State of the Utility Report 2011 - LOTT Clean Water Alliance
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Board of Directors Cynthia Pratt City of Lacey Doug Mah City of Olympia Ed Stanley City of Tumwater Sandra Romero Thurston County Cathy Wolfe Thurston County (2010) Executive Director Michael D. Strub, P.E. Acknowledgements Text written, compiled, and edited by Karla Fowler, Lisa Dennis-Perez, and Paula Williamson 2011 LOTT Board of Directors Cover photo by Doug J Scott Photo and graphic selection, editing, and production coordination by Karen Tuomey Graphic design by Cheri Huber (Huber Design) and Karen Tuomey Data, content, and review assistance provided by LOTT staff Photography by Charlie Kirry (Charlie’s Photography), Aerolist Photographers, Inc., and LOTT staff Water Filters glass artwork by Pam Beyette Published in March 2011
March 2011 On behalf of the LOTT Clean Water Alliance’s Board of Directors, I am pleased to present LOTT’s 2011 State of the Utility Report. This report includes highlights from 2010, which was another amazing year for LOTT, and a preview of projects planned for 2011. This annual report also provides a snapshot of how LOTT is doing in terms of meeting the goals and objectives established in the utility’s Strategic Business Plan. Through the plan, adopted in 2008, the Board of Directors established high standards for all parts of LOTT’s operations and management, including financial responsibility, environmental sustainability, accountability to the public and ratepayers, and a productive workforce. The Board receives detailed progress reports at our monthly meetings, but we look forward to this annual report, which displays results from the past year in the form of report cards for each of the main subject areas. As you will see, the results from 2010 have been impressive. Not only did LOTT meet nearly all of the measures of success, the utility also received a number of awards from local, national, and international organizations for the quality of work performed by LOTT’s dedicated employees. I encourage you to review the report cards and supporting information provided in this report. Sincerely, Ed Stanley President, Board of Directors
March 2011 With the completion of the Regional Services Center in 2010, LOTT has moved forward with a new public focus. Our recent wastewater treatment history has been largely “out of sight and out of mind.” With the opening of the new building, housing the WET Science Center, Administrative Offices, and Water Quality Laboratory, we now have a new public face for the utility at the Budd Inlet Treatment Plant site. Our staff has risen to the challenges of this new reality, and has welcomed over 3,000 visitors since the building opened to the public last summer. Additionally, 1,400 individuals toured LOTT’s treatment and reclaimed water facilities. This initial success is giving unprecedented public attention to the work performed by our highly trained and diligent staff, and creating a new generation of educated and conscientious consumers. This past year has been rewarding in other ways as well. We commissioned the new cogeneration system at the Budd Inlet Treatment Plant, capturing methane gas from the treatment process and using it to produce heat and electricity, powering and heating our new building as well as many processes in the plant. Eventually this system will also provide heating and cooling for the new Hands On Children’s Museum when that construction is completed. We made significant progress on planning for major treatment process improvements, including new primary sedimentation basins, scheduled to begin construction this year. At the same time, LOTT continued to excel at our primary business – treating wastewater to advanced secondary standards and treating portions of the flow to Class A Reclaimed Water standards. All of this would not have been possible without the dedication of our efficient and creative staff. I would also like to thank the Board of Directors for their support, their policy guidance, and their willingness to ask the tough questions over the past year. These key individuals ensure that the interests of our partner jurisdictions and the sewer ratepayers are carefully considered in all of our operations and projects. Sincerely, Michael D. Strub, P.E. Executive Director
/ State of the Utility Chapter 1 Chapter 4 Business Management. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Human Resources and Workplace Environment . . . 15 Strategic Business Plan Report Card. . . . . . . . . . . . . . . . . . . . 2 Strategic Business Plan Report Card. . . . . . . . . . . . . . . . . 16 Financial Accountability. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Key to Success . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Revenue Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Employee Development. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Capital Project Costs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Staffing Changes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 Property Acquisitions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 Commitment to Employee Wellness. . . . . . . . . . . . . . . . . . 18 Chapter 2 Chapter 5 Environmental Resource Management Capital Project Milestones . . . . . . . . . . . . . . . . . . . . . . . . . . 19 and Stewardship. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Diversity of Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Strategic Business Plan Report Card. . . . . . . . . . . . . . . . 6 Administrative/Education Center and Environmental Responsibility. . . . . . . . . . . . . . . . . . . . . . . . 7 Water Quality Laboratory. . . . . . . . . . . . . . . . . . . . . . . . 20 Permit Compliance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Deschutes Parkway to Tumwater Reclaimed Protecting Water Quality. . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Water Pipeline. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Produce and Use Renewable Resources. . . . . . . . . . . . . . . . 8 Mullen Road Reclaimed Water Pipeline . . . . . . . . . . . . 21 Reclaimed Water. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Martin Way Pump Station Reclaimed Biosolids. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Water Utilization. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 Methane. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Mottman Road Interceptor Replacement. . . . . . . . . . . 21 Water Conservation Program Summary . . . . . . . . . . . . . 10 Digester Improvements. . . . . . . . . . . . . . . . . . . . . . . . . . . 21 Aeration Blower Replacement. . . . . . . . . . . . . . . . . . . . . 21 Additional Capital Projects. . . . . . . . . . . . . . . . . . . . . . . 21 Chapter 3 Design Projects and Studies. . . . . . . . . . . . . . . . . . . . . . . . 22 Education, Communication, and Partnerships. . . . . . 11 Strategic Business Plan Report Card. . . . . . . . . . . . . . . . . 12 Grand Opening. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Chapter 6 New Name and Logo. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Budget and Capital Improvements WET Science Center Exhibits and Programs. . . . . . . . . 13 Plan Highlights. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 Facilities Use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 Project-Driven Budget . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 East Bay Redevelopment . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 Budget Overview 2011 Through 2018. . . . . . . . . . . . . . . . . . . 24 Capital Improvements Plan. . . . . . . . . . . . . . . . . . . . . . . . . 26 2011-2018 CIP and 2011 Capital Budget. . . . . . . . . . . . . . 26-27 2019-2053 CIP. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28-29
/ Achieving High Levels of Service Welcome to the State of the Utility Report This State of the Utility Report looks back at 2010 to assess LOTT’s performance and summarize the activities of the past year. In 2010, LOTT treated over 3.9 billion gallons of wastewater and produced over 540 million gallons of Class A Reclaimed Water. The utility was actively involved in planning, design, and construction of capital projects to maintain existing facilities and accommodate new capacity for the future. LOTT’s programs for pretreatment, flow reduction, and education were all expanded, with excellent results. This report provides highlights of those and other accomplishments. The report also looks ahead to activities planned for 2011, with a summary of the utility’s Operating and Capital Budgets.
