CONSTRUCTION TRAFFIC AND
ACCESS MANAGEMENT PLAN
Moorebank Precinct West Stage 2 and
Moorebank Precinct West Stage 3

14 SEPTEMBER 2021
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN

 SYDNEY INTERMODAL TERMINAL ALLIANCE
 PROJECT

 Moorebank Precinct West Stage 2 and Stage 3
 Construction Traffic and Access Management Plan

 Version Author

 Version Checker

 Version Approver

 Report No                            MIC2-QPMS-EN-PLN-0003

 Date                                 14/09/2021

 Revision Text                        M

This Construction Traffic and Access Management Plan meets the requirements under SSD 7709 MPW Stage
2 Condition of Consent B113, and SSD 10431 MPW Stage 3 Condition of Consent B20 as a management 'sub-
plan'.

 Original Author Details

  Author Details                       Qualifications and Experience

                                              has four years of experience in traffic and transportation
                                      engineering in both public and private sectors.          is experienced in
                 BE (Civil)(Hons)
                                      assessing traffic, transport and parking impacts through her
                                      involvement in various small to large scale developments.

                                               has over sixteen years of consulting experience in the field of
                                      traffic and transport planning for a broad cross-section of clients across
                                      the Australasian region.     has developed a range of skills through his
                                      involvement in projects such as traffic impact assessments, traffic
                   BE (Civil)(Hons)   modelling studies, car park design, Local Area Traffic Management
                                      (LATM) studies, construction traffic management planning, traffic
                                      control plans and roads safety audits.
                                            was endorsed as a suitably qualified person on 7 February 2018
                                      by DP&E.

                                                                                                              ii
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN

 Author Details                    Qualifications and Experience

                                         has four years environmental assessment and planning
                                  experience.       has experience in the preparation of and updates to
                                  management plans and sub-plans, including the preparation of
                                  construction traffic and access management plans and sub-plans.

REVISIONS
 Revision   Date         Description                                         Prepared by   Approved by

 A          Aug 2018     Draft – Internal Review                               /

 B          02/11/2018   Issued to ER

 C          17/12/2018   Updated to address ER comments

                         Updated to reflect Recommended Conditions of
 D          30/08/2019                                                             /
                         Consent

 E          24/10/2019   Updated to address ER comments on Rev D

 F          22/01/2020   Updated to address LCC comments

                         Updated to include a consultation summary and
 G          30/01/2020
                         for ER endorsement

                         Updated to address ER comments for ER
 H          10/02/2020
                         endorsement

 I          25/03/2020   Updated to address DPIE comments                      /

 J          22/03/2021   Updated in response to MOD 1

 K          15/06/2021   Updated to include CTAMP requirements of MPW
                         Stage 3 (SSD 10431)
 L          20/07/2021   Updated in accordance with ER comments on
                         Rev K.
 M          14/09/2021   Updated to reflect additional construction access
                         location.

                                                                                                          iii
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONTEXT
This Construction Traffic and Access Management Plan (CTAMP) is for construction activities being undertaken
at the Moorebank Precinct West (MPW) Site, in Moorebank, New South Wales under the MPW Stage 2
(SSD 7709) development consent and the MPW Stage 3 (SSD 10431) development consent.

This CTAMP was originally approved by the Department of Planning, Industry and Environment (DPIE) in
accordance with condition of consent (CoC) B113 of the MPW Stage 2 (SSD 7709) development consent prior
to the commencement of construction of the MPW Stage 2 Project.

The MPW Stage 3 (SSD 10431) development consent was issued by the Independent Planning Commission on
11 May 2021 and CoC B20 of that development consent requires the preparation of a CTAMP for the Project
for approval by the Planning Secretary. CoC B19 of the MPW Stage 3 (SSD 10431) development consent
allows for the expansion of the existing MPW Stage 2 CTAMP to cover the MPW Stage 3 development and
satisfy the requirements of CoC B20 of that development consent.
The CTAMP has been prepared accordingly and satisfies the requirements of CoC B113 of the MPW Stage 2
(SSD 7709) development consent and CoC B20 of the MPW Stage 3 (SSD 10431) development consent.

                                                                                                        iv
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN
ACRONYMS AND DEFINITIONS
Acronym/Term         Meaning

AS1742               Australian Standard 1742 – Manual of Uniform Traffic Control Devices

Ave. Delay           Average Delay

CCS                  Community Communication Strategy

CEC                  Community Engagement Consultant

CEMP                 Construction Environmental Management Plan

Contractor’s CLM     Contractor’s Community Liaison Manager

Contractor’s CM      Contractor’s Construction Manager

Contractor’s EM      Contractor’s Environmental Manager

Contractor’s PM      Contractor’s Project Manager

CoCs                 Conditions of Consent

CTAMP                Construction Traffic and Access Management Plan

CTIA                 Construction Traffic Impact Assessment

DAWE                 Department of Agriculture, Water and the Environment

DPIE                 NSW Department of Planning, Industry and Environment

DotEE                Department of the Environment and Energy merged with all functions of the Department
                     of Agriculture (February 2020) to form the Department of Agriculture, Water and the
                     Environment (DAWE)

EB/WB                Eastbound/Westbound

EIS                  Environmental Impact Statement

EPA                  Environment Protection Authority

FCMM                 Final Compilation of Mitigation Measures. These are the management and mitigation
                     measures (2 November 2018) included in Appendix 2 of the SSD 7709 Consent. The
                     revised FCMM as applicable to MPW Stage 3 are included in Appendix 3 of the SSD
                     10431 consent.

IMT                  Intermodal Terminal

IMT facility         The IMT facility includes the construction of the following key components together
                     comprising the Intermodal Terminal:
                     •   Truck processing and loading areas
                     •   Rail loading and container storage areas
                     •   Administration facility and associated car parking.

IPC                  Independent Planning Commission

km                   Kilometre

                                                                                                            v
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN

Acronym/Term              Meaning

LGA                       Local Government Area

LoS                       Level of Service

m                         Metre

MAAI                      Moorebank Avenue, Anzac Road Intersection

Minister, the             Minister of Department of Planning and Environment

MOD 1                     Modification 1 to SSD 7709, granted by the IPC 24 December 2020.

MPE                       Moorebank Precinct East

MPW                       Moorebank Precinct West

NB/SB                     Northbound/Southbound

PCTAMP                    Preliminary Construction Traffic and Access Management Plan

Project, the              The development of an intermodal freight precinct including associated commercial
                          infrastructure (i.e. warehousing), a rail connection, upgraded intersection on Moorebank
                          Avenue, subdivision of the MPW Site, provision of a works compound and material
                          storage areas, and associated works as approved by the MPW Concept Plan, MPW
                          Stage 2 (SSD 7709) and MPW Stage 3 (SSD 10431).

REMM                      Revised Environmental Management Measures. These are the management and
                          mitigation measures presented in the MPW Concept Plan (SSD 5066) Supplementary
                          RtS (August 2017).

