Analysis of cracks in metro segment using FEM, rectification methods proposed and associated cost saving, points to ponder for young designers
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
POINT OF VIEW Analysis of cracks in metro segment using FEM, rectification methods proposed and associated cost saving, points to ponder for young designers Vivek Abhyankar and Raviteja Kilaparthi One of the Elevated Metro Rail Viaduct projects near further investigate this issue and to get a third party proof Kolkata reported micro cracks in specific type of segments checking certificate from one of the eminent institutes in (S2 Type which had opening in a deck), repeatedly. The India (i.e. IIT) the authors performed detail 2D analysis problem persisted for more than one year or so due to and then 3D finite element analysis. The analysis was lenient approach from the owner, consultant and the done using a good software. Figure 1 shows model of contractor. But after some time when the supervision S2 segment with the stress contours. Various techniques agency noticed it, they almost stopped the work with an were adopted so as to simulate the real behaviour in the explanation as “poor workmanship by the contractor”. computer model. Later, the analysis was cross checked Then the construction team referred this problem to the by other software programs and similar conclusions were authors of present paper. Authors tried to investigate derived. To complete the whole modelling, analysis, the matter in detail including QAQC programs, designs, design and verification it took some time, during which safety precautions etc. and came up with a possible cause many innovative thoughts and techniques were tried / of cracks as ‘deficient reinforcement detailing around the adopted by the authors, which helped to establish the opening in the deck slab’ and not the workmanship. To Figure 1. Showing a model of S2-segment with the stress contours The Indian Concrete Journal March 2018 63
POINT OF VIEW (a) Local Thickening around the Opening in S2 segment and a typical photo of a crack developed on edge of a segment (b) Actual Cracks in S2 segment (left image shows crack other than diagonal and right image crack penetrating towards the thickness of concrete after extending till edge) (c) Schematic paper model with an opening before and after application of a force is shown above. In the second image i.e. after application of force the cracks developed in diagonal direction can be clearly seen Figure 2. Model and photos to demonstrate the effect of opening and associated diagonal cracks 64 The Indian Concrete Journal March 2018
POINT OF VIEW fact and finally to get the approval from the eminent / specified lifting points approved by the designer; during authorities/ third party proof checkers. lifting of a segment, complete weight of the Segment is borne by lifting points. If the lifting-span (i.e. distance between In the present paper the authors have explained this lifting points) is not maintained as per the design, then process and the learning they had from this complete additional stresses may generate in each component of the exercise and the financial implication (benefits) in segment (like Top deck, web and soffit etc.) and may even general, purely from academic point of view. This paper increase beyond the permissible values (fcr=0.7√fck), resulting will be very much useful for budding engineers / bridge into formation of cracks. In some cases viz. for the segment designers while detailing the reinforcement in segmental with opening in deck or soffit (where the opening is kept construction. for maintenance purpose, ref Figure 2) if the detailing goes wrong, especially for the reinforcement around the opening, INTRODUCTION the cracks will develop diagonally and may propagate outwards and in adverse cases even extend throughout the Bridge construction has several types; the two broad complete thickness of concrete section. Similar detailing categories of bridge construction are (i) precast construction mistake had happened during the detailing of the segment and (ii) cast in-situ construction. In precast construction, reinforcement in one of the Elevated-Metro viaduct design the segments are manufactured in ‘casting yard’, cured projects near Kolkata. In this paper the complete incidence till gain of sufficient strength in ‘stacking yard’ and then and learning are shared purely from academic point of view sequentially all segments are transported to construction without mentioning the names of parties involved. Hope the site and launched, one by one, using various bridge reader of this paper will learn about the intricacies involved launching techniques. Then segments are glued together in the detailing of reinforcement and will find it useful in followed by application of temporary stress to squeeze-out their day-to-day designs. the entrapped air at joints between two segments, the post- tensioing is done to form one integral span. Whereas, in cast In this elevated metro viaduct project, the same type of in-situ construction method, the whole structure is cast at cracks was seen around the openings. These cracks were the construction site itself, using formwork and supporting transmitting outwards in diagonal direction, during lifting. staging arrangement. In precast segmental construction, Usually in any segment with opening, the periphery of the while shifting the segments from casting yard to stacking opening is thickened / stiffened using RCC peripheral beam yard and there onward to site, they are lifted at predecided Figure 3. Description of clause 9.6.1 from SP 34:1987 The Indian Concrete Journal March 2018 65