The LOTT Clean Water Alliance has gone through significant changes in the past year, transitioning from a behind-the-scenes utility to one that encourages the public to visit our facilities and learn more about what we do. As a regional In December 2010, service provider of County Commissioner Strategic Business Plan wastewater treatment and Cathy Wolfe concluded A Framework for Effective Utility Management 2008 – 2012 reclaimed water production, the utility continually eight years of service as strives to meet the goals and Thurston County’s objectives established in our Strategic Business Plan. representative to the LOTT Board of Directors. The Strategic Business Plan serves as the basis Appointed to the LOTT for consistent and Board in September comprehensive reviews of operational and 2002, Board member organizational performance, Wolfe helped guide LOTT which are summarized in the annual State of the Utility Report. The plan through the transition to identifies the organization’s core values, benchmark levels of service, and measures of success for four topic areas: Business Management; Environmental Resource becoming a stand-alone Management and Stewardship; Education, Communication, and Partnerships; utility, establish high and Human Resources and Workplace Environment. standards for utility In this State of the Utility Report, you will find chapters for each of the four topics operations, and build a in the Strategic Business Plan, with the addition of chapters for capital project milestones and highlights of the 2011 Budget and Capital Improvements Plan. solid plan for the future. Each of the first four chapters includes a report card that summarizes LOTT’s She played an active role performance in terms of the Strategic Business Plan metrics established for that topic. in developing LOTT’s Strategic Business Plan, Overall, LOTT is performing extremely well and meets or exceeds almost all of its which defined core values, levels of service. The past year has been marked by many accomplishments and challenges, as highlighted in this report. As an organization, we constantly strive levels of service, and to improve, always with our primary mission in mind – cleaning and restoring measures of success that water resources for our communities. will be used to guide, evaluate, and improve the utility for many years to come.
/ Meeting Financial, Facility, and Capacity Benchmarks Business Management LOTT is committed to managing financial resources in a responsible, sound, and equitable manner. The organiza- tion is continually analyzing internal and external checks and balances to compare the utility’s financial health against accepted benchmarks. Yet business management is more than just finances. LOTT embraces asset man- agement and the triple bottom line to ensure responsible, long-term management of the utility. This includes a careful balance between maximizing existing treatment capacity and planning ahead for future capacity. 1
2010 Annual Strategic Business Plan Report Card Levels of Service Measure: Targets or Metrics Annual Performance Measure January to December Achieved Business Management Manage the utility within Service Revenue: 100% or greater of projected Wastewater WSC = 100.5% of projected revenue Yes financial benchmarks Service Charge (WSC) revenue New Connections Revenue: Annually review projected Reviewed in fall 2010 Yes revenue versus long-term Capital Improvements Plan needs Adequate for CIP Expenditures: Annually less than or equal to 85% of Expenditures = 78% of revenue Yes revenue Cash Balance: Positive annually End of year cash balance = $27,838,892 Yes Costs: Track budgeted versus actual total project costs 9 projects; 7 under-budget, 2 over-budget Ongoing with approved change orders Total budgeted costs = $33,134,801 Total actual costs = $32,577,874 Rate History: Track Wastewater Service Charge (WSC) WSC = 5.3% Ongoing versus inflation – Consumer Price Index (CPI) CPI = 0.8% Connection Fee History: Track Capacity Development CDC = 5.5% Ongoing Charge (CDC) fees versus construction inflation – PPIs = 2.3% and 2% Producer Price Indexes (PPIs) Revenue Needs: Track 6-year planning periods Planned rates for the 6-year period meet Yes revenue needs Operate within accepted State Audit: Free of findings Completed May 2010; No findings Yes business and financial standards Peer Review: Comprehensive peer reviews completed within QualServe review completed July 2009 Yes every 6-year planning period Internal Audit: Conducted at least once every 3 years In process Yes Independent Financial Operations Review: Conducted On track for completion in 2011 Yes every 3 years Liability Risk Audit: Conducted annually when topic is Completed 2010; Personnel practices; Yes applicable Favorable result Embrace asset management and Validated Capital Improvements Plan: Business case 35 projects on 6-year schedule On Track use of the triple bottom line* as evaluations (BCEs) for 100% of projects in the 6-year 18 projects with completed BCEs the operational standard for all schedule 4 in process; 3 ongoing; 10 scheduled system investment Ensure equitable distribution of Cost Distribution: Meet Capacity Development Charge Completed each month Yes costs between ratepayers and and Wastewater Service Charge allocation guidelines for new development all projects Preserve the design capacity at Budd Inlet Treatment Plant Capacity: Maintain optimum Maintained treatment capacity at or Yes the Budd Inlet Treatment Plant treatment capacity at 25 mgd during shoulder seasons above 25 mgd Discharge Capacity to Budd Inlet: 14.5 mgd dry weather Maintained capacity at or above 14.5 mgd Yes flow (DWF) and 28 mgd wet weather flow (WWF) DWF and 28 mgd WWF Build capital facilities Reserve Capacity: Maintain at an annual average of 1.5 mgd Maintained annual average of 1.5 mgd Yes just-in-time * The triple bottom line considers environmental, social, and economic impacts. 2
Financial Accountability Like other utilities, LOTT Business Management was impacted by the slower LOTT operates within accepted business and financial economy in 2010. New standards, using a number of benchmarks to ensure home construction responsible fiscal management. In 2010, LOTT’s annual diminished significantly, review by the State Auditor was free of findings for the 2009 resulting in fewer CDC fees calendar year. collected. WSC revenue has remained stable, but Revenue Sources revenue available for capital construction was reduced as LOTT’s primary sources of revenue are the monthly service a result of fewer CDCs. rate, known as the Wastewater Service Charge (WSC), and new connection fees, known as the Capacity Development Capital Project Charge (CDC). LOTT also receives miscellaneous Costs revenues from other sources, as well as loan funds to support large capital projects. Rates and fees are subject to Many capital projects were underway in 2010, with nine annual Board review. The monthly service rate for 2010 projects completed during the year. Most were completed was $30.00 per equivalent residential unit (ERU); the 2010 under budget, due in large part to a favorable construction CDC was $4,091.00 per new ERU. bidding environment. Capital Projects Completed 2010 Project Month Completed Budgeted Actual Under/(Over) Budget Hydraulic Gate Operator Overhaul February $58,675.00 $25,634.76 $33,040.24 Control System Upgrade March $3,290,400.00 $3,112,611.39 $177,788.61 Cogeneration System June $2,778,340.00 $2,924,144.52 ($145,804.52)* Deschutes Parkway to Tumwater Reclaimed July $3,364,385.00 $3,478,620.92 ($114,235.92)** Water Pipeline Administrative/Education Center and Lab September $20,150,000.00 $20,070,520.66 $79,479.34 Mullen Road Reclaimed Water Pipeline October $1,019,756.00 $891,252.01 $128,503.99 Budd Inlet Treatment Plant Fire Alarm October $500,360.00 $316,065.98 $184,294.02 System Upgrade Budd Inlet Treatment Plant Lighting Retrofit December $49,457.00 $41,278.08 $8,178.92 Mottman Road Interceptor Replacement December $1,923,428.00 $1,717,745.91 $205,682.09 Total $29,785,726.00 $29,439,628.08 $346,097.92 * The approved added cost was for the addition of three-way valves and other enhancements. The actual cost does not reflect the $1,700,000 energy grant received from Puget Sound Energy. ** The approved added costs were the result of unanticipated ground conditions, including rock obstructions and utility conflicts. The actual cost does not reflect forgivable principle for the State Revolving Fund loan monies. 3
Property Acquisitions • Martin Way Reclaimed Water Plant Expansion – LOTT purchased an easement for a portion of LOTT completed several property and easement purchases property owned by the City of Lacey south of the and started progress toward others in 2010. These Martin Way Plant. This easement, for nearly three acquisitions ensure that LOTT is able to maintain existing acres of property, will allow for future expansion of and reserve treatment capacity at the Budd Inlet Treatment treatment capacity. Plant and to build new facilities for additional capacity in the future. • Tumwater Plant Site Acquisition – LOTT began discussions with the City of Tumwater and the owners of the former brewery property about the possibility of siting a future reclaimed water plant on a portion of the property. Staff will continue to explore that alternative in 2011. • State Department of Fish and Wildlife (WDFW) Property – Discussions continued between LOTT and the State Department of General Administration, on behalf of WDFW, about the opportunities for purchase of three parcels located west of the Budd Inlet Treatment Plant. The City of Olympia, Port of Olympia, and LOTT hope to acquire the property to develop joint projects that provide numerous community benefits. • East Bay Easement – An easement was aquired by LOTT from the City of Olympia for a portion of property north of the new Hands On Children’s Museum in the East Bay district. The easement allows for the possibility of siting equalization basins under a parking lot in the future. • East Bay Public Plaza – Ownership of a .72-acre parcel in the East Bay district transferred from the Port of Aerial view of the Martin Way Reclaimed Water Plant and Olympia to LOTT in April. LOTT will own and surrounding area complete initial development of the site, working in cooperation with the other East Bay partners – Port of Olympia, Hands On Children’s Museum, and the City of Olympia. In 2010, LOTT received a Certificate of Achievement for Excellence in Financial Reporting for the 2009 Comprehensive Annual Financial Report from the Government Finance Hands On Children’s Museum and East Bay Public Plaza sites Officers Association. 4
/ Protecting and Renewing Resources Environmental Resource Management and Stewardship LOTT places a high value on environmental resource management and stewardship. As a utility responsible for cleaning and restoring water for our communities, our mission and our values are closely intertwined. Through high quality treatment, LOTT protects water resources and produces a number of renewable resources. LOTT also strives to complete capital projects and operate facilities with minimal impacts to the environment and the public. 5
2010 Annual Strategic Business Plan Report Card Levels of Service Measure: Targets or Metrics Annual Performance Measure January to December Achieved Environmental Resource Management and Stewardship Complete capital projects with Environmental Reviews: Proactively complete East Bay parcels 4 and 5 Interim Action Yes minimal environmental impacts environmental reviews as required and/or deemed optimal Workplan; East Bay Public Plaza; Primary for success Sedimentation Basins Investment in Enhancement: Track capital project Mitigation wetland at the Ongoing expenditures dedicated to enhancement and/or mitigation Hawks Prairie Ponds site = $4,693 Protect water resources through Permit Compliance: 100% compliance with numerical Budd Inlet Plant = 99.92% Nearly high quality wastewater treatment permit requirements Martin Way Plant = 99.92% Produce and reuse renewable Production of Class A Reclaimed Water: Trend production Budd Inlet Plant = 0.44 mgd (average) Ongoing resources including Class A per facility Martin Way Plant = 1.05 mgd (average) Reclaimed Water, Class B Biosolids, and methane Production of Class A Reclaimed Water: Trend percent of Reclaimed water = 12.4% flow Ongoing flow used to produce Class A Reclaimed Water Use of Class A Reclaimed Water: Trend use versus recharge/ Use = 34.4% Ongoing discharge Recharge = 59.3% Class B Biosolids: 100% of LOTT’s biosolids beneficially used Biosolids use = 100% Yes Methane: Track percentage of methane captured Methane use = 81.2% Ongoing for use Maximize use of existing Water Conservation: 500,000 gpd additional flow reduction Additional flow reduction On Track treatment capacity through cost- by 2012 2007-2010 = 306,950 gpd effective water conservation, inflow and infiltration reduction, Inflow and Infiltration (I&I): Trend annual I&I removal 0 projects completed in 2010 Ongoing and flow diversion projects over time Minimize odor complaints from Odor Compliance: 100% compliance with ORCAA Odor compliance = 100% Yes LOTT activities numerical requirements Odor Complaints: 5 or fewer per year Odor complaints = 0 Yes Support joint water quality and Investment: Track investments in water quality and habitat No financial investment Ongoing habitat improvement projects improvement and preservation projects Budd Inlet restoration = staff time Collaborate with partner Emergency Operations Plan: Update plan at least annually Completed August 2010 Yes jurisdictions and other entities to ensure emergency preparedness Joint Preparedness: Track participation in joint emergency No joint activities in 2010 Ongoing preparedness activities Hawks Prairie Reclaimed Water Ponds 6
