Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...

Page created by Sergio Conner
 
CONTINUE READING
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Current Status of Nuclear Power & Nuclear
           Safety in Bangladesh

19th Asian Nuclear Safety Network (ANSN) Steering
 Committee (SC) Meeting from 23 to 25 April 2014,
                 Da Lat, Vietnam.

              Md. Monzurul Haque
                     Chief Engineer and
                           Director
                     Engineering Division
            Bangladesh Atomic Energy Commission
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Outline
Bangladesh Overview
Introduction
Organization Chart of BAEC
Regulatory Infrastructure
International Legal Instruments adopted by
Bangladesh
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Outline
Present Power Situation
Current & Future Plans for NP
Development
Rooppur NPP Site Overview
Historical Background
Recent Progress
Structure of NEPIO
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Bangladesh: Overview
Area:                      147,570 sq. km.
Population:                160 million
GDP:                       1040 US$
GDP Growth:                6~6.5 %
Energy Consumption
– Total:                   230 kgOE
– Electricity:             320 kWh (approx.)
– Access to Electricity:   50% (approx.)
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Bangladesh: Overview
Political Map of Bangladesh with Neighboring Countries

                                              China

  Rooppur NPP site    Country without Nuclear Power      Country with Nuclear Power
                      Reactor                            Reactor
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Introduction

Bangladesh Atomic Energy Commission (BAEC) was
established in 1973 through promulgation of Presidential
Order 15. Main Functions of BAEC includes:

  Research and development in peaceful applications of atomic
  energy
                 TRIGA
  Generation of electricity
                 Reactor

  Promotion of international relations congenial to implementation
  of its programs and projects
  The program’s and projects of BAEC now focus on Health,
  Industries, Agriculture And Environment
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Organization Chart of
  Bangladesh Atomic Energy Commission (BAEC)

                            Ministry of Science and Information &
                                  Communication Technology

                                                        Chairman
                                                         BAEC                              COMMISSION

        Member                          Member                              Member                            Member
     (Physical Science)                (Bio Science)                      (Engineering)                      (Planning)

          NMCs               AECD                      NSRCD                    AERE                        Safety
        Directors           Director                   Director             Director General              Committees

                             HPD                                         ROMU               INST       IFRB          IFRB
                                                                                           Director   Director
                                                                                                                    Others
                                                                                                                    Director
                             Head                                        Director

                                                                  AERE
AERE : Atomic Energy Research Establishment                              RECD          HP&RWMU        RIPD          RPED
                                                                          Head           Head         Head          Head
ROMU : Reactor Operation & Maintenance Unit
NSRCD: Nuclear Safety & Radiation Control Division                                  RNPD                     Others
                                                                                    Head
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Government organization :

Bangladesh Atomic Energy Commission (BAEC) is
responsible for peaceful uses of nuclear energy in the
country.
 Primary Objectives of BAEC:
  Undertake fundamental research on various fields
  namely Physical, Biological and Engineering
              TRIGA
  sciences    Reactor

  Acquire and adopt related technology           like
  electronics, computer, material science etc.

  Render services to the end users.
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
Primary Objectives of BAEC:

Develop human resource for sustainable development of
nuclear technology.

Monitor and assess hazards of radiation and environmental
pollution.

Discharge international obligations in the field of atomic
Energy.
               TRIGA
               Reactor
Current Status of Nuclear Power & Nuclear Safety in Bangladesh - Asian Nuclear ...
R&D Establishment of BAEC

Atomic Energy Center, Dhaka.

Atomic Energy Research Establishment

National Institute of Nuclear Medicine & Allied Sciences
BSSMMU, Dhaka.
                 TRIGA
Fourteen Institute   of Nuclear Medicine & Allied Sciences
                Reactor
at different locations of the country.

