Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management

 
CONTINUE READING
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
Current Status of Fukushima
  Daiichi Nuclear Power Station

    -Efforts for Decommissioning and
   Contaminated Water Management-

Agency for Natural Resources and Energy, METI
                 April, 2020
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
< Outline >

 1.Progress on Fukushima Daiichi Decommissioning

 2.Overview of Water Management

   - Countermeasures for contaminated water

   - Issue of “ALPS treated water”

 3. Environmental Monitoring

 4. IAEA review mission

 5. Information Portal site

                                                   1
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
Introduction: Where is Fukushima Daiichi?

                              Approx. 250km
                                   from Tokyo

                                                           Approx. 2km

                                                Unit 1-4

                                                                    2
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
Overview : Current status of Fukushima Daiichi NPS

• The reactors of Fukushima Daiichi NPS are being kept in stable condition.
• “significant progress has already been accomplished to move Fukushima Daiichi from
  an emergency situation to a stabilized situation.” (IAEA review mission report,
  January 31, 2019)

      At the time of the nuclear accident                        Today

   The accident cut off the water supply to the          Reactors are being kept stable.
   reactors. As a result, the fuel generated heat, and
   hydrogen explosions occurred.
                                                                                           3
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
1-1. Decommissioning of TEPCO Fukushima Daiichi NPS (FDNPS)

◇ Fukushima Daiichi Decommissioning is a continuous risk reduction activity to protect
 the people and the environment from the risks associated with radioactive substances by:
      Removing spent fuel and fuel debris from the Reactor Building
      Reducing the risks associated with contaminated water and radioactive waste
◇ Safe and steady decommissioning is a prerequisite for reconstruction of Fukushima

                                 Spent fuel             Fuel that remains after its usage for power generation.
                               (Spent fuel pool)        Continuous cooling is needed to suppress the heat

      Water

                                                        Fuel that has melted and solidified by the accident.
                                Fuel Debris
                                                        Continuous cooling is needed to suppress the heat

                               Contaminated Water                    Radioactive Solid
                                  Management                        Waste Management

                             Units 1 and 2                                               Unit 3               Unit 4
  Removing fuel from                            Installation of fuel removal                                  Storage/Tra
                         Rubble removal                                                  Fuel removal         nsportation
  the Spent Fuel Pool                                    equipment
                                                        Units 1,3                        Units 2
                        Fuel debris       Ascertaining of the situation inside the                                            Storage/
                                                                                             Fuel debris retrieval
    Current              retrieval     PCV/ consideration of fuel debris retrieval etc                                      Transportation
    progress
                                                                                                   Consideration of                                   Dismantling
                                                                 Disassembly of                     scenario and
                                                                                                                            Design and construction
                                                                                                                                                       and other
                                                                                                                                 of equipment
                                                               reactor facility, etc                technologies                                         tasks
                                                                                                                                                                    4
                                                     Extended to 30-40 years
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
[Ref. 1] Current status of Unit 1-4 of Fukushima Daiichi NPS
                Unit 1                                        Unit 2                           Unit 3                            Unit 4

                                                                                       Removed fuel                    Removed fuel assemblies
           Spent fuel                                                                  assemblies 119/566
                                                                                                                                  1535/1535
         (Spent fuel pool)                                                               (As of 2020/3/26)            (Completed in 2014/12/22)

                                                                             Front                               Roof dome
                                                                                前室
                                                                             chamber                                                   Cover for fuel
                                                                                                                 Fuel handling           retrieval
 Hydrogen                                                                          Hydrogen                      machine                           Hydrogen
 explosion                                                                         explosion                     crane                             explosion

                             392                   Water injection     615
   Water injection                                                                     Water injection

                                              安全第一
                                                福島第一

 Core melt                                    Core melt                            Core melt

                                                                                          Confirmed that                                     Started fuel
                     Dismantling   Local                                                  the deposit
                     equipment                                                                                                               removal from the
                                   company
                                                                                          likely to be the                                   spent fuel pool by
                                   joins as a
                                                                                          fuel debris was                                    remote control,
                                   prime
                                                                                          able to be                                         for the first time
                                   constructor.
                                                                                          gripped and                                        from a nuclear
                                   [started
                                                                                          moved.                                             reactor with core
                                   Aug. 2019]
                Top of exhaust                                                            (Unit 2)                                           melt (Unit 3)
                stack                                                                     [Feb. 2019]                                        [Apr. 2019]       5
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
[Ref.2] Impact on the surrounding Environment

