 DIMENSIONS 2.7 SPECIFICATION CONTENT All drawings should contain a drawing number and AS/NZS 1100.301 sets out conventions for dimensions Keep tender, contract and project management title, the designer’s and owner’s name and the job on drawings. Where a finished dimension is critical matters separate from technical matters, and from address, and be dated for version control. Drawing for compliance or construction, identify it clearly in the proposed product and material selections. You conventions (line types and widths, lettering type the relevant drawing or specification. Timber size can describe product and material selections in each and size, symbols for building features and elements, should be identified by its actual finished size. work section, grouped together in a single schedule, designation of spaces, representation of materials or list them on the drawings. A mix of trade-based, and cross-referencing conventions) should generally material-based, process-based and element-based 2.6 SPECIFICATION STRUCTURE conform to AS/NZS 1100 Technical Drawing. sections or chapters is acceptable. Hand-drawn or CAD (computer-aided design) A good project-specific specification has a logical Specifications must be project-specific and drawings are acceptable. structure and navigation. The default standard not include unrelated generic information. classification system for New Zealand is Coordinated Drawing sizes vary, usually ranging from A0 to A4. Generic specifications with irrelevant information Building Information (CBI), recognised by the four- The size of drawing sheets should be consistent will prove frustrating for building consent authorities digit numbers used to classify each work section within a single set of project drawings. Sometimes and practitioners and can cause delays to consent (ie, chapter) of the specification. There should be drawings or diagrams of components and construction processing. ‘Preliminaries’ and ‘General’ sections, followed details are provided in A4 and bound in with specification by a series of technical work sections. Each work Specifications have typically been based on proprietary data (eg, a specific engineering construction detail). section or chapter should be laid out in a consistent model documents, or assembled by individual pattern (such as ‘General’, ‘Products’, ‘Execution’, designers in a modified trade-based format. 2.4 DRAWING RANGE ‘Selections’), and a consistent clause numbering Specification sections have a long history of subdivision system should be used. by trade (traditional and influenced by NZS 4202: The size and complexity of the project determines 1995 Standard Method of Measurement of Building the detail needed, and extent of associated Works or work sections (CBI based)). structural and building services-related documents. See section 6.0 for information on the form and content of drawings. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 11
2.8 SPECIFICATIONS AND DRAWINGS Electronic document lodging Your specification should complement the drawings, Many designers produce, deliver, store and retrieve and not contain erroneous information or contradict documents electronically. Some BCAs can also receive, itself or associated documents. Information on drawings process and store documents electronically. If you have suitable technology, you should ask the BCA if your need not be repeated in the specification and vice application can be lodged electronically. This can reduce versa. Repeating information can lead to contradiction the cost and inconvenience of producing and exchanging hard copy information, and prevent problems with accessing and confusion, but may be useful for key points. and interpreting hard copy or scanned documents. Using electronic material only will also help reduce the impact on You can decide how information is presented and the environment by cutting down on the amount of paper where it is located, but building consent authorities being produced. are entitled to ask for reasonable information in relation to a building consent. Consider whether information, for example project selections (eg, sanitary fittings or door hardware), is best placed on the drawings alongside details of cabinetwork, kitchen or bathroom fixtures, or in the specifications. You can also include drawings in a specification, such as standard details of a catch pit, or gully trap, a series of standard reinforcing details, or items for off-site fabrication. Including the specification data on the drawings will help the BCA and contractors on minor projects. Wherever you provide specifications and drawings in the documentation, they should be clear, correct and complete. 12 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
