Exhibit D Revised Bid Form and Payment Items Specification (Section 01290) - Truro-ma.gov

Page created by Wallace Santos
 
CONTINUE READING
Exhibit D

                                                            Revised Bid Form and Payment Items
                                                                    Specification (Section 01290)

F:\P2011\0202\C50\Bidding\Addendum\nsw_drn_East Harbor Eagle Neck Draft Addendum_20210722_Rev20210802.docx
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

SECTION 00411 - BID FORM

CONTRACT IDENTIFICATION:

          Eagle Neck Creek Salt Marsh Restoration Project
          East Harbor Culvert Repair Project
          Truro, MA

ARTICLE 1 – BID RECIPIENT

1.1      This Bid shall be submitted to:

         Town Administrator
         Truro Town Hall
         24 Town Hall Road
         Truro, MA 02666

1.2      The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an
         Agreement with the Town of Truro in the form included in the Bidding Documents to
         perform all Work as specified or indicated in the Bidding Documents for the prices and
         within the times indicated in this Bid and in accordance with the other terms and
         conditions of the Bidding Documents.

ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS

2.1      Bidder accepts all of the terms and conditions of the Instructions to Bidders, including
         without limitation those dealing with the disposition of Bid security. This Bid will remain
         subject to acceptance for 60 calendar days after the Bid opening, or for such longer period
         of time that Bidder may agree to in writing upon request of the Town of Truro.

ARTICLE 3 – BIDDER’S REPRESENTATIONS

3.1      In submitting this Bid, Bidder represents that:

         A. Bidder has examined and carefully studied the Bidding Documents, the other related
              data identified in the Bidding Documents, and the following Addenda, receipt of
              which is hereby acknowledged.

                   Addendum No.                           Addendum Date

                   _____________                          _____________

                   _____________                          _____________

         B. Bidder attended the mandatory Pre-Bid Conference, has examined the Site and

BID FORM                                                                                                 00411 - 1
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

              become familiar with and is satisfied as to the general, local and Site conditions that
              may affect cost, progress, and performance of the Work.

         C. Bidder is familiar with and is satisfied as to all federal, State and local Laws and
              Regulations that may affect cost, progress and performance of the Work.

         D. Bidder has carefully studied all:

              1. Reports of explorations and tests of subsurface conditions at or contiguous to the
                 Site and all drawings of physical conditions in or relating to existing surface
                 structures.

         E. Bidder does not consider that any further examinations, investigations, explorations,
              tests, studies, or data are necessary for the determination of this Bid for performance
              of the Work at the price(s) bid and within the times and in accordance with the other
              terms and conditions of the Bidding Documents.

         F. Bidder has correlated the information known to Bidder, information and observations
              obtained from visits to the Site, reports and drawings identified in the Bidding
              Documents, and all additional examinations, investigations, explorations, tests,
              studies, and data with the Bidding Documents.

         G. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or
              discrepancies that Bidder has discovered in the Bidding Documents, and the written
              resolution thereof by Engineer is acceptable to Bidder.

         H. The Bidding Documents are generally sufficient to indicate and convey understanding
              of all terms and conditions for the performance of the Work for which this Bid is
              submitted.

         I.   Bidder will submit written evidence of its authority to do business in the state where
              the Project is located not later than the date of its execution of the Agreement.

ARTICLE 4 – FURTHER REPRESENTATIONS

4.1      Bidder further represents that:

         A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed
              individual or entity and is not submitted in conformity with any agreement or rules of
              any group, association, organization or corporation;

         B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a
              false or sham Bid;

         C. Bidder has not solicited or induced any individual or entity to refrain from bidding;
              and

BID FORM                                                                                                 00411 - 2
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

         D. Bidder has not sought by collusion to obtain for itself any advantage over any other
              Bidder or over the Town of Truro.

ARTICLE 5 – BASIS OF BID

5.1      Bidder will complete the Work in accordance with the Contract Documents for the
         following lump sum and unit bid prices:

         A. The Total Contract Base Bid Price shall include, but not be limited to, construction of
              Eagle Neck Creek Salt Marsh Restoration Project which includes construction of the
              three-sided box culvert and associated site work and the East Harbor Culvert Repair
              which includes culvert repairs, concrete structure modifications and associated site
              work based on the following lump sum prices.

                       EAGLE NECK CREEK SALT MARSH RESTORATION
                               CONTRACT BASE BID ITEMS

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

ENC-1         MOBILIZATION/DEMOBILIZATION                                    LS               1
              AND GENERAL REQUIREMETS
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

ENC-2         SITE CLEARING AND DEMOLITION                                   LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

ENC-3         TEMPORARY TRAFFIC CONTROL AND                                  LS               1
              PROTECTION OF PUBLIC
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 3
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

ENC-4         TEMPORARY EROSION AND                                          LS               1
              SEDIMENTATION CONTROLS
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

ENC-5         CONTROL OF WATER                                               LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

ENC-6         TIMBER PILES                                                   LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

ENC-7         STEEL BEAM GUARDRAIL AND                                       LS               1
              BRIDGE RAIL TRANSITIONS
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars
              and                               Cents ($                 )

ENC-8         OLD COUNTY ROAD CULVERT                                        LS               1
              STRUCTURE
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 4
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

ENC-9         OLD COUNTY ROAD PAVEMENT                                       LS               1
              RECONSTRUCTION
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

ENC-10        OLD COUNTY ROAD STONE ARMOR                                    LS               1
              SLOPE AND CHANNEL PROTECTION
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

ENC-11        STORMWATER DRAINAGE                                            LS               1
              IMPROVEMENTS
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

ENC-12        TIDAL CHANNEL DREDGING                                         LS               1
              at the per Lump Sum Price of

                                                                Dollars
                                                                                                          $
              and                               Cents ($                 )

