                                                                  Work Health and Safety Act 2011 (WHS Act) –
                                                      Work Health and Safety Regulation 2017 (WHS Regulation)

DEMOLITION LICENCE – APPLICATION
DEMOLITION – 01         MAY 2021

Complete this form to apply for a new licence for     Privacy compliance statement
demolition work under the WHS Regulation 2017.        Information that you voluntarily provide in this
Complete the Demolition supervisor nomination         form is collected by SafeWork NSW to assess and
– application (Demolition – 03) (catalogue no.        process your application.
SW08100) to add additional supervisors to your        SafeWork NSW intends to use and disclose the
licence application.                                  information (including any personal information)
How to fill in this form                              you have provided in the following ways:
Refer to the Guide for applicants for demolition      1. to exercise its functions under the Work Health
licences and notifications (catalogue no.                and Safety Act 2011, including to administer,
SW08018) when completing this application.               monitor and enforce compliance with that Act
Please type directly into the form. When complete,    2. to record your information on a licence register,
save a copy before emailing or printing.                 parts of which will be published online
If completing by hand, please print clearly and       3. to disclose your information to other state,
mark box(es) with a tick where required.                 territory and the Commonwealth regulatory
For assistance call 13 10 50                             authorities
                                                      4. to educate about work health and safety and
Fees
                                                         contribute to external research about work
Refer to the SafeWork NSW fee schedule available         health and safety
at www.safework.nsw.gov.au or call 13 10 50.
                                                      5. as otherwise required or permitted by law,
Lodgement instructions                                   including for prosecution.
Email: licensing@safework.nsw.gov.au                  SafeWork NSW has a Privacy Management Plan
Identity documents                                    which provides more detailed information about
Applicant will need to provide 1 photo                who SafeWork NSW is, how to contact SafeWork
identification and 1 secondary identification         NSW, and how SafeWork NSW manages personal
document and will need to complete facial             and health information in line with NSW privacy
verification at a Service NSW Centre.                 laws. A copy of the Privacy Management Plan is
Photo identification                                  available at www.safework.nsw.gov.au.
• Current Australian Driver’s licence / permit        The Privacy Management Plan provides detailed
                                                      information about how you may access or
• Passport – Australian or international (current
                                                      amend personal information held about you by
  or expired within the last two years but not
                                                      SafeWork NSW.
  cancelled)
• Photo Australian citizenship card
Secondary identification documents
• Birth certificate, citizenship certificate or
  passport (passport must be current or expired
  within the last two years, but not cancelled).
• Current Medicare card
• Property lease agreement
• Home insurance papers
• Utility bills issued in the last three (3) months
• Current motor vehicle registration
• Motor vehicle insurance papers
• Telephone account issued in the last
  three (3) months.

                                                                                                          1/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

SectIon 1. tYPe oF DemoLItIon
 Indicate the demolition licence for which you are seeking a licence. Mark one box only.

    Restricted demolition              Demolition

SectIon 1.1 aUtHoRISatIonS ReQUIReD FoR an UPGRaDe oF a ReStRIcteD DemoLItIon LIcence

 Mark the appropriate boxes.

    Demolition of chemical installations             Demolition of pre-tensioned or post-tensioned structures
    Demolition using a tower crane on site           Demolition above 15 metres in height
    Demolition using explosives                      Demolition involving floor propping
    Demolition using a mobile crane with a rated capacity of more than 100 tonnes

SectIon 2. aPPLIcant’S DetaILS
 Mark one box only.

    Individual           Corporation

SectIon 2.1 coRPoRatIon aPPLIcant DetaILS
Registered name                                          ABN

                                                         ACN
Registered business (trading) name (if applicable)

                                                         * The ABN or ACN must be attached to the legal
                                                           name entered above
STREET ADDRESS (MUST NOT BE A PO BOX)                    POSTAL ADDRESS         Same as street address
Unit number/Street number/Property number                Unit number/Street number/Property number
(include Lot or DP number if applicable)                 (include Lot or DP/PO Box/GPO Box/Private Bag/Locked Bag)

Street name                                              Street name

Suburb                                                   Suburb

State                            Postcode                State                         Postcode

 Ensure all fields are filled out accurately with current information pertaining to the business and
 nominated contact person.

