CONTRACT NO. WM20/21-02 - 2021 Leachate Pond Primary Geomembrane and Floating Cover Replacement BACKGROUND REFERENCE DOCUMENT FOR
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
BACKGROUND REFERENCE DOCUMENT FOR CONTRACT NO. WM20/21-02 2021 Leachate Pond Primary Geomembrane and Floating Cover Replacement LANE COUNTY PUBLIC WORKS - WASTE MANAGEMENT DIVISION 3100 EAST 17TH AVE. EUGENE, OREGON 97403 Expires 06/20
TABLE OF CONTENTS PAGE DESCRIPTION OF WORK……………………………………………………………………….1 BACKGROUND…………..……………………………………………………………………….1 DESIGN INTENT………………………………………………………………………………….3 PHOTOS OF EXISTING FLOATING COVER AND ANCHOR WALL …………………….3
DESCRIPTION OF WORK Contract No. WM20/21-02 2020 Leachate Pond Primary Geomembrane and Floating Cover Replacement Perform the following general scope of work on 1.5 ac pond (65,544 sq ft): remove and dispose of existing floating cover system into onsite landfill; remove estimated 500,000 gallons of sludge and liquid from pond and dispose into onsite landfill; clean existing pond liner and perform electric leak survey on existing conductive liner; install new 80-mil smooth conductive HDPE geomembrane over the top of existing liner and perform electric leak survey; install new 60-mil RPP floating cover system with all appurtenances; and all other work called for in the plans and specifications. Project is located at the Short Mountain Landfill, 84777 Dillard Access Road, Eugene, Oregon 97405. BACKGROUND The existing leachate pond at the Short Mountain Landfill was constructed in 1998. The pond size is 1.5 acres, with a rectangular shape having rounded corners. The maximum pond depth from crest to sump is 13 feet. The interior side slopes are 3:1. The bottom slope is 4% with minimum 2% slopes hinge lines. The original bottom liner system is two layers of 60-mil conductive HDPE with an intervening geonet leakage collection layer. The bottom of the pond has a secondary riser pipe that allows monitoring and removal of any leakage through the primary geomembrane. The current leakage rate that the pond experiences, averaged over a one year period, is about 25 gallons per day. Removal of leachate from the pond occurs through a vertical pipe penetration in the sump that conveys the leachate to a pump station. Leachate inlet into the pond come in through pipes over the top of the liner system perimeter anchor. The secondary geomembrane is terminated around the perimeter by an extrusion weld to a concrete embedment strip in the perimeter concrete anchor wall. The primary geomembrane is extrusion welded to the secondary geomembrane about 4 inches behind the embedment strip. To eliminate rainwater from directly falling into the pond, which would have to be treated as leachate, the pond was fitted with a floating cover. The floating cover system was/is comprised of a 45-mil reinforced polypropylene geomembrane with a system of floats, weight tubes, hatches, and a weighted stormwater sump. The stormwater is pumped from the surface of the floating cover. The performance of the bottom liner system and floating cover system has been exemplary for 21 years. At this time, however, it is clear from cracking in the polypropylene geomembrane that the resin is at the end of its life, and the floating cover needs to be replaced. This need is the primary driver for doing this project. Since the floating cover will be removed for the first time since its construction 21 years ago, this will also be an opportune time to remove any accumulated sludge from the pond. Cleaning the sludge and removing the leachate will also provide a clean working surface for installing the new membrane liners. 1