ENC-13        SALT MARSH RESTORATION                                         LS               1
              at the per Lump Sum Price of

                                                                Dollars
                                                                                                          $
              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 5
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

ENC-14        FORMER RAILROAD EMBANKMENT                                     LS               1
              BREACH EXCAVATION NAD NATIVE
              CHANNEL BED STABILIZATION
              at the per Lump Sum Price of                                                                $

                                                                Dollars

              and                               Cents ($                 )

ENC-15        FORMER RAILRAOD EMBANKMENT     LS                                               1
              BREACH SLOPE STONE ARMOR AND
              BIOENGINEERED SLOPE PROTECTION
              at the per Lump Sum Price of                                                                $

                                                                Dollars

              and                               Cents ($                 )

ENC-16        STICK BRIDGE ROAD                                              LS               1
              RECONSTRUCTION
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

ENC-17        NATURAL BOULDER WALL                                           LS               1
              CONSTRUCTION
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

ENC-18        OLD COUNTY AND STICK BRIDGE                                    LS               1
              ROADS STABILIZATION AND
              VEGETATIVE RESTORATION
              at the per Lump Sum Price of                                                                $

                                                                Dollars

              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 6
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

EAGLE NECK CREEK SALT MARSH RESTORATION CONTRACT BASE BID PRICE

For purposes of bid comparison, the Eagle Neck Creek Salt Marsh Restoration Contract Base Bid
Price shall be stated below as the direct sum of the items listed above.

$                                                                                       (Amount in Figures)

                                                                                        (Amount in Words)

                                    EAST HARBOR CULVERT REPAIR
                                      CONTRACT BASE BID ITEMS

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

EH-1          MOBILIZATION/DEMOBILIZATION                                    LS               1
              AND GENERAL REQUIREMENTS
              (shall not exceed 5% of the total base bid)
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

EH-2          TRAFFIC CONTROL AND PROTECTION                                 LS               1
              OF PUBLIC
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

EH-3          TEMPORARY EROSION AND                                          LS               1
              SEDIMENTATION CONTROL
              at the per Lump Sum Price of
                                                                                                          $
                                                                Dollars

              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 7
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

EH-4          CONTROL OF WATER                                               LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

EH-5          SELECTIVE DEMOLITION                                           LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

EH-6          PERMANENT STEEL SHEETING                                       LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

EH-7          EARTHWORK                                                      LS               1
              at the per Lump Sum Price of
                                                                Dollars                                   $

              and                               Cents ($                 )

EH-8          PRECAST CONCRETE CULVERT                                       LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

EH-9          CAST-IN-PLACE MARINE CONCRETE                                  LS               1
              at the per Lump Sum Price of

                                                                Dollars
                                                                                                          $
              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 8
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

                                                                                                              Computed
Item          ITEM AND UNIT PRICE                                                       Opinion of             Total in
 No.          (WORDS AND FIGURES)                                            Unit        Quantity              Figures

EH-10         TYPE ‘A’ CONCRETE REPAIR                                       SF              80
              at the per Unit Price of

                                                                Dollars
                                                                                                          $
              and                               Cents ($                 )

EH-11         TYPE ‘B’ CONCRETE REPAIR                                       SF              50
              at the per Unit Price of

                                                                Dollars
                                                                                                          $
              and                               Cents ($                 )

EH-12         TYPE ‘C’ CONCRETE REPAIR                                       CY              160
              at the per Unit Price of

                                                                Dollars
                                                                                                          $
              and                               Cents ($                 )

EH-13         TIMBER STOP LOGS, METAL                                        LS               1
              FABRICATIONS, GRATINGS AND
              ACCESS RUNGS
              at the per Lump Sum Price of                                                                $

                                                                Dollars

              and                               Cents ($                 )

EH-14         SITE RESTORATION                                               LS               1
              at the per Lump Sum Price of

                                                                Dollars                                   $

              and                               Cents ($                 )

BID FORM                                                                                                 00411 - 9
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

EAST HARBOR CULVERT REPAIR CONTRACT BASE BID PRICE

For purposes of bid comparison, the East Harbor Culvert Repair Contract Base Bid Price shall be
stated below as the direct sum of the items listed above.

$                                                                                       (Amount in Figures)

                                                                                        (Amount in Words)

TOTAL CONTRACT BASE BID PRICE

For purposes of bid comparison, the Total Contract Base Bid Price shall be stated below as the
direct sum of the Eagle Neck Creek Salt Marsh Restoration Contract Base Bid Price and East
Harbor Culvert Repair Contract Base Bid Price listed above.

$                                                                                       (Amount in Figures)

                                                                                        (Amount in Words)

         B. The following add/deduct bid prices for respective Eagle Neck Creek Salt Marsh
              Restoration Contract Base Bid Items listed above (i.e., AD-6A applies to Contract
              Base Bid Item 6, AD-10A applies to Contract Base Bid Item 12, AD-14A applies to
              Contract Base Bid Item 14, and AD-16A applies to Contract Base Bid Item 16).