Beach Sand Minerals Exploration Center

Radiation Testing and Monitoring Laboratory

Rooppur Nuclear Power Project
Manpower of BAEC

Scientist and Technologists       570

Scientific and Technical staff    650

Administration and Accounts and   1000
others
                 Total            2220
Nuclear infrastructures
– Promotional
– Regulatory
Promotional
Major infrastructures of BAEC:
1. 3 MW TRIGA Mark-II Research Reactor,
2. Reactor safety analysis laboratory,
3. Radioisotope production laboratory,
4. Tc- 99 M Kit Production Facility
5. 3 MeV Van De Graff accelerator facility,
6. 3 MeV TANDEM accelerator facility .
7. 350 kCi & 50 kCi Co-60 Gamma irradiators,
8. Analytical laboratories including Isotope Hydrology laboratory
9. Radioactive waste management facility,
10. SSDL facility
11. VLSI laboratory and
12. Several nuclear medicine facilities
13. Tissue banking facility, etc.
Regulatory>
REGULATORY INFRASTRUCTURE>:
The Nuclear Regulatory Body of Bangladesh

    A Authority called Bangladesh Atomic
    Energy Regulatory Authority (BAERA)
    is working effectively as the Secretariat
    for the Regulatory Body for performing
    all regulatory activities under the
    BAERA Act- 2012 .
    Chairman, BAERA is the head of the
    Regulatory Body.
The BAER Act-2012 has established the regulatory
provisions on safety & security of radioactive/nuclear
materials, nuclear safety, physical protection of nuclear
material and installation, safeguards and import & export
control, SSAC, transport and waste safety, transport of
radioactive/ nuclear materials, emergency preparedness
and response.

The issue of nuclear liability and coverage has been
covered in the draft in the light of Vienna Convention on
civil liability for nuclear damage.
Regulatory Authority under the BAER
                    Act 2012

An Act entitled “Bangladesh Atomic Energy Regulatory
Act-2012” has been drafted on the basis of IAEA
Handbook of Nuclear Law and existing NSRC Act-1993
with consultation of Russian Federation and IAEA.

30 May 2012 this act (Bangladesh Atomic Energy
Regulatory Act-2012) has been passed by the National
Parliament.

                                                       16
In parallel, work is being accomplished for the
development of necessary regulations for timely issuing
permits/licenses for the siting , design, construction,
export and import of goods and services required for the
supply of equipment, materials for the nuclear power
plant commissioning and operation.

Bangladesh is actively considering signing of bilateral
agreements with nuclear regulatory body of vendor
country and international body for joint analysis and
development of regulatory documents for implementation
of NPP in Bangladesh.

Continued IAEA help and cooperation will be needed in
this regard.
Some Key Elements of the BAER Act-2012

 Establishment of Independent Regulatory Body
 Authorization Process
 Radiation Protection
 Safety and Security of Radioactive Materials
 Nuclear Safety
 Physical Protection of Nuclear Material and Installation;
 Safeguards and Import and Export Control
 State System of Accounting for and Control of Nuclear
Material (SSAC)
 Transport and Waste Safety
 Emergency preparedness and Response
 Nuclear liability and coverage, etc.                        18
Division of Nuclear Safety, Security & Safeguards:

 Recently BAEC Created “Division of Nuclear Safety, Security &
         Safeguards” to conduct the following activities:

   Obligations under NPT & Non Proliferation Treaties including
   Establishment of State Systems of Accounting and Control
   (SSAC)
   Implementation & Enforcement of Safety, Security & Safeguards
   Legislations
   Relevant Safeguards Procedures
   Physical Security of Nuclear Materials

    In Addition, this Division will Look after all the conventions/
   Treaties, those already sign and take necessary steps to sign
   the conventions/treaties required for implementation of NPP
Safety Committees

BAEC TRIGA Research Reactor has following
important Safety Committees:

 AERE Radiation Safety & Control Committee.

AERE Nuclear Safety And Safeguards
 Committee .

