Captive Coal Mining by Private Power Developers - Issues and Road Ahead: IDFC

Page created by Cecil Hawkins
 
CONTINUE READING
Captive Coal Mining by Private Power Developers – Issues and Road Ahead:

Summary of recommendations

Ministry of Coal has allocated captive mines to bulk users of coal, in public and private
sectors. However, very few of the coal blocks have started production. Summarized
below are the recommendations which may be taken up by the Central Government, State
Government and Developers to facilitate the rapid development of coal blocks:

1. Guidelines followed for Identification of Coal Blocks for Captive Allocation
Central Government: With reference to identification of coal blocks for allocation, the
following should be considered:
 Coal India Ltd (CIL)/ Singareni Collieries Company Ltd (SCCL), currently, identify
    blocks for allocation to private sector which are at a distance from the existing blocks
    of CIL/SCCL. This practice should be modified and blocks which are in the vicinity
    of CIL/SCCL and which are not included in the expansion plans of CIL/SCCL,
    should also be included in the list of captive blocks for allocation;
 In identifying captive coal blocks at ‘reasonable’ distance from existing mines and
    projects of CIL/SCCL, it should be considered that the distance should not be at a
    disadvantage to the captive coal block developer in terms of available infrastructure
    and other facilities;
 Without disturbing the present procedure of coal block allotment, the future allotment
    of coal blocks should be on the basis of better investigation and for which CMPDIL
    and other agencies should be mobilized

State Government: The State Government and its agencies should facilitate development
of infrastructure in the mining areas, particularly in providing right of way, railway
clearances, water, electricity, etc.

Developers: The captive block developers should coordinate with other coal block
developers in proximity to jointly fund the development of Infrastructure based on a
Master Plan prepared by an independent agency.

2. Allocation of Coal block
Central Government: The Ministry of Coal should not only look into the promoter
background and the end-use, but should also give adequate weightage to the technical &
financial capability of the applicants for timely development of the blocks. Further,
auctioning approach may be adopted for allocation of coal blocks. However, auctioning
of the block to the highest bidder may not be economically viable and adversely affect
the ultimate consumer. Thus, the following approaches, depending on the level of
information available for the coal blocks, may be adopted in taking the auctioning route
for allocation of blocks:
 Production sharing formula for fully unexplored blocks ;
 Maximum estimated production for partially explored blocks; &
 Lowest cost of power generated from coal from fully explored captive blocks with
    adequate information on the mineable coal reserves.

                                             1
3. Approvals and Clearances
Central Government
 Central Government should bring about the legal changes to have a single window
   approach through a nodal agency at the State Level under the department of mines,
   which would have representation from all the concerned departments in the State
   Government. The nodal agency can pre-determine the conditions for each category of
   land based on environmental sensitivity and nature of the proposed activity
   (prospecting, mining etc.). The nodal agency may complete the requirements of
   identification of land for compensatory afforestation, enumeration of trees, cost-
   benefit analysis, etc. before inviting application for mining lease.

   Public-Private Partnership model can be adopted in the form of a shell company
    formed for each of the captive blocks allocated. Shell companies (formed by the
    Public sector) are bid out to the private sector only after obtaining clearances and land
    acquisition is completed.

   MoEF should segregate coal bearing areas into ‘Go’ and ‘No-Go’ areas for each type
    of lease (Reconnaisance, Prospecting, and Mining) on the basis of the forest cover
    and environmental & ecological sensitivity. For areas defined as ‘Go’, it may be
    prudent to allow minimal or no forest & environmental clearances for investigative or
    prospecting purposes, with the conditionality that cutting of trees without prior
    permission is not allowed. Non-coal bearing areas can be used for rehabilitation
    colonies and townships.

   A concurrence by Forest Advisory Committee or the empowered committee is
    required for obtaining forest clearance. The committee then sends a report to the
    Hon’ble Supreme Court before sanction is accorded. This procedure needs to be
    reviewed to reduce delays in awarding clearances.

   MoEF clearances for projects which have a greater probability of commencing
    operations before the Eleventh Plan should be given priority.

   The Ministry of Coal as well as MoEF should grant consent to the developer of a coal
    block to develop the block in 2-3 phases, so that production could start early.

State Government: State Government should adopt procedures to issue the prospecting
license within a minimum time.

4. Land Acquisition
State Government: The procedure for land acquisition needs to be made less time
consuming as the State Governments in large number of cases own significant portion of
the land.

