Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India

 
CONTINUE READING
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                                              Vol. 12 (6) June (2019)

     Challenges faced for Installation of Emergency
 Restoration System (ERS) in the Major Natural Disaster
      Hit High Voltage Transmission Lines in India
                                                 Tamil Selvan M.1* and Kodi Malar2
                                    1. CSRD, SSS, Jawaharlal Nehru University, New Delhi – 110 067, INDIA
      2. Department of Energy and Environment, TERI School of Advance Studies, Institutional Area, Vasant Kunj, New Delhi - 110 070, INDIA
                                                          *mtselvan@mail.jnu.ac.in

Abstract                                                                   These events include human error, vehicle accidents,
High Voltage Transmission lines are subjected to                           vandalism, terrorism, design faults and poor maintenance
several natural disasters like earthquake, flood,                          practice. High voltage transmission lines are expected to
landslides, hurricanes etc. Power line failure due to                      certain level of damage risks, threatening to disrupt power
                                                                           supply infrastructure and can affect public safety. Utilities
these scenarios makes a severe financial damage to
                                                                           cannot avoid emergencies; therefore, it is important to know
consumers, utilities and the power producing agencies.                     their cause and respond quickly and efficiently to the
Also, transmission line failures occur due to harsh                        problem on timely manner.
weather and non-climatic reasons such as human
errors and mechanical failures. While it is impossible                     Emergency situations may include failure of structural
to prevent all such situations, electrical utility officials               systems and foundations, failure of conductor splices and
and contractors have to be equipped to meet such                           damage to conductor strands leading to conductor failure etc.
emergencies.                                                               Transmission line tower damage may also occur due to
                                                                           degradation of conductors due to wild-fires, flood, insulator
Emergency Restoration System (ERS) structures are                          breakage, failure of cross-arms and buckling of tower angle
                                                                           members or connection failures.
temporary solution designed to bypass the existing
transmission towers of any voltage in any terrain. They                    During winter, icing on Transmission Line causes line break
will be used until the main line is re-conductored or                      accident. So, the restoration of these kind of accident that in
restored. Planning includes determining which                              the event of the ice cover the intensity of work, repair and
transmission lines are important and the possible ways                     maintenance, takes relatively longer time as compared to
in which they can fail and how best to restore them.                       other places6. When the ice cover is formed, the overall
This includes general information about existing                           weight of the transmission line increases, which leads to the
structures and foundations, data on past weather-                          failure of the line.
related failures, weather criteria and structural
loading and the extent of damages. In this study, we are                   In all these cases, the utility demand is to restore the power
analyzing various challenges faced due to the major                        system to normalcy rapidly. The primary requirement in
                                                                           Emergency Restoration work is to revive the transmission
transmission lines failures in India during various past
                                                                           network, get the line back into normal operation as quickly
natural disasters. Supply of continuous power will be                      as possible and to restore electricity supply to the affected
the most important aspect of a transmission line                           consumers at the earliest. Another important concern is to
network during emergency time.                                             minimize the economic impact of the costs associated with
                                                                           the devastation and rebuilding. So, it is important to
Keywords: Emergency Restoration System, Transmission                       calculate the total cost to rebuild or restore a failed
Line, Powergrid, Natural Disaster.                                         transmission line, which is inversely proportional to the
                                                                           restoration time; the total losses are directly proportional to
Introduction                                                               the outage time. Therefore, one can view any Emergency
High voltage transmission lines carry electrical energy from               Restoration Plan as a combination of technical or
power generating stations to long distances and reach                      engineering processes with the financial planning.
substations. These transmission lines are passing through a
wide range of terrains, climates and physical environments                 Use of composite insulated cross-arms is expected to reduce
and are always at risk to experience catastrophic events, both             the cross-arm load on the structure and the clearance
weather-related and man-made. Weather-related events                       required for insulator swings. These towers are best suited to
include high winds, ice buildup, ice storms, flash floods,                 maintain uninterrupted power supply in an event of tower
rock or mud slides, erosion of foundations etc. Sudden                     failure. These ERS towers bypass the original transmission
power failures caused by nature are very common, however,                  system to restore power at the earliest, while the original
non-weather-related events are just likely.                                tower is being rectified. These towers are useful for restoring
*Author for Correspondence                                                 power supply following various natural calamities like
                                                                           floods, hurricane, cyclone etc. for conducting scheduled

