Government Functional Standard - GovS 002: Project delivery portfolio, programme and project management - GOV.UK

Page created by Gregory Chen
 
CONTINUE READING
Government
Functional Standard

GovS 002: Project delivery
portfolio, programme and project management

Version: 2.0
Date issued: 15 July 2021                     Approved
Government Functional Standard

This functional standard is part of a suite of management standards that promotes consistent
and coherent ways of working across government, and provides a stable basis for assurance,
risk management and capability improvement.
The suite of standards, and associated guidance, can be found at GOV.UK government
functional standards.
Functional standards cross-refer to each other where needed, so can be confidently used
together.
They contain both mandatory and advisory elements, described in consistent language
(see the table below).
 Term         Intention
 shall        denotes a requirement: a mandatory element.
 should       denotes a recommendation: an advisory element.
 may          denotes approval.
 might        denotes a possibility.
 can          denotes both capability and possibility.
 is/are       denotes a description.
The meaning of words is as defined in the Shorter Oxford English Dictionary, except where
defined in the Glossary in Annex B.
It is assumed that legal and regulatory requirements are always met.
Version 2 of GovS 002 replaces version 1.2 and has the same purpose, scope and intent.
The main changes relate to general enhancements derived from feedback, use and changes
to other functional standards. Former clause 7 on supporting practices has been split into two
separate sets of clauses covering planning and control, and solution delivery.

© Crown copyright 2021
Produced by Infrastructure and Projects Authority
You may re-use this information (excluding logos) free of charge in any format or medium,
under the terms of the Open Government Licence. To view this licence,
visit http://www.nationalarchives.gov.uk/doc/open-government-licence/ or
email: psi@nationalarchives.gsi.gov.uk
Where we have identified any third-party copyright material you will need to obtain permission
from the copyright holders concerned.

  2
Version: 2.0 – 15 July 2021                                   GovS 002: Project delivery

Contents
1.   About this government functional standard                                         6
     1.1 Purpose of this government standard                                               6
     1.2 Scope of this standard                                                            6
     1.3 Government standards references                                                   6

2.   Principles                                                                        7
3.   Context                                                                           8
     3.1 Introduction                                                                  8
     3.2 Portfolios, programmes, projects and other related work                       8
     3.3 Working with different delivery approaches                                   10

4.   Governance                                                                       10
     4.1   Governance and management framework                                        10
     4.2   Assurance                                                                  11
     4.3   Decision Making                                                            12
     4.4   Roles and accountabilities                                                 13

5.   Portfolio management                                                             16
     5.1 The purpose of portfolio management                                          16
     5.2 Portfolio governance and management framework                                16
     5.3 Portfolio management practices                                               18

6.   Programme and project management                                                 20
     6.1   The purpose of programme and project management                            20
     6.2   Programme and project governance and management framework                  20
     6.3   Life cycles                                                                20
     6.4   Programme and project management practices                                 23

7.   Planning and control practices                                                   27
     7.1   Overview                                                                   27
     7.2   Planning                                                                   27
     7.3   Benefits management                                                        28
     7.4   Resource, capacity and capability management                               29
     7.5   Reporting                                                                  29
     7.6   Risk and issue management                                                  30
     7.7   Change control                                                             30

                                                                                       3
Government Functional Standard

         7.8    Traceability management                                   31
         7.9    Information and data management                           32
         7.10   Finance                                                   32
         7.11   Procurement and contract management                       33
         7.12   Stakeholder engagement                                    33
         7.13   Communications                                            33

8.       Solution delivery practices                                      34
         8.1    Overview                                                  34
         8.2    Quality management                                        34
         8.3    User needs and requirements                               34
         8.4    Solution design                                           35
         8.5    Solution development and integration                      35
         8.6    Verification against design and validation against need   35
         8.7    Management of organisational and societal change          36
         8.8    Learning from experience                                  36
         8.9    Project delivery team induction and training              36
         8.10   Health and safety                                         37
         8.11   Environment and sustainability                            37

A.       References                                                       38
B.       Glossary                                                         40
C.       Example roles and accountabilities                               45
D.       The reference project life cycle                                 48
E.       Examples of life cycles reflecting different needs               49
         The extended life cycle                                          49
         A project life cycle example, based on agile delivery            50

     4
Version: 2.0 – 15 July 2021                                                      GovS 002: Project delivery

    1 About this standard
                                                       Principles
    2

    3                         Context: portfolios, programmes and projects

    4                          Governance (approvals, assurance and roles)

                                            Organisation management
                                                                                                                Governed
                                                                                                                through a
    5                                          Portfolio management                                             business
                                                                                                                plan

                                            Programme management                                                Governed
                                                                                                                through a
                                                                                                                business
                                                                                                                case
    6                      Project management                         Other related work

                                                                                                                Governed
                                                                                                                through a
                                           Work package management                                              work plan

    7                                    Planning and control practices

    8                                       Solution delivery practices

                              Request direction, advice and decisions        Provide direction, advice and decisions
        Key to arrows:        Report progress, escalate issues and risks     Keep appraised of context and risk

    n   Numbers refer to the section in the standard which covers each topic

Figure 1 Structure and scope of this standard

                                                                                                                       5
Government Functional Standard

1. About this                                    1.2 Scope of this standard
   government                                    This standard applies to portfolios,
                                                 programmes and projects undertaken within
   functional standard                           or across government departments and
                                                 their arm’s length bodies:

1.1 Purpose of this government                   •   ranging from those listed in the
                                                     Government Major Project Portfolio
    standard                                         (GMPP) through to those at local
The purpose of this government functional            business level
standard is to set expectations for the          •   whether for digital, infrastructure,
direction and management of portfolios,              transformation, service delivery, military
programmes and projects ensuring value for           capability, property, regulatory
money and the successful and timely                  compliance or other purposes
delivery of government policy and business
objectives.                                      •   regardless of delivery methodology
                                                     or technique used
This standard provides direction and
guidance for:                                    Other public sector organisations, devolved
                                                 or local, might find this standard useful.
•   permanent secretaries, directors
    general, chief executive officers of arm’s   Note: an organisation, in the context of
    length bodies and sponsoring bodies,         government functional standards, is the
    ensuring an environment exists which         generic term used to describe a government
    promotes delivery success and                department, arm’s length body, or any other
    integrates with their other activities       entity that is identified as being within scope
                                                 of a functional standard.
•   senior responsible owners, ensuring the
    breadth of practices required for            The structure of the standard is shown in
    successful delivery are used                 Figure 1.