5. Rehabilitation of Project Affected People (PAP)
Central Government: It is recommended that the Ministry of Coal coordinate with the
State Governments to align the State R&R Policies with the National R&R Policy.

                                             2
Further, the State Governments should facilitate the developers in negotiating the
compensation package with the PAP’s.

State Government: For general development and improvement in the coalfield areas, the
State Government could consider creating an “Area Development Fund” by applying a
levy on each tonne of coal produced. This fund could be utilized for social welfare of
PAP including their health & education, improvement of infrastructure, roads, water
supply etc.

6. Geological Investigations & Mining plan – alternate agencies
Central Government: New agencies with the competence to perform geological
investigations need to be set up and accredited by the Government of India. These
agencies should be independent and unaffiliated to Coal India Limited or other public
sector coal companies. These agencies or an independent expert group should also be
empowered to review and approve the mining plan, which would be an input to Ministry
of Coal.

7. Tapering coal linkage/ marketing of surplus coal
Central Government: The timeframe for development of coal block is likely to be much
longer than a power plant. Ministry of Coal, therefore, has decided to provide coal
linkage on a tapering basis to the power producers who have been allotted captive coal
blocks and whose mining plan has been approved. It is suggested that the Ministry of
Coal should provide for the condition that the mining lease should be approved before the
power plant commences operations.

8. Joint Allotment of Coal Blocks
Central Government: In case of joint allotment of coal blocks it has been observed that
some of the companies in the Joint Venture do not furnish the Bank Guarantee, which
hinders the development of the block. Companies in the consortium which furnish the
Bank Guarantee should be allowed to proceed with development of the coal block, and
the partners who fail to provide the bank guarantee should be replaced with other
companies from among the applicants whose applications are pending with the Ministry.

                                           3
Captive Coal Mining by Private Power Developers – Issues and Road Ahead

The rapid growth in the Indian economy has led to a robust growth in the demand for
power. The demand for power has been constantly outpacing supply. With a view to
reducing the demand-supply gap, large generation capacity additions have been planned.
Notwithstanding efforts to have a diversified portfolio of fuel options in power
generation, share of coal based generation has increased over the years and with large
capacity additions envisaged over next decade, coal will continue to remain the primary
source of fuel for power generation. Besides substantial coal based capacity additions,
increase in demand for coal has been accentuated by improved utilization of plants,
diminishing quality of coal and inadequate availability of gas.

With rapid growth in demand for coal, coal supply is proving to be a major cause for
concern. Government of India (GoI) is targeting coal based generation capacity addition
of about 53000MW by 2012 (end of the 11th Plan period), coal based installed capacity
would then be more than 125 GW by 20121. In this scenario, there is an apprehension that
coal companies may not be able to cater to the enhanced coal requirement due to resource
and other constraints. To augment the coal supply, Ministry of Coal, Government of India
decided to allocate captive mines to bulk users of coal, in public and private sectors, and
consequently many captive coal blocks have been allocated to power developers2.

In May 2007, at the Parliamentary Consultative Committee meeting of the Ministry of
Coal3, it was announced that to meet the coal demand about 81 coal blocks with
geological reserves of about 20 billion tonnes have been identified for allocation to
companies, both government and private, for permissible end uses. Out of these, 41 coal
blocks, with geological reserves of about 15.7 billion tonnes, were earmarked for the
power sector. Currently, the allocation coal mining blocks to companies, other than Coal
India Ltd (CIL), is done either under the government company dispensation route4 or
through the captive dispensation route. These blocks for power sector, have been further
categorized in 3 separate lists on the basis of method of allocation which are,
Government Company Dispensation Route, Screening Committee5 Route and Tariff
based Bidding as per the Ministry of Power Guidelines. The details of these blocks
identified for power sector are as follows:

          Method of allocation                         No. of blocks       Total reserves
                                                                           (Billion tonnes)
          Government dispensation route                      10                   6.1

1
  Power Scenario at a Glance for All India, CEA, GoI, July 2008; White Paper on Strategy for 11th Plan,
CEA & CII, August 2007
2
  Under the provisions of the 1993 amendment to Coal Mines (Nationalisation) Act, 1973.
3
  81 coal blocks identified for allocation under captive END-USE, Press Release, PIB, GoI, 18th May 2007
4
  Under the Government dispensation route, the block is allocated to a government company and this
company has the right to be used for a specific end-use such as power, steel and cement.
5
  A screening committee has been set up in the Ministry of Coal for screening the proposals received for
captive mining of coal & lignite. The screening committee comprises of members representing Ministry of
Coal, Ministry of Power, Ministry of Railway, Ministry of Steel, concerned State Governments, CIL,
CMPDIL, and Department of Industrial Policy & Promotion (Ministry of Industry).