                                                                                                               2/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

SectIon 2.2 InDIVIDUaL aPPLIcant DetaILS oR contact PeRSon FoR coRPoRatIon aPPLIcatIonS
Family/Surname                                Daytime contact number Mobile number

Given name                                               Email

Other names                                              Registered business (trading) name (if applicable)

Date of birth (DD/MM/YYYY)
                                                         ABN

SectIon 3. InSURance
 If you are an employer and not exempt under the Workers Compensation Act 1987 (WC Act) from
 holding a workers compensation insurance policy, you must supply a certificate of currency for workers
 compensation insurance with this application. Refer to the Guide for applicants for demolition licences
 and notifications (catalogue no. SW08018). You must also provide a certificate of currency for public
 liability insurance with ‘demolition’ listed as the business activity.

WORKERS COMPENSATION INSURANCE
    I am an exempt employer under the Workers Compensation Act 1987 OR

    I have attached a copy of the certificate of currency for workers compensation.
PUBLIC LIABILITY INSURANCE
   I have attached a copy of the public liability insurance certificate of currency with ‘demolition’ listed as
   the business activity.
SectIon 4. nomInateD SUPeRVISoR’S DetaILS
 Corporation applicants must nominate a person who is involved in the management of the corporation
 and who is qualified in the demolition work for which the licence is sought. This person is referred to as
 the management supervisor. Mark one box only.

    I am an individual applicant.
    I am involved in the management of the corporation. Please complete the following details:
Family/Surname                                           Date of birth (DD/MM/YYYY)

Given name                                               Daytime contact number        Mobile number

Other names                                              Email

SectIon 4.1 SUPeRVISoR’S DecLaRatIon (if supervisor is not the applicant)
I acknowledge and agree to be nominated as the management supervisor in this application OR with the
change in details as provided in this application OR to the removal of my name against the licence as
outlined in this application OR to be nominated as a supervisor for the additional demolition work outlined
in this application (delete whichever is not applicable).
Supervisor’s signature                                    Date (DD/MM/YYYY)

    The supervisor is no longer in my (licence holder’s) employment. This declaration does not require
    completion.

                                                                                                               3/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

SectIon 4.2 PoSItIon In tHe coRPoRatIon
Is the nominated supervisor a director or general manager (or equivalent) of the corporation?
    Yes.
    No. I have attached a letter from the director of the corporation, stating the supervisors role in the
        management of the corporation and authorising them to act as the management supervisor for
        the purpose of this licence.

SectIon 4.3 BUSIneSS aDDReSS (oF tHe manaGement SUPeRVISoR)
    Same as the corporation’s address.
Unit number/Street number/Property number
(include Lot or DP number if applicable)                   Suburb

Street name                                                State                         Postcode

SectIon 4.4 aDDItIonaL SUPeRVISoR(S)

 You must complete and attach the Demolition supervisor nomination – application (Demolition – 03)
 (catalogue no. SW08100) for each additional supervisor that you wish to nominate.

I am nominating additional supervisor(s):

    Yes, I have attached             (insert the number) demolition supervisor nomination forms.
    No

SectIon 5. QUaLIFIcatIonS (OF PRE APPROVED INDIVIDUAL APPLICANT OR
THE MANAGEMENT SUPERVISOR)
 Refer to the Guide for applicants for demolition licences and notifications (catalogue no. SW08018) for
 more details about the knowledge and experience required.

Have you previously been authorised to supervise demolition work on another NSW issued licence?
    Yes. Please indicate the type(s) of demolition work and the licence holder name and/or the licence
         number for whom you supervised work.

    No. Please go to section 6.

DEMOLITION
    Restricted demolition work
Licence number                             Licence holder name

    Demolition work
Licence number                             Licence holder name

DEMOLITION TYPES
    Demolition of chemical installations
Licence number                             Licence holder name

                                                                                                                 4/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

   Demolition of structures above 15 metres
Licence number                       Licence holder name

   Demolition using a tower crane
Licence number                       Licence holder name

   Demolition of pre or post tensioned structures
Licence number                       Licence holder name

   Demolition involving floor propping
Licence number                       Licence holder name

   Demolition using a mobile crane rated capacity more than 100 tonne
Licence number                       Licence holder name

   Demolition using explosives
Licence number                       Licence holder name