•   owners of departmental methodologies,        1.3 Government standards
    developing processes and techniques
    which are consistent in scope across             references
    government                                   The following standards are directly
•   assurance and audit bodies, for testing      necessary for the use of this standard:
    best practice                                •   GovS 003, Human resources
•   portfolio, programme and project             •   GovS 005, Digital, data and technology
    offices, managers, suppliers and their
                                                 •   GovS 006, Finance
    teams introducing the practices
                                                 •   GovS 007, Security
                                                 •   GovS 008, Commercial
                                                 •   GovS 009, Internal audit
                                                 •   GovS 010, Analysis
                                                 •   GovS 011, Communication

    6
Version: 2.0 – 15 July 2021                                   GovS 002: Project delivery

A functional standard supports achievement
of the outcomes sought by an organisation.
                                               2. Principles
It sets expectations for what needs to be      Those engaged in project delivery shall
done and why relating to the functional work   ensure:
within its scope, in order to achieve those
organisational outcomes.                       1. delivery objectives are aligned to
                                                  government policy and organisational
Note: for expectations relating to                objectives
management of a function across
                                               2. continuing business justification to
government, and management of functional
                                                  confirm benefits can be realised and
standards, see GovS 001, Government
                                                  risks managed within the organisation’s
functions.
                                                  risk appetite, and that unjustified work is
                                                  terminated
                                               3. governance and management
                                                  frameworks, and controls are
                                                  proportionate and appropriate to the
                                                  work and the level of prevailing risk
                                               4. accountabilities and responsibilities are
                                                  defined, mutually consistent and
                                                  traceable across all levels of
                                                  management
                                               5. experience and lessons are captured,
                                                  shared and used to promote future
                                                  performance improvement
                                               6. work is appropriately defined, planned,
                                                  monitored and controlled, quality is
                                                  actively managed to maximise the
                                                  likelihood of success and defined
                                                  working methodologies are tailored for
                                                  use accordingly
                                               7. outcomes and enabling outputs meet
                                                  the need and are validated by
                                                  stakeholders
                                               8. work is undertaken in multidisciplinary
                                                  teams and is assigned to people who
                                                  have the required capability and capacity
                                               9. the transition of capabilities to
                                                  operations is planned and programme
                                                  or project closure managed, with
                                                  ongoing operational responsibilities
                                                  agreed and accepted
                                               10. public service codes of conduct and
                                                   ethics and those of associated
                                                   professions are upheld

                                                                                           7
Government Functional Standard

3. Context                                          3.2 Portfolios, programmes,
                                                        projects and other related
3.1 Introduction                                        work
This section provides essential background          A portfolio comprises part or all of an
information for the use of this functional          organisation’s investment required to
standard.                                           achieve its objectives. Governed through
                                                    its portfolio (or business) plan, a portfolio
Portfolio, programme and project
                                                    comprises work components, such as
management is an integrated way of
                                                    other portfolios, programmes, projects and
meeting the government’s ambitions,
                                                    other related work.
driving better decisions and increasing the
likelihood of successful outcomes.                  A programme is a unique, temporary,
Collectively, portfolio, programme and              flexible organisation created to co-ordinate,
project management are referred to in               direct and oversee the implementation of a
government as project delivery.                     set of projects and other related work to
                                                    deliver outcomes and benefits related to a
                                                    set of strategic objectives. Programmes can
                                                    be undertaken in one or more tranches
                                                    (phases), each of which is structured around
                                                    distinct step changes in the solution
                                                    delivered and the resultant benefit realised.

                                   Host organisation

                                              Portfolio

                                                          Project            Other related
        Portfolio            Programme
                                                                                work

                                Project               Other related
       Programme                                                            Work package
                                                         work
                         stages

                            Work package             Work package

      Work package                                   Work package

Figure 2 Example of a hierarchy of work components

  8
Version: 2.0 – 15 July 2021                                      GovS 002: Project delivery

A project is a unique, temporary                  Note: for example, stages can represent
management environment, undertaken in             agile releases and work packages can
stages, created for the purpose of delivering     represent sprints.
one or more business products or                  A work package is a set of information
outcomes. A project might be standalone           relevant to the creation of one or more
within a portfolio or part of a programme.        deliverables or outputs. It comprises a
Other related work, not managed as a              description of the outputs required, work
programme or a project, might include:            plan and details of any constraints.
•   support services (see 4.4.9), solution        Figure 2 shows the hierarchical relationship
    architecture, finance and human               between work components, with each
    resources                                     higher-level component comprising the sum
•   ongoing improvement initiatives not run       of all connected lower-level components.
    as projects, but using a defined              Work components may cross organisational
    approach, such as agile delivered             and departmental boundaries.
    platform-based upgrades (see Annex E),
    six sigma and LEAN                            Note: the use of the terms ‘project’ and
                                                  ‘programme’ is not always indicative of the
•   service delivery, business as usual           formal definitions in this standard; however,
    operations                                    the distinction is important when designing a

                                          Portfolio

                                                                   Other related
                       Programme                                      work

                                             Other related
                 Project                        work

                                                 Agile approaches can be
                                                 used at different levels in
        Work              Work
                                                 the hierarchy depending
       package           package
                                                      on the context

Figure 3 Example showing where agile approaches can be used

                                                                                              9
Government Functional Standard

programme or project governance and
management framework.
                                              4. Governance
3.3 Working with different                    4.1 Governance and
    delivery approaches                           management framework
This project delivery standard defines a      4.1.1 Overview
number of practices needed for successful
outcomes. It defines the why and the what     Governance comprises prioritising,
for each but does not define how work is      authorising, directing, empowering and
to be undertaken. For example, ‘agile’        overseeing management, and assuring and
approaches are needed in many cases but       reviewing performance.
could be used at any point in the project
                                              4.1.2	Governance of project delivery
delivery hierarchy (see Figure 1 Structure
                                                     across government
and scope of this standardFigure 3).
                                              A governance and management framework
Nor, in the case of a project, does the       shall be defined and established at
standard define what the project life cycle   government level to monitor project delivery
stages should be, only that they can be       across government, which should include:
mapped to the reference life cycle.
The project might only include the delivery   •   mandatory policies, process, data and
of outputs when the project is part of a          other requirements together with
programme, or could include an extended           associated guidance
period of operation in other situations.      •   requirements for assurance, tracking
The delivery approaches and stages need           and reporting on the government’s
to be defined to suit the outputs and             major projects
outcomes delivered and the delivery
                                              •   the requirements and provision of expert
approaches taken. In a project where the
                                                  support and assurance
work is predominantly agile, the project
stages of discovery, alpha, beta, live and    Note: the IPA Mandate [9] sets out a
retirement meet that requirement              statement of the Infrastructure and Projects
(see GovS 005, Digital, data                  Authority’s role and the responsibilities of
and technology). Annex E includes some        departments in regard to project delivery.
examples.
                                              4.1.3	Governance of project delivery in
                                                     an organisation
                                              The governance and management of project
                                              delivery within an organisation should be an
                                              integrated part of that organisation’s overall
                                              governance.
                                              An organisation’s governance and
                                              management framework shall be:
                                              •   defined and established at
                                                  organisational level which complies with
                                                  government and departmental policies
                                                  and directives and with this standard