AERE Research Reactor        Operation   and
Utilization Committee.
International Legal Instruments adopted by Bangladesh

IAEA Membership: 27 September 1972

       International Conventions/Legal               Date of         Opened for         Date of entry         Bangladesh's
                   Agreements                        adoption         Signature           into force         Entry into force

Joint Convention on the Safety of Spent Fuel
                                                    05 September
Management and on the Safety of Radioactive Waste                  29 September 1997     18 June 2001
                                                           1997
Management

Vienna Convention on Civil Liability for Nuclear
                                                    21 May 1963      21 May 1963       12 November 1977
Damage

                                                       8-12
Protocol to Amend the Vienna Convention on Civil
                                                     September     29 September 1997    4 October 2003
Liability for Nuclear Damage
                                                       1997

                                                     26 October
Convention on the Physical Protection of Nuclear
                                                         1979        3 March 1980       8 February 1987              10 June 2005
Material

Convention on Nuclear Safety                        17 June 1994   20 September 1994    24 October 1996               24 Oct 1996

                                                                                        Remain open for
Convention on Supplementary Compensation for        12 September                              signature
                                                                   29 September 1997
Nuclear Damage                                          1997                               until its entry
                                                                                             into force.
International Conventions/Legal                       Date of            Opened for           Date of entry      Bangladesh's
                 Agreements                                 adoption            Signature              into force    Entry into force

                                                                          26 September 1986 (at
Convention on Assistance in the Case of Nuclear       24-26 September
                                                                          Vienna)and 6 October    26 February 1987      7 Feb 1988
Accident or Radiological Emergency                          1986
                                                                          1986 (at New York)
Convention on Early Notification of a Nuclear                             26 September 1986 (at
                                                      24-26 September
                                                                          Vienna)and 6 October                          7 Feb 1988
                                                            1986                                  27 October 1986
Accident                                                                  1986 (at New York)

International convention for suppression of acts of                       14 September 2005 to                          7 July 2007
                                                      13 April 2005                                  7 July 2007
nuclear terrorism                                                         31 December 2006

                                                      21 September 1988
Joint Protocol Relating to the Application of the
                                                                                                    27 April 1992
Vienna Convention and the Paris Convention                                 21 September 1988

Revised Supplementary Agreement Concerning the
Provision of Technical Assistance by the IAEA
                                                                                                                     31 December 1979
(RSA)

Treaty on the Non-Proliferation of Nuclear Weapons
                                                      12 June 1968            01 July 1968          5 March 1970      31 August 1979
(NPT)

Comprehensive Nuclear-Test-Ban Treaty
                                                                                                  Not yet in force      8 Mar 2000
Safeguards Agreements                             Date of Signature   In force

Application of Safeguards in connection with the Treaty on the Non-
                                                                         1982-06-11       1982-06-11
Proliferation of Nuclear Weapons

Protocol Additional to the Agreement between the People's Republic       2001-03-30       2001-03-30
of Bangladesh and the IAEA for the Application of Safeguards in
Connection with the Treaty on the Non-Proliferation of Nuclear
Weapons

                                 Bilateral Cooperation

      Bangladesh signed agreements for bilateral cooperation in the
      field of nuclear science & technology with the USA, Russia,
      France and China.
The rising expectation of introduction of nuclear power
   is a reality for Bangladesh
 Bangladesh is committed for addition of 2000 MW(e) Nuclear
Capacity by 2021 (the Vision 2021; the Perspective Plan of
Bangladesh; the Revised National Energy Policy)

*Power System Master Plan 2010,
            BPDB                                         24
Initiatives for developing electric grid for introduction of RNPP
Project Name          Objective                   Project    Present Status
                                                Completion
Ishurdi-Rajshahi   230 To meet the growing 2012-13           DPP approved
kV Transmission Line. demand   of  Rajshahi
                       area.
Rooppur-Bheramara-    To evacuate the power to 2016-17       DPP       under
Zajira     400     kV be      generated     at               preparation.
transmission line.    upcoming     RNPP     at
                      Ishirdi

 Improvement of national grid system is essential to make it compatible
NPP

Steps have been taken for signing of an agreement between Russian
             Organization and PGCB/BPDB on Grid Study