Environmental Responsibility Environmental Resource Management and Stewardship LOTT strives to operate facilities in 100% compliance with all regulatory requirements, and routinely invests in programs that provide for beneficial use, conservation, and protection of our natural resources. In 2010, LOTT produced more Class A Reclaimed Water than ever before and made significant progress toward meeting a long-term goal for flow reduction. Permit Compliance LOTT’s exceptional compliance rates of over 99.9% for the Budd Inlet Treatment Plant and the Martin Way Reclaimed Water Plant demonstrate the skill and commitment of LOTT staff. Plant performance is measured in a variety of ways, including volume of wastewater treated. An application for renewal of the combined National Pollutant Discharge Eliminaton System (NPDES) and state reclaimed water permit for the Budd Inlet Plant was submitted to the Departments of Ecology and Health on March 1, 2010. The existing permit expired September 30, Budd Inlet Treatment Plant and Budd Inlet 2010, but continues to be in force until the new one is issued. The application for renewal of the state reclaimed water permit for the Martin Way Reclaimed Water Plant and Hawks Prairie Ponds and Recharge Basins was submitted to the Departments of Ecology and Health on September 30, 2010. The current permit expires March 31, 2011. Volume of Wastewater Treated (million gallons) Budd Inlet Treatment Plant 2005 2006 2007 2008 2009 2010 Daily Average 10.60 12.10 11.07 10.19 10.11 10.85 Minimum Monthly Average 9.02 8.40 8.67 8.31 8.53 8.33 Maximum Monthly Average 13.07 19.30 15.31 13.88 11.53 14.62 Peak Flow 22.74 38.19 48.48 26.36 48.64 33.18 Martin Way Reclaimed Water Plant Daily Average N/A 0.67 0.67 0.57 1.00 1.04 7
Protecting Water Quality Treatment Plant and the Budd Inlet Reclaimed Water Plant, with its advanced biological nutrient removal and sand filter LOTT’s Industrial Pretreatment Program made progress technologies. The Martin Way Reclaimed Water Plant in decreasing pollutant loadings with two new campaigns. also performed at the highest levels of reduction for PPCPs, Surveys and materials outlining best management practices hormones, and steroids in comparison to other participating were sent to minor industrial users including: 1) mobile facilities. carpet, drapery, and upholstery cleaners; and 2) screen printing, photographic services, lithography, and letterpress Produce and Use Renewable Resources businesses. Through day-to-day operations, LOTT demonstrates a In March, the program underwent a two-day pretreatment commitment to environmental stewardship with the compliance inspection by the Department of Ecology. The production of three renewable products from the program had not been audited by Ecology since 2006. The wastewater treatment process. These include Class A audit found that the program was performing its primary Reclaimed Water, Class B Biosolids, and methane. functions extremely well and identified Reclaimed Water opportunities for continued LOTT monitors the production of Class A Reclaimed improvement. Water at both of its facilities. The trend of increased production of reclaimed water continued over the past year. LOTT participated in an Environmental The Department of Ecology’s pending new state Reclaimed Protection Agency Water Use Rule could significantly affect LOTT’s future and Department reclaimed water facilities and uses, so LOTT has remained of Ecology study, an active participant in that process. Activities during Pharmaceuticals and 2010 included commenting on four drafts of the rule and Personal Care the first draft of a guidance manual to support it, participa- Products in tion in advisory committee meetings and two workshops, Municipal Waste- and joining with other utilities in meetings with Ecology water and Their management and staff. LOTT also joined with other Removal by Nutrient utilities in September to provide funding through the Treatment Technologies, which was released in early March. Coalition for Clean Water for a consultant to assist Ecology The study examined pharmaceuticals and personal care with development of the guidance manual. In November, products (PPCPs), hormones, steroids, semi-volatile organic the Governor issued an Executive Order suspending compounds, and nutrients in influent, effluent, and biosolids non-critical rule development statewide until January 1, samples from five Pacific Northwest wastewater treatment 2012. Although that put the reclaimed water rule on hold, plants, including LOTT’s facilities. Samples from both of Ecology made the decision to continue work on the LOTT’s treatment plants also included reclaimed water. guidance manual during 2011. The Ecology study concluded that PPCP concentrations were reduced most effectively by LOTT’s Budd Inlet Reclaimed Water Production Average (million gallons per day) 2005 2006 2007 2008 2009 2010 Budd Inlet Reclaimed Water Plant 0.40 0.50 0.46 0.38 0.42 0.44 Martin Way Reclaimed Water Plant N/A 0.46 0.60 0.54 0.94 1.05 Total 0.40 0.96 1.06 0.92 1.36 1.49 8
Biosolids Environmental Resource Management and Stewardship Class B Biosolids, produced at the Budd Inlet Treatment Plant, are beneficially used for agricultural soil amendment and fertilizer. LOTT added a second biosolids management option in 2010 by entering into a new contract with Boulder Park, Inc. of Mansfield, Washington, for biosolids handling. This contract provides for biosolids hauling to, and land application on, winter wheat fields in Douglas County (Eastern Washington). This is in addition to the existing contract with Fire Mountain Farms, which previously took 100% of LOTT’s biosolids for land application in Lewis County (Western Washington). The total tonnage of biosolids hauled for 2010 reflects greater dewatering efficiency. Centrifuge 3, which had been out of service in late 2009, was brought back on-line, allowing staff to produce a drier finished product. The difference in weight equates to Douglas County biosolids application cost savings for biosolids hauling. Biosolids Produced and Hauled 2005 2006 2007 2008 2009 2010 Average Wet Tons Per Day 18.38 15.86 20.71 25.11 25.82 22.33 Total Wet Tons Per Year 6,708 5,789 7,561 9,189 9,455 8,150 Average Truck Loads Per Week 4.50 4.40 5.70 6.80 5.90 5.20 Total Truck Loads Per Year 235 227 295 351 309 270 Methane Methane is produced by bacteria in the digesters as part of the solids handling process. The amount of methane captured and used jumped substantially in 2010 with completion of the new cogeneration system. The cogeneration system produces both heat and electricity, saving approximately $150,000 per year in utility costs, greatly reducing the need to flare excess digester gas, and substantially reducing emissions from the site. The electricity produced is sufficient to meet all the needs of LOTT’s Regional Services Center as well as some of the processes in the Budd Inlet Treatment Plant. The heat is used for buildings and processes throughout the treatment plant and the Regional Services Center. It will also eventually serve the new Hands On Children’s Museum. Jenbacher cogeneration system On May 6, the utility held an open house to celebrate the completion of the cogeneration project, which was partially funded by an Energy Conservation Grant from Puget Sound Energy for $1.7 million, or 70% of the project cost. The project was completed in early 2010 under an Energy Performance Contract agreement with the Washington State Department of General Administration, Engineering and Architectural Services Division, with Trane as the primary contractor. Cogeneration system ribbon-cutting ceremony 9