POINT OF VIEW or a steel framing so that the stiffness is maintained properly segment, which could not be obtained as per the contractual (ref. Figure 2a). Figure 4 show typical cross section and plan agreements of the said project. Hence authors had to perform of segment ‘S2’ with the key dimensions. fresh calculations to verify the phenomenon of cracking. IDENTIFICATION OF THE PROBLEM AND At the beginning authors tried to make a 2D analysis of PLANNED ACTIONS segment to determine the forces (bending moment, shear force and axial force) in various parts. After obtaining these After the work was ceased on account of persistent cracks forces still the cracks in the segments could not be justified; the authors inspected all the relevant Quality control record hence a detail 3D FEM analysis had to be carried out. After (viz. material testing reports, procedures etc.) and all were processing the 3D model some clues were obtained. Further found in order; even all were approved time to time by the the 3D model was refined towards accuracy (Figure 7 client’s representative and the DDC. Hence there was hardly showing the schematic analysis models and Figure 8 any scope for deviation from the desired quality of concrete / showing the forces in 2D and 3D models). reinforcement and workmanship. Hence the authors focused their attention over the design / drawing and detailing. In design there were two broad areas – (i) the design of main GEOMETRY OF THE SEGMENT AND structure and (ii) design of temporary works and its effect REINFORCEMENT DETAILS on the permanent work. At beginning itself it was noticed The geometry of the typical S2 segment can be seen from that the DDC had released two revisions of drawings for the figure (cross-section, plan and elevation). M-40 grade of the segments under discussion. The first revision was ‘A’ concrete using OPC (No fly ash/micro silica/GGBS etc. was showing the orientation of opening ‘transverse to the bridge used) and Fe-500 grade reinforcement was used for casting axis’ and then the second revision ‘B’ was issued after segments. Modulus of elasticity of concrete Ec of 5000√fck about six months gap where the orientation was changed (in MPa) and that of steel reinforcement as 2.0 x 105 MPa in ‘longitudinal to the bridge axis’. As revision ‘B’ was a was considered by the original designer as per the Design last (latest) approved version, the complete construction Basis Note (DBN). Along the opening 2-T.16mm bars were took place as per revision ‘B’ of the drawing. But the provided at top at bottom (i.e. 4 bars total) along all four reinforcement detailing in revision ‘B’ was kept same as edges and diagonal bars of 2-T.10mm were provided at top revision ‘A’ by the Jr. Designer (by mistake)! Figure 5 shows and bottom, as shown in Figure 5c. Poisson’s ration of 0.25 the orientation of the opening and reduction in the concrete was specified in design but was not used in original design. area, Figure 5 also shows reinforcement details around the Even in original design detail temperature, shrinkage, creep opening as per revision ‘A’ and ‘B’. Figure 6a shows the analysis was done. It was found that the temperature was segment in lifted position with lifter beam and segment not cause of the cracks but it was purely structural. stacking position (ref. Figure 6c). After the revision ‘B’ was compared with standard detailing practices prescribed by In SP-34 code the types of openings in concrete are classified SP 34 : 1987 version of code (clause number 9.6.1), the lacuna as (i) small opening and (ii) big opening for which the in the reinforcement detailing came to the notice. The said reinforcement detailing deffres; unfortunately the code has clause (i.e. 9.6.1) is reproduced as below, for completeness not mentioned a specific criteria to distinguish between of explanation. these two; hence often the difference of opinion arises between designer and the proof checker. Hence in important The reinforcement provided in the S2 segment around cases the designer should himself ascertain the stresses the opening was 50% of the required, as per the above around the opening, and atleast adhere to the minimum mentioned clause. The designer himself claimed that for the reinforcement (if not detail analysis is done). In the present forces considered, there was no requirement of providing project the reinforcement provided along the opening was additional 50% reinforcement and SP34 code need not to far lesser that the minimum prescribed reinforcement for be followed. In the same way, the diagonal reinforcement even the small opening. In addition, due to the revision in provided were 39% of the required reinforcement as per said the drawing issued at last moment there was further mistake clause. Even the development length for diagonal bars was (shortfall) in the reinforcement. lesser than that specified in SP-34. COMPUTER SIMULATION (MODELING) For further investigations the authors requested the designer Finite element analysis (FEA also called FE method or simply to share the complete design calculations of the said FEM) is a computerized method of structural analysis in 66 The Indian Concrete Journal March 2018
POINT OF VIEW Figure 4. Section showing geometry of the segment along with key dimensions The Indian Concrete Journal March 2018 67
POINT OF VIEW Figure 5. Reinforcement detailing around the opening in revision ‘A’ and revision ‘B’ 68 The Indian Concrete Journal March 2018