              1. The estimated quantities stated below are included in the respective base bid
                 items.

              2. Payment under add/deduct bid items listed below would only be made for work
                 completed and accepted, in variance from the respective estimated quantities
                 stated below.
                       EAGLE NECK CREEK SALT MARSH RESTORATION
                                ADD/DEDUCT BID ITEMS

                                                                                               Opinion of
Add/                                                                                            Quantity          Computed
Deduct Item           ADD/DEDUCT BID                                                           in LS Bid           Total in
No.                   (WORDS AND FIGURES)                                           Unit          Item             Figures

ENC/AD-6A             TIMBER PILES                                                  LF              760
                      at the per Unit Price of

                                                                        Dollars
                                                                                                              $
                      and                              Cents ($                 )

BID FORM                                                                                               00411 - 10
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                              TRURO, MA
UPDATED 8/3/2021

                                                                                               Opinion of
Add/                                                                                            Quantity          Computed
Deduct Item           ADD/DEDUCT BID                                                           in LS Bid           Total in
No.                   (WORDS AND FIGURES)                                           Unit          Item             Figures

ENC/AD-12A TIDAL CHANNEL DREDGING                                                   CY              400
           at the per Unit Price of

                                                                        Dollars
                                                                                                              $
                      and                              Cents ($                 )

ENC/AD-14A DISPOSAL OF EXCESS FORMER                                                CY               50
           RAILROAD EMBANKMENT BREACH
           MATERIAL
           at the per Unit Price of
                                                                                                              $
                                                                        Dollars

                      and                              Cents ($                 )

ENC/AD-16A IMPORT ADDITIONAL STICK BRIDGE                                           CY              100
           ROAD FILL MATERIAL
           at the per Unit Price of

                                                                        Dollars                               $

                      and                              Cents ($                 )

         C. Alternate bid items have been computed in accordance with Paragraph 11.03.B of the
              General Conditions. The below East Harbor Culvert Repair Alternate Bid Items
              include all labor, materials, tools, equipment, overhead, profit, insurances, etc. to
              cover the finished work of the several kinds called for.

BID FORM                                                                                               00411 - 11
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

                                    EAST HARBOR CULVERT REPAIR
                                       ALTERNATE BID ITEMS

Alternate                   ALTERNATE BID ITEM AND PRICE                                         Alternate Bid
Bid Item                              (WORDS)                                                        Price
No.                                                                                                (Figures)

EH/ALT-1          TEMPORARY STEEL SHEETING
                  in lieu of East Harbor Culvert Repair Contract Base Bid
                  Item No. 7 at the Lump Sum Price of

                                                                    Dollars                      $

                  and                               Cents ($                )

ARTICLE 6 – TIME OF COMPLETION

6.1      Bidder agrees that the Work will be substantially complete within 260 calendar days after
         the date when the Contract Times commence to run as provided in Paragraph 2.03 of the
         General Conditions.

         A. Substantial completion for the Eagle Neck Creek Salt Marsh Restoration Project shall
              include, but not be limited to, construction of all structures and roadway, tidal channel
              and railroad embankment elements, including removal of all temporary cofferdam(s)
              and flow bypass conveyances resulting in restoration of normal and unimpeded flows
              through the proposed culvert structure as indicated on the Drawings.

         B. Substantial completion for the East Harbor Culvert Repair Project shall include, but
              not be limited to, construction of all structure repairs and culvert replacement,
              including removal of temporary upstream inflatable plug or bulkhead resulting in
              restoration of normal and unimpeded flows through the proposed replacement
              culvert as indicated on the Drawings.

6.2      Bidder agrees that work will be completed and ready for final payment in accordance with
         Paragraph 14.07.B of the General Conditions within 290 calendar days after the date
         when the Contract Times commence to run.

         A.        Bidder accepts the provisions of the Agreement as to liquidated damages in the
                   event of failure to complete the Work within the Contract Times.

BID FORM                                                                                               00411 - 12
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.1      The following completed documents are attached to and made a condition of this Bid:

         A. Required Bid security in the form of Bid Bond (00431).

         B. Certificate of Non-Collusion and Tax Compliance (00455).

         C. Qualifications of Bidder (00461).

ARTICLE 8 – DEFINED TERMS

8.1      The terms used in this Bid with initial capital letters have the meanings stated in the
         Instructions to Bidders, the General Conditions and the Supplementary Conditions.

ARTICLE 9 – BID SUBMITTAL

9.1      This Bid submitted by:

If Bidder is:
AN INDIVIDUAL
         Name (typed or printed):

         By:
                   (SEAL)
                                                  (Individual’s signature)
         Doing business as:

         Business address:

         Phone No.:                                                      FAX No.:

A PARTNERSHIP
         Partnership Name:
                (SEAL)

         By:
(Signature of general partner -- attach evidence of authority to sign)
         Name (typed or printed):

         Business address:

BID FORM                                                                                               00411 - 13
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

         Phone No.:                                                     FAX No.:

A CORPORATION
         Corporation Name:
               (SEAL)
         State of Incorporation:
         Type (General Business, Professional, Service, Limited Liability):__________________

         By:
                  (Signature -- attach evidence of authority to sign)
         Name (typed or printed):
         Title:
                                                                                                (CORPORATE SEAL)
         Attest
                  (Signature of Corporate Secretary)

         Business address:

         Phone No.:                                                     FAX No.:

         Date of Qualification to do business is                                                                    .

         A JOINT VENTURE

         Joint Venturer Name:

          (SEAL)

         By:
         (Signature of joint venture partner -- attach evidence of authority to sign)

         Name (typed or printed):

         Title:

         Business address:

         Phone No.:                                                     FAX No.:

BID FORM                                                                                               00411 - 14
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                        EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                             EAST HARBOR CULVERT REPAIR
20131222.A12                                                                                            TRURO, MA
UPDATED 8/3/2021

         Joint Venturer Name:
                (SEAL)

         By:
         (Signature -- attach evidence of authority to sign)

         Name (typed or printed):

         Title:

         Business address:

         Phone No.:                                                    FAX No.:

         Phone and FAX Number, and Address for receipt of official communications:

                    (Each joint venturer must sign. The manner of signing for each individual,
                    partnership, and corporation that is a party to the joint venture should be in the
                    manner indicated above.)

SUBMITTED on                              , 20  .
State Contractor License No. ___________________

BID FORM                                                                                               00411 - 15
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 0\00411 BID FORM_Combined
Projects_Rev20210723.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

SECTION 01205 – PAYMENT ITEMS

PART 1 - GENERAL

1.1        RELATED DOCUMENTS

      A.   Drawings and general provisions of the Contract, including General and Supplementary
           Conditions and other Division 1 Specification Sections, apply to this Section.