Water Conservation Program Summary The past year was another strong year for LOTT’s flow reduction program. LOTT and partner water utility staff worked diligently to implement a variety of water conservation projects, making substantial progress toward the overall goal of achieving 1,000,000 gallons per day (gpd) of flow reduction from 1997 through 2012. One of the most successful efforts for the flow reduction program is the WaterSmart program, which provides rebates up to 75% of project costs for water- efficient retrofits to industrial, commercial, and institutional customers. In 2010, 13 projects were completed and an additional three are on track for completion in early 2011. These projects included toilet, urinal, and aerator replacement in four schools in the Olympia School District, in 12 buildings owned by the City of Olympia, and in several other businesses. Walk-in coolers, ice machines, food steamers, and process equipment were also replaced in businesses as part of the program. Overall, the WaterSmart projects are estimated to reduce wastewater flows by 48,855 gpd. Trane presented LOTT In 2010, residential customers with an Energy Efficiency received 1,212 rebates for the purchase of water-efficient Leader Award at the washing machines through the WashWise program, for a flow ribbon-cutting event for reduction of 26,688 gpd. LOTT distributed 1,097 water saving kits the cogeneration system, to 803 households for a reduction of 14,438 gpd. Residential to recognize the project for customers also received 439 free environmental sustain- high-efficiency toilets for a flow High-efficiency dishwasher installed at the reduction of 16,243 gpd. Through ability, energy, and opera- Olympia High School the High-Efficiency Toilet program for commercial and multi-family tional efficiency. It is the customers, LOTT installed 334 toilets for a flow reduction of 12,018 gpd. Also in 2010, a Demonstration School project was completed at the Olympia High School first time the award was to install high-efficiency toilets, urinals, aerators, showerheads, clothes washers, and a commercial grade dishwasher for a flow reduction of 6,263 gpd. Overall, presented to a wastewater flow reduction of 124,505 gpd was achieved through the 2010 projects, marking treatment utility. steady progress toward the long-term goal of 1,000,000 gpd flow reduction by 2012. Flow Reduction Achieved (gallons per day) 2007 2008 2009 2010 Total Residential Projects 28,850 30,148 50,521 57,369 166,888 Commercial Projects 8,661 9,137 55,128 67,136 140,062 Annual Total 37,511 39,285 105,649 124,505 306,950 1997-2006 Total 580,473 Cumulative Total 887,423 10
/ Involving and Engaging the Community Education, Communication, and Partnerships LOTT is committed to community education and public participation to foster awareness and support for the essential services provided by the utility. Through communication and outreach, the public gains a better understanding of LOTT’s role in the community and plays an active role in utility planning for new and existing facilities. Open and transparent communications, access to information, and engaging educational programs are all essential to meaningful community participation and support for LOTT’s activities. 11
2010 Annual Strategic Business Plan Report Card Levels of Service Measure: Targets or Metrics Annual Performance Measure January to December Achieved Education, Communication, and Partnerships Provide open and transparent Reporting: 100% reports up-to-date 9 of 9 annual reports completed Yes access to information Access to Information: Track website visits over time Visits = 12,671 (monthly average) Ongoing Internal Communications: 100% scheduled internal 100% completed Yes communications completed Respond quickly and openly to Number of Inquiries: Track number of public inquiries Public inquiries = 840 Ongoing all public inquiries Response Time for Inquiries: 100% compliance with Calls and emails within 1 day = 99.2% Nearly response time guidelines Public records within 5 days = 100% Pursue recognition of excellence Professional Recognition: Track awards applied for and Applied for 6 awards Ongoing received Received 8 awards Professional Presentations: At least 1 LOTT representative to 8 presentations Yes present at professional or peer-reviewed forum annually 2 panel moderations Collaborate at the leadership Statewide Policy Development: Staff hours dedicated to Staff hours = 248 Monitoring level to advance responsible advancement of reclaimed water and other policies utility management and environmental stewardship Sharing Expertise: Host or visit at least 1 utility or Tacoma, Washington Yes community to share ideas and expertise Lakehaven Utility District, Washington Kitsap County, Washington King County, Washington Pierce County, Washington Spokane County, Washington Collaborate locally to offer joint Joint Events: At least 2 collaborative events/programs East Bay infrastructure ribbon-cutting; Yes community programs and events annually Hands On Children’s Museum ground- that foster public awareness and breaking; Thurston Climate Action Team support for LOTT activities (TCAT) kick-off; TCAT Action Plan workshop Involve the public in planning Regulatory Compliance: Complete required public East Bay parcels 4 and 5 Yes and design processes involvement for all SEPA regulated projects Interim Action Workplan public meeting Public Involvement: Complete workshops, meetings, and No additional activities in 2010 Monitoring interviews for additional projects as deemed appropriate Informed Public Consent: Achieve little or no opposition to No opposition for East Bay parcels 4 and 5; Yes proposed programs or facilities during final project stages Interim Action Workplan; East Bay Public Plaza; or Primary Sedimentation Basins Develop educational materials Community Presentations: At least 4 presentations annually Presentations = 13 Yes and programs that foster public awareness and support for LOTT Plant/Facility Tours: At least 10 tours annually Regional Services Center = 26 tours Yes activities Budd Inlet Plant = 72 tours Martin Way Plant = 9 tours Hawks Prairie Ponds = 6 tours Tour Participants: At least 300 participants annually Regional Services Center = 326 participants Yes Budd Inlet Plant = 1,282 participants Martin Way Plant = 56 participants Hawks Prairie Ponds = 69 participants Bug Education Center: Initially, at least 2,500 visitors annually Here Visitors = 3,095 (July - Dec) Yes Written Materials: Reports, brochures, or fact sheets for Written materials produced/updated = 31 Yes each major project and facility; provide for tours, events, on the website, and on request 12
Grand Opening Education, Communication, and Partnerships This was a very exciting year for the LOTT Clean Water Alliance. The August 14 grand opening event for the new Regional Services Center building, including LOTT’s new education center, represented the culmination of years of planning and hard work, as well as the utility’s transition to becoming a highly visible public entity. Over 300 members of the community attended the grand opening event. Visitors enjoyed refreshments and participated in activities hosted by the Hands On Children’s Museum, the City of Olympia, and the Port of Olympia. They explored the WET (Water Education and Technology) Science Center, classroom, and board room. Over 80 people toured the building to learn more about its environmental design, and many visitors toured the Budd Inlet Treatment Plant. Also at the event, the building’s reclaimed water feature was dedicated to Mike Sharar, LOTT’s former Executive Director who was instrumental in guiding Grand opening dedication the planning that established reclaimed water as the core of LOTT’s future ceremony development. New Name and Logo LOTT received the 2010 The move into the Regional Services Center, with National