RMS                       Roads and Maritime Services (now TfNSW)

ROL                       Road Occupancy License

RtS                       Response to Submissions

SIMTA                     Sydney Intermodal Terminal Alliance

SSD                       State significant development

SZA                       Speed Zone Authorisation

TCP                       Traffic Control Plan

TCS                       Traffic Control Signal

TfNSW                     Transport for New South Wales

The MPW Stage 2 Project   The MPW Stage 2 Project involves the construction and operation of a multi-purpose IMT
                          facility, rail link connection, warehousing and upgraded Moorebank Avenue intersection as
                          described in Section 4.1 of the MPW Stage 2 EIS, and as approved under SSD 7709.

The MPW Stage 3 Project   The MPW Stage 3 Project involves the progressive subdivision of the MPW Site into nine
                          allotments, importation of unconsolidated clean fill for compaction up to final land level and
                          structural fill for warehouse pad completion, establishment of a temporary works
                          compound area in the southern portion of the MPW Site, and ancillary development, as
                          approved under SSD 10431.
TMP                       Traffic Management Plan
                                                                                                                      vi
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN

Acronym/Term         Meaning

Warehouse JN        The warehouse known as Warehouse JN, identified as Warehouse 6 in the plan titled
                    ‘Precinct Modification Plan — Proposed’ (Drawing No JR-SK-A-0-9402, Revision G),
                    prepared by Bell Architecture and dated 16 October 2020)

VMS                  Variable Messaging System

Warehouse JR         The warehouse known as Warehouse JR, identified as Warehouse 5 in the plan titled
                     ‘Precinct Modification Plan — Proposed’ (Drawing No JR-SK-A-0-9402, Revision G),
                     prepared by Bell Architecture and dated 16 October 2020)

                                                                                                         vii
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
CONTENTS
REVISIONS .......................................................................................................................................................... 3
CONTEXT ............................................................................................................................................................. 4
ACRONYMS AND DEFINITIONS ........................................................................................................................ 5
1 INTRODUCTION ............................................................................................................................................... 1
1.1 Development Consent .................................................................................................................................... 2
1.2 Purpose .......................................................................................................................................................... 2
1.3 Objectives and Targets ................................................................................................................................... 3
1.4 Consultation .................................................................................................................................................... 4
2 ENVIRONMENTAL MANAGEMENT ..............................................................................................................10
2.1 Legal and Other Obligations .........................................................................................................................11
2.2 Training .........................................................................................................................................................19
3 IMPLEMENTATION ........................................................................................................................................20
3.1 Existing Environment ....................................................................................................................................20
3.2 Construction Overview ..................................................................................................................................21
3.3 Construction Traffic Management ................................................................................................................29
3.4 Stakeholders Communication .......................................................................................................................30
3.5 Management Measures ................................................................................................................................31
4 MONITORING AND REVIEW .........................................................................................................................41
4.1 Environmental Monitoring .............................................................................................................................41
4.2 Site Inspections ............................................................................................................................................42
4.3 Inspection of Traffic Controls ........................................................................................................................43
4.4 Environmental Auditing and Reporting .........................................................................................................43
4.5 Review and Improvement .............................................................................................................................43
4.6 Non-Compliance and Non-Conformance ......................................................................................................43
4.7 Complaints ....................................................................................................................................................43
COMPLIANCE AND OBLIGATIONS REGISTER .............................................................................................44
                    Evidence of Consultation ...........................................................................................................52
                    Driver’s Code of Conduct ...........................................................................................................53
Purpose and Objective .......................................................................................................................................53
Responsibilities of Drivers ..................................................................................................................................53
Monitoring ...........................................................................................................................................................54
                    Traffic Control Plan (TCP195).....................................................................................................56
                    Oversize Vehicle Fact Sheet .......................................................................................................57
                   Fill Importation Management Protocol ......................................................................................58
Introduction .........................................................................................................................................................59
Purpose and Objective .......................................................................................................................................59
Procedure ...........................................................................................................................................................59
Forecasting Fill Import Requirements .................................................................................................................59

                                                                                                                                                                  viii
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
Forecasting Truck Movement Requirements......................................................................................................59
Monitoring Material as it enters the Site .............................................................................................................59
Reporting and Documentation ............................................................................................................................60

APPENDICES
                     COMPLIANCE AND OBLIGATIONS REGISTER
                     EVIDENCE OF CONSULTATION
                     DRIVER’S CODE OF CONDUCT
                    TRAFFIC CONTROL PLAN (TCP195)
                    OVERSIZE VEHICLE FACT SHEET
                    FILL IMPORTATION MANAGEMENT PROTOCOL

LIST OF TABLES
Table 1-1 Objectives and Targets ..................................................................................................................... 4
Table 1-2 Consultation Summary ...................................................................................................................... 4
Table 2-1 Legislation, Planning Instruments and Guidelines ............................................................................ 7
Table 2-2 Conditions of Consent (CoCs) ........................................................................................................... 8
Table 2-3 Final Compilation of Mitigation Measures (FCMMs) ......................................................................... 9
Table 2-4 EPBC Act Approval ......................................................................................................................... 11
Table 2-5 Roles and Responsibilities .............................................................................................................. 12
Table 3-1 Summary of Existing Road Network ................................................................................................ 14
Table 3-2 Peak Hour Traffic Volumes on Key Roads in 2015 ......................................................................... 15
Table 3-3 Defect Rating and Response Timing............................................................................................... 25
Table 3-4 Management Measures ................................................................................................................... 27
Table 4-1 Environmental Monitoring ................................................................................................................ 34

LIST OF FIGURES
Figure 1-1 Site Location .....................................................................................................................................2
Figure 1-2 MPW Stage 3 Site layout…………………………………………………………………………………..3
Figure 3-1 Heavy Vehicle Route Plan.............................................................................................................. 22
Figure 3-2 Heavy Vehicle Route Plan (indicative fill sources and spoil destinations) ..................................... 23
Figure 3-3 Location and Access Points of Project Compounds ...................................................................... 25
Figure 3-4 WAD and IAD Areas....................................................................................................................... 28