1.2        SUMMARY

      A.   This Section describes the measurement and payment for the Work to be completed under
           each item in the Bid Form. The descriptions may not reference all of the associated Work.
           Work specified but not designated as a separate Bid item is considered incidental to all Bid
           items. The Contractor shall review all work associated with each work item and shall have
           no claim for being unfamiliar with the requirements of these specifications.
           1.    All work items described herein, including in measurement and payment descriptions
                 or otherwise, do not state all requirement of the work stated in the Contract
                 Documents; all such descriptions shall be inclusive of all incidental work for
                 respective items, as stated in the Contract Documents.
           2.    This Section addresses general measurement and payment requirements for:
                 a.     Contract Base Bid items
                 b.     Add/Deduct Bid items
                 c.     Alternate Bid items
                 d.     Allowances

1.3        DEFINITIONS

      A.   Payment Items: the Contractor’s distribution of the Contract Sum through listed work
           items, as outlined in this Specification, reviewed, and accepted by the Engineer.
           1.    Each item is specified to include a defined scope of services. However, not all
                 materials, labor, equipment, or services of a payment item are guaranteed to be listed
                 or specified.
           2.    Include costs associated with items of work required to complete the defined scope
                 of services within the appropriately specified payment item.
           3.    Payment items include all necessary materials, plus cost for delivery, installation,
                 applicable fees and taxes, administrative over-site, tools, labor, incidentals, overhead,
                 and profit.

PAYMENT ITEMS                                                                                       01205 - 1
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

           4.    Alternate and field-directed bid items will only be incorporated into the project if
                 selected and authorized in writing by the Owner.
           5.    All work described in the Contract Documents shall be included in the payment
                 items described herein.

      B.   Unit Price: An amount proposed by bidders, stated on the Bid Form, as a price per unit of
           measurement for materials or services identified in the Contract Documents.

      C.   Alternate: An amount proposed by bidders, stated on Bid Form, as a price in lieu of a
           stated base bid item.

      D.   Lump Sum: When used as an item of payment, means complete payment for the work
           prescribed for that portion of the Work under the item, or all work prescribed in the
           Contract, as the case may be.
           1.    Lump sum payment items are groupings of the Work as determined by the Owner
                 only for the Owner’s convenience. Such listings of payment items shall establish the
                 minimum level of detail for the Schedule of Values.

      E.   Provide: Procure, fabricate, sample/test, deliver, place/install, adjust, correct and replace if
           needed all products or materials to be incorporated into all temporary and permanent
           elements of the Work in accordance with the Contract Documents.

      F.   Complete and In Place: When used in the measurement and payment provisions, means
           the completion of the contract item, including the fabrication, testing, reporting,
           furnishing, installation, adjustment and correction of all products and materials to be
           incorporated into the Work including all equipment, tools, labor, health and safety
           requirements, and work incidental thereto, in accordance with all provisions stated in the
           Contract Documents.

1.4        PROCEDURES

      A.   To ensure payment items are balanced, Mobilization/Demobilization and General
           Requirements for the base bid and alternate bids shall be limited to no more than five (5)
           percent of the total bid price for the base bid or alternative bid item, respectively. Such
           limit will not prohibit the Contractor from seeking payment for documented expenditures
           (i.e., invoices or cancelled checks) in excess of this amount under other bid items during
           project startup and mobilization.

      B.   Unit prices, lump sum items and alternate bid items include all necessary material, plus cost
           for delivery, installation, insurance, applicable taxes, overhead, and profit.

      C.   Measurement and Payment: Refer to the Sections 1.5 and 1.6 herein for methods of
           measurement and payment.

PAYMENT ITEMS                                                                                       01205 - 2
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

      D.   Notify Engineer at least 72-hours prior to the time at which necessary measurements must
           be taken. Notification must be in advance of obscuring pay item; do not proceed until
           such measurements have been taken in the presence of the Engineer.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1        LIST OF EAGLE NECK CREEK SALT MARSH RESTORATION CONTRACT
           BASE BID ITEMS

      A.   Bid Item No. ENC-1 – Mobilization/Demobilization and General Requirements
           1.    Work associated with this item will be paid for at the stated price including
                 respective portions of work under all specifications necessary to initiate, sustain and
                 conclude Contractor’s activities at the project site.
                 a.     All or portions of the Contract Requirements and Division 1 specifications, as
                        applicable.
                 b.     Includes, but is not limited to: All labor, equipment, tools, and materials
                        necessary to complete the work associated with the mobilization and
                        demobilization of temporary field offices and sheds, temporary utilities,
                        materials, personnel, and equipment to and from the project site. Also
                        includes restoring all incidental areas inside or outside the project limits
                        damaged by Contractor’s activities or traffic control to existing condition or
                        better including construction access ways (e.g., Abby Lane and temporary
                        staging and storage areas) and restoring and establishing a satisfactory stand of
                        vegetation in non-hardscape areas damaged by construction.
                        Mobilization shall be considered complete when the Contractor has
                        commenced the work on-site. Demobilization shall be considered to be
                        complete when the Contractor has achieved final completion of the work and
                        removed all equipment and materials from the site. Amount bid for this item
                        shall not exceed 5 percent (5%) of the Total Lump Sum Base Bid Price.
                 c.     This work also includes Contractor's general requirements for completing the
                        work, including insurance, bonds, administration and general requirements,
                        meeting, schedules, temporary facilities and temporary measures not specified
                        elsewhere and miscellaneous costs associated with the Work including
                        incidentals not covered by other payment items.
                 d.     Also includes other incidental items such as field and laboratory testing,
                        construction survey layout, and as-built mapping.
           2.    Measurement: As measured by the Contractor and accepted by the Engineer.
                 Contractor will be paid 50% upon completion of mobilization, 25% upon earning

PAYMENT ITEMS                                                                                       01205 - 3
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                 50% of the total base bid contract value, and the remaining 25% upon completion of
                 demobilization from the site.
          3.     Payment: Mobilization/Demobilization and General Requirements will be paid for
                 on a Lump Sum basis, as stated on the Bid Form, complete and in place.