3.0 Design summary During the design process for any building project, • provide a useful checklist for the building consent 3.1 COMPLIANCE WITH BUILDING CODE designers make decisions on how compliance with authority to consider Building Code compliance CLAUSES the Building Code will be achieved. A design summary after the project is complete Make sure all relevant clauses of the Building Code is a tabulated list of how you propose to comply • help reduce the consent processing time and are correctly identified and considered during the with each of the relevant Building Code clauses. avoid costly delays. design process. The clauses need to be identified Design summaries are extremely helpful in explaining How extensive the plans, specifications and related on the building consent application form. If you use to the building consent authority the particular information are depends on the complexity and size a design summary, which you are encouraged to do, choices that were made to achieve compliance of the project, and how closely the design conforms you could reference the relevant clauses of the and why. A design summary, while not mandatory, with Acceptable Solutions or Verification Methods Building Code. has several benefits and is becoming industry under the Building Code. best practice. The relevant Building Code clauses for residential See section 4.0 for an example of a completed buildings are described below. However, always A design summary can: design summary. consult the Building Code to check that the relevant • help the designer (during the design phase) and performance criteria have been met. the building consent authority (during the building How much information is needed? See www.dbh.govt.nz/bcr-about-the-building-code consent processing phase) by providing a The purpose of building consent documentation is to for more information. checklist on how compliance with the Building demonstrate, to the satisfaction of the building consent Code is achieved authority, that all relevant performance requirements of the Building Code are met. In some cases, you will need • confirm which parts of the project are compliance- to describe how Building Code compliance is achieved for related (or only construction- or contract-related) individual building elements where the element must comply with a variety of Building Code clauses (eg, a • provide references to location of design boundary wall that is fire-rated, provides bracing, has documentation and details sound-control properties and is located in a wet area). • provide a checklist during construction, clarifying which changes will require a variation, amendment or a new building consent GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 13
BUILDING CODE CLAUSES E3 Internal Moisture – confirming that surfaces G1 Personal Hygiene – providing sufficient sanitary in wet areas are durable enough, easily cleaned fixtures (toilets, showers and basins) for cleanliness. B1 Structure – demonstrating how the building and designed to resist moisture, and that ventilation withstands likely loads, including wind, earthquake, G2 Laundering – providing sufficient laundry facilities. and the space temperature are sufficient to avoid live and dead loads (people and building contents). G3 Food Preparation and Prevention of the excessive build-up of moisture. B2 Durability – confirming the use of materials Contamination – providing sufficient safe and F1 Hazardous Agents on Site – identifying that will remain functional for the minimum periods hygienic facilities for food storage and preparation. and neutralising any hazardous agents or other specified (five, 15 or 50 years). G4 Ventilation – confirming required natural or contamination of the building site. C1–C4 Fire Safety – addressing outbreak of fire, forced ventilation to all occupied spaces. F2 Hazardous Building Materials – confirming demonstrating means of escape and boundary G7 Natural Light – confirming that sufficient natural the appropriate selection of glass and glazing separations. light is provided to occupied spaces and providing methods to ensure the