                                                                                                                                                           ix
CONSTRUCTION TRAFFIC AND ACCESS MANAGEMENT PLAN - Moorebank Precinct West Stage 2 and Moorebank Precinct West Stage 3 - SIMTA
1 INTRODUCTION
The Sydney Intermodal Terminal Alliance (SIMTA) received approval for the construction and operation of
Stage 2 of the Moorebank Precinct West (MPW) Project (State Significant Development (SSD) 7709), (the
Project) and subsequently Modification 1 (MOD1), which comprises the second stage of development under
the MPW Concept Approval (SSD 5066). SSD 10431 MPW Stage 3 was approved by the Independent
Planning Commission (IPC) on 11 May 2021. This Construction Traffic and Access Management Plan
(CTAMP) has been developed to manage traffic and access impacts during the construction of the
Moorebank Precinct West (MPW) Project and meets relevant SSD 7709 and SSD 10431 Conditions of
Consent (CoC).
Within this plan, a strategy has been established to demonstrate the Construction Contractor’s approach to
the management of traffic and access impacts. This CTAMP addresses the relevant requirements of the SSD
7709 (MPW Stage 2) and SSD 10431 (MPW Stage 3) development Consents, including the Environmental
Impact Statement (EIS), Response to Submissions (RtS) and Minister’s CoCs, and the applicable guidelines
and standards specific to the environmental management of construction traffic and access during the
construction phase of the Project, and applies to approved development works under both consents (and as
modified). In accordance with MPW Stage 3 CoC B16, this CTAMP has been prepared having regard to the
Environmental Management Plan Guideline: Guideline for Infrastructure Projects (DPIE April 2020).
The MPW Stage 2 Project involves the construction and operation of a multi-purpose Intermodal Terminal
(IMT) facility, raillink connection, warehousing, freight village, and upgrades to the Moorebank Avenue and
Anzac Road intersection. A detailed description of the Project is provided in CEMP Section 1.2.
The location of the MPW Stage 2 Project Site is shown in Figure 1-1.
The MPW Stage 3 Project involves the progressive subdivision of the MPW Site into nine allotments,
importation of unconsolidated clean fill for compaction up to final land level and structural fill for warehouse
pad completion, establishment of a temporary works compound area in the southern portion of the MPW
Site, and ancillary development. In accordance with MPW Stage 3 CoC B19, the approved MPW Stage 2
management plans have been updated to reflect MPW Stage 3 Consent requirements. The MPW Stage 3
Site is located wholly within the MPW Stage 2 construction footprint in the southern portion of the site and is
shown in Figure 1-2.

                                                                                                                   1
Figure 1-1 MPW Stage 2 site location

                                       1
Figure 1-2 MPW Stage 3 site location and layout

                                                  1
1.1 Development Consent

 1.1.1 SSD 7709 - MPW Stage 2
 The MPW Stage 2 Project has been assessed by the Department of Planning and Environment (DP&E)
 under Part 4, Division 4.1 (now Division 4.7 as of 1 March 2018) of the Environmental Planning and
 Assessment Act 1979 (EP&A Act) as State significant development (SSD). The Independent Planning
 Commission granted approval for the MPW Stage 2 Project on 11 November 2019 and is subject the CoCs
 (SSD 7709) with MOD1 approved on 24 December 2020. The Project, including its potential impacts,
 consultation and proposed mitigation and management is documented in the following suite of documents:
 •   State significant development (SSD) Consent SSD 7099
 •   Modification to Development Consent SSD 7709 MOD1
 •   Moorebank Precinct West – Stage 2 – Environment Impact Statement (Arcadis Australia Pacific Pty
     Limited, October 2016)
 • Moorebank Precinct West – Stage 2 Proposal – Construction Traffic Impact Assessment (CTIA) (Arcadis
   Australia Pacific Limited, October 2016)
 • Moorebank Precinct West – Stage 2 Proposal – Preliminary Construction Traffic Management Plan
   (PCTMP) (Arcadis Australia Pacific Limited, October 2016)
 • Moorebank Precinct West – Stage 2 Proposal – Response to Submissions, Revised CTIA (Arcadis
   Australia Pacific Pty Limited, June 2017)
 •   Moorebank Precinct West – Stage 2 – Response to Submissions (Arcadis Australia Pacific Pty Limited,
     July 2017)
 •   Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) Approval (No. 2011/6229)
     granted on 27 September 2016.

 1.1.2 SSD 10431 - MPW Stage 3

SSD 10431 MPW Stage 3 was approved by the IPC on 11 May 2021. The MPW Stage 3 development, including
proposed impacts, consultation and proposed mitigation and management is provided in the following suite of
documents:
 •   SSD 10431 Consent
 •   Moorebank Precinct West - Stage 3 Environmental Impact Statement (SSD 10431) (Aspect Environmental,
     April 2020)
 •   Transport Assessment - Moorebank Intermodal Precinct West - Stage 3 (SSD 10431) (Ason Group, April
     2020)
 •   Moorebank Precinct West - Stage 3 Response to Submissions (SSD 10431) (Aspect Environmental, July
     2020)
 •   Transport Assessment - Moorebank Intermodal Precinct West - Stage 3 (SSD 10431) (Response to
     Submissions) (Ason Group, July 2020).

 1.2 Purpose
 This CTAMP has been developed to address the CoCs and the Final Compilation of Mitigation Measures
 (FCMMs) for MPW Stage 2 and revised management and mitigation measures as Final Compilation of
 Mitigation Measures (FCMM) for MPW Stage 3, provided as Appendix 3 of the SSD 10431 development
 consent. This plan aims to demonstrate how impacts to traffic and access will be managed during
 construction of the Project. This plan provides methods to measure and reduce the impact to traffic and
 access by the Construction Contractor during construction, including all sub-contractor and consultant
 partners.
 This CTAMP provides a structured approach to manage traffic, access and road safety issues for the
 duration of the Project’s construction activities to provide a safe road environment, minimise impact on the

                                                                                                                2
surrounding road network and maintain access for all road users and the local community.
Specifically, the purpose of this CTAMP is to:
•   Detail the measures to be implemented to ensure road safety and network efficiency during construction.
•   Provide a heavy vehicle route plan.
•   Detail access and parking arrangements.
•   Detail procedures for notifying residents and community of any potential traffic disruptions.
The most recent, approved version of this plan will be implemented to manage the Project activities.

1.2.1 Scope of MPW Stage 3 Updates
The key components of the approved MPW Stage 3 works, which fit entirely within the approved MPW Stage 2
development footprint, are:
•   Establishment of a construction compound to facilitate approved site development works for the MPW site
    (as per the MPW Concept Plan and Stage 1 Early Works Approval (SSD 5066), MPW Stage 2 Approval
    (SSD 7709)) and future MPW site development, and includes hardstand, laydown and materials stockpile
    areas, temporary and permanent access roads, and installation of utilities and services.
•   Progressive subdivision of the MPW site to create nine allotments for the purpose of creating separate lots
    for the IMT, rail corridor, warehousing, and biodiversity conservation allotments (being proposed lots 5 to 13
    inclusive).
•   Ancillary works to facilitate establishment, access and servicing of the proposed application. Works will be
    progressively undertaken and include temporary and permanent access roads, earthworks, utilities
    installation/connection, stormwater and drainage infrastructure, signage and landscaping.
The scope of MPW Stage 3 construction traffic in relation to MPW Stage 2 is summarised as follows:
•   In accordance with the approved CTAMP for MPW Stage 2, construction access for MPW Stages 2 and 3
    will be provided by the existing Chatham Avenue – Moorebank Avenue intersection. Discussions are
    currently underway with TfNSW and LCC regarding an additional construction access point(s) to the north of
    Chatham Avenue for approved MPW Stage 2 and MPW Stage 3 works when Chatham Avenue is closed for
    works on the IMT rail corridor in the second half of 2021, and the CTAMP will be further revised to
    accommodate any changes to construction access points.
•   There will be no change to external heavy vehicle construction haulage routes that have already been
    approved under MPW Stage 2 (refer to Figures 3-1 and 3-2).
•   There will be no change to the types or volumes of construction vehicles, or the construction hours of
    operation already approved under MPW Stage 2, to accommodate MPW Stage 3 development works. Under
    MPW Stage 3 CoC A8, importation of fill material has been limited to 13,000 m3 of material per day across
    the MPW Stage 2 and MPE Stage 2 construction sites (refer to Section 3.2.3). Construction of approved
    MPW Stage 3 ancillary works and establishment of the works compound will largely generate internal traffic
    movements.
•   Cumulative light and heavy vehicle construction traffic numbers remain within those currently approved for
    MPE and MPW and no additional cumulative traffic movements are proposed, as traffic transfer movements
    would be generated internally from within MPW rather than from within MPE. Haulage routes for internal
    transfer of materials from MPW to MPE would be limited to either the Chatham Road or Anzac Road access
    from the MPW Site to Moorebank Avenue, and entry to the MPE Site via the existing site access point on
    Moorebank Avenue.
•   An indicative cumulative construction timeline for MPW Stages 2 and 3 and MPE Stage 2 is provided in
    Appendix G [This timeline was attached to the MPW Stage 3 RtS, and will be attached to the CTAMP as
    Appendix G].
The MPW Stage 3 scope is reflected in minor updates to the approved MPW Stage 2 CTAMP to accommodate
MPW Stage 3 conditions (i.e. this Plan).