  10
Version: 2.0 – 15 July 2021                                      GovS 002: Project delivery

•   referenced from the respective                agreement of the Infrastructure and Projects
    Accounting Officer System Statement           Authority and HM Treasury spending team.
The governance and management                     Government major projects shall be
framework should include the authority            reported through the Government Major
limits, decision making roles and criteria,       Projects Portfolio (see 7.5).
degree of autonomy, assurance needs,
                                                  Note: see also Treasury approval process [12]
reporting structure, accountabilities and
                                                  and Treasury assurance frameworks [13].
responsibilities together with the
appropriate governance and management
frameworks, as defined in clause 5.2 for
                                                  4.2 Assurance
portfolios and clause 6.2 for programmes          4.2.1 Overview
and projects. The governance and
management framework should be                    The purpose of assurance is to provide,
designed to be tailored to reflect the level of   through a systematic set of actions,
prevailing risk, the competence of those          confidence to senior leaders and
individuals involved, and the work required.      stakeholders that work is controlled and
                                                  supports safe and successful delivery of
4.1.4 Governance of major projects                policy, strategy and objectives.
Programmes or projects meeting one or             4.2.2	Organisational assurance of
more of the following characteristics shall              project delivery
be referred to the HM Treasury spending
team and the Infrastructure and Projects          Organisations should have a defined and
Authority for inclusion in the Government         established approach to project delivery
Major Project Portfolio (GMPP):                   assurance, which should be applied
                                                  proportionately to the risk and value of the
•   above the delegated authority limit for       activity, and which is integrated with the
    the organisation                              organisation’s overall assurance framework.
•   could create pressures leading to a           Typically, assurance should be on at least
    breach in departmental expenditure            three separate and defined levels including:
    limits, administration cost limits, or        •   by, or on behalf of operational
    estimates provision                               management that own and manage risk
•   would entail contractual commitments              to ensure appropriate standards are
    to significant levels of spending in future       being used
    years for which plans have not been set       •   by, or on behalf of senior management,
•   could set a potentially expensive                 independent of operational management
    precedent                                         to ensure first level of assurance is
                                                      properly designed, in place, and
•   is novel or contentious, or could cause
                                                      operating as intended
    significant repercussions, posing risks to
    the public sector                             •   by independent audit, or other impartial
                                                      body, to provide senior management
•   requires primary legislation or where
                                                      with an objective opinion on the
    HM Treasury consent is a statutory
                                                      effectiveness of governance, risk
    requirement
                                                      management, and internal controls,
Programmes and projects not meeting the               including the effectiveness of the first
above criteria may be added to the                    and second levels
Government Major Project Portfolio with the

                                                                                             11
Government Functional Standard

Internal audits shall be undertaken in          4.2.4	Assurance of government major
accordance with GovS 009, Internal audit.              projects
The requirements of the Orange Book shall       For government major projects, the
be met [6].                                     approach to assurance shall be defined in
                                                an integrated assurance and approval plan
4.2.3 Programme and project assurance           (IAAP) [10] which shall be validated by
Programmes and projects should have a           HM Treasury and the Infrastructure and
defined and integrated plan for undertaking     Projects Authority. HM Treasury does not
assurance and approvals which should be         normally approve a programme or project
developed with the initiation documentation,    without a validated integrated assurance
regularly reviewed, updated and maintained      and approval plan.
until closure.                                  For government major projects, assurance
Assurance reviews shall be scheduled prior      reviews of the entire programme or project
to significant decisions (such as contractual   shall be undertaken by the Infrastructure
commitments and gates) to provide               and Projects Authority, or as delegated by
decision makers with an assessment of the       them.
status and outlook for the work. The time
lapse between assurance reviews of the          4.3 Decision Making
entire programme or project should not be       Decisions relating to project delivery should
scheduled to exceed one year. Assurance         be made, and approvals and authorisation
reviews may also be undertaken in response      given, in a timely manner, in accordance
to an issue or to verify delivery.              with the organisation’s governance and
The work of internal and external assurance     management framework. Government
providers should be planned to minimise         policy should be complied with. Decisions
disruption to work, (for example, by            should be made by assessing options
combining project and programme reviews         against defined criteria and in consultation
as shown in Figure 1 Structure and scope of     with stakeholders and subject matter
this standard) avoiding overlaps with other     experts. Options shall be assessed in
assurance activities and duplication of         accordance with GovS 010, Analysis.
effort, whilst remaining rigorous and           Decisions should relate to, but not be
meeting the needs of stakeholders. Where        limited to:
assurance includes formal review activity,
the customer for the review should be           •   approving vision and strategy
clearly identified.                             •   approving business cases
Recommendations resulting from the              •   approving plans and baselines
reviews should be documented, agreed and
                                                •   setting risk appetite and tolerance
acted on.
                                                •   initiating a programme or project
Note: the Infrastructure and Projects
Authority’s Assurance tool kit provides         •   authorising the start of a new project
guidance for undertaking assurance                  stage, for example, at a gate or decision
reviews [3].                                        point (see 6.3) or for a new tranche of
                                                    a programme
                                                •   selecting suppliers
                                                •   deciding options for further study