                                                                         25
Bangladesh: Overview
Political Map of Bangladesh with Neighboring Countries

                                              China

  Rooppur NPP site    Country without Nuclear Power      Country with Nuclear Power
                      Reactor                            Reactor
Present Power Situation
                       Electricity Generation Scenario
  Electricity Generation Capacity: 8525 MW (December, 2012)
                                          Public Sector: 4794(56%)
                                          Private Sector: 3731(44%)

Fuel Type           Contribution
Natural Gas         67.21%
Furnace Oil         22.33 % Imported
Diesel              5.52 %
Hydro               2.58 %
Domestic Coal       2.35 %

  Max. Demand Served:                   6350 MW(August 04, 2012) 6080 MW(March15, 2013)
  (aged plants, poor capacity factor)
Current & Future plans for NP
              development
Policy Documents

 Perspective Plan of Bangladesh 2010~2021

Vision 2021:     -Digital Bangladesh
                 -Electricity for all

   Power system Master plan: 2010~2030
Vision: 2030; Long-term Power Development Strategy for Bangladesh

Generation Policy            2016       2020        2025      2030
Installed Capacity (MW)      14,493     22,509      29,717    38,685
Nuclear Power (MW)           0          2,000       4,000     4,000
Current & Future plans for NP development
                  Fuel Diversification

Fuel Type             2012               2030
Gas                  67.21%               25%
Oil                  22.33 %              5%
Domestic Coal         5.52 %              30%
Imported Coal         2.58 %              20%
Renewable +           2.35 %              10%
Cross Border
Nuclear                0%                 10%
Total Installed       8,525              38,685
Capacity (MW)
Rooppur NPP Site Overview (contd.)
Site Area: 261 acre + 300 acre up to river bank (acquire in process)
GPS Position: 24.06502, 89.045391
Rooppur NPP Site Overview (contd.)
Satellite picture of Site Area:

                       Flow direction of
                         Ganges River

                                                                   Highway &
                                                                    Railway
            Hardinge Bridge

                                                                     Proposed
             Lalon Shah Bridge                                      Power Plant
                                                                        Site
                        Intake point

                                       Left bank
                                        channel
                                                   Outfall point

                      Main channel
Rooppur NPP Site Overview (contd.)
                  Strategic Position of NPP

Establishment of Roopur NPP
will boost power generation as
well as industrialization in the
Western zone of Bangladesh.

          Nuclear Power Plant

          Cross Border Import

          Imported Coal Power Plant

                                      Source: Power System Master Plan
NATIONAL NUCLEAR POWER INFRASTRUCTURE
        Scope of Cooperation from National Stakeholders

  National Documents
1. Feasibility Reports on RNPP of 1977 – 78 and 1978 and   1987-
   1988;

2. Outcomes of the Pre-Project Activities of RNPP during 1999-
       2003;

3. Bangladesh Nuclear Power Action Plan, 2000 and

4. The lessons from the experiences and mistakes of the
      country’s nuclear power programme.

                                                               33
NATIONAL NUCLEAR POWER INFRASTRUCTURE
          Scope of Cooperation from IAEA

Key Reference Documents
    IAEA Milestones Document
    Evaluation Methodology Document
    Responsibilities and Capabilities of Owner/ Operator
  (NG-T-3.1)
    Draft on Invitation and Evaluation of Bids for Nuclear
  Power Plant
    Safety standards: GS-R part 1, GS-R3,
    Safety guides: SSG 16 and those relevant for Regulatory
  Framework

                                                              34
Present Power Situation (1/2)
Total Generation Capacity (Dec 2012): 8315 MW
    Public Sector : 4544 MW          Per capita electricity
    Private Sector : 3771 MW        consumption: 279 kWh

Generation Capacity by Fuel Type:
   Natural Gas     : 67.21%
   Furnace Oil     : 22.33%
   Diesel          : 05.52%
   Hydro           : 02.58%
   Coal            : 02.35%

Maximum Generation: 6314 MW (13 April 2013)

                                                              35
Present Power Situation (2/2)
Perspective Plan (OPP) of Bangladesh 2010 – 2021

VISION 2021: - Digital Bangladesh
                     - Electrification for all

Targets of Electricity Generation as per OPP 2010 – 2021:

By the year 2013 : 8,500 MW
By the year 2015 : 11,500 MW
By the year 2021 : 20,000 MW*
Addition of 2000 MW Nuclear capacity is a part of the ‘Vision 2021’ of
the Government of Bangladesh.