                                                   4
Method of allocation                           No. of blocks        Total reserves
                                                                                 (Billion tonnes)
             Tariff based bidding as per                          16                    6.0
             Ministry of Power guidelines
             Screening committee route                            15                   3.6
             Total                                                41                  15.7

According to Ministry of Coal, till 31st December 2007, 170 captive coal blocks have
been allocated, of which 15 blocks allotted to 3 PSUs and 9 private companies have
already started producing coal. Of the 170 captive coal blocks allotted (with reserves 39.3
billion tonnes), 76 coal blocks with reserves of about 23.6 billion tonnes have been
allotted to power sector (with 24 coal blocks allotted in 2007)6.

It may be noted that production of coal through the open cast mining of coal may not
need a lengthy lead time unlike production of coal in the case of underground mining,
which involves a lengthy gestation period, particularly when the stripping ratio is high.
Given the foregoing, one may be misled into believing that coal production can start
within a short period from the allotted coal blocks. However, this is not the case, as the
allocated mines could also involve underground mining.

Discussions with the private sector and public sector coal mine allottees have revealed
that the lead time is atleast 4-6 years, on account of the initial planning, conducting
geological studies to authenticate quantum and structure of reserves, obtaining several
statutory approvals from multitude of authorities & agencies, formulating mining plan
and getting approval, land acquisition, relief and rehabilitation issues, and infrastructure
development.

This note attempts to examine the problems being faced by the allottees of the captive
coal blocks and suggests recommendations which could shorten the actual lead time
involved in commercial production of coal from these coal blocks.

1. Guidelines followed for Identification of Coal Blocks for Captive Allocation

The guidelines adopted for demarcating the blocks are such that the developers would
face a number of problems in quickly bringing the allotted blocks to the production stage.
Ministry of Coal relies on Coal India Ltd (CIL) and Singareni Collieries Company Ltd
(SCCL), for identifying the captive coal blocks. The guidelines adopted by CIL & SCCL
for identifying and allotting coal blocks for captive mining are as follows7:

        The blocks offered to private sector should be at reasonable distance from existing
         mines and projects of CIL in order to avoid operational problems
        Preferably, blocks in greenfield areas having less or no development of basic
         infrastructure like road, rail link, etc. may be allotted to the public/private sector for

6
    Coal Directory of India 2006-07, Part-I: Coal Statistics, Ministry of Coal, GoI
7
    Coal Directory of India 2006-07, Part-I: Coal Statistics, Ministry of Coal, GoI

                                                        5
captive mining. The areas where CIL has already invested in creating such
      infrastructure for opening new mines should not be handed over to the private
      sector, except on reimbursement of costs
     Blocks already identified for development by CIL where adequate funding is on
      hand or in sight should not be offered to the private sector
     Public/private sector should be asked to bear the full cost of exploration in these
      blocks which may be offered
     For identifying blocks, the requirement of coal for about 30 years would be
      considered
     Others, which include Mine Plan approval under the provisions of Mines and
      Mineral (Development and Regulation) Act 1957, approval of the Directorate
      general of Mine Safety, and inspection by Coal Controller for an appropriate
      enforcement of conservation measures under the provisions of the Coal Mines
      (Conservation and Development) Act 1974.

The fact that the blocks are identified at a distance from the existing infrastructure of the
CIL and also that coal blocks are located in remote areas, devoid of all basic
infrastructure like road, rail links, electricity etc, it is difficult for the coal block allottees
to quickly bring the coal blocks to production stage. Development of infrastructure on a
piece meal basis i.e. individually on block by block basis may cause drain on the
resources of the developer, would not bring in economies of scale, and could be onerous
as well. Further, the blocks identified are only regionally explored with inadequate
information, which adds to risk and also reasons for delay in development of the blocks.