  12
Version: 2.0 – 15 July 2021                                      GovS 002: Project delivery

•   selecting a solution                         Cabinet Office expenditure controls require
•   pausing, terminating or closing work         central government bodies to obtain
                                                 expenditure approval from Cabinet Office
Decisions should be:                             ministers, based on professional advice
•   holistic, taking account of the external     from relevant functions, before certain
    context, whole life of outputs (such as in   expenditure is made or committed.
    life service, disposal) and negative         Organisations should take advice from
    impacts                                      relevant functional experts in advance of
                                                 planned expenditure, and comply with
•   communicated to the relevant
                                                 expenditure controls guidance.
    stakeholders
                                                 Note: expenditure control guidance can be
Decisions may be:
                                                 found in Managing Public Money [1] and in
•   conditional, with responsibility for         the annual consolidate budgeting guidance;
    fulfilling such conditions defined           see GovS 006, Finance.
•   phased to take into account risk (see 6.3)
                                                 4.4 Roles and accountabilities
A programme, project or other related work
shall be governed through a business case        4.4.1 Overview
or equivalent document, in accordance with
                                                 Roles and accountabilities shall be defined
HM Treasury requirements. If a project or
                                                 in the relevant governance and management
other related work is part of a programme,
                                                 framework and assigned to people with
its business case may be included within
                                                 appropriate seniority, skills and experience.
the programme’s business case. A business
                                                 This should include, but is not limited to, the
case should include a cost-benefit analysis
                                                 activities, outputs or outcomes they are
and demonstrate strategic, economic,
                                                 responsible for, and the person they are
commercial, financial and management
                                                 accountable to.
justification. The business case shall be
prepared and the investment appraised in         Each role holder should act as a role model
accordance with GovS 006, Finance.               for the behaviours expected when working
                                                 on project delivery.
The business case should be developed
over a number of phases and should be            Note: examples of roles and accountabilities
updated to reflect changes and reviewed          are provided in Annex C.
prior to every gate or decision point to         Note: the Project Delivery Capability
justify continuing the work.                     Framework [11] includes the professional
The Accounting Officer shall approve             standards for a range of project management
government major projects prior to               roles operating at different levels covering
submission to HM Treasury for authorisation      both leadership and technical skills.
[12]. Accounting Officer approval shall be       Note: further guidance on roles can be found
supported by an Accounting Officer               in AXELOS’ guides [Annex A 21-28].
Assessment for the outline business case
and, when advised by the senior                  4.4.2	Senior officer responsible for
responsible owner, for any subsequent,                  project delivery across
materially changed business cases [14].                 government
Note: guidance on investment appraisal,          The senior officer responsible for project
business cases and evaluation is provided in     delivery across government is accountable
the HMT’s Green Book [5].                        to the chief operating officer of the civil

                                                                                           13
Government Functional Standard

service for supporting successful project       4.4.4 Portfolio director
delivery across government, especially for      The portfolio director is accountable to a
government major projects, including but        defined higher-level authority for the
not limited to:                                 direction and governance of the portfolio,
•   setting standards and leading               for optimising the required benefits at an
    development of government-wide              acceptable level of risk. The portfolio
    policies, processes, tools and guidance     director provides leadership and direction
                                                and owns the portfolio’s vision and strategy.
•   government project delivery assurance
•   providing expert support and advice         Note: the higher-level authority depends on
                                                the context and might be the Accounting
•   monitoring government project delivery      Officer, a departmental, arm’s length body
    performance and if necessary,               or executive board or a portfolio board.
    intervening
                                                Note: see Annex C for more detail on this role.
•   assessing project delivery aspects in
    Spending Reviews                            4.4.5 Portfolio manager
•   system-wide improvement of project          The portfolio manager is accountable to the
    delivery                                    portfolio director (see 4.4.4) for planning and
                                                managing the portfolio as a whole and
•   building government project delivery        ensuring its work content is sufficient to
    capability                                  meet the portfolio’s objectives, including
Note: this role is normally undertaken by the   monitoring spend against budget and
chief executive of the Infrastructure and       benefits realisation. The portfolio manager
Projects Authority as defined in the IPA        leads and coordinates the effective and
Mandate [9].                                    efficient operation of portfolio management
                                                and ensures the flow of information to
4.3.3 Accounting Officer                        decision makers.
The permanent head of a government              Note: see Annex C for more detail on this role.
department is usually its Principal
Accounting Officer. An organisation’s           4.4.6 Sponsoring body
Accounting Officer is accountable (via a        The sponsoring body acts as the higher-
Principal Accounting Officer where              level authority for a programme or project
appropriate) to Parliament and the public       and is accountable to a defined higher-level
for the stewardship of public resources,        authority, normally the accounting officer
ensuring they are used effectively and to       (see 4.4.3). The sponsoring body acts as
high standards of probity. The Principal        the driving force for a programme or project
Accounting Officer generally appoints the       providing:
most senior executive in the arm’s length
bodies within the department’s ambit as an      •   top-level endorsement for the
Accounting Officer.                                 programme’s or project’s rationale
                                                    and objectives
Note: the Accounting Officer is generally the
Permanent Secretary or, in an arm’s length      •   direction to the senior responsible
body, the chief executive officer. See              owner, addressing escalated risks
Managing Public Money [1], Cabinet Office           and issues
Controls [2], Assurance framework [13],         •   making or referring decisions that are
Accounting Officer System Statements and            above the senior responsible owner’s
Accounting Officer assessments [14].                delegated authority

    14
Version: 2.0 – 15 July 2021                                        GovS 002: Project delivery

Note: the make-up of the sponsoring body           4.4.9	Portfolio, programme and project
(person or group) depends on the programme                support office manager
or project’s context. For example, for a project   The portfolio, programme and project
within a portfolio, the sponsoring body can be     manager and their respective teams should
the portfolio manager or director; for a project   be supported in the effective and efficient
within a programme, the sponsoring body can        undertaking of their roles. Services provided
be the programme manager.                          might include value added delivery support,
                                                   such as:
4.4.7 Senior responsible owner (SRO)
The senior responsible owner is                    •   defining processes and methodologies
accountable to the sponsoring body (see            •   undertaking analysis
4.4.6) for a programme or project meeting
                                                   •   operating aspects of governance
its objectives, delivering the required
outcomes and realising the required                •   providing consultancy and advice
benefits. The senior responsible owner             •   undertaking delegated responsibilities
owns the business case and is accountable
for governance (see section 4).                    •   undertaking administrative functions