       *Projected Peak Demand for 2021 as per PSMP-2010: 18,838 MW

                                                                         36
Current & Future Plans for NPP Deployment
Power System Master Plan-2010 (PSMP – 2010) proposes
long-term fuel-mix as follows:
   Energy                    2010            2021 (20,000 MW)
   Gas                       87.50%          30%
                                                       This share is
   Oil                       06.00%          03%
                                                     about 28% now !!
   Coal                      03.70%          53%
   Hydro                     02.70%          01%
   Nuclear                   0%              10%
   Renewable                 00.50%          03%

  By 2021, the share of nuclear will be 10% of 20,000 MW = 2000 MW
(2X1000 MW) from the Rooppur NPP.
 PSMP-2010 also proposes addition of another 2000 MW from Rooppur
nuclear plant as follows:
           1000 MW by 2025
           1000 MW by 2030                                              37
Historical Background
1961-70
 Nuclear power was identified as a feasible and viable proposition
 for Bangladesh (former East-Pakistan).

 Rooppur was selected as a site for NPP (70 MW, 140 MW, 200
 MW) and Pre-feasibility studies were conducted.

 1971: Independence from Pakistan.

1977~78
 Feasibility studies were conducted by Sofratome, France and
 viability of Rooppur NPP (125 MW) was confirmed.

 Postponed in light of cost-effectiveness
Historical Background
1981-90
 1981: Plant capacity raised to 300 MW and fresh initiative taken.

 1988-’89: New feasibility study was conducted by Lahmeyer
 International, Germany in association with Motor Columbus,
 Switzerland.

 Financing difficulties.

1991-97
 1996: Nuclear Power option was included in National Energy
 Policy

 1997: The government decided to expedite the implementation

        process of NPP with two units of 600 MW each.
Recent Developments with the NP Program (3/13)

Apr 2010: Technical Committee on Rooppur NP Project
(Rooppur NPP), headed by the Hon'ble Minister of State,
MOST, formed for monitoring the progress of project activities.

Jun 2010: A Working Group and Eight Working Sub-Groups,
headed by the Secretary, MOST, formed to initiate and
coordinate various activities of different Organizations/
Ministries for establishing required nuclear infrastructures as
outlined in the IAEA Milestone documents.

Jun 2010: National Committee on RNPP, headed by the
Hon'ble Prime Minister, formed to provide top level decisions
on various issues related to RNPP implementation.

                                                              40
Recent Developments with the NP Program (4/13)

Nov 2010: Decision was taken in the National Parliament for
the establishment of Rooppur Nuclear Power Plant (RNPP).

July 2011: IAEA conducted Site Safety Review Mission and
provided recommendations on site specific studies.

Nov 2011: Bangladesh and Russian Federation signed an
Intergovernmental Agreement (IGA) for bilateral cooperation
concerning the construction of a nuclear power plant in
Bangladesh.

          IAEA Site Safety Review
     Mission visiting Rooppur Site
                                                           41
Recent Developments with the NP Program (5/13)

        Signing of the IGA on 2nd Nov 2011
                                                 42
Recent Developments with the NP Program (6/13)

  Nov 2011: IAEA conducted INIR* Mission to review the
  status of the National Nuclear Infrastructure (Phase-I & II).

  The Mission concluded that the nuclear power program of
  Bangladesh has progressed into Phase 2, being in the stage
  of preparation to negotiate agreement(s)/contract(s) with
  selected Vendor.

 An Integrated Time-bound (2012 - 2015)
 Work Plan for developing necessary
 infrastructures for construction of Rooppur
 NPP has been prepared based on the
 findings of the INIR Mission.