• The environmental impact on the site and surrounding area have been
  significantly reduced.
                                                  (Bq/L)
                                                                                        10,000 over                                                Sea
                                                                200
                                                                180
                                           N                    160
                                                                140
                                                                120
                                                                100
                                                                            80
                                                                            60
                                                                                                        Guidance value recommended in the WHO
                                                                            40                        Guidelines for Drinking water quality (10Bq/L)
                                                                            20
                                                                                    0

                                                                                                 Evaluation of annual exposure dose at the site

                                                  Radiation dose rate ( mSv/year)
                                                                                                 boundary due to radioactive materials (cesium)
                                                                                                                                                       Air
                                                                                                 from the reactors buildings of Units 1-4

                              Near the south                                                            There has been no effect of the radioactive
                              discharge                                                                  material (dusts etc.) to the outside in the
                                                                                                            course of decommissioning work.
                              channel

   Whole map of Fukushima Daiichi Nuclear plant
                                                                                                                                                             20
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
1-2. The Mid-and-Long-Term Roadmap
  •    Decommissioning of Fukushima Daiichi NPS will be done by TEPCO in its responsibility.
  •    The decommissioning is an unprecedented work with technical challenges. The Government
       of Japan has been taking initiative based on the Mid-and-Long-Term Roadmap, with the
       target of the completion of decommissioning in 30-40 years in a safe and steady manner.

Time flame for Fukushima Daiichi Decommissioning
                           December                November 2013
                             2011          (Started fuel removal at Unit 4)                       Now
                                                                                                          December    End of   30-40years
                                                                                                            2021       2031    from cold shut down

Efforts for stabilization             Phase 1                                 Phase 2                        Phase 3-(1)   Phase 3
 Achieved cold shut             Period until start of
                                                                                                              Period until the completion
 down state                                                 Period until start of fuel debris retrieval       of decommissioning (30-40
                                spent fuel removal
 ・drastic suppression in                                    (within 10 yrs.)                                  years from the cold shut
                                (within 2 yrs.)
  release of radioactive                                                                                      down)
  materials

 Role of the Government of Japan
 • GOJ sets the Roadmap                                                       • Based on the “Roadmap”, mid-and long-term
  ₋ The Inter-Ministerial Council for Contaminated Water and                    measures has been undertaken while giving top
   Decommissioning Issues has set out the Roadmaps.
                                                                                priority to the safety and keeping the attitude to
   (Chairman: Chief cabinet secretary, First version: Dec. 2011)
                                                                                value the risk reduction.
  - Revised for five times to date
    (Revised in Jul. 2012, Jun. 2013, Jun. 2015, Sept. 2017, and
  Dec. 2019)
                                                                                                                                                 6
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
[Ref.3] Major milestones of Mid-and-Long-Term Roadmap (Dec. 2019)
                                                                                                                               30~40 years after cold
Dec. 2011              Nov. 2013                                    Now        Dec. 2021            End of 2031                    shutdown
                                                                                     Hold                                                   Hold
        Phase 1                                   Phase 2                              Phase 3-(1)               Phase 3

 Period until start of fuel     Period until start of fuel debris retrieval          Period until completion of decommissioning
 removal (within 2 years)       (within 10 years)                                    (30-40 years later)

 Major milestones                                                                                   Roadmap (Sept. 2017)     Revised Roadmap
  Contaminated                Reduce to about 150 m3/day                        Further reduction         Within 2020      Within 2020
  water                       Reduce to about 100m3/day or less                 of generation                  ー           Within 2025         NEW
  management
   Stagnant water             Complete stagnant water treatment in buildings*                           Within 2020        Within 2020(*)
   treatment
                              Reduce the amount of stagnant water in buildings to                              ー           FY2022 - 2024       NEW
                              about a half of that in the end of 2020
                              Complete of fuel removal from Unit 1-6                                           ー           Within 2031         NEW
                              Complete of installation of the large cover at Unit 1                            ー           Around FY2023       NEW
  Fuel removal
                              Start fuel removal from Unit 1     Methods have changed                   Around FY2023      FY2027 – 2028       REVISED
                              Start fuel removal from Unit 2     to ensure safety and                   Around FY2023      FY2024 - 2026       REVISED
                                                                       prevent dust scattering