Thus, to facilitate speedy development of coal blocks it is recommended that the
following should be considered in identifying and allocating coal blocks:
 If there are coal blocks in the vicinity of the CIL/SCCL blocks which are not included
    in the expansion plans of CIL/SCCL, then these blocks should also be included in the
    list of captive blocks for allocation and not excluded simply because of their
    proximity to CIL/SCCL blocks;
 In identifying captive coal blocks at ‘reasonable’ distance from existing mines and
    projects of CIL/SCCL, it should be considered that the distance should not be at a
    disadvantage of the captive coal block developer in terms of available infrastructure
    and other facilities;
 Without disturbing the present procedure of coal block allotment, the future allotment
    of coal blocks should be on the basis of better investigation and for which CMPDIL
    and other agencies should be mobilized

Further, in the context of inadequacies in infrastructure associated with the captive blocks
identified for allocation, it is recommended that the Central/State Government agencies
should facilitate development and creation of infrastructure in the mining areas,
particularly in providing right of way, railway clearances, water, electricity, etc. The
Government could also consider pre-identification of non-coal bearing corridors to be
used for rehabilitation colonies and townships.

                                                6
The captive block developers should coordinate with other coal block developers in
proximity to jointly fund the development of Infrastructure based on a Master Plan
prepared by an independent agency.

2. Allocation of Coal block

Allocation of coal block should not only look into the promoter background and the end-
use, but should give importance to the technical & financial capability of the applicants
for timely development of the blocks. The process of allocation of the block could also
take into consideration the extent of the preparedness of the developers and the projects.
Further, auctioning approach may be adopted for allocation of coal blocks. However, it
may be noted that auctioning of the block to the highest bidder may not be economically
viable, since it would get translated into a pass through in the cost of end-use product and
thereby adversely affecting the ultimate consumer.

The following approaches, depending on the level of information available for the coal
blocks, may be adopted in taking the auctioning route for allocation of blocks:

              Status of block              Possible criteria for allocation
         Fully explored                    Lowest cost of power generated

         Partly explored                   Maximum estimated production

         Totally unexplored                   Production sharing formula

Auctioning on the basis of maximum proposed production or production sharing formula
may be workable till sufficient data on the depth, seam thickness and quantity & quality
of the coal is available for the blocks put up for auction. However, once sufficient data is
available for the blocks put up for auction, the criteria for grant of block could be linked
to the lowest cost of power generated from captive coal block.

3. Approvals and Clearances

In the present legislative and regulatory framework, the allottee of a captive coal block
has to obtain multitude of clearances and approvals as provided under the provisions of
the Coal Mines (Nationalisation) Act, Colliery Control Rule 2004, Coal Mines
(Conservation and Development) Act 1974 and rules thereunder, Mines and Mineral
(Development and Regulation) Act 1957 (MMDR), Mineral Concession Rules 1960
(MCR), Environment Protection Act with its rules and procedures, and Forest
Conservation Act with its rules and procedures.

In the federal structure of India, the State Government is the owner of the minerals
located within the boundaries of the State. Thus, though the Central Government
allocates the coal blocks for captive mining, the State Government grants the
Reconnaissance Permit (RP), Prospecting Licence and Mining Lease under the provisions

                                             7
of the MMDR Act and Mineral Concession Rules. However, the State Government can
grant the mining lease only with the prior approval of the Central Government as
provided under section 5(1) of the MMDR Act. Central Government approves the
application only after the coal block allottee obtains the mining plan approval and obtains
clearances from several authorities at the Central, State and District level.

Although broadly three clearances are required, i.e. Grant of RP or ML, Environmental
Clearance and Forest Clearance, but depending on whether the allotted block is explored
or unexplored, in forest or non-forest area, etc. clearances may be required from multiple
authorities. The table below indicates the authorities and agencies at the Central and State
level from whom the approvals have to be sought by the coal block allottees before actual
production can begin:

Approvals / Clearances                    Authority / Agency Involved
Mining Lease
Approval or Purchase of Geological Report CMPDIL (purchase could also be from
                                          SCCL, MECL)
                                          Directorate General of Civil Aviation and
                                          Ministry of Defence (for unexplored blocks
                                          if aerial reconnaissance is conceived)
                               Mine Plan CMPDIL
                                          Coal Controller
                              Mine Safety Directorate General of Mine Safety
      Mining Technology & Conservation Coal Controller (under the provisions of
       Measures, and Coal Categorisation Colliery Control Rules and the Coal Mines
                                          (Conservation & Development) Act)
                            Mining Lease State Government (Mining Department),
                                          Ministry of Coal (GoI) – Reviewed at
                                          various levels within the Departments at
                                          the State & Central Government level
Environment
                       EIA / EMP Studies State Pollution Control Board
                                          State Environmental Impact Assessment
                                          Authority
                                          State Water Resource and Water Supply
                                          Department
                                          District Administration (for various aspects
                                          of site clearance)
                                          Coal Controller
                                          Department of Environment (MoEF)