*INIR : Integrated Nuclear Infrastructure Review
                                                                  43
Recent Developments with the NP Program (7/13)

Feb 2012: An Interagency Agreement (IAA) on cooperation in
the area of Nuclear Safety Regulations was signed between
the MOST and Russian Regulatory Body.

May 2012: An Act entitled “Bangladesh Atomic Energy
Regulatory Authority Act” was enacted in the National
Parliament for establishing an independent Regulatory Body.
Feb 2013: Bangladesh Atomic Energy
Regulatory Authority (BAERA) started   BAERA Building
functioning independent of BAEC
under the MOST.

                                                          44
Recent Developments with the NP Program (8/13)

June 2012: An MOU was signed between MOST and
ROSATOM regarding the training of staff of nuclear power
sector of Bangladesh.

June 2012: An MOU was signed between MOST and
ROSATOM for establishing an Information Centre on Nuclear
Energy System in Bangladesh.

June 2012: An MOU was signed between Dhaka University
and Russian Educational Institution for collaboration in nuclear
education and research.

                                                             45
Recent Developments with the NP Program (9/13)

July 2012: A Negotiation Team was formed by the GoB for
addressing the financial issues in connection with the RNPP.
Sep 2012: Joint consultation was held in Dhaka with the
Russian side for completion of site related comprehensive
engineering survey and environmental studies for the
Rooppur site.
Dec 2012: Nuclear Engineering Department was opened in
Dhaka University.

                                                            46
Recent Developments with the NP Program (10/13)

Dec 2012: A high level team visited Russian Federation to
have joint consultations with the Russian side on financing
of RNPP and modalities for funding.

Jan 2013: A Project Monitoring Committee (PMC) on
construction of RNPP was formed by the government with
the State Minister, MOST as the Adviser and Secretary,
MOST as the Convener of the Committee.

Jan 2013: An agreement was signed between the Russian
Federation and the People’s Republic of Bangladesh on
State Export Credit for financing of the preparatory stage
activities of Rooppur NPP project.

                                                              47
Recent Developments with the NP Program (11/13)

         HE Sheikh Hasina and HE Vladimir Putin converse
            during joint press conference (16 Jan 2013)

                                                           48
Recent Developments with the NP Program (12/13)

 Jan 2013: An MOU was signed between the Russian
 Federation and the People’s Republic of Bangladesh for
 financing of the Rooppur NPP construction (i.e., the Main
 Project) through State Export Credit .

 April 2013: A high level delegation headed by the Hon’ble
 Secretary, MOST visited the Russian Federation to finalize
 the draft text of the contract on the development of the
 Feasibility Evaluation, Environmental Impact Assessment
 for Rooppur NPP Site and the Performance of the
 Necessary Engineering Survey and Environmental Studies.

                                                             49
Recent Developments with the NP Program (13/13)

 Jun 2013: A Contract “for the Development of the
 Feasibility Evaluation, Environmental Impact Assessment
 for Rooppur NPP Site and the Performance of the
 Necessary Engineering Survey and Environmental Studies”
 was signed between BAEC and JSC ‘Atomstroyexport’ on
 June 27, 2013.
 October 2013: The second contract “for development of
 design documentation, first-priority working documentation
 and engineering survey for the Design stage of Rooppur
 NPP ” was signed on October 2, 2013.
 The third contract “for performance of first-priority
 construction and erection works of the preparatory stage to
 the ‘first-concrete’ at RoopPur NPP” is under negotiation.
                                                           50
Milestone of 1st contract (1/3)
Milestone 1 Activities:
    First priority Engg. Survey (ES) at site
    Technical requirements for design materials
    Technical assignment for development of FE
    Technical assignment for development of EIA

Milestone 2 Activities:
          Quality Assurance
          Environmental monitoring program
          Working program for engineering survey
          Technical assignments for engineering
    survey
                                                   51
Milestone of 1st contract (2/3)

Milestone 3 Activities:
    FE Volume 1
    Prel. Report. Anthropogenic conditions
    Prel. Report. Engg. & hydro-meteorological survey
    Prel. Report. Engg. & geological survey
    Prel. Report. Engg. & geodetic survey