  Fuel debris                 Start fuel debris retrieval from the first Unit                             Within 2021      Within 2021
  retrieval
                              (Start from Unit 2, expanding the scale gradually)
                              Technical prospects concerning the processing/disposal                    Around FY2021      Around FY2021
  Waste                       policies and their safety
  management
                              Eliminating temporary storage areas outside for rubble                           ー           Within FY2028       NEW
                              and other waste
  * Excluding the reactor buildings of Units 1-3, process main buildings, and High temperature incineration building.                                7
Current Status of Fukushima Daiichi Nuclear Power Station-Efforts for Decommissioning and Contaminated Water Management
1-3. Essence of fuel removal from pool and fuel debris retrieval

                           Fuel removal from pools                                  Fuel debris retrieval
        (Adoption of method for suppressing dust scattering)                    (Determination of method for
                                                                                   retrieval from Unit 2*)
                  Unit 1                              Unit 2

Installation of                                                Fuel handling
                                       Installation
                                                               machine             Robot arm
large cover                            of stand for
                                       removal                                    for retrieval

 • Review the method and staring time of fuel removal in order to              • Robot arm has been developed for
   prioritize safety such as suppression of dust scattering.                     retrieval work.

 • Aim the completion of fuel removal from all Units, including Unit 5         • Present detailed method for
   and 6, within 2031.                                                           retrieval

                                                                               • Retrieval will be started in 2021,
                                                                                 carefully, and will gradually expand
                                                                                 its scale.
                                                                                       * first implementing Unit
                                                                                                                        8
デブリ取りだしに向けて
                                   1-4. Towards fuel debris retrieval
In the “Mid-and-Long-Term Roadmap” revised in December 2019, it was
described that the trial retrieval will start at Unit 2 within 2021 and then the
scale of the retrieval will be gradually enlarged.
      Unit 1:Investigation of the distribution situation of deposits including small amount sampling will
             be done in the last half of FY2020.
      Unit 2:The trial retrieval of fuel debris and internal investigation will start within 2021.
           * In February 2019, the contact investigation inside PCV was conducted. Information such as
            hardness was acquired and it was confirmed that the deposit likely to be fuel debris was able to
            be gripped and moved.
      Unit 3: Measures to reduce water level in the PCV and detailed investigations are under
             consideration.

            -FY2019                    FY2020                       FY2021                 FY2022           FY2023-

                           Investigation at the bottom of PCV
                           (including small amount sampling)
Unit
 1

                                Metallic brush   Vacuum vessel

        Contact investigation
        (Feb. 2019)                                        Trial retrieval/Internal investigation
                                                                                                    Fuel debris retrieval
Unit
                                                                                                    (Gradual enlargement of the
 2                                                                                                  retrieval scale)

Unit                                                                                                 Detailed investigation
 3                                                                                                   at the bottom of PCV
                                                                                                                                  9
2-1 Generation of contaminated water, purification process and tank storage
◇ Water gets contaminated when it touches the damaged reactors and fuel debris in buildings.
    The level of groundwater outside is controlled to be higher than that of contaminated water
     inside the buildings to prevent the water flowing out of the building.
           Groundwater keeps flowing into the buildings
◇ TEPCO has been successful in removing most of radionuclides except tritium from contaminated water.
    ALPS (Multi-nuclide retrieval equipment) and the other equipment have been used. See more at P13
 It is ALPS treated water, NOT -contaminated water, that is stored in the tanks.
 Radioactive materials in ALPS treated water are reduced to about 1/1,000,000 (one millionth).