Even though the existing primary and secondary geomembrane pond liner appear to be performing very well at containing the leachate, the removal of the floating cover affords the opportunity to make any desired modifications to the existing liner system. The owner has decided that since the geomembranes are over 20 years old, it would be prudent to over-line the existing primary geomembrane with a new primary geomembrane. Installing a new primary geomembrane also necessitates some means of relieving any gases and liquids that might become trapped between the new and old geomembranes. Such measures have been incorporated into the new design, described below. DESIGN INTENT 2021 LEACHATE POND PRIMARY GEOMEMBRANE AND FLOATING COVER REPLACEMENT Key design intents for this project include the following: The existing integrity of the existing 60-mil HDPE primary geomembrane liner shall be maintained. The existing primary geomembrane has some important penetration seals around the outlet and the secondary riser pipe. Also its existing integrity is a valuable source of redundancy. Therefore it is the design intent that the Contractor shall take special care not to damage the existing geomembrane during cleaning and over-lining activities. Before the installation of the new primary geomembrane, the contract documents will require the conductive liner to be electrically surveyed for defects, and any found defects to be repaired. The Special Provisions do not allow cutting of any materials with razors above the existing geomembrane without the presence of 60-mil or thicker rubsheets. This will be enforced. The new geomembrane shall be a conductive smooth black (or white surfaced) 80- mil HDPE. Trial welds shall be conducted between the new material and samples taken from the existing pond. The sampling areas shall be near the crest and shall be patched. A new leakage detection and removal riser will need to be installed, necessitating a localized modification of the perimeter anchor wall. A limited leakage collection layer piping system is designed to be installed between the existing and new primary geomembranes. Also, gas vent holes need to be cut with hole saws (perfectly round with no angular corners) at the high end to allow trapped gasses to vent. The modifications to the anchor wall will necessitate the Contractor to provide and install some amount of new batten bar assembly for the floating cover. The new geomembrane shall be electrically tested for leaks. Leakage of leachate into either the existing secondary leachate collection and removal system, or the new leakage collection system between the new and existing primary geomembranes, shall be less than 50 gallons per day when the pond is in operations (current leakage rate averages approximately 25 gallons per day before construction began). This leakage rate is estimated to be the likely result of the occurrence of one “small hole” defined as having a diameter of 1/32”; or a total of four pinholes, defined as having a diameter of 1/64”; or some other combination of minor defects that would occur in the geomembranes under an average operating head of 6 feet of liquid. Contractor shall remedy leakage rates greater than this at no extra cost to Owner. 2
Some elements of piping and weight tubes on top of the existing primary geomembrane will need to be removed and later replaced to allow installation of the new primary geomembrane. All costs associated with this work are to be included in the bid. When removing the existing floating cover system for demolition, the contract assume that the following elements shall be salvaged: batten bar, stormwater sump assembly and pump, and hatches. All other elements shall be discarded and replaced with new materials. The contactor, at its option, may replace any of the intended salvage items with new materials, but at no extra cost. Note that the base bid assumption assumes that 96% of the existing ½” dia anchor bolts are re-usable, and the 6% may need to be ground off, redrilled, and epoxy set. In addition there are two locations where new batten bar assemblies are required to be supplied and installed by the Contractor: (1) where the anchor wall has to be raised to accommodate the new riser pipe, and (2) where the