Environmental an increase in public visibility, provided the utility Achievement Award for with an opportunity to modify its identity to better Public Education and reflect the organization and its mission. The LOTT Clean Water Alliance name and associated logo were Involvement from the implemented concurrent with the completion of the new building. This name National Association of allows the public to more easily recognize what we do – cleaning and restoring water for our communities. Clean Water Agencies for the WET Science WET Science Center Exhibits and Programs Center and expanded LOTT invested approximately $1.5 million on the development, fabrication, and education program. installation of the WET Center’s educational and fun, interactive exhibits. The The award recognizes displays and activities are designed to teach visitors about the water cycle, water LOTT’s commitment to quality, conservation, wastewater treatment, reclaimed water production and use, and careers at LOTT. The exhibits were designed by Aldrich Pears Associates, education through the with substantial LOTT staff involvement, and most of the exhibits were fabricated development of this by Pacific Studio. engaging and unique Prior to the opening of the new WET Science Center, LOTT staff spent a year learning center. planning programs and activities, and building relationships with local school districts. This advance work resulted in additional usage of the new facility. The Olympia and North Thurston School Districts incorporated visits to the WET Science Center in their science curricula. During the fall, every North Thurston 7th grader attended a presentation, worked with microscopes, explored the exhibit gallery, and toured the treatment plant. The Olympia School District is scheduled to bring their 6th graders to the WET Science Center for a similar program in early 2011, and the Tumwater School District will be tentatively scheduling visits for the spring. Local colleges and universities are also using the facility as a resource for their environmental and science courses. Special events and activities are scheduled for Saturdays, and occasional evenings, and interested individuals can Students touring the WET Science Center sign up to receive a quarterly newsletter announcing upcoming events. 13
Facilities Use In addition to classroom activities, the Regional Services Center has sparked the interest of a variety of groups who want to use the facility’s meeting spaces and exhibit gallery. LOTT staff developed a facilities use policy to allow community groups, government agencies, and non-profit organizations, with goals and missions that are aligned with LOTT’s interests, to hold events and meetings at the new building. This provides great community exposure to LOTT and its education center. WET Science Center Visitors July* August September October November December Total Walk-Ins 0 75 94 176 180 327 852 Youth Groups 14 16 0 0 11 0 41 School Groups 52 0 0 506 0 44 602 College Groups 0 0 0 0 43 27 70 Other Groups 49 12 155 146 340 78 780 Special Events 160 300 90 0 200 0 750 Total 275 403 339 828 774 476 3,095 * The WET Science Center was open to the public in July, although the grand opening occured on August 14. East Bay Redevelopment LOTT’s Regional Services Center is located in downtown Olympia, next to the East Bay district, a former Port of Olympia industrial area that is currently undergoing redevelopment. Environmental cleanup for the East Bay area has been underway in conjunction with redevelopment efforts. On June 2, the Port held a ribbon-cutting ceremony to celebrate completion of infrastructure work, which included streets, sidewalks, utilities, and lighting. In November, the redevelopment project took another huge step forward with the groundbreaking ceremony for the new Hands On Children’s Museum, held in LOTT’s board room and exhibit gallery. Other major projects occurring in the area include a new Olympia City Hall and the East Bay Public Plaza. LOTT will construct, own, and operate the East Bay Public Plaza, which will “connect” the WET Science Center and the new Hands On Children’s Museum, and serve as the heart of the East Bay district. Bob Droll, the landscape architect for the plaza, continued work on design throughout 2010. Conceptual design was completed in April and includes an inviting open public space with Rendering of the new East Bay Plaza a shallow, stream-like reclaimed water feature, interpretive elements, public restroom, and small performance stage for special events. Staff have been working with the Department of Health to permit the water feature for recreational use, as an interactive water feature and wading pool. 14
/ Maximizing Workforce Effectiveness Human Resources and Workplace Environment LOTT values its workforce as essential to the success of its mission and is committed to the health and safety of its employees and the public. In keeping with those values, LOTT continually strives to provide employee development opportunities that result in an adaptive, efficient, satisfied, and highly skilled workforce. At the same time, the organization builds and maintains a culture of safety. 15
2010 Annual Strategic Business Plan Report Card Levels of Service Measure: Targets or Metrics Annual Performance Measure January to December Achieved Human Resources and Workplace Environment Provide employee development Vacancy Rate: Monthly average less than or equal to 10% Employee vacancy rate = 1.7% (average) Yes and support programs that result in an adaptive, efficient, satisfied, Succession Planning: 100% of critical functions have a plan Continue to identify changes in critical On Track and skilled workforce by 2009 functions; Training for backup and redundancy ongoing Apprenticeships: 75% of apprentices become journey-level 1 of 1 apprenticeship completed Yes workers and fulfill service commitments Service commitments ongoing Career Development Program: Track and trend number of 6 employees participated in 2010 Ongoing employees participating in the program 5 employees completed plans Training: Track and trend average hours of training per Training = 88.9 hours per employee Ongoing employee per year (average) Employee Turnover: Report and trend information Employee turnover = 3 Monitoring Movement Within the Organization: Track and report 1 promotion Ongoing reassignments and reclassifications 5 reassignments Retirement Eligibility: Track number of employees eligible to 8 within 2 years Ongoing retire in 2-, 5-, and 10-year horizons 6 within 2-5 years 9 within 5-10 years Amount of Employee Experience: Track employee tenure Tenure = 10.8 years (average) Ongoing and relevant experience Relevant experience = 21 years (average) Build and maintain a culture Reportable Safety Incidents: Track monthly rate Satety incidents = 0.58 (monthly average) Ongoing of safety Time Loss: Track and report worker hours lost due to injury Time loss = 74.77 hours Ongoing Labor and Industries Experience Rating: At or below Experience rating = 0.9670 Yes industry base rate of 1.0 Contractor Safety: 100% compliance with health and safety Contractor safety compliance = 100% Yes standards Safety Incentive Program: 100% staff participation Safety program participation = 100% Yes LOTT Clean Water Alliance staff 16