                                                              ALPS

                                                      ② Most of the nuclides
                                                      except tritium are
                                                      removed in this process.
         ALPS-treated water
                                                          Continuous injection
                              ③ Treated water is            of cooling water                 ① Contaminated water
                              stored in tanks.                                               is sent to purification
                                                                                             equipment such as ALPS.
                                                     Fuel Debris
                                                                                      Damaged
                                                                                      Reactors
                               Flow of groundwater                                    at FDNPS

                                                                          Contaminated Water
                                                                                                             Sea-side
                                                                                 Sub-drain                 Impermeable
                                                                                                               wall
                                                                     Land-side Impermeable wall
                                                                         (frozen-soil wall)                              10
[Ref.4] Overview of water management
                                  *3 Basic Principles for water management
1. “Redirecting” groundwater from the
  contamination source                                                         8) Removing radionuclides from

                                                                                                                                          Flow of groundwater
      1) Pumping from Groundwater-bypasses and sub-drains                           contaminated water
      2) Installation of Frozen-soil impermeable walls
      3) Waterproof pavement to prevent rainwater seeping; and others               5) Prevent leakage from
                                                                                       the tanks

 2. “Preventing leakage” of contaminated water
                                                                             3) Waterproof pavement to prevent
      4)   installation of sea-side impermeable walls                           rainwater seeping
      5)   Prevent leakage from tanks (installing welded-joint tanks etc.)
      6)   Pumping from Groundwater-drains                                                                  1) Pumping from the Groundwater-
      7)   Ground Solidification by Sodium Silicate; and other measures                                        bypasses and Sub-drians
                                                                                                                 A
 3. ”Removing” the contamination source
                                                                                                                      2) Installation of Frozen- soil
      8) Removing radionuclides from contaminated water
                                                                                                                         impermeable walls
      9) Removing water in the trenches; and other measures

                                                                                         4        3         2
                                                                                                                 1

                                                                                                                             9) Removing water in
                                                                                                                              the trenches

1)Groundwater-
                                                                                                                 A´
   bypassing                                      6)Groundwater-
                                                     drains                   4) Installation of Sea-side               6) Pumping from
                            1) Sub-drains
                                                                                  impermeable walls                    Groundwater-drains
                          2) Frozen-soil walls     4)Sea-side walls
                                                                                               7) Ground solidification by
                                                                                                    Sodium Silicate
 A                                                                     A´                                                                                       11
2-2. Key figures of ALPS treated water

                                                                                Key Figures for ALPS treated water at the site
                                                                                           (As of March 12, 2020)
                                                                            Number of tanks          979

                                                                            Tank Storage volume      About 1.19 million ㎥
                                                                            Planned capacity         About 1.37 million ㎥
                                                                            (Under current plan)                (by the end of 2020)
                                                                            Annual increase of
                                                                                                     About 50,000~60,000㎥/year
                                                                            ALPS treated water

     ※ About 2 years will be needed for preparation and
        permission for disposal.                                            Time to reach its full capacity (forecast):
     ※There is a limited room for further tank construction
                                                                            around summer of 2022

Amount of Tritium (tritiated         Approx. 860 TBq* (16g)
water) in tanks                                 (*TBq = 1×1012 Becquerel)

Average Concentration of              0.73 MBq/L
Tritium                                         (*MBq = 1×106 Becquerel)

※Currently, several kinds of radionuclides other than tritium are found
   in ALPS treated water in tanks. → See page 13
※ If the treated water is discharged into the environment, it will be re-
   purified and diluted to meet the standards for discharge.

                                                                                                                                       12
2-3. Characteristics of ALPS treated water
 Two regulatory standards:
  1) Applicable to storage: to keep site boundary dose levels less than 1mSv/year                   Goal currently achieved through ALPS
  2) Applicable to release to the environment: to keep radionuclides concentrations of treated water less than the regulatory limit.

 There are various concentration of ALPS treated water in the tanks, because:
      Concentration of ALPS treated water depends on the attributes of water to be treated and operation management of ALPS
       such as frequency of absorbent exchange; and
      Especially in the first few years after the accident, which was before improvement of ALPS performance, concentrations of
       tritium in ALPS treated water was relatively high.

 In case of releasing ALPS treated water to the environment, the water needs to satisfy standard 2).
      TEPCO announced to re-purify ALPS treated water, to meet standard 2) for radionuclides other than tritium.
      After the re-purification, the water will be diluted to meet the standard 2) for tritium.
         9.76     Site Boundary dose levels

                    Direct rays from tanks/skyshine
                   Direct rays from sources other than
                    tanks/skyshine
                   Other (Groundwater bypass/sub-drains,
                    etc.)