Forest
                     Forest Clearance & Committee to Advise GoI (MoEF)
      Valuing Compensatory Afforestation Office of Chief Conservation of Forests,
                                         (Regional Office of MoEF)
                                         State Forest Department & District

                                             8
Authority
                                               Department of Forest (MoEF)
                                               State Revenue Department
                                               Hon’ble Supreme Court

Land Acquisition                           Ministry of Coal (under provisions of
                                           CBA)
                                           State Department of Revenue
Infrastructure     (Electricity,    Water, Appropriate Departments of the State
Railways, Road, etc)                       Government & Ministries of Central
                                           Government

It may be noted that of all the clearances, the MoEF clearance is the most time
consuming, since many departments and issues are involved in getting environmental
clearances and also vast majority of the coal blocks are situated on forest land. Even
geological investigations (which require drilling for exploration) in these areas require
MoEF approval. This approval is a lengthy process and takes a lot of time.

The Guidelines for Allocation of Captive Blocks & Conditions of Allotment through the
Screening Committee, Ministry of Coal, provides for the normative time limit ceilings
(Appendix 1) to ensure that coal production from the allocated captive blocks commence
production within 36 months (42 months in case the area is in forest land) of the date of
issue of letter of allocation in Open Cast (OC) mine and in 48 months (54 months in
case the area fall under forest land) from the date of said letter in Under Ground (UG)
mines. The following chart (drawing upon the ceiling time limit provided in the
Guideline) is an indicative depiction of the schedule of commencement of mining
operations from the time the coal block is allocated:

                                           9
The Guideline of MoC, mentioned above, is to ensure timely development and operation
of the allocated captive blocks. In order that the allottee adheres to the timeline, the
allottee has to provide a bank guarantee and the encashment of the bank guarantee is
dependent on achievement of the milestones consistent with the normative time limit
ceilings.

Time limits are specified in the Mineral Concession Rules and other legislations for
maximum time permissible for grant of approval on an application. This is based on the
time to be taken from the receipt of completed application. Since basic information
required for processing the application is available at the district level, particularly for
forest clearance, unless and until all such information is available, the application is
considered incomplete. The time taken at various levels of scrutiny delays the process.
Thus, in view of the large number of approvals required, it is unlikely that the timeline
specified by MoC for development of coal block would be adhered to by the coal block
allottees. The existing provisions of the Acts do not provide for deemed approval status
to applications if the time lines are not adhered to and thus there is no urgency in
disposing the applications within the specified time.

                                            10
From the above, the following limitations are thus evident in the process of grant of
     clearances and approvals, which would cause significant delay in production from the
     allotted captive blocks:

               Several parallel clearance & approval processes are to be pursued at the Central
                Government and State Government level, and the allottee has to follow-up the
                with the applications with various authorities.
               Environment and Forest clearance is extremely time consuming and significant
                delays arise in the public consultation process, valuation of compensatory
                afforestation, identification of non-forest land for compensatory afforestation,
                enumeration of trees and completion of cost-benefit analysis by the forest
                departments.
               The entire process of seeking approvals lack clarity, and often delays in one
                process causes delay in the others. Besides, conditions of Mining Lease are not
                standardized and could be significantly influenced by individual judgment of the
                granting authorities.

     A comparative study on grant of mining lease in Australia, Canada and India, included in
     the Report of the Expert Group constituted by the Ministry of Steel for formulating
     Guidelines for Preferential Grant of Mining Leases (2005), suggests that the time taken
     for grant of mining lease in Australia is about 1-2 years (12 + months) and in Canada
     about 2-3 years (12-36 months) as compared to 7-8 years in India (though the Mineral
     Concession Rule8 provides that the State Government shall dispose off the application for
     grant of mining lease within 12 months from the date of receipt of application). The
     observations of the study are listed in the following table:

           Australia9                      Canada                              India
State is fully empowered to State is fully empowered to State to grant mining lease with
grant mining lease              grant mining permit (MP)         the approval of the Central
                                                                 Government
Single     window      process, Single     window       process, Approvals are required from
involving 4 agencies:           involving     3     government multitude of authorities at the
 Department of Minerals & agencies:                             Central, State and District
    Energy                       Department of Natural levels, with the different
 Department of Environment        Resource                      authorities having little or no
 National      Native    Title   Department   of Environment   coordination amongst them.
    Tribunal                     Department of Labour           Broadly 3 different clearances
 Land Acquisition Authority                                     requiring submission of separate
    in Local Government                                          applications:

Minister       of   Minerals   and                                            (1)Approval of Grant of ML

     8
      Mineral Concession (Amendment) Rules 2002
     9
      The Mining proposal approval process and minimum timeframes of process as provided in the Regulatory
     Guideline No.1 of the Division of Minerals and Energy Resources, Government of South Australia, June
     2007 are presented in Appendix – 2 of this note. The regulations laid down by the Department of Industry
     & Resources, Government of Western Australia are similar.

                                                       11
Energy is the final approving                                         (2) Forest Clearance
authority, and takes decisions in                                     (3) Environmental Clearance
consultation      with      other
Ministries. Close interaction                                         Central Government grants
between       Department       of                                     forest    and  environmental
Minerals and Energy and                                               clearances      on       the
agencies      responsible     for                                     recommendations of the state
protection of environment.                                            Government.

Mining Lease: Time taken for         Mining Lease: The time taken
                                                             Mining Lease: Although time
grant of mining lease is 1-2         for grant of MP is 2-3 years.
                                                             frame     for    clearances     &
years. Time taken for activities     Fixed time frames are complied
                                                             approvals are specified as less
involved are fixed & largely         with.                   than an year in the various rules,
adhered to, except in cases                                  the actual time taken are usually
where      public     consultation
                              The project can be rejected if 7-8 years for grant of ML.
process       &        stakeholder
                              there are strong chances of
participation is involved.    adverse socio-economic and Identification of non-forest land
                              environmental impacts.         for compensatory aforestation
Applicants submit application                                takes long time and at times
for grant of lease with the                                  takes more than a decade.
Mining Registrar in the
Department of Minerals &                                     Requirement of enumeration of
Energy.                                                      trees, cost benefit analysis
                                                             carried by the State Forest
                                                             department is time consuming
                                                             (10-12 months)

Mining areas are categorized as      The project is first assessed -
per environmental sensitivity.       from Environment angle, before
Conditions & procedures for          processing for Mining Permit
each category are predetermined      (MP). Once the project gets
and identified in each case.         clearance from environment
Grant of mining leases in very       angle, the proponent makes an
sensitive areas require approval     application for MP.
from both houses of Parliament.

Applicant is required to submit      Department of Natural Resource -
a Bond to take care of               requires a bond or security to
environmental                 and    ensure that reclamation work is
rehabilitation considerations.       carried out.
Financial & technical strength       Info not available              Limited emphasis being given
of the applicant are taken into                                      on the technical and financial
consideration before grant of                                        strength of the applicant.
mining lease.
Minimum term of mining lease         The minimum term of Mining Mining lease is granted for 20-
is granted for 21 years.             Permit is 20 years.        30 years

                                                  12
Based on the above observations and discussions, the following suggestions may be
considered to speed up the approval process and grant of mining lease:

   A single window approach through nodal agency set up at the State level under the
    department of mines with representation from all the concerned departments of
    various ministries. The nodal agency can pre-determine the conditions for each
    category of land based on environmental sensitivity and the nature of the proposed
    activity (prospecting, mining etc.). The nodal agency may complete the requirements
    of identification of land for compensatory afforestation, enumeration of trees, cost-
    benefit analysis, etc. before inviting application for ML.

    Since a single window approach may require change in legal procedure, alternately a
    Public-Private Partnership model can be adopted in the form of a shell company
    formed for each of the captive blocks allocated, as has been done in the case of
    UMPPs in Power Sector wherein in shell companies (formed by the Public sector) are
    bid out to the private sector only after obtaining clearances and land acquisition
    process completed.

   As an immediate remedial measure, MoEF should map and segregate the entire coal
    bearing areas into ‘Go’ and ‘No-Go’ areas for each type of lease (Reconnaisance,
    Prospecting, and Mining) on the basis of the forest cover and environmental &
    ecological sensitivity. The GoI/Ministry of Coal (MoC) by not allotting the blocks
    under the ‘No-Go’ areas would prevent wastage of resource and also speed up the
    approval process for grant of lease. Thus, for areas defined as ‘Go’, it may be prudent
    to allow minimal or no forest & environmental clearances for investigative or
    prospecting purposes, with the conditionality that cutting of trees without prior
    permission is not allowed. Thus, although the need for detailed environmental impact
    studies, assessment of compensatory afforestation & enumeration of trees and cost-
    benefit analysis for forest clearance is required for mining approval, the same level of
    detail may not be required for limited drilling involved in prospecting or investigative
    purposes.