Key to Success Human Resources and Workplace Environment LOTT understands that employees are key to the utility’s success and has established programs to build a strong team and rewarding workplace environment. Emphasis on professional development, safety, and wellness ensures that the organization has a skilled and effective workforce that is ready and able to meet future Mike Strub, LOTT’s challenges. Executive Director, was Employee nominated by staff and Development received one of the LOTT’s Career Development Program first-ever Boss of the continued to provide employees with Year awards from the opportunities for profes- Thurston County Cham- sional development. LOTT laboratory staff Two employees, Laurie ber of Commerce and Pierce and Brent Morris, completed Bachelor’s degrees in the spring under this program. Karen Tuomey Express Personnel. He was promoted from Communications Coordinator/Web Designer to Graphic and Digital Media Designer after completing her Career Development Plan. Two was recognized for his additional employees, Tyle Zuchowski and Eric Hielema, completed the University of Washington’s year-long Project Management Certification Program, through commitment to creating Skill Enhancement Career Development Plans. Rick Hughes also completed a positive work environ- a Skill Enhancement Career Development Plan by earning a certificate in Executive Leadership at Cornell University. ment and ensuring pro- LOTT continued to support employee development in other ways. Two fessional development employees, Erin Michael and Julie Dufresne, graduated from the Leadership Thurston County program in June, and two additional employees, Ken Butti and opportunities for staff. Tyle Zuchowski, began the program in September. Eight employees, Joe Beyer, Ken Butti, Jim Howard, Erin Michael, Brent Morris, George Peterson, Howard Weisberg, and Tyle Zuchowski, participated in a 360° review process and received valuable feedback from their peers, subordinates, and supervisory staff to assist them in planning for future professional development opportunities. 17
Staffing Changes Several members of LOTT’s staff took on new responsibilities over the past year. These reassignments included the following: • Farah Derosier, Paralegal/Public Records Officer • Erin Michael, Human Resources Manager • Mike Rickert, Wastewater Treatment Plant Operator Apprentice • Ed Schumaker, Maintenance Worker II • Paula Williamson, Environmental Planner LOTT welcomed the following new individuals to its staff: • Adriel Grijalva, Facilities Technician • Natalie Neher, Records Technician • Joe Ferris, Inventory Control Specialist LOTT received a Happy Heart Special Achievement Award from the Thurston County Chamber and Thurston Adriel Grijalva Natalie Neher Joe Ferris County Public Health Commitment to Employee Wellness and Social Services LOTT began a unique program to encourage employees to increase their levels of physical activity. LEAP (LOTT Exercise and Activity Program) provides an Department WorkWell incentive to staff members who meet the Surgeon General’s recommended level of physical activity, at least five days Program. The award per week for thirty minutes, of qualifying activity. This new recognizes LOTT’s program is part of LOTT’s overall Wellness Program. Fit employees are less likely to use sick leave or be injured on comprehensive employee the job. An active Wellness Program is also a requirement of the “Well City” designation for which LOTT has applied. If Wellness Program. approved, LOTT will receive a discount on health insurance premiums, which in turn would lower operating expenses. 18
/ Planning, Financing, Design, and Construction Capital Project Milestones Capital projects are integral to LOTT’s mission and values. Existing facilities and equipment require repair, replacement, and upgrades. At the same time, LOTT must prepare for the future, building conveyance pipelines, recharge basins, and treatment facilities to accommodate projected increases in flows. Capital projects cross all four topic areas of LOTT’s Strategic Business Plan and reach into all of the LOTT partner communities. During 2010, LOTT completed or made substantial progress on many capital projects. 19
Diversity of Projects Capital projects are a major part of LOTT’s annual workload, and 2010 was a busy and productive year in that regard. During the year, a number of capital projects were started, continued, and/or completed. These projects are needed to repair and replace existing facilities to maintain current operations and treatment capacity, and to prepare for additional treatment capacity in the future. Administrative/Education Center and Water Quality Laboratory Construction of the new 25,000 square foot building and remodeling of 7,600 square feet of the old treatment plant administration building was completed in June 2010. The Miller|Hull Partnership was the architect for the project, which was designed to meet LEED Platinum certification for environmentally sustainable design and construction. Korsmo Construction was the general contractor on the project. Construction was completed on time and within budget, at approximately $13.5 million. LOTT received an Regional Services Center office space Energy Conservation Grant from Puget Sound Energy of $47,160 for the project’s energy enhancements. Staff moved into the building, now referred to as the Regional Services Center, on June 21. Public art for the building was completed by Pam Beyette, and installed in late August. LOTT’s Regional Services Center was awarded the Deschutes Parkway to Tumwater Reclaimed Water Pipeline Outstanding Achievement This four-phase project was designed to convey reclaimed water in Public Works Projects from the Budd Inlet Reclaimed Water Plant to portions of Olympia and Tumwater. Two phases of the project were award in the Buildings completed in 2009 and two were completed in 2010. The category by the state’s project was financed through the American Recovery and Reinvestment Act of 2009, awarded through the Washington State Infrastructure Assistance Department of Ecology’s State Revolving Fund loan process in coordination with Coordinating Council. the Environmental Protection Agency. The funding total, $2,148,796, consists of 50% forgivable principal and 50% conventional loan at 2.9% rate of interest for The award was the result 20 years. of the unique environmen- The Tumwater Reclaimed Water tal design and utility’s Pipeline segment required installation approach to financing the of a new pipeline from Tumwater Falls Park, south along Capitol Boulevard project. LOTT was able and Tumwater Valley Drive, to an to cash finance the entire interim end-point on the Tumwater Valley Municipal Golf Course. Work project, in part by secur- was completed by Hos Brothers ing grants and low-cost in May. Reclaimed water pipeline installation at the funding for other capital The Heritage/Marathon Park Re- Tumwater Valley Munipal Golf Course projects, including access- claimed Water Modification segment replaced a 4-inch pipeline with a larger 12-inch pipeline. The work spanned the ing green and environ- pedestrian footbridge over Capitol Lake between the two parks and required mental based funding. coordination with the State Department of General Administration. Donovan Excavating, Inc. and their subcontractor Nelson and Sons, completed the work 20 in June.