                                                                       1
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                                      Vol. 12 (6) June (2019)

maintenance work on the existing towers without major                  Training. To perform any quick emergency restoration work,
interruptions.                                                         critical materials must be readily available for installation.
                                                                       The inventory must include standard wire sizes in sufficient
Figure 1 shows the typical look of the 400kV ERS Tower                 quantities8. If the line consisted of poles, then the inventory
installation at a testing ground in Bihar State, India including       stock must have a reasonable number of poles of similar size
the erection of IEEE Standard 1070 emergency restoration               and strength of the same line. Structures used for restoration
towers thereby keeping field personnel well trained towards            work can be modular, temporary or permanent type.
latest developments. Also, it was planned to reduce the time
required to transport emergency materials to the job site by           An important part of any restoration work is to mobilize the
utilizing heavy helicopters and other air transport equipment          well-trained field personnels in the erection of the
as required. This ERS structure is supported by combination            replacement structures and stringing operations. A rapid
of guys and can be installed without any civil foundation.             mobilization of trained work force is vital to the process of
The ERS Tower erection is made with ease with the usage                emergency restoration. The restoration process consisted of
of Gin Pole which negates the need of heavy machineries.               a simple design with standard weather criteria for the re-
                                                                       route, required wood poles and other materials shifted to the
                                                                       affected site from inventory stock collected from every
                                                                       region of the country and special construction methods
                                                                       devised for quick restoration.

                                                                       Normally, a double circuit line will be transferred to 3 sets
                                                                       of ERS tower with two towers in each set thereby forming a
                                                                       double circuit. Surveying and transportation of materials to
                                                                       site is a major challenge. The real challenge will be at the
                                                                       time of installing the anchors as we can see the standard
                                                                       towers. If the soil is too soft, then it was not suitable for
                                                                       installing any type of anchors. Modular supports were
                                                                       specially designed for this by considering the guy angles and
                                                                       ease for transportation to the site. In ERS towers, the long
                                                                       modular steel supports offer the large width which is
                                                                       necessary for both connecting the guy wires and also
                                                                       increasing the stability of the ERS structure installed.

                                                                       Material and Methods
                                                                       One of the noteworthy features of ERS structures is that
                                                                       these are easy and quick to install. These structures do not
                                                                       require any foundation and can be set up on any soil type.
  Figure 1: Typical look of an ERS Tower Installation                  The base of the tower comprises a four-meter box upon
                                                                       which strong metallic angles can be assembled. These
When a high voltage transmission line goes down with one               towers are light in weight and can be transported easily using
or several damaged towers, the responsible utility agency              helicopters or manually.
incurs huge monetary losses and hundreds of non-
transmission hours. Given that the total losses and damages            Due to the vast expanse of India and the variety of climatic
are directly proportional to the outage duration, time is a            conditions, Powergrid is subjected to transmission lines that
crucial factor in reinstating or remediating the failed towers.        occasionally fail due to natural disasters. These natural
In some cases, the process of formally rebuilding a new line           disasters are result of mudslides, heavy ice, cyclones and
with original towers can take as long as 5 to 6 weeks.                 floods. Traditionally, restoration of these transmission lines
                                                                       was accomplished using available spare of normal towers.
However, by using an effective Emergency Restoration                   The typical self-supporting lattice type towers used in India
Plan, the field transmission structures can be replaced in few         were erected using derricks and in some cases, a complete
hours depending on the nature and depth of the damage.                 new foundation has to be constructed. These processes are
Proper planning benefits not only for maximized restoration            very time consuming and often resulted in prolonged
efficiency but can also minimize inventory levels. To face             outages.
this challenge, large amounts of inventory were required in
order to have spare lattice towers available for emergency             Many of the sites of these damaged transmission structures
restoration work.                                                      were difficult to access physically. The loss of these towers
                                                                       would sometimes result in backing down the generation and
An effective Emergency Restoration Plan contains three                 load shedding at industrial area in India. When major natural
essential elements like Planning, Emergency Materials and              disasters occurred, it was calculated that lost Gross Domestic

                                                                   2
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                                Vol. 12 (6) June (2019)

Product for India could be eighteen times the value of the       precautionary measure power supply was cut off in many
power that was lost.                                             parts. Chennai, Kanchipuram and Tiruvallur were the worst
                                                                 affected districts. In these districts, EHT transmission towers
Results and Discussion                                           and transmission lines collapsed due to the high wind speed
Vardah Cyclone, Tamil Nadu, 2016: The cyclone Vardah             and the substation equipments also got damaged.
struck land at Chennai Coast, Tamil Nadu on 12.12.2016
with a wind speed of 130 to 140 kmph, bringing with its          The power lines, poles and distribution transformers of
heavy rain that lashed the coast in Tamil Nadu devastating       distribution network was also affected due to high wind
the electrical infrastructures. To avoid accidents,              speed as the uprooted trees fell on the electrical network
                                                                 lines and structures.