safety of building users. D1 Access Routes – the safety of entry/exit to the F2 also considers building materials that give off appropriate visual awareness for the occupants. building and the safety of any internal or external noxious fumes. G9 Electricity – confirming the safe distribution stairs and slip resistance. and use of electricity. F4 Safety from Falling – confirming the safe design E1 Surface Water – the method of disposal of, of all barriers (including handrails and balustrades) G10 Piped Services – confirming the safe for example, rainwater from external surfaces, inside and outside the building (includes the design distribution of gas. and confirmation that surface water cannot enter of swimming pool fences under the Fencing of the building. G11 Gas as an Energy Source – confirming the Swimming Pools Act 1987). safe installation of gas-powered appliances. E2 External Moisture – confirming that the design F5 Construction and Demolition Hazards – and detailing of all external roof and wall claddings G12 Water Supplies – confirming the safe supply confirming protection of people and other property and external openings will prevent external moisture (avoidance of scalding and backflow), storage, during construction or demolition. from causing undue dampness or damage. reticulation and, where needed, heating of F7 Warning Systems – confirming provision of early potable water. warning systems to alert people to an emergency. 14 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
G13 Foul Water – confirming the safe and sanitary The drawings and construction details must be An applicant needs to provide a good reason collection and disposal of foul water and the specific to the project. You should clearly identify and justification as to why an authority should prevention of foul air from entering the building. in the specification the particular materials and/or waive a particular code clause in a given situation. systems you intend to use. Do not include information H1 Energy Efficiency – confirming the provision For more information on waivers and modifications on building products, methods or construction of a warm, dry interior environment through see www.dbh.govt.nz/UserFiles/File/ details not relevant to the particular design. insulation and controlling air movement, and the Publications/Building/BCA/BCA-Update- efficient use of energy. If an element of the design does not comply with April-2010.pdf a particular Acceptable Solution or Verification Manufacturer’s information Method, you need to demonstrate how that particular 3.2 GENERAL COMPLIANCE ISSUES element or part element complies with the Building Manufacturers should, as good practice, ensure their Simply stating that a project complies with the Code using other means of compliance, such as an information is dated and includes relevant technical Building Code or a particular Standard cited in an alternative solution. Your plans and specifications data. Some materials and products contain mixed Acceptable Solution is insufficient. You need to need to clearly demonstrate compliance. technical and marketing/promotional information. show how the building work will comply. For example, (Refer to AS/NZS 1388 Guidelines for Technical Where a building product or system is not necessary for a residential building the performance requirements Information for Building and Construction Products.) to achieve compliance with the Building Code, you of Building Code Clauses B1 (Structure) and B2 may be able to describe it generically, for example, The Acceptable Solutions and Verification Methods (Durability) can be achieved by demonstrating built-in shelving, storage units or kitchen and under the Building Code do not refer to specific compliance with NZS 3604: Timber Framed Buildings bathroom joinery carcasses. branded products or systems. However, you can and NZS 3602: Timber and Wood Based Products propose brand-specific products and systems to for use in Building, referenced in the Acceptable For more information visit www.dbh.govt.nz/ demonstrate compliance with the Building Code. Solutions B1/AS1 and B2/AS1. Because Standards UserFiles/File/Publications/Building/Guidance- Once the building consent has been issued, the provide several different options, you should always information/pdf/alternative-solutions.pdf building consent authority must approve any changes reference the relevant sections, clauses, figures and Waivers and modifications to the specific products or systems named in the tables within the particular Standard that you are application (where these affect Building Code applying to make it clear which particular solution is A territorial authority may waive or modify compliance). The building consent authority being proposed. Referencing Building Code clauses certain aspects of the Building Code when may treat these changes as minor variations. and Standards only is insufficient. granting a building consent, if requested. See section 1.8. GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 15