   B.     Bid Item No. ENC-2 – Site Clearing and Demolition
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02199            Water Control
                 c.     Section 02230            Site Clearing
                 d.     Section 02265            Excavation Support and Protection
                 e.     Section 02300            Earthwork
                 f.     Section 02925            Site Restoration
                 g.     Includes, but is not limited to: Demolition; handling, transport and disposal;
                        clearing and grubbing; pavement saw cutting; pavement micro milling; removal
                        and disposal of existing culverts, pavement, concrete block and concrete wall
                        at former railroad embankment breach area, and other structures within areas
                        of work that will conflict with construction; removing, stockpiling, and
                        resetting or disposing existing steel guardrail and posts as indicated on
                        Contract Drawings; removing and stockpiling for re-use existing stone armor
                        slope protection and native channel bed material within the area of the Old
                        County Road and former railroad berm embankments; excavating, grading,
                        and compacting subgrade required for installation of Old County Road culvert
                        and footings; excavating, removing, and disposing existing catch basins and
                        associated storm drain piping; protecting existing structures and vegetation to
                        remain; clearing shrubs and other vegetation as required for completion of the
                        work; and stripping, screening and stockpiling topsoil where such materials are
                        to be proposed for reuse on completed areas where depicted on the Contract
                        Drawings and as directed by the Engineer. Includes protecting features to
                        remain within and adjacent to work areas and repairing any damage to such
                        features resulting from the Contractor’s operations.
          2.     Measurement: As measured by the Contractor and accepted by the, pro-rated with
                 the Contractor’s progress of work in clearing areas and removing structures required
                 for completion of work.
          3.     Payment: Site Clearing and Demolition will be paid for on a Lump Sum Basis, as
                 stated on the Bid Form, removed and disposed of off-site, complete and in place.

   C.     Bid Price Item No. ENC-3 –Temporary Traffic Control and Protection of Public

PAYMENT ITEMS                                                                                       01205 - 4
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All portions of Division 1 specifications, as applicable.
                 b.     Section 01555            Traffic Control
                 c.     Includes, but is not limited to: Installation, maintenance and removal of all
                        temporary markings, barricades, signs, cones, lights and other products and
                        materials required for the control and protection of the traveling public and
                        working personnel during construction and maintenance including the
                        protection and control of vehicular, pedestrian, and recreational boating traffic
                        to public and private properties within and abutting the project site and
                        adjacent areas. Any traffic control devices which are lost, stolen, destroyed or
                        deemed unacceptable while in use shall be replaced without additional
                        compensation.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in completing respective items
                 requiring Temporary Traffic Control and Protection of the Public.
          3.     Payment: Temporary Traffic Control and Protection of the Public will be paid for
                 on a Lump Sum Basis, as stated on the Bid Form, for all material, labor and
                 equipment required or incidental to the satisfactory furnishing, installation, and
                 removal as described in the Contract Documents.

   D.     Bid Item No. ENC-4 – Temporary Erosion and Sedimentation Controls
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable, including:
                        Section 01572 Temporary Erosion and Sedimentation Control
                 b.     Section 02300            Earthwork
                 c.     Section 02925            Site Restoration
                 d.     Includes, but is not limited to: Installing, maintaining and removing all
                        temporary erosion and sedimentation control measures and practices for
                        completion of all work associated with the project. Includes removing and
                        disposing of all accumulated sediment off site and establishing temporary
                        vegetation in areas to remain dormant for extended periods as indicated on the
                        Contract Drawings.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in providing, maintaining, removing,
                 disposing and restoring all temporary and erosion control measures and practices
                 required for completion of work.

PAYMENT ITEMS                                                                                       01205 - 5
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

          3.     Payment: Temporary Erosion and Sedimentation Controls will be paid for on a
                 Lump Sum Basis, as stated on the Bid Form, complete and in place.

   E.     Bid Item No. ENC-5 – Control of Water
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02199            Control of Water
                 c.     Section 02240            Subsurface Dewatering
                 d.     Control of surface water and groundwater within respective project work areas
                        as work progress within the site, and protection of adjacent properties from
                        discharged/diverted waters.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: Control of Water will be paid for on a Lump Sum Basis, as stated on the
                 Bid Form, complete and in place. This includes preparation of a signed and stamped
                 Water Control Plan prior to construction.

   F.     Bid Item No. ENC-6 – Timber Piles
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02300            Earthwork
                 c.     Section 02459            Timber Piles
                 d.     Includes, but is not limited to: Installing timber piles as shown on the
                        Contract Drawings.
          2.     Measurement: The quantity of timber piles provided will be determined by
                 measurements completed per Add/Deduct Bid Item No. ALT-6A.
          3.     Payment: Timber Piles will be paid as piles are provided as shown on the Contract
                 Drawings and as stated on the Bid Form, complete and in place.
                 a.     The lump sum price, which is based on the stated estimated quantity of timber
                        piles provided, shall be adjusted per the actual linear footage of timber piles
                        provided and accepted by the Engineer per Add/Deduct Bid Item No. ALT-
                        6A. The price so-stated constitutes full and complete compensation for all
                        products, materials, equipment, tools labor, overhead and profit, and
                        incidentals required to finish the work and accepted by the Engineer.