   Forest clearance is a contentious issue and has been further compounded by the
    development which requires each case of forest clearance a concurrence by Forest
    Advisory Committee or the empowered committee, which has to then send a report to
    the Hon’ble Supreme Court before sanction is accorded. This procedure needs to be
    reviewed and the empowered Advisory Group or the empowered committee & MoEF
    could be delegated authority to accord approval in certain defined categories of forest
    areas.

   MoEF clearances for projects which have a greater probability of commencing
    operations before the Eleventh Plan should be given priority.

   The approval for the prospecting license by the state government should be issued as
    the foremost requirement within a minimum time. The developer could then develop

                                            13
the coal block in 2-3 phases, i.e. identify comparatively easier areas within these
   blocks (keeping in view government/private land, forest/non-forest land etc.) and get
   the required investigations, mining plan, approach etc. for the first phase so that
   production could start early, and simultaneously also repeat the cycle of activities in
   the subsequent phases. This approach will require due consideration and consents by
   Ministry of Coal as well as Ministry of Environment and Forest.

4. Land Acquisition

Unlike other industries siting of a coal mine does not leave room for choice in the land to
be acquired. Land has to be acquired where coal exists, irrespective of population base or
existence/ density of forest land. The present procedure on land acquisition is lengthy and
is prone to litigation. In a large number of cases, a large part of the land belongs to the
government, and in such cases the Government should take measures to transfer the land
to the developers in a shorter timeframe.

5. Rehabilitation of Project Affected People

As regards Rehabilitation of Project Affected People (PAP) there are many prevalent
Resettlement & Rehabilitation (R&R) policies. The Central Government has a National
R&R policy 2007, which provides for the State Governments to have their own policies.
States in proposing their R & R policies to the benefit of the PAPs are more stringent on
the project developers. Also providing employment to all PAP may not always be
possible as new technology driven mining methods is less labour intensive.

It is recommended that the Ministry of Coal should coordinate with the State
Governments to align the State R&R Policies with the National R&R Policy. Further, the
State Governments should facilitate the developers in negotiating the compensation
package with the PAP’s.

For general development and improvement in the coalfield areas, the State Government
could consider creating an “Area Development Fund” by applying a levy on each tonne
of coal produced. This fund could be utilized for social welfare of PAP including their
health & education, improvement of infrastructure, roads, water supply etc.

6. Geological Investigations & Mining plan – alternate agencies

In most coal blocks allocated to companies, detailed geological investigations have not
been done. At present, exploration for coal in India is carried out by Geological Survey of
India (GSI), Mineral Exploration Corporation Ltd (MECL), Singareni Collieries
Company Ltd (SCCL), Directorates of Mines and Geology of some states. These
agencies have limited capacity for drilling of areas (for collating data) and, currently, are
already fully stretched. Out of 22,400 km2 of the coal bearing sedimentary formations
identified by GSI, only about 10,200 km2, or only 45% of the total area, has been
systematically explored through regional and promotional drilling.

                                             14
Apart from geological investigations, in the present legislative framework the Mining
Plan is approved by Ministry of Coal (with technical inputs from CMPDIL). This further
delays the whole process.

Thus, new agencies with the competence to perform geological investigations need to be
set up and accredited by the Government of India. These agencies should be independent
and unaffiliated to Coal India Limited or other public sector coal companies. These
agencies or an independent expert group should also be empowered to review and
approve the mining plan, which would be an input to Ministry of Coal.

7. Tapering coal linkage/ marketing of surplus coal

The timeframe for development of coal block is likely to be much longer than a power
plant in view of the various problems faced by the developers. Therefore, there is a risk
that the power plant would be commissioned prior to the commercial operations date of
the coal mine. In order to mitigate this risk of delay in the commercial operations of the
coal mine, Ministry of Coal has decided to provide coal linkage on a tapering basis to the
power producers who have been allotted coal blocks for captive use. The tapering linkage
is being considered by the Ministry of Coal to facilitate the working of end-use plants in
case of development of coal blocks allocated to such consumers does not synchronize
with the operation of end-use plant. In this regard, MoC, in December ’07, came out with
a Guideline relating to issue of LoA/allocation of coal on ‘Tapering Basis’ to various
consumers. However, the application for such tapering linkage would only be considered
if the applicant has an approved mining plan for the coal block allocated.