                                                                                                          5/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

SectIon 6. eVIDence oF IDentItY DecLaRatIon
Individual applicants and Directors of Corporations will need to provide copies of relevant training qualifications
and attend Service NSW office to complete facial verification and attach copies of 2 identity documents.
 Photo identification        Document
 Only use one document       Current Australian Driver’s licence / permit
                             Passport – Australian or international (current or expired within the last two years but
                             not cancelled)
                             Photo Australian citizenship card

 Secondary documents         Document
 1. Allowed to use a         Australian Birth Certificate / card issued by the Registrar of Births, Deaths and Marriages
    combination of
    secondary documents      Student card issued by a tertiary institution

 2. Documents provided       Utility bill in applicant’s name (e.g. council rates notice, water, power or phone account)
    must contain the
                             Medicare card
    participants full name
    (not initials)           Credit or debit card, passbook or account statement from a financial institution (only
                             one per financial institution can be counted)

 SeRVIce nSW USe onLY
  Document type                            Date of issue State of issue      Documentation number        Expiry date

 Name of Service NSW Checking Officer                         Service NSW disclaimer
                                                              • Service NSW is acting as an agent for the SafeWork
                                                                NSW to identify you under the requirements set out
 Location of Service NSW centre                                 by the NSW Explosives Act.
                                                              • Your application will be forwarded to SafeWork NSW
                                                                who will determine whether a licence will be granted.
 Signature                            Date (DD/MM/YYYY)       • SafeWork NSW is required, under the NSW
                                                                Explosives Act, to provide licensees with certain
                                                                information. This information will be sent to you when
                                                                and if your application is approved.
 Notes

SectIon 7. eVIDence oF eXPeRIence anD tRaInInG / QUaLIFIcatIonS
 Applicant’s trading under a business name who will be nominating supervisor(s) to carry work out on
 behalf of the licence holder, will not be required to meet the training or experience requirements.
 All individual applicants will be required to meet the training and experience requirements.
 All nominated Supervisors will be required to meet the training and experience requirements.

Evidence of experience must be completed as outlined in the experience table and attached to the
application form that outlines work undertaken. Evidence must include a detailed description of work
experience for at least three (3) demolition jobs within the last five years. Supporting documents may
include, but is not limited to, contracts demonstrating the engagement demolition work, work diaries or
logbooks for the work undertaken. This must include dates and locations of jobs, quantities removed, and
a description of each job. Reference letters must be provided from employers or organisation on company
letter head, dated and signed with referees that can be contacted to verify the work undertaken. Refer to the
Guide for Applicants for Demolition licences and notifications (catalogue no. SW08018) for more information

                                                                                                                        6/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

RESTRICTED
                                                                                 nominated
Date          Project name/location      Demolition work completed                                  Supporting documents
                                                                                 supervisor
• Date work   Demolition project name,   Experience must involve                 Provide            • Site Induction register
  completed   site details/ location/    undertaking work in one or a            details of the     • Demolition Work Plan
• Duration    quantities removed         combination of trades, where            nominated          • Asbestos clearance
  of job      Minimum of 3 examples      demolition work was undertaken.         supervisor that      certificate (if applicable)
              over a 3 year period.      Minimum 3 jobs over a 3 year period.    supervised this    • Traffic Management Plan
                                         • Demolition                            work (include      • SWMS – copy of the one used
                                         • Carpentry                             contact details)     on the site with signatures
                                         • Building                                                 • Risk register
                                         • General Construction                                     • Plant service report for
                                         • Civil Construction                                         all plant used during the
                                         • Excavation                                                 demolition
                                         • Other                                                    • Reference letter

UNRESTRICTED
                                                                                 nominated
Date          Project name/location      Demolition work completed                                  Supporting documents
                                                                                 supervisor
• Date work   Demolition project name,   Experience must include being           Where              • Site Induction register
  completed   site details/ location/    involved in the undertaking of all      applicable         • Demolition Work Plan
• Duration    quantities removed         the below demoliton types. Note:        provide            • Asbestos clearance
  of job      Minimum of 3 examples      A restricted demolition licence can     details of the       certificate (if applicable)
              over a 3 year period.      be granted with one or more of          nominated          • Dilapidation report
                                         the below restrictions lifted if not    supervisor that    • Traffic Management Plan
                                         involved in all the demolition types.   supervised this    • Engineers report /
                                         Minimum 3 jobs over a 3 year period.    work (include        investigation
                                         • Demoliton of a structure or plant     contact details)
                                                                                                    • SWMS – copy of the one
                                           over 15 metres in height                                   used on the site with
                                         • Demolition that involved a                                 signatures
                                           chemical installation                                    • Risk register
                                         • Demolition that involve a tower                          • Plant service report for
                                           crane/s                                                    all plant used during the
                                         • Demolition that involved a mobile                          demolition
                                           crane with a rated capacity of
                                           more than 100 tonnes
                                         • Demolition of structural
                                           components that were pre-
                                           tensioned or post-tensioned
                                         • Demolition that involved floor
                                           propping
                                         • Demolition that involved
                                           explosives
                                         • Other