PAYMENT ITEMS                                                                                       01205 - 6
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

   G.     Bid Item No. ENC-7 – Steel Beam Guardrail and Bridge Rail Transition
          1.      Work associated with this item will be paid for at the stated price including, but not
                  limited to, work under the following:
                  a.    All or portions of Division 1 specifications, as applicable.
                  b.    Section 02845            Guardrail
                  c.    Includes, but is not limited to: Installing highway guardrail and bridge
                        transition guardrail as shown on the Contract Drawings.
          2.      Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                  rated with the Contractor’s progress of work in constructing respective items
                  associated with this bid price item.
          3.      Payment: Guardrails will be paid for on a Lump Sum Basis, as stated on the Bid
                  Form, complete and in place. Lump sum price shall include materials, equipment,
                  and labor necessary to assemble and erect all guardrail and bridge transition guardrail
                  components (including but not limited to posts, offset blocks, panels and connecting
                  hardware) in addition to connections to existing guardrail and concrete flared end
                  transitions. The use of special post designs, where necessary or directed by the
                  Engineer, shall be incidental to the work with no additional compensation.

   H.          Bid Item No. ENC-8 – Old County Road Culvert Structure
          1.      Work associated with this item will be paid for at the stated price including, but not
                  limited to, work under the following:
                  a.    All or portions of Division 1 specifications, as applicable.
                  b.    Section 02300            Earthwork
                  c.    Section 03300            Cast-in-Place Concrete
                  d.    Section 03600            Grout
                  e.    Section 03412            Precast Concrete Culvert Structure
                  f.    Section 07115            Bituminous Damproofing
                  g.    Includes, but is not limited to: Furnishing, installing, and compacting backfill
                        from the bottom of excavation up to the bottom of the base of the
                        reconstructed roadway; furnishing, handling, and installing precast concrete
                        three-sided culvert and its associated cast-in-place footings, approach slabs,
                        wingwalls, and wingwall footings; furnishing, handling, and installing precast
                        concrete flared end transitions, CT-TL2 barriers, and associated components;
                        and furnishing and installing sediment-filled stone armor channel/scour
                        protection within limits of culvert along with associated non-woven geotextile
                        fabric and bedding layer. Also includes excavating test pits as directed by the
                        Engineer within the footprint of the proposed culvert to investigate the
                        presence of potentially unsuitable river channel bed material. An allowance

PAYMENT ITEMS                                                                                       01205 - 7
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                        required under the project has been identified under the Division 1 Section
                        “Allowances.” The amount and provisions of the stated allowance shall be
                        included under this bid item.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: Old County Road Culvert Structure will be paid for on a Lump Sum
                 Basis, as stated on the Bid Form, complete and in place.

   I.     Bid Item No. ENC-9 – Old County Road Pavement Reconstruction
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02240            Formation of Subgrade
                 c.     Section 02300            Earthwork
                 d.     Section 02741            Bituminous Concrete Paving
                 e.     Section 02740            Pavement Markings
                 f.     Includes, but is not limited to: All pavement reconstruction paving operations
                        (including full-depth pavement reconstruction and micro-milling and installing
                        overlay) and pavement striping; furnishing, installing, and compacting roadway
                        base material; furnishing and installing bituminous roadway berms; and all
                        other incidental work (e.g. joint sealants, tack coats, etc.) as described in the
                        Contract Drawings.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: – Old County Road Pavement Reconstruction will be paid for on a Lump
                 Sum Basis, as stated on the Bid Form, complete and in place.

   J.     Bid Item No. ENC-10 – Old County Road Stone Armor Slope and Channel Protection
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02300            Earthwork
                 c.     Section 02381            Stone Armor Slope and Scour Protection
                 d.     Includes, but is not limited to: Furnishing and/or installing stockpiled or
                        imported stone armor slope, embankment edge, and channel protection along

PAYMENT ITEMS                                                                                       01205 - 8
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                        and adjacent to Old County Road embankment slopes along with associated
                        non-woven geotextile fabric and bedding layer materials. Also includes
                        furnishing and/or installing native channel bed material, topsoil, and gravel
                        borrow to void spaces as specified and depicted on the Contract Drawings and
                        as directed by the Engineer.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: Old County Road Stone Armor Slope Protection and Native Channel Bed
                 Material will be paid for on a Lump Sum Basis, as stated on the Bid Form, complete
                 and in place.

   K.     Bid Item No. ENC-11 – Stormwater Drainage Improvements
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02199            Control of Water
                 c.     Section 02240            Subsurface Dewatering
                 d.     Section 02260            Formation of Subgrade
                 e.     Section 02265            Excavation Support and Protection
                 f.     Section 02300            Excavation
                 g.     Section 02630            Storm Drainage
                 h.     Includes, but is not limited to: Furnishing and installing new catch basins
                        (with hoods), oil/grit stormwater treatment structures, subsurface infiltration
                        systems, and storm drain piping; backfilling, fine grading, and compacting; and
                        connecting existing outfall pipes to oil/grit stormwater treatment structures as
                        indicated on the Contract Drawings. Includes all labor, materials, excavation,
                        equipment and all other incidentals required to complete this work.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: Stormwater Drainage Improvements will be paid for on a Lump Sum
                 Basis, as stated on the Bid Form, complete and in place.