new primary geomembrane will liner over the top of the secondary rise pipe and need to be vertically battened to the inside of the anchor wall. For the hatches, only the aluminum frames and covers will be salvaged; new floats shall be provided for the hatches. The design intent is that the original floating cover design shall be replicated. Hence the design is based on markups of the 1999 ‘record drawings’, and no new design drawings are being provided. The most significant change in the floating cover to the original design is that the new cover is being specified as 60-mil reinforced material, whereas the original was only 45 mils. There are new project specifications for the supply and installation of the geosynthetics, contained in the Special Provisions. The project must be completed before the end of August. It is not acceptable for the County to go into the next rainy season without this project being complete. The County will intent to enforce the schedule and apply liquidated damages in full measure to ensure this schedule is met. PHOTOS OF EXISTING FLOATING COVER AND ANCHOR WALL In lieu of requiring a mandatory pre-bid meeting, it was deemed expedient to provide a series of photos showing existing site conditions. Even so, prospective bidder are welcome to visit the site ahead of time by contacting Jesse Berger as described in the bid documents. Photos on following pages. 3
STANDING ON MIDDLE OF NORTH SIDE LOOKING SW LOOKING ACROSS POND N-S AT LOCATION OF BROKEN SIDE WEIGHT TUBE CABLE 4
LOOKING N-S ON WEST END OF POND TOWARDS STORMWATER SUMP AT NW CORNER LOOKING SE TOWARDS STORMWATER SUMP 5
LOADOUT INLET DRAINS ON NORTH SIDE CENTER NORTH SIDE LOOKING AND ELECTRIC JUNCTIONS AND HATCH ABOVE POND SUMP 8
STANDING ON HATCH FLOATS AND VIEWING LEACHATE INSIDE OPEN HATCH. THE HATCH MECHANISMS SEEMED TO WORK VERY WELL. A SOUNDING OF THE LEACHATE AT THIS LOCATION WITH A 1X4 TO THE POND BOTTOM DID NOT INDICATE THE PRESENCE OF ANY SLUDGE. PREPARING TO WALK DOWN FLOATS TO STORMWATER SUMP. THE LINER FROM THE TOP FLOAT HAD BEEN CUT OFF FOR SAMPLING AND TESTING 9
STANDING AT STORMWATER SUMP LOOKING BACK TO THE NORTH STANDING AT STORMWATER SUMP LOOKING EAST 10
STANDING AT STORMWATER SUMP TO SW CORNER STANDING AT STORMWATER SUMP TO NW CORNER 11
STORMWATER SUMP VIEW OF CRACKED RESIN ON FLOATING COVER 12
ON NORTH SIDE LOOKING EAST. NOTE REMOVED BATTEN BAR TYPICAL VIEW UNDER FLOATING COVER NEXT TO ANCHOR WALL ON NORTH SIDE 13
VIEW UNDER FLOATING COVER NEXT TO ANCHOR WALL SHOWING EXTRUSION WELD UNDER GLOVE OF SECONDARY GEOMEMBRANE TO EMBEDMENT STRIP. THE EXTRUSION WELD UNDER THE HAMMER IS THE PRIMARY GEOMEMBRANE TO THE SECONDARY GEOMEMBRANE. THE INTENT IS FOR THE NEW PRIMARY GEOMEMBRANE TO BE WELDED BETWEEN THESE TWO WELDS TO THE EXISTING SECONDARY GEOMEMBRANE. THE INSIDE OF THE ANCHOR WALL WAS STRUCK WITH HAMMERS AND CROW BARS AND THE CONCRETE FOUND TO BE VERY SOUND. THERE WERE NOT PARTICULARLY STRONG ODORS OR NOXIOUS SMELLS BELOW THE COVER 14
BATTEN BARS REMOVED AND FLOATING COVER BEING PRYED AWAY FROM ANCHOR BOLTS ON EAST END 15
CONDITION OF EXISTING GEOMEMBRANES AND CONCRETE ANCHOR WALL ON EAST END APPEARED SIMILAR TO NORTH SIDE: VERY GOOD CONDITION. CONCRETE WAS SOLID AND HARD. 16
REMOVAL OF ANCHOR BOLTS ON SOUTH SIDE 17
EXAMPLE OF ‘BATTEN DETAIL USING EX. ANCHOR WALL’ REPAIR SHOWN ON DETAIL 1 OF DRAWING C26 FROM 1999 ON SOUTH SIDE. REASON FOR REPAIR IN 1999 IS NOT KNOWN, BUT IT APPEARS IN GOOD CONDITION AND NEW PRIMARY GEOMEMBRANE WELD COULD OCCUR JUST IN FRONT OF THIS. EXAMPLE OF ‘BATTEN DETAIL USING 12” CONCRETE BLOCK’ REPAIR SHOWN ON DETAIL 2 OF DRAWING C26 FROM 1999 ON SOUTH SIDE. REASON FOR REPAIR IN 1999 IS NOT KNOWN, BUT IT APPEARS IN GOOD CONDITION AND NEW PRIMARY GEOMEMBRANE WELD COULD OCCUR JUST IN FRONT OF THIS. 18
BATTENS REMOVED ON WEST END. AS AT ALL OTHER LOCATIONS, CONDITION OF EXISTING GEOMEMBRANES AND CONCRETE ANCHOR WALL BELOW FLOATING COVER APPEARED VERY GOOD. END 19
You can also read