1.3 Objectives and Targets
Table 1-1 outlines the objectives and targets set out for the Project for the management of traffic and access
during construction. These objectives and targets were developed by the Principal’s Representative based
on collective industry experience and best practice.

                                                                                                                     3
Table 1-1 Objectives and Targets

 Objective                                                   Target                            Timeframe          Accountability

                                                             No death or injury to
                                                             workers and the public, or
 Provide a safe environment for road users                                                     Duration of
                                                             damage to property, as a                             Contractor’s CM
 during construction                                                                           Construction
                                                             result of construction
                                                             related traffic activities

                                                             All notifications issued prior
 Minimise disruption to road users and access to                                               Duration of
                                                             to relevant works                                    Contractor’s CM
 adjoining properties (private and public)                                                     Construction
                                                             commencing

                                                             Zero obstruction to               Duration of
 Maintain access for emergency services                                                                           Contractor’s CM
                                                             emergency access                  Construction

^ Further details on the key roles and responsibilities associated with this CTAMP are provided in Section 2.2.

1.4 Consultation
This plan was prepared for MPW Stage 2 in consultation with Liverpool City Council, Campbelltown City
Council and was endorsed by Transport for NSW (TfNSW) and Roads and Maritime Services (RMS), as
outlined in Table 1-2. In July 2021, this CTAMP was further revised (Revision L) to accommodate MPW
Stage 3 CoC. Supplementary information to support the consultation undertaken and subsequent
endorsement provided is included in Appendix B.
Liverpool City Council were consulted on the change of construction site access arrangements included in
Revision M of this CTAMP. Designs of works and supportive traffic modelling relating to the use of
Bapaume Road as a construction access point have been presented to Liverpool City Council. Works to
establish the construction access and it’s subsequent use for construction-related traffic is subject to review
by Council’s Local Traffic Committee and issuing of a Section 138 Certificate.

Table 1-2 Consultation Summary

 Agency               Date            Person Contacted             Comment                                           Status

                                                                   Draft CTAMP provided for review and
                      01/11/2019      LCC representative           comment via email. Phone call followed the        Open
                                                                   email.

                                                                   Follow up phone call requesting an update
                      08/11/2019      LCC representative                                                             Open
                                                                   on progress of review

                                                                   Email sent indicating that CTAMP had been
                      12/11/2019      SIMTA representative                                                           Open
                                                                   received and would be reviewed

                                                                   Email sent indicating that MPW Stage 2 had
                                                                   been approved and a response to the
                      12/11/2019      LCC representative                                                             Open
                                                                   CTAMP is requested to be received within 2
                                                                   weeks by 25 November 2019.
 Liverpool City
 Council              22/11/2019      LCC representative           Email sent to follow up progress of review        Open

                                                                   Email sent indicating that CTAMP would be
                      22/11/2019      SIMTA representative                                                           Open
                                                                   reviewed by 25/11/2019

                      06/12/2019      LCC representative           Email sent to follow up progress of review        Open

                                                                   Email sent providing comments on the
                      06/12/2019      SIMTA representative                                                           Open
                                                                   CTAMP

                                                                                                                                    4
12/12/2019    LCC representative      Email sent responding to LCC comments           Open

                                                Phone call indicating comments had been
          12/12/2019    SIMTA representative    received and LCC would respond the week         Open
                                                starting 16/12/2019

Agency    Date          Person Contacted        Comment                                         Status

                                                Phone call had between LCC and SIMTA
                                                representatives. LCC indicated that
         17/12/2019     SIMTA representative    Liverpool Local Traffic Committee didn’t        Open
                                                have responsibility for comments on the
                                                CTAMP. This was confirmed via email.

                                                Meeting held between LCC and SIMTA
         17/01/2020     SIMTA representative    representatives to discuss issues raised by     Open
                                                LCC.

                                                Email sent providing a response to issues
         22/01/2020     LCC representative                                                      Open
                                                raised and updated CTAMP

                                                Email sent confirming that consultation with
         28/01/2020     SIMTA representative                                                    Closed
                                                LCC is considered closed.

         7/06/2021     LCC representative       Phone call between LCC and SIMTA               Closed
                                                representative to discuss updates to MPW
                                                Stage 2 CTAMP to accommodate MPW
                                                Stage 3 conditions and schedule a
                                                consultation meeting. LCC advised they
                                                would provide meeting dates

         8/06/2021     SIMTA representative /   LCC advised by email potential meeting         Closed
                       LCC representative       dates to discuss MPW Stage 3 CTAMP;
                                                reply email to schedule meeting date

         14/06/2021    LCC representative       Email to LCC, providing draft CTAMP and        Closed
                                                meeting schedule

         15/06/2021    LCC representatives /    TEAMs meeting between LCC                      Closed
                       SIMTA representative     representatives and SIMTA representative
                                                to discuss updates to approved MPW
                                                Stage 2 CTAMP to accommodate MPW
                                                Stage 3 conditions

         16/06/2021    LCC representative       Email sent to advise LCC representative        Closed
                                                regarding phone discussion with TfNSW
                                                (15/06/2021), and provide copies of emails
                                                sent to TfNSW.