   L.     Bid Item No. ENC-12 – Tidal Channel Dredging
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.

PAYMENT ITEMS                                                                                       01205 - 9
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                 b.     Section 02325       Dredging
                 c.     Includes, but is not limited to: Preliminary and final surveys of dredging areas;
                        dredging, transportation, and stockpiling of dredge material within areas of salt
                        marsh restoration/beneficial re-use as indicated on the Contract Drawings and
                        as directed by the engineer. Includes all labor, materials, equipment, survey and
                        positioning, tools, and all other incidentals required to complete the work.
          2.     Measurement: The quantity of material dredged and placed of will be determined by
                 measurements completed per Add/Deduct Bid Item No. ALT-12A.
          3.     Payment: Tidal Channel Dredging will be paid as dredging is completed to the limits
                 shown on the Contract Drawings for the channel dredging area and discharged in
                 the salt marsh restoration/beneficial re-use areas, as stated on the Bid Form,
                 complete and in place.
                 a.     The lump sum price, which is based on the stated estimated quantity of
                        dredging, shall be adjusted up or down per the actual cubic yards of tidal
                        channel material dredged and accepted by the Engineer per Add/Deduct Bid
                        Item No. ALT-12A. The price so-stated constitutes full and complete
                        compensation for all products, materials, equipment, tools labor, overhead and
                        profit, and incidentals required to finish the work and accepted by the
                        Engineer.

   M.     Bid Item No. ENC-13 – Salt Marsh Restoration
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02300            Earthwork
                 c.     Section 02925            Site Restoration
                 d.     Includes, but is not limited to: Placing, compacting, and grading dredged
                        material from tidal channel dredging operations for the purpose of
                        constructing the salt marsh restoration areas; furnishing and installing coir
                        fiber rolls around perimeter of restoration areas and coir matting and erosion
                        control blanketing for stabilization; furnishing and installing goose exclusion
                        fencing and stakes; furnishing and installing bioengineered slope protection
                        and erosion control blanketing along upper slope at former railroad
                        embankment breach area; and restoring areas with vegetation and plantings as
                        depicted on the Contract Drawings and as directed by the Engineer. Includes
                        all labor, materials, equipment and all other incidentals required to complete
                        this work.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.

PAYMENT ITEMS                                                                                       01205 - 10
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

          3.     Payment: Salt Marsh Restoration will be paid for on a Lump Sum Basis, as stated on
                 the Bid Form, complete and in place.

   N.     Bid Item No. ENC-14 – Former Railroad Embankment Breach Excavation and Native
          Channel Bed Stabilization
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02300            Earthwork
                 c.     Section 02485            Stone Armor Slope and Scour Protection
                 d.     Includes, but is not limited to: Removing and stockpiling for re-use existing
                        stone armor slope protection and native channel bed material from within the
                        former railroad embankment breach area; removing gravel from former
                        railroad embankment and hauling/transporting to and stockpiling at Stick
                        Bridge Road for re-use (if suitable) or hauling off-site for disposal (if not
                        determined suitable); and grading existing channel bed and railroad breach
                        slopes and re-installing stockpiled native channel bed material in channel
                        bottom and channel bench to elevations and dimensions shown on the
                        Contract Drawings and as directed by the Engineer.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item. The quantity of material handled, loaded,
                 transported and disposed off-site will be determined by measurements completed
                 per Add/Deduct Bid Item No. ALT-14A.
          3.     Payment: Former Railroad Embankment Breach Excavation and Native Channel
                 Bed Stabilization will be paid as work is completed to the limits shown on the
                 Contract Drawings and as stated on the Bid Form, complete and in place.
                 a.     The lump sum price, which is based on the stated estimated quantity of
                        material handled, loaded, transported and disposed off-site, shall be adjusted
                        up or down per the actual volume of material handled, loaded, transported and
                        disposed off-site and accepted by the Engineer per Add/Deduct Bid Item
                        No. ALT-14A. The price so-stated constitutes full and complete
                        compensation for all products, materials, equipment, tools labor, overhead and
                        profit, and incidentals required to finish the work and accepted by the
                        Engineer.

   O.     Bid Item No. ENC-15 – Former Railroad Embankment Breach Slope Stone Armor and
          Bioengineered Slope Protection
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:

PAYMENT ITEMS                                                                                       01205 - 11
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02300            Earthwork
                 c.     Section 02485            Stone Armor Slope and Scour Protection
                 d.     Section 02925            Site Restoration
                 e.     Includes, but is not limited to: Installing stone slope protection (and filling
                        voids with native channel bed material); installing bioengineered slope
                        protection measures (erosion control blanketing, lockdown netting, native or
                        engineered wetland soil, wattles, etc.); and restoring areas with vegetation and
                        plantings as depicted on the Contract Drawings and as directed by the
                        Engineer. Includes all labor, materials, equipment and all other incidentals
                        required to complete this work.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: Former Railroad Embankment Breach Slope Stone Armor and
                 Bioengineered Slope Protection will be paid for on a Lump Sum Basis, as stated on
                 the Bid Form, complete and in place.

   P.     Bid Item No. ENC-16 – Stick Bridge Road Reconstruction
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02260            Formation of Subgrade
                 c.     Section 02300            Earthwork
                 d.     Includes, but is not limited to: Fine grading, compacting, and preparing
                        subgrade for backfill and gravel driveway; installing geotextile filter fabric;
                        installing, grading and compacting excavated suitable material from former
                        railroad embankment breach area and/or imported gravel borrow and surface
                        gravel as depicted on the Contract Drawings and as directed by the Engineer.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item. The quantity of material furnished and placed
                 from off-site will be determined by measurements completed per Add/Deduct Bid
                 Item No. ALT-16A.
          3.     Payment: Stick Bridge Road Reconstruction will be paid as work is completed to the
                 limits shown on the Contract Drawings and as stated on the Bid Form, complete and
                 in place.

PAYMENT ITEMS                                                                                       01205 - 12
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                 a.     The lump sum price, which is based on the stated estimated quantity of
                        material furnished and placed from off-site, shall be adjusted up or down per
                        the actual volume of material transported from off-site, placed and accepted by
                        the Engineer per Add/Deduct Bid Item No. ALT-16A. The price so-stated
                        constitutes full and complete compensation for all products, materials,
                        equipment, tools labor, overhead and profit, and incidentals required to finish
                        the work and accepted by the Engineer

   Q.      Bid Item No. ENC-17 – Natural Boulder Wall Construction
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02300            Earthwork
                 c.     Includes, but is not limited to: Installing natural boulder wall along southern
                        edge of Stick Bridge Road as depicted on the Contract Drawings and as
                        directed by the Engineer. Also includes restoring disturbed areas along base of
                        wall with loam and seed as indicated on the Contract Drawings.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.
          3.     Payment: Natural Boulder Wall Placement will be paid for on a Lump Sum Basis, as
                 stated on the Bid Form, complete and in place.