                  1.44
                            0.96      0.92       0.90

                                                                         *These drawings are quoted from “Treated water `portal site(TEPCO HP)”
                                                                                                                                                  13
2-4. Process ahead
 Role of the subcommittee:
   1) to examine in a comprehensive manner, such as countermeasures for reputational damage,
and
   2) to compile report for the government
 GOJ will decide its basic policy, after receiving report of subcommittee and discussing with
  parties concerned.
                                Report
                             Feb. 10, 2020                                Share the discussion at subcommittee

   The Subcommittee
                                   1                                                  Stakeholders
     on handling of                               Government          2          (community people etc.)
   ALPS treated water

  Discuss from experts’                      Decide on basic policy       Listen to opinions of parties concerned
      point of view           Request for                                            Since April, 2020
 Nov. 2016 – Jan. 2020        Examination
                             Nov. 11, 2016

                               Approve

                                  3
   Nuclear Regulation                                TEPCO
        Authority         Measures for handling

                                 Apply        Decide on engineering
                                                                                                                 14
2-5.The key points of the report (1): Basic approach

 Reputational damage still remains and affects reconstruction of
  Fukushima.
 "Coexistence of reconstruction and decommissioning" is a basic
  principle:
  - Returning of residents and reconstruction efforts in the surrounding area have been
   proceeding.
  - Additional reputational damage should not be caused by a hastened disposition of ALPS
   treated water.

 Disposition of ALPS treated water needs to be completed until the
  completion of the decommissioning:
  - with necessary storage, and
  - with due consideration to the minimization of the impact on reputation

 In deciding the disposition of the ALPS treated water, the
  government must also compile a policy for countermeasures against
                                                               17

  reputational damage.
                                                                                            15
2-6. The key points of the report (2): disposal methods
 Vapor release and Discharge into the sea have been conducted and recognized as feasible
  methods.
 There are precedents for discharge into the sea in Japan and it is easy to operate necessary
  facilities. Thus this can be conducted with certainty.
 Radiation impact of both methods is considerably small compared to natural exposure to radiation.

                                    Vapor release                                                  Discharge into the sea
               Precedent in case of accident at NPP overseas                       Precedents exist world-wide
                  * Vapor is also released from reactors in normal operations
                    at the time of ventilation.                                     More reliable option
               In Japan, there is no example of vapor release                         * precedents in Japan and easiness of operating facilities
Technical       in order to dispose liquid waste.                                   Relatively easy to predict how discharged
 Issues        Difficult to predict how the released vapor is                       water is diffused in the ocean
                diffused into the air
                                                                                    Easy to examine proper monitoring method
               Difficult to establish proper monitoring
                methods
               Difficult to compare the social impacts of two methods
                 * Social impact is greatly dependent on consumer psychology.
 Social
 issues        May attract significant social concern                              May attract particularly large social concern if
                                                                                     no countermeasure for reputational damage
                                                                                     is taken
  The following three options have many insurmountable issues (regulatory, technological, and timewise)
   Geosphere injection:Need to seek for appropriate sites, and monitoring methods have not been established
   Hydrogen release :Further technological development would be required for pretreatment and scale expansion.
   Underground burial :In solidification process, water including tritium will be evaporated. New regulations may be necessary.
                        Area for disposal yard will be needed.                                                                                      16
[Ref. 5] Impact assessment for environmental release of ALPS treated water
[Conditions]
 Using UNSCEAR*1 assessment model*2 and precondition that all the treated water stored in tanks
  (containing 860TBq of tritium) is discharged in one year.
   (*1: UNSCEAR: The United Nations Scientific Committee on the Effects of Atomic Radiation)
   (*2: re-assessed with Japanese food consumption)
                                   [Ref. UNSCEAR 2016 Report, Annex A “Methodology for estimating public exposures due to radioactive discharges”]
     [case 1] Vapor release -------    Approx. 0.0012 mSv/year (1.3 μSv/year)
     [case 2] Discharge into the sea ---- Approx. 0.000071 to 0.00081 mSv/year (0.071 to 0.81 μSv/year)
 In both discharge methods, the impact of the radiation from the discharge is considerably small,
  compared with annual natural exposure in Japan: 2.1 mSv/year (2,100 μSv/year).