4.0 Design summary check sheet An example of a completed design summary follows. It is a useful guide to completing a consent application. DESIGN SUMMARY CHECK SHEET BCA use Project description: New single level 3 bedroom house with study and attached double garage. T imber framed construction on concrete E VODEZLWKßEUHFHPHQWZHDWKHUERDUGVRQDFDYLW\DQGORQJUXQFRUUXJDWHGURRI L Project information: Owner’s or agent’s name: Joe Public P Contact details: Ph 021 969 696 Designer’s name(s): Cool Design Ltd, Greendale AM Contact details: Ph 021 007 007 Site address: 71 Magellan Road, Greendale X Site legal description: Lot 10, DP 100902 E *RRGJURXQG UHIHU1=6FODXVH DQGFRQßUPHGE\VXEGLYLVLRQ Site data: Ground bearing geotechnical report ref # 010124. ED Exposure/corrosion zone Zone 1 (512m from coast by GIS ie 12m outside sea spray zone)) K Wind zone High, derived from NZS 3604, section 5. R Earthquake zone $ 1=6ßJXUH O Climate zone 2 (NZS 4218:2004) W Building data: Building category IV/Domestic (NZS 3604, table 1.1) Floor live loads 1.5 kPa (NZS 3604, table 1.2) Overall height of building 3850mm (NZS 3604) 16 GU I D E TO A P PLY I N G F O R A BU I L D I N G C O N S E N T ( R ES I D E N T I A L BU I L D I N G S ) – S EC O N D E D I T I O N
BCA USE KEY ASPECT/ BUILDING IDENTIF Y NOMINATED LOCATION OF DETAILS COMMENTS COMPON ENT MEANS OF COMPLIANC E IN CONSENT APPLICATION Foundation Concrete slab as per NZS 3604: 1999, Foundation plan (Sheet A03) Also refer to note 1 on Sheet A20 F ig. 7.13 (B) and F ig. 7.16 (B) Details 01, 01A, 02 on Sheet A09 and notes 2, 3 Sheet A20 Wall framing NZS 3604:1999, 90x45 MSG8 treated Notes 9, 12 Sheet A20 E to H1.2, lintels to table 8.9, cast-in- EROWERWWRPSODWHß[LQJV Roof framing NZS 3604:1999, Table 10.2 and SE D trusses PL Roof plan (Sheet A06) Trusses generally/rafters to raked ceiling of lounge only M Roofing E2/AS1, Table 11 Roof plan (Sheet A06) Longrun corrugated galvanised metal sheet(note 24, Sheet A20) A EX Cladding E2/AS1, clause 9.5 Sheet A16-18 F ibre cement, weatherboard on Risk matrix, Sheet A19 a cavity – see notes 10, 10a on Sheet A20 D Bracing NZS 3604:1999 Bracing plan, Sheet A05, A08 See separate bracing calculation sheet E Insulation Roof: H1/AS1, Table 2 (a) Sections A, B Sheet A09 Foundation: 1200W perimeter K Walls: H1/AS1, Table 2 (a) insulation of 40 thick poly = R value > 1.3 (schedule method) R Roof: R 3.2 (wool), see note 19, Sheet A20 O Walls: R 2.2 (wool), Schedule method – see note 20, Sheet A20 Internal linings W E3/AS1, clause 3.1 Sheet A19 Walls: Plasterboard – see notes 9, 12 on Sheet A20 Floors: Vinyl to wet areas, carpet elsewhere GU I D E TO A P PLY I N G F O R A BU I L D I N G C O N S E N T ( R ES I D E N T I A L BU I L D I N G S ) – S EC O N D E D I T I O N 17
BCA USE KEY ASPECT/ BUILDING IDENTIF Y NOMINATED LOCATION OF DETAILS COMMENTS COMPON ENT MEANS OF COMPLIANC E IN CONSENT APPLICATION E Bathrooms G1/AS1, Table 1 See bathroom plan, Sheet A08 Bathroom and separate ensuite L Acrylic shower unit, waste water to gully trap, ventilation via opening P window. M Plumbing Electric mains HWC as per 'UDLQDJHOD\RXW$VSHFLßFDWLRQ NZS 4606 p.25 A Water supply as per AS/NZ 3500.2 X Drainage AS/NZ 3500.2 Refer to site plan A02 Foul water to council main, storm E water to kerb and channel, wc to drain D Laundry G2/AS1, clause 1 Sheet A03 Tub and washing machine in garage E Table 1 K Kitchen G3/AS1, clause 1 6KHHW$DQGVSHFLßFDWLRQS Electric oven, range hood, stainless steel bench, fridge/freezer, R dishwasher O Smoke alarms F7/AS1, clause 3.1 Electrical Plan, Sheet A07 1 in hallway, 1 in lounge W Natural light G7/AS1, clause 1.0 1DWXUDOOLJKWYLDJOD]LQJ!àRRU area (see door/window schedule) Heating G9/AS1 Electrical Plan, Sheet A07 Heat pump Access D1/AS1, Table 6 Door/window schedule A09 Front entrance steps as per main private stairway Note: If someone else besides the building consent authority (eg, a chartered professional engineer) needs to inspect any aspect of work, note it in the relevant comment section. 18 GU I D E TO A P PLY I N G F O R A BU I L D I N G C O N S E N T ( R ES I D E N T I A L BU I L D I N G S ) – S EC O N D E D I T I O N