This is tricky and most of the captive block owners are unlikely to qualify for tapering
linkage even if their end-use plant is in an advanced stage of development. The Ministry
of Coal should consider reviewing this condition for grant of tapering linkage to facilitate
rapid capacity addition in power (considering the huge deficit situation in power and
sustenance of economic growth), and should consider granting tapering linkage based on
technical & financial capability of the developer and preparedness of the end-use project.
Instead of keeping approved mining lease as criteria for considering the application of
tapering linkage, the Ministry of Coal should provide for the condition that the mining
lease should be approved before the power plant commences operations.

8. Joint Allotment of Coal Blocks

In some cases a coal block has been allotted to a number of companies and the allottees
are required to submit Bank Guarantees to safeguard commercial obligations and ensure
timely development of the allotted coal blocks. If some partner companies of the
proposed Joint Venture do not furnish the Bank Guarantee, then the development of the
mine and of the associated power plant with the mine is held up.

It is recommended that if in the consortium of companies granted a coal block, one or
some of the partners are not serious, but the remaining partners are serious, then the
progress of the development of the block by the consortium should not be jeorpardised.

                                            15
Thus, companies in the consortium who furnish the Bank Guarantee should be allowed to
proceed with development of the coal block, and the partners who fail to provide the bank
guarantee should be replaced with other companies from among the applicants whose
applications are pending with the Ministry. However, pending the replacement of
partners, the development of the coal block should proceed as usual. In this regard, the
company allocated the coal block, having the requisite financial strength, could also be
given the freedom to choose partners from among the applicants whose applications are
pending with the Ministry.

9. Infrastructure status for Coal industry

Coal industry needs to be given infrastructure status so as to attract more players into this
industry and to incentivise domestic production of mining equipment. The infrastructure
status could be for both coal mining and coal washeries. Infrastructure status for the coal
sector would bring it to par with other sectors such as roads, railways, oil and laying of
oil and gas pipelines.

In the past, this proposal was rejected as bulk of the coal mining was under the public
sector. Coal mining, however, is expected to undergo a major change in the coming years
with production from captive coal blocks mainly by private sector companies. The main
beneficiaries would be power companies as concessions would make coal production
economical that would ultimately help in keeping power tariffs low. Coal companies
would be also able to import capital equipment and spares at concessional rates.

                                             16
Appendices

Appendix – 1: Normative Time Limit Ceilings as provided in Guidelines for
Allocation of Captive Blocks & Conditions of Allotment through the Screening
Committee, Ministry of Coal

Sno. EVENT                             TIME LIMIT
                                       in months from '0' date
1    Allocation                        0
2    Purchase of GR                    1.5
3    Bank Guarantee                    3
4    Mining Lease Application          3
5    Mining Plan submission            6
6    Mining Plan approval              8
7    Previous approval application     11
8    Previous approval                 11
9    Forest Clearance application      12
10   Forest Clearance                  18
11   Environment Clearance Application 12
12   Environment Clearance             18
13   Mining Lease grant                24
14   Land acquisition begin            9, 19
15   Land Acquisition                  30, 36
16   Opening permission application    34, 40 for OC
17   Opening permission grant          35, 41 for OC
18   Production                        36, 42 for OC
                                       48, 54 for UG

                                         17
Appendix – 2: (a) Flowchart of mining proposal approval process

Source: Mining Approvals in South Australia, Regulatory Guideline No.1 of the
Division of Minerals and Energy Resources, Government of South Australia, June 2007

                                        18
Note: PIRSA - Department of Primary Industries and Resources; TRC - Tenement
Review Committee - PIRSA independent peer review committee for lease application
assessments; DAC - Development Assessment Commission; EIC - Extractive Industries
Committee - a Subcommittee of DAC; EPA - Environment Protection Authority; MARP
- Mining and Rehabilitation Program; SEB - Significant environmental benefit (offset for
native vegetation clearance)

                                           19
Appendix – 2(b) Minimum Timeframe of Process

                                    20
21
Source: Mining Approvals in South Australia, Regulatory Guideline No.1 of the
Division of Minerals and Energy Resources, Government of South Australia, June 2007

                                        22
You can also read