   R.     Bid Item No. ENC-18 – Old County and Stick Bridge Roads Stabilization and Vegetative
          Restoration
          1.     Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable.
                 b.     Section 02925            Site Restoration
                 c.     Includes, but is not limited to: Restoring non-paved or non-gravel roadway
                        shoulder and adjacent sloped areas along Old County and Stick Bridge Roads
                        with loam and seed; installing soil-filled stone slope and embankment scour
                        and edge protection along Old County Road embankment slopes; and
                        installing embankment slope restoration and salt marsh restoration plantings
                        and vegetation as indicated on the Contract Drawings.
          2.     Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in constructing respective items
                 associated with this bid price item.

PAYMENT ITEMS                                                                                       01205 - 13
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

           3.    Payment: Old County and Stick Bridge Roads Stabilization and Vegetative
                 Restoration will be paid for on a Lump Sum Basis, as stated on the Bid Form,
                 complete and in place.

3.2        LIST OF EAST HARBOR CULVERT REPAIR CONTRACT BASE BID ITEMS

      A.   Bid Item No. EH-1 – Mobilization/Demobilization and General Requirements
           1.    Work associated with this item will be paid for at the stated price including
                 respective portions of work under all specifications necessary to initiate, sustain and
                 conclude Contractor’s activities at the project site.
                 a.     All or portions of the Contract Requirements and Division 1 specifications, as
                        applicable.
                 b.     Includes, but is not limited to: All labor, equipment, tools, and materials
                        necessary to complete the work associated with the mobilization and
                        demobilization, materials, personnel, and equipment to and from the project
                        site. Mobilization shall be considered complete when the Contractor has
                        commenced the work on-site. Demobilization shall be considered to be
                        complete when the Contractor has achieved final completion of the work and
                        removed all equipment and materials from the site.
                 c.     This work also includes Contractor's general requirements for completing the
                        work, including insurance, bonds, administration and general requirements,
                        meeting, schedules, temporary facilities and temporary measures not specified
                        elsewhere and miscellaneous costs associated with the Work including
                        incidentals not covered by other payment items.
                 d.     Also includes other incidental items such as field and laboratory testing,
                        construction survey layout, and as-built mapping.
           2.    Measurement: As measured by the Contractor and accepted by the Engineer.
                 Contractor will be paid 50% upon completion of mobilization, 25% upon earning
                 50% of the total base bid contract value, and the remaining 25% upon completion of
                 demobilization from the site.
           3.    Payment: Mobilization and Demobilization and General Requirements will be paid
                 for on a Lump Sum basis, complete and in place.

      B.   Bid Item No. EH-2 – Traffic Control and Protection of Public
           1.    The Town will provide a police detail if needed for deployment/retrieval of traffic
                 controls for Rt. 6 shoulder closures.
           2.    Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable

PAYMENT ITEMS                                                                                       01205 - 14
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
FUSS & O’NEILL, INC.                          EAGLE NECK CREEK SALT MARSH RESTORATION
20110202.C50                                               EAST HARBOR CULVERT REPAIR
20131222.A12                                                                 TRURO, MA
UPDATED 8/3/2021

                 b.     Section 01555 – Traffic Control
                 c.     Includes, but is not limited to: Installation, maintenance and removal of all
                        temporary markings, barricades, signs, cones, lights and other products and
                        materials required for control of vehicular and pedestrian traffic to public and
                        private properties within and abutting the project site and adjacent areas
           3.    Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in establishing, maintaining, and
                 removing temporary public protection measures.
           4.    Payment: Traffic Control and Protection of Public will be paid for on a Lump Sum
                 Basis, complete and in place.

   C.     Bid Item No. EH-3 – Temporary Erosion and Sedimentation Control
           1.    Work associated with this item will be paid for at the stated price including, but not
                 limited to, applicable portions of work under the following:
                 a.     All or portions of Division 1 specifications, as applicable
                 b.     Section 01572 – Temporary Erosion and Sedimentation Control
                 c.     Section 02300 – Earthwork
                 d.     Section 02925 – Site Restoration and Plantings
                 e.     Includes, but is not limited to: Installing, maintaining, removing and disposing
                        all temporary erosion and sedimentation control measures and practices for
                        completion of all work associated with the project. Includes removing and
                        disposing of all accumulated sediment off site and installing/maintaining
                        controls or establishing temporary vegetation in areas to remain dormant for
                        extended periods as indicated on the Contract Drawings.
           2.    Measurement: As measured by the Contractor and accepted by the Engineer, pro-
                 rated with the Contractor’s progress of work in providing, maintaining, removing
                 and disposing all temporary and erosion control measures and practices required for
                 completion of work.
           3.    Payment: Temporary Erosion and Sedimentation Control will be paid for on a Lump
                 Sum Basis, complete and in place.

   D.     Bid Item No. EH-4 – Control of Water
           1.    Work associated with this item will be paid for at the stated price including, but not
                 limited to, work under the following:
                 a.     All or portions of Division 1 specifications, as applicable
                 b.     Section 02199 – Control of Water
                 c.     Section 02240 – Subsurface Dewatering

PAYMENT ITEMS                                                                                       01205 - 15
F:\P2011\0202\C50\Deliverables\Bid & Construction Documents\Combined Projects\Div 1\01205 Payment
Items_Rev20210802.doc
You can also read