Exposure dose [mSv/y]                             Vapor release※1                    discharge into the sea※2
All radionuclides※3                                   0.0012※4                         0.000071~0.00081
 - tritium                                              0.0012                               0.0000068
  ※1 Sum of external dose from the atmosphere and soils, and internal dose from inhaling the air and ingesting terrestrial life (at 5km points from the FDNPS)
  ※2 Sum of external dose from beaches and internal dose from ingesting marine life.
  ※3 Estimation was conducted on the two assumptions that “ND (Not Detected)” nuclides are 1) their ND value and 2) zero.
  ※4 For exposure dose for [case 1 (vapor release)], there is no difference between the results from two assumptions

                          Comparison of radiation impact between natural exposure and
                             discharging treated water containing 860 TBq of tritium
        Vapor release           0.0012 mSv/year

Discharge into the sea        0.00081 mSv/year

    Natural exprosure                                                                                                     2.1 mSv/year
                                         0.05                                                  2.05              2.1               2.15
                                                           0.1                0.15                                                          mSv/y                17
2-7. The key points of the report(3):
                        Countermeasures against reputational damage

1) Well planned disposition process
2) Expansion and enhancement of countermeasures building on best practices
3) Continuous and flexible response

   <1. Well planned disposition processes >
    Re-purify radionuclides other than tritium
    Stop the disposition process in case of emergency
     e.g. environmental situation, malfunction of facilities
    Determine the details (starting time, volume, and period of disposition),
     while listening to opinions of stakeholders
    Disseminate information in a considerate and an easy-to-understand manner
        Concentration of pre-disposition ALPS treated water
        Monitoring results of surrounding environment
    Explain safety of surrounding environment by utilizing diffusion simulation
                                                                                   18
2-8. The key points of the report(3):     - continued

<2. Expansion and enhancement of countermeasures building on best practices>
< Risk communication>                     < Economic measures>
         - to convey relevant information             - for reputational damage

 Disseminating information on the          Constructing analytical framework
  disposal method and scientific             for:
  knowledge in advance                          Environmental monitoring, and
                                                Food sampling measurement
 Providing information via:
     Social media, mass media              Utilizing third-party certification to
     On-site lectures                       secure consumer trust, such as
                                                GAP (Good Agricultural Practice)
                                                MEL (Marine Eco-label)
 Strengthening information
  dissemination abroad                      Developing new market channels by
     Basic information on                      Promotion events for Fukushima
      decommissioning                            products
     Disposition methods in the world          Allocation of special sales staff in
      as well as precedents outside of           stores
      Japan                                     Opening of on-line stores etc.
                                                                                        19
3-1. Seawater radiation monitor near Fukushima Daiichi NPS

        Regulatory Limit Specified by Reactor Regulation
                                                           Bq/l
                                                                  ① North side of units 5 and 6 discharge channel
         ・Cesium 137: 90Bq/L
         ・Cesium 134: 60Bq/L

N

                                                                  ② Real time monitoring
         Sea-Side
     Impermeable Wall                                             <TEPCO’s website>
                                                                    http://www.tepco.co.jp/en/nu/fukushima-np/f1/seawater/index-e.html
                Unit 1 - 4

                                                                  ③ Near South Discharge Channel

Frozen-soil Wall

    Fukushima Daiichi NPS                                                                                                           21
3-2. Seawater radiation monitor around Fukushima Daiichi NPS

                                              ~20Km from Fukushima Daiichi NPS
      Seawater sampling points
                                              ①                                                ②

             ④

Fukushima
Prefecture

 Fukushima
   Daiichi
    NPS          ②                             30~100Km from Fukushima Daiichi NPS

             ①                                 ③                                               ④

                 ③

                            sampling points

                                                   (Source : NRA website)
                                                   https://radioactivity.nsr.go.jp/en/contents/8000/7742/24/engan.pdf
                                                                                                                        22
4.Summary of the 4 th IAEA Review
                            - November 2018 (final report: Jan. 31, 2019)-
Main findings
- “ IAEA teams said Japan has made significant progress since the accident in March 2011, advancing from an
   emergency situation towards a stable situation now.”
 - “The team acknowledged a number of accomplishments since the 2015 mission, including
      The repair of subdrains and construction of the frozen soil wall around reactor Units 1-4, which have
       reduced groundwater ingress into the reactor buildings.
      Improved site working conditions including a reduced need for full protective gear, and real-time
       radiation monitoring easily accessed by the workforce.
      Progress towards the removal of spent fuel from Units 1-3 as well as remote investigations of fuel debris
       by robots.”
- “The team said the Government of Japan, in engaging all stakeholders, should urgently decide on a disposition
path for ALPS treated water. “
【Reference】                                Ordinary clothing can be worn at 96% of the site
                                                 Areas where Protective clothing are required