POINT OF VIEW which a main structure is sub-divided into smaller elements; software may be used. But as in present case the loads were this process is called as ‘discretisation’. The assemblage of well within the elastic limits and present software could all the elements together is called as mesh, and it is nothing give the results as per real behavior, such need of advance but a mathematical model resembling the shape of main software did not arise. structure / object. FEA finds out required stresses and displacements developed at each element (nodes) in a mesh Two conditions, namely (i) segment lifting and (ii) segment (Locally and globally) due to the applied forces. As on today, stacking were idealized in the segments by changing the there are many professional software programs available for support conditions. In stacking of the segments usually the FEM modelling and analysis. In present study, a full scale segments are stacked in two layers (ref. Figure 6b) but in 3D model was developed in a good software to analyze rare cases the segments are stacked in three layers. Figure 6c the behavior of cracks developed around the opening of a illustrates the three layers stacking in some other project. In typical box girder segment, namely ‘S2 segment’ (second present project, considering the position of S2, there were segment in a bridge viaduct of said work) during its further two possibilities, (i) S2 in bottom layer (ii) S2 in top lifting. In the model only concrete could be modeled and layer. As segment S2 were the heaviest segments among all, not the reinforcements (especially reinforcements around they had to be stacked in the lower layer and even the design the opening); for modeling the reinforcements advanced consultant checked and confirmed the adequacy to withstand Figure 6. Showing segment in lifting position and stacking position (respectively) The Indian Concrete Journal March 2018 69
POINT OF VIEW load from the upper segment. Usually the construction sites tried (Figure 7). After the stress contours were obtained prefer three layer stacking as it makes more stacking place around the opening, it was realized that the stresses are available. But in such case the safe bearing capacity of soil varying along the element corners and are extremely high. should be higher. In Kolkata as SBC is generally low (due As the element size was larger (500mm x 500mm) the finer to clayey soils) in present project 2 layer stacking was used, behavior could not be obtained and the authors decided to which fortunately reduces the load on S2 segment. But still the segment cracks due to inherent reinforcement detailing refine the mesh size around the opening; thus the elements mistakes. were reduced to 125mm x 125mm (rectangular and triangular elements, Figure 8b shows the refined elements pattern). As mentioned earlier the construction took place as per revision ‘B’ of the drawings, the modeling was done as ANALYSIS RESULTS AND CORRECTIVE per position in revision ‘B’. The plate stress contours were ACTIONS obtained for both positions (lifting and stacking). The plate stress contours are shown ahead in this paper. As an The various results obtained from 2D and 3D analysis are as alternative to FEM model a 2-Dimensional model was also presented in the figure. Figure 7. Schematic models of the segment 70 The Indian Concrete Journal March 2018
POINT OF VIEW Figure 8. Forces in various components The Indian Concrete Journal March 2018 71
POINT OF VIEW Bending moments in various elements around the opening, in orthogonal (X, Y) and oblique / skew directions were found out from the analysis and result of the model. The working stresses developed due to the resulting bending moment were found out and compared with the permissible tensile stress values as per IS: 456 clause number 6.2.2 (fcr=0.7√fck). RCC design by working stress method was carried out to estimate the required stresses. Two such designs were carried out (i) for present project and (ii) another for a similar project with same loading and other conditions, which was already executed successfully. The stresses in ‘i’ were higher than that in ‘ii’ and also that as per the clause 6.2.2 of IS:456. The reinforcement detail in case ‘ii’ was found to be in order with the recommendations of BIS-SP-34 code. These findings were recommended to third party proof checking agency (IIT), and got readily approved. After the outcome this study was brought to the notice of the client & consultant. They asked to perform the segment lifting at 7th than the 3rd day. As per contract specifications the segments were to be lifted at 3rd days or gain of strength to concrete whichever is later. Even the lifting is done at 7th day, still the segment cracked. Then a few segments were lifted at 14th & 28th day. Even these segments cracked. Now the client & consultant got convinced with the shortfall in the reinforcement & not the shortfall in concrete strength. But this all consumed some project duration. RECTIFICATION MEASURES AND COST IMPACT After identification of the root cause of cracks, another question was how to rectify these cracks in (i) already erected segments and (ii) in segments to be cast in future. The segments to be cast in future were provided with the additional reinforcement as shown in Figure 9 as per SP-34 recommendations and it was noticed that there were no cracks i.e. the issue of cracking was resolved. For the old segments IIT recommended the treatment using epoxy grout. The cost of typical S2 segment was ranging between 3.5 lakh and 4.0 lakh in this project. When the PMC rejected about 13 segments on gross basis (without any in depth root cause analysis), the contractor got panic because it would have Figure 9. Corrected reinforcement detail around the opening cost them penalty of 48 lakh (approximately); not only so, 72 The Indian Concrete Journal March 2018