                                                                                                                                    7/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

    I have attached written reference(s) to support the experience detailed above
    I have attached two safe work method statements, required for each demolition type nominated above
    I have attached photographs of the work undertaken, required for each demolition type nominated above
I, the undersigned, do solemnly and sincerely declare that the information contained on this form is true
and correct in every particular, to the best of my knowledge.
Individual applicant/management supervisor’s signature            Date (DD/MM/YYYY)

Attach copy of the certification issued to applicant for the specified VET course:
   CPCCDE4001A - Plan and prepare for activities on demolition sites

   CPCCBC4012B - Read and interpret plans and specifications

   CPCCDE3018A - Select and use small plant and equipment for demolition tasks. This unit has a
   prerequisite unit

   CPCCOHS2001A - Apply OHS requirements, policies and procedures in the construction industry

   CPCCDE3019A - Demolish small buildings and structure using hand tools and small plant equipment

   CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies

   CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry

   CPCCDE3022A - Manage demolition recyclable and waste materials using load shifting equipment

   CPCCDE4003A - Supervise individual activities on demolition sites

   CPCCDE4002A - Plan and supervise demolition work to minimise environmental and public health and
   safety impact

   CPCCBC4002A - Manage occupational health and safety in the building and construction workplace

   CPCCDE4004A - Finalise demolition activities and supervise property handover
    I have attached a copy of my certificate or transcript or statement of attainment

GENERAL CONSTRUCTION INDUCTION TRAINING
It is a requirement of the WHS Regulation that workers carrying on construction work must have a General
Construction Induction Training (GIT) card, or training certification pending the issue of a GIT card.
GIT card number for the nominated supervisor

If a GIT course was completed within the last 60 days, provide the Statement of Training number issued
by the registered training organisation

If issued outside NSW, provide the state or territory where issued (a copy of the front and back of the
interstate card must also be attached)

                                                                                                             8/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

CONSENT TO VALIDATE QUALIFICATION CERTIFICATES
Declaration

I,                                                                                             (print name)
hereby authorise (insert name(s) of educational provider who issued your training certificate)

To provide SafeWork NSW with any educational training records that relate to my application for a
demolition licence.
Signature                                                    Date (DD/MM/YYYY)

PRIVACY STATEMENT
This information is collected by SafeWork NSW for the purpose of verifying the training documents
supporting this application for a demolition licence. The information will not be accessed by any third
parties in a way that would identify you, unless the disclosure is required by law.
Please go to section 9.

SectIon 8. DIScLoSURe StatementS
For legal purposes, the term ‘you’ on this page means:
• the licence applicant
• (in the case of a corporation applicant) the corporation itself and each officer of the corporation.
Have you ever been convicted or found guilty of an offence under workplace health and safety (WHS) laws
in Australia?
    Yes. If yes provide details.      No

Have you ever provided a statement or information to SafeWork NSW knowing that the information was
false or misleading?
    Yes. If yes provide details.      No

Have you ever failed to comply with the conditions of a conditional asbestos or demolition licence?
    Yes. If yes provide details.      No

Have you been issued a significant number of notices for unsafe systems of work?
    Yes. If yes provide details.      No

Have you ever had an asbestos or demolition licence cancelled or suspended by SafeWork NSW?
    Yes. If yes provide details.      No

                                                                                                             9/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

SectIon 9. manaGement SUPeRVISoR’S DecLaRatIon
I acknowledge and agree to be nominated as the management supervisor in this application.
The information provided in this application is true and correct.
Management supervisor’s signature                        Date (DD/MM/YYYY)

SectIon 10. aPPLIcant’S DecLaRatIon

I,                                                                                             (print name)
hereby declare:
• the information supplied in this application is true and correct to the best of my knowledge
• I consent to SafeWork NSW making enquiries and exchanging information with work health and safety
  regulators in other states, territories, or the Commonwealth regarding any matter relevant to this
  application
• I consent to SafeWork NSW making enquiries and validating my qualifications with the educational
  provider who issued my qualification certificates
• I consent to SafeWork NSW contacting my referees to verify my evidence of experience
• the applicant does not hold an equivalent licence granted by a corresponding regulator under a
  corresponding work health and safety law.
• I have read the privacy compliance statement and consent to SafeWork NSW using my information
  (including personal information) as outlined in the statement.