              Figure 2: Various Transmission Lines of Powergrid in India (Source: Powergrid Website)

            Figure 3: Load Pattern before and after Cyclone Vardah (Source: TANGEDCO Report, 2017)

                                                             3
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                               Vol. 12 (6) June (2019)

                                                                  trees are removed, so it faced difficulties in restoring the
                                                                  power.

                                                                  The average demand of Chennai City is around 2500 MW.
                                                                  On the day of Vardah Cyclone, due to pulling of 230 KV
                                                                  feeders on 12.12.2016, the load went to Zero MW. After
                                                                  restoration, the load gradually increased and is being
                                                                  maintained at around 2100 MW. Sum of about Rs.350 Crore
                                                                  was spent towards temporary restoration of damaged
                                                                  infrastructure of electricity network.

                                                                  Hudhud Cyclone Andhra Pradesh, 2014: In the past
                                                                  couple of years, the deployment of ERS towers has gained
                                                                  traction in India. As a result of Hudhud cyclone that struck
                                                                  Andhra Pradesh on 12.10.2014, some areas in the State went
                                                                  without power for few days. In order to prepare itself for
                                                                  such emergencies in the future Andhra Pradesh
                                                                  Transmission Corporation Limited has procured a total of 10
                                                                  ERS towers for three zones namely Visakhapatnam, Kadapa
                                                                  and Vijayawada7. Powergrid extended all out support to AP
                                                                  Transco, Railways and Vizag Steel Plant to restore the power
                                                                  system on emergency mode using ERS towers. Supply to the
                                                                  emergency services like hospitals, water supply pump
  Figure 4: Tower collapsed during Vardah Cyclone,                houses were restored by 14.10.2014.
                     Tamil Nadu
                                                                  Flood in J and K, 2014: In Sept 2014, devastating flood hit
It is calculated that total 59 nos. of EHT towers collapsed       the majority of portion of J and K resulting in damage of
and around 800 distribution transformers, 49,100 poles,           number of transmission line towers and sub-stations, which
4500 pillar boxes and 15,000 km conductors were damaged.          were submerged in water7. Powergrid extended manpower
ERS Towers are mainly used in place of damaged tower to           and material support to restore the transmission network and
enable power supply with very short time. But in certain          distribution network with supply of ERS, distribution
areas, power has been suspended to avoid accidents, unless        transformers, transformer oil and filter machine.

                       Figure 5: ERS Tower Installed during Hudhud cyclone restoration work

                                                              4
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                                  Vol. 12 (6) June (2019)