The senior responsible owner of a                  Support might be provided by single or
government major project is ultimately             multiple physical or virtual structures or
accountable to Parliament.                         offices (permanent and/or temporary), which
                                                   can be centralised or distributed.
Note: the Infrastructure and Projects
Authority’s SRO briefing notes provides            Note: the title of these roles may be chosen to
relevant documentation for senior responsible      reflect the scope and seniority, such as PMO
owners [4].                                        Director, PMO Manager, Head of PMO or
                                                   P3O® Director.
Note: see Annex C for more detail on this role.
                                                   Note: see Annex C for an example of a
4.4.8 Programme/project manager                    programme or project office manager role.
The programme/project manager is                   4.4.10 Other management and team roles
accountable to the senior responsible owner
for establishing the governance and                Other management and team roles should be
management framework and for the day-to-           defined to suit the needs of the work
day management of a programme/project,             required, for example those undertaking
to deliver the outputs and desired                 specialist roles, or managing the
outcomes, and realise the required benefits.       development of specialist outputs.
                                                   Examples include roles relating to benefits
Note: the job title of a programme/project         management, agile delivery, service and
manager can reflect the seniority of the           operations management, business change,
person, such as “project director” or              communications and various engineering
“programme director” or the type of work           disciplines.
being undertaken, such as in agile delivery.
                                                   Note: see Annex C for an example of a work
Note: see Annex C for more detail on this role.    package or team manager.

                                                                                              15
Government Functional Standard

5. Portfolio                                    governance and management framework
                                                should include, but not be limited to:
   management                                   •   roles and accountabilities, processes,
                                                    methods, techniques, guidance,
5.1 The purpose of portfolio                        templates and tools for governance
                                                    (see 4) the management practices
    management                                      (see 5.3) and supporting practices
Portfolio management is a coordinated               (see 7 and 8)
collection of practices and decisions that      •   the planning horizons to be used and
together enable an effective balance of             how often the plan should be reviewed
organisational change and business as               and updated
usual, whilst remaining within a specified
funding envelope and constraints.               •   the types of work component to be
                                                    included in the portfolio, together with
Portfolio management shall be an integral           criteria to identify them
part of an organisation’s business planning
and control activities.                         •   criteria and techniques for categorizing,
                                                    prioritising and selecting the portfolio’s
The portfolio director (see 4.4.4) and              work components
manager (see 4.4.9) should:
                                                •   processes for the initiation and
•   ensure investment is aligned to the             management of work components
    government’s policy and departmental
    vision and strategy                         •   how resources and funds are allocated

•   maximise benefits realised by the           •   a reporting framework
    portfolio as a whole                        The portfolio’s governance and
•   balance the portfolio to cover short-term   management framework should align to and
    and long-term objectives                    work with:

•   ensure risks across the portfolio are       •   the organisation’s governance and
    within the organisation’s risk appetite         management framework and decision-
                                                    making authorities
•   optimise the organisation’s capability
    and capacity to ensure the portfolio can    •   other organisational processes and
    be delivered                                    practices, such as those for strategy
                                                    and policy development, business
•   ensure those impacted by the portfolio’s        planning, finance, performance
    outcomes can take on the changes                reporting, capability and capacity
•   optimise the use of funds and resources,        management, enterprise risk
    bearing in mind the associated risks            management, and communications
                                                A record of the portfolio’s work components
5.2 Portfolio governance and                    should be kept up to date, including, for
    management framework                        each work component: component type;
                                                person responsible; status (for example:
A portfolio governance and management           proposed, in progress, paused, terminated,
framework (see 4.1), defining how a portfolio   completed); the position in the portfolio
is to be directed and managed, shall be         hierarchy; significant interdependencies
established, maintained, and communicated       between components under different senior
to appropriate stakeholders. The portfolio’s    responsible owners (see 4.4.7); an indicator

    16
Version: 2.0 – 15 July 2021                                                                  GovS 002: Project delivery

denoting whether the component is required                            planning activities. An organisation’s overall
to be reported as part of the Government                              portfolio may be managed as a set of sub-
Major Projects Portfolio. Additional data                             portfolios.
may be included for management, analysis                              The organisation’s group undertaking
and reporting purposes.                                               portfolio management may provide other
Portfolio management responsibilities may                             services, such as those provided by a
be assigned as each organisation sees fit                             programme management office (see 4.4.9),
and should be integrated with those                                   including methods, advice, resourcing, or
responsible for the organisation’s business                           tools support.

                                 Portfolio                      Work
                          vision, strategy               component
     Decision points                                                         See Figures 5 and 6.
                                 and plan               authorisation
     (Clause 4.3)

                                                                                                                   Outcomes
                                                            Portfolio
        Policy and
                                                                                                                      and
        objectives
                                                                                                                    benefits

     Assurance reviews
     (Clause 4.2)

                                                        Correction needed

                                     5.3.2
        Policy and                                                     5.3.4
                            Setting the vision and                                                      5.3.7
        objectives         strategy for the portfolio               Validating                                     Outcomes
                                                                                                      Portfolio
                                                                     portfolio                                        and
                                                                                                    performance
                                                                  objectives and                                    benefits
                                                                                                     reporting
                                                                     strategy
                                     5.3.3
                           Portfolio definition and
                                   planning

                                       Approved vision, strategy,
                                       definition and plan
     Management
                                                                       5.3.5                           5.3.6
     practices                                                    Authorising the                   Monitoring &
     (Clause 5.3)                                                  start of work                     analysing
                                                                   components                        portfolio
                                                                                                      delivery

     Programme and project management                              Programmes, projects and other
     (Section 6)                                                           related work

     Support
     practices                        7. Planning, control and 8. Solution delivery practices
     (Sections 7 and 8)

Figure 4 Portfolio management as an ongoing and iterative activity, showing decisions and
assurance reviews from section 4 and their relationship to the practices in sections 5, 6, 7
and 8