Mullen Road Reclaimed Water Pipeline Aeration Blower Replacement Capital Project Milestones The Mullen Road reclaimed water pipeline This energy-efficiency was installed for LOTT by the City of Lacey project was designed and to convey reclaimed water from the future constructed in a joint Mullen Road Reclaimed Water Plant. effort between Trane The 3,400 foot long 12-inch pipeline was and HDR to replace installed as part of the city’s project to one of LOTT’s four old, extend Mullen Road from Ruddell Road to inefficient blowers with College Street. a high-efficiency, turbo blower. LOTT received a Martin Way Pump Station Conservation Grant from Puget Sound Energy for Reclaimed Water Utilization $374,772 to cover nearly Work started on the Martin Way Pump 70% of the project cost. Station project in September. The project New turbo aeration blower replacement site Installation of the new involved supplying reclaimed water to the turbo blower is anticipated pump station from the Martin Way Reclaimed Water Plant in early 2011. at a usable pressure, installing a cat-walk, and installing an air gap tank. Hermanson Company completed the project, Additional Capital Projects which was commissioned in early 2011. It is expected to save over $3,000 per month in utility costs. A number of additional capital projects were completed in 2010. These projects included an Interceptor Sewer Inspection and Cleaning project, Budd Inlet Treatment Mottman Road Interceptor Replacement Plant Fire Alarm System Upgrade, Second Anoxic Mixers Due to erosion caused by a Replacement, Fiber Optic Line to rainstorm in 2009, the Capitol Lake Pump Station, Hydraulic gravity sewer line near Gate Operator Overhaul, and finalizing Percival Creek had to be of the Control System Upgrade project. replaced. To minimize costs and disruption to the public, LOTT received Energy Conservation the work was completed Grants from Puget Sound Energy for using auger boring to install two capital projects – $20,639 for approximately 650 feet of lighting upgrades in the Budd Inlet 18-inch pipeline at depths Treatment Plant and $8,816 for up to 45 feet. The work variable frequency drives on was completed by Donovan pressurization pumps, which serve Excavating and its subcon- the dissolved air flotation thickeners. tractors Nelson and Sons, Auger boring during the Mottman Road intercepter DBM Excavating, and replacement Gonzales Boring in April 2010. Digester Improvements This project included replacement of five recirculation pumps, five heat exchangers, four large influent gates and operators, and the addition of a 48-inch magnetic flow meter to the outfall. Pacific Crest, the contractor, began work in July. By December, all the equipment was installed and on-line, with pipe insulation and punch list items to be completed early in 2011. 21
Design Projects and Studies Throughout 2010, collaborative work was underway by HDR Engineering and the selected general contractor/construction manager, Mortenson Construction, Inc., to design new primary sedimentation basins and improvements for the existing LOTT’s Martin Way basins. Design will be completed in 2011. This will be the largest upgrade to the Budd Inlet Treatment Plant since nitrogen removal was added in the early 1990s. Reclaimed Water Plant LOTT has tentatively been approved on the Public Works Trust Fund list for $10,000,000, at 0.5% rate of interest for 20 years, to assist with funding for this and Hawks Prairie Re- large-scale project. claimed Water Ponds and Recharge Basins were chosen for the 2010 WateReuse Project of the Year Award by the WateReuse Association for small projects under 5 million gallons per day. Rendering of the planned primary sedimentation basins This international award recognizes projects Design of two other projects was completed in 2010. Parametrix completed design for the Screenings Pumps Replacement project, which will be bid and whose significance and constructed in 2011. Design of the Influent Pump Variable Frequency Drive Replacement project was also completed and will be bid in 2011. contributions to the LOTT also completed work on several studies. The Budd Inlet Reclaimed community continue to Water Plant Demand and Supply Analysis was completed by HDR. Brown and advance the water reuse Caldwell’s 5-year Groundwater Recharge and Reclaimed Water Conveyance Alternatives study was also completed in 2010, with publication of a final report. industry. The Budd Inlet Odor Control study was started by Brown and Caldwell, and Parametrix began work on the North Outfall Upgrade Evaluation. Brown and Caldwell completed a study that evaluated the need, size, and location of poten- tial equalization basins to help manage storm flows at the Budd Inlet Treatment Plant, and another identifying and evaluat- ing potential locations for a future satellite reclaimed water treatment plant in the Tumwater area. The Reclaimed Water Storage and Booster Pumping study was started in late 2010 by HDR. As a result of initial work on this study, LOTT submit- ted a Water Quality Financial Assistance Application to the Washington State Department of Ecology for the 2012 applica- tion cycle to fund a reclaimed water storage facility and pump station, which has been tentatively approved for $3,398,729 at 2.6% rate of interest for 20 years. Martin Way Reclaimed Water Plant 22