 Panorama image of the impermeable walls         Areas where ordinary clothing can be worn          Fuel Handling Machine
                                                                                                for the removal of spend fuel
        Frozen-soil walls                                                                                                  unit3

        Reactor building

                                                                                                                                   23
4.Summary of the follow-up mission of 4 th IAEA Review
                                             - Feb-Mar 2020 -
Background, Scope
- The total tank storage capacity will amount to approximately 1.37 million m3 by the end of 2020 and the tanks
   are expected to be full around the summer of 2022.
- The IAEA pointed out that “the Government of Japan, in engaging all stakeholders, should urgently decide on a
   disposition path for ALPS treated water“ in the 4th peer review mission in November 2018.
- The Government of Japan had requested the IAEA review of the management of the stored water, including the
   report by the Subcommittee on Handling ALPS Treated Water, issued on February 10, 2020.
Main findings
 - “The IAEA Review Team positively notes that ALPS subcommittee report addresses technical, non-technical and
    safety aspects necessary to make a decision. “
 - ”The IAEA Review Team considers that the methodology and criteria used for the down selection from the
    initial five options to two* are based on a sound methodology for the purpose of decision making.
      * controlled vapor release, and controlled discharges into the sea, the latter of which is routinely used by
       operating nuclear power plants and fuel cycle facilities in Japan and worldwide.
- “The two options selected are technically feasible and would allow the timeline objective to be achieved. “
- “The IAEA Review Team positively notes the efforts of the Japanese experts to adjust the well-established
   UNSCEAR methodology to the specific case of Japan.”

   【Reference】              Comparison of radiation impact between natural exposure and
                               discharging treated water containing 860 TBq of tritium
          Vapor release

  Discharge into the sea

      Natural exprosure
                                    0.5            1.0            1.5           2.05           2.1           2.2     mSv/y   24
5-1. Information Portal site (1) : Fukushima Daiichi NPS

 Decommissioning and Contaminated Water Management
  at TEPCO's Fukushima Daiichi NPS
   https://www.meti.go.jp/english/earthquake/nuclear/dec
   ommissioning/index.html
 Film, Fukushima Today 2019
  - Efforts to Decommission and Reconstruction
    https://www.youtube.com/watch?v=v_PeSp--Wuk
 Film, Fukushima Today
  - 8 years after the earthquake -
    https://www.youtube.com/watch?v=pKjsSAz5Kws

 Treated Water Portal Site
   http://www.tepco.co.jp/en/decommission/progress/watertreatment
   /index-e.html

 Observation Data, Fukushima Daiichi NPS
   https://www7.tepco.co.jp/responsibility/decommissioning/1f_newsr
   oom/data/index-e.html
                                                                      25
5-2 Information Portal site (2) : Fukushima Daiichi NPS

 Fukushima Daiichi Status Updates
   https://www.iaea.org/newscenter/focus/fukushima/status-update

 IAEA Review mission reports (Press release )
  IAEA Team Completes Fourth Review of Japan’s Plants to Decommission Fukushima Daiichi
  (November 13, 2018)
  https://www.iaea.org/newscenter/pressreleases/iaea-team-completes-fourth-
  review-of-japans-plans-to-decommission-fukushima-daiichi
  IAEA Issues Final Report on Fourth Review of Fukushima Decommissioning (January 31, 2019)
  https://www.iaea.org/newscenter/pressreleases/iaea-issues-final-report-on-
  fourth-review-of-fukushima-decommissioning

  IAEA Reviews Management of Water Stored at Fukushima Daiichi Nuclear Power Station
  (April 2, 2020)
  https://www.iaea.org/newscenter/pressreleases/iaea-reviews-management-of-
  water-stored-at-fukushima-daiichi-nuclear-power-station

 UNSCEAR 2016 REPORT
-Sources, effects and risks of ionizing radiation
  hhttps://www.unscear.org/unscear/en/publications/2016.html
                                                                                              26
You can also read