                                                                                                                               17
Government Functional Standard

Note: the portfolio’s governance and             The portfolio’s strategy should set the
management framework can be tailored from        context for the definition and planning of
Management of Portfolios [24]. Further           the portfolio, and inform the criteria for
guidance can also be found in ISO 21504 [33].    investment decisions and the approval of
                                                 work components.
5.3 Portfolio management
                                                 5.3.3 Portfolio definition and planning
    practices
                                                 The portfolio, as a whole, should be defined
5.3.1 Overview                                   and planned in accordance with the
Portfolios form part of the organisation’s       portfolio’s governance and management
governance and the delivery of its business      framework (see 5.2), to meet the purposes
plan. Portfolio management is cyclic in          listed in clause 5.1. The planning horizon
nature, enabling the organisation to             should be for a defined period aligned with
continuously adapt to the organisation’s         the organisation’s business plan. When
changing context and environment of the          planning the portfolio:
organisation in pursuit of its objectives        •   the government’s policy and
(see Figure 4).                                      organisational objectives, context and
                                                     priorities should be understood,
5.3.2	Setting the vision and strategy for           together with the current status of the
       the portfolio                                 portfolio and its work components
A vision should be defined and                   •   measures for the successful delivery of
communicated, stating the overarching                outcomes and realisation of benefits
aspirations of what is to be achieved in the         should be defined
long-term.
                                                 •   potential new work components should
A strategy, describing the objectives and            be categorised and evaluated, based on
desired delivery outputs and outcomes,               their degree of strategic fit, expected
shall be defined and communicated to                 benefits, efficient use of funds and risk;
inform future decisions and choices about            the views of stakeholders should be
how the portfolio’s objectives are to be             understood and considered
delivered. The portfolio strategy should
include:                                         •   work components should be prioritised
                                                     and selected, based on the results of
•   the organisational objectives and                the evaluation, taking into account the
    priorities from the business plan which          performance of existing work
    relate to the portfolio                          components
•   the portfolio’s long-term objectives         •   each work component should be
•   summary information on the benefits              traceable to government policy or
    and costs                                        organisational objectives (see 7.8)
•   outcomes and capabilities to be              •   the plan should be collated with
    delivered and how these link to the              interdependencies identified between
    portfolio’s objectives and priorities from       components within and outside the
    the business plan                                portfolio
•   key success factors and resource and         •   once approved, the portfolio plan should
    risk information                                 be baselined, and any changes
                                                     approved by the appropriate authority

    18
Version: 2.0 – 15 July 2021                                         GovS 002: Project delivery

5.3.4	Validating the portfolio’s objectives        •   availability of finance (see 7.10)
       and strategy                                 •   current capacity and capability
The portfolio’s objectives and strategy                 constraints in the organisation and
should be periodically reviewed to ensure:              supply chain (see 7.4)
•   they are still current and affordable           •   current level of portfolio risk, including
•   the right programmes, projects and                  those related to interdependencies
    other related work components are                   (see 7.6)
    being undertaken                                •   the views and reactions of impacted
If required, corrective action should be                parties and other stakeholders (see 7.12)
taken to amend the portfolio’s vision,              Stakeholders should be monitored and
objectives and strategy, or adjust the              engaged, with new stakeholders identified
portfolio’s scope and content.                      and existing stakeholders re-evaluated.
                                                    New risks and issues should be identified,
5.3.5	Authorising the start of work                and existing ones managed. Action should
       components                                   be taken to ensure the portfolio meets its
New work components should be identified,           objectives and reflects any constraints.
defined and authorised (in compliance with          Existing work components might be
an approved authorisation process, see 4.3          identified for amendment, rescheduling or
on decision making) to start when indicated         termination. Corrective and preventative
in the plan or as required by organisational        actions might trigger the need for new work
priorities. Before being initiated, the portfolio   components, scope changes or termination
manager (see 4.4.5) should confirm the aims         of work.
given in 5.1 are met, an impact assessment
of financial, resource or technical capability      5.3.7 Portfolio performance reporting
is available and that the programme or              Portfolio performance shall be reported
project does not conflict with or duplicate         against the portfolio plan, including, but
other related work. See clauses 6.4.2 and           not limited to, finances, benefits, costs,
6.4.5 on identifying and initiating a               outcomes, milestones and risks. Additional
programme or project.                               analysis and commentary should explain
When approving the start of a work                  variances. Reporting should reflect both
component, the problem or opportunity               achievement to date and a forecast for
should be known, even though the solution           future performance. See also 7.5.
and implementation approach might not
be known.

5.3.6	Monitoring and analysing portfolio
       delivery
The portfolio, as a whole, should be
monitored and analysed with respect to:
•   outcomes achieved, and benefits
    realised
•   adherence to constraints, including
    those for cost, benefit and schedule
•   delivery of primary outputs

                                                                                                19
Government Functional Standard

6. Programme and                                    templates and tools to be used to
                                                    undertake the practices in this standard
   project                                      The governance and management
   management                                   framework of jointly sponsored work should
                                                be defined to reflect the legitimate interests
                                                of the participating organisations.
6.1 The purpose of programme                    The programme’s or project’s governance
    and project management                      and management framework should align
                                                to and work with:
Programme and project management are
structured frameworks for defining and          •   the organisation’s project delivery
undertaking change. They provide a                  governance and management
framework for implementing policy and               framework (see 4.1.3)
business strategies to enable the               •   the portfolio’s governance and
government and organisations to achieve             management framework (see 5.2)
outcomes and benefits of strategic
importance. Programme and project               •   other organisational processes and
management includes the planning,                   practices, such as those for finance,
delegating, monitoring and control of all           human resource management,
aspects of a programme or project and the           performance reporting, capability
motivation of those involved to achieve the         and capacity management, risk
defined objectives within the defined               management, and communications
constraints, such as cost, benefit, schedule,   Note: the governance and management
quality, scope, and risk.                       framework can be tailored drawing on the
                                                government project delivery framework,
6.2 Programme and project                       departmental methodologies or, for major
    governance and                              projects, can be specially developed;
                                                guidance can also be found in the AXELOS
    management framework                        guides [Annex A, 21 to 28].
A programme and project governance and
management framework (see 4.1), defining        6.3 Life cycles
how a programme or project is to be
                                                The life cycle provides a phased approach
directed and managed, shall be defined and
                                                for governing work and underpins the
established. The governance and
                                                delivery plan, from start to finish. The life
management framework may change to
                                                cycle shall be defined and should include
reflect the phase of the work being
                                                approval gates/decision points and
undertaken. The governance and
                                                assurance reviews.
management framework should include:
                                                For government major projects the life cycle
•   authority and decision-making roles and
                                                and its attributes shall be defined in
    rules, including, but not limited to,
                                                accordance with this standard and the
    governance tiers, initiation of new work,
                                                requirements in the government project
    prioritisation, assignment of resources
                                                delivery framework.
    and funds, and issue resolution
                                                A project shall comprise stages, each of
•   roles and accountabilities, processes,
                                                which shall be preceded by a gate (decision
    methods, techniques, guidance,
                                                point) to authorise the start of the next
                                                stage and commit resources and funding.