5.0 Drawings This section gives examples and brief explanations Guidance is provided on the quality, content, of consent drawings. Please note these are form and type of information each drawing should examples only. include. The descriptions are not exhaustive but are typical of the information that should be shown. • Site plan • Location plan • Foundation plan Some of the recommended information is unrelated to the Building Code but will help the building consent authority • Floor plan determine whether the work complies or needs approval • Roof framing plan under other legislation, such as local bylaws or district plan • Exterior elevation requirements under the Resource Management Act. Such additional information, as well as Building Code related • Sections information, is shown in text boxes like this. • Construction details • Door/window schedule • Plumbing layout/schematic plan • Electrical plan • Wet area details GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 19
5.1 Site plan The purpose of a site plan is to show the location of the proposed building work on the site in relation to adjoining properties. Additional information When preparing the plan, check with the building consent authority and network utility operators for information on Dr awing t ype Recommended scale Minimum recommended detail ( Note 2 ) the location of existing services both to and across the site. ( Note 1) Including calculations for site coverage on the site plan will help the territorial authority determine compliance Site plan 1:200 (Note 4) Legal description, legal boundaries and easements with district plan requirements. (Note 3) North point Building location, including dimensions in metres to boundaries, and boundary fire ratings Table notes Spot levels or contours and site datum Note 1 Drawings may be combined. Location of existing and new services (water, power, gas, Note 2 Requirements may differ where the building project is an stormwater, foul water) and method of disposal/discharge alteration or addition to an existing building. Connection between services and network utility operators’ Note 3 For rural and/or larger sites a 1:500 (or 1:1000) location plan systems may be needed to confirm the site location. This is especially relevant where the distance to boundaries cannot be shown Proposed/actual driveway, site finishes (hard and soft) with levels on the site plan due to the size of the property. and falls Note 4 A scale of 1:500 or 1:100 may be adequate. Excavation details (cut and fill) and retaining walls Existing buildings and site features Identify known natural hazards Identify vehicle crossings 20 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
CONTRACTOR SHALL VERIFY ALL DIMENSIONS ON SITE. REVISIONS Site plan – sample only 6,310 4,433 580 6,200 2,600 580 1,230 600 8,370 3,295 CLIENT 6,310 5,013 11,210 8,370 3,295 CONTRACTOR 10 NOTE: Block boundary wall to Garage is 20mm off boundary .0 Boundary 34,198 9. K 9. 00 86 98 10 10 10 D 6 7 10 dp at .7 .7 .8 In 20 .5 um 48 21 06 65 Timber retaining wall 125x125 posts H4 treated and CONSULTANTS 200x50 retaining wall H4 treated Post hole to be at depth equal to dp gt vent gt dp height of retainng wall. 10 Proposed Garage .1 50 Finished slab level Fall seal 50mm 10 .6 10300 6,170 24 dp 15.00° DW PROPOSED NEW DWELLING First ABC STREET show floor ab City field empty n ha ove tche d 10 0 Area to be sealed 6,13 Locally ramp seal to garage door .7 Prop refer to floorplan 41 Finis osed H finished seal level 1070 hed sla ouse at perimeter 10200 SITE PLAN 2,280 0 b lev el dp ABC STREET Construct sump 200 Type 1 as E1/AS sump surface finished level 10150 Area to be excavated to gt a depth of approximately Note: Excavate locally around the 3,092 10050 shown shaded. 