                                                        52
Milestone of 1st contract (3/3)

Milestone 4 Activities:
    Tech. Reports of the Milestone 3 Activities
    FE Volume 2
    FE Volume 4
    FE Volume 5
    EIA

Milestone 5 Activities:
    FE Volume 3
    Other technical reports

                                                  53
Management System
Presidential Order 15 of 1973 mandated Bangladesh Atomic
Energy Commission (BAEC) to do the needful in connection
with the introduction of NP programme in the country.
The Bangladesh Nuclear Power Action Plan (BANPAP) of
2000 and the National Committee on Rooppur NPP (2010)
headed by the Hon'ble PM authorized BAEC to implement
Rooppur NPP until otherwise decided by the Government.
Very recently, an ADP Project has been started under MOST
for the implementation of the Rooppur NPP project.
It is expected that in course of time a government owned
Company will emerge under BAEC to work as the operator of
the Rooppur NPP.
                                                         54
Management System for Nuclear Power Infrastructure Development
                                      Prime Minister                     Structure of
  Legal and Regulatory              National Committee                      NEPIO
  Aspects, International
      Obligations
                                                                                           Legal and
                                                                                          Regulatory
   Ownership, Project                 Minister MOST                                      International
  execution and Project                                                                   Obligations
      Management
                                                                                         Ownership,
                                   Technical Committee                                     Project
       Funding and                                                                       Execution &
       Financing                                                                         Management
                                                                 BAEC &
 Development of Human                Secretary MOST              BAERA                  Development of
                                                                                           Human
      Resources                                                                           Resources
                                                              Coordination
 National Participation               Working Group            Committee                 Funding and
                                                                                          Financing

                                                             Nuclear Power and            Nuclear FC,
      Grid System                                                                          WM and
                                                           Energy Division (NPED)          Environ
                                                                                          Monitoring
 Nuclear Fuel Cycle, Waste
 Management and Environ
                                                                                          Grid System
       Monitoring
                                                                                         Development

    Heavy Equipment                                                                        National
 Transportation Planning                                                                Participation &
                                                                                         Procurement
                                                   NEPIO
Working Sub-Groups (Ministry)                                                Sub-Committees (BAEC)
                                                                                               55

                             Address all the 19 IAEA Milestone Issues                                     55
NATIONAL COORDINATION FOR DEVELOPING NUCLEAR INFRASTRUCTURE

                            Prime Minister

 Legal and Regulatory     National Committee
 Aspects, International
     Obligations
                                                                                 Legal and
                                                                                Regulatory
  Ownership, Project        Minister MOST                                      International
 execution and Project                                                          Obligations
     Management
                                                                               Ownership,
                          Technical Committee                                    Project
      Funding and                                                              execution &
      Financing                                                                Management

                            Secretary MOST               BAEC                 Development of
Development of Human                                                             Human
     Resources                                                                  Resources
                                                      Coordination
 National Participation     Working Group              Committee               Funding and
                                                                                Financing

                                                                                Nuclear FC,
     Grid System                                       Nuclear Safety and        WM and
                               Nuclear Power and                                 Environ
                                                       Radiation Control
                             Energy Division (NPED)                             Monitoring
                                                       Division (NSRCD)
  Nuclear Fuel Cycle,
Waste Management and                                                            Grid System
 Environ Monitoring                                                            Development

   Heavy Equipment                                                               National
Transportation Planning                                                       Participation &
                                                                               Procurement

Working Sub-Groups                        NEPIO
     (Ministry)                                                   Sub-Committees on RNPP
                                                                         (BAEC)
                                                                                  56
Implementation Strategy
Conduction of Engineering Survey (ES) and Feasibility
Evaluation (FE) studies and obtaining required regulatory
approvals (2013 – 2014) .
Undertaking extensive measures for developing required
human resources (2014 onward).
Development of conceptual, preliminary and detailed
engineering design of RNPP (2014 – 2015).
Establishment of general contract for construction and
commissioning of Rooppur NPP including the arrangements
for education and training of plant personnel (2015 onward).
RNPP Construction (2015 – 2020).