SafeWork NSW compiles a public register of asbestos removal licence holders on the SafeWork NSW website.
Please mark the proposed region(s) you will operate in, as per the SafeWork NSW region map key below.
     A         B         C          D          E           F              G         H           I      J    K      L       M or     ALL

                                                                                             Tweed Heads

                                                                                 Casino      Lismore
                                                         Moree                  H        F
                              Bourke           Walgett           Inverell
                                                                                          Grafton
                                                                            Glen Innes
         J                          I                          Narrabri
                                                Coonamble            Armidale
                                                                 Tamworth
                                Cobar       Nyngan Coonabarabran
                                                                              G Kempsey
                 Wilcannia
                                                      Gilgandra                  Port Macquarie
     Broken Hill                                                      Taree
                                                   Dubbo      C
                                                            Maitland B      Newcastle
                                                      Orange              Toronto
         K                       L       Parkes                        Gosford
                                                       Bathurst
          Wentworth               Griffith               Lithgow
                                                                   A Sydney
                       Hay                                       E Wollongong
                           Narrandera           Yass Goulburn
                                         Wagga      D
                     Deniliquin          Wagga
                                  Finley Albury      Canberra
                                                       Cooma
                                                          M
                                                           Bega

Applicant’s signature                                                                     Date (DD/MM/YYYY)

Note: It is an offence to make a false or misleading statement in applications under clause 268 of the WHS Act.
The maximum penalty is $10,000.
Note: A Director must sign on behalf of a Corporation.

                                                                                                                                               10/11
DemoLItIon LIcence – aPPLIcatIon DemoLItIon – 01 maY 2021

SectIon 11. LoDGement FeeS
 A fee must be paid on lodgement of the application form.
 Refer to the SafeWork NSW fees schedule available at www.safework.nsw.gov.au.

Pay by credit card or PayPal using the following link:

www.safework.nsw.gov.au/applicationpayments
STEP 1 – Click on the link or type the URL into your web browser
STEP 2 – Follow the instructions online to complete payment
STEP 3 – When the lodgement fee is paid online you will receive a receipt number. Please record the
receipt number below before lodging the application; not providing this information may result in delays in
processing your application.
Receipt number

Note: If you are having difficulty lodging this payment online, please contact SafeWork NSW on 13 10 50.

SectIon 12. cHecKLISt to SUBmIt YoUR aPPLIcatIon
Attached     Document

             Copy of certificate of currency of workers compensation insurance. Applicants who are
             not exempt employers (please refer to the Guide for applicants for demolition licences and
             notifications (catalogue no. SW08018)) must attach a legible copy of the certificate of currency
             for workers compensation insurance to this application.
             Copy of certificate of currency for public liability insurance stating business activity as ‘demolition’.
             If the supervisor is not a director or general manager (or equivalent) of the corporation, a
             letter from the director of the corporation, stating the supervisors role in the management of
             the corporation and authorising them to act as the management supervisor for the purpose of
             this licence.
             Copy of the certificate or transcript or statement of attainment showing successful completion
             of SafeWork NSW recognised training course. (Only required if seeking authorisation for the
             first time).
             Copy of General Induction Training card (front and back) if issued outside NSW.
             Written references that support the description of the work undertaken. (Only required if
             seeking authorisation for the first time).
             Two safe work method statements. Required for upgraded restricted demolition and for
             demolition licence work for each demolition type outlined in section 2.1.
             Photographs of work undertaken. Required for upgraded restricted demolition and demolition
             licence work, for each demolition type outlined in section 2.1.
             To add additional supervisor(s) to a licence complete and submit the Demolition supervisor
             nomination – application (Demolition – 03) (catalogue no. SW08100) for each supervisor.

Catalogue No. SW08099   |   © Copyright SafeWork NSW 0521   |   Customer Experience 13 10 50   |   Website www.safework.nsw.gov.au