    20
Version: 2.0 – 15 July 2021                                                                         GovS 002: Project delivery

 HM Treasury              Project            Strategic         Outline                 Full             Full         Full
                            brief              outline        business            business          updated      updated
 business cases                                  case             case                case

 Gates / decision
 points (Section 4.3)

                       Policy
                                            Feasibility        Appraisal       Definition        Delivery      Operation         Operations
                     (concept)

Assurance
reviews
(Section 4.2)                            Business            Delivery        Investment          Readiness      Operations review and
                                                             strategy          decision          for service

                                        Assess

                                                                                                                            Project completed
                                       feasibility

                                                            Appraise
                                                           and select

 Project stages
                                    Project started

                                                                                Define
 (Section 6.3)

                                                                                                     Deliver

                                                                                                                Operate,
                                                                                                               embed and
                                                                                                                 close

                                                                                 6.4.3
                        6.4.2                                             Overseeing a project                                         6.4.9
Management           Identifying                                                                                                     Reviewing
practices                                                                         6.4.4
                                                                           Directing a project
(Clause 6.4)

                                       6.4.5                                      6.4.6                            6.4.8
                                     Initiating                             Managing a project                    Closing

                                                                                 6.4.7
                                                                        Managing a work package

Support
practices                                                Planning, control and solution delivery practices
(Sections 7 and 8)

Figure 5 The reference project life cycle with gates, stages and assurance reviews from
section 4 and their relationship to the practices in sections 6, 7 and 8

                                                                                                                                                21
Government Functional Standard

  HM Treasury
  Business cases
                       Programme          Strategic       Outline   Programme       Programme              Programme
                             brief          Outline      business     Business        Business               Business
                                              case           case         case            case                   case
  Decision points
  (Section 4.3)

                        Policy                                         Programme                                                   Operations

  Assurance
  reviews                               Business         Delivery                                                    Operations review
  (Clause 4.2)                        justification      strategy                                                      and benefits
                                                                                                                        realisation

                                                       Tranche A

                                                                                                                          Project completed
                                        Assess
                                       feasibility                     As defined in the integrated
                                                        Appraise       assurance and approval plan
                                                       and select

                                                                                       Tranche B
                                                                       Project

                                                                             Project

                                                                                 “Other work”
  Project stages
  (Clause 6.3)                                                                                              Tranche C
                                                                                       Project
                                     Project started

                                                                                             “Other work”
                                                                                                           Project

                                                                                                            Tranche D

                                                                                                   “Other work”

                                                                             6.4.3
                          6.4.2                                       Overseeing a project                                              6.4.9
                       Identifying                                                                                                    Reviewing
  Management
  practices                                                                   6.4.4
  (Clause 6.4)                                                       Directing a programme

                                        6.4.5                                6.4.6                               6.4.8
                                      Initiating                     Managing a programme                       Closing

  Support
  practices                                            Planning, control and solution delivery practices
  (Sections 7 and 8)

Figure 6 Example programme life cycle, showing tranches, decisions and assurance reviews
from section 4 and their relationship to the practices in sections 6, 7 and 8

  22
Version: 2.0 – 15 July 2021                                      GovS 002: Project delivery

The project life cycle should be defined to      Model project life cycles may be developed
suit the circumstances by tailoring and          for undertaking particular types of project or
mapping to the reference life cycle shown in     programme.
Figure 5 and Annex D. The number of gates
                                                 Note: Annex D includes a detailed example
and stages, types of assurance review and
                                                 project life cycle. Annex E includes agile
form of the business case should be chosen
                                                 delivery and extended life cycle example.
to ensure governance is appropriate and
proportionate to the circumstances, with         Note: phases for a project are called stages
simpler projects having fewer stages             (PRINCE2® [22]). Stages can reflect the
(minimum of two) and more risky projects         approach taken, for example, developed
having more stages. See Figure 5 and             using an agile approach, such as discovery,
Annex D.                                         alpha, beta (private); beta (public) or in
                                                 ‘waterfall’, such as analysis, design,
A programme may be phased in one or              development, testing, implementation.
more tranches and might cover the whole          Further detail and examples of a project life
life of a product, service or system (see        cycle are included in Annexes D and E.
Figure 6).
                                                 Note: see Figure 5 for detail for each project
The following shall be defined for each gate     in a programme.
or decision point:
•   criteria for providing authorisation         6.4 Programme and project
•   the decision makers                              management practices
•   who should be consulted
                                                 6.4.1 Overview
•   the type of assurance review required
    prior to the decision (see 4.2)              The programme and project management
                                                 practices should be defined in the
Criteria should include, but not be limited to   governance and management framework
the following:                                   (see 6.2). Figure 7 shows the relationship
•   work aligns with policy and strategy and     between the roles defined in clause 4.4 and
    is still needed                              the practices in clause 6.4.
•   the business case is acceptable              6.4.2 Identifying – policy
•   risks have been identified and are           Identifying a programme or project ensures
    acceptable or can be mitigated               that the policy or other objective for
•   the solution is (or is likely to be)         undertaking the work is defined and likely
    acceptable                                   to be realistic before the first phase of work
                                                 is authorised to start, and funds and
•   there are funds and resources to             resources committed.
    complete the work and support any
    outcomes                                     The senior responsible owner (see 4.4.7)
                                                 shall be appointed. Potential team members
•   there is a plan for the next stage and       and subject matter experts should be
    outline plan for the remainder of the        identified and be involved with policy
    work                                         formulation to ensure the opportunity or
A decision might result in approval to           need is explored and understood and that
proceed, a request for work to be revised,       deliverability is taken into account.
or deferral or termination of the project.