                        Figure 6: Installation of ERS Tower in J and K during restoration work

Super Cyclone Phailin, Odisha and Andhra Pradesh,                   complete1. After transporting the ERS to location of
2013: A severe storm hit on 10/13/2013 at coastal area of           damaged tower of the 400kV Uri-Wagoora line, the actual
Odisha and Andhra Pradesh where most of the utilities were          work started on the 19/01/2000 under very adverse situation-
vastly disrupted by the strong winds that went up to a speed        very cold and snow climate as per figures 8 and 9.
of 220 kmph. When this very severe cyclonic storm crossed
the coast near Gopalpur and weakened before turning into a          Super Cyclone Damage in Orissa State, 1999: In the early
depression. Ganjam district in Odisha was totally destroyed         hours of the 29/10/1999, a massive and merciless cyclonic
by this storm. There were major disturbances in electricity         storm hit the coastal belt of Orissa killing thousands and
transmission utilities due to this cyclone Phailin. So, for         displacing millions. During the cyclone, it was observed that
precautions, load schedule was planned as in Andhra                 the wind blew at a velocity of 250-260 km per hour and the
Pradesh and the load was reduced to about 9,000 megawatt            sea rose up to 5-8 meters high with accompanying
(MW) against normal demand of 10,000MW and in Odisha,               continuous rain sweeping hundreds of thousands of houses
it was reduced to 600MW against the normal demand of                out of existence in the most part of Orissa.
2800MW.
                                                                    The worst affected districts ware Jagatsingpur, Kendrapada,
Based on IMD weather forecast information, extensive prior          Puri, Khurda, Bhadrakh and Balasore, those were totally de-
preparations were undertaken to tackle the effects of cyclone       linked from the rest of the country. Bhubaneswar, the capital
Phailin in the context of power requirements and supply.            city of Orissa state, was in darkness and all possible links
Advance planning was made to manage the generation and              with the outer world were cut off by this Super Cyclone.
load balance for unhindered and secure grid operation during        Communication within the State was impossible due to
cyclone period. The required power load and generation              complete ransacking of the electric and telecommunication
were managed in a balanced manner so as to achieve stable           wires and cables. Many ERS Towers were installed in large
transmission frequency. There were three Emergency                  number at different location to restore the power.
Restoration Systems (ERS) of PGCIL which were put on
standby readiness in AP and Odisha for quick deployment in          Cyclone Damage in Gujarat State, 1998: On 09/06/1998,
the event of damage.                                                a severe cyclone hit the coastal area of Gujarat State on the
                                                                    Arabian Sea. Wind speeds were measured at 130km/h and
Heavy Snowfall in J and K, 2000: The entire Kashmir                 estimated to be much higher in many locations. This cyclone
valley became almost dark because of the sabotage of two            caused major loss of life and properties in the coastal areas
towers feeding power to the Kashmir Valley on 16/01/2000.           of Gujarat state. Due to the high winds and severe flooding,
Successful deploying of ERS is on the 400kV double circuit          several major transmission lines of Gujarat State Electricity
Uri-Wagoora transmission line which carries the power from          Board were destroyed. Because of the much-needed
480 MW Uri Hydro Project in Jammu and Kashmir. The                  requirement of power in the cyclone affected area,
only highway from Jammu to Srinagar was closed due to               Powergrid undertook the challenge of rapidly restoring
heavy snowfall for few days. Thus, the ERS was transported          several of the vital transmission lines using ERS structures.
in an AN32 (Russian) Transport by the Air Force plane. The
required materials were transported in the above plane which        At one place, three towers were destroyed on the double
made several trips between Jammu and Srinagar to                    circuit 220kV transmission lines from Panandru thermal

                                                                5
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                              Vol. 12 (6) June (2019)

power station to Anjar route. These lines were rapidly           circuit on the 18/06/1998 using four ERS towers while the
restored using cranes and other heavy equipment along with       second circuit was restored on the 23/06/1998 using another
Powergrid’s ERS towers. Power was restored on the first          four ERS towers (Figure 11).

                         Figure 7: Odisha Power Demand met during Super Cyclone Phailin

Figure 8: Erection of the 400kV single circuit 15-degree
  tension ERS tower using manpower to pull the two                Figure 9: Two views of the almost completed 400kV
           conductors of the bottom phase.                        ERS tension tower showing the span over the double
                                                                                  circuit 220kV line

                                                             6
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                                      Vol. 12 (6) June (2019)

                           Figure 10: ERS towers used to restore power after the Orissa cyclone

                            Figure 11: Tower damaged during Gujarat cyclone and ERS Tower

Heavy Wind and Rainstorms in West Bengal, 1997: On                     quickly as possible. The closest emergency restoration
28/05/1997, heavy wind and rainstorms caused five double               system was located in Itarsi, which was 1500km away from
circuit 400kV suspension towers on the Maithon-                        site, therefore, it took 3 days to transport the material to the
Jamdeshbur transmission line in West Bengal State to fail.             restoration site. During this time engineers from Powergrid
The five suspension towers were located between two                    surveyed the site and decided to restore one circuit of the
tension towers in that location. All five suspension towers            400kV with the emergency restoration system (ERS) and
collapsed and the resulting collapse caused cross-arms on              followed other locations to restore complete line.
both tension towers to damage them. The terrain was
relatively flat and rolling terrain. Failure of these towers did       Challenges faced and Possible Solutions: As we have
not cause any outages but due to the increasing loads on               observed from the above case studies, even after carrying out
other redundant lines, it was critical to restore these lines as       condition monitoring and preventive maintenance, the