POINT OF VIEW the repair of already launched segments would have cost 6.2.2 and also as per the reinforcement detailing in SP34 them penalty of another 55 lakh (Thus the total penalty of code. Thereby it was noticed that the stresses around the about one cr. rupees along with time loss & bad name in the opening of S2 segment of the said project were beyond industry). the permissible values, which was the main cause for the development of cracks around the opening. The working After the author of paper scientifically proved that the stresses for the S2 segment of similar successfully executed mistake was not with the workmanship but the reinforcement project were less than the permissible values as per the detailing, the consultant and the client, both got worried. said codes. So, the authors of the paper has proved that the They got their design reviewed from many experts in the reinforcement detailing had gone wrong for the S2 segment industry and finally understood that there was a lacunae in of present ongoing project and it was not as per the norms of their own designs and drawings. Also the instruction used SP34 code but not the workmanship problem. The same was by the client to lift the segment at 14th day was against their approved by eminent proof checking agency. own contract specification and would have resulted into serious time loss i.e. from 2yr contract duration to about 8yr The proposed exercise made the authors to explore all along with additional cost resources, eventually the contract possibilities by which the segments could crack and cross rates (due to escalation) would have become unjustifiable check the attributing causes at site. Correct detailing of for them. So finally client has withdrawn this instruction. the reinforcement at the original design stage would have Later, client and consultant requested contractor to suggest avoided complete delay and even wastage of construction the rectification measures. On this, contractor submitted the materials used for rectifications. This case study is a classic proposal of ‘additional reinforcement’, which was costing example to the budding designers as (i) computer software merely 2 lakh rupees in remaining segments of whole is merely a tool, inferior / insufficient input could cause project. Whereas the segments which were pre-erected were inferior results (GIGO) as in present case; (ii) while reducing retrofitted with epoxy grout; the proof checker had already the reinforcement below the minimum recommended certified that as the cracks appeared in S2 segments during standards of IS / IRC codes (which are based of some lifting were in transverse direction, they did not influence research / reference) or a deviation alike, one has to carry out the structural performance of the bridge after application out in depth study / investigations to avoid the adversities of Post-Tensioning force and mere epoxy grouting was caused in present case. Each project is unique; designers / sufficient. Thus the estimate of 1cr rupees reduced to just a contractors / PMC and client all shall be alert at all stages few lakhs. Client, consultant, contractor and even authors (design, detailing, casting, erections), without any prejudice. learnt many lessons from the final technical and financial Site engineers should not hide the facts observed at site till output of this whole mission. Thus whole assignment was the end they become really sore. The present paper is really concluded technically & happily. an eye opener for all bridge designers & contractors and should be followed with open eyes. SUMMARY AND CONCLUSIONS The problem was identified from the construction site After the present study was concluded, the authors came sources. Authors obtained the available drawings (GAD across similar case of cracking around opening segment at and Reinforcement) of S2 segment namely Rev-A, Rev-B another road project in Delhi. Such repeated occurrence of and drawings from similar viaduct project. 2D and 3D FEM cracks due to reinforcement detailing mistakes inspired the modeling of S2 segment was done in the software with authors to compile present paper to avoid repeated detailing supports as lifting points and loads as self weight of S2 error among young bridge engineers. segment and UDL for Blister block. For the accurate results, the elements around the opening were refined. From both the References models, the required bending moments especially bending 1. ______ Plain and Reinforced Concrete, IS 456 : 2000, Bureau of moments for the plate elements around the opening were Indian Standards, New Delhi. obtained. Further working stresses were calculated with 2. Handbook on Concrete Reinforcement and Detailing, respect to the obtained bending moments and compared SP-34 :1987. with the permissible stress values as per IS 456 2000 clause The Indian Concrete Journal March 2018 73
POINT OF VIEW Er. Vivek Abhyankar, C.Eng (India), formerly working at Afcons Infrastructure Ltd., has 18+yrs of industrial experience in planning and design, detailing, construction of various enabling and permanent works in reinforced concrete and steel. He is a life member of various Institutes, professional trainer, visiting faculty for graduate and post-graduate students in structural engineering, guide for AMEI projects in civil engineering. He is a Gold medal winner in structural engineering, wrote various technical papers, contributed to two books, guide to various technical thesis, technical trainer and a certified internal auditor. Er. Raviteja Kilaparthi holds an M.Tech in structural engineering from VNIT-Nagpur. He is presently working as a design engineer in eminent firm in Mumbai. He has presented two technical papers in renowned journals / workshop. He has experience in the design and conceptualization of various enabling works required in bridge construction field. 74 The Indian Concrete Journal March 2018
You can also read