         23/06/2021    LCC representative       Email sent to follow up provision of           Closed
                                                comments on the CTAMP

         24/06/2021    LCC representative       Follow up email and phone calls regarding      Closed
                                                provision of comments on the CTAMP; left
                                                messages

         24/06/2021    LCC representative       Advised by LCC representative that             Open
                                                comments regarding the CTAMP would be
                                                provided the following week

                                                                                                         5
29/06/2021   SIMTA representative   Email sent from LCC providing comment          Closed
                                    regarding the CTAMP

30/06/2021   LCC representative     Revised CTAMP including LCC comments           Closed
                                    provided to LCC for review and final
                                    comment

5/07/2021    LCC representative     Email sent to follow up provision of receipt   Closed
                                    of response, and close out of consultation

                                                                                   Closed
7/07/2021    SIMTA representative   Email and letter sent confirming that
                                    consultation with LCC is considered

                                    Email sent requesting meeting to discuss
19/07/2021   SIMTA representative   change to CTAMP to accommodate                 Closed
                                    construction access rearrangements.
                                    Updated CTAMP will be Rev M.

                                    Email sent confirming availability for
21/07/2021   LCC representative     meeting and providing Microsoft Teams          Closed
                                    meeting invitation.

                                    Email sent with meeting agenda, Bapaume
2/07/2021    SIMTA representative   Access concept design, traffic modelling       Closed
                                    assessment and technical memo.

             LCC representative/    Microsoft Teams meeting between LCC
23/07/2021                                                                         Closed
             SIMTA representative   and SIMTA representatives.

                                    Meeting minutes sent to LCC followed by
27/06/2021   SIMTA representative   updated design drawings and traffic            Open
                                    modelling assessment to inform LCC Local
                                    Traffic Committee.

10/08/2021 SIMTA representative Draft CTAMP Rev M provided to LCC for              Open
                                    comment.

17/08/2021 SIMTA representative Follow up email sent requesting an update          Open
                                    on progress of review.

                                    Completed RSA and 100% detailed design
24/08/2021 SIMTA representative provided to LCC to inform LCC Local                Open
                                    Traffic Committee.

25/08/2021 SIMTA representative Follow up email sent requesting an update          Open
                                    on progress of review.

2/09/2021    SIMTA representative Follow up email sent requesting an update        Open
                                    on progress of review.

9/09/2021    SIMTA representative Follow up email sent requesting                  Open
                                    confirmation on close out of comment.

                                                                                            6
Draft CTAMP provided for review and
                01/11/2019    CCC representative     comment via email. Phone call followed the     Open
                                                     email.

                                                     Follow up phone call requesting an update
                08/11/2019    CCC representative                                                    Open
                                                     on progress of review
Campbelltown
City Council                                         Follow up email requesting an update on
                22/11/2019    CCC representative                                                    Open
                                                     progress of review

                                                     Email sent indicating CCC had no objection
                                                     to the CTAMP as long as heavy vehicles
                02/12/2019    SIMTA representative                                                  Closed
                                                     are prohibited from using Cambridge
                                                     Avenue

                                                     Draft CTAMP provided for review and
                11/12/2019    RMS representative                                                    Open
                                                     comment
Roads and
Maritime                                             Email sent indicating that RMS had been
                18/12/2019    SIMTA representative   advised by TfNSW that consultation would       Closed
                                                     be with LCC and not RMS.

                              TfNSW                  Draft CTAMP provided for review and
                11/12/2019                                                                          Open
                              representative         comment via email.

                                                     Email sent indicating that the CTAMP would
                                                     need to be submitted to LCC Local Traffic
                                                     Committee for review/approval and TfNSW
                                                     will provide comments for the CTAMP in
                11/12/2019    SIMTA representative                                                  Open
                                                     consultation with the LCC Local Traffic
                                                     Committee. TfNSW noted that they were
                                                     unable to view the CTAMP on the DPIE
Transport for                                        portal
NSW
                                                     Email sent indicating consultation had
                              TfNSW                  commenced with TfNSW. DPIE noted that
                11/12/2019                                                                          Open
                              representative         consultation could be undertaken outside
                                                     the DPIE portal.

                              TfNSW
                13/12/2019                           Email sent providing CTAMP for comment.        Open
                              representative

                13/12/2019    SIMTA representative   Email sent reiterating that TfNSW will         Open
                                                     provide comments in consultation with LCC

                                                     Local Traffic Committee and to ensure a
                                                     copy of the CTAMP is provided to LCC

                                                     Email sent noting that SIMTA are consulting
                              TfNSW
                18/12/2019                           with LCC and that consultation with TfNSW      Closed
                              representative
                                                     is considered closed.

                9/06/2021    TfNSW representative    Email sent summarising revisions to MPW       Closed
                                                     Stage 2 CTAMP to accommodate MPW
                                                     Stage 3 conditions, and requesting
                                                     schedule of a consultation meeting

                11/06/2021   TfNSW representative    Follow up email to schedule a meeting with    Closed
                                                     TfNSW

                                                                                                             7
15/06/2021   SIMTA representative   Discussions between TfNSW and SIMTA          Closed
                                    representatives regarding updates to
                                    approved MPW Stage 2 CTAMP to
                                    accommodate MPW Stage 3 conditions.
                                    SIMTA representative sent email with draft
                                    CTAMP and clarification details regarding
                                    CTAMP.

15/06/2021   TfNSW representative   Email sent with attached draft CTAMP and     Closed
                                    clarification details regarding CTAMP.

15/06/2021   SIMTA representative   Email sent advising TfNSW contact to         Closed
                                    review CTAMP, and further clarification
                                    required

15/06/2021   TfNSW representative   Email sent with attached draft CTAMP and     Closed
                                    clarification details regarding CTAMP.

23/06/2021   TfNSW representative   Email sent to follow up provision of         Closed
                                    comments on the CTAMP

23/06/2021, TfNSW representative    Follow up emails and phone calls regarding   Closed
24/06/2021                          provision of comments on the CTAMP; left
and                                 messages
25/06/2021

25/06/2021   TfNSW representative   Advised by TfNSW representative that         Closed
                                    comments regarding the CTAMP would be
                                    provided the following week

29/06/2021, TfNSW representative    Follow up email regarding provision of       Closed
1/07/2021                           comments on the CTAMP
and
5/07/2021

6/07/2021                           Email advising that TfNSW has had an
             SIMTA representative                                                Closed
                                    internal restructure and request for MPW
                                    Stage 3 CTAMP review and comment has
                                    been forwarded to the Customer Journey
                                    Planning Operations (CJPO) team for
                                    review and response.

20/07/2021   TfNSW representative   Follow up email to TfNSW regarding           Open
             and SIMTA              provision of comments on CTAMP. Reply
             representative         email from TfNSW providing contact details
                                    for CJPO team. Email to TfNSW CJPO
                                    team regarding provision of comments.

                                    Consultation between SIMTA and TfNSW
            TfNSW representative    regarding additional construction access
7/12/2020 –
8/04/2021
            and SIMTA               points onto MPW focussing on the 4th leg of Closed
            representative          the Moorebank Avenue / Anzac Road
                                    intersection (MAAI).

                                    TfNSW requested SIMTA consider
8/04/2021    TfNSW representative   alternative construction access points to    Closed
                                    MAAI, including Bapaume Road.