                                                            57
Prime Minister Sheikh Hasina lays the foundation stone of the first
Phase work of the Rooppur Nuclear Power Plant on 03-10-2013 in
Ishwardi, Pabna.
Asian Nuclear Safety Network, Topical Group List:
SL.    Topical Group                                Name, Designation & Address
No
  1.   Education and Training (ETTG)                Dr. Mohammad Ali, Member ( Now retired)
                                                    (Physical-Science), BAEC, Dhaka.
                                                    Email: aliaecd@yahoo.com.
                                                    Mobile: 01711182226
  2.   Emergency Preparedness and Response           Dr. Mamunur Rashid, Director (Physical-Science)
       (EPRTG)                                      Email: mrashid@agni.com
                                                    Mobile: 01819195251

  3.   Governmental and Regulatory Infrastructure   MS. Samina Rahman, Chairman, BAERA, Dhaka.( Now retired)
       (GRITG)                                      Email: samina_nita@yahoo.com
                                                    Mobile: 01913509645
  4.   Operational Safety of Nuclear Power Plants   Engr. M.Ali Zulquarnain, Member (Planning), BAEC, Dhaka
       (OSTG)                                       Email: zmaliee@gmail.com
                                                    Mobile: 01916276221
  5.   Radioactive Waste Management (RWMTG)         Dr. Debasish Paul , Chief Scientific Officer, INST, AERE, Savar,
                                                    Dhaka
                                                    Email: dpaul.physics@gmail.com
                                                    Mobile: 01552405463
  6.   Safety Analysis (SATG)                       Dr. Sk.Md. Yunus, Director, INST, AERE, Savar, Dhaka
                                                    Email: yunussm11@yahoo.com
                                                    Mobile: 01817619588
Asian Nuclear Safety Network, Topical Group List:
SL. No   Topical Group                            Name, Designation & Address
7.       Safety Management of Research Reactors   Engr. Ashraful Haque, Senior Engineer, ROMU,
         (SMRRTG)                                 AERE, Savar, Dhaka
                                                  Email: ahaque_90@yahoo.com
                                                  Mobile: 01680800654
8.       Siting (STG)                             Engr. Md. Monirul Islam, Member (Engineering),
                                                  BAEC, Dhaka.
                                                  Email: engr.monirbaec@yahoo.com
                                                  Mobile: 01554330547
9.       Information Technology Support Group     Mr.KaramNewaz, Chief Scientific Officer &
         (ITSG)                                   Director ICS, AERE, Savar, Dhaka.
                                                  Email: newaz1958@yahoo.com
                                                  Mobile: 01716199431
10.      Topical Group on Communication CTG)      Dr. Md. Mazibur Rahman, Chief Scientific Officer,
                                                  BAEC, Dhaka.
                                                  Email: shajal66@yahoo.co.uk
                                                  Mobile: 01925146926
11.      Topical Group on Leadership and          Engr. Md. Monzurul Haque, Director, Engineering
         Management for Safety (LMSTG)            Division, BAEC, Dhaka.
                                                  Email: mmhaque_2000@yahoo.com
                                                  Mobil: 01911341162
Concluding Remarks

Bangladesh Government is doing the
needful to embark on the Rooppur NPP
project through bilateral cooperation with
Russian Federation.
The matter of development of NPP
related legal documents as stipulated in
the BAERA Act- 2012 is under progress.

                                             61
Bangladesh seeks support and cooperation of the IAEA, the
identified vendor country and all relevant national and
international stakeholders for successful implementation of
RoopPur NPP Project in time.

Steps have been taken to develop national cyber network
infrastructure to make connectivity with ANSN knowledge pool
for dissipation and sharing of information knowledge and
experience in the field of nuclear safety.

IAEA and ANSN help and cooperation is needed to strengthen
nuclear safety in the country for its existing facilities and future
nuclear power plant.
Thank you very much for your kind attention…

                                           63
You can also read