                                                                   7
Challenges faced for Installation of Emergency Restoration System (ERS) in the Major Natural Disaster Hit High Voltage Transmission Lines in India
Disaster Advances                                                                                     Vol. 12 (6) June (2019)

break-down of transmission lines cannot be ruled out. This           power outages. Examples of structural, foundation and
is mainly because natural calamities are unpredictable events        hardware failures on high voltage transmission lines in India
and ranging various severity. Because of this Powergrid has          and restorative processes adopted were of help for better
deployed the IEEE Standard 1070 Emergency Restoration                planning and restoration work.
System for restoration of collapsed towers as we have seen.
Manual transportation and erection of the ERS tower takes            The effective emergency restoration procedures capable of
minimum 3-4 days when restoring a collapsed tower. But, if           being activated at short notice must be in place with all
we use hydraulic cranes or if helicopters can be deployed,           utility companies. These procedures must be based on the
the restoration work can be done in 2-3 days-time.                   knowledge of stock materials in storage, trained workforce,
                                                                     available equipment and resource mobilization, while
We observed from above studies that the restoration process          responding to power blackouts caused by natural disasters.
consisted of determining the cause of failure as due to              Since new materials and techniques are constantly being
galloping, replacing the hardware fittings and adding more           developed, these ERS systems and procedures require
vibration dampers to the conductors to increase damping.             periodic review with updated technologies. So, it is very
These three restoration activities discussed highlights and          much necessary for the transmission line utilities to take
the importance of utilizing available inventory, devising            precautionary actions to avoid and reduce these disruptions.
quick construction methods and deployment of temporary               Hence it is extremely important to restore the line as quickly
structures.                                                          as possible after failure whether it is planned or due to the
                                                                     natural disaster.
Powergrid has used these ERS systems many times for either
emergency restoration on transmission line or its                    References
maintenance activities. The results to date have met all of          1. Agrawal L.N. and Erickson Paul E., Planning and training
their expectations. As a result of Powergrid’s pre-planning          reduce restoration time for damaged transmission lines in India,
for potential emergencies on their transmission grid,                Lindsey ERS Reference Materials, White Papers (2000)
significant savings have been realized by them. From the
experience to date, Powergrid has modified their emergency           2. IEEE, IEEE Guide for the Design and Testing of Transmission
                                                                     Modular Restoration Structure Components, IEEE Std 1070-1995
restoration program in many ways as emergency restoration
                                                                     (1995)
materials have been made more decentralized through-out
India in order to reduce deployment time. Also, they have            3. Mukhopadhyay Subrata, Soonee Sushil K., Agrawal Vinod K.,
reduced inventory of permanent emergency towers from 5%              Narasimhan S.R. and Saxena Samir C., Impact of Super-Cyclone
to 10% of previous amounts, keeping only heavy tension               Phailin on Power System Operation - Defense Mechanism and
towers in stock.                                                     Lesson Learned, Conference: 2014 IEEE PES, General Meeting,
                                                                     At National Harbor, MD, USA (2014)
Recent developments in surveying technologies have
allowed the utility companies to re-think about the station-         4. Mukhopadhyay Subrata, Soonee Sushil K., Narasimhan S.R. and
elevation-offset formats that designers have traditionally           Porwal Rajiv K., An Indian Experience of Defense Against
                                                                     Blackouts and Restoration Mechanism followed, In IEEE PES
used for transmission line profile modelling to be used
                                                                     General Meeting, Pittsburgh, PA, USA (2008)
during disaster restoration work. This is the method of
surveying the affected area in some form of three-                   5. NDMA, National Disaster Management Guidelines, published
dimensional geographical information system (GIS) type               by National Disaster Management Authority Government of India
representation. Data are usually collected in electronic             (2012)
format or quick planning and the transmission line software
is capable of reading the data intelligently in any form.            6. Panth Dharmende, Reasons for failure of transmission lines and
Recent development of LIDAR techniques, Total Station,               their prevention strategies, International Journal of Electrical,
Geographical       Positioning   System      (GPS)       and         Electronics and Data Communication, 2(1), 1-4 (2014)
Photogrammetric techniques is used to study relatively
                                                                     7. Shankar Anand, Disaster Management in Electric Power
accurate land models for transmission lines.                         Transmission Sector, In International Workshop on Disaster
                                                                     Resilient Infrastructure (IWDRI), New Delhi (2018)
Conclusion
From this study, we can conclude that the sever natural              8. Vadivel Karthi K., Emergency Restoration of High Voltage
disasters are always un-predictable and result in various            Transmission Lines, The Open Civil Engineering Journal,
challenges for the utility companies. So, it emerges of having       11(Suppl-2 M6), 778-785 (2017).
an effective Emergency Restoration plan, which can help
control the financial impact of losses due to weather-related        (Received 06th April 2019, accepted 23rd April 2019)

                                                                 8
You can also read