                                    During a MAAI design meeting, TfNSW
             TfNSW representative   advised they would be unlikely to provide
15/04/2021   and SIMTA              Section 87 approval for MAAI access, and     Closed
             representative         that an alternative access should be
                                    considered. Bapaume Road access option

                                                                                          8
discussed.

             TfNSW representative   During a MAAI design meeting, SIMTA
22/04/2021   and SIMTA              discussed preparation of Bapaume Road         Closed
             representative         access concept design. No comments from
                                    TfNSW.

9/05/2021    SIMTA representative   Bapaume Road construction access              Closed
                                    concept design submitted to TfNSW.

                                    SIMTA advised TfNSW that work on a
10/05/2021   SIMTA representative   construction access at MAAI is on hold        Closed
                                    given TfNSW advice on 15/04/2021.

                                    TfNSW requested consolidated submission
10/05/2021   TfNSW representative   of Bapaume Road construction access           Closed
                                    documents.

                                    Updated concept design of Bapaume Road
10/06/2021   SIMTA representative   construction access for MPW submitted to      Closed
                                    TfNSW

2/07/2021    TfNSW representative   TfNSW provided comments on updated            Open
                                    concept design for Bapaume Road access.

                                    SIMTA informed TfNSW that DPIE advice
2/07/2021    SIMTA representative   had indicated addition of Bapaume Road        Closed
                                    construction access could be facilitated by
                                    a CTAMP update.

                                    TfNSW advised the updated CTAMP would
8/07/2021    TfNSW representative   need to be submitted to Customer Journey      Closed
                                    Planning Operations.

10/08/2021   SIMTA representative   Draft CTAMP Rev M provided to TfNSW for Closed
                                    comment.

17/08/2021   SIMTA representative   Follow up email sent requesting an update     Closed
                                    on progress of review.

23/08/2021   TfNSW representative   Email sent providing TfNSW comments on        Closed
                                    CTAMP.

25/08/2021   SIMTA representative   Email sent providing SIMTA responses to       Closed
                                    TfNSW comments.

                                    Follow up email sent requesting
2/09/2021    SIMTA representative   confirmation that SIMTA responses had         Closed
                                    addressed TfNSW comments.

6/09/2021    TfNSW representative   TfNSW confirmed comment responses             Closed
                                    accepted and no further comments.

                                                                                           9
1.4.1 MPW Stage 3 Consultation
 Consultation with LCC and TfNSW representatives was undertaken as part of the CTAMP update process
 for MPW Stage 3. LCC and TfNSW provided comment on the CTAMP, as updated to accommodate MPW
 Stage 3, and their comments and changes made to the CTAMP resulting from their comments are
 summarised in Table 2-1.

Table 2-1: Summary of LCC and TfNSW comments regarding MPW Stage 3 updates, and resulting changes to the CTAMP

  Agency
                   Agency Comments                                             Where addressed in this Plan

  LCC              Council has reviewed the CTAMP and has requested            -
                   the following comments be made to finalise the plan:

                   •   Heavy vehicles access to the development site should Section 3.2.2
                       be via the nominated route (i.e. the M5 Motorway and
                       Moorebank Avenue) unless the route is not available.

                   •   The construction access should be via Moorebank         Section 3.2.4
                       Avenue/Chatham Avenue intersection. An updated
                       CTMP is required for any changes to the existing
                       construction access.

                   •   Council is to be informed along with local residents (in Section 3.4
                       accordance with the Community Communication
                       Strategy) of any construction activities and road
                       access restrictions, which might affect the existing
                       road network and traffic conditions.

                   •   In addition to Road Occupancy licenses, road            Section 3.3.1.3
                       occupancy permits, and road opening approvals are
                       required for road occupancies (and works) within
                       sections of Moorebank Avenue and Avenue Road,
                       which are currently local roads under Council’s care
                       and control. Application forms for Council’s ROC
                       permits and RO approvals are available on Council’s
                       website.

                   •   A notice with contact phone number and email details    Section 3.4
                       for community to make contacts regarding work
                       activities are to be installed at the site.

  TfNSW            Provide key components of MPW Stage 3 development           Section 1.2.1

                   Detail scope of MPW Stage 3 construction traffic in relation Section 1.2.1
                   to MPW Stage 2 construction traffic

                   Provide details regarding construction timelines for        Appendix G
                   MPW Stages 2 and 3

                                                                                                                 10
2 ENVIRONMENTAL MANAGEMENT
This section outlines the relevant legislation and project requirements that apply to traffic management and
identifies additional permits and approvals that may be required during construction works.

2.1 Legal and Other Obligations
Table 2-2 details the legislation, planning instruments and guidelines considered during development of this
plan. Further detail concerning the legislation, planning instruments and guidelines identified below are
provided in the Compliance and Obligations Register within Appendix A of the CEMP.

Table 2-2 Legislation, Planning Instruments and Guidelines

    Legislation and
                              Description                                         Relevance to this plan
    Guidelines

    Environmental Planning    This Act establishes a system of                    The Development Consent conditions
    and Assessment Act        environmental planning and assessment of            and obligations are incorporated into this
    1979                      development proposals for the State.                plan.

                              Section 87 of the Roads Act requires the
                              consent of RMS for the construction, erection,      A ROL will be required for works on
                              installation, maintenance, repair, removal or       public roads associated with the Project.
    Roads Act 1993            replacement of a traffic control light.             Under Section 4.42 of the EP&A Act an
                              Section 138 of the Roads Act establishes a          ROL cannot be refused and is to be
                              requirement for a Road Occupancy Licence            substantially consistent with the consent.
                              for works on public roads.

    Local Government Act      Approval required from local government for         Works adjacent to public roads owned by
    1993                      some activities on or adjacent to public roads.     Council will require approval.

                              Incorporates most of the statutory provisions       Drivers transporting goods to and from
    Road Transport Act 2013   concerning road users, road transport and the       the Project must comply with the Road
                              improvement of road safety in NSW.                  Transport Act 2013.

                              Establish a framework for safe and efficient        Drivers accessing the Project must
    Road Rules 2014
                              movement of traffic on NSW roads.                   comply with the Road Rules 2014.

                              The key sections of this Regulation relevant
                              to the Project include, but are not limited to:
                              •   Clause 67: Duty on prime contractors to
                                  transport dangerous goods in                    Transport of dangerous goods must be in
    Dangerous Goods (Road
                                  accordance with the Australian                  accordance with the Dangerous Goods
    and Rail Transport)
                                  Dangerous Goods code                            (Road and Rail Transport) Regulation
    Regulation 2014
                                                                                  2014
                              •   Part 5: Consignment procedures for
                                  dangerous goods
                              •   Part 12: Safety equipment

                                                                                  The Act requires licenses for specified
                              The objective of this act is to object of the Act
    Protection of the                                                             activities (including road construction and
                              is to achieve the protection, restoration and
    Environment Operations                                                        storage activities) that control the air,
                              enhancement of the quality of the NSW
    Act 1997                                                                      noise, water and waste impacts of that
                              environment.
                                                                                  activity.