0 road crossing perimeter of the house to Form new 4m 2,80 Refer to floor plans for 225mm below finished slab level area to be battered back to ground level. Pt RS 206 1,60 0 CT386/187 dp dp 100 200 10 10 dia sewe Boundary 14,886 .7 .7 4,78 SIte Area 506m2 0 r sta Existing sewer lateral 76 04 ck go 100 dia sewer Ground floor Area 135.5m2 es up to be reused Boundary 14,886 wall 9 Accessory Building Area 52m2 and 1,95 3,27 vents Timber retaining wall SCALE 1:100 Area Ground Floor 187.5m2 0 throu 125x125 posts H4 treated and 3,325 gh ro Area First Floor 100m2 of 200x50 retaining wall H4 treated DATE 02 February 06 170 17,20 Post hole to be at a depth equal Total Area of Building 287.50m2 5 4,74 to height of retaining wall 0 JOB No. 0712 10 10 Site Coverage 26.8% 10 No 51 .8 .7 .8 10 9. DRAWN .5 CH 12 94 55 95 .0 63 390 84 9 1,91 Boundary 34,198 0 In CHECKED K KR 525 STATUS CONSENT 6,310 14,267 2,903 827 6,596 3,295 DRAWING No. REVISION SITE PLAN Note: existing ground levels shown thus A01 A 10 .7 Scale 1:100 48 © THE DESIGNS CONTAINED ON THIS SHEET OF DRAWINGS ARE COPYRIGHT GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N 21
5.2 Location plan A location plan is a high-level ‘bird’s eye view’ of the area surrounding the proposed building work. It shows the location of the proposed work in relation to adjoining streets or properties. These plans are particularly Additional information Where the property is located in a flood zone, confirm useful in rural or remote locations, or multi-unit residential complexes. the relationship between the site datum and the minimum occupied floor level set by the territorial authority in the Dr awing t ype Recommended Scale Minimum Recommended detail ( Note 2 ) district plan. ( Note 1) The distance to relevant boundaries can be added to the location plan, where this cannot be shown on the site Location plan 1:500 (Note 3) Legal description, legal boundaries and easements plan, due to the size of the property. North point Existing buildings and site features Table notes Identify known natural hazards Note 1 Drawings may be combined. Identify vehicle crossings Note 2 Requirements may differ where the building project is an alteration or addition to an existing building. Note 3 For rural and/or larger sites, a scale of 1:1000 or smaller may be needed to confirm the site location. 22 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N
Location plan – sample only XX XX IVE DR IV Y DR E YYY CLIENT CONTRACTOR CONSULTANTS PROPOSED NEW DWELLING ABC STREET setout position to be confirmed by designer and owner prior to excavation of founds. N 35,000 Lot XX DP YYY Area approx: 1.1125ha Total Building (inc verandahs): 404m2 Total site coverage: 3.63% M A E 57,000 R T SITE PLAN S SITE LOCATION PLAN 1 L 10,300 SCALE DATE 01 May 2010 JOB No. 07123 DRAWN CHECKED STATUS Construction Location Plan 1:1000 DRAWING No. REVISION A01 A GU I D E TO A P PLY I N G F O R A BU I L D I N G C O N S E N T ( R ES I D E N T I A L BU I L D I N G S ) – S EC O N D E D I T I O N 23
5.3 Foundation plan The foundation plan illustrates to the building consent authority and your building practitioners the foundation design you propose, and details its specific dimensions and construction requirements. Additional information Where the property is located in a flood zone, confirm Dr awing t ype Recommended scale Minimum recommended detail ( Note 2 ) the relationship between the site datum and the minimum ( Note 1) occupied floor level set by the territorial authority in the district plan. Foundation plan 1:100 (Note 3) Concrete slab dimensions and thickenings (where applicable) If a registered engineer has designed the foundations, Concrete slab reinforcing details and construction joints provide supporting information, including calculations, Foundation walls design assumptions (eg, soil bearing) and possibly a producer statement for design. Identify details of Pile layout with dimensions, pile type bearer sizes (including decks inspections and tests to be carried out by the design and pergolas) engineer on the building consent application form Finished floor heights in relation to site datum under the heading ‘Proposed owner inspections’. Sub-floor bracing layout Sub-floor ventilation (or show on elevations) Table notes Floor framing layout (optional) (Note 4) Note 1 Drawings may be combined. Specific design foundations Note 2 Requirements may differ where the building project is an alteration or addition to an existing building. Note 3 A scale of 1:50 may be needed where foundations are relatively complex. Note 4 Provided it is clear as to what is required, it may not be necessary to show each and every floor joist. 24 GUID E TO A PPLYIN G F O R A BUILDIN G C O N S E NT ( R ES ID E NTI A L BUILDIN G S ) – S EC O ND E DITI O N