                                                                                            23
Management
practices
(Clause 6.4)             Government Functional Standard

         Sponsoring body                                          6.4.3
         (see 4.4.6)             6.4.2                     Overseeing a project                        6.4.9
                              Identifying                                                            Reviewing
         Senior responsible                                        6.4.4
         owner (see 4.4.7)                                  Directing a project

         Programme/project                    6.4.5                6.4.6                    6.4.8
         manager (see 4.4.8)                Initiating       Managing a project            Closing

         Team manager                                             6.4.7
         (see Annex C)                                   Managing a work package

     Figure 7 Relationship between the roles and the programme and project management
     practices

     Before a programme or project is submitted                •    independent assurance reviews and
     for approval, the senior responsible owner                     audits
     should ensure:                                            •    ad hoc escalations and interventions
     •      the vision, justification and desired              The sponsoring body (see 4.4.6) should
            outcomes for the programme or project,             keep the senior responsible owner
            together with any strategic assumptions,           (see 4.4.7) updated on the wider context,
            are documented in a programme or                   providing guidance and direction, as
            project brief                                      needed or when requested. The sponsoring
     •      policy and decision makers have sought             body shall enable the senior responsible
            advice from experienced professionals              owner to have sufficient time to carry out
            on deliverability and risks                        their responsibilities effectively.
     •      the appropriate assurance review has               6.4.4 Directing
            been conducted (see 4.2)
                                                               Directing a programme or project ensures
     If policy and objectives change as the work               continuing strategic fit and relevance in the
     progresses through the life cycle, the senior             prevailing business context.
     responsible owner shall review the impact
     and consider whether the work is still                    The senior responsible owner (see 4.4.7)
     justified; resultant changes to the                       shall ensure the solution fulfils government
     programme or project should be controlled                 policy and/or meets the needs of the
     (see 7.7).                                                organisation and represents value for
                                                               money [20].
     6.4.3 Overseeing                                          The senior responsible owner shall provide
     Overseeing a programme or project ensures                 direction and make decisions regarding the
     the sponsoring body is satisfied that the                 future of the programme or project, taking
     team is able to achieve the objectives, meet              into account changes to the overall political,
     the organisation’s needs and stakeholders’                social, environmental, or technological
     expectations, and that risks are at an                    context and prevailing risk. This should
     acceptable level. Oversight can be through:               include ensuring the programme or project
     •      involvement in key decisions                       remains justifiable and assurance reviews
                                                               and approvals (such as at gates and at
     •      periodic reporting                                 closure) are undertaken at the right time and

          24
Version: 2.0 – 15 July 2021                                     GovS 002: Project delivery

corrective and preventative actions taken,       Criteria for determining the successful
if needed.                                       delivery of outcomes and realisation of
The senior responsible owner shall refer         benefits should be defined.
decisions above their delegated authority        Note: the choice of solution might require
to the sponsoring body (see 4.4.6) or other      a discovery stage (agile) or number of
appropriate decision makers, in accordance       investigative stages to be undertaken and
with the governance framework (see 4.3).         the use of specialist techniques such as
                                                 opportunity framing. See 6.3 life cycle.
6.4.5 Initiating
Initiating ensures a programme or project is     6.4.6 Managing
set up, defined and planned, and that the        The programme or project manager
team is mobilised and understands the            (see 4.4.8) should ensure the appropriate
opportunity or need to be addressed.             team (including suppliers) and facilities
The senior responsible owner (see 4.4.7)         are in place.
shall confirm:                                   New tranches, stages or work should be
•   a real policy, opportunity or business       planned and reviewed prior to authorisation
    need is being addressed                      (see 6.3).

•   communicate the vision, objectives and       Work packages should be initiated and
    desired outcomes to key stakeholders,        monitored against the plan or product
    together with strategic assumptions          backlog, risks mitigated, issues addressed,
                                                 and changes controlled. Lessons should be
•   set criteria for measuring success           continually captured and managed (see 8.8).
The programme or project manager (see            Outputs should be developed ready for use
4.4.8) should mobilise the team and facilities   (see 8.3 to 8.6) and stakeholders’ views
required to undertake the work and define        should continue to be addressed ensuring
the governance and management                    business changes and new ways of working
framework to be used (see 6.2).                  are being embedded, such that the desired
The team should understand the                   outcomes can be achieved (see 8.7).
requirements, assumptions, constraints and       Commercial and financial aspects should
risk potential, and should investigate           be addressed (see 7.10 and 7.11).
different solutions, delivery approaches and
implementation options for meeting the           The continuing justification for the
opportunity or need (see 8.4 and 8.7).           programme or project shall be monitored
Options shall be assessed in accordance          and business case updated, if appropriate
with GovS 010, Analysis.                         (see 4.3) in a controlled way (see 7.7).

A delivery strategy and plan for the work        6.4.7 Managing a work package
shall be developed, including approaches to      Managing a work package ensures the
be used for specialist work, taking into         deliverables within the scope of a project or
account lessons learned from previous,           other related work (see 3) are defined and
relevant work (see 7.2 and 8.8). The initial     delivered, in order that the outcomes can
justification for the programme or project       be achieved, and benefits realised:
shall be documented in a strategic outline
case (or equivalent).                            •   work should be defined, planned and
                                                     controlled in work packages or sprints
                                                     (see 7)

                                                                                              25
Government Functional Standard

•   goods and services should be procured         The programme or project manager, with
    and their delivery managed (see 7.11)         the team and key stakeholders, shall
•   stakeholders’ views should be sought,         undertake a closure review, which should
    validated and addressed (see 7.12)            include an assessment of performance
                                                  against the plan and the extent to which
•   outputs should be developed using             objectives are being met.
    methodologies and techniques which
    are proportionate and appropriate, and        New lessons should be captured and
    the quality verified and outcomes should      analysed together with those identified
    be validated against the requirements         during the work, significant learnings
    (see 8.6)                                     should be captured and shared (see 8.8).

•   lessons should be continually captured        Plans for post-closure reviews should be
    and managed (see 8.8)                         agreed by the senior responsible owner
                                                  (see 4.4.7).
Note: Annex C includes a role description for
                                                  Stakeholders shall be informed about
a person who manages a work package.
                                                  closure.
6.4.8 Closing
                                                  6.4.9 Reviewing outcomes
A programme or project shall be closed in a
controlled way. Closure can happen when           Reviewing outcomes determines the degree
the scope is completed or when work is            of the programme’s or project’s success.
terminated prematurely:                           The sponsoring body should ensure a
                                                  review is undertaken to assess the extent to
•   delivery of outputs and achievement of        which benefits realisation and operational
    outcomes to date should be confirmed          performance are meeting, and are likely to
•   unfulfilled requirements should be            continue to meet, the objectives and
    documented together with how they are         expectations stated in the business case.
    to be addressed                               Lessons should be captured and
                                                  communicated.
•   responsibilities for ongoing risks, issues,
    actions and benefit tracking should be
    handed over to, and accepted by, the
    appropriate business authority
•   documentation and information should
    be securely archived (see 7.9)
•   the team should be reassigned and any
    temporary facilities demobilised
•   contracts, financial and reporting
    systems reconciled and closed
Termination might occur because the work
is no longer needed or viable, or because
the risks associated with it have become
unacceptably high.

    26
You can also read