Additional legislation, standards and guidelines relating to the management of traffic and access include, but
are not limited to:
•     AGRD 04-1709 Guide to Road Design Part 4: Intersections and Crossings – General, 2017

                                                                                                                                11
•     AGTM 02-08 Guide to Traffic Management Part 2: Traffic Theory, 2015
•     AGTM 06-1907 Guide to Traffic Management Part 6: Intersections, Interchanges and Crossings –
      General, 2019
•     AS 1742 Parts 1 to 14, Manual of Uniform Traffic Devices (as required)
•     AS 1743.3-2009 Traffic control devices for works on roads
•     AS 3845:1999 Road Safety Barrier Systems
•     Austroads - Cycling Aspects of Austroads Guides, April 2014
•     NSW Centre for Road Safety, NSW Speed Zoning Guidelines Version 4, 2019
•     NSW Government - The Guide to Traffic and Transport Management for Special Events, July 2018
•     Relevant RMS Technical Direction and Guide updates.
•     RMS Delineation Manual, December 2010
•     RMS QA Specification G10 – Traffic Management, December 2018
•     RMS Roads Occupancy Manual, May 2015
•     RMS Supplement to Austroads Guide to Road Design, August 2015
•     RMS Traffic Control at Worksites Manual Version 54, July 2018
•     RMS Traffic Signal Design and Specification SI/TCS/8 Installation and Reconstruction of Traffic Light
      Signals, May 2013
•     RMS Works Authorisation Deed (to be applied for. See Section 3.3.1.1).

2.1.1 Compliance Matrices
The Project is being delivered under Part 4, Division 4.7 of the EP&A Act. The MPW Stage 2 and MPW Stage
3 CoCs include requirements to be addressed in this plan and delivered during the Project. These
requirements, and how they are addressed are provided within Table 2-3.

Table 2-3 Conditions of Consent (CoCs)

    CoC
             Condition                                              Where Addressed     How Addressed
    No.

    SSD 7709 MPW Stage 2 Primary Conditions of Consent

                                                                                        Qualification details are
             Prior to commencement of construction, the Applicant                       provided on the cover
             must prepare a Construction Traffic and Access Plan    This plan           page
             (CTAMP) and submit it to the Planning Secretary for
    B113     approval. The CTAMP must be prepared by a              Section 1.4         Consultation is detailed
             suitably qualified and experienced person(s) in                            within Section 1.4 and
             consultation with Council, and must be endorsed by     Appendix B          Appendix B;
             TfNSW and RMS.                                                             endorsement is
                                                                                        provided in Appendix B.

             The CTAMP must form part of the CEMP required by
             Condition C2 and, in addition to the general
             management plan requirements listed in Condition
             C1, the CEMP must:

                                                                                        Section 3.3 outlines
                                                                                        measures to reduce
    B114
             a)   detail the measures that are to be implemented                        traffic impact from
                  to ensure road safety and network efficiency      Section 3.3         project vehicles, to
                  during construction;                                                  ensure road safety and
                                                                                        network efficiency
                                                                                        during construction.

             b)   include a Heavy Vehicle Route Plan detailing:

                                                                                                                    12
CoC
        Condition                                                        Where Addressed        How Addressed
No.

                                                                         Section 3.2.2          Details the indicative
              i.        origin of imported fill,
                                                                                                spoil source locations
                                                                         Figure 3-2

                                                                         Section 3.2.2 Figure   Details the indicative
              ii.       destination of demolition material and spoil,
                                                                         3-2                    disposal destination

             iii.       heavy vehicle routes to and from the site
                        within the Campbelltown and Liverpool Local      Section 3.2.2          Details the primary and
                        Government Areas (LGAs), including                                      alternative routes to
                        compliance with the conditions of this           Figure 3-1             site
                        consent including Condition B89, and

                                                                                                Provides links to
                                                                         Section 3.2.2.1        resources to be
             iv.        management system for oversized vehicles;
                                                                         Appendix E             followed if oversize
                                                                                                vehicles are required

                                                                                                Detail access and
        c)          access and parking arrangements                      Section 3.2.4          parking arrangements
                                                                                                for the Project

                                                                                                Details the procedure
        d)          detail procedures for notifying residents and the
                                                                         Section 3.4            for notifying residents
                    community of any potential traffic disruptions.
                                                                                                and the community

                                                                                                Section 3.5 outlines
        Two lanes (one in each direction) of traffic on
                                                                                                measures to maintain
        Moorebank Avenue must be available at all times
B115                                                                     Section 3.5            two lanes of traffic on
        during construction, unless otherwise approved by
                                                                                                Moorebank Avenue at
        RMS.
                                                                                                all times.

                                                                                                Section 3.5 outlines
        All construction vehicles must be contained wholly
                                                                                                measures to reduce
B116    within the site and vehicles must enter the site before          Section 3.5
                                                                                                traffic impact from
        stopping.
                                                                                                construction vehicles.

                                                                                                Section 3.5 outlines
        All vehicles must enter and leave the site in a forward                                 measures to reduce
B117                                                                     Section 3.5
        direction.                                                                              traffic impact from
                                                                                                construction vehicles.

SSD 10431 MPW Stage 3 Primary Conditions of Consent

        Prior to the commencement of construction, the
B17
        Applicant must submit a Construction Environmental
        Management Plan (CEMP) to the Certifier and provide
        a copy to the Planning Secretary for approval. The
        CEMP must include, but not be limited to, the
        following:
                                                               Section 3.5
        Details of:                                            Appendix C                       Section 3.5 and
        ...                                                                                     Appendix C (Driver
            •    measures to ensure that sediment and other                                     Code of Conduct)
                 materials are not tracked onto the roadway by                                  detail measures to
                 vehicles leaving the site;                                                     manage sediment
        …                                                                                       control for vehicles
                                                                                                leaving the site
                                                                        This plan
        (i) Construction Traffic and Access Management
        Sub-Plan (see condition B20);

                                                                                                                          13
The Construction Traffic and Access Management
 B20
          Plan (CTAMP) must be prepared to achieve the
          objective of ensuring safety and efficiency of the road
          network and address, not be limited to, the following:

                 (a) be prepared by a suitably qualified and        This plan
                 experienced person                                                 Qualification details
                                                                                    are provided at the
                                                                                    front of this plan
                 (b) be prepared in consultation with Council       Section 1.4
                 and TfNSW                                          Appendix B      Consultation is
                                                                                    detailed within
                                                                                    Section 1.4 and
                                                                                    Appendix B;
                                                                                    endorsement is
                                                                                    provided in Appendix
                                                                                    B
                 (c) detail the measures that are to be          Section 3.3
                 implemented to ensure road safety and                              Section 3.3 outlines
                 network efficiency during construction in                          measures to reduce
                 consideration of concurrent construction and/or                    traffic impact from
                 operation traffic to and from the combined                         project vehicles, to
                 MPW site and the MPE site, and potential                           ensure road safety
                 impacts on general traffic, cyclists and                           and network
                 pedestrians and bus services                                       efficiency during
                                                                                    construction
                 (d) detail access and parking arrangements         Section 3.2.4
                                                                                    Details access and
                                                                                    parking
                                                                                    arrangements for the
                                                                                    Project

                 (e) include a Heavy Vehicle Route Plan
                 detailing:
                           (i)origin of imported fill               Section 3.2.2
                                                                    Figure 3-2      Details the indicative
                                                                                    spoil source locations
                           (ii) destination of spoil                Section 3.2.2
                                                                    Figure 3-2      Details the indicative
                                                                                    disposal location
                           (iii) heavy vehicle routes to and from Section 3.2.2
                           the site within the Campbelltown and Figure 3-1          Details the primary
                           Liverpool Local Government Areas                         and alternative routes
                           (LHAs), including compliance with                        to site
                           conditions of this consent, and
                           (iv) management system for oversized Section 3.2.2.1
                           vehicles                             Appendix E          Provides links to
                                                                                    resources to be
                                                                                    followed if oversize
                                                                                    vehicles are required

                 (f) detail procedures for notifying residents and Section 3.4
                 the community of any potential traffic                             Details the procedure
                 disruptions                                                        for notifying residents
                                                                                    and the community

The MPW Stage 2 Final Compilation of Mitigation Measures (FCMMs) were presented in the MPW
Stage 2 Response to Submissions (Arcadis July 2017) and are included as Appendix 2 of the SSD 7709
consent. The FCMM as relevant to MPW Stage 3 have been included as Appendix 3 of the SSD 10431
consent. A list of the FCMMs as relevant to the Project and how they have been complied within this
plan are provided in Table 2-3.

                                                                                                              14
Table 2-3 Final Compilation of Mitigation Measures (FCMMs)

 FCMM             Requirement                                                               Comment

 SSD 7709 MPW Stage 2 Primary Condition FCMM

 0B               The Construction Environmental Management Plan (CEMP), or
                  equivalent, for the Proposal would be based on the PCEMP
                  (Appendix I of this EIS), and include the following preliminary
                  management plans:                                                         This Plan

                  •    Preliminary Construction Traffic Management Plan (PCTMP)
                       (Appendix M of the EIS)
                  …
                  As a minimum, the CEMP will include the following sub-plans:
                  •    Construction Traffic Management Plan (CTMP)
                  …

 1A               A Construction Traffic Management Plan (CTMP) would be
                  prepared based on the Preliminary Construction Traffic
                  Management Plan (Appendix M of the EIS), detailing management
                  controls to be implemented to avoid or minimise impacts to traffic,       This plan
                  pedestrian and cyclist access, and the amenity of the surrounding
                  environment. The following key initiatives would be included in the
                  CTMP:

                                                                                            A 20km/hr speed limit is
                  Review of speed restrictions along Moorebank Avenue and                   designated on site.
                  additional signposting of speed limitations
                                                                                            Appendix C

                                                                                            All drivers will be required to
                                                                                            adhere to the nominated
                  Restriction of haulage routes through signage and education to
                                                                                            construction truck / haulage
                  ensure, where possible, that construction vehicles do not travel
                                                                                            routes to/from the site via the
                  through nearby residential areas to access the Proposal site, in
                                                                                            M5 and Moorebank Avenue.
                  particular Moorebank (Anzac Road) or the Wattle Grove residential
                                                                                            The Heavy Vehicle Route is
                  areas
                                                                                            identified in Section 3.2.2
                                                                                            and Appendix C.

                  Inform local residents (in conjunction with the Community
                  Information and Awareness Strategy) of the proposed construction
                  activities and road access restrictions that the construction traffic
                                                                                            Section 3.4
                  must adhere to and establish communication protocols for
                  community feedback on issues relating to construction vehicle
                  driver behaviour and construction related matters

                  Installation of specific warning signs at entrances to the
                  construction area to warn existing road users of entering and exiting     Section 3.5
                  construction traffic

                  Establishing pedestrian walking routes and crossing points                Section 3.5

                  Distribution of day warning notices to advise local road users of         Section 3.5
                  scheduled construction activities

                  Installation of appropriate traffic control and warning signs for areas   Section 3.5
                  identified where potential safety risk issues exist

                  The promotion of car-pooling for construction staff and other shared      Section 3.5
                  transport initiatives during the pre-construction phase

                                                                                                                              15
Facilitating emergency vehicle access to the site                      Section 3.5

              Management of the transportation of materials to maximise vehicle      Section 3.5
              loads and therefore minimise vehicle movements

              Minimising the volumes of construction vehicles travelling during      Section 3.5
              peak periods

              Maintaining access to neighbouring properties, in particular the       Section 3.5
              ABB site

              Monitoring of traffic on Moorebank Avenue during peak construction     Section 4.1
              periods to ensure that queuing at intersections does not
              unreasonably impact on other road users.

SSD 10431 MPW Stage 3 Primary Condition FCMM

0B             The Construction Environmental Management Plan (CEMP) and          This plan
               sub-plans prepared for MPW Stage 2 (listed below) will be amended,
               where required, to accommodate MPW Stage 3 conditions:
              Construction Traffic and Access Management Plan (CTAMP)
              ….
1A            A Construction Traffic and Access Management Plan (CTAMP)              This plan
              prepared for MPW Stage 2 details management controls to be
              implemented to avoid or minimise inputs to traffic, pedestrian and
              cyclist access, and the amenity of the surrounding environment
              would be amended, where required, to accommodate MPW Stage 3
              conditions. The following key initiatives, included in the MPW Stage
              2 CTAMP, continue to apply to MPW Stage 3:
               •   Restriction of haulage routes through signage and                 All drivers will be required to
                   education to ensure, where possible, that construction            adhere to the nominated
                   vehicles do not travel through nearby residential areas to        construction truck/haulage
                   access the Proposal site, in particular Moorebank (Anzac          routes to/from the site via the
                   Road) or the Wattle Grove residential areas                       M5 and Moorebank Avenue.
                                                                                     The Heavy Vehicle Route is
                                                                                     identified in Section 3.2.2 and
                                                                                     Appendix C.
               •   Inform local residents (in conjunction with the Community         Section 3.4
                   Communication Strategy (of the proposed construction
                   activities and road access restrictions that the construction
                   traffic must adhere to and establish communication
                   protocols for community feedback on issues relating to
                   construction vehicle driver behaviour and construction
                   related matters
               •   Installation of specific warning signs at entrances to the        Section 3.5
                   construction area to warn existing road users of entering
                   and exitingconstruction traffic

               •   Distribution of day warning notices to advise local road          Section 3.5
                   users of scheduled construction activities

               •   Installation of appropriate traffic control and warning signs     Section 3.5
                   for areas identified where potential safety risk issues exist

               •   The promotion of car-pooling for construction staff and other     Section 3.5
                   shared transport initiatives during the pre-construction
                   phase